You are on page 1of 186

Detailed Feasibility Report On BPCL's Bina-Kota Pipeline Project

(August 2007)

Detailed

Feasibility

RefXJrt

1.0

EXECUTIVE SUMMARY NEED & JUSTIFICATION PIPELINE ROUTE STUDY DESIGN BASIS OPTIMISATION STUDY FOR PIPELINE SYSTEM PROJECT DESCRIPTION .. BASIC ENGINEERING PROJECTIMPLEMENTATKJN ..ENVIRONMENTAL I SAFETY ASPECT CAPITAL COST ESTIMATE & RNANCIAL ANALYSIS APPENDIX I 1/ TABLES
1.f)

2 10 17 21 30 38 '47 77

2.0 3.0

4.0
5.0

6.0 7.0 8.0


9.0
10.0 11.0

83 90
102

OPTlMISATIONSTUOYREPORT PROOUCTPROPERTIES 103 COST ESTIMATES OPERATINGCOST 104

12.0

7 13.0

ANNEXURES I THROUGHPUTESTIMATES 1/ REVENUESTO THE PROJECT III RECONNAISSANCESURVEYREPORT IV GROUNDPROFIlE V HYDRAULICPROFILES VI BATCH SCHEDULE & PARCEL SIZE VI/ PROJECTSCHEDULE DATA SHEETS LAYOUTS I PROCESS FLOW DIAGRAMS ABBREVIATIONS
Bharat Petroleum Corporation Limited Bina - Kola pipeline project

14.0 15.0 16.0

105 106
107
1

p3{axI ~Kll!1O){ p;llfWn LIO!le IOdto:>

- elI/S

w~

ll!.ll!ll8

--- - -.
\.

~ - -I
I

I 10

Detailed Feasibility Report

BACKGROUND

Bharat Oman Refineries with a capacity

Ltd. (BORL),

is setting up a state-of-art,

grass root refinery Refinery site is

of 6 MMTPA

at Bina, Dist. Sagar, Madhya

Pradesh.

about 7 km from Bina Railway Junction. The Project activities are in full swing and the refinery is expected to be on stream by the year 2010. The total commitment is 550 crores of the

refinery project IS over Rs. 4000 crores and actuat expenditure

There

is a need for a product

pipeline

for evacuation

of finished

product from the

Refinery.

Since this Refinery is going to supply the products to cater to the markets of that a multi-product pipeline is laid to the consumption and economical the consumption zones of

BPCL, it is necessary identified,

as this would be most convenient Considering

mode for evacuation

the product from the Refinery. India, it is prudent

zones in Northern part of Pipeline

to lay a pipeline from Bina to connect the Multi-Product

being laid from Manglya to Piyala I Bijwasan at Kota.

fhe Board vide its resolution for preparation expenditure

of 9i2006 meeting, heid on 18.12.06, ClpprUV"U ii '"

";:Of'.

of DFR for product pipeline from Bina to Kota with sanction of an initial

of RS.3.5 crores towards carrying out various studies.

The work on Detailed route survey, soil resistivity survey, soil investigation cadastral completed surveys of proposed pipeline route are in progress

studies and

and are likely to be

by end Aug'2007.

Other various studies like EIA, Impact on wild life values,

etc. have also been taken up.

This DFR has been prepared

for laying of multi product pipeline from Bina to Kota. & benefits of laying a Multi-Product of facilities, preliminary Pipeline,

The report deals with need, justification pipeline system optimization,

brief details

cost estimates,

environmental

aspects, financial analysis and execution philosophy

for the project.

3
Bharat Petroleum Corporation limited Bina - Kota pipeline project

, ,
Detailed Feasibility Repxt

1.1

NEED, JUSTIFICATION TRANSPORTATION

& BENEFITS OF PIPELINE MODE OF

Pipelines have proved to be most convenient and economical for transportation of high volume of petroleum products. The advantage of pipeline system is its relatively easier and routine nature of operation, inexpensive maintenance and continuous movement of products. There is no problem of returning empty

containers to loading points as in the case of other modes of transport, resulting in saving in energy and cost. Transit loss, which is sizable in other modes of transport, is also considerably reduced.

1.2

THROUGHPUT ESTIMATES

Throughput estimates of Bina - Kota pipeline for the years 2010-11 to 2019-20 are enclosed as Annexure throughput sections. I. Throughput estimates also cover details of Piyala and Piyala - Bijwasan

in Kota - Mathura ; Mathura -

Pipeline throughput figures have been worked out taking into considerati.on the following: BPCL volumes ex Kota comprising of Kola volumes and Udaipur

volumes ( fed by road from Kola) BPCL volumes ex Mathura comprising of Mathura ( local), Bharatpur and Tundla TOP volumes ( Road fed ex Mathura) BPCL volumes ex Piyala and Road fed volumes for Parwanoo , Chandigarh , Kat/igodam, Roorkee TOP and Rail fed volumes for

Najibabad TOP, Bhatinda TOP, Lalru, Jammu, Srinagarl ( Road fed ex Jammu)

Pampore .

4
Sham Petroleum Corpofation Umited

Sina - Koti1 pipeline project

Detailed Feasibility Report

BPCL volumes ex Bijwasan for Bijwasan, Shakurbasti and ATF volumes for Delhi AFS tenminal1 and 2.

As per the projected volumes, throughput for the year 2013-14 works out to be

--.-----------------------------------

2.764 MMTPA and for 2019-20 works out to be 3.588 MMTPA

The above

throughput is considering MS (2 grades), SKO, HSD (2 grades) and ATE

For the purpose of DFR, 2.8 MMTPA throughput has been considered as Phase I throughput. Pipeline optimisation and selection of pipeline size has

been done considering throughput of 3.6 MMTPA However, Pumping Stations being provided presently would cater to only Phase I throughput

The tankage at Kota and batch size has been worked out considering Phase-I throughput of the pipeline. Since the product from Bina Refinery is mainly

meant for up North locations which would be fed ex Mathura, Piyala and Bijwasan, only heart cut product has been considered for Kola so as to

reduce the tankage at Kota. Interface generated will be absorbed in Piyala tanks.

For laying the pipeline, it has been considerd that Bina-Kota Pipeline would become a part of Bina-Kota-Piyal&Bijwasan Pipeline a1d pumping

requirements have been worked out. Accordingly, in case Bin&Kota section is not being operated, pipeline can be operated from Manglya to PiyaIa section as designed.

1.3

OPTIMISATION STUDY

For the purpose Clf oplimisation, a number of alternatives involving critical parameters such as pipeline diameter, pumping system capacity, operating . cost etc. were considered for working out economics and selectioriof optimum size of pipeline.
5
Bharat Petroleum COfjJOfation Umited 8ina - Kola pipeline project

Detailed Feasibility Report

An optimization

study has been carried out considering

Bina-Kota Section.

Based on this study, it is observed that 18" dia pipeline would be the most optimum size.

1.4

PROJECT PROPOSAL

The project envisages construction of 265 Km long pipeline from Bina to Kota TOP (under construction). Based on heart cut pumping at Kota no additional

tankage is envisaged at Kota. From Kota to Piyala 440 kms, 16" API 5L Gr 60 pipeline is laid and was commissioned in Mar 07. TOP's will remain as

Bharatpur, Mathura and receipt terminal shall be at Piyala. Since ATF was not envisaged earlier in Mumbai-Manglya -Piyala- Bijwasan pipeline there will be requirement of ATF tanks at Piyala which is not a part of DFR

From Piyala to Bijwasan,

57 kms, 8" API 5L X-56 Grade feeder pipeline for

catering to petroleum requirements of Bijwasan and Shakurbasti is laid and was commissioned along with Manglya - Piyala pipeline in Mar 07.

The system shall have dedicated Tele-rommunication Control and Data Acquisition (SCADA) system.

system and Supervisory SCADA system will be

integrated with existing SCADA system for Mumbai - Bijwasan pipeline. The aim of SCADA is to ensure effective management and supervision of the pipeline operating from a centralized location using remote terminal units

located along the pipeline. This system is also used for leak detection.

The

proposed pipeline shall be protected against external corrosion by impressed Current Cathodic Protection system and against intemal corrosion by dozing corrosion inhibitors.

6 Bharat Petroleum Corporation Umited Bina - Kota pipeline project

Detailed Feasibility RepJrt

1.5

PROJECT FACILITIES

Facilities proposed for the pipeline system at various terminals and along the cross- country portions of the pipeline are as follows:

Pipeline coated with 3 layer PE coating a) Bina despatch terminal to IPS I section (Ch.130):
Pipeline size & material 455mm (18") 0.0. x 6.4 mm WT API 5l GRX-65, 130 KM 84 Kglcm"(g)

Pipeline length Pipeline Design Pressure

b)

IPS I (Ch.130)to Kota (Ch. 265) :


Pipeline size & material 455 mm(18') 0.0. x 6.4 mm WT API 5l GRX-65 135 KM 84 Kglcm"(g)

Pipeline length Pipeline Design Pressure -

c)

Pipeline Associated Facilities 7 nos. CP/SV stations shall be between Bina to Kota. provided along the pipeline route

In Phase I, pumping stations will be at Bina and Kota and in Phase /I pumping stations will be at Bina , Kota and Kaarvadi ( existing

intermediate pigging station ( IP 4 location) for Manglya - Piyal~ pipeline project ) e) Intermediate pigging station at chainage 130 is proposed along the pipeline route. 7.
Bharat Petroleum Corporation limited

Bina - Kof3 pipeline project

Detailed Feasibility Report

1.6

PROJECT & OPERATING COST

Fixed Cost Basis: The capital cost of pipeline from Bina to Kota (inc!. cost of additional pumping station reqUired at Kota) is estimated at Rs 38462 crore. The total estimated

cost of the project works out to Rs. 405.82 crore including a foreign exchange component of Rs.31.55 crore at May 2007 price levels and interest during

construction (IDC), which is Rs.21.20 crores. The operating cost of the pipeline is estimated at Rs 16.00 crore annually.

Completion

Cost Basis:

The working for cost of Bina - Kota pipeline on completion cost basis has been done by ascertaining trends of variation of AICPI, WPI, FE variation, Statutory variation, Steel price for the past 10 years and assuming average growth rate, year wise escalation has been worked out based on expenditure in line with project cost phasing. The cost of Bina Rs 405.99 Kota pipeline on completion cost basis works out to

crore and Rs. 428.37, including

IDC. The total cost variation in

completion cost against fixed cost is Rs 22.55 crores i.e. 5.55 % over fixed cost of Rs 405.82 crores.

1.7

PROJECT PROFITABILITY

In the Base case, project revenues have been calculated cOnsidering a tariff of 70% of rail freight for the movement of products through Bina - Kota pipeline. Based on this cost benefit analysis, earnings to the tune of Rs.121 crores on the estimated throughput of 2010-11 are envisaged, which shall be the

revenues for this Project. Based on these revenues, the pipeline is expected to provide good returns on the base case as follows:

8
Bharat Petroleum Corporation Umited

Bina - Kota pipeline project

Detailed Feasibility Reoort

IRR on Fixed Cost Basis: The IRR for the project on the total capital cost of Rs 405.82 Grores is 19.53% based on the present revenues generated on pipeline transportation and the minimum cost of the project. IRR worked out for the following sensitivity cases considering differential below:
,----------.-------------

project cost and revenues

generated are tabulated

Sensitivity --

cases
--

IRR
17.94 % 16.07 %

Increase in project cost by 10%

Revenues generated from pipeline operations with a tariff of 60% instead of 70%. IRR on Completion Cost Basis:

The IRR based on the completion cost of Rs. 405.99 crore and an IDC of Rs. 22.38 crore works out to 18.60 %. 1.8 PROJECT SCHEDULE

The proposed project facilities are expected to be completed in 27 months (24 months mechanical completion plus 3 months for commissioning t stabilization) from zero date i.e. from the date of DFR approval.

1.9

ENVIRONMENTAL ASPECT

Ministry of Environment & Forests has recommended that all bulk quantities of Petroleum Products be transported through welklesigned risks in transportation by rail and road. Transp.ortation of petroleum products through pipeline is superior to other modes of transportation due to the inherent advantages of increased safety, reliability, reduced rail t road traffic congestion, minimal product loss in transit, lower energy consumption etc. Besides, pipeline projects are environment friendly by minimizing fugitive emissions tin transit risk.
9
Sharat Petroleum Corporation Umited Bina - Kota oloeline project

pipelines to minimize

pafOJd i1Utpdtd eJO){-

etJ.18

or

P'lllWn uopeJOCI.Jo:) w~

~et19

.J ....

,,~--- -- ,
'

'

Detailed Feasilility Report

2.1

NEED & JUSTIFICATION

21.0

Bharat Oman Refineries Ltd. (BORL) is setting up a state--of-art, grass root refinery with a capacity of 6 MMTPA at Bina, Dist. Sagar, Madhya Pradesh The refinery site is about 7 KMs from Bina Railway Junction. The Project activities are in full swing and the refinery is expected to be on stream by 2010.

2.1.1 The consumption of petroleum products in India is growing at a steady rate and has now reached a stable growth rate of 4-5%. Though the overall growth in 200~ over the previous year is only about 0.3%, the

growth in MS and HSD has been significant. The consumption of petroleum products has gone up from about 30.8 MMT in the year 198081 to 112 MMT in 2005-()6 With a CAGR of around 5%: The trend in the first quarter of 2006-D7 also shows a robust growth and it is estimated that the demand for retail petroleum products (MS and HSD) will grow at around 4 to 5 % from 2006-D7 onwards.

2.1.2 The entire production of BORL Refinery will be marketed by BPCL for which facilities will be set-up up at BORL. BPCL would also' be entering into a product purchase and sale agreements with BORL on take or pay basis.

2.1.3 The emphasis of BPCL would be to utilize the location advantage of the Refinery and reinforce its presence and enhance market share in central and northern India market. The products of Bina refinery will be marketed in the central and northern regions of the COIXllry.

2.1.4

The analysis of demand for products in the target demand centres of BORl in northern India would be over 60% of the overall products to be
11 Sharat Petroleum Corporation Umited Dina - Kota pipeline project

De/i1iled Feasitility Report

evacuated from BORL and the balance being road and rail movements in Central India. Additionally, products of BORL will also be marketed by BPCL through its large depot network in the northem region.

2.1.5 The products from Bina refinery will move to northern region through the proposed Mumbai-Manmad-Manglya-Piyala pipeline as well as rail/road

depending upon the destination. As per the estimates the demand of MS and HSD together in the targeted demand centres in north India would be around 2 MMT in 2010-11.

2.1.6 There is a need for a product pipeline for evacuation of finished product from the Refinery. Since this Refinery is going to supply the products to cater to the markets of BPCL, it is necessary that a multi-product pipeline be laid to the demand centres, as this would be most convenient and economical mode for evacuation of the product from the Refinery. Considering the demand centres in Northem part of India, it is prudent to lay a pipeline from Bina to connect the Multi-Product Pipeline being laid from Manglya to Piyala I Bijwasan at Kota.

2.1.7

In a free market scenario, besides supply security, competitive product positioning in the inland markets will be of paramount importance and would remain as the backbone to support the marketing efforts.

2.1.8

The positioning of product and making it available at the same price to BPC customers as made available by the competitors would be the crucial factor for sustaining the market share. The cost of transportation and the availability of product at the right time are crucial to sustain the market share.

2.1.9 Hence, it is proposed to lay a 18" diameter 265 km long cross-country


pipeline from Bina to Kola which would help in evacuation of MS, SKO, 12
Bharat petroleum CorporatJon Umited
Dina - KoiiJ

pipeline project

Det1iled Feasibility Re{XJrt

,
HSD & ATF from BORL Refinery economically in a reliable and optimal manner.

2.1.10 This pipeline shall ensure product availability I reliably to cater to petroleum requirement in strategic northern sector. The throughput of the pipeline has been worked considering the sales volumes of 2005--06 with the following growth assumption:
Growth 2006-07 2007-08 to 2010-11 2011-12 onwards MS SKO HSD

5% 5% 4%

0% 0% 0%

4% 4% 4%

2.1.11 The total throughput figures have been worked based on following distribution pattern from Kota:

Pipeline throughput figures have been worked out taking into consideration the following:~v'BPGL volumes ex - Kota comprising of Kota volumes and Udaipur volumes (fed by road from Kola) ./ BPCL volumes ex - Mathura comprising of Mathura Bharatpur and Tundla TOP volumes (Road fed ex Mathura) ./ BPCL volumes ex Piyala and Road fed volumes for Parwanoo , Chandigarh , Kathgodam, Roorkee TOP and Rail fed volumes Srinagarl (local),

for Najibabad TOP, Bhatinda TOP, Lalru, Jammu, Pampore ( Road fed ex Jammu) ./

BPCl volumes ex Bijwasan for Bijwasan, Shakurbasti and ATF volumes for Delhi AFS tenninal1 and 2.

13 Bharat Petroleum Corporation Umited Bina - Kola pipeline project

Detailed Feasibility RefX]ft

Based on the above distribution pattern, pipeline throughput works out as below: (Figs. In TMT)
--

Route Bina - Kota "ota - Mathura Io\athura - Piyala ~iyala - Bijwasan

M$-4 363 363 315 292

2013-14 M$-3 HSD-4 HSD-3 915 205 703 180 775 703 146 609 538 0 404 0 2019- 20 HSD-4 HSD-3 889 1147 889 975 771 674 511 0

SKO 139 135 84 14

ATF 439 439 439 439

Total 2764 2595 2131 1149

Bina - Kota Kota - Mathura '-'athura - Piyala Piyala - Bijwasan

M$-4 M$-3 459 248 459 216 399 176 370 0

SKO 139 135 84 14

ATF 707 707 707 707

Total 3588 3380 2810 1602

The pipeline is being put as a strategic requirement to ensure product security and to service the markets in the northern region.

2.2

BENEFITS OF PIPELINE TRANSPORTATION

The transportation through pipelines is the most economical means of movement of large volumes of petroleum products. advantages over other modes of transportation: It has the following

i)

Pipeline transportation requires the least energy as compared to other modes, including rail movement. Conservation of energy is a priority activity identified by the Govt. of India.

ii)

The cost of transportation is least in the case of pipelines and moreover, reduces as the pipeline depreciates. On the other

14 Bharat Petroleum Corporation Umited Bina - Koti1 pipeline project

De/iJiled FffiSiMity Report

hand, freight charged by the Railways has been increasing continuously.

iii)

Pipeline transportation is environment friendly vis-a-vis rail I road movement The environmental impact of the pipeline during

construction, operation and maintenance phases is negligible. The environmental impact during construction is mostly reversible since, after laying the pipeline, the land is restored to normal use. During operation and maintenance of the pipeline, only a

small quantity of effluent is generated at pumping stations and at terminals for which oil water separators are provided. These

separators also take care of any oil spillage in the installation in a safe manner.

iv)

Pipeline transportation results In enhanced safety as there is minimum handling of product. The subterranean nature of the pipelines also makes them intrinsically safer than other modes of transportation.

v)

Petroleum products being volatile in nature, certain losses during loading I unloading operations and during transportation are unavoidable. However, it is observed that these losses can be

minimised in the pipeline mode. Experience shows that whilst pipeline transportation losses range between 0.1% to 0.15% the losses in the rail I road transportation are as high as 0.32% to 0.5% especially in lighter products like MS, which is also a high value product.

vi)

Transportation by rail requires large amount of land for building up . railway sidings which increases the cost of installations and alsci restricts the choice in selection of installation sites.
15
Bharat Petroleum Corporation Umited

Bina - KoliJ pipeline project

Detailed Feasibility I?e{xJrt

,
vii)

Pipeline transportation allows multi-product handling, using the same facilities, whereas different types of wagons are necessary for different "class" of product. Therefore, pipelines are more suited for effecting quick changes in product mix required to be transported. Improved technology would allow transportation of

propane and butanes in the same pipeline which would further accentuate the advantage in favour of pipeline transportation.

viii)

Increase / decrease in transportation volume can be effective without much time delay / disturbance and cost in case of pipeline transportation.

ix)

Natural calamities like floods, breaches, etc, disturb surface transport systems. As major part of the pipeline system

traverses below the ground, the pipelines are normally less affected by natural calamities.

x)

Transportation by modes other than pipelines, especially road, has an adverse effect on the environment through exhaust emissions apart from the wear and tear caused to the

infrastructure like roads, leading to high maintenance cost for the economy.

xi)

Land costs are minimal since the pipelines are laid underground. Further, in case of pipelines, the land can be restored back to its normal use after the construction work is completed. In case of

rai/transportation, the land use pattern is permanently changed. /nthe pipeline option, it is possible to traverse even through very difficult terrain.

16
Bharat Petroleum Corporation Umited Bina - Kota pipeline project

Pi}{aKi atJf/iJd!d /!/ox ~ rolS

~n

l.IO!leJ<ldJOJ wnapq;ld

~eJe1/8

Detailed FB:JSibilityReport

3.1

PIPELINE ROUTE STUDY A pipeline route study was carried out to identify alternative pipeline routes and the same were analyzed to facilitate selection of best economical pipeline route

3.2

SCOPE OF STUDY The scope of the study comprised of the following :

Desk-top study with 150,000 and 1:250,000 scale Survey of India maps and identification of pipeline route from Bina to Kota.

Reconnaissance survey along the pipeline route

Preparation of the pipeline route study report

3.3

P1PEUNE ROUTE STUDY REPORT.

3.3.1 MIs MASCON Multiservices Pvt. LId. have carried out the reconnaissance survey Tor me plpeiine. DFR is based on reconnaIssance survey report submitted by Mis MASCON

3.3.2 Approach and methodology adopted for reconnaissance survey for route selection is described below: Safety of public lives, properly and also safety of pipeline. Shortest I optimum pipeline length Easy and favourable terrain conditions, avoidance of large water bodies. Ravines, depressions, unstable ground etc. Avoidance of sharp bends andturnings Avoidance of historical monuments Minimum demolition activity and up rooting of minimum numbers of trees.
18 Bhara! Petroleum Corporation Umited 81na - Kota pipeli/Je project

Detailed FeasitNIity Report

Consideration

Of availability of infrastructure and access to pipeline

route during and after construction. Avoidance of Reserve Forests, built up areas, places of worship, burial grounds. Existing and further development in the regions such as roads, Rail lines, canal network, industrial units etc.

Based on above factors (as applicable), the pipeline route has been selected

including alternatives .

3.3.3 Conclusion

The total length of the best economical pipeline route is as under:

Blna to Kota

265 Kms

The position of Stc:rting & Terminating Points are as under;

-t. Starting Point, Bina - Dist. Sagar of Madhya Pradesh State)


Latitude - 240 - 15' - 43"

Longitude - 780 - 10' - 07"

.) TermInation

PoInt, Kota - Dist.Kota of Rajasthan State)

Latitude

- 250 -11' - 20-

Longitude - 750 - 58' - 27"

Salient features of finally proposed alignment are as under,

19 Bharat Petroleum CorporatlOn Umited 81na - Kota p;peIine projed

a. Total Length of the route:

265 kms Madhya Pradesh & Rajasthan 3 nos. 3 nos. 16 nos. 10 nos. 8.6 kms.

b. Name of states c. No of National Highways :


d. No. Of State Highways d. No of other major roads e. No of Rivers f. Length in forest

g. Elevation @ start point h. Elevation at end point

400 mts. 255 mts. Rat 3 nos.

i. General terrain
j. Canals k. NaJla I Drain: 3005.

3.3.4 A detailed reconnaissance survey repOrt is enclosed as Annexure III.

20
Bharat Petroleum Corporatlon Umited

BiN - /(()fa pIpeine project

P<1(axI ;;uJFK!.td e}O)I- elli8

p;qfWn UOAeJOdJo::> II

w~

tell!ll8

~~--

-~

..

._----

D=tailed Feasibility

Re{XJlt

4.1

BASIC PARAMETERS

4.1 1 Products to be transported

Motor spirit (MS) (2 Grades) High Speed Diesel (HSD) (2 Grades) Superior Kerosene Oil (SKO) Aviation Turbine Fuel (ATF)

4.1.2 Pipeline Throughput

As given below

Growth % MS SKO HSD

Upto 2010-11 5.0% 0.0% 4.0%

Beyond 2010-11 4.0% O.OOA> 4.0%

Route Bina - Kota Kota - Mathura Mathura - Piyala Piyala - Bijwasan

MS-4 363 363 315 292

2013-14 MS-3 HSD-4 HSD-3 SKO 205 703 915 139 180 703 775 ,.135 609 538 84 146 14 i 0 404 0

ATF 439 439 439 439

Total 2764 2595 2131 1149

Bina - Kota Kota - Mathura Mathura - Piyala Piyala - Bijwasan

2019-20 MS-4 MS-3 HSD-4 HSD-3 1147 248 889 459 889 975 459 216 771 674 399 176 0 511 0 370

SKO 139 135 84 14

ATF 707 707 707 707

Total 3588 3380 2810 1602

As per the projected volumes, throughput for the year 2013-14 works out to be 2.764 MMTPA and for 2019-20 works out to be 3.588 MMTPA

For the purpose of DFR, 2.8 MMTPA throughput has been considered as. Phase I throughput. Pipeline optimisation and selection of pipeline size has

22 ~~tP~m~~Um~
Bina - KoliJ pipe5ne project

Deti1iled FeasiaJity Report

been done considering'throughput

of 3,6 MMTPA However, Pumping Stations

being provided presently would cater to only Phase I throughput

Batch sizes have been worked out considering pipeline,

Phase-I throughput of the

Since the product from Bina Refinery is mainly meant for up North

locations which would be fed ex Mathura, Piyala and Bijwasan, only heart cut product has been considered for Kota so as to reduce the tankage at Kota Interface generated will be absorbed in Piyala tanks,

For laying the pipeline, it has been considered that Bina-Kota Pipeline would become a part of Bina-Kota-Piyala-Bijwasan Pipeline and pumping

requirements have been worked out. Accordingly, in case Bina-Kota section is not being operated, pipeline can be operated from Manglya to Piyala section as

designed .

4.1,3 Properties of Products:

As per Appendix II.

4.14

PROJECT SCOPE AND BATTERY LIMITS

I II ,

' Pipeline from Bina Dispatch Terminal to Kota Tap off point Pumping stations at Bina and Kota for further pumping to PiyaJafor Phase I throughput. Pumping stations at Bina Kota and Kaarvadi ( Existing IP-4 Intermediate pigging station location for Manglya - Piyala pipeline project) for phase II throughput.

III N V

Intermediate Pigging Station at ch.130 from Bina. Tap off point connection to Kota depot under construction. Hook up with existing 16" Manglya - PiyaJa pipeline at Kota.

23
Bharat Petroleum Corporation Umited Sino - Kola pipeline project

DetdiletJ Feasibility Report

4.1.5 BATTERY LIMITS

Upstream

Product manifold at Bina

Downstream

Hook up wilh existing Manglya Piyala pipeline at Kota

4.1.6 DESIGN CONDITIONS Pipeline Throughput Refer Annexure-I Pipeline size shall be optimised for a throughput facilities of 3.6 MMTPA Other be

such

as pumps

shall

designed based on Ph-I throughput of 2.8 MMTPA

II

Mainline pumps

As per design. Pumps (1+1) wittfVFD shall be designed fOf handling MSI HSD ISKO I ATF

III

Other Facilities

All other facilities shall be designed to match the pipeline and pump capacity.

IV

On stream Hours

8000 hrs/yr.

Permissible Interface percentage : As given below Product tank to accommodate interface

Interface of MS/SKO HSDISKO

Interface quantity acre table

MS HSD

1%
2% Refer Annexure-VI
24

VI

Product sequence and Parcel

Bharat Petroleum Corporation Umited


Bina - Kola pipeline project

Det3/1ed Feasitility RefXXf

size (batch volume) m3

VII

Design Temperature

Above Ground - 65 C Buried portion - 45 C

VIII

Over design Margins

On flow On pipe length

Nil :Nil

IX
X

Design Life

35 Years

Pipeline Length

265 km

XI

Basis for Hydraulic calculations

Pipeline hydraulics shall be carried out based on HSD at 25 C. Pumps shall be suitable for all other products.

XII

Corrosion allowance

O.5mm

XIII

Pipeline internal roughness

45 microns

XIV

Pigging Facilities

Permanent pigging facilities "Intelligent Intermediate Pigging" pigging shall

suitable for be provided. will be

station

provided as per requirement

xv

Subsoil temperature (1 M below ground)

XVI

Design code

ASME 831.4 & OISD guidelines will be . followed as applicable. However, in 25


Bharat petroleum Corporation Umited Bina - Kola JipeJine project

DelBiled Fmsibi/ity Re{XJft

case of contradictory stipulations, the stringent condition will prevail.

