Developers Manual

Version 1.24

Developers Manual

Revisions

The following clauses in this manual were revised on the dates shown.
Revision Issue Date Number 1.0 4 August 1999 1.1 6 April 2000 Reason for Change Initial Issue

1.2

1.3 1.4 1.5

1.6

1.7 1.8

Amendments to clauses 2.1, 2.3.2, 4.1, 5.1, 18.1, 19.1.3, 19.1.5, 22.2, 23.1.2, 23.1.4, 26.1.1, 26.1.4, 26.2.1 and 27.1 Clauses 4.2 and 27.1.1 deleted New sections 28 and 29 added Modifications to table of contents, maps, glossary of terms and minor editorial changes 16 January Amendments to clauses 2.1, 2.2, 2.3.2, 2.3.3, 9.4.2, 9.4.3, 18.1.1, 18.1.2, 2001 19.1.5, 22.1.2, 22.1.3 (deleted), 24.3.6, 25.1.3 (added), 25.2.5, 25.2.6, 25.3, 26.1.1, 26.1.2, 27.1.1 and 29 Modifications to table of contents, glossary of terms and minor editorial changes 10 September Amendments to clauses 2.1, 2.2, 10.1.3, 19.1.5, 24.1.1, 24.3.7 (added) 2001 Modification to table of contents May 2002 Amendments to clauses 2.1,18.1.1, 19.1.5, 24.3.1, 24.3.6, 29.3 (added) Section 18 renamed and Section 10.1 clarified Modifications to table of contents and glossary of terms September Amendments to Clauses:2003 2.3 numbered in body of document, 9.4.3 Category g) added; drawing guidelines changed to WCX CAD Standard (formerly WCX Pack), 2.2 Wastewater Manual Volume 2 replaced with Design Standard Number 51 and for drawing standards WCX CAD Standard (formerly WCX Pack) added, and Vacuum Sewerage Manual added. 6. amended. 10.1.12 Vacuum Sewerage added. 25.2.6 inserted and existing 25.2.6 & 25.2.7 re numbered, 22.6.2 amended and 22.6.2.1, 22.6.2.2 and 22.6.2.3 added. Design Standards added to Glossary of Terms and in general text through out manual as required. Modifications to table of contents January 2006 Contact details in Clauses 5.1 5.2 & 5.3 amended Clause 2.2 list of manuals amended to include External Approvals Manual Clause 8 Title changed to External Approvals modifications to text to accommodate External Approvals Manual and new location of Prelims to Works Clause 10 Initial Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 10.1 Clause 12 Final Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 14.1 Requirement for Serviceable Lots list added at clause 10.1.7 other clauses July 2006 renumbered to suit and Submission Cover Sheet for Review of Initial May 2007 Engineering Design Submissions amended Amendment to clauses Clause 2.3.3 Added The Construction Engineer is responsible for

arranging the construction of the works to meet the requirements of the relevant manuals, codes and standards. Section 11 Numbering reformatted on Submission Cover Sheet

1.9

February 2008

External Approvals Paragraph to added outlining requirement to obtain comment from external agencies regarding developments adjacent to or crossing a road reserve or asset under control of an external agency.

Developers Manual

Developers Manual

Revision Number

Issue Date

Reason for Change

1.10

1.11 1.12 1.13

1.14

1.15

1.16

1.17

1.18

1.19 1.20 1.21

Modifications to table of contents Clause 9.6 Deleted from the Design Co ordination by fax request on 9420 2203 and replaced it with by completing the Application Form at Attachment 3 and forwarding it to your Submission Contact. Added Attachment 3 Application for single use of Water Corporation example drawings for pumping station facility in electronic format. Submission Cover Sheet for Acceptance of Final Engineering Submissions April 2008 paragraph 5 external approvals amended to ensure that the required actions are completed Clause 2.3.4 Paragraph to serve notice that the Corporation has the right to May 2008 accept or reject nominated engineers. Clause 10.1.13 paragraph amended following request from Principal September Engineer Infrastructure Design Branch 2008 Clause 10.1.14 Paragraph titled Low Pressure Sewerage and amended to explain in what circumstances Grinder Pumps are permitted. Clause 6 of the Submission Cover Sheet for Review of Initial Engineering October Design Submission redrafted to indicate if adjacent lots are likely to become 2008 serviceable as a result of the works. Clause 6 of the Submission Cover Sheet for Acceptance of Final Engineering Submission redrafted to indicate property details of lots of lots rateable as a result of the works Paragraph 5.3 As Constructed Contact details amended February Clause 15.2 re drafted to outline the requirement relating to the Final 2009 Design Submission for Urban Drainage works. March 2009 Contact details for Kalgoorlie para 5.2 amended also 5.3 amended to ensure all as constructed details are forwarded to the Spatial Information Management Group Submission Cover Sheet for Acceptance of Final Engineering Submissions April 2009 paragraph 5 External Approvals amended to ensure that all requirements relating to the External Works Manual and the Utilities Code of Practice are met. August 2009 Clauses 10.1, 11,22.5, 24, 24.5.3 and 26 aligned to similar provision in the Advanced Works Agreement Manual . Additional checklist examples added clause 11.2 also Attachment 4 (ie example of a Wastewater As Constructed plan) Amended the Wastewater Reticulation and Water Reticulation Initial Design September Checklists Paragraphs 10.4.4 and 11.4 deleted 2009 Paragraph 24.5.2 relating to as constructed information for Water Reticulation works revised Clause 22.7 Joint Final Inspection changed to Final Takeover Inspection October Clause 24.5.3 Amended to attachment 4 2009 Clause 24.5.4 Typographical error amended Clause 24.5.5 amended to reflect details contained in 24.5.2 Clause 5.1 Main Extension contact details amended December Appendix 4 Example Wastewater Reticulation As Constructed Plan 2009 reformatted as A3 Clauses 10.1, 11.3, 11.4 & 11.5 changed to incorporate requirements of January Urban Main Drainage Manual. 2010

February 2008

July 2010

1.22

October 2010

Section 3 Process Flowchart Preliminaries to Works amended to External Approvals and Preliminaries to Works Section 5 Perth Contacts amended to include Main Relocations Section 11 amended to include Design Standard Variation Request criteria Section 13 Manager Land Development amended to Manager Development Services Branch Section 11.2 Submission cover sheet for review of initial engineering design amended Section11.3 Water and wastewater reticulation initial design checklists

Developers Manual

Developers Manual

Revision Number

Issue Date amended

Reason for Change

1.23
1.24

March 2011
June 2011

Section 24 Incomplete submissions will not be accepted or captured until requested information is received. Section 5 Corporation Contacts Section 5.2 Inspection Contacts Amended following Section 5.3 As- Constructed Information Contacts country re alignment Section 5.4 State Map Section 5.5 South West Region Map Section 5.6 Metropolitan Map

Developers Manual

Developers Manual

Feedback Form
To provide feedback on the Developers Manual, please complete this form.
Publication Information

Title: Developers Manual


Your Information

Revision Status: Address: Fax: Page No.:

Name: Phone:
Proposed Change Information

Section: Para Reference (e.g. 1.2.3): Description of change:

Reason for change:

Do you require a response to your suggestion/request?


