WEEKLY PROJECT REPORT

MONTH OF JUNE 2009


WEEK : 3

No Project Description Quotation No. Project Status Documentation Completion

Site Diary Layout Acceptance


Remarks / Notes Action to be taken
Start End D.O Ref No. Site Photos Test Result BQ
Ref No. Diagram Certificate

A COMPLETED PROJECT
Project Basis

a. Installation infrastructure cabling and 7-Feb 4-Apr √ √ √ √ All installation competed and project invoiced to Status of deposit claim will be know by next
related cabling for Heitech Padu Heitech Padu. Project security deposit yet to week after meeting between the both party.
relocation node at Etiqa Tower, Kuala received from due to finalisation project status
Lumpur between Heitech and building management.

b. Installation IP CCTV at FCN pop N/A √ √ √ √ N/A √


- Site survey 3-Mar 13-Mar
- Installation of CCTV unit 31-Mar 16-Apr
- Configuration and Commissioning 30-Apr 30-Apr
- User hand on training 8-May 8-May
- Submission of documentation 14-May 14-May

c. Relocation CCTV camera for ALC at Wisma √ N/A N/A N/A N/A N/A N/A Installation completed.
TV, Angkasapuri

d. Relocation and installation of new access √ N/A N/A N/A N/A N/A N/A Installation completed Invoiced
door card at Wisma PKNS, Petaling Jaya

e. Installation of 20 nos of UTP connection 2-Apr 2-Apr √ √ Installation completed Invoiced


at FCN network room

f. Installation of 9 nos of UTP connection at 28-Apr 28-Apr √ √ Installation completed Invoiced


FCN network room

g. Installation cable tray, telephony and 3-Apr 8-Apr √ √ √ √ Installation completed


coaxial cabling at JPJ datacentre,
Cyberjaya
h. Installation coaxial cabling at Wisma DRB 22-Apr 27-Apr √ √ √ √ Installation completed Invoiced
Hicom, Glenmarie for JARING

i. Relocation of Door Access Unit at radio 22-May 23-May √ N/A N/A N/A N/A N/A N/A Installation completed Invoiced
conti, Wisma Radio

x. INTERNAL WIRING
Installation UTP cabling at South City √ N/A N/A N/A N/A N/A N/A Completed and just waiting Heitech Padu to Follow up with Riduan for the work order status
Plaza, Sri Kembangan produce Work Order
Installation UTP cabling at Hospital Sungai √ N/A N/A N/A N/A N/A N/A Completed and just waiting Heitech Padu to Follow up with Riduan for the work order status
Buloh produce Work Order

3 Installation IP CCTV and switches at Kolej -


Kommunit, Kuala Langat, Banting
- Installation fiber optic cable √ Completed
- Installation UTP cable √ Completed
- Installation equipment rack √ Completed
- Splicing and testing the fiber optic cable √ Completed
- Installation CCTV camera √ Completed
- Installation switches elements √ Completed
- Testing & comissioning CCTV unit √ Completed
- Configuration of switches √ Completed
- Installation CCTV server √ Completed
- Testing and commissioning √ Completed
- User training for Kolej Komuniti Date of training yet to decide Training date wil be follow-up with Kolej
personnel. Komuniti for the avaiablity of staff schedule
1 Installation 8-core coaxial cable at Celcom -
Sri Manjalara, Kepong for Tune Talk
- Installation cable Test Bed Cable 12-May 12-May √ √ √ √ Installation completed and tested Layout diagram will compiled in project final
- Installation Coaxial cable 25-May 26-May Installation completed and lacing properly doc.
Layout diagram will compiled in project final
√ √ √ √
- Installation electrical cable 26-May 26-May Installation completed doc.
√ √ √
- Connector termination at the both side 26-May 27-May √ √ √ Termination BNC commpleted
- Installation UTP Cat-5e for connection to 26-May 26-May √ √ √ √ Installation complete
router and firewall Celcom

2 Installation RUCKUSS wireless system at √ √ √ √ Installation compeleted and invoiced.


Fibrecomm office

3 Supply 15U equipment rack at Tune Talk √ Rack size need to change for depth of 1000mm. Waiting for supplier to confirm bout delivery
office period
4 INTERNAL WIRING
a. Maju Junction √ Completed and just waiting Heitech Padu to Email and follow up for work order
produce Work Order
b. Allianz, Jalan Jejaka Cheras √ Completed and just waiting Heitech Padu to Email and follow up for work order
produce Work Order
B Current weekly project :

1 Installation coaxial and erathing cable at 19-Jun 22-Jun √ √ √ √ Installation completed. Submission invoice will be made after received
Plaza Hamodal from MDF rack to Tune PS from cuatomer.
Talk office

C Upcoming Work
1 Housekeeping equipment rack Waitng confirmation PO from Heitech Padu to Installation date will be known after meeting
termination at JPN data centre, Putrajaya procure material for installation with JPN personnel on 19-June-2009

2 Installation infrastructure at Takaful Etiqa, All installation material already bought by Massa Installation date will be known after meeting
SS14, Subang Jaya, Selangor Engineering Sdn Bhd with Etiqa property division on 18-June-2009