Natural Gas Processing

Qualifications and Experience


2010

This document is confidential proprietary information and disclosure of any information contained herein to any third party or use of such information other than to evaluate this document is strictly prohibited.

MA G://20100517NGQual

Aker Solutions Americas Inc.

Table of Contents

Section 1 Summary of Qualifications Section 2 Gas Processing Capabilities Section 3 Gas Processing Technology Section 4 Project Experience & Selected Profiles

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 1 Summary of Qualifications


Aker Solutions has specialized in projects for the natural gas industry for over 40 years. We have substantial expertise in all areas of gas production and processing including the following: Inlet Gas Separation Slug Catchers Filters Filter Separators

Acid Gas Removal Benfield Amines (MEA, DEA, MDEA) Selexol Sulfinol Ryan Holmes Mol Sieve Membranes

Sulfur Recovery Claus Plants Super Claus Plants SCOT Tail-Gas Units Strefford LO-CAT

Dehydration Glycol Drizo Molecular Sieve

NGL/LPG Extraction and Treating Refrigerated Lean Oil Plants Cryogenic (turbo-expander) Caustic Scrubbing Merox

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 1 Summary of Qualifications (cont.)


NGL Fractionation LNG Import Terminals Export Terminals Liquefaction Ethane Production Ethane/Propane Production Propane/Propylene Splitters Iso/normal Butane Splitters Isobutane Production (Engelhard and UOP) Deisopentanizer

Nitrogen Rejection and Cold Box Design Compression Reciprocating Machines Centrifugal Machines Screw Type Machines

Gas Plant Simulation Software Used by Aker Solutions Software HYSIM/HYSIS Pro II (Simulation Sciences) SPED (Bryan Research) T-Sweet (Bryan Research) AMSIM (DB Robinson) Sulfur Recovery (Amoco) Entire gas plant simulation Fractionation, expander plants, and dehydration Sulfur plant simulation Amine plant simulation Amine plant simulation Design claus sulfur plant according to the Amoco technology Use

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 2 Gas Processing Capabilities


Aker Solutions has specialized in projects for the natural gas industry for over 40 years. Aker Solutions experience in gas processing work undertaken during recent years involves the whole range of engineering and management skills from conceptual design through to start-up and operation. Study work and FEED package preparation is often part of a large project where Aker Solutions has gone on to do EPC scope or continued as the clients project manager. Gas Processing Plants The gas treatment plant consists of several components that are typical of most plants. The design of these units is studied in some depth to create a flowsheet of the overall plant that meets the economic and technical optimization criteria imposed. Slugcatchers Slugcatchers from small single vessels to large multi-finger units have been designed and built by Aker Solutions. The recent Conoco Syria unit was a multi-finger unit with a capacity of over 400 m3. The Conoco Theddlethorpe units were 800 & 1300 m3 (5,000 and 8,000 bbls) finger units, and the British Gas North Morecambe project has a large single vessel. The S. Pars design is for 4800 m3 (30,000 bbls) and the Taweelah gas plant slugcatcher is 10,000 m3 (60,000 bbls). Our past experience with various types and sizes of slugcatchers provides the depth of knowledge Aker Solutions has in the design and construction of this equipment. Gas and Liquid Separation Gas and liquid separation using horizontal and vertical separators, with or without internals, are common components designed by Aker Solutions. For separators with proprietary designs of coalescing vanes or packs, specific equipment providers contribute to the design. Aker Solutions has developed certain proprietary technology in designing compact separators. Acid Gas Removal The range of processes offered includes physical and chemical solvents. Aker Solutions has designed straightforward MEA and DEA units and under license proprietary units such as Benfield, MDEA, Sulfinol, Selexol, Ucargol and other activated MDEA depending on bulk removal or partial removal. Molecular sieves and membrane systems for special removal services have also been addressed. The Petronas project included an in-depth assessment of all the available processes followed by the evaluation of the selected process. (Refer to recent Acid Gas Removal projects at the end of this section.)

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 2 Gas Processing Capabilities (cont.)


