Professional Documents
Culture Documents
Version 1.24
Developers Manual
Revisions
The following clauses in this manual were revised on the dates shown.
Revision Issue Date Number 1.0 4 August 1999 1.1 6 April 2000 Reason for Change Initial Issue
1.2
1.6
1.7 1.8
Amendments to clauses 2.1, 2.3.2, 4.1, 5.1, 18.1, 19.1.3, 19.1.5, 22.2, 23.1.2, 23.1.4, 26.1.1, 26.1.4, 26.2.1 and 27.1 Clauses 4.2 and 27.1.1 deleted New sections 28 and 29 added Modifications to table of contents, maps, glossary of terms and minor editorial changes 16 January Amendments to clauses 2.1, 2.2, 2.3.2, 2.3.3, 9.4.2, 9.4.3, 18.1.1, 18.1.2, 2001 19.1.5, 22.1.2, 22.1.3 (deleted), 24.3.6, 25.1.3 (added), 25.2.5, 25.2.6, 25.3, 26.1.1, 26.1.2, 27.1.1 and 29 Modifications to table of contents, glossary of terms and minor editorial changes 10 September Amendments to clauses 2.1, 2.2, 10.1.3, 19.1.5, 24.1.1, 24.3.7 (added) 2001 Modification to table of contents May 2002 Amendments to clauses 2.1,18.1.1, 19.1.5, 24.3.1, 24.3.6, 29.3 (added) Section 18 renamed and Section 10.1 clarified Modifications to table of contents and glossary of terms September Amendments to Clauses:2003 2.3 numbered in body of document, 9.4.3 Category g) added; drawing guidelines changed to WCX CAD Standard (formerly WCX Pack), 2.2 Wastewater Manual Volume 2 replaced with Design Standard Number 51 and for drawing standards WCX CAD Standard (formerly WCX Pack) added, and Vacuum Sewerage Manual added. 6. amended. 10.1.12 Vacuum Sewerage added. 25.2.6 inserted and existing 25.2.6 & 25.2.7 re numbered, 22.6.2 amended and 22.6.2.1, 22.6.2.2 and 22.6.2.3 added. Design Standards added to Glossary of Terms and in general text through out manual as required. Modifications to table of contents January 2006 Contact details in Clauses 5.1 5.2 & 5.3 amended Clause 2.2 list of manuals amended to include External Approvals Manual Clause 8 Title changed to External Approvals modifications to text to accommodate External Approvals Manual and new location of Prelims to Works Clause 10 Initial Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 10.1 Clause 12 Final Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 14.1 Requirement for Serviceable Lots list added at clause 10.1.7 other clauses July 2006 renumbered to suit and Submission Cover Sheet for Review of Initial May 2007 Engineering Design Submissions amended Amendment to clauses Clause 2.3.3 Added The Construction Engineer is responsible for
arranging the construction of the works to meet the requirements of the relevant manuals, codes and standards. Section 11 Numbering reformatted on Submission Cover Sheet
1.9
February 2008
External Approvals Paragraph to added outlining requirement to obtain comment from external agencies regarding developments adjacent to or crossing a road reserve or asset under control of an external agency.
Developers Manual
Developers Manual
Revision Number
Issue Date
1.10
1.14
1.15
1.16
1.17
1.18
Modifications to table of contents Clause 9.6 Deleted from the Design Co ordination by fax request on 9420 2203 and replaced it with by completing the Application Form at Attachment 3 and forwarding it to your Submission Contact. Added Attachment 3 Application for single use of Water Corporation example drawings for pumping station facility in electronic format. Submission Cover Sheet for Acceptance of Final Engineering Submissions April 2008 paragraph 5 external approvals amended to ensure that the required actions are completed Clause 2.3.4 Paragraph to serve notice that the Corporation has the right to May 2008 accept or reject nominated engineers. Clause 10.1.13 paragraph amended following request from Principal September Engineer Infrastructure Design Branch 2008 Clause 10.1.14 Paragraph titled Low Pressure Sewerage and amended to explain in what circumstances Grinder Pumps are permitted. Clause 6 of the Submission Cover Sheet for Review of Initial Engineering October Design Submission redrafted to indicate if adjacent lots are likely to become 2008 serviceable as a result of the works. Clause 6 of the Submission Cover Sheet for Acceptance of Final Engineering Submission redrafted to indicate property details of lots of lots rateable as a result of the works Paragraph 5.3 As Constructed Contact details amended February Clause 15.2 re drafted to outline the requirement relating to the Final 2009 Design Submission for Urban Drainage works. March 2009 Contact details for Kalgoorlie para 5.2 amended also 5.3 amended to ensure all as constructed details are forwarded to the Spatial Information Management Group Submission Cover Sheet for Acceptance of Final Engineering Submissions April 2009 paragraph 5 External Approvals amended to ensure that