Professional Documents
Culture Documents
ASSiGNMENT NICMAR/CODE Office Name AJEET SINGH 213-03-11-11416-2153 Reg. No. (PGPCM) Course No. Course Title Assignment No. Date of Dispatch Last Date of Receipt NCP 23 Construction Contracts and Contracting
ASSIGNMENT Contract administration and monitoring is the most important area of construction management. Contract administration process start right from the day work is assigned to the contract. Discuss any project contract currently in progress with your company and how administration and monitoring is being done. Draw the organization chart for the activity and explain all the function carried out. Do you think the system is achieving results? Discuss.
Name of project:
Earthwork, Blanketing and Construction of RUBs under Maharjganj Mashrakh new Railway Line Project.
Project Description:
This project requires construction of 59 nos of RUBs to provide safe passage to people in the 36.155 kms stretch of new railway line connecting Maharajganj in Siwan Dist., Bihar to Mashrakh, Chhapra Dist., Bihar. The idea of providing so many RUBs is that if people are not given a grade-separated passage then Level Crossings will have to be provided which is a safety hazard in the first place. Every year, there are thousands of causalities reported due to accidents on Level Crossings. Hence in a new line project it is beneficial to plan ahead and minimise the number of Level Crossings.
Name of company: Name of contractor: Type of contract: Value of contract: Time schedule:
Construction Organisation, N.E. Railway Megotia Construction Pvt. Ltd., Jamshedpur. Works Contract 15.81 crores Contract awarded in May09. Completion period was 15 months
2.
ESTIMATION Estimation was done in house by Planning and Design Cell of the construction organisation. Firstly, an ABSTRACT ESTIMATE is prepared for lump-sum estimation of total project cost. Allotment of funds from Railway Board is done on the basis of this Abstract Estimate. While process of funds allotment is going on in Railway Board, the scope of work is discussed in detail and exact quantities to be carried out is reached which forms the basis of DETAILED ESTIMATE. Based on Detailed Estimate, tenders are floated and awarded to lowest eligible tenderer.
3.
On the basis of Lowest quote, the contract was awarded to the agency mentioned above in March09.
Compensation for Price Variation if the delay is not due to the fault of the contractor. This agreement required three activities Earthwork, Blanketing and RUBs. None of these activities can start if the land is not handed over by the State Government to the Railway. However, there may be delays on the part of State Government in acquiring the land causing delay in execution of project. Thus, the machinery allotted for the project and human resources may remain blocked for a period longer than planned by the contractor. Also the cost of materials is bound to rise while in the waiting period due to market factors. Therefore some compensation for unavoidable delays due to unforeseen reasons is warranted. In this contract, there is a clause for PRICE VARATION ESCALATION. Timely Payments to the contractor. This contact is worth 15.81 crores and the agency is required to have successfully executed any work of similar nature for 1/3 of this value. Generally agencies keep their capital circulating among various projects based on the need. Hence it is of utmost importance for any contractor that his capital is not blocked. There is no fixed time schedule in this contract nor there is any provision of payments linked to any specific goals. The payment is completely in discretion of PM and he is empowered to prepare and disburse bills on his satisfaction. The benefit of this system is that it is completely flexible but a major disadvantage is that the PM can cause undue hindrances to the contractor if he wishes so.
required to establish a field lab for testing of materials and specimens as per the above mentioned codes and keep a record of the result obtained. For the overall monitoring and spot checking, Railway representatives are responsible and they regularly check and ensure that these records are regularly maintained. 3. If the contractor executes any work without the knowledge of Railway representatives, he shall remain responsible for the quality of the deliverables. He will be required to furnish all records in this case and arrange for Non-destructive testing of the work. The PM if satisfied can accept or reject his work.
ORGANISATIONAL CHART
Chief Engineer-1
Dy. Cheif Engineer -1 Dy. Cheif Engineer -2 Dy. Cheif Engineer/Design Dy. Cheif Engineer -3 Dy. Cheif Engineer/Planning Dy. Cheif Engineer -4 Dy. Cheif Engineer -5 Dy. Cheif Engineer -6 Dy. Finance Manager
Chief Engineer-3
Chief Engineer-4
At the top of the organisation is Chief Administrative Officer/Construction (CAO/Con.). He is responsible for the overall administration of the Construction Organisation. He allocates work to each Chief Engineer. He is responsible for liasoning with General Manager of the Railway and also Railway Board for demand of additional funds and submission of yearly expenditure report/Funds Demand.
