AUTHORITY'S NOTIFIED CLAIM NO.

C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE Ref II. DIRECT COST FOR ADDITIONAL WORKS
D-WALL PANEL NO.: S13

Working Period: 1-June-09 to 18-June-09 Star / FSR Rate STAR FSR STAR

Item No.

Description A Chisel Rescue Works at S8

Unit Ls ls m day

Quantity

Rate $

Amount -

Remarks

A.1 Chisel Repair Cost A.2 Demolition of Guidewall A.3 25mm Steel Plates - 10 pcsx (pc/ day)

0.00 $ 0.00 $ 0.00 $

1,180.00 $ 20.00 $

2.14 $

B Chiselling Work B.1 Grab Crane Cost B.1.1 Rental of grab Crane B.1.2 Grab fuel cosumption(base on 25ltrs/hr) B.1.3 Grab operator B.1.4 Banksman B.1.5 25mm steel plates -10pcsx(pc/day) B.2 Chisel and Maintenance Cost B.2.1 Cost of chisel B.2.2 welder Welding Machine including electrodes(5% of B.2.3 Chiselling time) Oxy & Acethylene Gas Cutter(5% of Chiselling B.2.4 time) hr hr hr hr 216.00 216.00 0.84 0.84 $ $ $ $ 3.84 12.00 12.00 16.00 hr hr hr hr day 16.75 $ 418.75 $ 16.75 $ 16.75 $ 1.00 $ 70.00 0.75 24.15 6.04 2.14

23.45

included in 6b included in 6b included in 6b included in 6b included in 6b

STAR STAR STAR FSR STAR

included in 6b included in Item K $ $ 10.05 13.40

STAR FSR FSR FSR

C Additional Excavation Works - Grab Crane C.1 Grab+ Grab crane cost C.1.1 Cost of Grab C.1.2 Rental of Grab crane C.1.3 Fuel consumption(base on 25ltrs/hr) C.1.4 Local operator C.1.5 Banksman C.1.6 General worker C.1.7 25mm steel plates-10pcsx(pc/day) C.2 Tools Consumption C.2.1 Replacement of Wire Rope C.2.1.1 34mm x 120m C.2.1.2 Splicing charges C.2.1.3 OD 127 x ID 60.5 x 36 Wire Solid Thimble C.2.2 Replacement of Damaged Grab Teeth C.2.2.1 25RC10 C.2.2.2 Holder C.2.2.3 Pin & Retainer set set set 7.00 7.00 7.00 $ $ $ 36.00 75.00 10.50 roll set set 0.00 0.00 0.00 $ 7,350.00 $ $ 35.00 75.00 hr hr hr hr hr hr day 96.00 $ 96.00 $ 2,400.00 $ 96.00 $ 96.00 $ 96.00 $ 4.00 $ 10.21 70.00 75.00 17.48 6.04

1,489.14

included in 6b included in 6b included in 6b included in 6b included in 6b 579.84 included in 6b

STAR STAR STAR STAR FSR

6.04 $ 2.14

STAR

$ $ $

STAR STAR STAR

$ $ $

252.00 525.00 73.50

STAR STAR STAR

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE Ref II. DIRECT COST FOR ADDITIONAL WORKS
D-WALL PANEL NO.: S13

Working Period: 1-June-09 to 18-June-09 Star / FSR Rate STAR

Item No. C.3 Maintenance Cost C.3.1 Mechanic x2

Description

Unit

Quantity

Rate

Amount

Remarks

day

4.00

472.80

included in Item K

C.3.2 Welding Works(20% of grab maintenace time) C.3.2.1 Welder C.3.2.2 C.3.2.3 Welding Machine including electrodes(10% of Grab maintenance time) Oxy & Acethylene Gas Cutter(10% of Grab maintenance work) hr hr hr 96.00 2.10 2.10 $ $ $ 12.00 12.00 16.00 $ $ 25.20 33.60 included in Item K FSR FSR FSR

