You are on page 1of 48

OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTEE

Barangay of Aslum
Municipality of Julita
Province of Leyte

SUB-PROJECT PROGRAM OF WORK


Sub-Project Title
Sub-Project Category
Physical Target
Total Sub-Project Cost

Diversion Works Structure


1

Project Description
Construction of Diversion Work Structure
Item No.
1.00
2.00
3.00
3.10
3.20
3.30
3.40
3.50
3.60
4.00
4.10
4.20
4.30
5.00
5.10
5.20
5.30
6.00
6.10
6.20
6.30
6.40

Scope of Work
Coffer Dam
Diversion of Water & Care of Creek
Intake Weir Structure
Excavation
Boulder Fill
Gravel Bedding
Concrete Class "A" (3000 psi)
Reinforcing Steel Bars
Structural Backfill
Handlaid Riprap
Excavation
Gravel Bedding
Riprap (Handlaid)
Grouted Riprap
Excavation
Gravel Bedding
Riprap (Grouted)
Intake Works
Excavation
Concrete Class "A" (3000 psi)
Reinforcing Steel Bars
Structural Backfill
Total
Breakdown of Estimated
Sub-Project Cost
A. Direct Cost
Material Cost
Equipment Rental
Labor Cost
a.) Skilled
b.) Unskilled
Sub-Total A
B. Indirect Cost
Pre-Engineering
Engineering Supervision
Contractor's Profit
Taxes
Hand Tools
Materials Testing
Capability Building
Administrative & Overhead
Sub-Total B
TOTAL (A+B)
Add:
Contingency
Percent
Total Estimated Cost
Add:
O & M (other amenities)
GRAND TOTAL

Implementation Mode
Sub-Project Duration
Equipment Needed
Technical Personnel
Percentage

Administration
1 Bagger Concrete Mixer, Water Pump
2

Quantity
20.00
123.25

Unit
LM
cu.m.

Unit Price
1,597.33
50.45

261.51
42.50
17.00
83.88
4,131.67
130.38

cu.m.
cu.m.
cu.m.
cu.m.
kgs.
cu.m.

68.37
1,035.29
832.29
4,255.66
43.77
78.70

24.00
8.00
16.00

cu.m.
cu.m.
cu.m.

62.08
953.00
1,036.25

cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
kgs
cu.m.

KALAHI-CIDSS Grant

Prepared by:

Source of Fund
Community

LGUs

Other Source

Total
31,946.50
6,217.80
17,880.00
44,000.00
14,149.00
356,956.50
180,861.00
10,260.00
1,490.00
7,624.00
16,580.00
687,964.80
Total
Cost

Approved by:
BUENAVENTURA L. PITAO
Engr.II, Prov'l. Agr'l. Office - Leyte

Reviewed by:

Chairperson - Brgy. Sub-Project Mgt. Com.


Noted by:

Deputy Area Coordinator

Note: a.) Costing to be used on the MIBF will be the Total Cost Estimate
b.) Costing of O & M will be monitored during the conduct of the SET
*Costing to be supported with detailed Training Schedules

Regional Infrastructure Engineer

CONCRETE VOLUME:
Thickness, m. Width, m. Height, m. Length,m. Volume, cu.m.
Retaining Wall:
Retain Wall Left
Retain Wall Right
Cut-off Wall:
Left Ret. Wall
Right Ret. Wall
Upstream
Downstream
Wall Footing
Left Abutment
Right Abutment
Pier

Flooring:
Wier
R/L Abutment
Cut Walk:
Total Concrete Volume
Boulder Fill (200-400mm)
Gravel Bedding

0.20
0.20
0.20
0.20

2.50
2.00
2.50
2.00

10.41
14.00
10.41
14.00

5.21
5.60
5.21
5.60

21.61

0.20
0.20
0.20
0.20
0.20
0.20

1.00
1.00
1.00
1.00
1.00
1.00

24.41
14.00
24.41
14.00
6.00
8.00

4.88
2.80
4.88
2.80
1.20
1.60

18.17

5.28
5.28

10.56

0.20
0.20

1.20
1.20

0.20
0.30
0.20
0.30
0.30

0.85
0.30
0.05
0.10
0.30

0.20
0.20
0.10
0.10
0.10

6.00
1.00
5.12
5.12
0.60

0.20
0.20

6.00
1.00

0.50
0.50

6.00
1.00

Grouted Riprap:(200-400mm)
Right Abutment
Left Abutment

0.30
0.30

4.83
4.83

Handlaid Riprap:(300-400mm)
Gravel Bedding

0.40
0.20

8.00
8.00

Boulder (200-400mm)