Your signature: Date:

Yes

No

Please return completed form to: Development Services Branch Water Corporation PO Box 100 LEEDERVILLE WA 6902 Fax: 9420 3193

Developers Manual

Developers Manual

Table of contents

Foreword 1. Glossary of Terms 2. Introduction 2.1 Scope 2.2 Technical and Other Manuals 2.3 Roles and Responsibilities 3. Process 4. Fees 5. Corporation Contacts 5.1 Submission Contact 5.2 Inspections Contact 5.3 As-Constructed Information Contact 5.4 State Map 5.5 South-West Region Map 5.6 Metropolitan Map 6. Preliminary Investigation 7. Land Requirements 7.1 General 8. External Approvals 8.1 General 8.2 Preliminaries to works 8.3 Objections 8.4 Completion required for acceptance of Final Submission 9. Design Requirements 9.1 Design Submissions 9.2 Drawing Certification 9.3 Design Responsibilities 9.4 Drafting Standards 9.5 Standard Drawings 9.6 Example Drawings 10.Initial Submission 10.1 Requirements for the Initial Submission 11.Requests Details of Initial Submission 11.1 General 11.2 The Submission Cover Sheet 11.3 The Initial Design Checklist 11.4 Design Drawings 11.5 The Development Staging Plan 11.6 The Supplementary Survey Plan 12.Review of Initial Submission 12.1 Acceptance 12.2 Amended drawings 13.Objections to the Corporations Requirements 14.Final Submission 14.1 Requirements of the Final Submission: 14.2 Approval from Western Australian Planning Commission 15.Details of the Final Submission 15.1 The Submission Cover Sheet 15.2 Design Drawings

8 9 11 11 11 11 13 14 14 14 15 16 17 18 19 20 20 20 20 20 20 21 21 21 21 21 21 21 21 22 22 22 23 23 24 26 29 29 29 29 29 30 30 30 30 31 31 31 33

Developers Manual

Developers Manual

16.Acceptance of a Final Submission 16.1 General 17.Alterations to an Accepted Final Submission 18.Pre-Start-Up Meeting Requirements 18.1 General 18.2 Notice of Proposed Works 19.Start-Up Meeting 19.1 General 20.Construction Requirements 20.1 General 20.2 Protection of Corporation Assets 21.Isolation of New Works (Sewers and Drains Only) 21.1 General 22.Inspection of Works During Construction 22.1 General 22.2 Construction Engineers Log of Inspections and Tests 22.3 Notification of Inspectors 22.4 Site Safety 22.5 Progressive Site Inspections by Asset Inspector 22.6 Pre -Takeover Inspection and Checklist 22.7 Final Takeover Inspection 23.Connection to Existing Assets 23.1 General 24.Recording of As-constructed Information 24.1 General 24.2 Submission Requirements of As-constructed Information 24.3 As-constructed Information 25.Takeover of the Works 25.1 General 25.2 Requirements for Takeover 25.3 Date of Takeover 26.Warranty Period 26.1 General 26.2 Remedial Repairs during Warranty 27.Final Acceptance Certificate 27.1 General 28.Attachment 1: Clearance to Work Permit Guidelines 29.Attachment 2: Breakdown of Costs 29.1 Category C Water and Wastewater Pumping Stations and Pressure Mains 29.2 Category D Water Tanks 29.3 Category G Water and Wastewater Treatment Plants 30.Attachment 3: Application for Single Use of Water Corporation Example Drawings 31.Attachment 4: Example Wastewater Reticulation as Constructed Plan

33 33 34 34 34 34 34 34 35 35 36 36 36 37 37 37 37 37 38 38 40 40 40 41 41 41 41 42 42 42 42 42 42 43 43 43 44 45 45 45 45 46 47

Developers Manual

Developers Manual

Foreword

The Developers Manual is an initiative by the Water Corporation in response to feedback from the development industry for greater standardisation of requirements for water, sewerage and urban drainage developments. The manual is made up of topics extracted from the technical manuals that deal with administrative rather than technical requirements. In bringing these requirements together considerable effort has been made to standardise, clarify and simplify them. The terminology of the manual reflects the reality that the only agreement the Water Corporation has is with the Developer, not with any Consulting Engineer or with any Contractor. Please use the Feedback Form on page 3 if you have other ideas for improvements. Any feedback is welcome and all suggestions for improvement will be carefully reviewed and acknowledged. This manual refers to the Water Corporation Technical Manuals and Design Standards for technical information relating to water, sewerage and drainage works. These manuals will be updated in the future to remove information that is in this new manual and bring them in line with it where necessary. Should material in a technical manual or Design Standard conflict with information in this manual, this manual takes precedence.

Developers Manual

Developers Manual

1.

In this Manual the following words and expressions shall have the following meanings. These meanings do not necessarily comply with the meanings given in the Water Corporation Act and other Water Corporation publications. Agreement Alignment As-constructed Document Asset Inspector Beneficiary Lot The formal legal document between the Developer and the Corporation with respect to fulfilling the WAPC conditions for a designated area of subdivision (known as the Agreement Area). The line on which the pipes are laid and measured from the adjacent cadastral boundary. The document on which details of the constructed works are recorded and submitted to the Corporation. An officer of the Corporation responsible for assessing and or inspecting the works. Lots that acquire water supply or wastewater service availability, as a result of an extension of the reticulation, without the owner having paid, or been deemed to have paid, Headworks Contributions. A permitting procedure to authorise a contractor to conduct work on, or near a designated asset, other than where the personnel carrying out the work are being directly supervised by a person who has operational control of the asset. The Engineer or Engineering Firm appointed by the Developer to manage the construction of the Works. The plan provided by the Design Engineer showing contours of existing surface levels or finished surface levels. The agreement between the Developer and the Contractor for the execution of the works. A person or organisation bound to execute the works under a contract. The amount payable to the Contractor for the execution of a contract. The body corporate known as the Water Corporation, Western Australia. The drawings prepared by the Design Engineer, showing the proposed works. The Engineer or Engineering firm appointed by a Developer to prepare design drawings and documents for submission to the Corporation. The Corporations Design Standard relevant to the works being undertaken as defined in Clause 2.2. The person or organisation that has made an agreement with the Corporation to provide drainage, water or sewerage infrastructure. The plan showing the total land holding controlled by the Developer and the planned stages of development of the holding. A water supply pipeline to which standard services are not normally connected. A defined area of land over which the Corporation has a right to enter for purposes defined by agreement or statute and subject to any conditions/restrictions implied therein. Such purposes can include for example, access, construction, maintenance and repair. A person qualified to be a Chartered Professional Engineer, and who has appropriate engineering experience.

Glossary of Terms

Clearance to Work Permit Construction Engineer Contour Plan Contract Contractor Contract Price Corporation Design Drawings Design Engineer Design Standard Developer Development Staging Plan Distribution Main Easement

Engineer

Developers Manual

Developers Manual

Final Acceptance Certificate Final Inspection Clearance Final Takeover Inspection Inspection Main Drain Main Sewer Precalculated Cadastral Plan Preliminaries To Works Region Regional Office Reticulation Shall Should Specification Standard Drawings Takeover Technical Manual Warranty Period

A certificate issued by the Corporation at the end of the Warranty Period provided conditions have been met as detailed in Section 0. A letter issued by the Asset Inspector confirming that the Works are acceptable. (See Clause 27) The inspection prior to Takeover as detailed in Clause 0. Any activity undertaken to assess the condition of the works. An existing or proposed drain within the Metropolitan Area that is declared under legislation and controlled by the Corporation. A wastewater collection sewer to which connections are not normally made. A surveyors precalculated cadastral plan of the proposed subdivision development. The procedure necessary to address the Corporations Statutory requirements for General and Major Works. An area of the State designated as a Corporation Region. The principal office of that Region. The pipelines and appurtenant works constructed to provide a water supply or sewerage service to a subdivision development. A mandatory requirement. A requirement to be adopted unless circumstances justify a variation. The document containing the technical clauses to be read in conjunction with the design drawings for the works. Registered Corporation drawings, which are intended to reduce the amount of work involved in the preparation of drawings though some additions may be required before submission. When the Corporation assumes ownership of the works and the Warranty commences. (See Section 25) The Corporations technical manual relevant to the works being undertaken as defined in Clause 0. The period commencing from Takeover as defined in Section 26.

10

Developers Manual

Developers Manual

2.
2.1

Introduction
Scope

This Manual explains the administrative requirements for the provision of works that are covered by an agreement, for the works to be incorporated into the Corporations schemes and taken over by the Corporation, from the preliminary investigation stage to the final acceptance of works by the Corporation. Works consist of the following categories: a) Water and sewerage reticulation involving land subdivision b) Water and sewerage reticulation mains extensions not involving land subdivision c) Water and wastewater pumping stations and pressure mains d) Water tanks e) Main sewers and water distribution mains, and f) Urban main drainage works. g) Water and wastewater treatment plants. 2.2 Technical and Other Manuals

This manual should be read in conjunction with the Technical Manual or Design Standard relevant to the type of works being undertaken together with other appropriate Water Corporation manuals or standards as listed below: for water reticulation works the Water Reticulation Manual for water distribution mains the Water Distribution Manual for sewerage reticulation works the Wastewater Manual Volume 1 and the Water Services Association of Australia Sewerage Code for wastewater pumping stations Design Standard Number 51 for drainage works the Urban Main Drainage Manual for electrical works the Electrical Manual of Standards for any works if nominated by the Water Corporation the Engineering Design Process Manual for drawing standards the WCX CAD Standard (formerly WCX Pack) for vacuum sewerage the Vacuum Sewerage Manual for all works the External Approvals Manual (includes Preliminaries to Work) Where this manual conflicts with another manual or standard this manual takes precedence (not applicable where the works are nominated by the Water Corporation as being subject to the Engineering Design Process Manual). 2.3 Roles and Responsibilities

2.3.1 Developer The developer is the proponent of the works. The developer is responsible for: (a) carrying out the requirements of the Agreement with the Corporation for these works (b) appointing a Design Engineer, a Construction Engineer and a Contractor to carry out the works in accordance with this manual and the Technical Manuals and Design Standards. 2.3.2 Design Engineer The role of the Design Engineer is to achieve a design for the works that is accepted by the Corporation. The Design Engineer is responsible for carrying out that design in accordance with relevant manuals and standards.