D Additional Excavation Works - BC Cutter D.1 BC cutter cost D.1.1 Rental of BC cutter D.1.2 Fuel consumption(base on 40ltrs/hr) D.1.3 BC cutter operator(x2) D.1.4 Banksman D.1.5 General worker D.1.6 25mm steel plates-10pcsx(pc/day) D.2 BC cutter desander plant cost D.2.1 Cost of desander plant for BC cutter D.2.2 Cost of filter press for BC cutter D.2.3 Cost of Desander'generator rental D.2.4 Cost of filter press ' generator rental D.2.5 BC cutter's desanderplant superviser D.2.6 BC cutter's desanderplant labour D.3 Mechanic x2 D.4 Tools Consumption D.4.1 Replacement of cutter teeth D.4.1.1 BC Teeth D.4.1.2 Teeth Holder D.4.2 Replacement of Wire Rope D.4.2.1 34mm x 120m D.4.2.2 Splicing charges D.4.2.3 MOM Certificates D.4.2.4 OD 127 x ID 60.5 x 36 Wire Solid Thimble D.4.3 Cutter Wheel Maintenace Works D.4.3.1 Welder Welding Machine including electrodes(10% of BC D.4.3.2 cutter maintenance time) hr hr 216.00 8.53 $ $ 12.00 12.00 roll set length set 0.00 0.00 0.00 0.00 $ 7,350.00 $ $ $ 35.00 50.00 75.00 set set 190.00 190.00 $ $ 19.00 79.99 day day day day day day day 7.00 7.00 7.00 7.00 7.00 7.00 7.00 $ $ $ $ $ $ $ 413.79 367.82 92.86 35.71 387.12 145.14 472.80 day hr day hr hr day 7.00 $ 11,828.57 0.75 545.54 6.04

20,061.52

included in 6b included in 6b included in 6b included in 6b 1,014.72 included in 6b

STAR STAR STAR FSR FSR STAR

6,720.00 $ 7.00 168.00 168.00 7.00 $ $ $ $

6.04 $ 21.40

included in 6b included in 6b included in 6b included in 6b included in 6b included in 6b included in Item K

STAR STAR STAR STAR STAR FSR STAR

$ $

3,610.00 15,198.10

STAR STAR

$ $ $ $

STAR STAR STAR STAR

included in Item K $ 102.30

FSR FSR

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE Ref II. DIRECT COST FOR ADDITIONAL WORKS
D-WALL PANEL NO.: S13

Working Period: 1-June-09 to 18-June-09 Star / FSR Rate FSR STAR

Item No. D.4.3.3

Description Oxy-Acethylene Gas Cutter(10% of BC cutter maintenance time)

Unit hr LS

Quantity 8.53 $

Rate 16.00 $ $

Amount 136.40 -

Remarks

D.4.4 BC Cutter Repairing Cost

Appendix 7b

E Additional Coring Works - BG Machine E.1 BG Boring Rig Cost E.1.1 Rental of BG Boring Rig E.1.2 Fuel Consumption(Base on 40ltrs/hr) E.1.3 BG operator E.1.4 Banksman E.2 Excavator Cost E.2.1 Rental of Excavator C/W operator E.3 Mechanicx2 E.4 25mm steel plate -5pcsx(pc/day) F Additional Backfilling Works F.1 Grade 7 Concrete for Backfillilng Works F.1.1 Supply of Grade 7 Concrete for Backfillilng Works F.1.2 Labour for Backfilling of Grade 7 Concrete F.2 Bentonite F.2.1 Supply of Bentonite for Backfillilng Works F.2.2 Labour for Backfilling of Bentonite F.3 LSS (Type 1) F.3.1 Supply of LSS (Type 1) for Backfilling F.3.2 Labour Cost for Backfilling of LSS (Type 1) F.3.3 Night Surcharge for Delivery of LSS (Type 1) F.4 Tremie Set G Backfilled Works during Construction of D-Wall Disposal of suitable and unsuitable excavated materials surplus excavated materials m3 m3 ls day m3 $ $ 58.00 15.00 m3 m3 $ 13.20 m3 m3 $ $ 93.22 15.00 day hr hr hr hr day day day 1.00 960.00 24.00 24.00 24.00 1.00 1.00 1.00 $ $ $ $ $ $ $ $ 2,500.00 0.75 17.47 6.00 20.83 500.00

472.80

Included in 6b Included in 6b Included in 6b Included in 6b Included in 6b Included in 6b 472.80 included in Item K Included in 6b $ -

STAR STAR STAR FSR STAR STAR

472.80 $ 10.70

STAR

$ $

STAR FSR

STAR STAR

$ $

STAR

$ 1,000.00 $ 74.95

$ $

STAR STAR

G.1

m3

By Taisei

H Verticality Check - KODEN H.1 KODEN Machine H.2 Local Engineer Rate = $234.30 / 8 hours = $29.29 H.3 Supervisor H.4 General Worker (x2) hr hr $ $ 16.13 6.04 hr hr $ 29.29

$ $ -

STAR included in Item K STAR

included in Item K $ -

STAR FSR

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE Ref II. DIRECT COST FOR ADDITIONAL WORKS
D-WALL PANEL NO.: S13

Working Period: 1-June-09 to 18-June-09 Star / FSR Rate

Item No.