XVII

Surge Control

Suitable system

surge will be

controVsurge provided as

relief per

requirement of design.

XVIII Pipeline laying

Buried.

XIX Corrosion protection system

Internal protection Suitable corrosion inhibitor injection system shall be provided.

External protection - PE I other suitable coating will be provided. - Cathodic protection by impressed current for buried portion of pipeline will provided.

xx

Seclionalizing valves

Sectionalizing valves (SVs) will be provided as per ASME B31.4 &.


OISD.

XXI Ground Profile

As per Annexure- IV

4.1.7 INSTRUMENTATION

General

Adequate instrumentation

and control

system will be provided for safe and efficient operation. Supervisory contrOl and. data acquisition (SCADA) system
26
Bharat petroleum Corporation Umited 8ina - Kota pipeline project

Detailed Feasibility Report

shall be designed for remote monitoring and control The pipeline shall be

monitored and controlled through panel based instruments

"
III

Type of control

Electronic

Final control element (peV)

Electrohydraulic

Safety valve

Thermal Relief Valve/Safety Valve and Safety valve isolation will be provided wherever required as per design.

These isolation valves shall be locked open.

Density Meters

Density meters will be provided at Bina, /Pigging Station, Kota TOP's (1+1) or as required for density measurement and interface detection. Location of one
density meter at -Kola tap off point Sh8!!

at approximately 500 meters from the piping manifold


&

the

location

of

second shall be close to the manifold valves. 4.1.8 I CUSTODY TRANSFER REQUIREMENTS Flow meters

Turbine flow meters with one spare


shall be provided at Bina , Intermediate Pigging (if required, as per leak

detection requirements), & Kota tap off point.

"

Meter proving

Existing Meter prover

of Mumbai27

Bharat Petroleum CofpOfation limited 8ina - Kota pipeline project

Detailed FeasIbility Report

Manmad

Manglya

Bijwasan

pipelinewill be used.

4.1.9

SCADA General The SCADA system aims at ensuring effective and reliable control,

management and supervision of the pipeline from a centralized location using remote terminal units (RTUs) along the pipeline route at suitable location. II SCADA monitoring and Control SCADA system compatible with

existing Manglya -

Piyala pipeline

project shall be installed. SMCS will remain at Mumbai and Bina will

becomeRemoteWork station.

28
Shamt Petroleum Corporation Umited
Bina - Kola pipeline project

Detailed Fmsibility Report

BINA - KOTA MULTI PRODUCT PIPELINE

(GROUND PROFILE)

Chainage Elevation Location Chainage Elevation Location Chainage Elevation Location

(Km)
----

(m)
400 Bina 405
.---

(Km)
98.15 98.31 ___ 99B 106.14 109.89 111.00 113.67 116.87 120.07 . 124.06 124.85 126.99 14u.76 146.86 _ 148.02 Sind river 149.30 154.02 165.22 169.98 171.19 173.63 179.76 184.31

(m)
480 474 467 475 470 460 440 412 402 395 388 372
,,"Cl:<
.

(Km)
189.38 195.22 198.42 204.75 208.35 209.77 212.15 215.61 218.10 221.00 224.01 224.54 ""5.?(l1 227.40

(m)
278 266 26[J 272 269 262 265 270 266 260 243 255 253 252 Kali Sindh 240 river 255 257 259 260 250 257
._._.~

I
,

0.00 0.26 6~ 8.80 12.42

-___
-.

439 _.-Betwa 360 river 390 405 420 450 490 470 480 512 520 505 490 460 472 487 495 492 488

------j
--I
.-

I
i

-.

18.80 20.30

---~ 25.60 27.50 46.20 56.30 63.30 68.50 71.30 74.50 81.80 86.57 90.06 94.34 95.05 95.82 95.96 97.31

350 330 Parbati 310 river 322 277 302 301 293 289 280

227.90 230.49 235.77 244.28 248.08 251.52 252.31 253.31 265.00

. 493 490

259 . Kola 256

..

29 Bharat petroleum Corporation limited


81na - Kola pipeline project

Detailed Feasibility Report

5.1

OBJECTNE

The

main objective

of pipeline

route and system

optimization

is to

transport petroleum products at the desired throughput and at the optimum cost during the design life of the pipeline system. pipeline system involves establishing Economic design of between

an optimum relationship

pipeline size and pumping configuration (in tenms of number of pumps and power requirements). A smaller diameter pipeline requires a more

powerful pumping system and vice-versa.

Lower investment in pipeline

may be offset by higher investment in pumping and consequently, higher

power consumption for a given throughput.

Hence, for a given throughput,

there is an optimum size of pipeline and optimum pumping system which

will give the least Net Present Value (NPV) of the investment (Capital and Operating) for the design life of the pipeline system.

Oplimisation

study has been carried out for pipeline diameters 14", 16", considering appropriate wall thickness and pipeline

18" and

20"

construction material.

For the purpose of DFR, 2.8 MMTPA throughput has been considered as Phase I throughput. However, the pipeline optimisation and selection of

pipeline size has been done considering throughput of 3.6 MMTP A

5.2

BASIS FOR ANALYSIS

Analysis has been carried out on the fOllowing basis: -

BORL Dispatch Tenminal shall be at Bina The pipeline shall tenminate at Kota and will be connected at Kola by 16" APISL X -60 Grade, 440 kms Kota - Piyala pipeline. pipeline is

Design pressure for 16" API SL X -60 Grade Kola -Piyala 88 kg I cm2.

31 Bharat Petroleum Corporatlon-limited


Dina - Kalil pipeline project

Detailed Feasibility Report

Design capacity for 16" Manglya - Piyala pipeline for Phase I is 2.2 MMTPA and Phase II design throughput is 3.5 MMTPA While facilities! tankage have been designed with Phase I throughput, designed for 3.5 MMTPA pipeline was

TOP's will be at Bharatpur (under construction) and Mathura. IP Station, for particular size of pipeline are considered in optimization study as per the requirement. Location of IP -3 ( Chakbiloli, Sawai and

Madhopur) for Manglya - Piyala pipeline is at Ch 130 from Kota IP 4 ( Kaarvadi, Bharatpur) is at Ch 241 from Kota. Ground profile attached as Annexure IV.

5.3

PRODUCT CHARACTERISTICS

Since

HSD constitutes

major portion

of the quantity required

to be

transported, product characteristics of HSD have been considered for the purpose of optimization.

5.4

PIPEUNE PARAMETERS & COST DATA

Pipeline, parameters under. 1)

& cost data considered

for the optimisation are as

Pipeline Parameters Une Pipe Specification API 5L Gr. 8, X-42, X-46, X-52, X-56 , X-BO, X-65, X -70 Design Factor Corrosion Allowance Pipeline Ute

0.72
0.50

mm

35 years

2)

Cost of following items! systems have b,een ,considered constant as they are common lor all the scenarios! altematives :

32
Bharal Petroleum Corporation Umited
Bina - Kola pipeline project

DetaJ/ed feasibility Report

Land & land development at Dispatch, Receiving & SV stations TOP's I Tankages etc. SV Stations Survey & soil investigation ROU compensation Telecom & SCADA Design and engineering project management construction supervision procurement and

Owner's Management expenses Start up and commissioning charges Margin money for.working capital Financing charges Futur.e escalation beyond May, 2007

5.5

PIPELINE SIZE For transportation been evaluated. thickness of various throughput sizes of 14", 16", 18" & 20" have In order-to -select-- the- bestattemativer~va!iOlJS, pipe_wall for each pipe size with a corrosion pipeline to be

have been considered

allowance of 0.5 mm.

Minimum thickness of cross-rountry

provided has been taken as 6.4 mm.

5.6

MAIN PUMPING UNITS

A pump configuration of one main & one standby pumps at Bina and one main and one standby pipeline size, pump if at Intermediate has been pumping stations for.

particular

required

considered

for. the

optimization study.

5.7

COST & PRESENT VALUE The alternatives have been evaluated based on capital cost investment

and the operating cost over the pipeline life. 33


Bharat Petroleum Corporation Umited Dina - Kota pipeline project

Detailed Feasibility RepoFt

5.8

OPTIMISATION ALTERNATIVES

Considering Phase II throughput of 3.6 MMTPA for designing the pipeline size, optimization study has been carried out based on least net present value. The results of the optimization study are summarized as below: -

5.8.1

Optimization

- Alternative-I

A) Pipeline size ( Bina - Kola segment)

14"

Pump station at Bina dispatch terminal and intermediate pump station with 1W+15 pumping configuration for Phase I.

Pump station at Bina dispatch terminal and intermediate pump station with 1W+15 pumping configuration for Phase II.

5.8.2

Optimization

- A1temative-ll

Pipeline size (Bina - Kota segment)

16" pull . ing

Pump station at fllna dispaici1 ierminai wiih I VV TiS configuration for Phase-I.

Pump station at Bina dispatch terminal with 1W + 15 pumping configuration for Phase-il.

5.8.3

Optimization

- A1temative-lll

Pipeline size ( Bina - Kola segment)

18"

Pump station at Bina dispatch terminal with 1W + 15 with pump configuration for Phase I. Pump station at Bina dispatch terminal with 1W + 15 with pump configuration for Phase II.

34

Bharat Petroleum Corporation Umited


Dlna - KotiJ pipeline project

Detailed Feasibility Report

5.8.4

Optimization

- Alternative-IV

Pipeline size ( Bina - Kota segment)

20"

Pump station at Bina dispatch terminal with 1W + 1S with pump configuration for Phase I. Pump station at Bina dispatch terminal with 1W + 1S with pump configuration for Phase II.

5.9

Optimization

Study Report

5.9.1

The results of Optimization Study Report are endosed as Appendix.

5.9.2 It is observed from the results of the Optimization Study that Alternative
III, for 18" API 5L X -42 pipeline from Bina to Kota is found to be the most optimum size, if this pipeline is being designed as a stand-alone pipeline pipeline and has the least Net Present Value.

5.9.3

However, Bina-Kota pipeline cannot be optimized in isolation as most of ' ...lS requlr ed' " ...... ~ t""'" tI1 e proouct -ro-IJC ua Piyala and Bijwasan.
l'll;;U LV

....... , ti ens u-p no. u lloea

ex.

Math urn,

5.9.4

Bina pumping

;<ota pipeline as standalone

pipeline will require only a single to Kota in case of

station at Bina for pumping the product

selected pipeline option. However, additional pumping station at Kota is required in all cases for pumping the product upto Piyala for Phase I

throughput. It is further observed that ilitial year throughput of 2.4 MMTP A upto Piyala can be met by increasilg the grade of pipeline from Gr. 42 to

X 65 and without the requirement of additional pump station at Kota. Also, considering flexibility & expandability and the cost difference in grades to consider

being not substantial, it is recommended X 65 from Bina to Kola.

18" API 5L Grade

35 Bharat Petroleum Corporation Umited


81m - Kola pipeline project

Detailed Feasibility Report

The results of the optimisation study are summarized as below: -

Phase I ( 2.8 MMTPA)

a) Pumping Station at Bina, 416 Klfhr, 71 Kg/em2 ( Although, pump actual head requirement is 22 Kg/em2 is our higher head in order to facilitate direct pumping to being provided for running the pumping at lower speed) ,pump selected

Piyala. VSD is

b) Pipeline TOP at Kota (under construction)

c) Pumping Station at Kota , 390 KJ/hr. 73 Kg/em2

d) Pipeline reCeipt terminal at Piyala ( under construction)

e) For 1.15 MMTP A product movement from Piyala to Bijwasan pump facilities at Piyala shall suffice.

f)

Pipeline receipt terminal at Bijwasan

Phase II ( 3.6 MMTPA)

a) Pumping station at Bina ,540 KlJhr 40 KgIem2 (Utilisation of existing pumps of Phase I will be explored in detailed

Engineering stage)

b) Pipeline TOP at Kota

c) Pumping Station at Kota 5091<11hr.70 KgIcm2

d) Pumping station at Kaarvadi. Bharatpur in Kota - Piyala section ( IP-4 location), 509 K1/hr, 52 Kg/crif 36
Bharat Petroleum CorporatIon Umited

Bina - Kota pipeline projet::t

Def:aiJed Feasibility

Repat

e) Pipeline receipt tenninal at Piyala

f)

For 1.6 MMTPA product movement

from Piyala to Bijwasan, pump

facilities at Piyala under construction shall suffice.

g) Pipeline receipttenninal

at Bijwasan

Proposed pipeline from Bina to Kola shall be as follows:-

$eQment
.

Dia 18" API 5L X-65, 6.4MM

Length 265Kms

Bina - Kota

37
Bharat PetrOleum Corporation Umited

Bina - Kota pipeline project

,
Detailed Feasibility Report

6.0

PROCESS DESCRIPTION

The process description including operating and control philosophy for the proposed pipeline system will be as given below:

6.1

OPERATING & CONTROL PHILOSOPHY

6.1.1

For achieving Phase I capacity for 2.8 MMTPA, Bina - Kola Multi-product pipeline consists of one pumping slation at Bina for pumping the product to Kota. For further pumping to Piyala through another pump station is required at Kola. Manglya - Piyala pipeline For Phase-II operation for

achieving a throughput of 3.6 MMTPA, two intenmediate pumping stations are envisaged at Kola and Kaarvadi ( existing IP -4 location of Manglya Piyala pi! project ). Intenmediate pigging station is 130 from Bina proposed at chainage

Bina pumping station takes suction from pipeline manifold

comecting all the product tanks at Bina Dispatch tenminal. Kota will act as tap off point and further product movement win be through existing 16" illiangiya - Piyala pipeline. Only heart cut product will be laken into Kota tanks. envisaged SCADA (Supervisory Control and Data AcquiSition) system is to ensure effective and reliable control, management and

supervision of pipeline from centralized location USing Remote Telemetry Units (RTU) along the pipeline route at suitable location. Since, Bina -

Kota pi! is joining the existing Mumbai - Manglya - Piyala I Bijwasan pipeline at Kota , it is advisable to keep SMCS (SCADA Monitoring Control Station) at Mumbai. Bina can be Remote Work station. &

Leak

detection system for pipeline wiD be augmented with the existing package of Mumbai - Manglya - Piyala pipefine.

At Kola the product is routed. to existing tanks through pipeline JmInifold. No additional lankage is envisaged at Kota tap off point

39
Bharat petroleum Caporatloj-, Umi\ed

,
Detailed Feasibility Rt!fX"T

The control centre at the Bina pumping station shall have operational control related to pumping of products from tanks for Bina - Kota pipeline system. All supply operations for \he pipeline system shall be under \he

control of BPCL's Despatch Terminal at Bina and \hey shall ensure supply of the product at normal operating conditions. The Despatch station shall

make all necessary arrangements for \he product despatch and ensure

proper lining up of the system in conjunction with the receipt terminals.

Based on the face-ta-face pumping of product and in order to maintain the product specifications, an optimum scheduling of batch size is established based on \he permissible contamination levels.

6.1.2

Batch Schedule & Parcel Size

The philosophy assumed for working out parcel size and batch scheduling is that only heart cut product will be laken at Kola, Bharatpur & Mathura while interface will be pumped further to Piyala. The inter-face generated in Bina - Kola, Kola - Mathura and Mathura - Piyala sections routed to Piyala terminal storage tanks. The presentiankage" adequate to receive heart cut product will be

at Kola ;~

At Piyala, 3 nos. ATF lanks 5500 KL each will be required. One tank will be under pipeline receipt another for testing and 3r lank for pipeline dispatch to Bijwasan. Scope of the same is exduded from the DFR.

MS Euro IV parcel needs to be sandwiched between MS Euro III parcels


t

and during cutting of interface at Piyala, parcel of MS Euro IV shall be cut dean by taking heart cut product while taking interface in MS Euro III product. This will result in down gradation of certain quantities of Euro IV MS. HSD Euro IV parcels would also be required to be handled in the same way.

40
Bhara! Petroleum Corporation Umiled

8ina - KiJta pipelIne project

Detailed Feasibility Report

Similar1y, ATF parcel needs to be sandwiched between SKO parcels and during cutting of interface at Piyala, parcel of ATF shall be cut clean by taking heart cut product while taking interface in SKO producl result in down gradation of cenain quantities of ATF. This will

Batch schedule and parcel sizes have been worked out accordingly and are attached as Annexure VI.

6.1.3

Instrumentation

and Control

All controls, recording and remote indicating devices shall be mounted on the control panel in control room. Motor operated valve push buttons with position indicators and status of locaVremote operation, booster pump unit sequence, pump unit sequence, station sequence, shutdown and alarm devices are also included in the control panel. system and thermal Arrival relieflsafety Suitable surge control as per the by density

valves will be provided shall be detected

requirement

of the interface

instrument located at Kota TOP. Turbine Row meters shall be provided at Kota TOP, Pigging station (as per requirement of leakdelection sysiem).

6.1.4

Pump Station operation Pump unit sequence for the mainline pump at Bina performs the following functions:

Check the position of MOV on the discharge of main pump and bring it to dose position, if required.

Check the position of MOV on the suction of main pump and bring it to open position

Main pump motor is started and MOV of discharge is opened after a time delay. 41 Bharat Pe!rOIeum Corporation Umited
Bina - Koti1 pipeline project

Detailed Feasibility Re{XJrt

Any of the main pumping units can also be shut down manually by pressing the stop button. As the motor stops, the suction and discharge

valve closes automatically after a time delay. The station sequence sends a ready signal through RTU to the immediate pumping station for start-up. In case any pump station trips other station shall be informed through RTU or control panel, if required.

The main pumping units will be shut down automatically in the event of low suction pressure or high discharge pressure. pressure provided will also shut down the pumps. on the downstream Very high station discharge One control valve will be

of each pump station for controlling the

pressure in th' pipeline.

A pressure controller is provided on the suction

side of the pumps to keep the suction pressure within the limits.

6.1.5 Sump Tank and Pump

Sump tanks are provided at Intermediate

Pigging station, Intermediate

Pumping station, TOP's and Receipt Terminals for collection of slops from various points sucn as neaaer Ora/ns. scrapper drain. iine iiushing etc. The collected slop will be pumped into the HSD product passing throqgh the main pipeline by means of sump pump and slop transfer pumps in case of Kota to mainline tanks. Provision will be also kept tor pumping the slop to tank lorries. The sump pump and the slop transfer pump are

suitably interlocked to trip in case of low liquid level in the sump tank.

6.1.6 Corrosion Inhibitor Dosing System

Corrosion inhibitor chemical tank and pump is provided at Bina for dosing the corrosion inhibitor chemical uPstream of mainline pumps tor corrosion protection. The dosing rate can be varied by stroke adjustment of pumps:

Inhibitor tanks shall be provided with level instruments to stop the pumps in case of low level in the tank.

42
Bharat Petroleum Corporation Umited

8ina - Kola pipeline project

Detailed [t=ibi/ily ~

6.1.7

Sectionalizing

& Mainline station

Inlet/Outlet

valves

Along the main pipeline 7 sectionalising valves are provided.

Whenever

required, the sectionalising valve and mainline station valve can be closed from SMCS after ensuring the shutdown of entire pipeline operation.

6.1.8

Kota tap off I Mathura tap off I Piyala receipt terminal

Operation

Despatcher

at Bina shall advise the terminal operator of the time and Station valve shall remain open during normal A pressure control valve shall control the

product being pumped.

product receiving operation. terminal inlet pressure.

The terminal operator shall select and open the

MOV on the proper distribution manifold to receive the product in proper storage tank. Anival of interface shall be detected by the density

instrument

located at the .terminal.

Online sulphur I colour detection The interface

meters are also required for cutting low sulphur products. shall be taken to tanks as per allowable contamination levels.

6.2

PROCESS DESCRIPTION

6.2.1

Bina Dispatch station

The petroleum products shall be taken into the pipeline at Bina Dispatch Station through pipeline manifold connected to all product tanks. At Bina, the products are metered before entering the suction of mainline pump. Two flow metering assembfies (1+1) are proposed in parallel at the

downstream of two basket filters (1+1) before mainline pump suction. The flow is measured corrected using turbine meter. Row computers indicate the

volumetric .flow rate as well as the mass flow rate of the

petroleum products to be transported.

43
Bharat ~m Corporation Umited Bina - Kola pipeline project

Deli1i/ed Feasibility Re{Xit7

Booster

pumps have been provided to enable pumping of petroleum

products from storage tanks at Bina.

VFD units for Main and Standby pumps is proposed at Bina due to various throughputs requirements and different density of products required to be pushed. Pump with motor and VFD with flow rate ranging from 250-600 M'/hr capacity and 850 MLC discharge head have been selected for Bina . These pumps would also enable us to meet the throughput requirement of direct pumping upto Piyala for 2.4 MMTPA without any additional pumping stations.

Corrosion

inhibitor is injected at the pump suction to prevent internal Corrosion inhibitor dosing tank and corrosion

corrosion of the pipeline.

inhibitor dosing pump have been provided for injecting corrosion inhibitor. Scraper launcher is provided at Bina for pigging operation.

6.2.2 Intermediate Pigging Station


proVided at chainage i 30 irom

Intermediate

pigging stations are

Billa.

Scraper receiver and Scraper launcher are provided for pigging operation. A sump tank is provided for collection of slops from various points such as header drains, scraper drains, fine flushing, TSV relief ete. Tha slops from the tank shall be pumped back into the pipeline with the help of sump pump mounted on the tank and slop transfer pump. Station by-pass

arrangement shall be kept at the pigging station.

6.2.3 Kota Tap off point and Interinediate Pumping Station

44
Bharat PetJOIeum Corporatjoo Umited

81m - Kola pipeline projed

Detailed Feasibility Report

At Kola pump station, Scraper receiver and scraper launcher are provided for pigging operation. A sump tank is provided for collection of slops from

various points such as header, drains, scraper drains, line flushing, TSV relief etc. The slops from this tank shall be pumped back into the pipeline with the help of sump pump mounted on the tank and with the slop transfer pump. Provision will also be kept for pumping the slop to tank lorries.

Corrosion inhibitor dosing system shall also be provided

Kota terminal commissioning

is under construction

and facilities

shall be ready for land shall be

in Dee 07. A part of the Kota terminal

designated for pipeline receipt facilities have been marked in the layout.

and future pump station which

There will be not be any additional

requirement of land for putting pumping facilities during Phase II of the project.

Following facilities are to be provided in Phase I:

Metering system Flow rate of the product through the pipeline will be metered by turbine flow meters to meet the requirement of SCADA.

Pig Receiver & launcher Pig receiver, launcher, pipeline manifold and facilities for sampling will be provided at Kota tap off point.

Storage Tanks Storage facilities at Kota terminal (under construction) do not require any augmentation and shall meet the heart cut parcel size requirement. It is proposed to handle only one grade of MS and one grade of HSD at Kota through this pipeline. The existing planned tankage ( under construction) is as below:

)
Bharat Petroleum Corporation
R;ni1 -

4S
Limited

Kota oipeline woiect

Detailed Feasibility Report

Storage facilities at Kota terminal (under construction) do not require any augmentation and shall meet the heart cut parcel size reqUirement It is proposed to handle only one grade of MS and one grade of HSD at Kota through this pipeline. The existing planned tankage ( under construction) is as below:

PRODUCT
1-..

TANKAGE AVAILABLE

ADDITIONAL TANKAGE REQUIRED

--

HSD MS SKO SLOP

20300 KL ( 3 X 6700 + 1 X200) 5200 KL (2 X 2500 + l' 200) 1916 KL (2 X 858 + 1 X200)
-

--

Product

Pipeline Receipt Manifold

To ensure proper product receipt at Kota Installation a pipeline receipt

manifold along-with necessary control room and associated facilities shall be provided in the space identified inside the tenninal.

~;re fighting system

Fire fighting system of the pipeline receipU dispatch manifold shall be hooked up with fire fighting facilities of Kota tenninal.

6.2.5

RECEIVING TERMINAL AT PIYALA

There will be no additional facilities

required in existing Piyala receipt

tenninaJ except construction of 3 ATF tanks 5500 KL each for handling ATF receipts. Cost of the A TF tanks is excluded from the scope of DFR

46 Bharat Petroleum Corporation Umited


81na - Ko(a pipeline project

Rf0Jd ~

EQO)/ -

ellIS

pajlWn lIOIll!J<X\JOJwl13\Oll<ld le.ll!tlll

Lv

--

-~

--,

'.
,-

.....

,...---

-' .

~ .
,

- .-l:

"

.-

"

,,-

:
:

-~

..

;\0...
! '

Detailed Feasibility

RefXJrt

7,0

BASIC ENGINEERING

Basic engineering succeeding

of the proposed pipeline system is presented

in the

paragraphs under the following headings:

Pipeline facilities Instrumentation and Control System

SCADA & APPS System Telecommumcation System

Power Supply System Cathodic Protection System Fire Protection Facilities Environmental Aspects

7.1

PIPEUNE FACIUTIES

7.1.1 Preliminary Location of Pipeline Facilities


The proposed pipeline facilities is depicted in the Schematic Arrangement for Pipeline route,

7.1.2 Pipeline Design Parameters a) Bina to Intennediate pigging station Ch.130:

Design pressure Pipeline Length Pipeline material Pipeline size and wall thickness

84 Kg/cm2g 130 km API 5L Gr, X-65 18" NB. wall thickness 6.4 mm

48
Bharat proo\eJm Corporation Umited

Bina - KoliJ plpeJ1ne projet:t

Dffailed FeasiN/ity Report

b)

Intennediate

pigging station

to Kota Tap off Ch 265 :

Design pressure Pipeline Length Pipeline material Pipeline size and wall thickness

84 Kg/cm2g 135 km API 5L Gr. X-65 18" NB. wall thickness 6.4 mm

c) Common

Design Parameters:

Design Temperature Buried Above Ground Corrosion Allowance Product Handled 45 Deg. C 65 Deg. C O.5mm MS (2 grades). HSD (2 grades). SKO and ATF

7.1.3

Pipeline

Materials

Pipeline

and its appurtenances

shall

be provided

with carbon steel

materials suitable for the intended service, as indicated below:

a)

lJnepipe

Line pipe shall conform to API specification 5L The grades and size of line pipe shall be API 5L Gr. X-65 from Bina to Kota. Pipe wan thickness shall conform to ASME 831.4 and shall also meet the requirements of OISD 141.

b)

Pipeline f"lttings and f1an~es All pipeline materials downstream of the mainline pumps, such as valves, flanges and fittings etc. shall be of Class 600# rating.
49
Bharat Petroleum Corporation Umited

8ina - Kola ppe/lne project

Detailed Feasibi5ty Report

c)

Flow Tees

All branch connections on the mainline, which are greater than 40% of the mainline diameter, shall be provided with flow tees to allow smooth passage of pigs. Flow tees shall be designed as per ASME B 31.4. The material of flow tee shall be compatible with line pipe material.

d)

Insulating

Joints

Insulating joint shall be provided at transition point of aboveground and underground section of pipeline for electrical isolation. Insulating joints

shaH be of mono-block type.

e)

SectIonalizlng

Valves / Station Block Valves

Sectionalizing

valves and Station Block Valves shall be motor operated,

fulJ.-bore ball valves (MOV). All sectionalizing valves shall have provision for remote operation ,.. .-;"
-

(ROV). SeclionaliZlng

valves snail be buried arid

provided

with stem extension. Mainline valves shall be full-bore type

baD valves, to allow smooth passage of scrapers or pigs through them. These valves shall conform to API-6D. 7.1.4 Corrosion Coating

The selected

corrosion coating shall be suitable for the temperature

range specified in the Process Design Basis.

Three layered PE coating I suitable alternative is considered for Bina Kota Pipeline.

50

Bharal Petroleum Corporation Umited


Dina - Kota {ipeline project

Detailed Feasibi5ty Report

Field weld joints shall be coated with heat shrinkable sleeves or cold applied tapes. However, heat shrinkable sleeves have been considered in the DFR cost estimates.

In addition to the corrosion coating, the entire buried portion of the pipeline system shall be provided with impressed current C.P system.

7.1.5 Pipeline Construction

Pipeline and associated facilities shall be constructed in accordance with ASME B 31.4 and other applicable API standards. The pipeline shall be laid underground with minimum one meter cover. Additional cover, wherever required, shall be provided in accordance with 0150 141.

Welding shall be carried out as per AP/1104.

All welds shall be 100%

radiographed. After the installation is completed, the entire pipeline shall be hydrostatically tested. The hydrostatic test pressure at any test section shall be 1.25 times the design pressure. Hydrostatic testing of terminal piping shall be carried out separately.

