SECTION 07920 SEALANTS AND CAULKING
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. Work includes providing sealant and caulking as indicated on Drawings or as described herein. The required applications of sealants include, but are not necessarily limited to, the following general locations: 1. Flashing reglets and retainers. Exterior wall joints, including the exterior and interior perimeter of metal door, window. Flooring joints. Sidewalk joints. Other exterior joints noted on Drawings. Joints at penetrations of walls, decks and floors by piping and other services and equipment. Fire rated sealant as required for any penetrations of fire rated walls, decks and floors.

DESCRIPTION

B.

DATE JOB/EWO

2.

REV. NO.

3. 4.

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

5. 6.

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

7.

C.

CONSTRUCTION AGENCY
________________ DATE:

The required applications of caulking include, but are not necessarily limited to, the following general locations: 1. 2. Perimeter of interior door, window. Other interior joints noted on Drawings.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

1.02

RELATED SECTIONS A. Section 03300 Section 04340 Cast-In-Place Concrete. Reinforced Unit Masonry: Sealants required in conjunction with CMU. Sheet Metal Flashing and Trim. Standard Steel Frames.
DWG. TYPE PLANT NO. INDEX DRAWING NO.

Date:

B.

C. D.

Section 07620 Section 08112

SECTION 07920
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

1 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
E. F. G. H. Section 08120 Section 08410 Section 09111 Section 09260 Aluminum Doors & Frames. Aluminum Entrances Metal Stud Framing System. Gypsum Board System.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

DESCRIPTION

1.03

REFERENCES A. ASTM C792-93 Cracking and Chalking of Elastomeric Joint Sealants. Latex Sealing Compounds. Use of Sealants in Acoustical Applications. Elastomeric Joint Sealants. Flexible Cellular Materials - Sponge or Expanded Rubber. Flexible Cellular Materials - Vinyl Chloride Polymers Copolymers (Open-Cell Foam). Preformed Concrete Expansion Joint Fillers for Concrete Paving and Structural Construction.

B. C.

ASTM C834 ASTM C919 ASTM C920 ASTM D1056

DATE JOB/EWO

D. E.

REV. NO.

F.
DISCIPLINE ENGINEER

ASTM D1565

__ ________ _ DATE: ________

G.

ASTM D1751

PROJECT ENGINEER
____________ DATE

H.

CERTIFIED _ __________
DATE: ________

SWRI (Sealant, Waterproofing and Restoration Institute) - Sealant and Caulking Guide Specification.

1.04

SUBMITTALS A. Submit under provisions of Saudi Aramco Contract Document.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

B.

Product Data: Provide data indicating sealant chemical characteristics, performance criteria, substrate preparation, limitations, color availability. Samples: Submit two samples, 4 inch (100 mm) in size illustrating sealant colors for selection. Manufacturer's Installation Instructions: Indicate special procedures, surface preparation, or perimeter conditions requiring special attention.

C.
Date:

D.

SECTION 07920

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

2 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

1.05

QUALITY ASSURANCE A. Perform work in accordance with SWRI requirements for materials and installation. Perform acoustical sealant application work in accordance with ASTM C919.

ENGG

CERT

B.

DESCRIPTION

1.06

QUALIFICATIONS A. Manufacturer: Company specializing in manufacturing the Products specified in this section with minimum three years documented experience. Applicator: Company specializing in performing the work of this section with minimum 2 years documented experience approved by manufacturer.

B.
DATE JOB/EWO

1.07

ENVIRONMENTAL REQUIREMENTS A. Maintain temperature and humidity recommended by the sealant manufacturer during and after installation.

REV. NO.

DISCIPLINE ENGINEER

1.08

COORDINATION A. Coordinate work under provisions of Saudi Aramco Contract Documents. Coordinate the work with all sections referencing this section.