22.00
22.00
No. of Units
2.50
2
2.50
2
2.50
2
2.50
2
2.50
2

0.85
0.45
0.05
0.15
0.23

14
1
14
14
8
Total

16.80
0.20
7.17
7.17
0.48
83.88

14
1
Total
14
1
Total

16.80
0.20
17.00
42.00
0.50
42.50

5.00
5.00
Total
5.00
5.00
Total

7.24
7.24
14.49
16.00
8.00
24.00

31.33
60.06

Reinf. Steel Bars


Retain Wall Left
Bar A 12mm
Bar B 12mm
Temp. Bars 10mm
Retain Wall Right
Bar A 12mm
Bar B 12mm
Temp. Bars 10mm
Wall Footing:
Left Footing 12mm

Width, m. Height, m. Length,m.


0.75
1.25
24.00
1.10
2.45
24.00
3.50
24.00
0.75
1.10

Flooring:

Discharge end (Two sides)


Vert. 12mm
Hor.12mm
Cut-off 12mm
Vert.12mm

24.00
24.00
24.00

121.00
121.00
9.33

242.00
429.55
224.00

22.00
22.00
22.00
22.00
14.00
14.00

111.00
8.50
111.00
8.50
31.00
71.00

166.50
187.00
166.50
187.00
434.00
426.00

1.50
1.00

37.41
37.41

188.07
6.00

282.11
224.49

1.50
1.00

37.41
37.41

188.07
6.00

282.11
224.49

1.30
1.00

6.00
6.00

31.00
6.00

40.30
36.00

1.30
1.00

8.00
8.00

41.00
6.00

53.30
48.00

2.40

5.25
14.00
7.00
14.00

28.35
23.80
37.80
67.20

8.00
8.00

4.00
41.00

32.00
24.60

20.00
20.00

101.00
19.00

363.60
380.00

3.50
5.50

9.38
5.50

10.00
3.25

4.50
5.85

1.50
1.50
1.50
1.50
6.00
6.00

Right Footing 12mm

Cut-off Wall:
Left Abutment:
Vertical Bars (12mm)
Temp. Bars (12mm)
Right Abutment:
Vertical Bars (12mm)
Temp. Bars (12mm)
Upstream
Vertical Bars (12mm)
Temp. Bars (12mm)
Downstream
Vertical Bars (12mm)
Temp. Bars (12mm)
Pier:
Bracing (Vert.) 12mm
Horizontal 12mm
Pier Post 12mm
Stirrups 10mm
Cut Walk:
Longitudinal 12 mm
Temp. Bars 10mm
Intake Wall:
12mm Bothways

1.25
2.45
2.50

No. of Units
2.00
2.00
2.00
2.00

0.85
0.85

2.70
2.60
2.70
2.60

0.60
0.60

2.00
2.00

No. of pcs.
Total Length, m
121.00
242.00
121.00
429.55
12.67
304.00

0.90
0.90

0.90
0.90

0.50
0.50

1.34
0.90
0.45
0.45

1.80
1.80
Total

Excavation:
Retaining Wall:
Retain Wall Left U/S

Top,m.
2.00

12mm dia.
10mm dia.

Bottom,m. Height, m. Length,m. Volume, cu.m.


1.40

1.90

5.00

16.15

D/S
Retain Wall Right U/S
D/S
Cut-off Wall
Left U/S
D/S
Right U/S
D/S
Flooring:

Grouted Excav.
Left Abutment
Right Abutment

Handlaid Riprap:Excav.
Struc. Backfill:

1.80
2.00
0.30
2.00
1.80
2.00
0.30

1.40
1.40
0.30
1.40
1.40
1.40
0.30

1.90
1.90
0.25
2.10
1.75
1.75
0.50

12.00
5.00
14.00
5.00
12.00
5.00
14.00

36.48
16.15
1.05
17.85
33.60
14.88
2.10

0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70
6.00
1.20
0.50
0.15

0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.50
0.15
0.40

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.70
1.00
2.00
3.00

5.00
12.00
5.00
6.00
5.00
12.00
5.00
8.00
14.00
14.00
14.00
14.00
Total

2.75
6.60
2.75
3.30
2.75
6.60
2.75
4.40
58.80
11.90
9.10
11.55
261.51

2.30
2.00

0.50
0.50
2.00

2.50
3.00
0.50

5.00
5.00
5.00
Total
5.00

17.50
15.00
5.00
37.50
24.00

8.00
Top,m.

Retaining Wall:
Retain Wall Left

Retain Wall Right

Cut-off Wall

1.80
1.55
1.80
5.00
1.80
1.55
1.80
5.00
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

0.60

Bottom,m. Height, m. Length,m. Volume, cu.m.