Chief Engineer acts as the CPM for each project. Projects are allotted to the Chief Engineers by CAO/Con and they are responsible for awarding and managing the contracts above 10 crore.
Dy.Chief Engineers works under the Chief Engineer and act as CPM for managing the contracts below 10 crore.
Contract Management authority at various level are independent to manage their contracts regarding time extension, variation in quantities, inclusion of new items, variation in expenditure as allowed by General Conditions of Contract prescribed by Railway Board.
Executive Engineers assist the Dy. Chief Engineer and Chief Engineer in areas of administration on site w.r.t Quality Control and Monitoring of Progress.
All proposals which entail expenditure more than 25% of the stipulate value should first be vetted by Dy. Funds Manager before allocation of additional funds.
Yes
No
Extension with Price Yes Escalation Project Urgent New Contract for No remaining work
Arbitration Any dispute arising between the Employer and the Domestic or Foreign Contractor related to any matter arising out of or connected with this contract, the disputes shall be settled in accordance with the Indian Arbitration Act, 1996 and any statutory modification or re-enactment thereof. Further, it is agreed between the parties as under: (i) Number of Arbitrators depends upon the value of arbitration amount involved. (ii) Procedure for Appointment of Arbitrators: The arbitrators shall be appointed as per following procedure: (a) Employer will forward a panel of 10 names to the Contractor and Contractor will give his consent for any name out of the panel to be appointed as one of the Arbitrators as the case may be. (b) In case of more than one arbitrator, Railway will decide the second Arbitrator out of the remaining names in the panel as mentioned in Para (a) above. (c) The third Arbitrator shall be chosen by the two Arbitrators so appointed by the parties and shall act as Presiding Arbitrator. In case of failure of the two Arbitrators appointed by the parties to reach upon consensus within a period of 30 days from the appointment of the Arbitrators subsequently appointed, then, upon the request of either or both parties, the presiding Arbitrator shall be appointed by the General Manager, N.E. Railway. (iii) Neither party shall be limited in the proceedings before such arbitrators to the
evidence nor did arguments previously put before. (iv) Arbitration proceedings shall be held at Gorakhpur, India and the language of the
arbitration proceedings and that of all documents and communications between the parties shall be in English. (v) The decision of the majority of arbitrators shall be final and binding upon both
parties. The expenses of the conciliator/arbitrators shall be as per the scales fixed by the employer from time to time and shall be shared equally by the Employer and the Contractor.
However, the expenses incurred by each party in connection with the preparation, presentation will be borne by it. (vi) All arbitration awards shall be in writing and shall state the reasons for the award i.e
SPEAKING ORDER. However, in case the Contractor is a Public Sector Enterprise/ Govt. Department, the dispute arising between the Railway and the Contractor shall be settled through Permanent Arbitration Machinery (PMA) of the Department of Public Enterprise, Govt. of India as per prevailing rules.
Monitoring Methods
1. 2. 3. Monitoring by financial progress through monthly expense report Monitoring by physical progress through undertaking site inspections Administering by disbursement/Non-disbursement of Contractors Bill as no payment schedule is provided in the contract. 4. 5. Quality control by spot-inspections and non-destructive/partially-destructive testing. Surprise checks by Vigilance Organisation of Railway. Vigilance Organisation is independent of the project and is empowered to scrutinise records/take samples from the site. 6. 7. Debarring the failed contractors from participating in the bidding of any further contracts. Provision of LIQUIDATED DAMAGES @ 0.5% per week delay if the delay is on the contractors part. However, if the delay is on the part of Railway then contractor is entitled to Price Escalation Compensation.
Recommended Reading a. b. c. Contract Management in Construction Industry C.V.J. Varma and Bhupinder Kumar Construction Contracts Administration Charles S. Phillips Arbitration: Essential Concepts - Steven C. Bennet