11

Developers Manual

Developers Manual

The Design Engineer must be a registered holder of all current and relevant manuals, codes and standards. 2.3.3 Construction Engineer

The role of the Construction Engineer is to manage the construction of the works. The Construction Engineer is responsible for arranging the construction of the works to meet the requirements of the relevant manuals, codes and standards. 2.3.4 Notification

The Developer should inform the Corporation in writing of the names of its Representative, Design Engineer and Construction Engineer. Where such advice is not received, information supplied by engineering organisations will be accepted in good faith as being in accordance with the Developers wishes. The Corporation reserves the right to accept or reject nominations based on its assessment of the capability, capacity and past performance of the nominated party.

12

Developers Manual

Developers Manual

3.

Process

13

Developers Manual

Developers Manual

4.

Fees

The following fees are payable by the developer to the Corporation. Fees will remain valid for the life of the submission. 4.1.1 Water Reticulation Planning Fee is a payment for water supply reticulation planning which is based on 3.75% of the Water Corporations estimate of the construction cost of the works. This fee is payable for all water supply reticulation submissions accepted, irrespective of whether the works proceed or not. 4.1.2 Connection to Existing Works Fee is a payment for the Corporation to connect new infrastructure to the Corporations existing system. These fees are dependent upon the type and size of connections and are payable prior to the connection being undertaken. a) For water works, in situations where an invoice has not already been received, the Construction Engineer shall apply to the Submission Contact for a determination of the fee amount. b) For sewerage and drainage works the Construction Engineer shall apply to the Customer Technical Services in the Regional Office for a determination of the fee amount. For sewerage and drainage works the fee may include the installation and removal of a physical isolation e.g. a plug. 4.1.3 Review of Design Fee is a payment for the Corporation to review design submissions for headworks infrastructure i.e. wastewater pumping stations, water supply distribution mains, urban main drainage works etc. Whether or not a Review of Design Fee is payable should be discussed during the Preliminary Investigation stage of the project (see Section 6).

5.
5.1

Contacts
Submission Contact

Perth Subdivision Works Main Extensions Main Relocations Agricultural Goldfields Great Southern North West Mid West

Manager Land Servicing Development Services Branch Water Corporation John Tonkin Water Centre 629 Newcastle Street, Leederville PO Box 100 LEEDERVILLE WA 6902 Land Servicing Consultant Water Corporation SGIO Building Cathedral Avenue, Geraldton PO Box 43 GERALDTON WA 6531

Phone: 9420 2099 Fax: 9420 3193

Phone: 9923 4942 Fax: 9923 4966

14

Developers Manual

Developers Manual

South West

Land Servicing Consultant Water Corporation Level 3, 61 Victoria Street, Bunbury PO Box 305 BUNBURY WA 6231

Phone: 9791 0400 Fax: 9791 2280

5.2

Inspections Contacts Inspection Services Perth Region 256 Bannister Road , Canning Vale PO Box 1525 Canning Vale Delivery Centre 6970 Regional Works Inspector Agricultural Region Water Corporation 263 Fitzgerald Street PO Box 265, NORTHAM WA 6401 Regional Works Inspector Great Southern Region Water Corporation 215 Lower Stirling Terrace ALBANY WA 6331 Regional Works Inspector Mid West Region Water Corporation SGIO Building Cathedral Avenue PO Box 43 GERALDTON WA 6531 Regional Works Inspector North West Region Water Corporation Welcome Road, Karratha PO Box 84, KARRATHA WA 6714 Regional Works Inspector South West Region Water Corporation PO Box 305 BUNBURY WA 6231 Phone: 9424 8462 Fax: 9424 8409

Perth

Agricultural

Phone: 9622 4804 Fax:9622 4866

Great Southern

Phone: 9842 4210 Fax: 9842 4255

Mid West

Phone: 9923 4964 Fax: 9923 4966

North West

Phone: 9186 1258 Fax: 9185 8313

South West

Phone: 9791 0400 Fax: 9791 2280

15

Developers Manual

Developers Manual

5.3

As-constructed Information Contact Senior Spatial Analyst Spatial Information Management Group Water Corporation 629 Newcastle Street Leederville WA 6007 bill.spittles@watercorporation.com.au Phone: 9420 2791 Fax: 9420 3112

Sewerage or Drainage All Regions

Water All Regions

Spatial Data Team Leader Spatial Information Management Group Information Services Branch Water Corporation 629 Newcastle Street Leederville WA 6007 peter.jeffers@watercorporation.com.au

Phone: 9420 2069 Fax: 9420 3212

16

Developers Manual

Developers Manual

5.4

State Map

17

Developers Manual

Developers Manual

5.5

South-West Region Map

18

Developers Manual

Developers Manual

5.6

Metropolitan Map

19

Developers Manual

Developers Manual

6.

Preliminary investigation

To ensure that the concept and capacity of the proposed works are compatible with the Corporations overall planning requirements, the Design Engineer shall discuss the broad planning concepts of the design with the Water Corporation Submission Contact. If a vacuum sewerage system is proposed in lieu of gravity or other alternative servicing proposals they must ensure that this planning is acceptable to the Water Corporation. The requirements shall be discussed at an early stage in the planning of the development. Any requirements that will be imposed by other Authorities on the operation of the works must be discussed and agreed to by the Corporation.

7.
7.1

Land requirements
General

7.1.1 All easements, reserves and land to be owned by the Corporation required for a project shall be shown on the design drawings. 7.1.2 Where easements or reserves outside of the developer's land holding are required, written agreement in principle to the arrangements proposed to acquire these easements or reserves is required. 7.1.3 Land requirements for permanent or temporary works shall be discussed with the Corporation Submission Contact (Clause 5.1) at an early stage in the planning of the development, prior to the Initial Submission. 7.1.4 Where necessary the Corporation will require the Design Engineer to produce any documentation necessary to acquire land. 7.1.5 All land requirements shall be satisfied prior to the takeover of the works.

8.
8.1

External approvals
General

At an early stage in the preparation of a submission the Design Engineer shall give attention to the requirements for reference to external agencies as detailed in the Corporations External Approval Manual [including the Corporations (Statutory) requirements for Preliminaries to Works action as required by the Water Agencies (Powers) Act 1984]. 8.1.1 Particular attention and early discussion needs to occur where a design proposal is adjacent to, within or crosses a reserve or asset under the control of either the Mains Roads Department (MRD), Public Transport Authority (PTA), Western Power or Telstra. 8.1.2 Prior to discussing a proposal with these bodies all alternatives should first be considered and input on your design invited from the Corporation before any formal approvals are sought. An impact statement and a ranking is required for each of the options considered 8.2 Preliminaries to works

The Design Engineer shall determine the category of the Works as described in Sections 86 to 97 of Water Agencies (Powers) Act 1984 and shall satisfy the requirements of Guideline 1.2 of the Corporations External Approval Manual.

20

Developers Manual

Developers Manual

Works can be categorised as General, Major or Exempt. Major works are generally carried out by the Corporation and therefore not included in this manual. Most works will be General works and the remainder will be Exempt works. 8.3 Objections

Objections to the proposed works that cannot be resolved by the Design Engineer shall be referred to the Submission Contact (Clause 5.1). All objections shall be resolved prior to commencement of construction. 8.4 Completion required for acceptance of final submission

Completion of all requirements of Preliminaries to Works, including full resolution of objections, is a mandatory condition for acceptance of the Final Submission. (See Clause 14).