1.20
1.20
1.20
1.20
1.20
1.20
0.20
0.20
0.20
0.20
0.20
0.20
0.20
0.20

1.70
1.70
1.70
0.60
1.70
1.70
1.70
0.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

5.00
12.00
5.00
14.00
5.00
12.00
5.00
14.00
5.00
12.00
5.00
6.00
5.00
12.00
5.00
8.00
Total

12.75
28.05
12.75
42.00
12.75
28.05
12.75
14.00
1.75
4.20
1.75
2.10
1.75
4.20
1.75
2.80
183.40

Intake Works:
Excavation

Top,m.
Bottom,m. Height, m. Length,m. Volume, cu.m.
1.10
1.10
0.40
20.00
8.80

138.26

31.90

123.25

Backfill

0.30
1.00
0.24

Concrete Volume

Division Box:
Flooring
CHB Footing

Length,m.

No. of CHB's
Mortar/Plaster

0.20
1.00

0.28
20.00
0.20
5.00
0.24
20.00
1.80
1.34
0.12
0.80
0.92
0.12
Total Concrete Volume
Top, m

Concrete
Height, m. Width, m. Volume, cu.m.
0.30
Total
-

(3.00) pcs.
(0.02)
Concrete Mortar
Cement
Sand
Gravel

Reinforcing Bars
Vertical Bar
Horizontal Bar
CHB Found.

1.40
1.00
1.15
0.29
(0.09)
1.35

Length,m.

Total
-

Width, m. Height, m. No. of Pcs. Total Bar Length


Total
Bar nos.
-

2.40

Weight, kgs.
214.90
381.44
187.26
214.90
381.44
137.98
147.85
166.06
147.85
166.06
385.39
378.29

250.51
199.34
250.51
199.34
35.79
31.97
47.33
42.62
25.17
21.13
33.57
41.40
28.42
15.15
322.88
337.44

660.32

8.33
4.88
4.00
5.19
22.40
3,749.88
381.80
Conc. Vol.
Backfill

21.61

116.64

18.17

13.73

130.38

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

1.00

Coffer Dam

20

Linear Meter (Lm)

A
1
2
3

Material
1/2" X 4' X 8' Marine Plyboard
2" X 2" Coco Lumber (False work)
Assorted Common Wire Nails

Quantity
7.50
180.00
12.00

Unit
pcs.
bd.ft.
kgs.

Unit Cost

Unit Cost
835.00
9.50
50.00

Sub-Total
B

Name & Capacity of Equipment


None

Labor Derivation
(Subsidiary Work Description)
Hour/board foot
Board foot per Linear meter
Hour/Linear meter

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Days

1,597.33
Cost
6,262.50
1,710.00
600.00

8,572.50

Rate/Day

Cost

Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
0.064
180.00
11.52

3.00

28.80

Number No. of Day


1.00
29.00
2.00
29.00

Rate/Day
350.00
228.00

Cost
10,150.00
13,224.00

20.00

Sub-Total

23,374.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

2.00

Diversion of Water and Care of Creek

A
1

Material
Diesel Fuel

Quantity

Unit

123.25
Quantity
8.00

Unit Cost

cu.m.
Unit
liters

50.45

Unit Cost
39.85

Total
B

Name & Capacity of Equipment


4" Water Pumps and accessories

Number No. of Day


1.00
17.00

Labor Derivation
(Subsidiary Work Description)
Dewatering/pumping ( cu.m./day)

Labor Requirement
Water Pump Operator

318.80

318.80

Rate/Day
119.00

Total
C

Cost

Cost
2,023.00

2,023.00

Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
123.25

7.25

1.00

17.00

Number No. of Days


1.00
17.00

Rate/Day
228.00

Cost
3,876.00

Total

3,876.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
3.10

Work Description

Quantity

Unit

Unit Cost

Excavation

261.51

Material
None

Quantity

Unit

Unit Cost

Cost

Name & Capacity of Equipment


None

Number

No. of Day

Rate/Day

Cost

Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist

Labor Requirement
Skilled Laborer
Unskilled Laborer

cubic meter (cu.m.)

