Professional Documents
Culture Documents
Barangay of Aslum
Municipality of Julita
Province of Leyte
Project Description
Construction of Diversion Work Structure
Item No.
1.00
2.00
3.00
3.10
3.20
3.30
3.40
3.50
3.60
4.00
4.10
4.20
4.30
5.00
5.10
5.20
5.30
6.00
6.10
6.20
6.30
6.40
Scope of Work
Coffer Dam
Diversion of Water & Care of Creek
Intake Weir Structure
Excavation
Boulder Fill
Gravel Bedding
Concrete Class "A" (3000 psi)
Reinforcing Steel Bars
Structural Backfill
Handlaid Riprap
Excavation
Gravel Bedding
Riprap (Handlaid)
Grouted Riprap
Excavation
Gravel Bedding
Riprap (Grouted)
Intake Works
Excavation
Concrete Class "A" (3000 psi)
Reinforcing Steel Bars
Structural Backfill
Total
Breakdown of Estimated
Sub-Project Cost
A. Direct Cost
Material Cost
Equipment Rental
Labor Cost
a.) Skilled
b.) Unskilled
Sub-Total A
B. Indirect Cost
Pre-Engineering
Engineering Supervision
Contractor's Profit
Taxes
Hand Tools
Materials Testing
Capability Building
Administrative & Overhead
Sub-Total B
TOTAL (A+B)
Add:
Contingency
Percent
Total Estimated Cost
Add:
O & M (other amenities)
GRAND TOTAL
Implementation Mode
Sub-Project Duration
Equipment Needed
Technical Personnel
Percentage
Administration
1 Bagger Concrete Mixer, Water Pump
2
Quantity
20.00
123.25
Unit
LM
cu.m.
Unit Price
1,597.33
50.45
261.51
42.50
17.00
83.88
4,131.67
130.38
cu.m.
cu.m.
cu.m.
cu.m.
kgs.
cu.m.
68.37
1,035.29
832.29
4,255.66
43.77
78.70
24.00
8.00
16.00
cu.m.
cu.m.
cu.m.
62.08
953.00
1,036.25
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
kgs
cu.m.
KALAHI-CIDSS Grant
Prepared by:
Source of Fund
Community
LGUs
Other Source
Total
31,946.50
6,217.80
17,880.00
44,000.00
14,149.00
356,956.50
180,861.00
10,260.00
1,490.00
7,624.00
16,580.00
687,964.80
Total
Cost
Approved by:
BUENAVENTURA L. PITAO
Engr.II, Prov'l. Agr'l. Office - Leyte
Reviewed by:
Note: a.) Costing to be used on the MIBF will be the Total Cost Estimate
b.) Costing of O & M will be monitored during the conduct of the SET
*Costing to be supported with detailed Training Schedules
CONCRETE VOLUME:
Thickness, m. Width, m. Height, m. Length,m. Volume, cu.m.
Retaining Wall:
Retain Wall Left
Retain Wall Right
Cut-off Wall:
Left Ret. Wall
Right Ret. Wall
Upstream
Downstream
Wall Footing
Left Abutment
Right Abutment
Pier
Flooring:
Wier
R/L Abutment
Cut Walk:
Total Concrete Volume
Boulder Fill (200-400mm)
Gravel Bedding
0.20
0.20
0.20
0.20
2.50
2.00
2.50
2.00
10.41
14.00
10.41
14.00
5.21
5.60
5.21
5.60
21.61
0.20
0.20
0.20
0.20
0.20
0.20
1.00
1.00
1.00
1.00
1.00
1.00
24.41
14.00
24.41
14.00
6.00
8.00
4.88
2.80
4.88
2.80
1.20
1.60
18.17
5.28
5.28
10.56
0.20
0.20
1.20
1.20
0.20
0.30
0.20
0.30
0.30
0.85
0.30
0.05
0.10
0.30
0.20
0.20
0.10
0.10
0.10
6.00
1.00
5.12
5.12
0.60
0.20
0.20
6.00
1.00
0.50
0.50
6.00
1.00
Grouted Riprap:(200-400mm)
Right Abutment
Left Abutment
0.30
0.30
4.83
4.83
Handlaid Riprap:(300-400mm)