9.
9.1

Design requirements
Design submissions

Designs for the works shall be submitted by a Design Engineer. 9.2 Drawing certification

Each drawing (and document) forming the submission shall be signed by an Engineer who has the authority to act on behalf of the Design Engineer making the submission. 9.3 Design responsibilities

Compliance with the Corporations Technical Manuals and Design Standards and with statutory requirements shall be the responsibility of the Design Engineer. Acceptance by the Corporation of a submission shall not relieve the Design Engineer of this responsibility or the responsibility for any discrepancies, errors or omissions in the submission or for the adequacy of the design. 9.4 Drafting standards

9.4.1 For all works, drafting shall generally be in accordance with Australian Standard 1100, Part 101. 9.4.2 For works in categories a) and b) of the Scope (Clause 2.1), drawings shall be suitable for microfilming. Where available, a digital copy of the drawings will be submitted along with the required number of hard copies. In particular, a digital copy of the pre-calculated cadastral plan will expedite the incorporation of information into the Corporations Facility Mapping System. The digital file to be in MGA94 coordinates. 9.4.3 For works in categories c), d), e), f) and g) of the Scope (Clause 2.1), drawings shall conform to the Corporations WCX CAD Standard (formerly WCX Pack). The standard is available from Infrastructure Development Branch, phone contact 9420 2294. 9.5 Standard drawings

Standard Drawings are available in the Technical Manuals and Design Standards. Additional hardcopies or digital copies are available by fax request to the Infrastructure Development Branch at 9420 2203.

21

Developers Manual

Developers Manual

9.6

Example drawings

For Wastewater Pumping Stations Example Drawings shall be used. These can be purchased in digital form by completing the application at Attachment 3 and forwarding it to you Submission Contact.

10.

The major purposes of the initial submission are for the Corporation to: ensure that the planned works conform with the overall planning; and ensure that the preliminaries to works have commenced. 10.1 Requirements for the initial submission

Initial submission

General The initial submission shall consist of: 10.1.1 10.1.2 10.1.3 10.1.4 The Submission Cover Sheet. (See Clause 11.2 The Initial Design Checklist Two copies of the Design Drawings. (See Clause 11.4) A letter from the owners of land, other than the Developer, agreeing in principle to the granting of any easement or reserve considered by the Corporation to be necessary for the works. One copy of the Development Staging Plan for staged developments. (See Clause 11.5) One copy of a Supplementary Survey Plan in cases where there is a likelihood of conflict of services or variations from the standards in the Technical Manuals or Design Standards. (See Clause 11.6) One copy of the approved structure plan for the area

10.1.5 10.1.6

10.1.7 Drainage

Additionally, submissions for Drainage works shall contain: 10.1.8 10.1.9 10.1.10 One copy of the Local Water Management Strategy for the area One copy of the Urban Water Management Plan for the area A letter that includes: A reference to the Department of Waters drainage strategy for the area. A statement setting out the Developers understanding of who is responsible for funding of any proposed future connection of a catchment to any part of the drain covered by this submission. A letter from the appropriate waterway/wetland catchment management agency (eg. Swan River Trust) detailing its comments on the drainage proposal where appropriate. One copy of a soils investigation report where an investigation is required.

10.1.11 10.1.12

22

Developers Manual

Developers Manual

10.1.13 10.1.14

One copy of the summary of the proposed pollutant removal processes and mechanisms within the drainage system including sizing calculations, where appropriate. Two copies of the technical specification. The technical specification shall consist of the technical clauses covering the work, or a statement shall be included in the covering letter confirming that the specification is the same as one previously submitted.

Wastewater pumping stations Additionally, submissions for pumping station works shall contain confirmation that water, electricity, telephone services and an all weather access road will be available in the road reserve in front of the pumping station. Vacuum sewerage Additionally, submission for Vacuum Sewerage Systems shall contain: 10.1.16 A statement from a supplier of an approved vacuum valve, as listed in the DS36 Product Atlas stating that the supplier has received the system design prepared by an approved designer. The statement must guarantee the hydraulics of the system and confirm that the guarantee is transferable to the benefit of the Water Corporation. The Review must be carried out by a suitably experienced Engineer and the Engineer must be explicitly identified in the statement referred to above. Currently approved vacuum valves are: Airvac (contact Watercon as local agent) Flovac (contact Flovac Vacuum Sewerage Systems) Low Pressure sewerage 10.1.17 Low-pressure sewerage systems incorporating grinder pumps . are not currently accepted for wide scale use. They may be accepted for splitting of blocks that are currently serviced by this method. This has typically only occurred where the sewer was installed under the Infill Sewerage Program.Any other proposals for use of this system are to be referred to the Land Servicing Manager.

11.
11.1

Design standard variation requests


General

Given that the Corporations Design Standards are developed to ensure that fit for purpose assets capable of achieving their economic design life with minimal operating and maintenance costs are delivered, a request for a variation will need to be comprehensively justified. 11.1.1 Requesting a design standard variation The Design Engineer shall submit a request to vary a Design Standard in writing to the Submissions Contact. The request shall, at a minimum address the following: A Design drawing detailing the variation/s A statement detailing the reasons / circumstances prompting the request An assessment of the impacts and benefits for both the Corporation and their client Details of the options considered to negate the need for the variation

23

Developers Manual

Developers Manual

11.1.2

Considerations to be made before a design standard variation is submitted Design Standard variations that are requested for any of the following reasons will generally not be considered by the Corporation: Substandard site investigation activities resulting in obstacles or constraints of a non-latent nature Seasonal impacts that will resolve themselves with time Where the Design Engineers assessment is for significant impact to the Corporations fundamental objectives Where the request relates purely to the financial benefit of the proponent Where the request is lacking in some or all of the requirements set out at 11.1.1

11.2 Submission cover sheet for the initial engineering submission to be completed in the following format.

24

Developers Manual

Developers Manual

For the review of initial engineering design submissions Important information for Design Engineers The following details are required to be sent to the Water Corporation with the initial submission of a design: 1. Please make sure that all information listed, including attachments, is included so that the Submission can be processed without delay. 2. Please verify the information by signing on the bottom of the page 3. Please include the signed original of this form with the Initial Design Submission when forwarding to Water Corporation 4. Please ensure all actions are completed on the following submission cover sheet including the water and wastewater checklists

Submission Cover Sheet

General

WAPC number: Stage name/number: Service type (water, wastewater, drainage):

Details of designer

Name of company: Postal address: Phone: Fax: Email Design engineer: Qualified to design works, see Clause 1 and 2.3.2 (please tick)

Design compliance
Attached and completed relevant design checklist

Funding
I confirm that the developer is aware that any easements and/or reserves considered by the Water Corporation to be necessary will be provided free of cost to the Corporation. I confirm that the developer is aware that the works are to be provided at their cost.

External approvals
A strategy for the approval of other parties, including Preliminaries to Works, has been developed with reference to the External Approvals Manual. Note: Should a formal Preliminaries to Works Notice be required Water Corporation authorisation to proceed is a prerequisite.

Declaration of consent
I am duly authorised to represent the proponent/landowner in design matters.

Verification of consent
Signature (Design Engineer) _______________________ Date __________________

Your name and company name _______________________________________________ Email ______________________________________________________________________

25

Developers Manual

Developers Manual

11.3

The Initial Design Checklist for the initial engineering Submission to be in the following format and be specific to the relevant asset type

26

Developers Manual

Developers Manual

Wastewater Reticulation Initial Design Checklist


Location and/or stage name: ____________________________________________

Note: This checklist is to be used to undertake a review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this checklist is to be signed by an engineer qualified and authorised to do so. Content of submission
Submission Cover Sheet enclosed. Two copies of the Design Drawings enclosed.

Drawing format
The drafting is to the appropriate standard i.e. plans are clear and to an appropriate scale. The drawings contain all of the relevant Water Corporation referencing e.g. property address and/or staging identifiers and/or WAPC references are correctly shown on the plans. Beneficiary lots have been identified clearly on the Design Drawing. All easements have been denoted. Note: If the submission is assessed as not meeting the above criteria, the submission will be returned and no further processing or assessment of the submission will occur.