all requirements relating to the External Works Manual and the Utilities Code of Practice are met. August 2009 Clauses 10.1, 11,22.5, 24, 24.5.3 and 26 aligned to similar provision in the Advanced Works Agreement Manual . Additional checklist examples added clause 11.2 also Attachment 4 (ie example of a Wastewater As Constructed plan) Amended the Wastewater Reticulation and Water Reticulation Initial Design September Checklists Paragraphs 10.4.4 and 11.4 deleted 2009 Paragraph 24.5.2 relating to as constructed information for Water Reticulation works revised Clause 22.7 Joint Final Inspection changed to Final Takeover Inspection October Clause 24.5.3 Amended to attachment 4 2009 Clause 24.5.4 Typographical error amended Clause 24.5.5 amended to reflect details contained in 24.5.2 Clause 5.1 Main Extension contact details amended December Appendix 4 Example Wastewater Reticulation As Constructed Plan 2009 reformatted as A3 Clauses 10.1, 11.3, 11.4 & 11.5 changed to incorporate requirements of January Urban Main Drainage Manual. 2010
February 2008
July 2010
1.22
October 2010
Section 3 Process Flowchart Preliminaries to Works amended to External Approvals and Preliminaries to Works Section 5 Perth Contacts amended to include Main Relocations Section 11 amended to include Design Standard Variation Request criteria Section 13 Manager Land Development amended to Manager Development Services Branch Section 11.2 Submission cover sheet for review of initial engineering design amended Section11.3 Water and wastewater reticulation initial design checklists
Developers Manual
Developers Manual
Revision Number
1.23
1.24
March 2011
June 2011
Section 24 Incomplete submissions will not be accepted or captured until requested information is received. Section 5 Corporation Contacts Section 5.2 Inspection Contacts Amended following Section 5.3 As- Constructed Information Contacts country re alignment Section 5.4 State Map Section 5.5 South West Region Map Section 5.6 Metropolitan Map
Developers Manual
Developers Manual
Feedback Form
To provide feedback on the Developers Manual, please complete this form.
Publication Information
Name: Phone:
Proposed Change Information
Yes
No
Please return completed form to: Development Services Branch Water Corporation PO Box 100 LEEDERVILLE WA 6902 Fax: 9420 3193
Developers Manual
Developers Manual
Table of contents
Foreword 1. Glossary of Terms 2. Introduction 2.1 Scope 2.2 Technical and Other Manuals 2.3 Roles and Responsibilities 3. Process 4. Fees 5. Corporation Contacts 5.1 Submission Contact 5.2 Inspections Contact 5.3 As-Constructed Information Contact 5.4 State Map 5.5 South-West Region Map 5.6 Metropolitan Map 6. Preliminary Investigation 7. Land Requirements 7.1 General 8. External Approvals 8.1 General 8.2 Preliminaries to works 8.3 Objections 8.4 Completion required for acceptance of Final Submission 9. Design Requirements 9.1 Design Submissions 9.2 Drawing Certification 9.3 Design Responsibilities 9.4 Drafting Standards 9.5 Standard Drawings 9.6 Example Drawings 10.Initial Submission 10.1 Requirements for the Initial Submission 11.Requests Details of Initial Submission 11.1 General 11.2 The Submission Cover Sheet 11.3 The Initial Design Checklist 11.4 Design Drawings 11.5 The Development Staging Plan 11.6 The Supplementary Survey Plan 12.Review of Initial Submission 12.1 Acceptance 12.2 Amended drawings 13.Objections to the Corporations Requirements 14.Final Submission 14.1 Requirements of the Final Submission: 14.2 Approval from Western Australian Planning Commission 15.Details of the Final Submission 15.1 The Submission Cover Sheet 15.2 Design Drawings
8 9 11 11 11 11 13 14 14 14 15 16 17 18 19 20 20 20 20 20 20 21 21 21 21 21 21 21 21 22 22 22 23 23 24 26 29 29 29 29 29 30 30 30 30 31 31 31 33
Developers Manual
Developers Manual
16.Acceptance of a Final Submission 16.1 General 17.Alterations to an Accepted Final Submission 18.Pre-Start-Up Meeting Requirements 18.1 General 18.2 Notice of Proposed Works 19.Start-Up Meeting 19.1 General 20.Construction Requirements 20.1 General 20.2 Protection of Corporation Assets 21.Isolation of New Works (Sewers and Drains Only) 21.1 General 22.Inspection of Works During Construction 22.1 General 22.2 Construction Engineers Log of Inspections and Tests 22.3 Notification of Inspectors 22.4 Site Safety 22.5 Progressive Site Inspections by Asset Inspector 22.6 Pre -Takeover Inspection and Checklist 22.7 Final Takeover Inspection 23.Connection to Existing Assets 23.1 General 24.Recording of As-constructed Information 24.1 General 24.2 Submission Requirements of As-constructed Information 24.3 As-constructed Information 25.Takeover of the Works 25.1 General 25.2 Requirements for Takeover 25.3 Date of Takeover 26.Warranty Period 26.1 General 26.2 Remedial Repairs during Warranty 27.Final Acceptance Certificate 27.1 General 28.Attachment 1: Clearance to Work Permit Guidelines 29.Attachment 2: Breakdown of Costs 29.1 Category C Water and Wastewater Pumping Stations and Pressure Mains 29.2 Category D Water Tanks 29.3 Category G Water and Wastewater Treatment Plants 30.Attachment 3: Application for Single Use of Water Corporation Example Drawings 31.Attachment 4: Example Wastewater Reticulation as Constructed Plan