68.37

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
261.51

3.50

6.00

12.45

Number No. of Days


1.00
12.00
5.00
12.00

Rate/Day
350.00
228.00

Cost
4,200.00
13,680.00

Sub-Total

17,880.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
3.40
A
1
2
3
4
5
6

Work Description
Concrete Class "A"
(3000 psi)
Material
Portland Cement
Fresh Sand
Gravel (G1)
1/4" X 4' X 8' Ordinary Plywood
Coco Lumber (False Work)
Nails and Hardware

Quantity

Unit

83.88
Quantity
800.00
53.00
70.00
57.00
5,033.00
210.00

cubic meter (cu.m.)


Unit
bags
cu.m.
cu.m.
pcs.
bd.ft.
kgs.

Unit Cost
195.00
350.00
725.00
385.00
10.50
52.50

Total
B

Name & Capacity of Equipment


Concrete Mixer (1 bagger)

Number No. of Day


1.00
24.00

Rate/Day
298.00

Total
C

Unit Cost
4,255.66
Cost
156,000.00
18,550.00
50,750.00
21,945.00
52,846.50
11,025.00

311,116.50
Cost
7,152.00

7,152.00

Labor Derivation
(Subsidiary Work
Description)
Concrete Works (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
83.88
3.50
6.00
23.97

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No.of Days


2.00
24.00
4.00
24.00

Rate/Day
350.00
228.00

Total

Cost
16,800.00
21,888.00

38,688.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

3.50

Reinforcing Steel Bars

4,131.67

Kgs.

A
1
2
3
4

Material
12mm X 20' Reinforcing Bars
10mm X 20' Reinforcing Bars
# 16 Tie Wire
Hacksaw Blade

Quantity
704.00
103.00
124.00
6.00

Unit
pcs.
pcs.
kgs.
pcs.

Unit Cost
180.00
165.00
55.00
45.00

Total
B

Name & Capacity of Equipment


None

Number

No. of Day

Rate/Day

Unit Cost
43.77
Cost
126,720.00
16,995.00
6,820.00
270.00

150,805.00
Cost

Labor Derivation
(Subsidiary Work Description)
Cutting, Bending & Placing of RSB
(kgs/day)

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
4,131.67
80.00
2.00
51.65

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Days


1.00
52.00
1.00
52.00

Rate/Day
350.00
228.00

Total

Cost
18,200.00
11,856.00

30,056.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No.

Work Description

Quantity

Material

Quantity

Name & Capacity of Equipment

Labor Derivation
(Subsidiary Work Description)

Unit

Unit

Number No. of Day

Unit Cost

Rate/Day

Quantity Manpower Number of Manpower


Required Capability
Assigned

Labor Requirement

Number No. of Day

Rate/Day

Unit Cost

Cost

Cost

Number of Days to
Complete the Work

Cost

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

3.60

Structural Backfill

130.38

Material
None

Name & Capacity of Equipment


None

Quantity

Unit

Unit Cost

cubic meter (cu.m.)


Unit

Number No. of Day

78.70

Unit Cost

Cost

Rate/Day

Cost

Labor Derivation
(Subsidiary Work Description)
Backfilling & Tamping (cu.m./man-day)

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
130.38
3.00
5.00
8.69

Labor Requirement
Unskilled Laborer

Number No. of Day


5.00
9.00

Rate/Day
228.00

Cost
10,260.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

4.10

Excavation (Handlaid Riprap)

Material
None

Quantity

Unit

Unit Cost

Cost

Name & Capacity of Equipment


None

Number

No. of Day

Rate/Day

Cost

Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist.

Labor Requirement
Skilled Laborer
Unskilled Laborer

Quantity

Unit

24.00

Unit Cost

cubic meter (cu.m.)

62.08

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
24.00

3.50

6.00

Number No. of Days


1.00
1.00
5.00
1.00

Rate/Day
350.00
228.00

Sub-Total

1.14

Cost
350.00
1,140.00

1,490.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

4.30

Handlaid Riprap

16.00

A
1

Material
Boulder (300mm-400mm)

Quantity
16.00

Unit

Unit
cu.m.

Unit Cost

cubic meters (cu.m.)

