Professional Documents
Culture Documents
Layout of data should be as per convenience of calculation and analysis. The forms should have a recording space for item of measurement, unit of measurement, and operator remarks about tool change, operator change, machine change etc.
Layout of data should be as per convenience of calculation and analysis. The forms should have a recording space for item of measurement, unit of measurement, and operator remarks about tool change, operator change, machine change etc.
Case I: The spread of the process 6 is appreciably less than the difference between the specification limits. Case II: The spread is approximately equal to the difference between the specification limits. Case III: The spread of the process is appreciably greater than the difference between the specification limits.
Case I: When the process 6 is appreciably less than difference between specification limits
Frequency curves A,B,C, D and E indicate various positions in which the process can be centered. With any of the position A, B and C practically all the products manufactured will meet the specifications as long as the process stays in control. In general when conditions A, B and C come it represents the ideal manufacturing situation. When the control chart shows that one of this control chart exists, many different possible actions may be considered depending on the relative economy.
For example it may be considered economically advisable to permit X to go out of control if it does not go too far, i.e., the distributions may be allowed to move between positions B and C. This may avoid the cost of frequent machine setup and of delays due to hunting of assignable causes of variation that will not be responsible for unsatisfactory product. Or where acceptance has been based on 100% inspection, it may be economical to substitute acceptance based on control charts. Or where there is an economic advantage to be gained by tightening the specification limits, such action may be considered. With the process in the position D some points will fall above the upper specification limit. Similarly with the process in position E some products will fall below the lower limit. In either case the obvious action is to bring the centering of the process towards that of A.
Case II: When the process 6 is equal to the difference between specification limits In this situation only the process
exactly centered between the specification limits, as in position A, will practically produce everything conforming to the specifications. If the distribution shifts away this exact centering as in B or C, it is apparent that some of the products will fall outside the specification limits.
Here the obvious action is to take all steps possible to maintain the centering of the process. This usually calls for continuous use of the control charts for X and R with subgroups at frequent intervals and immediate attention to points out of control. If fundamental changes can be made that reduce dispersion that eases the pressure. Consideration should also be given to changing of the tolerances.
Case III: When the process 6 is less than the difference between specification limits
The third type of situation arises when the specification limits are so tight that even with the process in control and perfectly centered some non conforming parts still get produced as in position A.
This primarily calls for a review of tolerances. It also calls for a fundamental change in the process that will reduce the process dispersion. It is still very important to maintain the centering of the process; the curves in position B and C show how a shift in process average will increase the non conformity.
I: Low value of distribution ( ) is appreciably above LSL. II: Low value of distribution is at LSL. III: Low value of the distribution is appreciably below LSL.
Determining the trial control limits: Calculations of the trial control limits was made after the first 16 subgroups which completed the production order. As shown in the figure on the right these were done by finding out the A2 and D4 factors for a subgroup size 5. Drawing preliminary conclusions from the graphs: Subgroup 1 is above the upper control limit on the R chart. Subgroup 10 is below the lower control limit on the X chart. Moreover the last 10- of the 6 points fall below the central line.
Determining the trial control limits: Calculations of the trial control limits was made after the first 16 subgroups which completed the production order. As shown in the figure on the right these were done by finding out the A2 and D4 factors for a subgroup size 5. Drawing preliminary conclusions from the graphs: Subgroup 1 is above the upper control limit on the R chart. Subgroup 10 is below the lower control limit on the X chart. Moreover the last 10- of the 6 points fall below the central line.
It is evident from the process that the natural tolerance of the spread is substantially greater than the specified tolerance. Therefore, unless the process dispersion is reduced the process will keep producing non conforming components.
It is evident from the process that the natural tolerance of the spread is substantially greater than the specified tolerance. Therefore, unless the process dispersion is reduced the process will keep producing non conforming components.