33 33 34 34 34 34 34 34 35 35 36 36 36 37 37 37 37 37 38 38 40 40 40 41 41 41 41 42 42 42 42 42 42 43 43 43 44 45 45 45 45 46 47
Developers Manual
Developers Manual
Foreword
The Developers Manual is an initiative by the Water Corporation in response to feedback from the development industry for greater standardisation of requirements for water, sewerage and urban drainage developments. The manual is made up of topics extracted from the technical manuals that deal with administrative rather than technical requirements. In bringing these requirements together considerable effort has been made to standardise, clarify and simplify them. The terminology of the manual reflects the reality that the only agreement the Water Corporation has is with the Developer, not with any Consulting Engineer or with any Contractor. Please use the Feedback Form on page 3 if you have other ideas for improvements. Any feedback is welcome and all suggestions for improvement will be carefully reviewed and acknowledged. This manual refers to the Water Corporation Technical Manuals and Design Standards for technical information relating to water, sewerage and drainage works. These manuals will be updated in the future to remove information that is in this new manual and bring them in line with it where necessary. Should material in a technical manual or Design Standard conflict with information in this manual, this manual takes precedence.
Developers Manual
Developers Manual
1.
In this Manual the following words and expressions shall have the following meanings. These meanings do not necessarily comply with the meanings given in the Water Corporation Act and other Water Corporation publications. Agreement Alignment As-constructed Document Asset Inspector Beneficiary Lot The formal legal document between the Developer and the Corporation with respect to fulfilling the WAPC conditions for a designated area of subdivision (known as the Agreement Area). The line on which the pipes are laid and measured from the adjacent cadastral boundary. The document on which details of the constructed works are recorded and submitted to the Corporation. An officer of the Corporation responsible for assessing and or inspecting the works. Lots that acquire water supply or wastewater service availability, as a result of an extension of the reticulation, without the owner having paid, or been deemed to have paid, Headworks Contributions. A permitting procedure to authorise a contractor to conduct work on, or near a designated asset, other than where the personnel carrying out the work are being directly supervised by a person who has operational control of the asset. The Engineer or Engineering Firm appointed by the Developer to manage the construction of the Works. The plan provided by the Design Engineer showing contours of existing surface levels or finished surface levels. The agreement between the Developer and the Contractor for the execution of the works. A person or organisation bound to execute the works under a contract. The amount payable to the Contractor for the execution of a contract. The body corporate known as the Water Corporation, Western Australia. The drawings prepared by the Design Engineer, showing the proposed works. The Engineer or Engineering firm appointed by a Developer to prepare design drawings and documents for submission to the Corporation. The Corporations Design Standard relevant to the works being undertaken as defined in Clause 2.2. The person or organisation that has made an agreement with the Corporation to provide drainage, water or sewerage infrastructure. The plan showing the total land holding controlled by the Developer and the planned stages of development of the holding. A water supply pipeline to which standard services are not normally connected. A defined area of land over which the Corporation has a right to enter for purposes defined by agreement or statute and subject to any conditions/restrictions implied therein. Such purposes can include for example, access, construction, maintenance and repair. A person qualified to be a Chartered Professional Engineer, and who has appropriate engineering experience.