7.1.6 Construction

Methodology

For the construction of main pipeline in different type of strata and installation of associated pipeline aossings, the methodology described here in below has been considered. The construction methodology described here below only highlights the aspects that have major bearing on the cost of construction. The infonnation used for the selection of a specific construction method is based on the

reconnaissance survey carried out by Mis Mascon Multiservices Pvt Ltd. and shall be firmed up during the detailed engineering when the survey data will be available. 51
Bharat PetroleUm Corporation Umited Blna - KoIi1 ppeJ/ne project

Detailed Feasibi5ty Report

A)

Main Pipeline

a) Open Cultivatedl

Barren land open cultivated using and

The majority of the pipeline route passes through barren land. Conventional trenching

and back-filling

trenching

machine has been considered for laying of the pipeline in such areas. A typical cover considered. b) Rocky Soil with murram, gravel and weathered rock of one (1) metre over the top of pipeline has been

Hard and weathered rock are noticed in route most!y near river crossings and reserved forest areas. In addition to this, sheet rock is also located at few locations. Generally, weathered rock I murram can be excavated with the help of dozer I ripper and back-hoes, however, controlled blasting can also be resorted to speed up the excavation activities in rocks. A

minimum of 300 mm thick layer of soft back-fill material shall be provided all around the pipeline prior to back-filling the trench with excavated material. INhere blasting can not be carried out, due to close proXImity oj existing facilities, mechanical equipment for rock excavation can be used. 7.1.7 Pipeline Crossings

a) Rail
All railway lines shall be crossed by boring method. Approval of designs and construction methodology shall be obtained from concerned railway authorities. Pipeline at railway crossings shaH be provided with casing pipe. The carrier pipe shall be installed inside casing pipe. The casing pipe shall be three nominal pipe sizes larger than carrier pipe or as specified by Railways. The minimum cIear cover at the crossing above top of pipe6ne shall be 1.7m. The crossing angle shall be as close to 90 as posstble. The railway crossings shall comply with the requirements
Bharat prooleum Corporation uniited Dina - Kola Jipe/jne project

of 52

Detailed Feasibility ~t

API 1102 and Indian Railway Authorities. Casing insulators and end seals shall be provided to isolate carrier and casing pipes. b) Roads & Canals

Road crossings shall comply with the requirements requirements of the concerned road authorities.

of API 1102 and the Pipeline at National

Highways and State Highways crossings shall be provided with the casing pipe. Metalled roads other than the national highways and state highways shall be crossed by open cut method. However, at locations, where it is not feasible to cross the road by open cut method, boringfjaCking method shall be used. No casing pipe shall be considered at such locations. All the cart tracks crossings shall be C3rried out by open cut method_ The road crossings shall be provided with a minimum clear cover of 12 m measured from top of the carrier pipe.

Irrigation canals shall be crossed by boring method wherever required by the staMory authorities. All other minor canals and nallas crossings shall be carried out with conventional open .cut method unless directed

otherwise by the concerned authorities. The canal crossings and other water crossings shall be provided with a minimum clear cover of 1.5 m.

Casing pipe in case of rail/road crossing will be 2 sizes larger and separate casing pipe for OFC will be provided.

c)

Minor RiverCroSSing

Minor rivers crossings are considered to be crossed by conventional open cut method. Pipeline shall be installed approx. 1.5 m below the lowest Lowest bed level shall be calCl!lated after giving due

bed level.

consideration to scour depth of such water crossings. The finepipe shall be concrete coated, if required, to provide sufficient negative buoyancy. 53
Bharat PeIroIeum Corporation united Bina - Kola ppeJine project

Detailed Feasibi5ty RqxJrt

eJ

Major River Crossing

Major river crossing i.e. Betwa river may be carried out by Horizontal Directional Drilling (HDD) method. Pipeline shall be installed approx. 2.5 . m below the lowest bed level. Lowest bed level shall be calculated after giving due consideration to scour depth of such water crossings.

7.2

PIPEUNE INSTRUMENTATION

& CONTROL SYSTEM

7.2.1

Instrumentation

& Control system will be provided for safe and effICient

control of Bina - Kota pipeline.

PLC's shall be used for the process interlocks/shutdown operatioo and station monitoring at Bina Dispatch

logicl MOV's

and Kota tap off point.

For phase II. where existing intennediate pigging station at Kaarvadi Will be used as Pumping station, PLC shall be implemented later.

Controi--- paneis-~si1aii be liSed~fui mounting- the --flow computers and controllers etc. at all the locations where metering facilities are provided. Bina and Kota tap off shall have control panels and the cabinets for monitoring and controls. These control facilities shall also be extended to be viewed in existing RWS for Manglya - Piyala / BfJW3S3npipeline.

New

control

room

at

Bina

and

Kota

shaD be

constructed

for

accommodating the new control panels, PlC system and the cabinets ete..

Controllers

for the pressure based.

and flow control

shall be single

loop

microprocessor actuators.

Control valves shall be With Electro Hydraulic

54
Bharat Petroleum Corporation Umited 8/na - Kola ppeJine project


I
I

I I -'
IIPLC's shall be with redundant processor; and dual 110. and control.
Detailed Feasibility Rep;>rt

power supply, communication

PLC operator consoles shall be used for station monitoring

Volume flow measurement

metering facilities shall be provided at the Flow meters shall be Turbine

required locations in line with the P&IDs. flow meters.

For proving of the turbine flow meters on this pipeline, bi-direc1ional meter prover available at Manmad shall be used.

,
Unit control panels at each pump station for the mainline and booster pumps shall be provided' by the pump vendor. bearing and winding temperature-monitoring

Vibration monitoring,

system for all multi stage

horizontal pump and motors shaD be provided on the UCP located in the control room. be implemented station PlC Pump machine interlockslstar1lstop and trip functions shall

in the pump UCP and this UCP shall be interfaced 10 the from stationlSMC and for status

system for stopllriplESD

monitoring.

7.3

SCADA & APPS SYSTEM

7.3.1 Introduction

The

SCADA

& APPS system aims at ensuring effective and reliable and supervision of the pipeline from centrarlZed

control,

management

location using Remote Terminal Units (RTUs) at various pipeline facilities.

55 Bharat Petroleum Corporation Limited


Dlna - Kofi'Jppe/!ne projed

Detailed Feasibility Report

7.3.2 SCADA & APPS Requirements

The SCADA system Will monitor and control the pipeline facilities in a timely manner and provide centralized alarm and event management and operation and management reports for all distributed pipeline facilities.

The SCADA

system

shall also ensure proper pipeline shutdown by closing

various pipeline facilities in orderly manner in the emergency situation.

With the objective to enhance the SCADA system monitoring & control availability as part of system network planning, the availability of data connectivity of RTU's distributed along the pipeline would be increased by connecting Bina station over 2 Mbps OFC link and back up communication line. link ( BCl) using 2 Mbps leased

a)

The SCADA Master control Station (SMCS) wi!l remain at Mumbai and the same shaH be augmented to accommodate Additional remote workstation RTU'g for 8ina - Kot2 p!peHn~ in the control room at

shall be provided

Bina and Kota.

New SCADA system compatible with existing Manglya -

Piyala pipeline project shall be installed.

b)

The following pipeline facilities shall be considered for telemetry purposes through RTUs located at these locations for Bina - Kota Multi-product

Pipeline project

Bina Despatch terminal Intermediate Pigging station at Ch 130 7 Nos. Sectionalizing valve/cathodic protection stations Kota TOP

56
Bharat Petroleum Corporation Umited 81na - Kota pipeline project

. .

Detailed FeasibtIJty Report

c)

The APPS(Application volume balance

software) covering Transient modeling enveloping and Batch tracking shall be provided

leak detection

covering all four products, i.e., High speed diesel(HSD), Motor spirit(MS) & Superior Kerosene oil (SKO) and ATF Suitable modifications in existing APPS system for Manglya - Piyala section will be required to be done

7.3.3

Design Criteria

,
The SCADA system shall meet the requirements of Open architecture in the following manner:

a) The system shall meet the requirements of interoperability, portability and scalability as per the following intemational standards, with their latest

version numbers:

i)

The SCADA software with the main SCADA data base shall be built on operating system conforming to IEEEPOSIX standards, X10pen

portability guide .

ii)

The work station SCADA MMI and APPS MMI shall conform to OSF MOTIFIX-Windows standards or WIN 32.

t" '.

b) i)

The networ1<ing shall support OSlfTCP/lP network connectivity.

ii)

The communication

protocol between

Master station and RTUs

shall conform to lEE 802.3 standard.

Iii)

The SCADA data base management system shall support database access through SOL

57
Bharat petroleum Corporation Umited Bina - Kola pipeline project

Detailed Feasibtlity Report

iv)

Communication

protocol between master statio& RTU's shall n or DNP 30/ DNP 3.0 over Ethemet

confirm to IEC 87-5-101/104

II

The SCADA and APPS system shall be adequate(without adding any hardware to the already installed system at SMCS and remote work station) to accommodate100% future expansion (w.rt additional RTUs

and consequent pipeline length and facilities, communication channels, additional remote workstations etc) without any limitations and without affecting the various system performance parameters and keeping

memory, CPU and disk utilization within 50%.

III The poll time considering all I/O parameters of all RTUs including time for scanning, polling, processing and complete updation on SCADA and APPS database & MMI shall not exceed 15 seconds

7.3.4

System Configuration

a) The remote--woFkstationat Bina shaH reconnected,to Ethemet link.

SMCS with 2 MB

The remote workstation [RWS] shall provide complete The

SCADA & APPS MMI capability [displays, graphics, reports).

background informatinn for SCADA AND APPS MMI shall be fetched from RWS resident disk [any change in the background infonmation at SMCS will automatically transferred to RWS resident disk] and the foreground database] information [alarms/events, access from SMCS. real time database, historic

The RWS shall be capable of

performing all MMI functions such as calling of all displays, graphics, reports, alarm acknowledgement & issuing controls [under the password control] etc. The system status display shall indude the complete status of SMCS and RWS.

The remote workstation shall be based on multiprocessor architecture with two processors installed (as a minimum).
58 Bharat Petroleum Corporation limited 8im - Kola pipeline project

Detailed Feasibility Report

7.3.5

System functional

requirement

The SCADA system shall fulfill the following funclional requirements:

Data Acquistion Monitoring and Control Alarm and Event Deteclion Trending Report Generation Data Archiving Communication handling and Error recovery

Data base Configuration and Engineering Functions System Maintenance & Security Integration with Application software

The APPS system shall fulfill the following functional requirements:

Confirmed leak alarm with leak detection lime, leak location and size during steady and transient operation states.

InventOr) analysis function Pipeline transportation efficiency function Pressure, flow, temperature & property profiles Instrument monitoring function Scrapper tracking function Shut in leak detection under non flowing conditions

7.3.6

Test Equipment

& Special Tools

Test equipment shall include the following as a minimum: 39


Bharat PetrOleum Corporation Umited

8ina - Kola pipeline project

,
Detailed Feasibility Repon _

a) 2 Nos, Portable Diagnostic Test Unit (PDT). The PDT shall be

minimum Pentium IV based laptop with active matrix display

b) 2 Nos. of Plant simulators

c) 4 Y, digit Digital Multimeter with builtin signal level meters and with carrying case - 2 Nos

d) Digital real time oscilloscopes, 100 MHz, 2 channels, sampling 100 m/s - 1 No. The requirement of test equipment shall be reviewed during ordering stage after looking into availability from Mumbai-Manmad and Manmad-Manglya and Manglya - Delhi pipeline project

7.4
7.4.1

TELECOMMUNICATION

SYSTEM

The pipe line 265 km connecting Bina to Kota shall pass through the cross country areas which are not adequately covered by the public

telecommunication system, hence a new dedicated telecommunication system is proposed to be implemented to meet the operation and maintenance requirements of this pipeline. The new telecom system shall Manglya - Piyala /

be hooked up with existing system of Mumbai Bijwasan pipeline.

Considering

the implementation

schedule, comparative economics of

. ,
)

various communication media and availability of the right-of-way along the pipeline route, an optical fibre communication system is proposed as the main communication requirements. system for the pipeline operation and for future

60
Bharat petroleum Corporation Umited

Dina - Kota pipeline project

Detailed feasibility

Report

7.4.2

TELECOMMUNICATION

REQUIREMENTS

The

telecommunication

system

shall

enable

voice,

data,

video

communication

and CCTV as detailed below:

Providing voice communication at the various stations through ordinary, digital weather proof and explosion proof telephones (at hazardous areas) .

The same shall include the following:

Direct dialing facility between attended stations and at various unattended SV locations.

Conference facility connecting all the attended stations.

Pig Monitoring /Watchman connections connecting all stations.

Hotline facility connecting attended stations.

Providing low speed data communication for SCADA.

Providing high-speed data communication for SCADA at Bina and

other stations .

Providing facsimile communication amongst attended stations.

Providing EPABX network connecting attended stations

61
Bharat Petroleum Corporation Umited

)
81m - Kota pipeline project

Detailed Feasibi5ty Report

Providing Video Conferencing between Bina , Kota and existing Mumbai - BiJwasan VCS stations

Providing CCTV at all attended!

un attended locations.

7.4.3

SYSTEM ENGINEERING CONSIDERATIONS

A) The following considerations! assumptions are made:

Bina, IP station at ch 130 and Kota will be attended stations(3 nos.).

..
B)

Rest of the stations shall be telecom unattended stations (7 nos.)

Overall end-to-end system availability shall be better than 99.99% at 1*10'


10

BER for optical fibre communication system. The mean time to repair of

a faulty module is taken as 1 hour.

C) The

optical

fibre

communication

system

shall

meet

the

current

requirements traffic. The

& shall provide for some future expansion in voice and data optical fibre communication system shall be based on

Synchronous International architecture.

Digital Hierarchy (SDH). SDH is future proof technology. Telecommunication Union (ITU-T) standardizes SDH

Concepts like ring protection shaH achieve higher system

reliability required (the same shall be achieved by providing by duplicating the signals and sending them through two parallel optical fibres).

J
D) The network shall have built-in setf-diagnostic and network management capabilities to continuously check the communication network with existing network management centre. In case of an optical fibre cable cut Istation ) failure. data upto the fibre break/station failure shall be available at Bina. The NMC in that case shall also control and monitor the various stations upto the fibre break/station failure.

62
Bharat Petroleum Corporation Urnited

8ina - Kola {ipeJine project

7.4.4 TELECOM SYSTEM

Detailed FeasilJi/ity Report

The network management system shall perform the following functions:

1) Automatic

and

continuous

monitoring

of transmission

equipment

functional status.

2)

Collection of network fault data at the management center(s) and the presentation of this data either automatically or when requested.

3)

Registration of fault data and storage for statistical analyses.

4)

Remote measurement

of transmission equipment parameters from the

. management center, manually or automatically.

5)

Remote

control

of transmission

equipment

from the management

center, manually or automatically.

6)

Transmission channel reconfiguration from the management center(s).

The advantage of SOH (Synchronous digital hierarchy) are detailed below:

7.4.5 SYNCHRONOUS

DIGITAL HIERARCHY

All elements of the system are synchronized to the same master clock.

Thus no justification is required to bring signals up to a common rate .

Signals from all levels of the POH can be accommodated in the SOH by packaging them in the payload area of an STM-1 frame.

After adding a number of bytes, known as the Path Overhead (POH), the payload forms a Virtual Container (VC). 63
Bharat PetrOleum Corporation Umited

Blna - Kola pipeffne projed

Detailed Feasibility Re{X>rt

Addition of a pointer indicates the position of the payload in the VC. It is then called a Tributary Unit (TU) or an Administrative Unit (AU).

This allows the payload to slip in time relative to the STM-1 frame in which
it is contained.

Adjustment of the pointers is also possible where slight changes occur because of propagation delay and the like.

7.4.6

The result of this is that in any data stream it is possible to identify individual signals, and drop or insert infonnation, thus overcoming one of the main drawbacks of the PDH.

SYSTEM IMPLEMENTATION

PLAN

Considering the present requirements & the possibility of Mure expansion requirements, a STM-4 digital optical fibre communication link is proposed to be implemented telecommunication as the main communication requirements. system to meet the

The scope of the telecom works through optical system shall cover all the attended and unattended stations along the pipe fine.

7.4.5

BROAD SPECIFICATION OF MAJOR EQUIPMENTISUB-SYSTEMS

a1)

OPTICAL FIBRE CABLE The Optical fibre cable shall be corrugated steel tape annored

comprising of 12 nos. Single Mode fibres suitable for working in 1550/1310nm wavelength region & suitable for direct underground burial including laying in wet and swamp areas. The fibre in the
64
B/Jarat Petroleum Corporation Umited

Bina - Kola pipeline project

,.
Detailed Feasibility Report

safety code and safe-operating safety of the neighbourhood.

practices will be followed thus ensuring the

9.3

SAFETY FEATURES

The pipeline would be protected by a combination of external and internal corrosion impressed respectively. protection current systems cathodic by multi-layer and pOlyethylene corrosion And coating, inhibitors

protection

State-of-M

Supervisory

Control

Data Acquisition

systems (SCADA) the pipeline

for continuous monitoring of operating parameters of with leak detection system, dedicated Tele-

coupled system

communication contingencies.

would ensure

immediate

response in case of

9.4

ENVIRONMENTAL

ASPECTS

Wrthaview hazards,

to minimise environmental it is essential toemphasise

impact and reduce operational

the importance of these-aspects at

concept and design stage. Among these, maximum weightage is given to the route selection and the safety features in pipeline design. VrtaJ

features considered for route selection with respect to the environment are

Avoidance
"

of populated

areas to minimise hazards to life and

property. Shortest pipeline length with minimum number of bends

Avoidance of ecological or othefwise sensitive areas Avoidance of water bodies and wet lands

Minimum obstructions, i.e .. minimum numbers of road crossings Easy Accessibility for conStruction and inspection purppse ..

85 Bharat Petroleum Corporation Umited


Dim - Kola ppe!ine project

Detailed Feasibiity Report

The

impacts

during

construction

(i.e.,

preparation

of ROU,

trench

excavatior~ environmental quality, land

backfilling,

etc.) and operation

of the pipeline on various

components, i.e., air quality, water quality, noise quality, soil use, ecology, floralfauna and socio-economic etc are

described in brief in the following sections.

9.4.2

Environmental

Impacts

9.4.2.1

Air Quality

a)

Construction Phase There would be a short term and localised impact with respect to dust emissions during the construction period due to earth moving and trenching equipment

Vehicular exhaust emissions like S02, and dust will be released construction~es.

N02,

CO, Hydrocarbons due to various

into the atmosphere

The impact

due to vehicular exhaust emissions and dust on air

quality is minimum, short term and reversible in nature.

b)

Operational Phase During the operation of the pipeline the impact on air quality will be with respect to volatile hydrocarbons, the identified source being the truck loading and the evaporation losses from storage tanks. impact due to these volatile hydrocarbons insignificant The

on air quality will be

Overall the project will have a significant positive impact on air quality of the region due to reduction in road movement of POL products.
86
Bharat PelrOIeum wrporation Umi!ed

Bim - Kola ppe!ine project

Detailed Feasibility Report

9.422

Water Quality

a)

During the construction of the pipeline the impact on water quality due to trenching! backfilling across the river crossing will be

marginal.

The construction across minor rivers will be carried out The major river, Betwa will be crossed by The HOD crossing

during the dry season. Horizontal

Directional Drilling (HOD) method.

will reduce the impact on ecology of the river.

Overall the impact during the construction reversible and for a very short duration.

phase will be marginal,

b)

Operational Phase There would be no impact on wdter quality due to the operation of the pipeline. The effluents generated due to pigging, floor wash areas and from storage tanks will be

from pump houseJloading

treated to meet the regulatory requirement before disposal.

9.4.2.3

Noise Quality

a)

Construction Phase During the construction phase there \Wuld be increased noise The effect will

levels during the day time at the construction site. however be confined to the site only.

b)

Operational Phase During the operation period the source of noise will be the transfer pumps located at Bina and Kota TOP. The impact however, will be restricted to pump house and will not be felt beyond the boundary limits of the terminal.

87
Bharat Petroleum Corporation Umited

Bim - Kolappeline project

Detailed Fea5ibiJty Report

Overall the impact on noise level will be insigniftcant due to the pipeline operation.

9.4.2.4

Soil Quality and land Use Pattern

The impact on soil characteristics

along the pipeline route will be

reversible and negligible. The soil excavated during the trenching will be backfilled with the top soil layer replaced in original condition (without losing its fertility).

The impact on the land use pattern along the pipeline route will be restricted to the extent of Right of Use (ROU). the land will be returned to the owner for original use.

In the forest land the area falling in the ROU will be deared of trees for which compensatory afforestation' will be done in consultation with forest department

Overall. the impact on land use pattern will be mostly reversible except at the terminals.

9.4.2,5

ECOLOGY

Aquatic

The impact on aquatic ecology due to pipeline construction will be restricted 10river crossings. Very marginal impact on minor river crossings is expected due to laying of the pipeline. The impact however is

reversible. The pipeline will be laid across the minor rivers during the dry season to avoid the impact.

88
Bharat PeiroIeum Corporation Umited

Dina - Kola ppe/ine project

Detailed Feasibi6ty Re{Vrt

Terrestrial The Eco-sensitive areas from the point of pipeline project are the conidor passing through the forest land. Impact on the forest land would include cutting of trees falling in the ROU The pipeline route does not pass

through any National Park or habitat of rare or endangered wild life

9.4.2.6 SOCIO-ECONOMICS

The overall impact on Socio-economics of the region will be beneficial in long term. The society will gain in terms of employment during the

construction and operational period and indirectly in terms of improved air qualityltraffic conditions at terminals and along the product movement The

route. The pipeline project will also result in improved road safety.

state will benefit due to saving of fuel consumption and improved product distribution network.

Overall, the pipeline project will have long termed positive impact socio-

or-......,...l"\r-ni,..~I ,

... .... --'i .... , ...,.... .1.

The detail

Environmental

Impact Assessment

(EIA) Report will be

prepared as per regulatory (State Pollution control Board, Ministry of Environment and Forest (MOEF) - New Delhi) requirements. The study would inter-alias inctude the Risk analysis and Emergency Preparedness Plan (OPP) and Environment Management Plan (EMP). Study of impact of pipeline on water bodies and impact on wild life shall be carried out separately.

89
Bharat PetrOleum Corporation Umited

Dina - Kola pipeline project

Detailed Feasibility Report

~
-

'

....
, __ - __ ~ .----c

-. .

,
" )

~
_\ __ -

-""'-.
_...:.0 _~

90 Bharat PetrOleum Corporation Umited


8ina - Kola ppeJine project

Detoiled Feasibility RefXJrt

CAPITAL COST ESTIMATES & FINANCIAL ANALYSIS

10.1.0 GENERAL

Cost estimates

have been prepared

for the selected

option of the

proposed pipeline from Bina to Kota . Facilities considered for Phase-I and Phase-II are as follows:

- Phase-I:

Pipeline from Bina to Kota. VFD Mainline & Booster Pumps at Bina & VFD Mainline pumps at Kota. Intermediate Pigging Station at Ch.130 and 7 SV/CP stations enroute. No

additional tankage is envisaged at Kota.

- Phase-II:

Change of pumps at Bina. Kota and new pump station at existing intermediate pigging station cf MMIPL Ext project at Kaarvadi

Based on the oolimization study. 18" diameter pipeline is found to be most optimal size for transporting petroleum products from Bina to Kota.

Detailed capital cost estimates and the operating cost estimates have, therefore. been worked out and are elaborated in this chapter. throughput Pipeline

of 3.6 MMTPA has been considered for identifying pipeline for all the

sizes whereas throughput of 2.8 MMTPA has been considered balance facilities and cost estimates.

The total capital cost of pipeline from Bina to Kota

is estimated at Rs

384.62 aores including a foreign exchange component of RS.31.55 crores at April. 2007 price levels. The costs excludes Financing charges and

margin money for the working capital.

The detailed break up of cost under each item of work along with summary of estimates has been given in accompanying
Bharat Petroleum Corporation Umited

Tables 1,2.3,4,5 and 6

.
91

Oina - Kola ppe!ine project

Detailed Feasibility Rep:xt

The operating cost of the pipeline is estimated at Rs 1600 crores annually (Refer Table 7)

10.1.1BASIS OF COST ESTIMATES

Basis of Costing

Cost estimates for various items of work are based on the physical requirements set after preliminary engineering. Last awarded rates for Manglya - PiyalalBijwasan pipeline project and offers received for Vadinar - Bina pipeline project under execution suitably adjusted for time period and capacities have been utilised for costing. For major items budgetary offers have been obtained from several vendors.

Pipeline

RiQhtof Way Compensation

An 18 M wide Right of Way is proposed to be acquired along the entire cross country route of pipeline except in reserved forest areas where 7 M wide right of way shall be acquired. ROW compensation at 30% of cost of land has been

provided, along with crop compensation for one season.

..
)

An 18- M wide ROU is proposed to be acquired along the entire route.

For

calculating ROU land compensation, land cost has been assumed as RS.2.3 lacs per hectare in Madhya Pradesh and Rs. 3.0 .lacs per hectare in Rajasthan as estimated for survey contractor. V\lhile calculating crop compensation, rates assumed for cultivable land are Rs 1500001- per hectare and for barren land as Rs 25000/- per hectare.
Bharat Petroleum Corporation Umited Bina - Kota pipeline project
92

Route Survey & Investiqation

This includes the cost for route survey, soil investigation and soil resistivity survey along the pipeline route as well as hydrological surveys of 4 major river crossings

II

Line Pipe

Line pipe of specified grade has been considered to be imported for working out cost estimate and is also based on budgetary quote received. Following rates have been adopted:

18" API5L X-65 - Rs 46850f-excIED

and Sales Tax

Tonnage of MIL pipes for Bina - Kota - 19400 MT

III

SectionalisingValveStations

The sectionalising valves to be installed on the main pipefine are through condUit ball valves to API-6D standard. motor-operated from Bina to Kota In all there are 7 sectionalising valves and all are

Cost of bulk materials like piping electrical & instrumentation civil WofKs at these stations have been estimated on factor basis.

IV

Line Material

Line materials such as LR bends, insulating joints, flow-tees and scraper traps have been estimated based on MTO and in-house cost data.

Coatingand Transportation 93
Bharat petroleum Corporation Umited Bina - Kota pipeline project

Detailed

F<>...aslbtlityReport

The underground portion of the pipeline is proposed to be coated with PE coating

Coating cost has been taken as Rs 10.6 lacs per Km which is based on budgetary quote.

Cost also includes the transportation of Bare pipe from port to coating yard and for coated pipes transportation from coating yard to Dumpsites.

VI

MainPipelinelaying

The total pipeline route has been classified as per soil strata, i.e., normal, rocky and steep ghat. All major/minor rivers and road crossings are assumed to be carried by open-cut method except Betwa river and Nationai Highways(NH). Betwa river is National

proposed to be crossed by Horizontal Directional Dri/ling(HDD) method.

highways / Railway crossings are assumed to be executed by cased crossing by jacking/boringlllt:u ,00.

Laying cost has been based on earlier recently executed MMIPL Ext project escalated with time.

VII

Telecommunication

Optical fibre communication

system has been considered based on MTO

which

broadly includes OFC (12 fibre), SlM-1 and associated facilities.

Optical fibre cable (12 fibre single modecorrugated steel tape armoured 265 KM

Cost of above facilities including mandatory spares has been estimated based on Budgetary quotes.
94
Shamt Petroleum Corporation Umned Bina - Kola pipeline project

Detailed Feasibility Report

Cost of the above system has been estimated based on budgetary quote

VIII

SCADA & APPS

For monitoring and control of the pipeline, cost of following facilities has been considered in the cost estimate:

Remote

work

stations

at Sina and

Kota and

future

previsions

for

Intermediate Pumping Stations at Kaarvadi Remote Telemetry Units (RTUs) at all SV/IP stations SCADA and Application Software Package

Interface of SCADA I APPS system with existing system provided for Manglya - Piyala pipeline project

Cost of the above system has been estimated based on budgetary quote.

IX

Despatchstation & Kota TOP

Equipment Major items considered at various stations are as below:

VFD Mainline & Booster pumps at Bina Despatch station Corrosion Inhibitor dosing pumps and associated facilities at Bina and Kota Scraper Receivers I Launchers Basket filters Metering facilities .

Cost of augmenting the facilities has been considered at Kota.

No additional

tankage is envisaged at Kota as on!y heart cut product will be taken at Kota. 95
Bharat Petroleum Corporation Umited
Bina - Kola pipeline project

Delailed Feasb7ity Report

Pump house and HT sub-station have been considered to cater to intermediate pump station for the purpose of costing

Bulk Materials

Piping, Electrical and instruments items cost for each terminal has been estimated on the MTD worked out and inhouse cost data.