Planning considerations Influencing factors

The design complies with current Water Corporation planning. The design allows for all interconnecting flows (current and future). Where the proposal is dependent on the delivery of headworks assets, the design of headworks assets are at a stage where they are capable of acceptance by the Corporation. The design makes appropriate allowance for existing or proposed physical features of influence i.e. retaining walls, trees, other services, building etc. In the case of designs in existing established areas, the route has been surveyed and the locations of other services and obstructions that may impact on the design have been established. Where the design requires the approval of other parties (i.e. DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed.

Design criteria
Without compromising the planning, the design meets the fundamental objectives of: a) minimising access chambers b) minimising sewer depths c) minimising sewer length d) maximising the locating sewers in public land The design incorporates the most appropriate Access Chamber types and running traps where required. All lots served have sewer junctions at a location and depth suitable to correctly serve the lot/s and boundary traps where required. All fill requirements are denoted (i.e. if design based on contours appropriate tolerances have been applied) All sewer grades are within acceptable tolerances. All sewers terminate at the extremity of the land served unless future extension does not need to be catered for. Connections to existing works have been appropriately designed (i.e. flow to flow where called for) and isolation from live works requirements have been considered and designed appropriately. The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. The design considers the proposed construction technique and/or constraints. For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval. I certify that this design has been reviewed and complies with Water Corporation requirements.

Signature (Design Engineer) _______________________

Date

__________________

Your name and company name _______________________________________________

27

Developers Manual

Developers Manual

Water Supply Reticulation Initial Design Checklist


Location and/or stage name: ____________________________________________

Note: this checklist is to be used to undertake a review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this checklist is to be signed by an Engineer qualified and authorised to do so. Content of submission
Submission Cover Sheet enclosed Two copies of the Design enclosed

Drawing format
The drafting is to the appropriate standard i.e. plans are clear and to an appropriate scale The drawings contain all of the relevant Water Corporation referencing e.g. property address and/or staging identifiers and/or WAPC references are correctly shown on the plans Beneficiary lots have been identified clearly on the Design Drawing. All easements have been denoted. Note: If the submission is assessed as not meeting the above criteria, the submission will be returned and no further processing or assessment of the submission will occur.

Planning considerations
The design complies with current Water Corporation planning Where the design covers more than one water supply zone, the zoning boundary is accurately shown.

Influencing factors
Where the proposal is dependent on the delivery of headworks assets, the design of headworks assets are at a stage where they are capable of acceptance by the Corporation. The design makes appropriate allowance for existing or proposed physical features of influence i.e. retaining walls, trees, other services, building etc. In the case of designs in existing established areas, the route has been surveyed and the locations of other services and obstructions that may impact on the design have been established. Where the design requires the approval of other parties (ie; DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed.

Design criteria
Without compromising the planning, the design meets the fundamental objectives of: e) minimising water main sizing f) efficient use of valves g) minimising bends h) efficient use of hydrants i) minimising long services j) maximising dual services k) minimising dead end mains The design incorporates valving that considers shutdown requirements and the number of properties impacted. The design considers finished surface levels in relation to cover on mains. All water mains terminate at the extremity of the land served unless future extension does not need to be catered for. Connections to existing works have been appropriately designed. The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. The design considers the proposed construction technique and/or constraints. For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval. I certify that this design has been reviewed and complies with Water Corporation requirements.

Signature (Design Engineer) _______________________

Date

__________________

Your name and company name _______________________________________________

28

Developers Manual

Developers Manual

11.4

Design drawings

Technical requirements for the design drawings are given in the appropriate technical manuals and design standards. The design drawings shall include the following: locality plan (drainage only) site plan construction drawings design data plan (sewerage and drainage only). major event plan for drainage (only if required by Water Corporation) For water reticulation works and small sewerage works the site plan and the construction drawings may be combined. 11.5 Development staging plan

The Development Staging Plan is only required for staged developments. A Development Staging Plan need only be submitted with subsequent stages if planning has been revised or if requested by the Corporation. The Development Staging Plan shall show: The total land holdings controlled by the Developer in the area Integration with the Corporations scheme plan Any subdivisions and existing roads The sequence of stages Proposed final contours or, if appropriate, levels for the area Integration / implementation of drainage planning with the proposed staging of development 11.6 Supplementary survey plan

If requested for water and wastewater submissions, the Supplementary Survey Plan shall show any additional survey data obtained for the design of the works such as details of all other existing and proposed services, and significant features such as trees etc. For drainage submissions a Supplementary Survey Plan shall be provided and include as a minimum: Finished surface levels at critical low points in the catchment The extent and level of proposed fill Contours of proposed earth works Road levels where substantially different from ground level Details of existing or proposed water mains sewers, gas mains, underground cables and other services Seasonal and design water levels in the drainage system and compensating basins

12.
12.1

Review of initial submission


Acceptance

The submission will be checked for conformity with the Corporations overall planning requirements. The submission will be:

29

Developers Manual

Developers Manual

Accepted - if the submission is acceptable to the Corporation, it will be stamped as accepted, the Corporation reference numbers and one copy of the drawings will be returned to the Design Engineer. The Design Engineer will then be in a position to proceed with the final submission; or Accepted with amendments if the submission is acceptable to the Corporation with minor amendments, it will be stamped as accepted conditional to the amendments being made, or Rejected if the initial submission is not acceptable, the Corporation will reject the submission and request that the design be reconsidered. Amended drawings

12.2

When drawings are amended and resubmitted, they shall be distinguished from previous submissions by a new revision identifier. A brief description and date of the amendment shall be included in the title block.

13.

Objections to the Corporations requirements

If a Design Engineer objects to a planning or design decision made by the Corporation, the objection shall be stated in writing. The objection shall be addressed to the Corporation Submission Contact (see Clause 0), quoting Corporation and WAPC references and all relevant information. At the request of the Design Engineer, unresolved objections shall be referred by the Submissions Contact to the Manager Development Services Branch.

14.

Final submission

The Final Submission includes the provision of final plans, incorporating references provided by the Corporation and any amendments required as a condition of acceptance the finalisation of Preliminaries to Works. 14.1 Final submission requirements

The final submission shall consist of the following documents: The Submission Cover Sheet. (See Clause 15.1) Copies of the Design Drawings, calculations and specifications as detailed in Clause 15.2. An agreement in writing formalising the arrangements for the provision to the Corporation of any land, reserves or easements required for the works. A list of the existing lots serviceable as a result of the works. The list shall show the lot numbers and land use e.g. residence, industrial units, stables etc. (NB property owners names and addresses are not required). Drainage In addition, final submissions for drainage shall include: Maintenance agreements negotiated with the Local Authority in accordance with the requirements in the Technical Manual and Design Standards A copy of the letter of acceptance from the Local Authority stating that all aspects of the submission including where applicable, environmental, social implications and the provisions for major storm events, are to the Local Authority's requirements.

30

Developers Manual

Developers Manual

14.2

Approval from the Western Australian Planning Commission

Final Submissions for works associated with land subdivision will not be accepted by the Corporation prior to subdivision conditional approval from Western Australian Planning Commission. 15. Details of final submission

15.1 Submission cover sheet The Submission Cover Sheet for the final engineering submission shall be in the following format:

31

Developers Manual

Developers Manual

For acceptance of final engineering submissions


Important information for Design Engineers:
The following details are required to be sent to the Water Corporation with the Final submission of a design. 1. Please make sure that all information listed is included so that the Submission can be processed without delay. Please note that accepted submissions will only be forwarded to the Inspections Contact when details of the Construction Engineer and the Contract are provided. 2. Please verify the following information by signing on the bottom of the page. 3. Please include the signed original of this form with the Final Engineering Submission when forwarding to Water Corporation. 4. Please note that the Water Corporation will not accept a final submission until advice of WAPC conditional approval of the subdivision has been received. 5. Please note that it is a requirement of the Developers Manual for details of Item 3 & Item 4 to be provided in writing a minimum of five days prior to commencement of the works.