Description I Verticality Check - Plumb Down Method

Unit

Quantity

Rate $

Amount -

Remarks

I.1 Grab Crane Cost I.1.1 Rental of Grab Crane Rate = $1,607.14 / 8 hours = $200.89 I.1.2 Grab Fuel Consumption (Based on 40L/hr) I.1.2.1 Rate 1ltrs=SGD$ 0.75,hourly rate=0.75x40=$30 I.2 Use of Round Chisel Rate = $245 / 8 hours = $30.63 I.3 Manpower Cost I.3.1 Grab Operator Cost I.3.2.1 Rate = $130.36 / 8 hours = $16.30 I.3.4 Banksman I.3.5 Local Engineer I.3.5.1 Rate = $234.30 / 8 hours = $29.29 I.3.6 Supervisor I.4 25mm steel plates-10pcs(pc/day) J Hacking of Overbreak Concrete due to MBFC Obstruction J.1 Hacking of Overbreak Concrete J.2 Removal of Debris off-Site K Additional Work Cost for Reinforcement Cage K.1 Distmantling Work K.1.1 Reusable steel bar K.1.2 Wastage/Un-Reusable Steel Bar K.2 Manpower Cost K.2.1 Labour cost for dismantling work L Direct Manpower L.1 Korean Site Manager x2 persons (25%) L.2 Local Engineer x2(25%) L.3 Korean Site Engineer x2 (25%) L.4 Safety Supervisor L.5 Supervisor/Foreman x2(25%) L.6 Mechanic x2(25%) L.7 Welder x2(25%) day/Night day/Night day/Night day/Night day/Night day/Night day/Night 2.25 2.25 2.25 2.25 2.25 2.25 2.25 $ $ $ $ $ $ $ 765.36 468.60 740.62 178.58 387.10 472.80 288.00 tons 60.23 $ 240.00 $ $ $ $ $ $ $ $ $ 14,455.44 7,427.39 1,722.06 1,054.35 1,666.40 401.81 870.98 1,063.80 648.00 43,929.74 25% of Claimable days 25% of Claimable days 25% of Claimable days 25% of Claimable days 25% of Claimable days 25% of Claimable days 25% of Claimable days STAR STAR STAR STAR STAR STAR FSR tons tons 46.48 13.75 Material by Taisei Material by Taisei m3 m3 93.42 93.42 hr day $ $ 16.13 21.40 $ $ $ $ 14,455.44 By Taisei By Taisei hr hr $ $ 6.04 29.29 hr $ 17.48 included in 6b included in 6b included in 6b included in Item K included in 6b included in Item K included in 6b STAR FSR STAR STAR litres hr $ $ 0.75 30.63 hr $ 200.89 included in 6b included in 6b included in 6b included in 6b included in 6b included in 6b STAR STAR STAR

GRAND TOTAL $

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE D-WALL PANEL NO.: S13
Rig No. 4 Date 02-Jun-09 11-Jun-09 Time 07:30 - 07:30hr 07:30 - 07:30hr Works changed teeth changed teeth TOTAL BC Cutter No. 01 (BC40) Date Time Works No. of Teeth Replaced No. of Teeth Replaced 5.00 2.00 7.00

TOTAL BC Cutter No. 02 (BG 40 BC40) Works Change Teeth Change Teeth Change Teeth Change Teeth Change Teeth Change Teeth Change Teeth Change Teeth Change Teeth

0.00

Date 01-Jun-09 02-Jun-09 03-Jun-09 04-Jun-09 05-Jun-09 06-Jun-09 07-Jun-09 08-Jun-09 09-Jun-09

Time 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr 07:30 - 07:30hr

No. of Teeth Replaced 10.00 20.00 20.00 30.00 10.00 30.00 20.00 30.00 20.00

TOTAL GRAND TOTAL

190.00 197.00

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE BC cutter and Grab Maintenance(Time) Summary (For Additional works only)

D-WALL PANEL NO.:

S13

Working Period: 1-June-09 to 18-June-09

Excavation Works(Maintenance time summary)


(C)Grab (D)BC cutter

Remarks

Date 01-Jun-09 02-Jun-09 03-Jun-09 04-Jun-09 05-Jun-09 06-Jun-09 07-Jun-09 08-Jun-09 09-Jun-09 10-Jun-09 11-Jun-09 12-Jun-09 13-Jun-09 14-Jun-09 15-Jun-09