Civil & Mechanical works

Cost provision for all civ~ works at all Terminals IStations have been estimated based on MTDI Area. At other stations, it has been provided on factor basis.

Mechanical works like erection of equipment, piping, electrical & instruments have been estimated on factor basis.

XI

Design Engg, Procurement, construction supervision

The works of detailed engineering, procurement and construction supervision will be entrusted to a consultant. BPCL's in-house management costs towards

salaries, wages of the staff assigned for this project and other administrative expenses like ren~, travel, communication, offICe establistvnent, at various

construction sites are provided on factor basis .

XII

Contingency

A contingency provision of 2.5 % has been made in the cost estimates. 10.1.2 Exclusions

96
Bharat Petroleum Corporation Um~ed Bina - Kola pipeline project

De/aiiaf Feasibility Report

The cost estimate excludes the following. Margin money for working capital Escalation cost beyond May'2007 10.1.3 INDIRECT COST

Indirect cost like ocean freight, custom duty, excise duty, sales tax, iniand handling
& transportation, have been estimatedat prevailing rates given below.

Ocean freight

- line pipe $ 75/MT - Other materials/eqpt 6% of FOB cost 34.1307% of CIF cost (incl.3 % Education cess) 1648%( incl. 3% Education cess)

Custom Duty

Excise Duty

C.S. Tax I VAT Port handling

'lot.

2%

Inland handling Work Contract Tax Insurance

5% 4% 1%

10.1.4 EXCHANGE RATE

1 US$ = Rs. 42.2

10.1.5 ANNUAL OPERATING COST Basic parameters considered for working out the annual operating cost are as under: Corrosion Inhib~or Rs 4.5 lakh/MT

97
Bhara! Petroleum Corporation Limned Bina - Kola pipeline project

Detailed Feasibility Report

Power

Rs 5/KWHR

Misc. (Diesel, oil etc)

Lumpsum

Salary wages:

Rs. 10 lakhs p.a.lperson

Manpower ( Pipeline operations) Bina Kota 10 10

No. of persons

Operating hours

8000

Repair & Maintenance

Pumps Pipeline CivilWorKs

3% 1% 2.5%

10.1.6 EXCLUSIONS

ATF tankage cost at Piyala.

98
Sharal Petroleum Corporation Limited Bina - Kota pipefine project

Detailed Feasibility Report

10.1.6 PROJECT PROFITABILITY

The profitability of the proposal under a free market scenario has been worked out under different scenarios and the basic assumptions are as follows :-

Construction period Commissioning Interest rate on loans The debt equity ratio Repayment installments Moratorium for debt Repayments Project Life

24 + 3 months 3rd year, 2010-11

11 %
2:1

12
2 years after commissioning of

project for loan repayment 15 years and the residual value of the project has been considered at 5% of capital investment

Operating cost Corporate Tax Book depreciation

Rs.61.00 per MT (approx.) 33.66% 4.75% per annum, straight line method (SLM) on plant and machinery.

The interest during construction of Rs. 21.2 crores will be funded through debt and will be capitalised. The project will be financed by equity contributions first and then through debt.

Project revenues have been calculated considering a tariff of 70% of rail tariff for movement . of products through Bina - Kota pipeline. Based on this cost benefit analysis, earnings to the tune of RS.121 crores on the estimated throughput of 2010-11 are envisaged, which shall be the revenues for this Project. (Refer Annexure II for details.). The throughput for the commissioning year i.e., 2010-11 has however been coflsidered at 75% of actual volumes.
99
Bharat Petroleum Corporation Limited
RinA - Kola oioeline Draiect

Detailed

Feasibility

Report

On the basis of above, the profitability of the project is as below: IRR on Fixed Cost Basis: The IRR for the project on the total capital cost of Rs 405,82 crores is 19,53% based on the present revenues generated on pipeline transportation and the minimum cost of the project IRR worked out for the following sensitivity cases

considering differential project cost and revenues generated are tabulated below:

I Sensitivity

cases Increase In ro ect cost b 10%

fIRR
17,94 % 16,07 %

Revenues generated from pipeline operations with a tariff of 60% instead of 70%,

IRR on Completion Cost Basis: The IRR based on the completion cost of Rs, 405,99 crore and an IDC of Rs, 22,38 crore works out to 18,60 %,

100
Bharat Petroleum Corporation Limited
Bina - Kola pipeline project

Detailed Feasi/JiMy Re{XJrt

10.2

Conclusion

Based on financial analysis results and their sensitivity analysis, the project is found to be financially viable.

101
Bharat Petroleum Corporation Umited Bina - Kola pipeline project

APPENDIX

-I

BINA

- KOTA

PIPELINE

PROJECT

OPTIMISATION

STUDY

- SUMMARY

OF RESULTS

SL NO.

DESCRIPTION

PHASE ALTERNATIVE 14"

BINA - KOT A SECTION ALTERNATIVE ALTERNATIVE 16" 18"

ALTERNATIVE 20" 23552

(Rs in lacs
1 CAPITAL COST ESTIMATE 2 ANNUAL OPERATING COST

Phase I Phase II Phase I Phase II

22389 6024 646 1350 24855

21462 2063 302 659

21934 1050 140 336

NET PRESENT VALUE

NOTE: 1 2 3 4 OPTIMISATION STUDY HAS BEEN WORKED OUT FOR ALL THE FOUR ALTERNA TlVES. LAND COST HAS NOT BEEN CONSIDERED. POWER HAS BEEN ASSUMED TO BE AVAILABLE AT BAITERY FOR ANNUAL OPERATING COST POWER TARIFF -RS 5.OJKWHR AT ALL PUMPING STATIONS CONSIDERED. MANPOWER & THEIR SALARY & WAGES NOT CONSIDERED. 5 NPV CALCUlATION PROJECT UFE IS DONE BASED ON FOLLOWING PARAMETERS: - 35 YEARS COSTRUCTION PERIOD - SCHEDULE OF 24 MONTHS PUMP LIFE - 15 YEARS (pUMP REPLACEMENT COST CONSIDERED DURING 15TH & 30TH OPERATING YEAR) 6 PHASING OF EXPENDITURE TAKEN AS 1ST YEAR - 15% 2ND YEAR - 50% 3RO YEAR 7 ) 35% COST OF COMMON FACILITIES AS SHOWN IN EXCLUSIONS BELOW HAVE BEEN EXCLUDED FROM THE COST ESTIMATE . LIMIT.

,
0
I

f,Nft L

f~ .. IYlJ>tJeT

<5Ul

T!:

PRODUCT AVAILABILITY

FROM BINA REFINERY

~
PRODUCT QTY. (TMTPAj

LPG
,

Naphtha Euro III MS Euro IV MS

234 272 385 400 441 500 . 1871 1000 109 103

SKO
ATF

Euro III HSD Euro IV HSO Sulphur Surplus Coke

, . ,

I
I

Sharat Oman Refineries LId Sjna Refinery Project . Revised Configuration Study ANNEXURE:1

Final Report 6540-02-41-PS-001,Rev-C

-~~~~--~~~----_._--_.

INDIAN PETROL SPECIFICATIONS REQUIRED TO MEET ERUO-III EQUIVALENT EMISSION NORMS Sr. No. Characteristics Unit Requirements Unleaded Regular Oranqe 720-775 10-45 40-70 75 min. 210 2 91 81 5 360 150 0.005 60 750
O~n ';';...J\J

i. 2. 3.

4. 5. 6. 7. 8. 9. 10.

Colour, visual Density @) 15"C Distillation: a) Recovery upto 70C (E 70) b) Recovery upto 100C (E 100) c) Recovery upto 150C (E 150) d) Final Boiling Point (FBP), mal<. e) Residue, max. a) Research Octane Number (RON), min. b) Motor Octane Number (MON), min. Gum content (solvent washed), max. Oxidation stab~itv, min. Sulphur, total .1TlaX. Lead content (as Pb),max. Reid Vapour Pressure fRVP), mal<. Vapour Lock Index (VU) a) Summer, max..
b) Ot.her -lIl0riftS. max

kQ/m' % volume % volume % volume c % volume

Unleaded Premium Red 720-775 10-45 40-70 75 min. 210 2 95 85 5 360 150 0.005 60 750 950 1 Class 1 18 42 2.7 3 5 10 10 7 . 15 8

m<li100 ml minutes
I1lQ/I<Q

g/J kPa

11. 12. 13. 14. 15.

I
'-

Benzene Content. ITlaX. Copper strip corrosion for 3 hrs: @ SOUC, . max. Olefin content, max: Aromatics content, max. OXygen content, max. Oxygenates Content : a) Methanol, max. b) Ethanol, max. c) lso-propyt alcohOl, max. d) Iso-bytyl alcohol, mal<. e) Tertlary..butyt alcohol, max. f) Ethers containing 5 or more carbon atoins per molecule, max. Q) Other OxvQenates, mal<.

% volume
rating

. 1 Class 1 21 42 2.7 3 5 10 10 7 15 8

% volume % volume
% mass

% volume
.

% volume

% volume % volume % volume % volume


% volume % volume

ENGINEERS INDIA LID NEW DELHI

Bina Refinery Project Revised Configuration Study


---~----------------_

6540-02-41-PS-001,RtN-C

..

ANNEXURE:2 INDIAN PETROL SPECIFICATIONS.REQUIRED TO MEET EURO-lV EQUIVALENT EMISSION NORMS Sr. No. Characteristics Unit Requirements Unleaded Regular . Orange 720-775 10-45 40-70 75 min. 210 2 91 81 5 360 50 0.005 60 750 950

i
!

- I
I

,
'

, ,

Colour, visual Density @ 15uC . DistiDation : a) Recovery upto 70C (E 70) b) Recovery upto 100DC(E 100) c) Recovery upto 150DC(E150) d) Rnal- Boiling Point (FBP), max. e) Residue, max .. 4. a) Research Octane Number (RON), min. b) Motor Octane Number (MON). min. 5. Gum content (solvent washed), max. 6. Oxldation stability, min. 7. Sulohur, total, max. 8. Lead content (as Pb), max. 9. Reid Vapour Pressure (RVP), max. 10. Vapour lock Index (VLI) a) Summer, max. b) Other months, max 11. Benzene Content, max. 12. Copper strip corrosion for 3 hrs. @ 5OuC, . max. 13. Olefin content, max. 14. Aromatics content, max. 15. Oxygen content, max. . Oxygenates Content: a) Methanol, max. b) Ethanol, max. c) lso-propyl alcohol, max. d) lso-bytyl alcohol, max. e) Tertiary-butyl alcohol, max. f) .Ethers containing 5 or more carbon atoms per molecule, max. g) Other QxvQenates, max. 1. 2. 3.
.

kgfm"

Unleaded Premium Red 720-775 10-45 40-7D 75 min. 210 2

I
,

% volume % volume % volume


DC

% volume

95
85 5 360 50 0.005 60 750 950
1

mq!100 ml mi!'lUtes l1'lQ/kQ

. .gn

kPa

% volume
rating

Class 1

Class 1 18 35 2.7 3 5 10 10 7 15 8

% volume % volume % mass % volume % volume % V{)lume % volume % volume % volume % volume
% volume

21
35 2.7 3 5 10

10
7 15 8

ENGINEERS INDIA LTO

NEW DELHI

'.

. Sharat Oman Refineries lld . Bina Refinery Project Revised Configuration Study

Final Report 6540-02-41-PS-001,Rev-C

ANNEXURE:3 INDIAN DIESEL SPECIFICATIONS REQUIRED TO MEET EURO-III EQUIVALENT EMISSION NORMS Sr. No.
1.'

Characteristics

1--

Unit % mass % mass

Requirements 0.01 0.3 without additives 51 46 360

2. 3.
4.

5.

, 6. 7.
8. 9. 10. 11,

Ash, max. Carbon residue (Ramsbottom) on 10% residue, max. Celane number (CN), min. Cetane Index (CIl, min. Disbllation ; 95% vol. Recovery at DC, max. Flash point: a) Abel, min. Kinematic viscosity (Q) 40uC Density @l15"C Total sulphur, max .. Water content, max. Cold fdter plugging point (CFPP) a) Summer, max. b) Winter. max. Total contaminations, max.

"C

DC cst

kglm'
maiko

35 2.0-4.5 820-845 350 200 18 6 24


?l:;

DC DC mg/kQ glm' % mass microns rating

12.

,.,

Oxidation

S+.abi!!t--J.m2.X..

14. 15. . 16.

Polycylic Aromatic Hvdrocarbon IPAH), max. Lubricity, corrected wear scar diameter Iwsd 1,4\ (a) 60DC. max. Copper strip corrosion for 3' hrs . @'! 50C. max. ...

11 460 Class-1

J
ENGINEERS INOlA LTO NEW DELHI

, ,

, Bharat Oman Refineries Ltd Bina Refinery Project Revised Configuration Study

Final Report 6540-02-41-PS-D01,Rev-C

ANNEXURE:4 INDIAN DIESEL SPECIFICATIONS REQUIRED TO MEET EURO-IV EQUNALENT EMISSION NORMS Sr. No. 1.. 2. Characteristics Unit Requirements 0.01 -0.3 without additives 51 . 48 360
. .

Ash, max. Carbon residue (Rams bottom} on 10% residue, max. Cetanenumber (CN), min. 3. Cetanelndex (CI). min . 4. 5. Distillation: 95% vol. Recoverv at C, m= 6. Flash point: a} Abel, min. 7. Kinematic viscosity @ 40uC 8.. Densitv (cj) 15"C 9. Total sulohur. max. 10. Water content, max; 11, Cold filler plugging point (CFPP) a} Summer. max. b) Winter, max. 12. Total contaminations. max. 13. OxIdation stability, max. 14. Polycylic Aromatic Hydrocarbon (PAH). malL 15. Lubricity. corrected wear scar diameter (wsd 1,4}@60oC. max. 16. Copper strip corrosion for 3 hrs. (cj) 50oe, m= .
.

0/0 mass
% mass

"C

..

c cst kalm' JTlQ k<:! mQ/kg c

35 2.0-4.5 820-845

50
200 18 6 24 25 11 460 Class-l

c
mq/k<:! Qlm' % mass microns rating

I ,

!
I

I I

ENGINEERS INDIA LTO NEW DELHI .

, 8hara1 Oman Refineries Ltd Bina RefineriesProject

Fanal Report 654()''''()2-41-PS-001--Rev-C ---~---~

Revised Conflguration~St>t'uJ~d~y

---

ANNEXURE-5 (1 OF 1)

LIQUEFIED PETROLEUM GAS (LPG) DOMESTIC GRADE

TEST

METHOD

SPECIFICATION

Vapour Pressure @ 4D'C, KPa

0: 1267

Max. 1050 (152 psi)

Free-Water

VISual

Nil

.. .. ..

Hydrog~," Sulphide, pprnw (1)

0:2420

Pass

Mercaptan sulphur. ppmw (2)

IP: 272

Max. 150

Copper Strip Corrosion (Bomb) 1 hr. @ 38"C

0:1838

Max. No.1 Strip

Volalility : Evaporation Temperqture for 95%v, "C

D:1837

Max. 2

Note: . 1) "Pa5$" test indicates Hydorgen Sulphide not more than 5 ppm.

2>"

Product shaA contain minimum 10 ppm Mercaptansw as Sulphur at the first despatching location to ensure the detection of odour. .

- I
,.

.. \

I
CONFIDENT1AL:Properiy of ENGINEERS INDIA l TO. To be used or reproduced E'NGINEERS INOlA l TO.

only willi !he permlssloo of

~ ..__ . "'- Revised Conflgl)fBOOrl SWdy

ANNEXURE - 6 (2 OF 3)

TEST
DlstlMation:
{!oj

METHOD
P: 18

SPECIFICATION

IBP, 'C 10% V reco .. ered @ C 50% 00%


V \I

To be reported Max.. 205 To be reponed To be reported Max 300 Max. 1.5 Mclx. 1.5
(61

recovered @ C recovered @ C

FBP, 'C Residue, Ofov

loss, %v Water Separation Index Modified (WSlM) Thennal StabIlity (JFTOT) (1l Finer Pressure DiffeJential. mm Hg Tube Rating, VlS\I3I P: 142 P :97

Min. 70

Max. 25.0 Less than 3, no .Peacock' or

Abnormal Colour Deposits Anti-Oxldant (Actlve ingredient) mg/Ii1Ie ~l


Max. 24.0

.,
Metal Deactivalor (Atlive Ingredient), mgJIilre ", Antl-S1allcAddltIve S1adls 450 mgIIilre ("l Max. 0.7
Max. 3

.,

Eledrical ConductMty of Doped Fuel, piro-sjemensImeter lubricity

ASTM 0 2624

Mln.EO
Max. 450

ASTM 0 5001

Max- 0.85 #

CONFORMS TO BIS SPEC IS:1571-2OO1 and OEFSTAN 91-91nSSUE 4 # The requJrementlodelBm>ine lubricily as per IS 1571-2001 appf>es only to ATF containing more than 95% hydrnprocessed maIeriaI where a1leasl2O% of1h:s Is severely hydro processed. Defence requirement to be met at 0.65 mrn. Max. To meet this requirement. approved Lubridly AdditNe as mentioned In 4.2.4 of 1S:1571, 200110 be added by appropriate agency before being Inducted into 1he aircraft NOTES: 1) Clear, bngtlt and free from sorld matter and visually undissolved water at nom1al embient temperature. 2) Sharp separatlciri no emufslon or predpIlat<>, wilhinor upon either Iayer_ .' 3) Defence requirements to be met al22 pen::ent by volume maldmum and at 20 percent by volume, max for defence alrt:rafls filI1!<l with eogIne of n=lan origin. 4) Calculala tI1eAPI g,...;ty tom the de!emjned DegreesAPI~ 60160 "F speclflc gi-av;ty as lOlkrNs-

141.5 -131.5 Sp. Gr. 60/60 'F Determine .AnTfDla Point F then Aniline Gravity Product ~ API Gravity x An~ne Polnt "'r
I

J
CONFlDENTlAL:P",,,,,,y of ENGINEERS J>IOlA L 11). To be .-. ENGINEERS INOlA L11).
Of _

rrly _

!he ""' , of

ANNEXURE

- 8 (3 OF 3)

5) A Condenser bath temperature

of 32 to 4Q F (O to 4 AcC)-s-h-a-H-b-e-u-se-d-.-----------c

-.-

~-----

6) If anti-static additive Is not present in the fuel, the WSIM shall be 85 min . . 7) The test, shan be carried out under the foflowing Maxlmum heater ~ubetemperabJre Fue{SystemPressure conditions 260"'C 3.45 M.Pa

Fuel Row Rate 3.0 mVminute Test Duralion 150 minutes For Tube rating, VlSuai shan be the" refree method in cases of cflSpute.

8)ANTI-O~DAJ<TS
Min. 17.0 mgIIitre of anli-oxldant shall be added to the product intended for blending with -hydrogen For fuel (orfuel component) which has not b~n hydrogen treated, such addition is optionaL t~ted' fuels.

,
,

The foIlowlng anti-mddants ere approved : a) ~6-~~~rn b) ~6 - dllertiary-butyl--4-methy1-pheno1 c) ~4 - lfll11elhyl-6-ter1iary-butyl-p/1enol d) 75 percent mIn. 2.6 - ditertJary-bulyl-phenoi 25 percentl11al(. tertiaJy and lritBItlaty-butyl-phenols e) 55 percent mln,2.4 - d1melhyl-6-ter1iary-butyl-phenols 15 percen~ 4 - melhy\-2. 6 - diler1iary-butyl-phenol \Nith the remalnder a IJ1iX1uIs of mooomelhyl and dimelhyl-tel1iaenols. The amount and nature of the anll-oxfdao(s) so added. shall be stated on the quaIIy cerlI1lcates. f) A rn/XIlJIeof 72% minimum. 2,4 lfurethyl-&-1;ertiary-butyt phenol 28% minimum. mixtJJre of tertiary.butyl-methyl phenols and lertlary-butykfunelhyl phenols. 9) METAl DEACllVATOR The following metal deactivator Is approved : "'.'" - d'~a. 1.2 - llfOI)alle<fl8!tina The amo<ml of the metal deadivalor so added, stlaU be slated on lhe quaiity certiflC8teS. 9) STATIC DlSS1PATORADD1TNE (SDA) The lolowing SOA are approved : Shell An_ additive ASA 3
Dupont stadis 450

Max. 1 rrgIIt

Max. 3 rrgIIt

,
.
)

;;
~
) )

I
~ of9lGlNEERS _l;o. To be used '" reproduced oolywllh the ~ ENGINERS INOlA lTD. of

,
>

:;

,
)

: 01101;:;. Utlldll

r-t::lllllt:'llt:3

L~U

, "ror

r'\Cp'--"t

Bina Refmeries Project

654Q-D2-41-PS-001-Rev-C

Revised Configurafron Study

ANNEXURE

- 9 (1 OF 1)

SUPERIOR KEROSINE
,

, I ,

TEST

METHOD

SPECIFICATION

~I ,

Acidity. inorganic Buming Quality : a) Char value. mWkg of oil consumed b) Bloom on glass chimney Colour (Saybolt), Copper Strip corrosion for 3 hrs. at 50C

P:2
P:5

Nil

Max. 20 Not darker than grey

P: 14.
P: 15

Min. +10 Not worse than No.1

, .,

Distillation: a) Percentage recovery b) Final boiling point,OC Flash Point (Abel), C Smoke Point, mm. Total Sulphur, %wt.

P: 18
below 200C Min. 20 Max. 300

P :20
P: 31
P : 34/ ASTM 0:4294

Min. 35

Min. 18' Max. 0.25"

Conforms to BIS : 1459 - 1974

For supplies of Defence & railway signal lamps, smoke point of the product shall be minimum 22 mm. Under the emergency IS Specifications for kerosene, smok.e point for general supplies has been relaxed to minimum 18 mm . For supplies to Defence, total sulphur content percentage by weight of the product

shall be 0.20 max.

.;

1
CONFIDENTlAL:Property

-I ",
,

of ENGINEERS INDIA L To be USed or reproduced onJy wi1h the permission 'of ENGINEERS INDIA L

m.

m.

Detailed Feasibility Report

) )

103
Sharat Petroleum Corporation Um~w Bina - Kola pipeline project

.
1: \,.~.C!\~~:

ESTIMATED

PROJECT

COST:

BINA . KOTA SUMMARY

PIPELINE

PROJECT

SHEET

jPROJECT:

BINA - KOTA PIPELINE

,
SU~Y SNO CRIPTION All FX COSTS ARE IN RS LAKHS RS SC TOTAL

J
A PlIANT & MACHINERY 1 BINA DESPATCH 2 INTERMEDIATE 3 KOTA RECEIPT 4 KOTA DISPATCH 4 PIPELINE SUB TOTAL (A) UNIT PIGGING FACILITIES FACILITIES STN. AT CH. 130

1081 94 83 1005 816 3078 @5.0% @4.0% 3078

1399 348 245 957 11937 14886 1725 1380 17990 excluded

561 218 257 251 15243 16530

3041 rypE OF ESTIMAT 660 PRELIMINARY 584 ESTIMATE 2213 27996 34495 1725 1380 MAY. 2007 AS ON

B DESIGN, ENGG. & SUPRV.


C OWNER MGMT. EXPNS.

SUB TOTAL (A+B+C)

16530

37599

START UP & COMM. SUB TOTAL (A+B+C+D)

E CONTINGENCY SUB TOTAl (A+B+C+D+E)

@2.5%

77 3155

372 18362 excluded

413 16944
-

862 38462

F WORKJNG CAPfTAL MARGIN


SUB TOTAL (A+B+C+D+E+F) G FINANCING CHARGES

,-

I I
excluded

SUB TOTAL (A+B+C+D+E+F+G) TOTAl COST 3155 18362 16944 38462

Table 2
PROJECT: BlNA - KOT A PIPELINE

PIPELINE ( 18" - 265 Kmsl


SNO DESCRlPT10N ALL COSTS ARE IN RS LAKHS FX A MAJOR ITEMS RS SC TOTAL

ROUTE SURVEY, SOIL INVESTIGATION, HYDROLOGICAL SURVEY FOR RIVER CROSSINGS, 1 ETC 2 ROU & LAND ACQUISITION 3 LINE PIPE(19lO MT) tee, LR bends, 29 8555 29 B555 2809 183 566 474 40 23273 US$-Rs422 B INDIRECT COSTS 1 OCEAN FRT. & CUSTOM DUTY 2 PORT HANDLING 3 EXCISE & SAlES 4 SERVICE TAX 5 ~ORK CONTRACTS 6 INSURANCE SUB TOTAL (B) SUB TOTAL (A+B) [TOTAL COST TAX & INLAND FRT. TAX 46 0 278 0 0 325 CUSTOM DTY=34.1307% NOTES ESTIMATE AS ON MAY. 2007 PRILIMINPRY 186 928 186 92B 9OB9 TYPE OF ESTIMATE

9OB9

LINE MA TERIAL(flow 4IJ's) 5 LAYING

6 COATING & TRANSPORTATION 7 CATHODIC 9 SCADA PROTECTION SYSTEM


.

2809
46 377 364 82 210 9427 137 108 109 245 13076

8 O.F. TELECOM

10 S V STATIONS
SUB TOTAL (A)

0
770

n
1883

n
1616

EXCISE DUTY =16.48% TAX=3% 4%

a a a a
46 816 816

a
1616 551 0 2167 15243 15243

1883 SAlES

a a
277 2510 11937 11937

551 WCTAX=4% 277 SERVICE TAX=12.36% 4729


.

27996 27996

Table 3
PROJECT: BINA - KOTA PIPELINE

,.

BINA DESPATCH UNIT SNO DESCRIPTION A MAJOR ITEMS 1 MAIN LINE VFD PUMPS 2 BOOSTER 3 BASKET FILTERS 4 SCRAPPER LAUNCHER 5 C I DOSING PUMP 6 CI DOSING TANK-SS SUB TOTAl (A) B BULK MATERiAlS PIPING 2 ELECTRICAl 3 INSTRUMENTATION SUB TOTAl (B) C SPARES SUB TOTAl (C) SUB TOTAl (A+B+C) ALL COSTS ARE IN RS LAKHS FX RS SC TOTAL 800 24 0 5 5 34 350 280 65 695 13 13 742 0 0 200 130 70 400 0 80
.

,,

800 75 0 8 0 883 100 15 115 22 22 1020

75 24 8 5 5 0 917 450 280 80 0 810 35

TYPE OF ESTIMATE

PRILlMINARY

ESTIMATE AS ON MAY. 2007

NOTES

35 US $ - Rs 422
-

1762 CUSTOM DTY=34.1307% EXCISE DUTY =16.48% 200 SAlES TAX=3% 130 WCTAX=4% 70 SERVICE TAX=12.36% 400 0 80 2242 430

0 ERECTION
1 MECHANICAL

2 ELECTRICAl 3 INSTRUMENTATION SUB TOTAl (D) E lAND F CIVIL WORKS SUB TOTAl (A+B+C+D+E+F) G INDIRECT COSTS 1 2 3 4 5 6 OCEAN FRT. & CUSTOM DUTY PORT HANDLING & INLAND FRT. EXCISE & SALES TAX SERVICE TAX WORK CONTRACTS TAX INSURANCE SUB TOTAl (G) SUB TOTAl (A+B+C+D+E+F+G) 61 1081 1081 61 369 110 148 1020 742

480

, ,
,

0 0 59 22 81 561 561

110 148 59 22 30 799 3041 3041

30 657 1399 1399

, ~,

TOTAl COST

Detailed Feasibility Re{XJrt

cable shall be as per G.652 specifications.

The cable shall be fire

retardant, chemical resistant, termite & rodent proof and moisture proof

a2)

OPTICAL FIBRE CABLE LAYING The optical fibre cables shall in general follow the pipeline route. The cable shall be laid directly in the pipeline ROW in the same pipeline trench at the pipeline bottom level. The cable shall be laid -500mm away from the pipeline edge.

b)

OPTICAL TRANSMISSION EQUIPMENT


/

STM-4 system in (1+1) configuration

on the main line (1st Tier)

connecting Bina to Kota and other stations as required based on link calculations and future connectivity.

The above equipment shall include interfaces (opticaVelectrical) and tributary cards.