Gravel Bedding
0.40
0.20
8.00
8.00
Boulder (200-400mm)
22.00
22.00
No. of Units
2.50
2
2.50
2
2.50
2
2.50
2
2.50
2
0.85
0.45
0.05
0.15
0.23
14
1
14
14
8
Total
16.80
0.20
7.17
7.17
0.48
83.88
14
1
Total
14
1
Total
16.80
0.20
17.00
42.00
0.50
42.50
5.00
5.00
Total
5.00
5.00
Total
7.24
7.24
14.49
16.00
8.00
24.00
31.33
60.06
Flooring:
24.00
24.00
24.00
121.00
121.00
9.33
242.00
429.55
224.00
22.00
22.00
22.00
22.00
14.00
14.00
111.00
8.50
111.00
8.50
31.00
71.00
166.50
187.00
166.50
187.00
434.00
426.00
1.50
1.00
37.41
37.41
188.07
6.00
282.11
224.49
1.50
1.00
37.41
37.41
188.07
6.00
282.11
224.49
1.30
1.00
6.00
6.00
31.00
6.00
40.30
36.00
1.30
1.00
8.00
8.00
41.00
6.00
53.30
48.00
2.40
5.25
14.00
7.00
14.00
28.35
23.80
37.80
67.20
8.00
8.00
4.00
41.00
32.00
24.60
20.00
20.00
101.00
19.00
363.60
380.00
3.50
5.50
9.38
5.50
10.00
3.25
4.50
5.85
1.50
1.50
1.50
1.50
6.00
6.00
Cut-off Wall:
Left Abutment:
Vertical Bars (12mm)
Temp. Bars (12mm)
Right Abutment:
Vertical Bars (12mm)
Temp. Bars (12mm)
Upstream
Vertical Bars (12mm)
Temp. Bars (12mm)
Downstream
Vertical Bars (12mm)
Temp. Bars (12mm)
Pier:
Bracing (Vert.) 12mm
Horizontal 12mm
Pier Post 12mm
Stirrups 10mm
Cut Walk:
Longitudinal 12 mm
Temp. Bars 10mm
Intake Wall:
12mm Bothways
1.25
2.45
2.50
No. of Units
2.00
2.00
2.00
2.00
0.85
0.85
2.70
2.60
2.70
2.60
0.60
0.60
2.00
2.00
No. of pcs.
Total Length, m
121.00
242.00
121.00
429.55
12.67
304.00
0.90
0.90
0.90
0.90
0.50
0.50
1.34
0.90
0.45
0.45
1.80
1.80
Total
Excavation:
Retaining Wall:
Retain Wall Left U/S
Top,m.
2.00
12mm dia.
10mm dia.
1.90
5.00
16.15
D/S
Retain Wall Right U/S
D/S
Cut-off Wall
Left U/S
D/S
Right U/S
D/S
Flooring:
Grouted Excav.
Left Abutment
Right Abutment
Handlaid Riprap:Excav.
Struc. Backfill:
1.80
2.00
0.30
2.00
1.80
2.00
0.30
1.40
1.40
0.30
1.40
1.40
1.40
0.30
1.90
1.90
0.25
2.10
1.75
1.75
0.50
12.00
5.00
14.00
5.00
12.00
5.00
14.00
36.48
16.15
1.05
17.85
33.60
14.88
2.10
0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70
6.00
1.20
0.50
0.15
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.50
0.15
0.40
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.70
1.00
2.00
3.00
5.00
12.00
5.00
6.00
5.00
12.00
5.00
8.00
14.00
14.00
14.00
14.00
Total
2.75
6.60
2.75
3.30
2.75
6.60
2.75
4.40
58.80
11.90
9.10
11.55
261.51
2.30
2.00
0.50
0.50
2.00
2.50
3.00
0.50
5.00
5.00
5.00
Total
5.00
17.50
15.00
5.00
37.50
24.00
8.00
Top,m.
Retaining Wall:
Retain Wall Left
Cut-off Wall
1.80
1.55
1.80
5.00
1.80
1.55
1.80
5.00
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.60
1.70
1.70
1.70
0.60
1.70
1.70
1.70
0.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
5.00
12.00
5.00
14.00
5.00
12.00
5.00
14.00
5.00
12.00
5.00
6.00
5.00
12.00
5.00
8.00
Total
12.75
28.05
12.75
42.00
12.75
28.05
12.75
14.00
1.75
4.20
1.75
2.10
1.75
4.20
1.75
2.80
183.40
Intake Works:
Excavation
Top,m.
Bottom,m. Height, m. Length,m. Volume, cu.m.