1,036.25

Unit Cost
850.00

Cost
13,600.00

Total
B

Name & Capacity of Equipment


None

Labor Derivation
(Subsidiary Work
Description)
Handlaid Riprap (cu.m./day)

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Day

13,600.00

Rate/Day

Cost

Quantity Manpower Number of Manpower


Required Capability
Assigned
16.00

8.50

6.00

Number No. of Day


1.00
2.00
5.00
2.00

Rate/Day
350.00
228.00

Total

Number of Days to
Complete the Work
1.88

Cost
700.00
2,280.00

2,980.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

4.20

Gravel Bedding (Handlaid)

A
1

Material
Gravel (G1)

Quantity

Unit

8.00
Quantity
8.00

Unit
cu.m.

Unit Cost

cubic meters (cu.m.)

953.00

Unit Cost
725.00

Cost
5,800.00

Total
B

Name & Capacity of Equipment


None

Labor Derivation
(Subsidiary Work
Description)
Bedding (cu.m./hour)

Labor Requirement
Unskilled Laborer

Number No. of Day

5,800.00

Rate/Day

Cost

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
8.00

2.00

8.00

0.50

Number No. of Day


8.00
1.00

Rate/Day
228.00

Cost
1,824.00

Total

1,824.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

Unit Cost

Excavation (Grouted Riprap)

37.50

cubic meter (cu.m.)

79.47

Material
None

Quantity

Unit

Unit Cost

Cost

Name & Capacity of Equipment


None

Number

No. of Day

Rate/Day

Cost

Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist.

Labor Requirement
Skilled Laborer
Unskilled Laborer

Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
37.50

3.50

6.00

Number No. of Days


1.00
2.00
5.00
2.00

Rate/Day
350.00
228.00

Sub-Total

1.79

Cost
700.00
2,280.00

2,980.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

A
1
2
3
4

Work Description

Quantity

Unit

Unit Cost

Grouted Riprap

14.49

cubic meters (cu.m.)

2,280.25

Material
Portland Cement
Fresh Sand
Gravel (G1)
Boulder (200mm-350mm)

Quantity
61.00
5.00
1.00
14.00

Unit
bags
cu.m.
cu.m.
cu.m.

Unit Cost
195.00
350.00
725.00
850.00

Total
B

Name & Capacity of Equipment


None

Number No. of Day

Rate/Day

Cost
11,895.00
1,750.00
725.00
11,900.00

26,270.00
Cost

Labor Derivation
(Subsidiary Work Description)
Grouted Riprap (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
14.49
7.50
13.00
1.93

Labor Requirement
Foreman
Skilled Laborer
Unskilled Laborer

Number No. of Day


1.00
2.00
2.00
2.00
10.00
2.00

Rate/Day
400.00
350.00
228.00

Total

Cost
800.00
1,400.00
4,560.00

6,760.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

3.20

Boulder Fill

A
1

Material
Boulder (200mm-400mm)

Quantity

Unit

42.50
Quantity
43.00

Unit
cu.m.

Unit Cost

cubic meters (cu.m.)

1,035.29

Unit Cost
850.00

Cost
36,550.00

Total
B

Name & Capacity of Equipment


None

Labor Derivation
(Subsidiary Work
Description)
Handlaid Riprap (cu.m./day)

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Day

36,550.00

Rate/Day

Cost

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
43.00

8.50

6.00

5.06

Number No. of Day


1.00
5.00
5.00
5.00

Rate/Day
350.00
228.00

Cost
1,750.00
5,700.00

Total

7,450.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

3.30

Gravel Bedding (Boulder Fill)

A
1

Material
Gravel (G1)

Quantity

Unit

17.00
Quantity
17.00

cubic meters (cu.m.)


Unit
cu.m.

Unit Cost
725.00

Total
B

Name & Capacity of Equipment


None

Number No. of Day

Rate/Day

Labor Derivation
(Subsidiary Work
Description)
Bedding (cu.m./hour)

Quantity Manpower Number of Manpower


Required Capability
Assigned
17.00
2.00
8.00

Labor Requirement
Unskilled Laborer

Number No. of Day


8.00
1.00

Rate/Day
228.00

Total

Unit Cost
832.29
Cost
12,325.00

12,325.00
Cost

Number of Days to
Complete the Work
1.06

Cost
1,824.00

1,824.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description
Concrete Class "A"
(3000 psi)

A
1
2
3
4
5
6

Material
Portland Cement
Fresh Sand
Gravel (G1)
1/4" X 4' X 8' Ordinary Plywood
Coco Lumber (False Work)
Nails and Hardware

Quantity

Unit

Unit Cost

1.35

cubic meter (cu.m.)

