PNG: Maritime & Waterways Safety Proj (Loan 2978)

Approval & Amount: Dec 2012, $41.71Mmpl Employer: National Maritime Safety Authority Procurement Period: 2014-2016 Procurement Packages: Navaids Replacement & Installation Work $9.8M Hydrographic Survey - $13.9M Pre-installation survey - $1.9M AIS (VHF transponder) Installation work and maintenance - $1.3 M Tide gauges installation work - $1.1 M Hydrographic Survey equipment - $0.7 M Vehicle Purchase - $0.1 M Navaids2003 Maintenance - $4.2 M 2-6 November

PNG: Bridge Replacement for Improved Rural Access Project (Loans 2783/2784)
Approval & Amount: September 2011, $87.9Mmpl Employer: Department of Works Procurement Period: 2014 Construction Period: 2014-16 Procurement Packages Package 3 Ramu Highway $19.7 (April/May 2014) depending on availability of loan and govt funds All ICB with FIDIC Contract Conditions

PNG: Civil Aviation Devt Investment Program Project 2 (Loans 3069/3070)


Approval & Amount: April 2013, $66.8Mmpl Employer: National Airports Corporation Procurement Period: 2014Construction Period: 2015 Procurement Packages: Goods: Port Moresby Instrument Landing System - $2.0M Port Moresby 3 Fire Tenders - $3.6M Works: Port Moresby domestic apron extension - $6.4M

Cont. PNG: CADIP


Mount Hagen Improvements for F100 and new terminal - $33.5M Hoskins Improvements for F100 - $17.3M Wewak Improvements for F100 - $11.4M Gurney Improvements for F100 - $6.9M Hoskins Security Fence - $1.9M Wewak Security Fence - $2.0M Kavieng Security Fence - $2.0 Gurney Security Fence - $1.9M Goroka Security Fence 1.8M Consultancy Services Design and Supervision - $6.7M Survey & Geotechnical Investigations - $1.1M CAA Operations Training Program - $2.1 M Project Implementation Unit Consultants - $6.7M

PNG: Highlands Region Road Improvement Investment Program Project 2 (Loans 3076/3077)
Approval & Amount: December 2013, $109.0 Mmpl Employer: Department of Works Procurement Period Construction Period Procurement Packages: Supervision Consultants - $6.43M Long-term maintenance and capacity development of NRA - $3.3M Individual Consultants to support Dept of Works and National Road Safety Council - $1.25M

TIM: Road Network Upgrading Sector Project (Loans 3020/3021)


Approval & Amount: September 2013, $50Mmpl Employer: Ministry of Public Works Procurement Period: 2014 Construction Period: 2014-2016 Procurement Packages Civil Works Manatuto to Laclubar $35.0M (bidding is still open) Laclubar to Natarbora - $54.0M Civil Works: other national road - $15.2M Consulting Services Road Safety and Public Transport - $0.2M Various goods for Road Safety - $0.2M

SOL: Sustainable Transport Infrastructure Improvement Program


Approval & Amount: September 2014, $14 Ml Employer: Ministry of Finance/Ministry of Infrastructure Development
Procurement Packages: still to be decided Note: Fact-finding Mission in June 2014

ADB Business Opportunities Fair 16

TIM: Road Network Upgrading Project (additional financing)


Approval & Amount: August 2014, $23.5Mmpl Employer: Ministry of Public Works Procurement Period: 2015 onwards Construction Period: 2015 Procurement Packages: still to be decided

TIM: Road Network Upgrading Sector Project (Addtl. Financing)


Approval & Amount: December 2014, $39.79 Mmpl Employer: Ministry of Public Works Procurement Period: 2015 onwards Construction Period: 2015 Procurement Packages: still to be decided