1.10
1.10
0.40
20.00
8.80
138.26
31.90
123.25
Backfill
0.30
1.00
0.24
Concrete Volume
Division Box:
Flooring
CHB Footing
Length,m.
No. of CHB's
Mortar/Plaster
0.20
1.00
0.28
20.00
0.20
5.00
0.24
20.00
1.80
1.34
0.12
0.80
0.92
0.12
Total Concrete Volume
Top, m
Concrete
Height, m. Width, m. Volume, cu.m.
0.30
Total
-
(3.00) pcs.
(0.02)
Concrete Mortar
Cement
Sand
Gravel
Reinforcing Bars
Vertical Bar
Horizontal Bar
CHB Found.
1.40
1.00
1.15
0.29
(0.09)
1.35
Length,m.
Total
-
2.40
Weight, kgs.
214.90
381.44
187.26
214.90
381.44
137.98
147.85
166.06
147.85
166.06
385.39
378.29
250.51
199.34
250.51
199.34
35.79
31.97
47.33
42.62
25.17
21.13
33.57
41.40
28.42
15.15
322.88
337.44
660.32
8.33
4.88
4.00
5.19
22.40
3,749.88
381.80
Conc. Vol.
Backfill
21.61
116.64
18.17
13.73
130.38
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
1.00
Coffer Dam
20
A
1
2
3
Material
1/2" X 4' X 8' Marine Plyboard
2" X 2" Coco Lumber (False work)
Assorted Common Wire Nails
Quantity
7.50
180.00
12.00
Unit
pcs.
bd.ft.
kgs.
Unit Cost
Unit Cost
835.00
9.50
50.00
Sub-Total
B
Labor Derivation
(Subsidiary Work Description)
Hour/board foot
Board foot per Linear meter
Hour/Linear meter
Labor Requirement
Skilled Laborer
Unskilled Laborer
1,597.33
Cost
6,262.50
1,710.00
600.00
8,572.50
Rate/Day
Cost
Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
0.064
180.00
11.52
3.00
28.80
Rate/Day
350.00
228.00
Cost
10,150.00
13,224.00
20.00
Sub-Total
23,374.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
2.00
A
1
Material
Diesel Fuel
Quantity
Unit
123.25
Quantity
8.00
Unit Cost
cu.m.
Unit
liters
50.45
Unit Cost
39.85
Total
B
Labor Derivation
(Subsidiary Work Description)
Dewatering/pumping ( cu.m./day)
Labor Requirement
Water Pump Operator
318.80
318.80
Rate/Day
119.00
Total
C
Cost
Cost
2,023.00
2,023.00
Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
123.25
7.25
1.00
17.00
Rate/Day
228.00
Cost
3,876.00
Total
3,876.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
3.10
Work Description
Quantity
Unit
Unit Cost
Excavation
261.51
Material
None
Quantity
Unit
Unit Cost
Cost
Number
No. of Day
Rate/Day
Cost
Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist
Labor Requirement
Skilled Laborer
Unskilled Laborer
68.37
3.50
6.00
12.45
Rate/Day
350.00
228.00
Cost
4,200.00
13,680.00
Sub-Total
17,880.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
3.40
A
1
2
3
4
5
6
Work Description
Concrete Class "A"
(3000 psi)
Material
Portland Cement
Fresh Sand
Gravel (G1)
1/4" X 4' X 8' Ordinary Plywood
Coco Lumber (False Work)
Nails and Hardware
Quantity
Unit
83.88
Quantity
800.00
53.00
70.00
57.00
5,033.00
210.00
Unit Cost
195.00
350.00
725.00
385.00
10.50
52.50
Total
B
Rate/Day
298.00
Total
C
Unit Cost
4,255.66
Cost
156,000.00
18,550.00
50,750.00
21,945.00
52,846.50
11,025.00
311,116.50
Cost
7,152.00
7,152.00
Labor Derivation
(Subsidiary Work
Description)
Concrete Works (cu.m./day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
Rate/Day
350.00
228.00
Total
Cost
16,800.00
21,888.00
38,688.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
3.50
4,131.67
Kgs.
A
1
2
3
4
Material
12mm X 20' Reinforcing Bars
10mm X 20' Reinforcing Bars
# 16 Tie Wire
Hacksaw Blade
Quantity
704.00
103.00
124.00
6.00
Unit
pcs.
pcs.
kgs.
pcs.