4,262.00

Quantity
13.00
1.00
1.00
1.00
81.00
3.00

Unit
bags
cu.m.
cu.m.
pcs.
bd.ft.
kgs.

Unit Cost
195.00
350.00
725.00
385.00
10.50
52.50

Total
B

Name & Capacity of Equipment


Concrete Mixer (1 bagger)

Number No. of Day


1.00
0.40

Rate/Day
298.00

Total
C

Cost
2,535.00
350.00
725.00
385.00
850.50
157.50

5,003.00
Cost
119.20

119.20

Labor Derivation
(Subsidiary Work
Description)
Concrete Works (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to


Required Capability
Assigned
Complete the Work
1.35
3.50
6.00
0.39

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No.of Days


2.00
0.40
4.00
0.40

Rate/Day
350.00
228.00

Cost
280.00
364.80

Total

644.80

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

Excavation (Intake)

8.80

cubic meter (cu.m.)

Material
None

Quantity

Name & Capacity of Equipment


None

Unit

Number No. of Day

Unit Cost

Rate/Day

Labor Derivation
Quantity Manpower Number of Manpower
(Subsidiary Work
Required Capability
Assigned
Description)
Cu.m./Man-day @ 0-4m throwing dist. 8.80
3.50
6.00

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Days


1.00
0.40
5.00
0.40

Rate/Day
350.00
228.00

Sub-Total

Unit Cost
67.73
Cost

Cost

Number of Days to
Complete the Work
0.42

Cost
140.00
456.00

596.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

Unit Cost

Structural Backfill

2.40

cubic meter (cu.m.)

95.00

Material
None

Quantity

Unit Cost

Cost

Name & Capacity of Equipment


None

Rate/Day

Cost

Unit

Number No. of Day

Labor Derivation
Quantity Manpower Number of Manpower Number of Days to
(Subsidiary Work
Required Capability
Assigned
Complete the Work
Description)
Backfilling & Tamping (cu.m./man-day) 2.40
3.00
5.00
0.16

Labor Requirement
Unskilled Laborer

Number No. of Day


5.00
0.20

Rate/Day
228.00

Cost
228.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

A
1
2
3

Work Description

Quantity

Unit

Reinforcing Steel Bars


(12mm)

682.72

Kgs.

Material
12mm X 20' Reinforcing Bars
# 16 Tie Wire
Hacksaw Blade

Quantity
128.00
20.00
6.00

Unit
pcs.
kgs.
pcs.

Unit Cost
180.00
55.00
45.00

Total
B

Name & Capacity of Equipment


None

Number No. of Day

Rate/Day

Labor Derivation
Quantity Manpower Number of Manpower
(Subsidiary Work
Required Capability
Assigned
Description)
Cutting, Bending & Placing of RSB 682.72
80.00
2.00
(kgs/day)

Labor Requirement
Skilled Laborer
Unskilled Laborer

Number No. of Days


1.00
9.00
1.00
9.00

Rate/Day
350.00
228.00

Total

Unit Cost
43.37
Cost
23,040.00
1,100.00
270.00

24,410.00
Cost

Number of Days to
Complete the Work
8.53

Cost
3,150.00
2,052.00

5,202.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.

Work Description

Quantity

Unit

Unit Cost

Trash Trap

LS

1,867.50

Material
" X 1" X 20' Angle Bar
10mm X 20' RSB
Welding Rod

Name & Capacity of Equipment


None

Quantity
1.00
5.00
0.50

Unit
pcs.
pcs.
kgs.

Number No. of Day

Unit Cost
650.00
165.00
85.00

Cost
650.00
825.00
42.50

Total

1,517.50

Rate/Day

Cost

Labor Derivation
Quantity Manpower Number of Manpower Number of Days to
(Subsidiary Work
Required Capability
Assigned
Complete the Work
Description)
Trash Fabrication (days per trap)
1.00
1.00
1.00
1.00

Labor Requirement
Welder

Number No. of Day


1.00
1.00

Rate/Day
350.00

Total

Cost
350.00

350.00

DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No.

Work Description

Quantity

Material

Quantity

Name & Capacity of Equipment

Labor Derivation
(Subsidiary Work
Description)

Unit

Unit

Number No. of Day

Unit Cost

Rate/Day

Quantity Manpower Number of Manpower


Required Capability
Assigned

Labor Requirement

Number No. of Day

Rate/Day

Unit Cost

Cost

Cost

Number of Days to
Complete the Work

Cost

You might also like