Glossary of Terms
Clearance to Work Permit Construction Engineer Contour Plan Contract Contractor Contract Price Corporation Design Drawings Design Engineer Design Standard Developer Development Staging Plan Distribution Main Easement
Engineer
Developers Manual
Developers Manual
Final Acceptance Certificate Final Inspection Clearance Final Takeover Inspection Inspection Main Drain Main Sewer Precalculated Cadastral Plan Preliminaries To Works Region Regional Office Reticulation Shall Should Specification Standard Drawings Takeover Technical Manual Warranty Period
A certificate issued by the Corporation at the end of the Warranty Period provided conditions have been met as detailed in Section 0. A letter issued by the Asset Inspector confirming that the Works are acceptable. (See Clause 27) The inspection prior to Takeover as detailed in Clause 0. Any activity undertaken to assess the condition of the works. An existing or proposed drain within the Metropolitan Area that is declared under legislation and controlled by the Corporation. A wastewater collection sewer to which connections are not normally made. A surveyors precalculated cadastral plan of the proposed subdivision development. The procedure necessary to address the Corporations Statutory requirements for General and Major Works. An area of the State designated as a Corporation Region. The principal office of that Region. The pipelines and appurtenant works constructed to provide a water supply or sewerage service to a subdivision development. A mandatory requirement. A requirement to be adopted unless circumstances justify a variation. The document containing the technical clauses to be read in conjunction with the design drawings for the works. Registered Corporation drawings, which are intended to reduce the amount of work involved in the preparation of drawings though some additions may be required before submission. When the Corporation assumes ownership of the works and the Warranty commences. (See Section 25) The Corporations technical manual relevant to the works being undertaken as defined in Clause 0. The period commencing from Takeover as defined in Section 26.
10
Developers Manual
Developers Manual
2.
2.1
Introduction
Scope
This Manual explains the administrative requirements for the provision of works that are covered by an agreement, for the works to be incorporated into the Corporations schemes and taken over by the Corporation, from the preliminary investigation stage to the final acceptance of works by the Corporation. Works consist of the following categories: a) Water and sewerage reticulation involving land subdivision b) Water and sewerage reticulation mains extensions not involving land subdivision c) Water and wastewater pumping stations and pressure mains d) Water tanks e) Main sewers and water distribution mains, and f) Urban main drainage works. g) Water and wastewater treatment plants. 2.2 Technical and Other Manuals
This manual should be read in conjunction with the Technical Manual or Design Standard relevant to the type of works being undertaken together with other appropriate Water Corporation manuals or standards as listed below: for water reticulation works the Water Reticulation Manual for water distribution mains the Water Distribution Manual for sewerage reticulation works the Wastewater Manual Volume 1 and the Water Services Association of Australia Sewerage Code for wastewater pumping stations Design Standard Number 51 for drainage works the Urban Main Drainage Manual for electrical works the Electrical Manual of Standards for any works if nominated by the Water Corporation the Engineering Design Process Manual for drawing standards the WCX CAD Standard (formerly WCX Pack) for vacuum sewerage the Vacuum Sewerage Manual for all works the External Approvals Manual (includes Preliminaries to Work) Where this manual conflicts with another manual or standard this manual takes precedence (not applicable where the works are nominated by the Water Corporation as being subject to the Engineering Design Process Manual). 2.3 Roles and Responsibilities
2.3.1 Developer The developer is the proponent of the works. The developer is responsible for: (a) carrying out the requirements of the Agreement with the Corporation for these works (b) appointing a Design Engineer, a Construction Engineer and a Contractor to carry out the works in accordance with this manual and the Technical Manuals and Design Standards. 2.3.2 Design Engineer The role of the Design Engineer is to achieve a design for the works that is accepted by the Corporation. The Design Engineer is responsible for carrying out that design in accordance with relevant manuals and standards.
11
Developers Manual
Developers Manual
The Design Engineer must be a registered holder of all current and relevant manuals, codes and standards. 2.3.3 Construction Engineer
The role of the Construction Engineer is to manage the construction of the works. The Construction Engineer is responsible for arranging the construction of the works to meet the requirements of the relevant manuals, codes and standards. 2.3.4 Notification
The Developer should inform the Corporation in writing of the names of its Representative, Design Engineer and Construction Engineer. Where such advice is not received, information supplied by engineering organisations will be accepted in good faith as being in accordance with the Developers wishes. The Corporation reserves the right to accept or reject nominations based on its assessment of the capability, capacity and past performance of the nominated party.
12
Developers Manual
Developers Manual
3.
Process
13
Developers Manual
Developers Manual
4.