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

B. 1.09

CERTIFIED _ __________
DATE: ________

GUARANTEE Provide 5 year guarantee warranting materials against defects and failures. Repair or replace materials which become defective or fail within the contract warranty period, at no additional expense to SAUDI ARAMCO.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

1.10

DELIVERY, HANDLING AND STORAGE A. Deliver, store, protect, and handle products under provisions of Saudi Aramco Contract Documents. Deliver to site in manufacturers external shipping containers, unopened, with brand names, date of manufacture, color and material designation clearly marked. Elastomeric sealant containers shall be clearly marked as to Type, Grade, and Use per ASTM C920.
SECTION 07920

B.
Date:

C.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

3 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
D. Store all sealants at temperatures not exceeding 40 degrees C nor less than 5 degrees.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

CERT

PMT

ENGG

PART 2 - PRODUCTS 2.01 MANUFACTURERS A. 1. Tremco Limited (Middle East) Riyadh Tel: 05 440 7379 Fax: 01 416 0940 HILTI Supplier: Saad H. Abu Khadra & Co. Dammam Tel: 03 857 1957 Fax: 03 857 3986 Saudi Industrial Paint Co. Ltd. (SIPCO) Saudi Chemical Industries Co. Ltd.

DESCRIPTION

2.

DATE JOB/EWO

3. 4. B. 2.02

REV. NO.

Or approved equal.

MATERIALS A. General: Use the same caulking and sealant system materials throughout the project. Colors: Colors of caulking and sealant materials will be selected by a SAUDI ARAMCO Representative from the manufacturer's standard colors. Compatibility: Before purchasing of each specified sealant, investigate the compatibility of the joint fillers and other materials in the joint system. Provide only materials which are known to be fully compatible with the actual installation condition, as shown by manufacturer's published data or certification. D. Sealant Backer Rod: Compressible rod stock of polyethylene foam, polyethylene jacketed polyurethane foam, butyl rubber foam, neoprene foam or other flexible, permanent, durable non absorptive material as recommended for compatibility with sealant by the sealant manufacturer. The rod will control the joint depth for sealant, break bond of sealant at bottom of the joint, form optimum shape of sealant bead on the back side, and provide a highly compressible backer to minimize the possibility of sealant extrusion when the joint is compressed.
SECTION 07920

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

B.

CERTIFIED _ __________
DATE: ________

C.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

4 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
E. Sealant: Silicon based, single component, chemical, curing to withstand movement of up to 50 percent of the joint width and to be satisfactorily applied throughout a temperature range of 40 - 120 degree F shall be used for roof flashing, interior glazing, duct work and any general interior usage for sealant. General Electric Silicone Sealant 1200 or a suitable equal, approved by SAUDI ARAMCO, shall be used. Sealant: Polysulfide, 2 part complying with federal specs. TT-S00227C Type II Class A, exterior control joints, exterior glazing, anodized window systems, door frames and any other exterior application, not mentioned previously. SIPCO, Brimo-kol sealant or equal, approved by SAUDI ARAMCO shall be used. Fire-rated Sealant: Type of Application 1. Cables and Cable Tray 2. Cable only UL Reference WL 4012 TREMCO CAJ 3141 TREMCO Tremco Material Tremstop PS (Pillows)
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

DESCRIPTION

F.

G.
DATE JOB/EWO REV. NO.

DISCIPLINE ENGINEER

Tremstop 1A (Intumescent Acrylic Sealant) Tremstop Acrylic (Acrylic Sealant) Tremstop Acrylic (Acrylic Sealant) Dymeric (Polyurethane Sealant) FyreSil (Silicone) + Tremstop WS FyreSil (Silicone)

__ ________ _ DATE: ________

3. Floor to walls

PROJECT ENGINEER
____________ DATE

4. Concrete Walls

CERTIFIED _ __________
DATE: ________

HWD 0017 TL/PV 120-02 TREMCO WWS 0024 TREMCO FFS 1015 TREMCO CAJ 6007 TREMCO CAJ 5067 TREMCO CAJ 2069 TREMCO CAJ 1233 TREMCO CP651 HILTI

5. Concrete Floors

CONSTRUCTION AGENCY
________________ DATE:

6. Bus Ducts

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

7. Insulated Metal Pipe 8. Plastic Pipe


Date:

Tremstop D (Tremstop WS + MCR) FyreShield (Ceramic based Sealant) Fire stop cushion 1 hour fire rated
SECTION 07920

9. Metal Pipes

10. Walker duct (Header trench)

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

5 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

PART 3 - EXECUTION 3.01 EXAMINATION A. Verify that substrate surfaces and joint openings are ready to receive work. Verify that joint backing and release tapes are compatible with sealant.