Primary reference clock (cesium non-duplicated) shall be used for synchronization of transmission equipment

c)

Primary/Drop-insert Multiplex Equipment

The multiplex equipment shall be based on PCM-TOM technology. The equipment shaD interface to the input side with Voice and data circuits and shall interface with optical transmission equipment at the output side. The 011equipment shall provide direct access to time slots required for drop and insertion without resorting to

bringing all the channels to base band level and shall also allow through passage of signals if Oropllnsertion is not required at the repeater. 65
Bharal PffiOleum Corporation Umited

B/na - Kota fipelJne project

Derailed Feasibility RefXJfl

Acoustic booths shall have polyester powder coating

The acoustic

booth shall be mounted on a floor mounting type steel pole and shall house the explosion proof telephone set Equipment shall be provided with howlers.

j)

Facsimile

Equipment

The equipment shall conform to CCITT recommendation T-30, v.27 ter G2, G3 mode. It shall be connected to electronic telephone It shall be designed to transmit

exchange to provide dialing facility.

7.5

charts/messages

of upto A4 size .

POWER SUPPLY SYSTEM

7.5.1 Electrical Distribution system

The electrical

distribution

system for various manned and unmanned

stations along the Bina - Kola Product Pipeline shall be as follows :

7.5.1.1 Bina Despatch Terminal

i)

It is assumed that total power requirement of approx. 3.5 MW ( indo 2 MW for Bina Dispatch facilities) will be met from refinery CPP. The power shall be provided from the four Pole structure of CIR-

cpp to HT Breaker /4 pole structure of Bina Dispatch Terminal by


an

IVG or UIG cable.

ii)

The power distribution system is backed up at 33111 KV supply from MPSEB and suitable arrangements exist to ensure

uninterrupted

/continuous

power to the Bina Dispatch Terminal

either from main power CPP or from MPSEB.

68

Bharat Petroleum Corporation limited


81m - Kota ppeline project

Detailed Feasibility Report

iii)

An outdoor type transformer of 4 MVA capacity shall be provided for stepping down the voltage from 331 11 KV to 6.6 KV for pipe line transfer immersed The transformer shall be 3 phase, double wound, oil

ONAN cooled type with cable connection terminals on

the HV/L V side conforming to IS2026 (part I to part IV)Mainline pumps will be fed from 6.6 KV switchboard started.

iv)

Motors

upto 751<VV shall be connected

to contractor-conlrolled

starter feeders of Power-cum-Motor Control Centre.

v)

1 No. 125 KVA DG set shall be provided with AMF facility to take care of emergency loads, Critical such valves, as Air SCADA, TELECOM, C ..P.

INSTRUMENTATION,

Conditioning,

System, Fire alarm system and jockey pump. Possibility of utilising the existing DG sets at Manglya shall be explored.

vi)

110V lead-acid battery banks along with battery charger shall be provided to meet the DC power requirements meant for switchgear control and critical DC lighting etc. and instrumentation loads.

vii)

1 Nos. -230V AC UPS with lead-acid battery back-up shall be provided meeting instrumentationJtelecomlSCADA requirement

viii)

48 V DC & 24V DC rectifiers shall be provided & fed from230V UPS to feed DC requirement of Te/ecom & Instrumentation

respectively.

ix)

415 V PMCC

shall be provided

for feeding to UPS, battery

chargers, lighting system CPTR units and aR other auxiliary loads like welding receptacle, power panels etc. -

69

Bharat Petroleum Corporation Umited


81/lil - Kola fipe/ine fK"Oject

Detailed Feasibtlity RefX'rt

x)

Break glass fire alarm point shall be provided at strategic locations along the escape route and smoke detectors in the sub-station and control room. The fire alarm system shall be controlled by the main fire alarm panel
0

be located at the control room.

7.5.1.2

Intermediate

Pigging Station

i)

It is assumed that 11 KV power supply in Intermediate Pigging Station shall be available from MSEB by single circuit overhead line at 2-pole structure. This shall be stepped down to 433 V level by 1 No. 11/ 0.433KV transformer with off ckl tap changer. Additionally, DG back up of 80 twA shall be provided.

ii)

11/0.433tw transformer of suitable rating shall be provided to meet 415V PMCC for pipeline facilities.

iii)

Motors upto 75 t<W shall be connected to contractor-controlled starter feeders of Power-cum-Motor control Centre. above 75 KW and upto '160 KVYshaii---be--foo'fromACB feeder. LT motor

PMCC through

iv)

Power supply to SCADA, Telecom, Instrumentation, CP system and other critical loads shall be fed through a static vollage regulator to take care off vide voltage variation which may take place in 11 tw system.

v)

415V regulated power will be received at ACDB and shall be distributed.

vi) .

48V DC Battery charger arid Battery bank shall be provided to make the power source reliable.

70
Bharat PelroIeum Corporation limited
Billa - KoliJ pipeline project

Detailed Feasibility Report

vii)

Except AC load, if any, and receptacle all other loads shall be fed from 48V DC.

viii)

Two nos. 48VDC1230 V AC inverter (1 OP +15) shall be provided to feed lighting load and exhaust fans.

ix)

48V DC124 V DC/DC converter shall be provided to feed 24 V DC load.

7.5.1.3

Intermediate

Pumping Station at Kota

i)

It is assumed

that dual feeder

33 / 11 KV power supply at

Intermediate Pumping Station shall be taken from Rajasthan State Electricity Board

An outdoor type transformer of 2 MVA capacity shall be provided for stepping down the voltage from 331 11 KV to 6.6 KV / 433 KV for pipe line transfer. The transformer shall be 3 phase, double wound, oil immersed ONAN cooled type with cable connection terminals on the HV/L V side conforming to 152026 (part I to part IV)Mainline pumps will be fed from 6.6 KV switchboard started.

ii)

Motors upto 75 t<NV shall be connected starter feeders of Power-cum-Motor

to contractor-controlled

control Centre.

iii)

One No. 125 KVA DG set shall be provided with AMF facility to take care of emergency loads such as SCADA, Telecom.

Instrumentation, pump.

C. P. System, Lighting system, Fire Alarm, Jockey

71
Bharal PelrO";um Corporation Umited

8ina - KOlappe!ine project

Detailed Feasibility RefXJrt

iv)

110V lead-acid battery banks along with battery charger shall be provided to meet the DC power requirements meant for switch gear control and critical DC lighting etc. and instrumentation loads.

v)

1 Nos. 230V AC UPS with lead-acid provided requirement and meeting

battery back-up shall be

instrumentationltelecomlSCADA

vi)

48 V DC & 24V DC rectifiers shall be provided & fed from 230V UPS to feed DC requirement of Telecom & Instrumentation

respectively.

vii)

415 V PMCC shall be provided

for feeding

to UPS, battery

chargers. lighting system CPTR units and aU other auxiliary loads like welding receptacle, power panels etc.

viii)

Break glass fire alarm point shall be provided at strategic locations along the escape route and smoke detectors in the sub-station and control mem.The nre-8!8rm system shall. be controlled by the main fire alarm panel to be located at the control room.

7.5.1.4

Intermediate CP/SV/SV-cum-CP

Station

i)

Power supply at all stations shall be arranged from grid at 11 KV through one No. 11/0.433 KV transformer. One No. static voltage to take care wide

"
"
)

regulator

shall be provided

after transformer

voltage variations of 11 KV system.

ii)

415V regulated power will be received at ACDB and shall be distributed.

"
) 72

"
"
)

Bharat Petroleum Corporation

Umited

Dina - Kola ppeline project

"

Detailed Fe.asibility R~

iii)

48V DC Battery charger and Battery bank shall be provided to make the power source reliable.

iv)

Except AC load, if any, and receptacle all other loads shall be fed from 48V DC.

v)

Two nos. 48VDCI230 V AC inverter (1 feed lighting load and exhaust fans.

or +1 S) shall be provided

to

vi)

48V DC124 V DC/DC converter shall be provided to feed 24 V DC load.

vii)

20 IWA DG sets shall be provided at all SV stations.

7.5.1.5

Broad specification of major equipment 3-phase, double wound, type, oil immersed, ONAN cooled, outdoor type

i)

Transformer

power and distribution transformer as per SLD.

ii)

HV Switchboard

: a)

33 IW indoor type, metal-clad SF6 /vacuum circUit breaker isolator panels.

b)

6.6 KV indoor type, metal-clad switchboard consisting of incomers, buscouplerS provided breakers. and with outgoing feeders drcuit

SF6/vacuum

Hi)

MV Switchboard

415 free standing, metal-clad, dust and vermin-proof in draw outlfixed execution.
73

Bharat Petroleum Corporation Umited


8ill3 - Kola

ppeline project

Detailed FeasibilJly Report

iv)

Motor

TEFC, IP-55, squirrel cage inductions motors with space heaters for motors rated above 30 .,0N

v)

DC System

100% redundant, float-cum-boost battery charger with battery back-up for manned station and nickel-cadmium

battery back up for unmanned stations.

vi)

UPS

230V, phase dual redundant UPS with bypass circuit and ACDB and lead-add battery back-up for 30 min.

vii)

NGR

Punched grid stainless steel, neutral grounding resistor, having voltage rating

at 6.6 1 33K\/---rated fur-apprepri~t&ea:t"';


fault current for 10 seconds.

vii)

Diesel Generator

125KVA Diesel Generator to only feed the emergency load in the event of power failure.

7.6

CATHODIC PROTECTION SYSTEM

7.6.1 IntroductIon

For the proper functioning of cross-country pipeline system, both from the safety and economy points of view, the pipeline must be protected against corrosion which is a potential danger to the health of the pipeline. External pipeline protection will be a combination of corrosion coating and cathodic protection techniques. Suitable coating is proposed for the buried 74
Bharat Petroleum Corporation Umited
Dim - Kota pipeline project

Detailed Fea5ibility Report

pipeline.

The proposed pipeline shall be cathodically protected by an

Impressed current CP system as a permanent facility.

During the construction phase, the pipeline will be protected by temporary cathodic protection using sacrificial anodes, with a design life of 2 years. Permanent cathodic protection system for the pipeline shall be by

impressed current method, with a design life of 35 years.

Necessary crossings

measures

to mitigate stray

current

interference

due to

of high tension lines, electrified railway track and existing

pipelines in the close vicinity shall be specified.

7.6.2 System Description

Salient features of the cathodic protection system proposed for the

pipeline are described below :

7.6.2.1Temporary

cathodic protection USing magnesium sacrifidal anodes shall

be provided for the constnJctjon pnase. The design iife of the temporary CP shall be 2 years.

7.6.22Permanent

cathodic protection system of the pipeline shall be by

impressed current method. The design life of pcp shall be considered 35 years.

Necessary

measures shall be adopted to mitigate the stray current

interferences due to crossing of high tension line, elec1rilied railway track, existing pipeline in the close vicinity etc. by providing grounding cells , diodes etc.

The location of these stations shall be selected in such a manner that the entire line would be adequately protected.
Bharat Petroleum Corporation

Wherever an SV station or 75

Umited

Bina - Kola pipeline project

Detailed Feasibility Report

Telecom repeater station happens to be located, the CP station shall be made to coincide with it to avail the common reliable power source and SCADA system. However, IT required, at places other than SV Stations

CP Station with RTU shall be provided.

At the cased crossings, cathodic protection shall be provided. The casings shall be uncoated.

All major river crossings shall be insulated by provision of insulating joints at both banks and extra care shall be exercised for their protection by suitable means.

For monitoring interval.

purpose, test stations shall be installed at approx.

1 Km and

In addition, test stations shall be provided at all aossings

near insulating joints.

The central monitoring system shall be adopted for the CP of the proposed line. Therefore, all CP stations which are co-related with SV and Telecom stations shall be provided witn means for daia acquisition which shall be interfaced to the pipeline SCADA through a local RTU.

Power supply at all intermediate CP stations shall be arranged from grid of 11 KV through 1110.433 KV transformer. In case of grid failure, a suitable But

standby power system shall be provided with Ni-Cd battery back-up.

power supply for the CP system at the despatch terminal, Intermediate terminal and receiving terminal shall be fed from transformer-rectifier However, power supply to CP system at intermediate arranged through OCIDC converter. units.

stations shall be

76 llharat PetrOleum Corporation Umited Dina - Kola ppe/lne p-ojed

Detailed Feasibtll'ty Report

77 Bharat Petroleum orporatlon Umlled Billa - Kotil pipeline project

Detailed Feasibility Re{XJrt

8.1

PROJECT IMPLEMENTATION

A Project schedule of 24 months mechanical commissioning facilities has been proposed

completion and 27 months of the project

for implementation

from the date of DFR approval.

A Prime consultant will be

appointed coinciding with the project approval to provide the necessary services in the areas of basic design, detailed engineering, procurement, tendering, construction supervision, commissioning management services. The project activities can be divided into the fOllowing four distinct phases, although there will be some overlap of these phases . assistance and project

ROU Acquisition/NOes Basic and Detailed Engineering Procurement Construction

8.1.1 ROU AcquisitioniNOCs

(0-12 Months}

Acquisition

of ROU along the pipeline route and acquisition of land for pigging stations, CP/SVllelecom stations, along with It is

various tenninals, surveys/soil

investigations,

will also be done during this phase.

presumed that detailed pipeline route surveys would have been carried out and sulVey reports would be available on the Zero date. Hydrological & Geo-technical Investigations of river crossings would be carried out ROU of 18 M wide laying the

through regular tendering process during the phase.

corridor will be acquired all along the cross cooolly route for pipeline. Competent

Authority for 2 states could be appointed who will

acquire the ROU under Petroleum & Mineral Pipeline Act by publishing Section 3 & Section 6 Notification in -official Gazette of Govt. of India. The option of utilising the services of existing competent authority of MMIPL Ext project for Rajasthan Section from CA available at Kota can be
78
Bharat Petroleum Corporation LimitesJ

Billa - Kot<Jpipeline project

Detailed Feasibility Re{XJrt

explored, however for MP section new CA to be identified as the present CA available for MMIPL Ext at Uliain will be occupied for Vadinar - Bina p/l project.

Simultaneously

all approvals/NOC's

namely PCB/MOEF

approvals I rail, It has

road, river crossings, DM NOC's, forest approval will be obtained.

been presumed that all approvals will be available within 4 months of start of project. month. MOE&F approval is planned to be obtained by the end of 4th

8.1.2

Basic and Detailed Engineering

, a)
Basic Engineering (0-3"' month)

Project Management consultant \YOuld be appointed within 1 month of project approval. important to meet This activity falls on critical path and is the project package schedule. Thereafter the

processJbasiveogineering

will be prepared

in next 2

montlJs. This package will mainly consist of process design basis, process description, piping and instrumentation diagrams,

equipment list and data sheets, instrument data sheets, line list and operation & control philosophy.

a)

Detailed Engineering for Procurement and Construction (4th to _11th month)

Based on the process package and various reports, detailed technical specifications

survey/investigation for line pipes, line

materials, equipment and instruments will be prepared.

Techno-commercial prepared

recommendation

for the above items will be placement of orders by 79

by the consullant

for further

Bharat Petroleum Corporatloo Umited

8ina -

Ko/i1 ppe/ine

project

Detailed Feasibtity Re{X'rt

Owner.

Review of the vendor drawings for bought-<Jut items will

also be carried out during this phase.

Detailed Engineering for Construction

consists of two sub-phases,

one relating to preparation of tenders and the activities leading to forwarding recommendations for award by ONner, and second

relating to preparation of detailed engineering drawings to be issued for construction. There will be overlapping phase of incorporating

vendor drawing information in finalizing IFC drawings.

8.1.3 Procurement

(yd month to 22"" month)

procurement

procedure

will' be

prepared will

by

the

consultant

in

consultation

with Owner.

The consultant

prepare vendor list for

critical and major equipment and materials,


v

float material requisitions, techno-commerciaf Mer placement of

receive

offers from vEmdOrs, evaluate

and prepare

recommendations

for placement of orders by Owner.

orders, consultant will obtain delivery schedules and quality plans from the vendors, follow-up with the vendors for manufacturing and delivery

progress, inspection in stages (as required), custom dearance and inland transportation arrangement will be done by the consultant The last
00

activity in procurement would be SCADA, which would end in 22 from zero date.

month

8.1.4

Construction

I Mechanlca! completion (9'i' month to 24'" month)

Following construction project

packages are proposed for the execution of the

a)

Main PipeHne and Associated Works i) Coating of finepipes & transportation

80
Bharat Petroleum Corporation Urrited
Dina - Kola ppe/ine project

. .-v .' .
~ ~

DffiJi!ed Feasibility Report

ii)

Pipeline laying including OFC laying, Cathodic Protection and HDD crossing. All works related to unmanned stations

I,
I
I

will also be covered in this package iii) Pipeline laying is proposed to be carried out in 2 spreads and the work in both the 2 spreads would be taken up

I ~

simultaneously.

I~
I-

b)

Composite/separate

package

for

Terminals

. including

all

civiVstructurat, mechanical, electrical and instrumentation works. The consultant will provide supervision during construction phase and provide assistance to Owner during mechanical completion of the pipeline, terminats and other packages, such as

Telecommunication system, SCADA & APPS system etc.

The consultant will also provide warehousing services for all bought out items.

8.1.5

Commissioning

(25th month to 27th month)

Pre - commissioning activities are primarily divided into three sub groups : o Inspection by various agencies - Post mechanical completion various checks are required to be made in the form of Internal project team inspections, Inspections by Consultant PooD

group, Inspection by Operations I user group prior to final OISD inspection

Electro geometric

pigging

of the pipeline will be done for

checking the health of the pipeline prior to commissioning.

81

Bharat PelroIeum Corporatlon Umlled


Bina - Kola pipeline project

[)etai!ed FeasIbility Rervrt

All requisite

NOC's like PCB Consent to operate, OM NOC,

CCOE license shall be required to be taken prior to charging of the of the pipeline

Commissioning

of the pipeline shall be done after receiving

also

dearance and on obtaining required NOC's with association from User function.

82
Bharat PetrOleum Corporation Umited

Dina - Kola plp6me project

- ~ -

~ ... .

..

1
-

--

---

.. -..

.
-

I
-

83
81na - Kola

ppel/ne project

Det3i1ed Feasibiity Report

9.1

INHERENT MERITS OFPIPEUNE TRANSPOR!ATION

The pipeline mode has been found to be superior to other modes of transportation due to the inherent advantages of increased safety,

reliability and reduced rail I road traffic congestion, minimal product loss in transit, lower energy consumption etc. Besides, the pipeline project has been proved to be environmental friendly by minimizing gaseous as The

emissions' and in-transit hazard of movement of petroleum products compared to other modes of transportation such as rail and road.

pipeline system will not have any adverse effect on the ecolqgical balance and environmental underground. conditions, since the pipeline will be completely buried

Ministry of Environment quantities

& Forests has also recommended that all bulk .

of petroleum prOducts be transported through well designed The advisory Committee on Environmental of MOP&NG has-also

pipelines to minimize risks. Planning & Co-ordinalion

<'PPf""'m"n

pipeline

projects in view of its environment friendly character.

9.2

POLLUTION FREE PROJECT lOlL CONSERVATION

The pumping of product through Bina - Kota Pipeline will be done using electric motors to drive the pumps. Therefore, there will be no air or water pollution due to this project consumption, Additionally, this project will reduce the HSD

that would have been consumed in the movement of the

product by rail and road and hence, it will aid the petroleum conservation efforts.

There will not be any gaseous emissions at ti}e receiving terminals, as the storage tanks wm be provided with floating roofs to minimize the

vaporization

of product

These terminals will be equipped with relevant.


84

Bharal Petroleum Corporation Umited


Bina - Kola ppe!Jne project

..
,

I.

~m~~

Table 4 PROJECT: PIGGING BINA - KOT A PIPELINE STATION AT CH. 130 ALL COSTS ARE IN RS LAKHS FX A MAJOR ITEMS 1 SCRAPPER RECEIVER 2 SCRAPPER LAUNCHER 3 SUMP TANK & PUMPS 4 BASKET FILTERS SUB TOTAL (A) B BULK MATERIALS PIPING 2 ELECTRICAL 3 INSTRUMENTATION SUB TOTAL (B) C SPARES SUB TOTAL (C) SUB TOTAL (A+B+C) D ERECTION 1 MECHANICAL 2 ELECTRICAL 3 INSTRUMENTAl SUB TOTAL (D) E LAND F CIVIL WORKS SUB TOTAL (A+B+C+D+E+F) G INDIRECT COSTS 1 2 3 4 OCEAN FRT. & CUSTOM DUTY PORT HANDLING & INLAND FRT. EXCISE & SALES TAX SERVICE TAX 5 0 32 18 48 0 0 21 7 7 5 94 94 105 348 348 28 218 218 37 18 48 21 7 7 139 660 660 89 242 70 40 15 125 20 40 190
.

SNO

DESCRIPTION

RS 10 8 0 15 24 18 50 15 65 6 6 89 39 125 50 25 200 3 3 242

SC

TOTAL 10 8 5 5 20 24 62 175 50 40 0 0 5 265 9 NOTES 9 US $ - Rs 42.2 336 CUSTOM DTY=341307% EXCISE DUTY =1648% 70 SALES TAX=3% 40 WCTAX=4% 15 SERVICE TAX=12.36% 125 20 40 521 ESTIMATE AS ON MAY. 2007 TYPE OF ESTIMATE

ION

5 WORK CONTRACTS TAX 6 INSURANCE SUB TOTAL (G) SUB TOTAL (A+B+C+D+E+F+G)

TOTAL COST

Table ~
PROJECP BINA - KOTA PIPELINE

KOTA REl;EIPT FACILITIES SN, ~ DESCRIPTION A MAJOR ITEMS 1 BASKET FILTERS 2 sCRAPPER RECEIVER 3 SUMP TANK & PUMPS SUB TOTAL (A) B BUlK MATERIALS PIPING 2 ELECTRICAL 3 INSTRUMENTATION SUB TOTAL (B) C SPARES SUB TOTAL (e) SUB TOTAL (A+B+C) 0 ERECTION 1 MECHANICAL 2 ELECTRICAL 3 INSTRUMENTATION SUB TOTAL (0)

ALL COSTS ARE IN RS LAKHS FX 0 10 10 40 10 50 18 18 . 78 24 60 40 30 130 10 10 164 ... 0 0 60 45 35


'I~

RS 24

SC

TOTAL 24 10 0 0 34 100 40 40 0 180 28 NOTES 28 US $ - Rs 42.2 242 CUSTOM DTY=34.1307'?h EXCISE DUTY =1648% 60 SALES TAX=3% 45 W C TAX = 4% 35 SERVICE TAX=1236%
i4U

TYPE OF ESTIMATE

ESTIMATE AS ON MAY 2007

E F

PIPELINE CONTROL ROOM CIVIL WORKS SUB TOTAL (A+B+C+D+E+F) 78 5 0 164 28 14 33

60 20 220

60 20 462 33

G INDIRECT COSTS 1 OCEAN FRT. & CUSTOM DUTY 2 PORT HANDLING & INLAND FRT. 3 EXCISE & SALES TAX 4 SERVICE TAX 5 WORK CONTRACTS TAX

0 0 27 10 37 257 257

14 33 27 10 6 122 584 584

6 INSURANCE
SUB TOTAL (G) SUB TOTAL (A+B+C+D+E+F+G) TOTAL COST 5 83 83

6 81 245 245

T ableJ3
PROJECT: BINA - KOTA PIPELINE KOTA DISPATCH FACILITIES SfiO DESCRIPTION A MAJOR ITEMS 1 MAIN LINE PUMPS ALL COSTS ARE IN RS LAKHS

FX
800 75

RS

SC

TOTAL 800 75

,
, .

2 BOOSTER PUMPS 3 BASKET FILTERS 4 C I DOSING PUMP 5 CI DOSING TANK-SS SUB TOTAL (A) B BULK MATERIALS PIPING 2 ELECffilCAL ( loci Power Conn) 31NSffiUMENTATION SUB TOTAL (B) C SPARES SUB TOTAL (C)
-

a a
875 40 15 55 18 18 948

24 4 4 32 60 250 65 375 10 10 417

24 4 4

TYPE OF ESTIMATE PRILIMINARY

907 100 250 80 ESTIMATE AS ON MAY. 2007

a a a
60
.M

430 28 NOTES 28 US $ - Rs 422 1365 CUSTOM DTY~34.1307% EXCISE DUTY ~15.48% 60 SALES TAX~3% 100 V'JCTAX=4% 30 SERVICE TAX~1236% 190 15

SUB TOTAL (A+B+C) D ERECTION

,
,

1 MECHANICAL 2 ELECittjCi\i... 3 INSTRUMENTATION SUB TOTAL (D)

,vv

30 190 15 0 10 25 215

CIVIL WORKS 15

F LAND FOR PUMPING STN. G FIRE FIGHTING SUB TOTAL (E+F+G) SUB TOTAL (A+B+C+D+E+F) H INDIRECT COSTS 1 OCEAN FRT. & CUSTOM DUTY

a
2540 1595 400 89 86 27 10 7 618 2213 2213

a
948 57

15 432 343 89 86

2 PORT HANDLING & INLAND FRT.


3 EXCISE & SAlES TAX 4 SERVICE TAX

a a
27 10

5 WORK CONTRACTS TAX 6 INSURANCE


SUB TOTAL (G) SUB TOTAL (A+B+C+D+E+F+G) TOTAL COST 57 1005 1005

7 525 957 957 36 251 251

Table 7 Annual OperatinQ Cost - Phase I


-

S No. A 1 2 3 4 B 1

Description
I

Annual Consumption I Annual Cost (Rs Lakhs) Qty. Rate 1 Unit

Variable Operatinq Cost Corrosion inhibitor Power consumption Bina Power consumption Kota Miscellaneous Diesel Oil etc. Fixed OperatinQ Cost Pipeline patrolling & manning of SV Stations Salary and wages Bina -10 Kota - 10 Misc. expenses indo transportatiol & communication

I
MT KWHR KWHR LS 14 2800000 8704000 4.5 5 5

I
I

63 140 435 150

LS

20

10

75

,
2
\

200
I

LS

150

I
3.00% 1.00% 2.50% 80 268 6

Repairs & maintenance Pumps @3% Pipeline @1 % ( indo Line material, Coating, TelecomlScadalCP) I LS Civil works @ 2.5% Insurance charges LS

30

To ta I ........ Say ..

1597 16 Cr.

DetiJiled Fea5ibi5ty Repxt

'.

.
~

:
I

; t
I

"'
::

i .

~
-'

Ii"
'
.' _ .j

i
I

~ l
;

"\.' - -
_ .

104
Shara! Petroleum Corpomlion Umijed Bina - Kata pipeline project

'-' v

U \J

\j

'J

"

.,
FY 201]-14

Bln~Kot/l

Plpf'llne

-Throughput

E~tlmates

MmEXUPJ

FY 2010-11
Route Blna - Kota

FY 201112

F'().01'J]O
H$D-4 flSD-)

Kota Mllthurli
Mathura Plyala Plyala B!Jwasan

MS-4 MS-) HSD-4 H$D-J SKD AT' Total MS-4 MS-) HS{H HSD] SKD 84l 13' ll5 190 650 811 139 no 20410 121 183 616 717 \l5 33\ 168 6\0 689 13\ )30 22644 322 162 626 541 84 ))0 18"'5 291 136 \62 280 131 8' 0 l59 no 963 270 0 J7J 260 0 0

'" "
SKO

'" "

SKO ATF Total MS4 MS-) M5-4 MS) HSO-4 HSD) ATF Tolal 248 91\ 139 419 2764 703 36) 205 36) 2519 216 703 771 \l5 419 2595 363 180 363 2368 'S' 2131 399 176 538 lI\ 146 609 8' 363 19304 )70 11<49 0 0 192 0 <0' 363 f020

SKO

'"

" '" '"


ATF

889 88' 771 511

1147

97S 674 0

'" 115
84 14

AH 701
707

Tot ~l

~ 3380

707 Z810 707 1602

FY 2010-11
Dt>stinatlon,

FY 2011-11

FY201)14 SKO ATF Total MS-4 MS] HSD-4 HSD-] SKO Total MS-4 MS-)

fYI01910 HSD-4 HSD-) Si<.O ATF

Route

MS.4 MS-)

HSD-4 HSD-)

ATF

Total

MS-4 MS-]

HSD-4 H50-]

rQt.'li

Ex-Kota

TOP

Kota TOP Udaipur Sub Totll\ ExBhlH/ltpur TO? Bharatpur TOP ExMllthura TOP Mathura TOP Tundla TOP Sub Total
Ex-Plyal/!

PL-Interject!on b-Kota

to MumP!