Submission Cover Sheet

General
WAPC number: Stage name/number: Service type (water, waste water, drainage):

Initial design review


I confirm that this submission conforms with the Initial Submission returned by the Water Corporation including required amendments OR If any variations have been made, a description and reason for each variation is attached Where a variation to a design standard has been approved the relevant approval is attached

Details of construction engineer (if known)


Name of Company: Postal Address: Phone: Email Project Manager: Qualified to carry out works Fax

Details of contract (if known)


Name of Contractor: Address: Phone: Email Project Manager: Contract Price (excl GST): $ Qualified to carry out works Fax:

External approvals
1. The requirements of the External Works Manual and the Utilities Providers Code of Practice have been satisfied
i.e. All necessary approvals have been identified and obtained including environmental clearances and conditions that have been imposed by those authorities on the construction or operation of the works. 2. All approvals shall be kept for the statutory period and only those that relate to land owners directly impacted by the works or where requested by the Water Corporation have been included. 3. There are no unresolved objections arising from the Preliminaries to Works process for the proposed works. 4. For Non Subdivision works, a statement is attached regarding the identification and management of clearing of native vegetation including a copy of the Clearing Permit if applicable.

List of existing lots now serviceable as a result of the works


Please ensure this question is completed before signing off on this form. Failure to complete correctly may result in delays with processing your submission. The attached list details lot numbers and property use (e.g. house, industrial units, stables etc) of lots that have become serviceable because of the works carried out. (NB Property Owners names and addresses are not required). Serviceable land will be rated as per Section 41(1) (b) of the Water Agencies (Powers) Act 1984

Verification of content Signature Design Engineer __________________________ Date ________________

32

Developers Manual

Developers Manual

15.2 Drawings Technical requirements for the Design Drawings are given in the Appropriate Technical Manuals and Design Standards. Drafting standards are specified in Clause 9.4. For all works the Design Drawings shall comprise: Six hard copies of the site plan Six hard copies of the construction drawings Two hard copies of the design data plan (sewerage and drainage only) Two hard copies of the major event plan for drainage (If required by Water Corporation)

For water reticulation works and small sewerage works the site plan and the construction drawings may be combined. In addition, for works in categories C, D, E, F and G of the Scope (Clause 2.1) the Design Drawings shall include an electronic copy of the above drawings (site plan, construction drawings and design data plan). Addition Information In addition, the Final Design Submission Drawings for Urban Main Drainage works may include when requested: One copy of the design calculations Two hard copies of the specifications plus an electronic copy An electronic copy of the computer model used

16.
16.1

Acceptance of a final submission


General

The plans will be signed by the Corporation to indicate that the final submission has been accepted. One copy of the accepted drawings of the final submission will be returned to the Design Engineer. The acceptance of a final submission will remain valid for a period of 12 months from the date of acceptance. If construction has not started within this period the acceptance will lapse and the submission shall be re-submitted. If the construction is divided into more than one stage and work on some of the stages has not commenced within 12 months of the date of acceptance, then acceptance for these stages will lapse and a new submission will be required. Acceptance by the Corporation of the submitted documents shall not relieve the Design Engineer of the responsibility for any discrepancies, errors or omissions in the documents, adequacy of the design or conformance with the relevant Technical Manual or Design Standard.

33

Developers Manual

Developers Manual

17.

Alterations to an Accepted Final Submission

Once the Corporation has accepted a final submission, any alterations to the design shall be discussed with the Corporation and determination as to whether a new submission is required shall be made by the Corporation. Requests for minor realignments of pipelines or relocation of access chambers, valves and connections within the requirements of the Technical Manuals and Design Standards shall be discussed with the Asset Inspector. Requests for any other changes shall be discussed with the Submissions Contact.

18.
18.1

Pre-start-up meeting requirements


General

The name of the Construction Engineer and contact details. The name and contact details of the Contractor and or subcontractors. The contract price for the works, as defined in the Scope (Clause 2.1). For works in categories A, B, E and F a total cost only is required. For works in categories C, D and G a breakdown of costs shall be given. See Section 29. The proposed date for commencement of work.

Before construction commences the Construction Engineer shall ensure: The Final Submission has been accepted by the Corporation. Clearance to Works (CTW) Permit has been obtained, when required, from the Corporation (Customer Service Delivery). (See Section 28) The Contractor employs personnel who have appropriate skills and if required by the Corporation accreditation, for the performance of the tasks in which they are involved. Accreditations required shall be designated in the relevant Technical Manual or Design Standard Notice of Proposed Works

18.2

Where property, other than that owned by the Developer, will be affected by construction of the proposed works, the Construction Engineer shall ensure that written notice has been given to the occupiers of such property at least 10 days prior to commencement of work that will affect the property.

19.
19.1

Start-up meeting
General

The Corporation will advise the Construction Engineer when the plans ave been received by the Inspections Contact (Clause 5.2). Prior to the commencement of the works the Construction Engineer shall contact the Inspections Contact and arrange for the assignment of an Asset Inspector. From this point forward arrangements are to be made directly with the assigned Asset Inspector. Prior to the commencement of the works the Construction Engineer shall arrange and attend a Start-Up meeting with the Asset Inspector. 34 Developers Manual

Developers Manual

The Start-Up meeting shall be held at the site of the proposed works. The Construction Engineer shall ensure that a record of the meeting is made. This record shall detail the key information and agreements reached. The following issues shall be addressed at the start-up meeting: Dates for commencement and completion of construction. Method of isolating the new works from the existing works during construction. Inspection Plan, detailing which parts of the works (including testing) the Asset Inspector will inspect, when these inspections are proposed to take place, and any requirements necessary to facilitate these inspections. Nomination of additional staff who will access the site of the proposed works, to carry out inspections. Contact and reporting arrangements including signing of site inspection reports. Arrangements for the protection of Corporation Assets. Arrangements for the connection of new work to existing infrastructure. Arrangements for inspection and testing processes. Milestone meetings at which joint attendance is required. Commissioning plan


A copy of the meeting record shall be forwarded to the Asset Inspector prior to the first inspection.

20.
20.1

Construction requirements
General

If a change of Contractor becomes necessary, the Construction Engineer shall notify the Corporation of the new Contractors name and contact information as provided for in Clause 18.1. Any requirements of the Corporation regarding the Contractors work shall be directed to the Construction Engineer, not to the Contractor. Work shall be carried out in accordance with the requirements of the relevant Technical Manual or Design Standard, relevant Acts and By-laws and this manual. The Construction Engineer shall ensure that the Contractor is aware of, and agrees to comply with, the requirements of any authority in regard to the protection, diversion or relaying of any service affected by the works. The Construction Engineer shall ensure that the Contractor is conversant with any agreement with any Authority such as the Department of Aboriginal Affairs or Ministry for Planning into which the Design Engineer, the Developer or the Corporation may have entered. The Construction Engineer shall ensure that the Contractor verifies by survey the location and level of the point of connection to the existing system.

35

Developers Manual

Developers Manual

20.2

Protection of Corporation Assets

Corporation assets shall not be disturbed without the approval of the appropriate Regional Office on each and every occasion. OR Excavation or construction work shall not be carried out in close proximity to any existing Corporation asset until: A joint inspection of the asset has been carried out by the Corporation and the Construction Engineer to ascertain the condition of the asset; and The Asset Inspector has been given two working days notice of the intention to commence work.

The Construction Engineer shall ensure that adequate measures are taken to protect the Corporations assets from damage during construction of the works. If any damage occurs to existing assets the Construction Engineer shall immediately notify the Corporation and the cost of repairs will be charged to the Developer.

21.

Isolation of new works (sewers and drains only)

The purpose of isolating non-commissioned sewers from live sewers is to provide a safe working environment for construction, testing and inspection of the new work. Where the noncommissioned sewer system is not isolated from the live sewer, entry to and work within the new sewer system is subject to the provisions of Australian Standard AS2865, Safe working in a confined space. 21.2 General

The Construction Engineer shall make the necessary arrangements for the new works to be isolated from the live sewer prior to the commencement of construction and ensure that the isolation is maintained until the Final Inspection Clearance has been issued by the Asset Inspector (See Clause22.7). The new works shall be either not connected (physical break) or shall be physically isolated from the live sewer. A physical break is the preferred method and should be used wherever practical. Where a physical break is not practical, the Construction Engineer shall apply to the Corporation (Customer Technical Services) to have the live sewer sealed off prior to construction and removed following the issue of the Final Inspection Clearance of the works. The Water Corporation will notify the Construction Engineer in writing when the line has been isolated (seal installed and ready for testing) and again when the isolation has been removed. Where the live sewer has been plugged (150 or 225mm sewers), the Construction Engineer shall arrange for the plug to be tested to 50 kPa for one minute with no drop in pressure. The test shall be conducted on the upstream side of the plug prior to any entry by Corporation staff. The test shall be logged in the Construction Engineers Log of Inspections and Tests. Where the live sewer has been sealed with a plastic membrane and brickwork (Sewers 300mm and above), the Construction Engineer shall establish a testing schedule acceptable by Worksafe to ensure that the isolation is effective.