ENGG

CERT

B.
DESCRIPTION

3.02

PREPARATION WORK A. Inspection: Examine joint surfaces to receive caulking and sealant materials, and report to SAUDI ARAMCO Representative, all unacceptable conditions. Cleaning: 1. General: Thoroughly clean all joints scheduled to receive caulking and sealant materials. Rake joint to full width and depth. Remove loose particles present or resulting from cleaning operations, by blowing out joints with oil free compressed air. All traces of bituminous materials must be removed. Porous Surface: Clean surface, such as concrete by grinding, blast-cleaning, mechanical abrading, acid washing or a combination of these methods to provide a clean, sound base surface for caulking and sealant adhesion. Remove form oils by blasting-cleaning. Insure that concrete is fully cured and free from laitance, loose aggregate and surface treatments. If surface treatments are present, test for adhesion before proceeding with sealing work. Nonporous Surfaces: Clean surfaces, such as metal and glass, in accordance with system manufacturer's recommendations. Do not use solvents that leave a residue. Apply and remove solvents with clean white cloths. Do not allow solvents to air dry without wiping.

REV. NO.

DATE JOB/EWO

B.

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

2.

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

3.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

C.
Date:

Protection: Prior to priming, apply masking tape to adjacent surfaces. Leave masking tape in place until tooling operation is complete.

3.03

APPLICATION A. General: Employ only proven installation techniques which will insure that sealants will be deposited in uniform, continuous ribbons without gaps or air pockets and with complete "wetting" of the joint bond surfaces equally on opposite sides. Except as otherwise indicated,
DWG. TYPE PLANT NO. INDEX DRAWING NO.

SECTION 07920
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

6 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
fill sealant rabbet to a slightly concave surface, slightly below adjoining surfaces. Where horizontal joints are between a horizontal surface and a vertical surface, fill joint to form a slight cove, so that the joint will not trap moisture and dirt. B. Back-up: Install back-up material to a proper depth in all joints. Use back-up material of a suitable size and shape, so that when compressed (25 to 50%), it will fit in all joints as required. When using a back-up of hose or rod stock, roll the material into the joint to avoid lengthwise stretching. Do not twist or braid the hose or rod stock. Use bond-breaker strips in all joints, where sufficient room for back-up material does not exist and where required by manufacturer's recommendations. Primer: Prime surfaces in accordance with manufacturer's recommendations and allow to dry before applying sealing material. Caulking and Sealing: Follow manufacturer's instructions regarding mixing, pot life and application procedure. Do not apply sealing materials when the temperature of the material, air or substrate is below 7.2 Deg. C (45 Deg.F) or during wet or humid weather. Apply sealing materials in full bead and force into joint. Polysulfide Sealant Installation: Comply with standards issued by Thiokol Chemical Corporation, except where more stringent requirements have been shown or specified, or issued as recommendations by the sealant manufacturer. Tooling: Tool joints to compress the compound into the joint. Except as recommended by the sealing material manufacturer, do not use liquid solutions to moisten tools. Remove masking tape immediately after cooling. All sleeves penetrating floors or fire rated walls or partitions shall be sealed by an approved sealant equivalent to the rating of the floor/wall partitions. All ducts and pipes which pass through fire wall shall have sheet metal sleeve around them.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

DESCRIPTION

ENGG

CERT

PMT

C.
DATE JOB/EWO

D.

REV. NO.

DISCIPLINE ENGINEER

E.

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

F.

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

G.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

H.

3.04
Date:

CLEANING Remove excess sealing materials from adjacent surfaces. Clean surfaces using procedures recommended by the sealing material manufacturer.

SECTION 07920

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

7 OF 8

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

3.05

PROTECTION OF FINISHED WORK A. Protect finished installation under provisions of Saudi Aramco Contract Documents. Protect sealants until cured.

ENGG

CERT

B.

REV. NO.

DATE JOB/EWO

DESCRIPTION

END OF SECTION

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

SECTION 07920

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS