SECTION 07220 ROOF AND DECK INSULATION

ENGG

PART 1 - GENERAL
DESCRIPTION

1.01

DESCRIPTION Description of Work: This Section includes roof deck insulation consisting of the following: Rigid board insulation 4" (unless otherwise indicated in the drawings) polyisocynurate insulation PIR over entire roof area.

DATE JOB/EWO

1.02

RELATED SECTIONS A. B. C. D. Section 07531 Section 07620 Section 07820 Section 07920 Fully adhered membrane roofing system. Sheet Metal Flashing Trim. Metal Framed Skylights. Sealants and Caulking.

REV. NO.

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

1.03

REFERENCES A. B. ASSTM E-84 ASTM-96 Core Form Flame Spread. Test Methods for Water Vapor Transmission of Materials. Insulation Board, Thermal, Faced, Polysocyanurate.

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

C.

FS-HH-I-1972/GEN

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

1.04

QUALITY ASSURANCE A. Applicable Standards: Comply with the Standards specified in this Section. Comply with AES-N-004. (January 1, 1983). Insulation must be compatible with the membrane roofing system being used. Fire Ratings: Comply with fire resistance ratings as shown, and as required by governing authorities and codes and comply with the following roof insulation requirements:
SECTION 07220

Date:

B.

C.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

1 OF 3

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
UL listing for "Roof Deck Construction" which are rated "FireAcceptable".
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

CERT

PMT

ENGG

1.05

PRODUCT DELIVERY AND STORAGE A. Delivery: Deliver insulation undamaged and in a dry condition. Materials received which are obviously not dry or otherwise damaged will be rejected. Storage: Store insulation on wood blocking and under a weather tight cover. Do not store on new concrete or on the ground.

DESCRIPTION

B.

PART 2 - PRODUCTS 2.01 MANUFACTURERS A. B. C. 2.02 Saptex The Arabian Chemical Company (Polystrene) Arabian Fiberglass Insulation Company.

REV. NO.

DATE JOB/EWO

MATERIALS A. Roof insulation shall be polyisocynurate PIR rigid foam with skin, as manufactured by SAPTEX. Density shall be 35kg/m3 or 2 lb./ft. compressive strength of 280 kPa (40 psi). Water absorption 1% in volume. Insulation shall have a minimum R-value of 18 ft2.h.oF/BTU. To reach 15 ft2.h oF/BTU thermal resistance thickness shall be 4".

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

B. C.

CONSTRUCTION AGENCY
________________ DATE:

PART 3 - EXECUTION 3.01 INSTALLATION A. General: Keep insulation dry during and after application, and protect against excessive foot and wheel traffic. Cut insulation to fit neatly around projections, pipes and vents through roofing. Lay insulation loosely on top of roof metal or concrete slab Install only as much as can be covered by roofing membrane on the same day. Do not leave insulation exposed to sunlight or weather. Seal all edges of insulation adjoining vertical surfaces as recommended by the membrane roofing manufacturer.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

SECTION 07220

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

2 OF 3

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

ENGG

CERT

B.

The separation layer, F2B Fiberfex, or Carlisle HP Protective Mat or equal as recommended by the SAUDI ARAMCO Representative. Shall be loosely laid on top of the EPDM membrane (at areas below concrete walkways tiles).

3.02
DESCRIPTION

CLEANING Remove Trash, debris, equipment and parts from job site.

3.03

PROTECTION Finished roof areas shall be protected from damage by Contractor during construction.

REV. NO.

DATE JOB/EWO

END OF SECTION

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

SECTION 07220

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

3 OF 3

00

You might also like