36

Developers Manual

Developers Manual

22.

Inspection of works during construction

22.1 General The Construction Engineer shall make provision for access by Corporation Officers or representatives of the Corporation to inspect the works during construction. The Asset Inspector (including additional staff) shall have access to the site at any time provided the Construction Engineer or Contractor is on site. Inspections by the Corporation do not in any way relieve the Construction Engineer of the responsibility for ensuring that construction of the works is in accordance with the design documents and that it complies with the requirements of the Technical Manual or Design Standard. The Construction Engineer shall arrange for the provision of all personnel and equipment required for scheduled inspection and testing. 22.2 Construction engineers log of inspections and tests

The Construction Engineer shall ensure the works are inspected and tested to ensure that the requirements of the Technical Manual or Design Standard are satisfied. The Construction Engineer shall ensure a log of all inspections and tests undertaken are maintained. The log shall record the following information: Inspections and/or tests witnessed of the works, which were considered satisfactory. To this effect the Construction Engineer shall sign the following statement on the Construction Engineers log: I am satisfied that the above inspection and tests have been carried out. Inspections and / or tests witnessed of the works, which were considered unsatisfactory. Any remedial action undertaken to the works as a result of an unsatisfactory inspection prior to re-inspection.

A copy of the Construction Engineers inspection log and test results shall be available to the Asset Inspector on site. The log shall include but not be limited to the date, time, item tested, type of test, result of test and the witness. The person witnessing the inspection and /or test shall sign the log. 22.3 Notification of inspectors

The Construction Engineer shall notify the Asset Inspector when the stages of construction that were agreed at the Start-Up meeting are about to be achieved. These stages may be revised during the construction period by mutual agreement. Notification shall be made at least one full working day in advance of the stage of construction being reached. If the Asset Inspector cannot complete an inspection due to the condition of the works, reinspection costs may be charged to the Developer. 22.4 Site safety

Asset Inspectors will comply with the Contractors site safety procedures while on site. Asset Inspectors will not enter sites that they consider unsafe by Worksafe Standards.

37

Developers Manual

Developers Manual

Should construction proceed without the Asset Inspector having the opportunity to carry out an inspection because of unsafe conditions, a final inspection will not be undertaken until any inspection cancelled because of unsafe conditions has been successfully completed and the construction approved. Where safety issues relating to the inspection cannot be resolved between the Construction Engineer and the Asset Inspector they shall be referred to Worksafe for advice/resolution. 22.5 Progressive Site Inspections by Asset Inspector

The Construction Engineer shall give no less than 1 working days notice of any request for a Progressive Site Inspection. On arrival at the site the Asset Inspector shall advise the person in charge of the site prior to conducting any inspection. At each inspection the Asset Inspector will complete a Site Inspection Report. The report shall describe the works inspected and any non-conformances identified. The Site Inspection Report shall be signed on site by the person agreed to at the Start-Up meeting. The Asset Inspector shall provide a copy of the Site Inspection Report to the person agreed to at the Start-Up meeting. Works will not be connected to existing assets until payment of all associated fees has been made and a Final Inspection Clearance has been issued. 22.6 Pre-takeover inspection

Prior to booking a Final Takeover Inspection the Construction Engineer Shall undertake a Pre-takeover Inspection. A Pre-takeover Inspection Checklist Shall be completed by the Construction Engineer and provided to the Asset Inspector with all of the Test Logs prior to the Final Takeover Inspection.

38

Developers Manual

Developers Manual

Plan Set No: _____________ WAPC Ref No. _____________ Location and/or stage name: _____________________________ This checklist is to be used by the Construction Engineer to undertake pre-takeover inspection prior to booking a final takeover inspection with the Water Corporations Asset Inspector. The certification at the bottom of this checklist is to be signed by an Engineer qualified and authorised to do so.

Pre-takeover inspection checklist

Test and inspection logs/certificates


Test and inspection logs have been maintained, checked and signed for (delete if not applicable): a) Pressure testing b) Ovality testing c) Lines sighted d) Spark testing e) Product specification (date of manufacture, supplier / brand) f) Bedding, jointing and installation of pipe work checked g) Anchor blocks in place and to specification h) Valve and hydrant supports are in place and to specification i) Denso tape and paste has been applied where required Compaction Certificates have been maintained, checked and signed. All testing equipment used has been recorded by Identification No. and current calibration certification is provided.

Water supply physical inspection items


The following items have been physically inspected and verified: a) b) c) d) All water services are in place , correctly positioned, protected and to specification Denso tape and paste has been applied where required All valves and hydrants are in place and to specification All marker posts are in position and to specification

Wastewater Physical Inspection Items

The following items have been physically inspected and verified: a) Isolation is in place b) Access chambers (complete, clear , correct covers) c) Maintenance Shafts (complete, clear, correct covers) d) Property connection markers are in place I certify that the assets constructed meet all Water Corporation requirements. Signature _______________________ Date __________________ Your name and company name _______________________________________________

39

Developers Manual

Developers Manual

22.7

Final takeover inspection

When the works have been completed the Construction Engineer shall arrange a Final Inspection with the Asset Inspector. The Construction Engineer shall provide no less than 2 working days notice of any request for a final Inspection. Where the works include the construction of a Sewerage Pumping Station the Construction Engineer shall supply to the Asset Inspector delivery dockets for the following key components: Pumping station segments detailing manufacturer and class of pipe Pumping station top slab detailing manufacturer, type and class of covers Sluice, reflux and knife gate valves detailing manufacturer, class and the Australian standard to which it was designed

Prior to the final takeover inspection the Asset Inspector shall confirm with the Construction Engineer the requirements to enable the inspection to be carried out. The Asset Inspector and the Construction Engineer shall jointly inspect the works. Where the number and/or seriousness of non-conformances indicates that the works have not been adequately inspected and/or tested by the Construction Engineer, the Asset Inspector may terminate the Final Inspection and require the Construction Engineer to carry out his own inspection of the works before again making arrangements for a Final Takeover Inspection. At the conclusion of the Final Inspection the Asset Inspector will complete a Site Inspection Report. The report shall describe the works inspected and any non-conformances identified. Where the works are deemed to be acceptable the Asset Inspector shall arrange for a final inspection clearance to be issued to the Construction Engineer.

23.
23.1

Connection to existing assets


General

Connections or alterations required to the Corporations existing infrastructure because of new works shall be by prior arrangement with the Corporation. All such work shall be at the Developers expense. The Corporation reserves the right to undertake all such connections or alterations. The Construction Engineer shall make the necessary arrangements for the payment of fees for the connection of the new works to the existing assets (see Section 4). When the works are deemed to be acceptable, the Asset Inspector shall initiate the connection of the new works upon the request from the Construction Engineer. New works will not be connected to existing assets until payment of all associated fees has been made and a Final Inspection Clearance has been issued.

40

Developers Manual

Developers Manual

24.
24.1

Recording of as-constructed information


General

The As-constructed information shall be certified "As-constructed", signed and dated by an engineer who has the authority to act on behalf of the organisation that is responsible to the Corporation for the construction of the works and by the surveyor (who is eligible for membership of I.E.M.S.A. or I.S.A.) responsible for the survey. The As-constructed details shall be in accordance with the relevant Technical Manual or Design Standard or this manual. 24.2 Submission Requirements of As-constructed Information

The completed and signed As-constructed information shall be submitted to the As-constructed Information Contact (see Clause 5.3). One copy of the As-constructed information shall be submitted. 24.3 As-constructed information

Water Reticulation works As-constructed information shall consist of: The As -constructed plan in accordance with the typical information provided in Water Corporation Design Standard 63. The latest pre-calculated cadastral plan (in MGA94 Coordinates only) for large areas, otherwise a hard copy for small subdivisions.