16

TOP by Road

a
a

5
21

o o
a
28

8' )8
III

2 2

102
146

"

o o o

17 5
12

o o
o
29

87 19 126

106
46 152

o
a a

10 6 16

98 42

110

o
o

,
2

a
a
II

140

169

"
81

15 7 J2

o
o a
JI

Pllnterjectlon

to Mum-Plyala 2

7\

)5

77

JI

" o
38 PL-lnterJectlon Ex-Plyala TOp Ex-Plyala Ex-Plyalll Ex-Plyala Ex-Plyala Ex-Plyala E)(-Piyala Ex-Plyala to Mum-PI Road

14

57

138 38

301
,)

<0

2\

50

144 <0 184

44 0 44

JI1

5
lY

o
57

o
'0

5
30
I

o
59

'5
3\7

" o
44 2l

21

6)

156 100

176

3<'
216

5 J1

o
63

"
o
70 12 54

" o
44 14 1

Jl4 49

\6

)3

81

197 \6 253

o
56

383

5 38

o
81

" o
44 \4 2 2 7 __~ _~

411

TOP

P;yal3 TOP

20

0
16

182

Pz.rwanco
Chandl~arh
Kathgodam

Roorkee TOP NaJlbabad TOP Bhatlnda TOP

TOP- Road TOP Road TOP Road TOP Rail TOP- Rail TOP Rail TOP- Rail

o
a

25

o o
a

o "2 61
12 2

21

189

o
"
12 50

14

114 83

80
39 64

0
0 0

17
26 9

o
a o

1 7

<0
66

o o
a

0 19

105

141
91

29

0 15 J4

260

0 88

]03 115 48

18
9

o o
a

~-

Jammu
Srinagar/Pampore

ExPlyRllll/ex-JammuRd

17 o 8 20 131
260 0

o o o o o

'8
21 28 172 70

7
\ 11 8 ,

17 5 2S

o o o o
a

49 44
205 88

0 0
0 0

18 5
26 9

o o
o

18
29

5
1\

51
4\

o
182 359

38 II -479

7 5 70
14

62 35 882
633

0 0
21136 270

18 8

o o o
189
]7J

179 7J <0 13 498

8 , 7 5 70
14

113
91 65

)6
91, 657 )63

o o o o o o
23
292

10 5 28

10 8 146

o o o o o o
205

30
II 193 79

2 7 5
II

"
70

o o

,
26 5
J4 9

o o __~
067

55 119 97
71 38

,
8 7

"

o o o
o

o o o

]6 <10 244

5 \1 8

55
28b

" 15
538

5
70

o o
29

26
8 176 O~

o o
o
26~

1001--_'9T 56 J\ 674

~
82 44 ~2_~8
89S

-~\t
--:;i--t
701

981 710
439 439

ExBJiwasan TOP Bijwasan TOP Sijwasan-AFS Total Throughput

~1
707 __ 7071

o
811

:J

o
703 915
139

JlO

C--

330
322 183

330
2410 335 190

363 650
80139363

..!.!!!
3588

626

139

330

2519

363

205

4392764

459

248

889

1147,

1 J9

1--

\,

'-.J

\ J

\ )

\)

lj

1:

IJ'

,)

')

'.J

. }

'j

,}

'J.

~ ~

, "

BINA - KOTA PIPELINE PROJECT REVEI~UESTO THE PROJECT

AHNEXURE II

.. !t ifr-i\~~IJ~ , ... Throughput- ~01 0-11 Pipeline Frelllht ail 31 .. ~, , .tIij~;@'nf:9rqrest: ATF Total MS HSD SKO MS HSD SKO ATF Total MS HSD SKO ATF OJst-K~ Rs/MT Rs/MT Rs/MT Rs)MT TMT TMT TMT TMT TMT Rs Crorl Rs Cron Rs Cron Rs Cron Rs Crores
70% Ex-Kota TOP Ex-Bharatpur TOP Ex-Mathura TOP Ex-Piyala TOP Ex-Bjiwasan TOP 303 461 428 539 601 311 449 414 510 572 311 449 414 510 572 269 388 358 441 494 21 6 67 151 260 122 62 233 661 359 4 7 44 70 14 139 146 75 344 882 963 1 0 3 8 15 26 4 3 10 34 21 71 0 0 2 3 1 6 0 0 0 0 19 19 5
3

572 Total

330

14 45 55 121

505 1437

330 2410

1
I I

,
,
1

BHARAT PETROLEUM CORPORATION LIMITED

RECONNAISSANCE-SURVEY-REPORT

"FOil
,

alMA -KOTA PIF'ELU"U~RO.JECT


_

..... "C'--

_.

",0,'

.V(Rl"'~ --I
( Ra-oRT )

SURVEY AGENCY

UASCOM -

7I.~

CHAPTER - 1

EXECtrfiVESU~Y
.
.

1.0.0 1.1.0

Executive Preamble:-

Summary

Bharat Petroleum Corporation Umited has proposed to lay a Petroleum Product cross countrY pipeline through the slates of Madhya Pradesh and Rajasthan from Bina to Kola. and .Mascon MSC. PvlLtd .. have and Detailed

been entrusted with job of Carrying out Reconnaissance Route Survey for this proposed pipeline. 1.2.0

This report covers the Reconnaissance Survey part of the job. where the scope is to ... To carry out Reconnaissance Survey along the routes which seem to be explored for finalzing the optimum route and highlighting

obstructions I constraints there on. if any. 1.3.0 Avoid quarry sites and forest area, as far as possible. Identify and fIX the reference I flag points along the proposed routes.

The possible alternative routes have been studied in depth on available SOl sheets and on field.

1.4.0

The position of Starting & Terminating Points are as under; .:. StartinQ Point. Bina - Dist. Saqar of Madhva Pradesh State I
latitude longitude - 2Ao- 15' - 43" - 78 -10' - 07"

.:. Termination
latitude longitude

Point. Kola - Dlst.Kota

of Rajasthan

Statel

- 25" - 11' - 20" -

71' - 58' - ZT"

M..1sc:on MS.C. Prt

Ltd

1.5.0

Salient features of finally proposed alignment are as under,

a.

Total Length of the route

253 kms Madhya Pradesh & Rajasthan

b. Name of states

c.
d. d. e. f. g. h. i. j. k.

No of National Highways No. Of State Highways No of other major roads No of Rivers Length in forest Elevation @ start point Elevation at end point General Canals Nalla I Drain terrain

3 nos.
3 noS. 16 nos. 10 nos. 8.6 kms. 400 mls. 255 mls. Flat.

3 nos.
3no5.

==x==x==x==

) )

)
~on

M.S_c. Pvt. Ltli

) )

CHAPTER - 2 APPROACH & METIIODOLOGY

2.0.0

Approach & methodology adopted for reconnaissance selection is described below; The final pipeline route selection

survey for route

2.1.0

is on the basis on the following

observations. Safety of public lives, property and also safety of pipeline. Shortest I optimum pipeline length Easy and favourable terrain conditions, avoidance bodies, Ravines, Depressions, Unstable ground etc. of large water

Avoidance of steep rising or falling ground, hills & valleys. Avoidance of sharp bends & turnings .. Avoidance of historical monuments. Minimum demolition activity and up rooting of minimum numbers of trees. Consideration of availability of infrastructure route during and after construction. & access to pipeline

Avoidance of Reserve Forests, built up areas, places of worship, burial grounds. Existing & further development in the regions such as roads, Rail lines, Canal network, industrial units etc.

Based on the above factors (as applicable), the pipeline route has been selected in the office induding alternatives. The reconnaissance party consisted of experienced personnel of .

MASCON and Engineers of B.P.C.L The party moved in the area, which was fortunately, open as there were no standing crops and the visibility

was good. Important turning points were marked on the ground with yellow paint on nearby trees or prominent places. Their positions were marked on SOl maps with the help of handheld GPS. The crossing points of major obstades yellow on nearby trees I structures etc.
M.a.scon MS.C. Pvt.Ud

likQ roads, rivers were painted

,
CHAPTER - 3 DETAILED FEATURES OF ALTERNATIVROUTES STUDIED . AND AN OVERVlEW ON TIlE FINAL ROUTE -

3.0.0 DETAlLEDFEATURESOF VARIOUSSECTIONS OF THE ROUTE:


The entire alignment can be subdivided in five major divisions. They are.

a. b. c. d. e.

MKTG Terminal at Bina to Betwa River i.e. Sagar District of M.P. From Belva River to Sind River Ashoknagar District of M.P. From Sind River to Parbati River i.e. Guna District of M.P. as well as Rajasthan State starts. From Parbati River to Parwan River Baran District. From Parwan River to Kola Tenninal

3.0.1

Section wise Detailed Description of the Route is as under.


a. MKTGTERMINALAT BINA to BET'NARIVER I SADARDISTRICT OF M.P.l

,
,

The proposed alignment of pipeline originates from MKTG Tenninars North Wall comer i.e. about 182m east from comer of BORl marketing Terminal Wall. This point falls in Bina Tehsil of Sagar District, M.P. State.

The route moves in North West direction up to Betwa river.

Starting

elevation is 400m from Mean Sea level and elevation on Bank of Betwa is 390 on the bank and at the bed is 375m. Scaled chainage of Betwa River is 8.8 Km. The river is perennial and even in summer also it flows In full bed witdth and having water of depth of about 4 to 6 m as per local information. Total with at crossing is 250m. Upto this terrain is gentle

plane and cultivated. Soil nature is black cotton. Main crops are Soyabin
) )

in rainy session and Wheat & Chana in winter. b. BETVARIVERTOSIND RIVERIASHOKNAGAR DISTRICT OF M.P.I From Betwa River pipeline moves in North West direction. The terrain is gentle plane upto Mala Protected Forest hill area. Upto this pipeline

crosses Village road Malhargarh - Mungaoli at Ch. 10.4 KM. Ketha nadi
M.a.scoD MS.C. Pvt

Ltd

, ,
,

at Ch. 21.6Km

and S.H.No.19 (Vidisha - Mungaoli), at Ch. 22.1 km.

Forest is mainly open mixed jungle having mainly khair trees. The highest M.S.L 520m at Ch. 45.5 KIn. The length in forest is 3.8 Km at proposed pipeline crossing then after pipeline descending from hill and

,
,

moves in the same direction upto Sind River from cultivated plane area. Main crops are Soyaben in rainy seas ion and Wheat, Chana in Winter. Cultivation Vidisha is mainly depends on rain. Here pipeline crosses MDR ( at Ch. 40.3 Km, Orr Nadi at Ch. 52.4 and

,
j

- Ashoknagar)

ultimately crosses Sind River at Ch.80.8. The bank of river is at elevation 470m and at Bed level is 460ml In general pipeline passes at 500m district ends and

M.S.L level through this section. Here Ashoknagar

Guna District of M.P.starts. Soil is black cotton and main crops are Soyabin, Wheat Chana, Mung & Masur. c. SINO RIVER TO PARBATI RIVER (GUNA DISTRICT OF M.Pl From here proposed
)

pipel!ne moves almost in same

North West

direction, In this section it crosses Kota - Bina West Central Railway (B.G) Single line non electrified tracks at allOut 150m West oi Guna Ashoknagar Road ( MDR ) at pipeline Ch.90.7 Km and then after Guna Bhind (WC) Railway B.G Single line, nOlMllectrified at Ch. 92.4 km. of

immediate after this railwaytine SIR Rasala NO.1 Protected Forest

about 0.8 Km in length ,mainly mixed bushes. This forest falls at about at Ch.97.5 Km. pipeline passes Then N.H.No.3 crosses at Ch. 98.0 Km. Proposed through undulating cultivated ground and crosses

Khyawada Protected Foresl scatte.ed teak.

Here mainly it is open mixed jungle witt1

It Is mainly a hiD terrain with average M.S.L is 420m.

The forest starts at Ch.111.4 Kmand ends at 113.6 Km. The length of this forest is 2.2 KIn. After that pipeline passes through almost cultivated

plane land of which general M,S.L is from 415ml to 350ml again crosses

Then after it

Reserved' Forest before Hamirpur Village. 'This falls toCh.147.7ml Total length is 0.8 Km. It is open

J
J
) )
')
~

between Ch.145.6ml

mixed juIlgle mainly teak trees. Then at Ch.149.3 Km alignment crosses Parbati River. At bank M.S.Lis 325mt and in bed it is 32Omt. River is

perennial. At this place the water depth is about 3 to 4 m. Soil of this

M.S.c. Pvt Ud

::>

area is rocky in forest and black cotton in cultivated area. Main crops are Soyabin, Wheat, Chana, Masur, Moth etc. cultivation depends on rain.

At the end of this section at Parbati River, the stale of Madhya Pradesh ends and State of Rajasthan starts.
d. PARBAT) RIVER TO PARWAN RIVER (BARAN DISTRICT OF RAJASTHAN)

In this section pipeline moves in the same direction

i.e. Nortn West

direction. It crosses Andheri Nadi at Ch.164.7 Km. The M.S.L is 290m!.

at the bank of river. The river is non perennial. It has sheet rock in the bed. Further the alignment moves in same direction and and cross Kota - Bina (!N,.C. Railway). This railway is BG Single line, non electrified. The chainage NHNo.90, is 167.0 Km. Then after 200 m alignment crosses

at route Ch.167.2km.

Then after it passed through gentle (Jhalawad - Baran) Road at

cultivated plane land and cross S.H.No.1 Ch.195.3 Km. Mer

this point the proposed alignment

pass through

about 6 to 7 Km from stony waste area, before it crosses to Parwan River at Ch221.9 240 ml cotton. Km. The bank elevation is 255 mt crops are soyabin, wheal and that of Bed is

The main

chana. The soil is black

e. PARWAN
Alignment

TO KOTA TERMINAL

IKOTA DISTRICT OF RAJASTHAN

STATE)

progresses

in the same North West direction and crosses

River Kali Singh at Ch.227.9 km. The Bank level is 250mt and bed level is 245ml
I

At this portion river has almost stagnant water. Mer this point

alignment crosses Chambal Right main Canal at Ch.249.7 km. Then it crosses (BPCL) N.H.No.76 at Ch251.9 Km and ends at at Kota Terminal

at Ch.253 Km.

The crops are same as previous stretch , like

soyabin, wheal chana etc.

To optimize alignment, three alternative

routes are investigated

with

some common overlap and out of these three routes the best route is enlisted as Alternative I, other two are A1temtive II & III.

..
('I.V' ~ ,,~. ~

-? '

"'<~

~~!W~,~~'t.,W.'~n~

'-

These all three altematives

are shown on route map attached as Alt-I,

AL T-II and AL T-1I1. In details they are, AL T-I ( 253 kms.1 : A - B - C -E - F- G - J - K - L - M - N - P - Q - R - T - U - V - W X- Y -Z-A3 -A4. AL T- II 1 253.6 kms.) : A- B- 0-1A1 -A3-A4. K- L- M- N-O- P-QR-S - T - U-W-Xy-

AL T -11I1252.1 kms.l: A - 8 - C- E - F- H - J - K - L - M - N - P - Q - T - U - V - Y - A2 A3 - A4.

A line diagram

at Annexute

II shows common length and changed

alignment in various alternative routes. 3.1.0 Details of Different Alternatives :

As mentioned earlier. the route selected at Alternative I is very suitable and viable alternatives Comparative route. However for crossing important locations various

are worked out and examined. statement of crossing encountered in various route are

given at table attached at annexure II. Abstract is as under. Sr. No. Description Length in Kms. Railway Crossings National Highways State Highways Other Pucca Roads Rivers Canals Drain I Nallas Cart Tracks I VR Forest Length Other Crossings Alternative I 253 3 3 3 16 10 3 3 5 8.6 2 Alternative II 253.6 3 Alternative III 252.1 3 3 3 15 10 3 2 5 8.6 2

1 2
3

3 3
16 10 3 3 6 8.6 2

5 5
6

7 8 9 10

M,lSC(lD MS.C. PvL Ltd.

,
, , ,_'" ~~ :.'; ",<n.~ : _"); '"

CONCLUSION: The comparison of all the alternative routes In view of the comparative statement is as per Annexure II, ,it can be concluded that

Alternative I is most suitable route The Total Length of this route is 253 Km., out of which 149.30 Km of length is in Madhya Pradesh and 103.70 Km of length is in Rajasthan State. This Altemative Route has been detailed as under. 3.2.0
---._--.

THE PROPOSED FINAL ROUTEPASSESTHROUGH ..


---------

STATES
---- ----.-----

DISTRICTS
i. --

LENGTH in kms.
----

I MADHYA PRADESH
~--

SAGAR

8.8
----

--

1'.-A-SHOKNAifAff

72 68.50
--

---

----

i[GUNA
-o

'lfRA:JASTHAN
-----.-----.---.

--i.-EiARPj.,f Ii. KOTA ---.


___ 0

- - ---

72.60
--------

--

--

---- --

----

-."

-"'

----

-_._-

31.10
--.-

TOTAi..---2 STATES
----

---SOiSTRICiif
- ---------,---

--.-

--

253 kms
___

--

----,--

--

---_u-

.un

.--

-------

___

--

ASSUMING ADDITIONAL 1 KMS OF PIPELINE INSIDE BINA TERMINAL & ANOTHER 1 KMS IN KOTA TERMINAL & ASSUMING 3 % INCREASE IN SURVEY , THE LENGTH FOR LOCAL DEVIATIONS DURING DETAIL COMES TO 262 KMS. THUS FOR ALL PURPOSES, TAKEN AS 265 KMS. BINA - KOTA PIPELINE LENGTH CAN BE

3.3.0

LAND UsE PATTERN Sr. No.


1 2 3

Name Of District Sagar Ashok Nagar Guna Total of M.P.


Baran

Length In Kms
8.8 72 68.5 149.30 72.6 31.1 103.70

Land Use Cultivated


7.8 62.9 44.5 115.2 53.1 28.7 81.8

Rockv/Barren
1.0 9.1 24 34.1 19.5 2.4 21.9

Kola Tolal Of rajasthan

M.l3COn

MS.C ~

Ltd

,
"~, C"'\Il"',~ 1;

,3Z,.~~;t;,ay,:,t"~

3.5.1

LAND CoMPANSATION

,
, ,

Average Rate of Land in M.P.

= Rs. 2,30,000=00 per Ha.

Average Rate of Land In Rajasthan is = Rs. 3,00.000=00 per Ha.

ROU lenQth in MP is about 150 km. ROU Width is 18 mts. Land Cost is Rs. 2,30,000=00 per ha.

Therefore ROU cost @ 10% of rate is,

150 *18 * 0.1' 1oo

230000

= Rs. 62,10,000=00

A-1

ROU Ienoth in Raiasthan ROU Width is 18 mts.

is about 103 km.

Land Cost is Rs. 3,00,000=00 per ha.

Therefore ROU cost@

10% of rate is,

,
103 *18' 0.1 300000

= Rs. 55,62,000=00

A-2

1oo

Hence Total Land Compensation A-1 + 1>.-2 Rs. 62,10,000

will be,

+ Rs. 55,62,000 = 1,17,72,OOO=OO A

~n

us..c. Pvt Ltd

10

,
I

.
-', '>'!',tlt!;-l'"

'''~{",'R.J"~:.~tp..Ml:~~;:'~"a'~.'

3.5.2

CROP COMPANSATION :

Average Crop Rate per Hector for M P and Rajasthan is,v For Cultivable land = Rs. 1.50.000/- per Ha. For Barran and other land = Rs. 25,0001- ha.

For Madhya Pradesh: i. Cultivable Land = 11520 '1000 '18 '1500000 10000 = Rs. 3.11.04.000/__ .. __ B-1

ii

Other Land

= 34.20 ' 1000 18' 25000


1oo

-'
For Rajasthan:

= Rs. 1.53,90,001-

... B-2

Cultivable Land = 81.80 '1000 '18 '150000 10000 = Rs. 2,20,860001. B-3

ii

Other Land

= 21.90 '1000'

18' 25000

1oo = Rs. 9.85,500/- __ .


.8-4

Hence Total Crop Compensation will be,

B-1+8-2+8-3+8-4 = Rs. 3,11,04,0001- + 15,39,0001+ 2,20,86,000/- + 9,85,500

= 5,57,14,500
)

=x=x==x=

Mucxro. M S. C. Pvt lid

11

,
_" """t

,.eJ:"~ ;~;laOm'f~<!!~;:~~

'-

. ,

r
,

CHAPTER - 4 DETAILS OF MAJOR CROSSINGS ON PROPOSED

ROUTE

L~
Major Crossings:
Railways National Highways State Highways Rivers Canals(Major) 3Nos. 3 Nos. 3 Nos. 10 Nos. 3 Nos.

All these crossings

are narrated below.

A.

RAILWAYS REMARK

SIl.NO.-' -- ., 'lOCATION 1 -AiCh:90.70 Kni'2 AtCn 94.40 Km


u

- RailWay
-

LIooKota~B1naEl:Gline(WCR)

RailWaYlioo~El.G.Une(WCR)Guna: Elllind
Section

B.

NATIONAL HIGHWAYS

;' 'SR.NO:'~'--'-locAl1ON

----'.--

-----~'-REMAAK-

r-f----,Afch:98:00Km'--NH
-,. -2--,-AT
'-

- 3, Gulla: shiviXiii~-.~:_
Hlg/Ttiay No.90 - Sara - KaWai

Ch 167.20Km-;-Nat!oual

'-'T-~-ATCh252.110 ---.-.- --------

Km----Naifciiiiil~y-t'j(:,:76 -.--

.--

...

-.--

C.

STATE HIGHWAYS ( MAJOR)

SI<.No,- --. LOCATION 1 .. (rch 22.10-Kni-' 2 Af'ch 12290Kiii-3 -. ATCh195.30Km-

, S.t-lNo.1!fVkisha -:-MungaouiASjltlatfedR03d)

-stale~NO:-ZfGuna S1aleHghway'NoTSarnn-

- FatetoQafh .. -JhalaWai' -

~DMS.C.Pvtud.

12

D.

RIVERS SR. No. LocAnON REMARK Betwa River Kethan Nadi OrrNadi Khera Nadi Sind RiVer -KaneraNadi . Parbat; River An<ihenNadi Parwan River

1 2 3 4 5 6 7 8 9

8.80 21.60 52. 10 73.30 80.8085.90

i4ij-:Jb
164.70 221.90

E.

CANALS SR.No.
LOCATION

REMARK Canal

1 2 3

138.40

165.80

249:'75" --

"

- "calial --ChanibaiRfghtMafncanai-

1---------

~--

END

L~

~M.s.C.Pvt.Ud..

13

ELEVATION (m)
C> C> C>

'" C>
C)

o o

.t>
C)

C>

C>
C)

'"

Ol

C> C>

8.8

BE1WA RNEF

21.6

: STATE IfI!lHWAY-1

c
,

32

52.1

68.6

80.8

90.7 98

~~WAY

-.-,+-

N~TlONAL HJ<?HWAY~

Gl m

~ Z
112

I'JiA YANtWNJA P r.

. . . .
.

00 -I::!!

m z "lI ",::0

-"
"lIO

r rn
"lI

3;
~ 149.3
167

p~n
WCR IlAlLWAY

\!!::o Z
rn

167.2
STATE HiGHwAY (ATRU-~ANA) ~ ATE HtGH.tA Y

171.7 195.3

(J~WOR

- o/-RANI

..
221.9 227.9
I'ARWAN RNEF KAJi.I SINOH

mYE'
l>

249.7
:J :J

253
-

(I)

1__

X C

, 'P

,-

,,

'J

.,

, !

,,

'J

'J

., . .
,

'j

, j

,,

, !

,, ,

Annexure ALTERNATIVE Ilernatlvea LT .1 LT II LT 111 A


A

II

ALIGNMENTS

SCHEMATIC DIAGRAM

connecting Points (TPa) L L L M M M N N N 0 0 0 P P P

chematlc IIgnment

(Point

o--t
I

locatIon, left or Right)

Common Points

Nearest Legend

tata Dlatrlcts

conM.S.c. Pvt. Ltd.

Il

"~;i:,

'j

"'~"."< ~~';\~~~~~"Vf{~

'Annexure III
rliST Sr. No, 1 2 OF CROSSINGS Name of Crossing FOR ALL ALTERATIVES
Alternative r'ternative

ACROSS BINA - KOT A PIPELINE


Alternative Remarks
"---

NO.1 Bina MKTG Terminal


Bina Agasode (V~lage Road) Puraina Bhaijpur (WBM Road)

NO.2 No.3 Chalnage in Kms. 0,00 0,00 0.00 0.18 5.10 8.80 0.18

0.18 5.10 8.80

3 4

5.10 8.80 Perrine) water in bed about 4 - 5 meter depth

Betwa River

5 6 7

Malhargadh - Mungaoli ( Asphalted Road) Kethan Nadi S.H.No.19 Vldisha Mungaoli (Asphalted Road) Mala Prttected Forest start Mala Prttected Forest End MDR - Barkhera Ashoknagar (Asphalted Road) Sawan - Bhado Asphalted Road Orr Nadi Tumenkhed Ashoknagar (Asphalted Road) WBM Road Ashoknagar - AmahitaJ Murram Road - Danga; Dongra Kachnar - Ashoknagar (Asphalted Road) Mathner - Shadhara (Asphalted Road) Amoda - Bljalpur

10.40 21.60 22.10

10.40 21.60 22.10

10.40 21.60 22.10 Perrinel

8 9 10

30.30 34.10 40.30

30.30 34.10 40.30

30.30 34.10 40.30

Dense mixed bushes with scattered trees

11 12 13

46.90 5210 54.60

46.90 5240 55.30

51.90 52.10 54.00

Pradhanmantrf Vilage Road Perrine) Pradhaltmantrf Road

14 15

59.30

59.30 61.50 6210 71.00 71.50

59.30 6250 Pradhanmantrf Road Pradhanmantr1Road

16 17

6'L5O

68.60

68.60

18

~Il

M.S.C PvL Ud

16

..
. , "'\"~, "~, oT.''ii..,~>-IJt~~\<l:l;'{",,_

Sr. No. 19 20 21 22 23 24

Name of Crossing
-

Khera Nadi Sind River Khod Ka Nala Kanern Nadi Murram Road PagaraKarod Railway Une Kola - Bin.i B.G. Une (WCR) MDR GunaAshoknagar GAIL - HBJ 18" Gas Pipeline Railway Une - B.G. Une (WCR) Guna - Bhin<! Section SIR RisaIa NO.1 Protected Forest (Start) BfR-R!sa!3. No. ~ Protected Forest (End) National Highway No.3 AsphaItedRoadN.H.No.3 - Umri Nata Guna - Pura (Asphalted Road) Guna - Rampur (Asphalled Road) Guna - Rampur (Asphalted Road) Khyawada - Protected Forest (Start) Khyawada - Protected Forest (End) Sukha NaIa Murram Road Baneh Sabra

Alternative Fternativel Alternative No.1 No.2 No.3 Chainage in Kms. 73.30 73.30 79.70 80.80 8290 85.90 84.80 90.70
83.60

Remarks

80.30
-

83.80 84.00 88.00

8280 84.90

89.60

90.10

25 26 27

89.80 9240 94.40

89.50 94.40 96.90

89.60 91.80 93.80 -

28

97.10

98.50

96.20

29 30 31 32 33 34 35 36 37 38 39

~7.9C 98.00 99.40 99.70 101.30 107.00 110.10 111.40 113.60 115.10 120.40

99.3-C

97.GO

99.40 100.80 101.20 10280 108.50

97.80 98.50 99.10 100.70 106.40 109.50 112.80 113.00 114.50 119.80 Fairly mixed jungle mainly Teak Perrinal

t'

111.60

11290

115.10 116.60 121.90

.
17

Sr.

Name of Crossing

No. 40 41 42 43 44 Slate Highway No. 23 Guna - Fatehgarh Canal Resereved Forest near Hamirpur (Start) Resereved Forest near Hamirpur (End) Parbati River Andheri Nadi Canal Railway Une Kola - Binc B.G. Une (WCR) National Highway No.90 Bara - Kawai (GAIL) HBJ Gas Pipelinel MDR Road Atru - Antana (Aspha/ted Road) Nimada - Diwali (Aspha/ted Road) State Highway No.1 Baran - Jhalawar Mirjapur - Hanmat Khera Anta - SUrsan Road Parwan River Rajgartl- Kundanpur (Asphalted Road) KalI Slndh River Chambal Right Main Canal National Highway No.76 End Point

Alternative rlternativel Alternative No.1 No.2 No.3 Chainage in Kms. 12230 122.90 124.40 138.40 145.60 139.90 14710 148.90 150.90 166.20 166.90 168.50 170.00 172.00 172.90 181.20 196.80 212.50 213.60 223.60 223.90 229.80 251.20 253.40 253.60 137.80 145.00 146.80 149.20 16480 165.80 167.10 167.30 167.30 169.50 176.70 195.40 208.10 212.20 223.90 224.70 229.90 249.80 252.00 252.20 Unlined

Remarks

.-

Open mixed jungle mainly Teak

147.40 149.30 164.70 165.80 167.00 167.20 169.10 171.70 180.60 195.30 208.00 21210 221.90 22230 227.90 249.70 252.80 253.00

Perrianal4 - 5 meter depth SheelRockinbed

45 46 47 48

Crossing at 202 km stone

49 50 51 52 53 54 55 66 57 58
) )

S.H. AsJilalled V.lage Road - Asphaned Village Road - Asphaned Bed Sheet Rock

59 60

Four Lane In progress Kota Tennlnal


.