Unit Cost
180.00
165.00
55.00
45.00
Total
B
Number
No. of Day
Rate/Day
Unit Cost
43.77
Cost
126,720.00
16,995.00
6,820.00
270.00
150,805.00
Cost
Labor Derivation
(Subsidiary Work Description)
Cutting, Bending & Placing of RSB
(kgs/day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
Rate/Day
350.00
228.00
Total
Cost
18,200.00
11,856.00
30,056.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No.
Work Description
Quantity
Material
Quantity
Labor Derivation
(Subsidiary Work Description)
Unit
Unit
Unit Cost
Rate/Day
Labor Requirement
Rate/Day
Unit Cost
Cost
Cost
Number of Days to
Complete the Work
Cost
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
3.60
Structural Backfill
130.38
Material
None
Quantity
Unit
Unit Cost
78.70
Unit Cost
Cost
Rate/Day
Cost
Labor Derivation
(Subsidiary Work Description)
Backfilling & Tamping (cu.m./man-day)
Labor Requirement
Unskilled Laborer
Rate/Day
228.00
Cost
10,260.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
4.10
Material
None
Quantity
Unit
Unit Cost
Cost
Number
No. of Day
Rate/Day
Cost
Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist.
Labor Requirement
Skilled Laborer
Unskilled Laborer
Quantity
Unit
24.00
Unit Cost
62.08
3.50
6.00
Rate/Day
350.00
228.00
Sub-Total
1.14
Cost
350.00
1,140.00
1,490.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
4.30
Handlaid Riprap
16.00
A
1
Material
Boulder (300mm-400mm)
Quantity
16.00
Unit
Unit
cu.m.
Unit Cost
1,036.25
Unit Cost
850.00
Cost
13,600.00
Total
B
Labor Derivation
(Subsidiary Work
Description)
Handlaid Riprap (cu.m./day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
13,600.00
Rate/Day
Cost
8.50
6.00
Rate/Day
350.00
228.00
Total
Number of Days to
Complete the Work
1.88
Cost
700.00
2,280.00
2,980.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
4.20
A
1
Material
Gravel (G1)
Quantity
Unit
8.00
Quantity
8.00
Unit
cu.m.
Unit Cost
953.00
Unit Cost
725.00
Cost
5,800.00
Total
B
Labor Derivation
(Subsidiary Work
Description)
Bedding (cu.m./hour)
Labor Requirement
Unskilled Laborer
5,800.00
Rate/Day
Cost
2.00
8.00
0.50
Rate/Day
228.00
Cost
1,824.00
Total
1,824.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
Unit Cost
37.50
79.47
Material
None
Quantity
Unit
Unit Cost
Cost
Number
No. of Day
Rate/Day
Cost
Labor Derivation
(Subsidiary Work Description)
Cu.m./Man-day @ 0-4m throwing dist.
Labor Requirement
Skilled Laborer
Unskilled Laborer
Quantity Manpower
Number of
Number of Days to
Required Capability Manpower Assigned Complete the Work
37.50
3.50
6.00
Rate/Day
350.00
228.00
Sub-Total
1.79
Cost
700.00
2,280.00
2,980.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
A
1
2
3
4
Work Description
Quantity
Unit
Unit Cost
Grouted Riprap
14.49
2,280.25
Material
Portland Cement
Fresh Sand
Gravel (G1)
Boulder (200mm-350mm)
Quantity
61.00
5.00
1.00
14.00
Unit
bags
cu.m.
cu.m.
cu.m.
Unit Cost
195.00
350.00
725.00
850.00
Total
B
Rate/Day
Cost
11,895.00
1,750.00
725.00
11,900.00
26,270.00
Cost
Labor Derivation
(Subsidiary Work Description)
Grouted Riprap (cu.m./day)
Labor Requirement
Foreman
Skilled Laborer
Unskilled Laborer
Rate/Day
400.00
350.00
228.00
Total
Cost
800.00
1,400.00
4,560.00
6,760.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
3.20
Boulder Fill
A
1
Material
Boulder (200mm-400mm)
Quantity
Unit
42.50
Quantity
43.00
Unit
cu.m.