Fees
The following fees are payable by the developer to the Corporation. Fees will remain valid for the life of the submission. 4.1.1 Water Reticulation Planning Fee is a payment for water supply reticulation planning which is based on 3.75% of the Water Corporations estimate of the construction cost of the works. This fee is payable for all water supply reticulation submissions accepted, irrespective of whether the works proceed or not. 4.1.2 Connection to Existing Works Fee is a payment for the Corporation to connect new infrastructure to the Corporations existing system. These fees are dependent upon the type and size of connections and are payable prior to the connection being undertaken. a) For water works, in situations where an invoice has not already been received, the Construction Engineer shall apply to the Submission Contact for a determination of the fee amount. b) For sewerage and drainage works the Construction Engineer shall apply to the Customer Technical Services in the Regional Office for a determination of the fee amount. For sewerage and drainage works the fee may include the installation and removal of a physical isolation e.g. a plug. 4.1.3 Review of Design Fee is a payment for the Corporation to review design submissions for headworks infrastructure i.e. wastewater pumping stations, water supply distribution mains, urban main drainage works etc. Whether or not a Review of Design Fee is payable should be discussed during the Preliminary Investigation stage of the project (see Section 6).
5.
5.1
Contacts
Submission Contact
Perth Subdivision Works Main Extensions Main Relocations Agricultural Goldfields Great Southern North West Mid West
Manager Land Servicing Development Services Branch Water Corporation John Tonkin Water Centre 629 Newcastle Street, Leederville PO Box 100 LEEDERVILLE WA 6902 Land Servicing Consultant Water Corporation SGIO Building Cathedral Avenue, Geraldton PO Box 43 GERALDTON WA 6531
14
Developers Manual
Developers Manual
South West
Land Servicing Consultant Water Corporation Level 3, 61 Victoria Street, Bunbury PO Box 305 BUNBURY WA 6231
5.2
Inspections Contacts Inspection Services Perth Region 256 Bannister Road , Canning Vale PO Box 1525 Canning Vale Delivery Centre 6970 Regional Works Inspector Agricultural Region Water Corporation 263 Fitzgerald Street PO Box 265, NORTHAM WA 6401 Regional Works Inspector Great Southern Region Water Corporation 215 Lower Stirling Terrace ALBANY WA 6331 Regional Works Inspector Mid West Region Water Corporation SGIO Building Cathedral Avenue PO Box 43 GERALDTON WA 6531 Regional Works Inspector North West Region Water Corporation Welcome Road, Karratha PO Box 84, KARRATHA WA 6714 Regional Works Inspector South West Region Water Corporation PO Box 305 BUNBURY WA 6231 Phone: 9424 8462 Fax: 9424 8409
Perth
Agricultural
Great Southern
Mid West
North West
South West
15
Developers Manual
Developers Manual
5.3
As-constructed Information Contact Senior Spatial Analyst Spatial Information Management Group Water Corporation 629 Newcastle Street Leederville WA 6007 bill.spittles@watercorporation.com.au Phone: 9420 2791 Fax: 9420 3112
Spatial Data Team Leader Spatial Information Management Group Information Services Branch Water Corporation 629 Newcastle Street Leederville WA 6007 peter.jeffers@watercorporation.com.au
16
Developers Manual
Developers Manual
5.4
State Map
17
Developers Manual
Developers Manual
5.5
18
Developers Manual
Developers Manual
5.6
Metropolitan Map
19
Developers Manual
Developers Manual
6.
Preliminary investigation
To ensure that the concept and capacity of the proposed works are compatible with the Corporations overall planning requirements, the Design Engineer shall discuss the broad planning concepts of the design with the Water Corporation Submission Contact. If a vacuum sewerage system is proposed in lieu of gravity or other alternative servicing proposals they must ensure that this planning is acceptable to the Water Corporation. The requirements shall be discussed at an early stage in the planning of the development. Any requirements that will be imposed by other Authorities on the operation of the works must be discussed and agreed to by the Corporation.
7.
7.1
Land requirements
General
7.1.1 All easements, reserves and land to be owned by the Corporation required for a project shall be shown on the design drawings. 7.1.2 Where easements or reserves outside of the developer's land holding are required, written agreement in principle to the arrangements proposed to acquire these easements or reserves is required. 7.1.3 Land requirements for permanent or temporary works shall be discussed with the Corporation Submission Contact (Clause 5.1) at an early stage in the planning of the development, prior to the Initial Submission. 7.1.4 Where necessary the Corporation will require the Design Engineer to produce any documentation necessary to acquire land. 7.1.5 All land requirements shall be satisfied prior to the takeover of the works.
8.
8.1
External approvals
General
At an early stage in the preparation of a submission the Design Engineer shall give attention to the requirements for reference to external agencies as detailed in the Corporations External Approval Manual [including the Corporations (Statutory) requirements for Preliminaries to Works action as required by the Water Agencies (Powers) Act 1984]. 8.1.1 Particular attention and early discussion needs to occur where a design proposal is adjacent to, within or crosses a reserve or asset under the control of either the Mains Roads Department (MRD), Public Transport Authority (PTA), Western Power or Telstra. 8.1.2 Prior to discussing a proposal with these bodies all alternatives should first be considered and input on your design invited from the Corporation before any formal approvals are sought. An impact statement and a ranking is required for each of the options considered 8.2 Preliminaries to works
The Design Engineer shall determine the category of the Works as described in Sections 86 to 97 of Water Agencies (Powers) Act 1984 and shall satisfy the requirements of Guideline 1.2 of the Corporations External Approval Manual.