,
)

~hsc.on MS.C. Pvt..Ud.

18

.
..

;..' . ,,"t

,~,.,

<~

~r&~~!rW[~""':
F

'"

'

-0

Annexure IV
-

REFERANCE SURVEY OF INDIA MAP

1. Scale 1: 2.50,000

Sr. No.
1 2 3 4 5

Map Number
54L 54H 540 54C 450

2. Scale 1: 50.000

Sr. No.
1 2 3 4 5 6 7 8 9 10 11 12 13

Map Number
46L I 3 54 H 115 54 H 111 54 H 110 54 H 110 54H/6 54H/2 54 0/13 540/9 540/5 54C/8 54C/4 450/16

) )

.
Mas.con Ms.c. Pvt Ltd.
19

.
"',.~ 1\ ". "l:'.i~;;-\l..~ . ~h.;;; .. ~.i;';"-'l,.' V

"i'.. ~Y',

Annexure V

PHOTOGRAPHS

Masoon MS.C Pvt. Ud

20

,
I I

~-..

~.

""""""

BINA TERMINAL

BINA TERMINAL

MARKETING TERMINAL LAYOUT

J
~n

MS.C. PVl Ud..

21

'

~""~"!~.:~

BETWA RIVER

STATE HIGHWAY 17

SINDH RIVER

Mascoa MS.C Pvt. Ltd.

21

. .. ~ <~r ""~~ ,';'.M.

~.:'I\

........

" .~~

KOTA - BINA - RAILWAY

near 10828 -1082 /9

, ,

,
GUNABHIND RAILWAY (WCR)

near 1100114 -1100/15

.'

National Highway - 3

Mncon MS.c Pvt.l1d.

23

, ,

..
, ~~ '~1V.

:::J"_'<~~')~_~-:<,:'_,~
_,_.o:_!-

:~.1"".'!'.'

c:~~

KHAYWADA FOREST

PARBATI RIVER

ANDHERJ NADI

Ma.!C()n MS.C. Pvt l.Jd.

2.

BINA-KOTARAILWAY

..

NATIONAL HIGHWAY 90

,y/

PARWAN RNER
.).

:>

Ma..scon MS.C. Pvt Ud

25

' -.J

\ I

\ I

"

\ )

\)

'.

I,

I j

I,

, ,
,

,,

. .

'

---,--------------------------------------------------------.-,

-- --,----------.-----

Annexul'e

IV

Ground Profile: Blna Kota pipeline project


600

500

81 400

300

,;. i~::;,:;/t
~

.,~

::;

200

_,;v;'\f+--:~-~,

100

o
ASHOKNAGAR
1'+.0

, , , , ,

,..,....."

-+

GUNA
II."

BARAN
Iv.\)

KOTA RAJASTHAN ~=0=8=.8=K=M=S="'OL"'."'O====-1


------>

M,P, 1~,2 KMS

Distance In Kms from Sina

\J

\ J

I)

"

I)

, j

I)

,>

,, ,

f.

"

,,

\ ,

.
-

, ,,
f

--------------------------. ANNEXURE - V(a)

------

HYDRAULIC PROFILE( PH-I) BINA

KOTA SECTION

800
700

600
500
Q

IJS 400

J:

300
200 100

a
DISTANCE IN KMS
---.------.------------.-----~~

I,
I

I
J

,
-

'

~,4

,~'t"~~~4lk

:&1i,>;'~C',,"',~~ '\;;'SW

,,

"
l
-------... -----""1

HYDRAULIC PROFILE (PH-II) BII~A - KOTA SECTION


1000 900 800 700 600
c
~

i
j

:r

500 400 300


'.,:.

.: ,
'.,','

200 100 0
<:l
l
",,-,-'-,.,.

:KOTA '.',.'
I I I I

iI
I

,,~ ,,~
~,

0151 ANCE IN KMS

-_.

'~ 6~L

"'

--,-

-~

..

>-, ,,-,.,--

""f~~>"

. ~- -.,

9L9

L89
O~9

ZOO

0
~

889

U
LU

U>

< ~

OL9 B9 9~9 66v


VBV 9V
ggv :1i ~ ~

~
Q.

0
~

< < Z

In

::::""'i

m
::I:
Q.

Lvv BV~ z lev cs: t-

LU ~ LL

9~v C 66 6
U ~L ~9

In

-"

~
Q.

::i
::>

ii C
> ::I:
a a a a a a a a a a a
<D

9V 9 BZZ
vlH

LH

.ZB
0
~ ..--

..-

..--

co
a'lf3H

a a

a a

I
I

--

II

'J

"

,"

"

')

.,

"

< ,

..

'j

,;

'j

,,

'IYALA - BIJWASAN

BATCH CYCLE

latch sequence latch size 'umplng time latch cycle tlma low rate (.)

( (MS Euro 4 - SKO- ATF - SKO) - (HSD Euro 4 - SKO - ATF - SKO) ) 80 cycles ( (514155 3475 - 55) - (608455 - 3475 - 55) ) 80 cycles

( (25.4 - 0,3 19.1 - 0.3) (35.2 - 0.3 -19.1 - 0.3) ) 80 cycles 8000 173 hrs KUhr (with 1.15 MMTPA ,8000hrs, 0,83 d.mslty)

,oles: I. Blna KotaMethura-Plyala & Plyala-BIJwasan shall be separate batch cycles 2. MS Euro IV will be sandwhlched between MS Euro III product. Similarly HSD Euro IV will be sandwhlched between HSD Euro III product l. While withdrawing product at Kota, only heart cut product to be taken and allinterfac ~s will be taken In Plyala tanks 4. MTBE dosing 10 be done at Plyala for enhancing Octane number requirements. 5. ATF Is meant only for BIJwasan. ATF will be sandwhlched between SKO parcels and laken directly 10 Plyala. From Plyala It will be pumped to Bijwasan

,,
~y" ;'" "

,,
Project

r'\,

.
PMC
\

~lOa KOla f"ljJeliile

2
3 4 5 6 7

Project Start Appointment or PMC Bin. Kol. Pipeline Project Survey. and LAnd Acquilltion Detailed route .urvey Route Survey D.ta Land IdenlincaUon and Procurement NOC's and Approvals MOEF

end LAnII Acquisition ,

i
,!,

.J BI~e Kota Pipeline

~ :

: :

.. ,
..

ProJ,ect

8 9
10 11 12 13 14 15 16 17 18 19

CCOE PCB
DM'e IrrlgaUon Rellweya Hlghwaya GramPanohayal ROU and land acqulatlon Section 3(1) (part) Section 8(1) (part) Soctlon 3(1) (full) SecUon 8(1) (full) Studlea and Data Collection

~'''r
I
,,

ftcatlon and Procurement

!; i

, I, ,,
;
I !

aya

at

\;
i

ROU and tand acqulatlon ( )(part) \


I

20
21 22 23

n 1(1) (part) 3(11 (lull) ,


;

full)

Collecllo

Taak Blna - Kete pipeline prolool: 24 M ( Moch ""mpl) + 3 M Comm Date: Sat 4128/07 Crt\lcaI Taak ProQreea Mlleotone

Summary Rolled Up TUk

Rolled Up Prog' Spl~ E><lemal Teaka

Rolled Up Crt\IclaI Tm Rolled Up Mlleetona Peoel

1~~!j:ff))W<1<?;li~,;'\i

<)

Project Summary

...

..,.
Um~&d

E1 :Bharat Petroleum C<lrpora:t1on

~ ..
Sollinveatigotion Data HydroioglcaJ I Hydnogr SUrvlY Basic Englnlerlng Procua Deelgn Procua Optlmlaatlon I Batch Sizing P&ID'a p1peUne P&ID'a Data Sheats ( balance ) Detailed engineering Preliminary Layouts and Plot Plan. Final Equipment Layouts Final Plot Plan Preliminary Sludloa (Piping) Piping GAD'. lotMTO Final MTO ClvlVStnJoturel Drawing. (Part) CMVStruoturaI Drawings (Final) Arohltactu.-J O lgn ElocIr1oaI SLO and lDad llot ElectrlcaJ Deelgn and DraWinga InatnJmenlalIon Oaalgn and DraWinga Plot plana SV_

""".
"".

-"T

"""~JA ,._' .,.-~'


0

'~'t)~," l~-' ...;.:.. "J'\. ~ .f J..."}-.., . ~.

'.

.'

---..'

"

"L','

-:" ..... '-#'.-_ )'.

,\j.

_ _'. )._(j-'~.

I +

I,

'lIIIlI' I

Ulne ydro

nDala Hydrogr Surv Y Inearlng

I I

'

'a

Sheela {

(Piping)

awlnga (Part)

Teak <eta pipeline project : Mach compl) + 3 M Comm


III 4/28107

Summary RoIIad Up Taek

..

Rolled Up progreas

Cr1tJca1 T k Progreoa MIIoatono

Split
External Tulal

RoIIad Up Cr1lIcaI raak RoIIad Up MllaetDn. Page 2

lit~1ihW'it<i'W'),1

Project Summary

..........

E2:Bharat Petroleum Corporation Limited

"

"

')

\) \ I \, '\. J I) '\ I " ,~ ,~ "

ILI.Te~",I,,,!..L:.:!."

__

~~--_''''--''~'''~T''P'l..:.,.,.L.~<~

. "

lool.L.~

. ,.p,

.1 'Ir'

,,,' ,

f'\

'"

0\.' .' , .. ,.J...''''''-t>. .... ~.--r . -.Jo .... ."-r-= .. .l....:.~._ ---:..
, ..

FI .~e~

,III\. L

. All... Ip
&

.~_-~"'-I

..

.1\ ,

'.\

Prepallltion of Allgnmlnt Sheet & Drawlnge


49 50

of Allgrvlllnt fCronlng'OrI I

I.

he Ing.

Drawing.

\
\'
I

PreparatiOn 01 Crossing Drawing.


Procurement

Procurement
i
!

51

Lln. Pipes MRUllI Plpn Client Approval Requ t for Quotation Reoelpt 01 Bid. TeehJComm. Bid Analyols Client Approvsl RtoOrnmsndstion Order Plsoemlnl FOB O.lNery (Plrt)l.llot OeU'IeryIt Catting Verd lit lot FOB OIIl"llY (Ptrt) 2nd lot Delivery It Catting Verd 2nd lot FOB OelMry (Completo) OollvoryIt Coollng Site (Compllte) UnoMatoI1als MR lor UllI Ms1ertsls II Bid j",aly
I

52
53

i
i
i

II
I
I !

54

55

se
57

I,
,
prova'

58
59 60 61

0", '
\acOmenl:

I
I

I
I

Oollvery (P 1.t lot \ Ilvellf at Coati , g YOId 1st lot Oolivillf

62
63,

a ) 2nd lot

IVOllf .t Coo log Yerd 2nd lot!

64 65 66

i B OollvI'Y ( , amplet.) ellf ai C ting alto (Complol.) I i . Unt Matarlala i


I

II,

Request lot QuctsIIon

T k

Summary RoIIId Up TIIk

..J

Rolled Up Progroll
Spill

Bins Kola plpallno project : 24 M ( Mooh compl) + 3 M Comm Dot.: Sot 4128107

Cr!IlceI Tllk

Rolled Up Crttlcal T,ok Rolled Up _,,. Page 3

Exlemol T ",

1'It'!~Il~lki'l

(>

Projocl Summlry

.......

E3:Bharit Petroleum CorporatIon limited

,'

'- '

"

'---'

".'

'\'

t. 1

"
.'

"I
(

~)
T""\._

\j
'

U
.

()

.J.Y':\-,b! . TechJComm. Bid Analyail Client ApplOVll Recommtnd8llon Orelsr Piloement FOB Dellvlry (Part) Dellvery II Site (part) FOB Dellvsry (Complell) 9 D8I1veryIt Slle (Completl) Scrapper l.Aunchor & Receiver 10
11

:-i

..,... .c.--=L'~ ..... -,L-;:'-~


,. .01$ i'

. .;....,..

.....

--

~_i

( I

,
,

,,
I

, ,,

omm. Bid An IYlta


i provIll
i

tlc)n

very (port) It Site (Port) OalIvery (Complete) Ivery It SIle (Compllte)


pper Launcher ~ Receiver

i
I

MR..scrapper l.Iunchllr Cllsnl ApplOVII Rlqueat for Quotation Rec8lplof Bldl TechJComm. Bid AnaIyaII Client ApproV81
Recommendation

Launc:her

, , ,
I

I
I I r QuotlU?n IBIdI
I

I,
i

92
83

!
lBldAn

84
85

y81.

ro"l!

88 87
85 811

ndlUDn

Ordsr Plaoemsnt FOB Delivery Receipt It Stte Melnllne' 800_ Pwnpe " ..,., I' Booater .
oJ

Ivlry te I Mllnll e' 8oo~r umpl

! i

I
Pumpl

MR-MsInline & Boostar Pumps

i,
j
Rolled Up progra Spltt
ExtImal Taaka

Teal<
BIni - Kola plpellne project :

Sunvnery Rolled Up Teak

24 M ( Mech OOmpl) 3 M Comm


Olte: Sat 4I28!07

CrItlo8lTIsk Prog . Mllutone

Rolled Up Cdtlco ITuk Rolled Up MlioIl,,",, Pege 4

~~;;I4'~'iI)lj!1

Project Summlry

.......

E4:Bhl",t Petroleum CO'l'Ora\lon L1m~ed

,/
\!,.,

'

,,
~'.
Rttqu t for QuocatlOn
~-' (; ~ .. f)
I ~

~;
I

~,

.,

~J

~J

'~L::::-~~l..r~!:;!"a. -.'!ll- -,1.l,.. .l.l,..l


or'Ouot.lion olBldt

,
(J;;'

ly' SJ'-'

, ,

Receipt 15 16
17 16

or Bid.
onvn.lUd

TeohJCOmm. Bid AnaJyaIa Client Appl'OVll Recommondatlon Order PIIoomont FOB D.llvlry

I
yll.

.""

,
LC

, , ,

, ,,
\

,,
.,

I
;

"'-

Ap~V~1
dolIIon

I
i
, I Slit Cabl.

P'-nont

00
01

Rapt

at Slto

Optical Fibre Cabl. MR-OptIoaI FIbrt Ctblt Cltonl Approval Roquttl for Quotation Rapt of Bidt

I
I

02
103 104

105 106
107 106 109 110 111 112 113 114 115

TechJCOmm. Bid Analyala Clltnt Approval Rooommond.llon Ordtr Plaotmtnt FOB OtIlvary (Pill) Recelpt.t S~. (Pill)
(port)

FOB Dallv.ry (Fuji) R-'PI at Slto (fuJQ M

(Full)

III (Full) ng Syatom i

M.llr1ng Sylllm MR-MtltrIng syatom

,,;

Tule line Kola plp.llno proJooI :


l4 M ( Mech compl) + 3 M Comm )010: Sot 4126/07

., RoIItd Up Tule

Roliod Up Progr
Spltt
Ex1emtl Taakt

CrIIlooJTule Progrooo MIIettono

RoIItd Up CrIIlooJTule RoIItd Up MI1ttIDnt PIgt S

1D~9f.;:
ES:Bhanlt Potroloum COrp<lnlllonlImltod

P,oJoel Summory

......

J",,,,,,

'

'..I

"

'J

"'IQ
b

IT!l-O<_"'tl,~.,

" Requllt for Quolatlon

117 118 119 120 121 122 123 124 125 126 127 128 129 13(l 131 132 133 134 135 136 137 138

;
Reeelpt of Bldo Toch.IComm. Bid AnoJyoIa Client Appf'OVll RtcoIl1IntndatIon Order PlIotment FOB Ottlvery RoooIpt II SIIa al81lal Tllecom 8y.wn MRToloeom Syalom Client Approval Requoal for Quotatlon RIlOOi,ol of Bids ToohJComm. Bid Anaiyals Client Approval Rocommondatlon Order P~ent FOB Ottlvery RoooIpt It Sita SCAIlA APP8 8yotom MR-SCAOA & APPS CUonl Approval Ivary
pt atalla
i

!
i

II
,I ,,
I

,, ,
;

8yotom

I
I I

! !
yals

i
i

! !

,APP8 8yllom

I
!

TuI<

SUll1IMIY

Rolled Up progr
Spill

81na . Kola plpollna prolset : 24 M ( Mach COmpl) + 3 M Comm


DIlo: Sat 4/28/07

Cr1IIcaITask Progr MJioalonI

RoIlod Up Took

RoIlod Up Cr1tIcII'full RoIlod Up MiIooloI11 PIQo e

Extama'Taaka

tt~~i~~'t1iIll:;:j.I;':]

(>

Pr<>JsetSummary

.......

El3:Bharat Petroleum

Corporation Limited

~,

"

,~ IT-,,.. /\)" ....


140

'.J

\)

LJ "

1 )

I)

I'

,,

()

t;.

'}

")

.~t.'"1 AI .. QI... ~ilOl.

-r"

Q.\, .
.

.J~,,"."_'.j..I., t.JJl..;
,'i:

'J

~)

lJ

Ij

'(J

Ii

'fJ

lj

'f)

()

'J

IJ

~;,~I:'~,J_~~-+"'~~-=:_~'----';_~
Q

, J

,,

"

. .
,

oq"".\\..

Receipt of Bide TeohlComm. Bid Ana/yl1& Client Approve!


Recommendation

RAtcolpl 01 BI

141 142 143 144 14S 1-lC1 147 148 1411 150 151 152 153 '54 155 156 157 156 ,sg '50 151

Order Placement FOB DelIve1y DoIIv~ R_pt M.V.Packagl MR-M.V.PaclcIge Client Approve! Requeet for QuoleUon Receipt of Bide TeohJComm. Bid Analysla YIII) Client Approve! RlCOmmtndat1on Order Piaoorrwnt FOB DelIVery(Plrt) R_pt II Sile (Part) It Sile ptat8"o

.V.Package ,

Ii
i
I

I ,
;

I
IV'/(Plrt) at 81to (Plrt)

FOB Delively (Full) R_pt H.V.Packago .Package MR-H.V.PaclcIgo V.PoCkigl Tool< II Sile (Full)

DollvllY (Full)
pt at 8110 (Full)

I I I

,
;

Summary RoIlod Up Tool<

..J 0

Rolled Up Progro Split E>dornaITee" Project Summery E7:Bhlrol Petroloum Corporollon Umttod

Blno - Kola plpellno project : 24 M ( Moch COmpl) + 3 M Comm Deto: Sot 4/28107

CrIUoalTee. progreu MJJoilono

RoIlod Up CI1!looITool< RoIIod Up MIIooIono Pogo 7

'1
I-

,)

::Y'

.,,,,

\J

LJ

'\'

I)

1.

I. ,

1)

,)

'j

1;.

'(

I .

~J.~L,\.t~~".l1J.!A:l# l/'''~ '~':l~~;'.~' 4' '4'''~-'''~' ~"-'~ I

t.

~.

3
4

,i

nl .. ppr..;".1 ,

'"

-l ~

(,

, ,,

.
I,

,,

Roque.l for QuolIUon Recolpl of Bidl


,\

Toch,JComm, Bid Analyolo Cllont ApplO'lal Reoommondotlon Order Placemont FOB D.iIvIIy (Part) Racelpl It Site (Plrt) FOB DtlIvory (FuIQ

.1.
I

; ,;

(Plrt)

ii

illite (Plrt)

I
ory (FUll)

2 '3 14 I~ Ie T7

RocoIpl.t Site (Full) Tumk.y lnotrumontallon MR.Tumkoy lnolrumonlatlon CII.nt Approvol Roqueol for Quotation Receipt of Bido TochJComm. Bid AnlJyola
BId
'"

i pi a181

(Full)

key lnotrumon"Uon n

16
79

yola

CllonlApplO'lal ROOOIlIl11ItldIt OrdltPIaowtnl


t

eo
51

62
53 54

I
(Port)

FOB DtlIvoty (Part) RocoIplll Site (Pill)

I
I

at "" FOB DtlIvoty (Full)

(Port)

Full)

Took In Kol. pipeline proJoot : 4 M ( Mach OOmpl) + 3 M Comm


.le: Sel 4126107

Sumrnory RoUod Up Took

Rolled Up Progro
Spirt

Cr1ticoJTook progruo
M1J1IloI1o

Rolled Up Cr1tIcII Tuk RoUod Up MIJootono

<>

EJdorn., T ko
Pre)act Summ.ry

~ ~

....

PIG. 8

E8:Shll'lt P.tro~um Corporatlon Limited

'.'

'J \
,"
.",,,

'I

\ ..J

_J

'I

\1

" ~'A '..::'-I.J


1,_~1 ~ 'I~ .-1'-':...1.:-)" L" ',::

1.-

g'_

c-

10.

~.Co,pt" olt. I' .11)

"

~'....J",:\l~t1--ll"'.J-.~J.'

...... '

188 187 188 1811 IgQ 191 192 193 1~4 1~8 1~8 1;7
1;8

Surgl RIIII' Valv MR-Surgl RIIIII Valv Cllint Approval RequlIl for Quotation Receipt 01 Bldl. Teoh.(Cornm. Bid Analysis CUentApproval R-.nmendaIIon Order P~ent FOB Dellvl/)' (Plrt) Receipt It Site (Part) FOB Delivery (Full) Reoelpt It Site (FuIQ Control Vllv MRoControlVllvea CUint Approval Requlll for Quotatlon RlOll/pt of Bidl TIOIlJComm. Bid AnaIyela CUentApproval R~ Order Placement

I,
i I
1
I

. II'- .t'$.. (F\.'1


1

Urgl Rlllif Valv I


i

!
I
I

i
i

i
ety (Part) pt It aile (Plrt) DelIVlry (Full) plat 6RI (FuR)

I
I
I
I

I
I

1~ 200 201 202 203 20-1 205 206 207

I i I,
I

trol V.lv

I
I , I I ,

,I

I
II
II

i,
I

I,
1Yelal

i
Till<
Summery ~

Rolled Up Pro;reea
Spltt

Blna - Kola plpellnl projocl : 24 M ( Mech compl) + 3 M Comm Dell: Sit 4128107

CrUlcaJTIal< progreaa MUee\ona

Rolled Up Till<

RO/ladUp Cr1tIoolTill< RoUedUp MilIIl4no

Exl4m1'TI""

~~lJ.m:i
E9:Bharat Petroleum Corporation Limited I

Projoot Summlry

,,

.,
-208
20g 210 211 212
213

, J

1 ,

.
I

,,

"

Receipt It 5110(Part) FOB O.Uvety (FUIQ Receipt It S~I (FuIQ Full Boro Boll Volvu MR-Full BOft BollVolv Cllont Approval Roqutolfor Quotatlon Rooolpt or Bid. ToohJComm. Bid Analyal. Client .l.pprovol RooommondolJon Order Plooomont FOB Oollvory(Port) Receipt at Sito (Part) FOB Otllv.ry (Full) R~a1 SItAI (FuIQ 'I ulllo I Boll V.lvu

214 215
216 217 218

vol

iI
I

Quototic n fllds Iyolo

21g 220 221 222 223


224

225 228 2Z7 226


22g

Inaul.lIon Jolnts

MR-lnaulollon Joinlo CIItnl Approval RoqUMIlor Quotation Receipt of Bid.

nJotnto
01

I r QuollUon I lido

230

Tooh./Comm. Bid AnoiyIIo

I
IIId

yolo

Till<
Blna Kota pIpeline project :

24 M ( Meoh compl) + 3 M Comm


Date: Sat 4128107

P-

Summary RoIIodUp Took

Rolled Up Progr Split EldamoI Tooko Projoc:lSwnmory


"""

Cr1tloolTook

M11ootono

RoIIodUp CrttIooIT k _ RoIIod Up MIItolDno PIge 10

<>

r~"!f$t;w::Q,[;y~ ~!',I

..

,,,

......

.,
'~
...... 1 IT.

. . . .
, ,
,

,, , ,

. . . ..
,
'

.,~,
~'~~ ~)Ll _'
l~

",Ik. .

.np)-.hdl

pp.

11\

232 233 234 235 235 237 238 239 240 241 242 243 244 245 24e 247 248 249 250 251 252 253

Recommendation Order Placem.nt FOB DoIJvery RlOtlplat Sito

I
ndetlon

Placemllnt livery

D.G.Sota and UPS MRD.G.SoIa and UPS Cllant Approval Roquoat for Quotlllon Rooolpt 0' Bldo TechJComm. Bid Anaftsls

Q.

Sets and UPs

UPS

i
,

Iysll

Cllant Approval Reoomm.ooatlon Order Placement FOB, Dallvory RaooIpt at Sitl Tendering and Construction Una pipe Coaling FIna1IaalIon of Tander Spoco:CoaUng cuw.Ap~ I of NIT/RFQ RaoaIpt of Blda ToehnIoaIl Commorolal Bid AnIIyaII i IuuI ng livery alSlta

!
T8ncs.r1ng and Construction

Tool< Bini KotI plpellna proJect: 24 M ( Moch compl) + 3 M COlnm Oat.: Sat 4128/07 Cr1lIcaITool< ProglMO MIIaItona

yala

8ulll/llllY

RolI~ Up Progr.u

RolIOdUpTool<

8plJl

RoIlad Up Cr1lIcaI Tool<_ RolIOd Up

Exlamal T ka
projoot Summary

~m~);iJ~:j;d:!;';:j~;1

_,\1 0

.......
E11 :Bharwt p.trol,um
COrponrtlon L1mlted

Pagal1

"

. -~

--,

.A 255 256 257 258 259 260 261 262 263 264 265 266 267 266 269 270 271 272 27~ 274 275 276
Recommendation Award or CO<1traol Pipeline CoaUng (111101) ReooIpt et Site Dumpyard (111101) Pipelin. CoaUng (2nd 101) RoooIpt II Silo Dumpyard (2nd 101) Plpellnl Coaling (FuU) RlOOlpt at Slla Dumpyard (Full) Una pipe LAying Flnallaallon o!Tander Clionlo Approval l8Iu. of NIT/RFQ R808lpt 01 Bide Technical I CommorcIai Bid Analyell CUenta Approval Rocommandallon Award or Contract PlptjIno laying (Part CompleUon) PI~"" Compoalto laying (Full) WOI1<a Spece:Compoalto Wo Speea:Laying

~.

..
l.q. ,~
ell

~~

..)?. =,~_'
pr. ".1

'.

"

'Jo

'

,J

I I

(lall

I
I

rd (111 101)

II. D oaUn I Sito

I yard (2nd , 101) Full) umpyard

!
i

(Full)

,,
,

n. pipe LAying ,LAy g

I
I , !

I Tlndir :S ,

ova'
TIRFQ IBldl

I,
I i

If corm"" Approvll:

II BId

Iyals I

ard of Centra t ,

LAying' , (Plrt Compl.tion)


I

In. LAying (Full)

Compo&tt.e
i

Work.

FInaIIaalIon o!Tender ClIontaApPfO\'ll

'Compostta Cu.nto

Works Approvil

.J
Bina Kola pipeline project :
24 M ( Mach campi)
+

Rolled Up Progr Split


f)tmal T k.

RoIIod Up Taak

3 M Comm

Date: Sit 4128107

RoIIod Up Cr1lIcaI Taak RoIIod Up MIloolon. Poga12

lill:r~iiWllI!1~

Proj.ct Summary

......