Sample n 10 10 10 10 10 50 50 50 50 50 50 50 50 50 D 0 1 1 1 0 5 4 6 4 8 1 3 5 3 n 10 20 30 40 50 100 150 200 250 300 350 400 450 500
Totals d 0 1 2 3 3 8 12 18 22 30 31 34 39 42
Occurrence ratio P = d/ n .0000 .0050 .0667 .0750 .0600 .0800 .0800 .0900 .0880 .1000 .0886 .0850 .0867 .0840
The proportion defective only tends to approach p =0.08. Sometimes it gets closer, sometimes it backs away from p. Before the total sample size was 100, the occurrence ratio was below .08. Between 100 and 150 it was 0.08 and thereafter above. Principle: We can say that the p= d/n is an estimate of the constant probability of population p. How close the estimate will be depends on sample size n, the value of p and also upon chance.
50
50 50 50 50
5
5 5 4 3
550
600 650 700 750
47
52 57 61 64
.0855
.0867 .0877 .0871 .0853
50
50 50 50 50
6
4 7 4 4
800
850 900 950 1000
70
74 81 85 89
.0875
.0871 .0900 .0895 .0890
Probability laws
Consider again the production line producing pieces with a constant probability .08 of the piece being a minor defective, and such that each piece is independent of the other produced.
This means that the probability of the next piece being a defective is 0.08 and the piece being good is .92 irrespective of the preceding piece.
Now let us suppose that we draw a sample of two pieces and inspect them. The outcomes are that the sample may contain 0, 1 or 2 defectives. Let us find the probabilities of this outcome or events. For the probability of the samples containing no defectives, we must have good pieces on both draws.
Probability Laws
Probability Laws
If 2 events A and B might occur on a trial or experiment, but the occurrence of either one prevents the occurrence of the other, then events A and B are called mutually exclusive. For two such events P(A) + P (B) = P( A or B, mutually exclusive events) We have seen this in the earlier example in the 1 good case P (1 Good) = .0736 +0.0736 If one of the two events A and A is certain to occur on a trial, but both cannot simultaneously occur, then A and A are called complementary events.
We have seen this in the example of a single draw where p was given as 0.08.
Laws of Probability
Two events A and B are independent if the occurrence or non occurrence of A does not affect the probability of B occuring. Whenever a process produces defectives independently, or at random, so that the probability of a defective on the next piece does not depend upon what the preceding pieces were like, then we have the case of independent events. Such a process is said to be in control, that is stable, even though some non conformity is produced. Not all processes do behave in this manner. For example: We consider the production of 3000 piston ring castings. The sample of 100 contain 25 defectives whereas the remaining 2900 only 4. This was because the defectives occur in bunches from a certain defect producing condition. Particularly in this case it was found that the castings were made from stacks of molds, and if the iron is not hot enough when poured into a stack, many castings may be defective. Under such conditions, whether a piece is good or defective does have an influence on the probability of the next one being defective. If two events A and B are independent, then we have : P(Both A and B occurring) = P(A). P(B)
As a second example of probability, let us consider drawing without replacement from a lot of N=6 speedometers, of which 1 is defective Let N = no. of pieces in one lot and D= no. of defective pieces in a lot Now consider the very simple case in which we just draw a random sample of 1 from a lot of 6. Random means that each of the six meters is equally likely to be chosen for the sample. Probability of each is 1/6. There are only two kind of meters good and defective with P(good) = 5/6 and P(defective) = 1/6. Now next consider drawing a sample of n= 2 from the lot having N =6, of which D=1 is defective. This may contain no. of defectives either d=0 or 1. This is a case of two consecutive drawings which are not independent. Take first the case of the sample yielding no defectives, that is, two good meters. We need P(2 good) = P(good, good) = P(good on first draw). P(good on 2nd draw given good on 1st draw) = 5/6. 4/5 = 2/3
Similarly for d=3 there are only 4 orders of sampling results P(d=3) = 4 (0.9)2(0.1)2 =.0036
Finally for d =4, all four must be defective P(d=4) = .0001
This is also a representative of the dth term of a Binomial distribution of n =4 and the p =0.9 and q= 0.1. d P(d) P= d/n In general 0 .6561 .00 P(d) = C(n,d) (p)n-d(q)d 1 .2916 .25
2 3 4 Total .0486 .0036 .0001 1.0000 .50 .75 1.00