20
Developers Manual
Developers Manual
Works can be categorised as General, Major or Exempt. Major works are generally carried out by the Corporation and therefore not included in this manual. Most works will be General works and the remainder will be Exempt works. 8.3 Objections
Objections to the proposed works that cannot be resolved by the Design Engineer shall be referred to the Submission Contact (Clause 5.1). All objections shall be resolved prior to commencement of construction. 8.4 Completion required for acceptance of final submission
Completion of all requirements of Preliminaries to Works, including full resolution of objections, is a mandatory condition for acceptance of the Final Submission. (See Clause 14).
9.
9.1
Design requirements
Design submissions
Designs for the works shall be submitted by a Design Engineer. 9.2 Drawing certification
Each drawing (and document) forming the submission shall be signed by an Engineer who has the authority to act on behalf of the Design Engineer making the submission. 9.3 Design responsibilities
Compliance with the Corporations Technical Manuals and Design Standards and with statutory requirements shall be the responsibility of the Design Engineer. Acceptance by the Corporation of a submission shall not relieve the Design Engineer of this responsibility or the responsibility for any discrepancies, errors or omissions in the submission or for the adequacy of the design. 9.4 Drafting standards
9.4.1 For all works, drafting shall generally be in accordance with Australian Standard 1100, Part 101. 9.4.2 For works in categories a) and b) of the Scope (Clause 2.1), drawings shall be suitable for microfilming. Where available, a digital copy of the drawings will be submitted along with the required number of hard copies. In particular, a digital copy of the pre-calculated cadastral plan will expedite the incorporation of information into the Corporations Facility Mapping System. The digital file to be in MGA94 coordinates. 9.4.3 For works in categories c), d), e), f) and g) of the Scope (Clause 2.1), drawings shall conform to the Corporations WCX CAD Standard (formerly WCX Pack). The standard is available from Infrastructure Development Branch, phone contact 9420 2294. 9.5 Standard drawings
Standard Drawings are available in the Technical Manuals and Design Standards. Additional hardcopies or digital copies are available by fax request to the Infrastructure Development Branch at 9420 2203.
21
Developers Manual
Developers Manual
9.6
Example drawings
For Wastewater Pumping Stations Example Drawings shall be used. These can be purchased in digital form by completing the application at Attachment 3 and forwarding it to you Submission Contact.
10.
The major purposes of the initial submission are for the Corporation to: ensure that the planned works conform with the overall planning; and ensure that the preliminaries to works have commenced. 10.1 Requirements for the initial submission
Initial submission
General The initial submission shall consist of: 10.1.1 10.1.2 10.1.3 10.1.4 The Submission Cover Sheet. (See Clause 11.2 The Initial Design Checklist Two copies of the Design Drawings. (See Clause 11.4) A letter from the owners of land, other than the Developer, agreeing in principle to the granting of any easement or reserve considered by the Corporation to be necessary for the works. One copy of the Development Staging Plan for staged developments. (See Clause 11.5) One copy of a Supplementary Survey Plan in cases where there is a likelihood of conflict of services or variations from the standards in the Technical Manuals or Design Standards. (See Clause 11.6) One copy of the approved structure plan for the area
10.1.5 10.1.6
10.1.7 Drainage
Additionally, submissions for Drainage works shall contain: 10.1.8 10.1.9 10.1.10 One copy of the Local Water Management Strategy for the area One copy of the Urban Water Management Plan for the area A letter that includes: A reference to the Department of Waters drainage strategy for the area. A statement setting out the Developers understanding of who is responsible for funding of any proposed future connection of a catchment to any part of the drain covered by this submission. A letter from the appropriate waterway/wetland catchment management agency (eg. Swan River Trust) detailing its comments on the drainage proposal where appropriate. One copy of a soils investigation report where an investigation is required.
10.1.11 10.1.12
22
Developers Manual
Developers Manual
10.1.13 10.1.14
One copy of the summary of the proposed pollutant removal processes and mechanisms within the drainage system including sizing calculations, where appropriate. Two copies of the technical specification. The technical specification shall consist of the technical clauses covering the work, or a statement shall be included in the covering letter confirming that the specification is the same as one previously submitted.