Unit Cost
1,035.29
Unit Cost
850.00
Cost
36,550.00
Total
B
Labor Derivation
(Subsidiary Work
Description)
Handlaid Riprap (cu.m./day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
36,550.00
Rate/Day
Cost
8.50
6.00
5.06
Rate/Day
350.00
228.00
Cost
1,750.00
5,700.00
Total
7,450.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
3.30
A
1
Material
Gravel (G1)
Quantity
Unit
17.00
Quantity
17.00
Unit Cost
725.00
Total
B
Rate/Day
Labor Derivation
(Subsidiary Work
Description)
Bedding (cu.m./hour)
Labor Requirement
Unskilled Laborer
Rate/Day
228.00
Total
Unit Cost
832.29
Cost
12,325.00
12,325.00
Cost
Number of Days to
Complete the Work
1.06
Cost
1,824.00
1,824.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Concrete Class "A"
(3000 psi)
A
1
2
3
4
5
6
Material
Portland Cement
Fresh Sand
Gravel (G1)
1/4" X 4' X 8' Ordinary Plywood
Coco Lumber (False Work)
Nails and Hardware
Quantity
Unit
Unit Cost
1.35
4,262.00
Quantity
13.00
1.00
1.00
1.00
81.00
3.00
Unit
bags
cu.m.
cu.m.
pcs.
bd.ft.
kgs.
Unit Cost
195.00
350.00
725.00
385.00
10.50
52.50
Total
B
Rate/Day
298.00
Total
C
Cost
2,535.00
350.00
725.00
385.00
850.50
157.50
5,003.00
Cost
119.20
119.20
Labor Derivation
(Subsidiary Work
Description)
Concrete Works (cu.m./day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
Rate/Day
350.00
228.00
Cost
280.00
364.80
Total
644.80
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
Excavation (Intake)
8.80
Material
None
Quantity
Unit
Unit Cost
Rate/Day
Labor Derivation
Quantity Manpower Number of Manpower
(Subsidiary Work
Required Capability
Assigned
Description)
Cu.m./Man-day @ 0-4m throwing dist. 8.80
3.50
6.00
Labor Requirement
Skilled Laborer
Unskilled Laborer
Rate/Day
350.00
228.00
Sub-Total
Unit Cost
67.73
Cost
Cost
Number of Days to
Complete the Work
0.42
Cost
140.00
456.00
596.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
Unit Cost
Structural Backfill
2.40
95.00
Material
None
Quantity
Unit Cost
Cost
Rate/Day
Cost
Unit
Labor Derivation
Quantity Manpower Number of Manpower Number of Days to
(Subsidiary Work
Required Capability
Assigned
Complete the Work
Description)
Backfilling & Tamping (cu.m./man-day) 2.40
3.00
5.00
0.16
Labor Requirement
Unskilled Laborer
Rate/Day
228.00
Cost
228.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
A
1
2
3
Work Description
Quantity
Unit
682.72
Kgs.
Material
12mm X 20' Reinforcing Bars
# 16 Tie Wire
Hacksaw Blade
Quantity
128.00
20.00
6.00
Unit
pcs.
kgs.
pcs.
Unit Cost
180.00
55.00
45.00
Total
B
Rate/Day
Labor Derivation
Quantity Manpower Number of Manpower
(Subsidiary Work
Required Capability
Assigned
Description)
Cutting, Bending & Placing of RSB 682.72
80.00
2.00
(kgs/day)
Labor Requirement
Skilled Laborer
Unskilled Laborer
Rate/Day
350.00
228.00
Total
Unit Cost
43.37
Cost
23,040.00
1,100.00
270.00
24,410.00
Cost
Number of Days to
Complete the Work
8.53
Cost
3,150.00
2,052.00
5,202.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No.
Work Description
Quantity
Unit
Unit Cost
Trash Trap
LS
1,867.50
Material
" X 1" X 20' Angle Bar
10mm X 20' RSB
Welding Rod
Quantity
1.00
5.00
0.50
Unit
pcs.
pcs.
kgs.
Unit Cost
650.00
165.00
85.00
Cost
650.00
825.00
42.50
Total
1,517.50
Rate/Day
Cost
Labor Derivation
Quantity Manpower Number of Manpower Number of Days to
(Subsidiary Work
Required Capability
Assigned
Complete the Work
Description)
Trash Fabrication (days per trap)
1.00
1.00
1.00
1.00
Labor Requirement
Welder
Rate/Day
350.00
Total
Cost
350.00
350.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No.
Work Description
Quantity
Material
Quantity
Labor Derivation
(Subsidiary Work
Description)
Unit
Unit
Unit Cost
Rate/Day
Labor Requirement
Rate/Day
Unit Cost
Cost
Cost
Number of Days to
Complete the Work
Cost