Wastewater Reticulation works (the information/instruction below amends and/or supplements that contained in Wastewater Manual Volume 1) The As-constructed plan in accordance with the typical information provided at Attachment 4 of this Manual. All aspects of Section 6 of the Water Corporations Wastewater Manual Volume 1 must be complied with, other than the As-constructed plan mention at 24.5.3 replacing all references to Field Notes. The latest pre calculated cadastral plan (in MGA94 Coordinates only) for large areas, otherwise a hard copy for small subdivisions. A contour plan if earthworks have been carried out that has changed a contour by 0.5 metre or more. Wastewater pumping stations and pressure mains, main sewers water tanks, water distribution mains and urban main drainage works Marked up Design Drawings, signed by the Construction Engineer and an electronic copy of the asconstructed documents. As-constructed information must comply with the requirements of the relevant Technical Manuals or Design Standards. Should the submission be assessed as not meeting the above criteria with regard to completeness and correctness there will be no acceptance date recorded or capture commenced until requested information is received.

41

Developers Manual

Developers Manual

25.
25.1

Takeover of the works


General

Only whole projects, as defined by a submission, will be considered by the Corporation for Takeover. The Developer shall remain fully responsible for the works until the date of written notification of Takeover from the Corporation. A prerequisite to Takeover is that the works are the subject of an agreement between the Developer and the Water Corporation. 25.2 Requirements for Takeover

Subject to connection to the existing system being available, Takeover is achieved when: A Final Takeover Inspection has been completed and a Final Inspection Clearance has been issued by the Asset Inspector. The Construction Engineer has certified that the works have been constructed in accordance with the documents accepted by the Corporation and the requirements of the Technical Manual or Design Standard. The as-constructed information has been submitted to the As-constructed Contact and has been validated. The Corporation will validate the data within 10 working days of its submission, if the information is correct. The Construction Engineer has certified that restoration has been performed to the satisfaction of any affected property owner and authorities. Any fees required have been paid. All land requirements have been satisfied. The Corporation has cleared the subdivision agreement requiring these works. The Corporation has notified the Developer in writing that Takeover has been achieved. Date of Takeover

25.3

The date of Takeover will be taken to be the date that all the requirements of the previous Clause have been completed.

26.
26.1

Warranty Period
General

The warranty period shall commence on the date of take-over. The warranty period shall be for 1 year. During the warranty period, the Corporation shall be responsible for operational maintenance of the works in accordance with normal practice.

42

Developers Manual

Developers Manual

26.2

Remedial Repairs during Warranty

During the Warranty Period the Developer Shall be responsible for ensuring that satisfactory remedial repairs arising from faulty design, workmanship or materials are carried out. The cost of any consequential damage and claims resulting from such defects shall be charged to the Developer. During the warranty period, the Corporation may, at its discretion carry out remedial repairs where the fault affects the service to customers and/or public safety. The Corporation will notify the Developer of the work carried out as soon as practicable where the remedial repairs are attributable to the construction of the works. The cost of the remedial repairs shall be charged to the Developer. 26.3 Remedial Repairs post Warranty

Where remedial works carried out by the Corporation are determined to be attributable to a design or construction error or omission the cost of the remedial works shall be charged to the Developer. Remedial works shall include, but not be limited to, the absence of infrastructure components (i.e. missing sewer junctions), incorrect installation (i.e. inadequate bedding or compaction) and inadequate separation of any component of the works from other infrastructure (i.e. inappropriate separation distance between water and electricity assets).

27.
27.1

Final acceptance certificate


General

Prior to the end of the Warranty period the Corporation will assess whether there are any defects. If so, the Asset Inspector will notify the Developer of the list of defects. Otherwise, the Asset Inspector will issue the Developer with the Final Acceptance Certificate, within seven days before the end of the Warranty Period. Providing that any defects have been rectified to the satisfaction of the Corporation, a Final Acceptance Certificate shall be issued by the Corporation.

43

Developers Manual

Developers Manual

28.

Attachment 1 Clearance to work permit guidelines

Assets likely to be affected include: Water mains (especially RC, AC, CI etc) Pressure mains Main sewers Piped Water Corporation main drains Pump stations (pipework, pits, electrical cables, alarm lines etc) Requirement for a permit is essentially a product of: Type of asset Proximity and depth of excavation in relation to an existing asset Soil conditions Construction method

Clearance to work permits will be required where: 1. Open excavating parallel to or crossing an existing water main, pressure main, main sewer or piped drain at an acute angle (less than 450 ) where the integrity of the asset may be impacted by the Works. (e.g. within 2 metres of an asset and greater than 1 metre below the invert of an asset). Note: there may be instances where this citeria is not appropriate and the desiginer must therefore consider the type of asset, proximity of the sewer, difference in invert levels and soil conditions. If any doubt exists the specific circumstances should be referred to the Region for assessment. Crossing under an existing asset where the clearance between the assets will be minimal (say <500mm). Any crossing under a water main with a diameter greater than 200mm. Excavating in or around pump station sites as buried assets and services are not necessarily in accordance with that shown on 'as-constructed' plans. Any connection to an existing asset. All Works in the vicinity of RC mains should be referred to the Region for special consideration.

2. 3. 4. 5. 6.

Most failures have occurred as a result of the loss of support to RC or AC water mains and are preventable if a "cut and cap" is arranged at the appropriate time. If any doubt exists the designer/contractor should refer the specific circumstances for assessment by the region.

44

Developers Manual

Developers Manual

29.

Attachment 2
Breakdown of costs

As per Clause 18.1 it is required that a breakdown of costs, into the components shown below, be provided for works in the following categories. 29.1 Category C Water and Wastewater Pumping Stations and Pressure Mains

Civil works: Includes all civil costs associated with site preparation and concrete structures (Water - pump blocks, footings, floor pads, ducting etc. Wastewater wet well, floor pad, overflow storage, oxygen dissolver etc.) and any building (irrespective of material used for the building), as well as the costs of any cranes, sound proofing etc. Machinery: Mechanical equipment included costs of pumps, valves and interconnecting pipework (excluding manifolds). Electrical installation: Includes cost of motors, switchboards, HV equipment, instrumentation, telemetry and control systems. Pipework and fittings: Costs of pipework, valves, pits, surge vessels etc located outside of the pumping building but within the site. Fencing roads: Costs of roads and parking areas, with separate entries for sealed and unsealed roads if applicable. Pressure Mains: Cost of pipework from the boundary of the site to the discharge point. 29.2 Category D Water Tanks

Tank name: Including material and capacity of tank, and for elevated tanks the tank height. Tank structure: Includes all costs associated with site preparation, tank construction, stilling tubes and cathodic protection. For elevated tanks also includes the cost of the stand. Pipework and fittings: Costs of pipework, valves, pits etc located outside of a radius of three (3) from the tank but within the site. Fencing roads: Costs of roads and parking areas, with separate entries for sealed and unsealed roads if applicable. Instruments: Telemetry, mag flow meters etc (if applicable). 29.3 Category G Water and Wastewater Treatment Plants

Breakdown of costs to be assessed on an individual basis.

45

Developers Manual

Developers Manual

30.

Attachment 3

Application for single use of Water Corporation example drawings for pumping station facility in electronic format
Pumping station requirements PS Type (10, 10D, 40, 40D or 90): Estimated kWs (Decontactor Model Only): PS Title/Name: PS Peak Design Flow (Estimated): PS Catchment Pumped Outflow (Estimated): Nominated Discharge Sewer Size & Access Chamber: Pressure Main Size & Length: PS Pipework Size: Emergency Overflow Discharge Location (Brief Description): Level of lowest sewered lot in PS Catchment: Maximum HGL of Emergency Overflow: Storage Volume in Sewerage System below emergency overflow IL: Pumping facility Pumping Station Civil Works PS Discharge Pipework and Valves Pumping Equipment Electrical Switchboards and Equipment Copy of Funding Agreement Provided Water Corporation contact if applicable: Applicant Details Main Consulting Engineer: Nominated Civil Design Engineer: Electrical Design Engineer: Drafting Software/Version and Release No: Date of Application: Contact & Postal Address: E-mail Address: On completion please return to the Serving Consultant managing the project. Water Corporation Office Use Forward the completed form to IDB with advice that payment of the applicable fee is required/not required. Developer funded Yes / No Yes / No Yes / No Yes / No Yes / No Developer pre-funded Yes / No Yes / No Yes / No Yes / No Yes / No

46

Developers Manual

Developers Manual

31.

Attachment 4: Example of wastewater reticulation as constructed plan

47

Developers Manual