Wastewater pumping stations Additionally, submissions for pumping station works shall contain confirmation that water, electricity, telephone services and an all weather access road will be available in the road reserve in front of the pumping station. Vacuum sewerage Additionally, submission for Vacuum Sewerage Systems shall contain: 10.1.16 A statement from a supplier of an approved vacuum valve, as listed in the DS36 Product Atlas stating that the supplier has received the system design prepared by an approved designer. The statement must guarantee the hydraulics of the system and confirm that the guarantee is transferable to the benefit of the Water Corporation. The Review must be carried out by a suitably experienced Engineer and the Engineer must be explicitly identified in the statement referred to above. Currently approved vacuum valves are: Airvac (contact Watercon as local agent) Flovac (contact Flovac Vacuum Sewerage Systems) Low Pressure sewerage 10.1.17 Low-pressure sewerage systems incorporating grinder pumps . are not currently accepted for wide scale use. They may be accepted for splitting of blocks that are currently serviced by this method. This has typically only occurred where the sewer was installed under the Infill Sewerage Program.Any other proposals for use of this system are to be referred to the Land Servicing Manager.
11.
11.1
Given that the Corporations Design Standards are developed to ensure that fit for purpose assets capable of achieving their economic design life with minimal operating and maintenance costs are delivered, a request for a variation will need to be comprehensively justified. 11.1.1 Requesting a design standard variation The Design Engineer shall submit a request to vary a Design Standard in writing to the Submissions Contact. The request shall, at a minimum address the following: A Design drawing detailing the variation/s A statement detailing the reasons / circumstances prompting the request An assessment of the impacts and benefits for both the Corporation and their client Details of the options considered to negate the need for the variation
23
Developers Manual
Developers Manual
11.1.2
Considerations to be made before a design standard variation is submitted Design Standard variations that are requested for any of the following reasons will generally not be considered by the Corporation: Substandard site investigation activities resulting in obstacles or constraints of a non-latent nature Seasonal impacts that will resolve themselves with time Where the Design Engineers assessment is for significant impact to the Corporations fundamental objectives Where the request relates purely to the financial benefit of the proponent Where the request is lacking in some or all of the requirements set out at 11.1.1
11.2 Submission cover sheet for the initial engineering submission to be completed in the following format.
24
Developers Manual
Developers Manual
For the review of initial engineering design submissions Important information for Design Engineers The following details are required to be sent to the Water Corporation with the initial submission of a design: 1. Please make sure that all information listed, including attachments, is included so that the Submission can be processed without delay. 2. Please verify the information by signing on the bottom of the page 3. Please include the signed original of this form with the Initial Design Submission when forwarding to Water Corporation 4. Please ensure all actions are completed on the following submission cover sheet including the water and wastewater checklists
General
Details of designer
Name of company: Postal address: Phone: Fax: Email Design engineer: Qualified to design works, see Clause 1 and 2.3.2 (please tick)
Design compliance
Attached and completed relevant design checklist
Funding
I confirm that the developer is aware that any easements and/or reserves considered by the Water Corporation to be necessary will be provided free of cost to the Corporation. I confirm that the developer is aware that the works are to be provided at their cost.
External approvals
A strategy for the approval of other parties, including Preliminaries to Works, has been developed with reference to the External Approvals Manual. Note: Should a formal Preliminaries to Works Notice be required Water Corporation authorisation to proceed is a prerequisite.
Declaration of consent
I am duly authorised to represent the proponent/landowner in design matters.
Verification of consent
Signature (Design Engineer) _______________________ Date __________________
25
Developers Manual
Developers Manual
11.3
The Initial Design Checklist for the initial engineering Submission to be in the following format and be specific to the relevant asset type
26
Developers Manual
Developers Manual
Note: This checklist is to be used to undertake a review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this checklist is to be signed by an engineer qualified and authorised to do so. Content of submission
Submission Cover Sheet enclosed. Two copies of the Design Drawings enclosed.
Drawing format
The drafting is to the appropriate standard i.e. plans are clear and to an appropriate scale. The drawings contain all of the relevant Water Corporation referencing e.g. property address and/or staging identifiers and/or WAPC references are correctly shown on the plans. Beneficiary lots have been identified clearly on the Design Drawing. All easements have been denoted. Note: If the submission is assessed as not meeting the above criteria, the submission will be returned and no further processing or assessment of the submission will occur.
The design complies with current Water Corporation planning. The design allows for all interconnecting flows (current and future). Where the proposal is dependent on the delivery of headworks assets, the design of headworks assets are at a stage where they are capable of acceptance by the Corporation. The design makes appropriate allowance for existing or proposed physical features of influence i.e. retaining walls, trees, other services, building etc. In the case of designs in existing established areas, the route has been surveyed and the locations of other services and obstructions that may impact on the design have been established. Where the design requires the approval of other parties (i.e. DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed.