Quantity

Unit
hr

Quantity 3 11.75 9.25 4.5 12.75 7.5 10 11.25 8.25 7

Unit
hr hr hr hr hr hr hr hr hr hr hr

See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c See Appendix 5c

4.75

hr hr hr hr hr hr hr hr

6 3.5 3.25 3.5

hr hr

Total Maintenance Hours

21

85.25

AUTHORITY'S NOTIFIED CLAIM NO. C907/001 - ARTIFICIAL OBSTRUCTIONS AND INTERFERENCE TO DIAPHRAGM WALL WORKS AT STATION / MBFC INTERFACE ADDITIONAL WORKS(Time) SUMMARY

D-WALL PANEL NO.:

S13

Working Period: 4-May-09 to 26-May-09

Item No.
A

Description Chisel rescue works Chiselling Works(Grab Trimming) ii ii ii

Date(from)
N.A

Date (to)
N.A

Time(from)
N.A

Time(to)
N.A

Quantity

Unit
hr

Remarks
N.A

11-Jun-09 12-Jun-09 13-Jun-09 14-Jun-09 total chiselling hours

1.75 7.75 3.75 3.5 16.75

hr
hr hr hr hr

see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c

Additional excavation Works(Grab) ii ii

12-Jun-09

15-Jun-09

day day day

see attached Apx 5c see attached Apx 5c see attached Apx 5c

Total Additional excavation Works Day

day

Additional excavation Works(BC Cutter)

04-Jun-09

10-Jun-09

7 7

day day

see attached Apx 5c

Total Additional excavation Works Day

E F G H

Additional Coring Works(BG.Boring Rig) Additional Backfilling Works Disposal Cost for Backfilling Works during Construction of D-wall Verticality Check(Koden)

13-Jun-09 N.A N.A

13-Jun-09 N.A N.A N.A N.A N.A N.A

01-Jan-00 N.A N.A hr

see attached Apx 5c N.A N.A see attached Apx 5c

Total Verticality (Koden Check) hours

1.5

hr

Verticality Check(Plum-down Method)) ii ii ii ii ii ii ii ii ii ii ii

10-Jun-09 11-Jun-09 12-Jun-09 13-Jun-09 14-Jun-09 15-Jun-09

1 3 2.25 0.5 1 1

hr hr hr hr hr hr hr hr hr hr hr hr

see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c see attached Apx 5c

Total Verticality check(Plumb-down Method) hours

8.75

hr

STATION - D-WALL (MBFC INTERFACE) - Panel No. S13


S.N Location Panel No Length (M) Thickness 3 (M ) Area (M2) Ground Level (mRL) Cut-Off Level Toe Level (mRL) (mRL) OA Level (mRL) Excavation OA Concrete Depth (m) Excavation Depth (m) Depth (m) Backfilling Depth for Crosswall (Y or T Section) (m) 0.00 Excavation Vol. (m3) Excavation in OA Vol. (m3) Theoritical Concrete Vol. (m3) Backfilling Vol. Rebar Cage Anchorage for T or Y Quantity Bars for Section with (kg) Couplers G40 (T) (kg) Concrete (m3) 0.00 No. of Couplers

Station Dwall - MBFC

13

5.700

1.20

6.84

104.210

103.500

41.50

53.21

62.71

11.71

62.00

428.94

80.10

424.08

5.70

6.84

428.94

80.10

424.08

ION AND COMPLETION OF LANDMARK STATION INCLUDING ASSOCIATED TUNNELS FOR DTL LINE STAGE 1

STATION - D-WALL (MBFC INTERFACE) - Panel No. S13


S.N Commence ment Date Month Casting Date Location Panel No Length Thickne Area (M) ss (M3) (M2) Ground Cut-Off Toe Level Level Level (mRL) (mRL) (mRL) OA Level Excavation OA Concrete Backfilling Excavation Excavation Theoritical (mRL) Depth (m) Excavation Depth (m) Depth for Vol. in OA Vol. Concrete Vol. Depth Crosswall (m3) (m3) (m3) (m) (Y or T Section) (m) 53.210 53.210 64.00 30.00 13.00 0.00 63.29 29.29 215.04 104.40 43.68 0.00 212.65 101.93 Actual Backfilling Vol. Rebar Anchorage Concrete for T or Y Cage Bars for Vol. Section with Quantity Couplers (m3) G40 (T) (kg) (kg) Concrete (m3) 408.00 0.00 0.00

1 2

01-Jun-09 01-Jun-09

Jun-09 Jun-09

18-Jun-09 18-Jun-09

Station Dwall - MBFC Station Dwall - MBFC

S S

13(Left) 13(Right)

2.800 2.900

1.20 1.20

3.36 104.210 3.48 104.210

103.500 103.500

40.21 74.21

5.70

6.84

319.44

43.68

314.58

408.00

No. of Couplers