E12:Bharat Plltrolaum Corporation limited

\)

l J

\)

\ J

~ J

t)

')

I.,

1;

<:

",

"

. '.
ANNEXURE - VI

.~

.-

BATCH SCHEDULE AND PARCEL Sill:


BINA - KOTA BATCH CYCLE Batch sequence ( (MS E3 _ MS E4 _ MS E3 _ SKO _ ATF SKO)1 time - (HSD E3 - HSD E4 - HSD E3 - SKO - ATF - SKO)4 times ( (6023 _ 21303 _ 6023 _ 730 _ 4633 _ 730)1 time - (5742 - 8823 - 5742 - 730 - 4633 - 730)4 times) ( (12.4 _ 43.8 _ 12.4 _ 1.7 _ 10.6.1.7)1 time (13.8 - 21.2 13.8 - 1.7 10.6 - 1.7)4 times) 24 cycles

) 24 cycles

Batch size Pumping time Batch cycle time Flow rate KOTA - MATHURA Batch sequence

24 cycles

8000 416

hrs KUhr (with 2.76 MMTPA ,8000hrs, 0.83 density)

BATCH CYCLE ( (MS E3 _ MS E4 _ MS E3 _ SKO _ ATF _ SKO)1 time - (HSD E3 - HSD E4,- HSD E3 - SKO - ATF - SKO)4 times ( (5267 _ 21303 _ 5267 _ 712 - 4633 - 712)1 time - (4863 - 8823 - 4863 - 712 - 4633 - 712)4 times) ( (11.5 _ 46.6 _ 11.5 _ 1.7 - 11.3 _ 1.7)1 time - (12.4 - 22.6 - 1;~.4 - 1.7 - 11.3 - 1.7)4 times) 24 cycles

) 24 cycles

Batch size Pumping time Batch cycle time Flow rate MATHURA - PIYALA Batch sequence

24 cycles

8000 391

hrs KUhr (with 2.59 MMTPA ,8000hrs, 0.83 d3nslty)

BATCH CYCLE. ( (MS E3 _ MS E4 _ MS E3 _ SKO - ATF - SKO)1 time - (HSD E3 - HSD E4 - HSD E3 - SKO - ATF - SKO)4 times ( (4289 _ 18486 _ 4269 _ 443 _ 4633 - 443)1 time - (3376 - 7fi43 3376 - 443 - 4633 443)4 times) ( (11.4 _ 49.3 _ 11.4 _ 1.3 - 13.7 - 1.3)1 time - (10.5 - 23.8 - 10.5 - 1.3 - 13.7 - 1.3)4 times) 8000 321 hrs KUhr (with 2.13 MMTPA ,8000hrs, 0.63 density) 24 cycies

) 24 cycies

Batch size Pumping time

24 cycies

Batch cycle time Flow rate

'.

..

.. .
l.
.
'

1 . _. --- --

105
Bharat Petroleum Corporation Limited Bina - Kola pipeline project

. :.:~:._._---------------------.

1--..--L--

PlANT : 81NA - KOT A SECTION


SERVICE IISD, MS, SKO, AIF

-----

DIAMETER LENGTH GRADE FLOW RATE . M31HR

INCHESlNB
KMs

18 265 AP\5LX.{;5

GRADE
.

OPERA TlNG PRESSURE KGlCM2g

250

IMXN.IoI

600

NOilMAl 6-75 25.0 84.0

OPERATING TEMPERATURE. DEG C DESIGN PRESSURE KGIC/ootIg

DESIGN TEMPERATURE, DEG C BURIED PORTION OVERGROUND PIPE PORTION

45.0 65
.

.. .

MATERIAl FOR PIPEUNE CORROSION ALlOWANCE_ PlPEUNE SHALL BE SUITABlE FOR PIGGING

CS
u.o

YES (FOR IHTELUGEHT PlGGING)

T
CATHODIC PROTECTION REQUIREMEKT

I
YES (BURIED PORT1ON)

NOTE: 1. SUITA8l.E EXTERNAl. COATING AND CATHODIC PROTEC11DN SYSTEM SHAll BE PROVIDED FOR PROTECTION AGIIdIlST EXTERNAL CORROSION

-.

,.,
if

IlHARA.T PETROLEUM CORPK. LTD.

PIPE1.INE

PROCESS DATA SIIEET lIlNA KOTA PIPEUNE PROJECT

DataSheet 1

-:k~'_.
-""""-------------,

_
--

-'-

PLANT:

BINA - KOTA SECTION (PHASE I)


TYPE OF pUMP BOOSTER pUMP (~ CENTRIFUGAl MS,SKO,HSD,ATF 15-45 0_45 - 9_17 0-1-0,7 AT 38 DEG C 700-870 NO NO

T
OPERATING UNITS : 1 STANDBY: 1 PROPERTIES OF LIQUID LIQUID HANDLED PUMPING TEMPERATURE VISCOSITY AT PUMPING TEMPERATURE VAPOUR PRESSURE AT PUMPING TEMPERATURE LIQUID DENSITY AT PUMPING TEMPERAT1JRE PRESENCE OF CORROSIVE I TOXIC COMPONENTS SOlIDS IN SUSPENSION POUR POINT (FOR CONGEAUNG SERVICE) OPERATING CONDITIONS FOR ONE PUMP FLOW RATE MAXIMUM MINIMUM SUCTION PRESSURE ~SCHARGEPRESSURE DIFFERENTIAL PRESSURE ~FFER~PRESSURE NPSH AVAIlABLE

DEGC CS KGlCM2A KGMl

DEGC

M31HR M31HR KG1CM2 A KGlCM2 A KG1CM2 METERS METERS

6lXtO 25110 1_0 6_0 5,0 62 1

NOTE -2 IoLC lA-C NOTE -2

CAPACITY CONTROl FOR VOLUMETRIC pUMPS - METliOOOF CONTROL TYPE Of CONTROl CONTROl RANGE PREClSION-A+-MlNlMUt.tRA TE MECHANlCAl. DATA DESIGN PRESSURE MAXIMUM SUCTlON PRESSURE DESIGN TEMPERAT1JRE MATERIAL OF CONSTRUCTION CASING IMPELLER SEAl. TYPE UNERATING DRIVER

KG1CM2 G KG1CM2 G DEGC

a5 1-0 65

cs cs
MECHANICAl SEAl. SUCTlON 1501 DISCHARGE 1501 ELECTRIC MOTOR

STEAM T1JRBINE DATA INlET PRESSURE KGICM2 G INlET TEMPERA T1JRE DEGC DESIGN PRESSURE KGICM2 G DESIGN TEMPERAT1JRE DEGC EXHAUST PRESSURE KG1CM2 G LINE RATING SUCTION DISCHARGE NOTES: 1. THE PUMP SHAl.l. BE SUITABlE FOR All PETROLEUM PRODUCTS "THE DISCHARGE PRESSURE Will VARY FOR DIFFERENT PRODUCTS, HOWEVER FOR SElECTION OF PUMP ~FFERENTIAL HEAD (MLC) Will BE GOVERNING 3. THE MOTOR SHAl.l. BE SUITABlE FOR END OF CURVE OPERA TIO~ ~ All THE MATING FLANGES Will BE IN VENDOR'S SCOPE.

IlIIARAT PETROI.EIlM CORPN.. Lm.

IlOOSTER pUMP AT BlNA (PItASE-

PROCESS DATA SHEET BINA-KOTA PFeUNEPROJECT

DataSheet 2

PLANT: I
OPERATING UNITS : 1 PROPERTIES OF LIQUID UQUID HANDLED PUMPING TEMPERATURE VISCOSITY AT PUMPING TEMPERATURE STANDBY: 1

BINA - KOTA SECTION (PHASE I)


MAINLINE PUMP (BINA) TYPE OF PUMP CENTRIFlJGAL MS,SKO,HSD,ATF DEGC CS KGlCM2A KG1M3 1s-45 0.'15-9.17 0.I-O.7AT38DEGC 700-870 NO NO DEGC

-----

VAPOUR PRESSURE AT PUMPING TEMPERATURE uaUID DENSITY AT PUMPING TEMPERATURE PRESENCE OF CORROSIVE I TOXIC COMPONENTS SOUDS IN SUSPENSION POUR POINT (FOR CONGEAUNG SERVICE)

OPIERATING CONDIT1ONS FOR ONE PUMP FLOW RATE SUCTION PRESSURE DiscHARGE DlFFERamAL PRESSURE PRESSURE DIFFERENTIAL PRESSURE NPSH AVAILABlE CAPACITY CONTROl FOR VOLUMETRIC METHOD OF CONTROl TYPE OF COKTROl CONTROL RANGE PRECISION AT MNlMUM RATE PUMPS MAXIMUM MINIMUM M31HR M31HR KG1CM2 A KG1CM2 A KG1CM2 METERS METERS 600.0 250.0 5.0 70.0 615.0 780 MLC 60. MLC NOTE - 2 NOTE-2

MECHANICAL DATA DESIGN PRESSURE MAXM.IM SUCTlON PRESSURE DESIGN TEMPERATURE MATERIAL OF CONSTRUCTION CASING IMPEllER SEAL TYPE UNE RATING DRIVER STEi'M TURBINE DATA INLET PRESSURE INLET TEMPERATURE DESIGN PRESSURE DESIGN TEMPERATURE EXHAUST PRESSURE UNE RATING NOTES: I, THE PUMP SHALl BE SUITABlE FOR AlL PETROLEUM

KG1CM2 G KG1CM2 G DEGC

.84 KG 6KG

55
CS CS MECHANICAl. SEAL SUCTION llOl DISCIIARGE 60llII

ELECTRIC MOTqR WITH VFD NA KGICM2 G DEGC KG1CM2 G DEGC KG1CM2 G SUCTION DISCHARGE

PRODUCTS

2- THE DlSCIlARGE PRESSURE WILL VARY FOR DIFFERENT PRODUCTS; HOWEVER FOR SELECTION OF PUMP DtFFEREHT1Al HEAD (MlC) WILL BE GOV1ERNING I 3. AlL THE MA T1HG FLANGES WILL BE IN VENDOR'S SCOPEI

II

IlIMRAT

PETROLEUM

CORPN. LTD.

MAlNUNE PUMP AT BINA (PIIASE-

PROCESS DATA stEET BlNA - KOTA PlPEl..t PROJECT

DataSheet 3

~~~" --"~__~"'0.----------------------------,
.,

..
PLANT: I
OPERATlNG UNITS : 1 STANDBY: 1 PROPERTIES OF LIQUID LIQUID HANDLED PUMPING TEMPERATURE VlSCOSfTY AT PUMPING TEMPERATURE VAPOUR PRESSURE AT PUMPING TEMPERATURE LIQUID DENSITY AT PUMPING TEMPERATURE PRESENCE OF CORROSIVE I TOXIC COMPONENTS SOlIDS IN SUSPENSION POUR POINT (FOR CONGEALING SERViCEl OPERATING CONDITIONS FOR ONE PUMP FLOW RATE MAXIMUM MINIMUM SUCTION PRESSURE DISCHARGE PRESSURE DiFFERENTIAl PRESSURE DIFFEREHTIAl PRESSURE NPSH AVAIlAIlLE CAPACfTY CONTROl. FOR \/OlllMETRlC METHOD OF CONTROl. fTYPE OF CONTROL CONTROl. RANGE PRECISION AT MINIMUM RATE MECHANICAl. DATA ~RESSURE SUCTION PRESSURE DESIGN TEMPERATURE MATERIAL OF CONSTflUCTION CASING IMPELlER SEAL TYPE UNE RATING DRIVER STEAM TURBINE o.r.TA INlET PRESSURE INlET TalI'ERATURE DESIGN PRESSURE DESIGN TEMPERATURE EXHAUST PRESSURE LINE RATING PUMPS TYPE OF PUMP

BINA - KOTA SECTION (PHASE II


MAINLINE PUMP ( KOT A) CENTRIFUGAL MS,SKO.HSD,ATF 15-45 0.45--9.17 O.1.{).7AT 38 DEG C 7OO-a7O NO NO

... ,

DEGC CS KG.'CM2A KG1M3

-"'

DEGC

M31HR M31HR KG1CM2 A KG.'CM2 A . KG.'CM2 METERS METEIlS

liOll.O =.0 5.0 73.0 68.0 820 C 60 C

NOTE-2 NOTE-'

.,

-.<.

KG1CM2 G KG.'CM2 G DEGC

64 KG 6KG 65 CS CS MECHANICAl. SEAL SUCTION 6001I DISCHARGE 6001I ELECTRIC MOTOR WITH VFD NA

KG.'CM2 G DEGC KG.'CM2 G DEGC KG1CM2 G SUCTION DISCHARGE

NOTES: 1. THE PUMP SHAU BE SUITABlE FOR AlL PETROlEUM PRODUCTS 2. THE DISCIWlGE PRESSuRE Wll VAIf'f FOR DIFFERENT PRODUCTS, HOWEVER FOR SELECTION OF PUMP D1fFEREHJW. HEAD C) WIll BE GOVERNING I I 3. AlL THE MATlNG FlANGES WIll BE IN VENDOR'S SCOPE. I I

Ii

BHARAT PTROlEIIM CORPN. LTD.

MAINLINE PUMP AT KOlA (PllASE-l)

PROCeSS o.r.TA SHEET BINA - KOlA PI'E\.JNE PROJECT

DataSheet 4

pLANT :BINA DISPATCH STATION

I
SERVICE
TYPE NO REQUIRED

----MSJSKOIHSD/ATF PIPEUNE
PIG LAUNCHING BARREL WITH HINGED CLOSURE 1
---.--

I
DESIGN PRESSURE KGiCM2G

84
65.0 3.0 SHAll 126 BE SUITABLE FOR LAUNCHING INTEWGENT PIG IN 16" PIPEUN

I
DESIGN TEMPERATURE DEG C

I
CORROSION AllOWANCE MM

I
PERFORMANCE SPECIFICATION

I
HYDROTESTPRESSURE BODY NECK REDUCER

2Z' PIPE, lJ3AW API 51.X 65


16" PIPE, lJ3AW , API 51. X 65

2Z'. 18 BW WELDED
7.1MM SIZEQNCH) 31~ 31~ T NUMBER 1 1 1 1 1 1

I
THICKNESS

I
I

APPURTENANCES

T1HERMAL REUEF VALVE PRESSURE GAUGE VENT CONNECTION DRAIN CONNECTION UT1UTY CONNECTION lOCKER CONNECTION QUICKOPENlNG. PlATES, FORGED

:r
T 10'"

END CLOSURE

I
SUPPORT AS REQUIRED

-,
..

I)...
~,

BllARAT

PETROLEUM CORPN. LTD.

PIG l.AUNCHING BARREL

PROCESS DATA SHEET BINA - KOTA P1PEUNE PROJECT

DataSheet 5

PLANT:

INTERMEDIATE

PIGGING STATION (tNO) CH.t30

I
SERVICE
TYPE NO REQUIRED

I
MSISKOIHSD/ATF
PIG RECEIVING BARREl 1

--~-i

1
.-

PIPELINE
WITH HINGED CLOSURE

.----------

I
DESIGN PRESSURE KG1CM2G

&4
65.0 3.0 SHALL BE SUITABLE FOR LAUNCHING INTELLIGENT 126 'ZZ' PIPE. LSAW. API51X65 18" PIPE LSAW API 51.X 65 'ZZ"18'BWWELOED 7.1MM SIl(INCH) THERMAL RELIEF VALVE PRESSURE GAUGE VENT CONNECTION DRAIN CONNECTION UTILITY CONNECTION KICKER CONNECTION NUMBER 1 1 1 1 1 1 PIG IN 18" PIPELINE

DESIGN TEMPERATURE

DEG C MM

I
CORROSION AlLOWANCE

I
PERFORMANCE SPECIFICATION

I
HYDROTESTPRESSURE BODY NECK REDUCER

...
T

THICKNESS

T T
APPURTENANCES

3/' 3/'
T 3" T 10'

END CLOSURE

QUICK OPENING, FORGED PLATES, AS REQUIRED

,
,

SUPPORT (

,
,

,t
,

,
, ,

"

BIlARA T PETROLEUM CORPN. L TO.

PIG RECEIVING BARREl WITH HINGED CLOSURE

PROCESS DATA SHEET BlNA KOT A PIPELINE PROJECT

DataSheet 6

---PLANT: [ SERVICE
TYPE NO REQUIRED

.........

,11;'.".-----------

-----------.

INTERMEDIATE PIGGING STATION (1NO} CH.130

I
MSISKOIHSD/ATF
PIG LAUNCHING BARRfl 1 I<G'CM2G 114 65,0
.

PIPELINE

T
WITII HINGED CLOSURE

---

I
DESIGN PRESSURE

I
DESIGN TEMPERATURE DEG C

I
CORROSION ALLOWANCE MM SPECIFICATIOH 3D

I
PERFORMANCE SHALl BE SUITABLE FOR LAUNCHING 1NTEl.UGEJfT PIG IN 16" PIPEUNE 126
2Z' PIPE LSAW API 51. X 65

I
HYOROTESTPRESSURE BODY NECK

16" PIPE. LSAW .API5I.X65


2Z' 18

REDUCER THICKNESS

BW WELDED
"

,
,
,

.,
I

7.1MM SIZE(lNCH) J/4" 3/4" Z' NUMBER 1

APPURTENANCES

THERMAL REUEF VM..VE PRESSURE GAUGE VEHT CONNECTION DRAIN CONNECTION UTlUTY CONNEcnoN KICKER CONNECTION
.

~
Z' 1(1'

1 1 1 1

END CLOSURE

T
SUPPORT

QUICK OPENING. FORGED PLATES, AS REQUIRED

.,

,,_.

'(151.

, BHARAT PETROlEUM

COflI'N, LTtl.

PIG I.AUNCHINO BARREL

DalaS/leet 7

_.

PROCESS DATA SHEET KOTA PI'ElN! PROJECT

pLANT :TAP OFF POINT AT KOTA

MSISKOIHSD/ATF P1PEUNE
PIG RECEMNG BARREL WITH IRNGED CLOSUllE
1 -~

I
SERVICE
I

TYPE

i
NO REQUIRED

I
DESIGN PRESSURE KG1CM2G 84 65.0 3.0 SHAU BE SUITABLE FOR LAUNCHING INTELLIGENT PIG IN 18" PIPEUNE 126 2Z' PIPE ,lSAW ,APl51. X 65

, , ,
/

I
DESIGN TEMPERATURE DEG C

I
CORROSION ALLOWANCE MM

I
PERFORMANCE SPECIFICATION

I
HYDROTEST PRESSURE

, ,

BODY NECK REDUCER

18" PIPE lSAW APl51. X 65 2Z' '8 7.1MM


.

BWWEWED

I
THICKNESS

I
APPURTENANCES TllERMAl. REUEF VAlVE PRESSURE GAUGE . VENTCONNECTION DRAIN CONNECTION UTILITY CONNECTION I<ICKER CONNECTION QUICK OPENING, FORGED PlATES, AS REQUIRED

SIZE(INCH) 314" X'SO X10"

NUMBER 1
1

1
l

END CLOSURE

I
SUPPORT

( {

I"....

'~""""'m

PIG RECEMNG BARREL WlTH IINGED CLOSURE

PROCESS DATA SHEET BlNA - KOTA PIPELNE PROJECT

DataSheet 8

:-:~

,:1

;1~iIli-~IlII'->~IiI-,".<" 7 L~

f: ":~_

.~

PLANT: BINA DESPATCH STATION SERVICE TYPE PROCESS DATA FLUID HANDLED OPERATING PRESSURE KGlCM2G OPERATING TEMPERATURE DEG C DESIGN PRESSURE KGlCM2G DOES VESSEL REQUIRE FULL VACUUM DESIGN DESIGN TEMPERATURE DEGC

CORROSION INHIBITOR DOSING TANK VERTICAl I

0-

- r r
CORROSION INHIBTOR ATM 25 FUll OF WATER NO 65

0-

--

....

MECHANICAL DATA MATERIAL OF CONSTRUCTION

..
,

-.
.,
-,

-,
~
""

CORROSION ALlOWANCE INSULATION REQUIRED INO INSULATION THICKNESS IS INLET BAFFlE DEFlECTOR REQUIRED NO VESSEl SUBJECTED TO STEAM OUT CONDlTlONS NO IF 'YES' STEAM TEMPERATURE DEGC STEAM PRESSURE KG1CM2G VORTEX BREAKER REQUIRED No rtPE DEMISTER REQUIRED NO IF 'YES' REF. DATASHEET NUMBER IS DESIGN FOR NACE CODE REQUIRED NO NOZZlES AND CONNECTIONS RATING FOR VESSEL NOlZElS 15011 MARK NUMBER SIZE IN SERVICE MARK N1 1 11112 INlET N2 1 2 OUTLET N3 1 VENT 2 N4 1 2 STANDPIPE N5 1 2 STANDPIPE

SHELL SS UNER MM NIL ITYPE MM .

NUMBER

SIZE IN

SERVICE

!
<

NOTES: 1 THIS TANK IS FITTEDWIDlA VERTlCAlSUMP PUMP. 2 THESE DIMENSIONS TO BE PROVIDED BY TtF. SUMP PUMPVENDEOR. 3 THIS TANK SHAll BE INISTALlED UNDERGROUND.

.0

BHARAT PETROlEUM

CORPN. LTD.

HORIZONTAL VESSEl

PROCESS DATA SHEET BINA- KOTA P1PEUNE PROJECT

"

DataSheet9

"

.,
-.,

'~

...

PLANT SERVICE: TYPE

BINA DESPATCH STATION CORROSION INHIBITOR DOSING TANK VERTICAl

.~

",
~

SKETCH OF THE VESSEL

...,
1200 MM

~
"" ~
""
f

.. ~

N5

r-'
f

BHARAT PETROLEUM CORPN.lTD.

VlERTICAl VESSEL

PROCESS DATASliEET B1NA_ KOTA PIPEUNE PROJECT

...2':::i;'>i

f 'rI-iliiilillliiiiliiliil".'

-----------

pLANT SERVICE: TYPE

INTERMEDIATE

PIGGING STATION SUMP TANK (UNDERGROUND) .. HORIZONTAL .__ ..

. ;

PROCESS DATA FLUID HANDLED OPERATING PRESSURE KGlCM2G OPERATING TEMPERATURE DEG C DESIGN PRESSURE KGlCM2G DOES VESSEL REQUIRE FULL VACUUM DESIGN DESIGN TEMPERATURE DEGC
'.

t~~ ~.'~ ___


-~

MS, SKO, HSD, ATF ATM AMBIENT FUUL OF WATER NO

-~-

65

MECHANICAL DATA MATERIAL OF CONSTRUCTION SHEUL CS LINER CORROSION AULOWANCE MM 3 INSULATION REQUIRED I NO I TYPE INSULATION THICKNESS MM -NO IS INLET BAfFLE DEFLECTOR REQUIRED VESSEL SUBJECTED TO STEAM OUT CONDITIONS NO IF 'YES' STEAM TEMPERATURE DEGC STEAM PRESSURE KGlCM2G . VORTEX BREAKER REQUIRED T No'f TYPE DEMISTER REQUIRED NO IF 'YES' REF. DATASHEET NUMBER IS DESIGN FOR NACE CODE REQUIRED NO NOZZLES AND CONNECTIONS ,M RATING FOR VESSEL NOZZELS MARK NUMBER SIZE IN MARK SERVICE F 1 4 FEED LT 1 4 LEVEL TRANSMITTER LS 1 4 LEVEL SWITCH HIGHILOW V 1 4 VENT M 1 24 MANHOLE P 1 NOTE-2 pUMP S 1 4 SAMPLING HATCH S1 1 2 SPARE WITH BLIND NOTES; 1 THIS TANKS IS FITTED WITH A VERTICAL SUMP PUMP

NUMBER

SIZE IN

SERVICE

,
)
.i .;

I-

"
I

I
2 THESE DIMENSIONS TO BE PROVIDED BY THE SUMP PUMP VENDOR 3 THIS TANK SHALL BE INSTALLED UNDERGROUND.

)
.;

BHARAT PETROLEUM CORPN. LTD.

HORIZONTAL VESSEL

PROCESS DATA SHEET BINA- KOTA PIPEUNE PROJECT

DataSheet 10

.;..,.-

,
,,
",

>.".

, ,
...

"'PLANT SERVICE TYPE : INTERMEDIATE PIGGING STATION SUMP TANK HOTIZONT AL

....
"

SKETCH OF THE VESSEL

---

1//1/////
"

I I
HLL

! .
,

-r---- -------

~
C>
II

~l
LLL~------NOTE-21

C> C> C>

"

'5: '5:

I
14
NOTE-2

~I

--.-'

,,(i),

BHARATPETROLEUM

CORPN. LID.

HORIZONTAL VESSEL

PROCESS DATA SHEET BINA - KOTA PlPEUNE P~ECT

---------------------

-"

:.:..;.J

1'"
-!

-, .
'\..

I ~-

,I

-00.'

. ~

.1

j -

106
Bhara! Petroleum Corporation Umited Bina - Kota pipe6ne project

~
$"

~
c ~

~~ ~n g 6
I!:
Q
A~hokNagarDlatrlct

ID ~

<" z<

~i~

1) ~

~ .~"
8

i ~ ~~~ ~ID~

l1i

e ~~~ ~ i 3.
q
',,,

~"""""",",",,,"~.~~.J:!!~,~~~,~~~,~,:,~,~,!:,~,"~,~1.11 I.I . I.I .. I.~.~ . I............


t

~.~.l
,

I" ~c~.
{j

~Q

n.

~r:i

"&HUB ~$
~

!:;;;!~~" Mo

.,

~~

~i
~~

~ll

~~

iii~

~~~ ~~
~ ~~ ~~ ~ "'iii
( Kota

~:;!

~~ .

~.~~.~~!.~~~ .. :.~~~;~.~~.~ I : ...


BaranDistrict ( )

Gun. DI.trlct

.'<"

'>.,

f",~

..

"J,

1J'r~'I!c,

.'

~u Ian
,

32.3 Ian
u ~

,.u~ ,~.;:.~~;~.:~; ~ " I

I ~.U I":

oI u'" I

Lllng~h 265 Kill


Major Rivera
. Canat.
,1,"-,

.5 3
'\'.1;' , .. '~~~"!f,.

'Sliwa, Sind, Parbati, .!?arwan,Mlisind Chamb~l,~\gntMaln. Canai (Saran),NH.


~"::"
,

",:'

"

'

LEGEND
R,LY.CRG. N.H"

NH
SH

N(;\2Mi\ln~Agra),NigO '.: ,~~~~J;j 1ll(Kdta-Baran) '" , . l;,;:<:"~~h~:<,' ,

)t)~~~;;;:.~:~ SH .19 (Barkhera-Mungaoll), GunaAshokNagar SIi;SK:23 (Fataligarh_ Guna), SH~nB~ranoJhalawar) .


I,,, .. ' ,"

S.H

Raiiway crolling.
Forest

. Blna-Kota (2)& Guna-GwEDr 8.8 Krns


GAIL

RIVER CANAL

PII crossing

pipeline

,
- , -..mu. . trlll1IIU1IIl _ -

-.-

..

......,.~

1_:::::=======--------------------------------------'"
verallea
r-ea51D111C)'

J<e{X1IT

107
Bharat Petroleum Corporation Umited Billa - Kola pipeline project

Deti1i1ed Feasibility f/e{Vrt

7-~--

-----------------.
Detailed Feasibility RejxYt

22. 23 24. 25. 26. 27. 28. 29. 30. 31. 32.
33.

HDD HSEB 110 IDC IEC IRR ISDN ITU KBPL KRL LAN LCD IEEElPOSIX

Horizontal Directional Drilling Haryana State Electricity Board Input! Output Interest During Construction Intemational Electro Technical Commission Intemal Rate of Retum Integrated Services Digital Network Intemational Telecommunication Union Kandla Bhatinda Pipeline Kochi Refinery Limited Local Area Network
I,

Liquid Crystal Display Institute of Electrical and Electronics Engineers! Portable Operating System Interface Long Radius Bends Metre of Liquid Column Ministry of Environment and Forest Motor Operated Valves Maharashtra State Electricity Board Material Take Off Medium Velocity Net Present Value National Fire Protection Association

34. 35. 36. 37. 38. 39. 40. 41. 42. 43.

LR Bends MLC MOEF MOV MSEB MTO MV Spray NPV NFPA

109
Sharat Petroleum Corporation Limited Bina - ~q/a pipeline project

..

Detailed Feasibility Rf'{XIft

44 45. 46. 47. 48. 49. 50. 51. 52. 53. 54. 55_ 56. 57. 58. 59. 60. 61. 62. 63.
)

NH NMC NRL OFC OISD OLTC ONAN OMC OSF I MOTIF PABX PCB PDH PDT PE Coating PLC PMCC POH RCC RISC ROU ROV ROW RTU

National Highway Network Management Centre Numaligarh Refinery Ltd. Optical Fibre Cable Oil India Safety Directorate On Load Tap Changing Transformer Oil Natural Air Natural Other Marketing Companies Open Software Foundntion Standards Private Automatic Branch Exchange Pollution Control Board Plesiochronous Digita! Hierarc.~y Portable Diagnostic Test Unit Poly Ethylene Coating Programmable Logic Controller Primary Motor Control Centre Path Over Head Reinforced Cement Concrete Reduced Instruction Set Computer Right of Use Remote Operated Valves Right of Way Remote Terminal Unit I Remote Telemetry Unit
110 Bharat Petroleum Corporation Umited

64. 65.

.)

66.

Bina - Koiftpipe/ine -

project

..-----------------------Detailed Feasli5ly Rqxxt

111 Bharat Petroleum Corporation Umiled

~:Kota pipe(me project

,
,

16"

You might also like