Design criteria
Without compromising the planning, the design meets the fundamental objectives of: a) minimising access chambers b) minimising sewer depths c) minimising sewer length d) maximising the locating sewers in public land The design incorporates the most appropriate Access Chamber types and running traps where required. All lots served have sewer junctions at a location and depth suitable to correctly serve the lot/s and boundary traps where required. All fill requirements are denoted (i.e. if design based on contours appropriate tolerances have been applied) All sewer grades are within acceptable tolerances. All sewers terminate at the extremity of the land served unless future extension does not need to be catered for. Connections to existing works have been appropriately designed (i.e. flow to flow where called for) and isolation from live works requirements have been considered and designed appropriately. The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. The design considers the proposed construction technique and/or constraints. For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval. I certify that this design has been reviewed and complies with Water Corporation requirements.
Date
__________________
27
Developers Manual
Developers Manual
Note: this checklist is to be used to undertake a review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this checklist is to be signed by an Engineer qualified and authorised to do so. Content of submission
Submission Cover Sheet enclosed Two copies of the Design enclosed
Drawing format
The drafting is to the appropriate standard i.e. plans are clear and to an appropriate scale The drawings contain all of the relevant Water Corporation referencing e.g. property address and/or staging identifiers and/or WAPC references are correctly shown on the plans Beneficiary lots have been identified clearly on the Design Drawing. All easements have been denoted. Note: If the submission is assessed as not meeting the above criteria, the submission will be returned and no further processing or assessment of the submission will occur.
Planning considerations
The design complies with current Water Corporation planning Where the design covers more than one water supply zone, the zoning boundary is accurately shown.
Influencing factors
Where the proposal is dependent on the delivery of headworks assets, the design of headworks assets are at a stage where they are capable of acceptance by the Corporation. The design makes appropriate allowance for existing or proposed physical features of influence i.e. retaining walls, trees, other services, building etc. In the case of designs in existing established areas, the route has been surveyed and the locations of other services and obstructions that may impact on the design have been established. Where the design requires the approval of other parties (ie; DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed.
Design criteria
Without compromising the planning, the design meets the fundamental objectives of: e) minimising water main sizing f) efficient use of valves g) minimising bends h) efficient use of hydrants i) minimising long services j) maximising dual services k) minimising dead end mains The design incorporates valving that considers shutdown requirements and the number of properties impacted. The design considers finished surface levels in relation to cover on mains. All water mains terminate at the extremity of the land served unless future extension does not need to be catered for. Connections to existing works have been appropriately designed. The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. The design considers the proposed construction technique and/or constraints. For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval. I certify that this design has been reviewed and complies with Water Corporation requirements.
Date
__________________
28
Developers Manual
Developers Manual
11.4
Design drawings
Technical requirements for the design drawings are given in the appropriate technical manuals and design standards. The design drawings shall include the following: locality plan (drainage only) site plan construction drawings design data plan (sewerage and drainage only). major event plan for drainage (only if required by Water Corporation) For water reticulation works and small sewerage works the site plan and the construction drawings may be combined. 11.5 Development staging plan
The Development Staging Plan is only required for staged developments. A Development Staging Plan need only be submitted with subsequent stages if planning has been revised or if requested by the Corporation. The Development Staging Plan shall show: The total land holdings controlled by the Developer in the area Integration with the Corporations scheme plan Any subdivisions and existing roads The sequence of stages Proposed final contours or, if appropriate, levels for the area Integration / implementation of drainage planning with the proposed staging of development 11.6 Supplementary survey plan
If requested for water and wastewater submissions, the Supplementary Survey Plan shall show any additional survey data obtained for the design of the works such as details of all other existing and proposed services, and significant features such as trees etc. For drainage submissions a Supplementary Survey Plan shall be provided and include as a minimum: Finished surface levels at critical low points in the catchment The extent and level of proposed fill Contours of proposed earth works Road levels where substantially different from ground level Details of existing or proposed water mains sewers, gas mains, underground cables and other services Seasonal and design water levels in the drainage system and compensating basins
12.
12.1
The submission will be checked for conformity with the Corporations overall planning requirements. The submission will be:
29
Developers Manual
Developers Manual
Accepted - if the submission is acceptable to the Corporation, it will be stamped as accepted, the Corporation reference numbers and one copy of the drawings will be returned to the Design Engineer. The Design Engineer will then be in a position to proceed with the final submission; or Accepted with amendments if the submission is acceptable to the Corporation with minor amendments, it will be stamped as accepted conditional to the amendments being made, or Rejected if the initial submission is not acceptable, the Corporation will reject the submission and request that the design be reconsidered. Amended drawings