Gas Compression Gas compressors with electric motor and gas turbines drivers like the RR RB211, GE Frame machines and LM2500s is a common part of the evaluation of the processing plant. The evaluation of compression alternatives often includes the determination of onshore and offshore options in conjunction with the pipeline options. This aspect was considered recently on the Theddlethorpe, South Pars and Taweelah projects. Dehydration and Hydrate Suppression The choice between dehydration using glycol, methanol, or molecular sieves is usually decided by the downstream processing requirements. Molecular sieves are normally utilized in cryogenic NGL/LPG Extraction plants where water concentration must be reduced to ppm levels. Aker Solutions can provide a wealth of experience in the selection of proper hydrate inhibition methods. NGL/LPG Extraction Aker Solutions has substantial experience in all areas of gas processing operations including NGL/LPG Extraction from natural gas streams. Aker Solutions experience in NGL/LPG Extraction processes from natural gas streams includes refrigerated lean oil absorption plants, high pressure straight refrigeration units using external refrigeration, cryogenic J.T. expansion plants and cryogenic expander plants. Aker Solutions has developed different cryogenic processes for extraction of NGL/LPG from natural gas including very high ethane and propane plus recovery utilizing turboexpanders. NGL Fractionation Aker Solutions has substantial experience in fractionation system design for separating ethane, propane, butanes and pentane plus products. The NGL fractionation systems designed by Aker Solutions are optimized for energy efficiency and capacity utilization. Our design experience includes new fractionation systems ranging from 20,000 barrels per day to over 100,000 barrels per day of inlet throughput. Aker Solutions has also worked on many capacity increases of the existing fractionation systems. Substantial increases in throughput have been achieved from upgrades of existing fractionations for Enron and TransCanada. Our experience includes butane splitters with heat cycle Aker Solutions has achieved as for energy optimization. We have also designed the much as 50% increase in the butamer units for converting n-butane to iso-butane and existing fractionation systems by integrating the butamer unit with the main fractionators carefully analyzing the existing units to achieve the overall fractionation system efficiency. In and making necessary modifications order to meet the final product specifications, product which saved substantial capital cost treating is required. Aker Solutions has experience with for the upgrade. the removal of impurities like CO2, moisture, H2S, COS and mercaptans from the various products to meet the required specifications. These methods include caustic, non-regenerables, and scavenger processes, as well as regenerable processes like molesieve for final product treating.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 2 Gas Processing Capabilities (cont.)


LNG Aker Solutions LNG experience has evolved from an impressive background in overall gas processing. Aker Solutions has specialized in projects for the natural gas industry for over 40 years. Our experience in gas processing work undertaken during recent years involves the whole range of engineering and management skills from conceptual design through to start-up and operation. Study work and FEED package preparation is often part of a large project where Solutions has gone on to do EPC scope or continued as the clients project manager. Our experience includes import/export terminals and liquefaction facilities. We design all LNG facilities per NFPA 59A and all worldwide industry-accepted standards. Sour Service Equipment and Materials Aker Solutions always considers materials selection for equipment and pipe to NACE requirements for sour service. For this type of study our specialists group can offer the necessary expertise to meet the requirements of the project. Sulfur Recovery Sulfur recovery in sour gas processing plants often requires the assessment of Claus type units and tail gas clean up. This has become more important now that there are tougher controls on flaring. Aker Solutions recent experience in sulfur recovery units (SRU) and tail gas treating units includes small units like 60 tons per day SRU units for Shell Offshore in Alabama with SCOT tail gas treating units. On the large scale units Aker Solutions is involved in design and construction of three (3) trains of 400 tons per day each SRU units with a single RESULT tail gas treating unit for SINCOR in Venezuela. Aker Solutions experience also includes the various enhancements of SRU including Superclause units. Additional tail gas treating experience not only includes the H2O based processes like SCOT and RESULT units, but also includes SO2 based and other processes like liquid redox. Utilities and Offsites Utilities such as vent and flare facilities, steam, hot oil, fuel etc. have a significant contribution to the economics of a process and local conditions are always different with each plant. Offsite facilities such as tankage and run down lines require process definition. Aker Solutions is well positioned to provide needed assistance to our clients in helping with the utilities, infrastructure and logistics. Aker Solutions has delivered substantial cost savings to our clients by offering dedicated teams to focus on delivering utilities and off-site project scopes to support larger capital programs.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 2 Gas Processing Capabilities (cont.)


Deep Ethane Recovery Aker Solutions has developed different cryogenic processes for the extraction of ethane from natural gas including very high ethane and propane plus recovery utilizing turboexpanders. Aker Solutions has considerable experience in dealing with the design of the high ethane and propane plus recovery process utilizing new as well as existing gas plants. The technical and economic considerations for the process facilities to be incorporated into the existing gas plant are different from those relating to new installations. Aker Solutions has field-proven design for high ethane and propane plus recovery processes. These processes can have many variations depending on the ethane plus content of the gas and the inlet conditions. The general outline of most of Aker Solutions-developed processes for high ethane and propane plus recovery using turboexpanders is provided in the following text. The basic process involves the dehydration of the inlet high pressure gas using fixed bed molecular sieves to remove the water to less than 1 ppmv. The bone-dry gas is processed in brazed aluminum heat exchangers to cool the high pressure inlet gas with the low pressure methane-rich residue gas. Normally a complex heat exchanger train is used to conserve the cold refrigeration from the process to minimize the external refrigeration. This involves prefractionation steps in the demethanizer column to recover the coolant from the cold NGL liquids. The high pressure cold inlet gas is separated from the condensed liquids and is expanded using the turboexpander. The expander not only helps provide the cold refrigeration in the process to condense the ethane and heavier NGL liquids, but also recovers the useful work to compress the low pressure gas to minimize the compression horsepower. The cold fluids from the expander discharge and the high pressure separator liquids are fed to the demethanizer to remove the methane and lighter components from the ethane and/or propane and heavier NGL liquids. Aker Solutions high ethane recovery processes utilize an internal or external reflux system to provide the cold lean reflux for the demethanizer. These processes provide high ethane recovery, higher energy efficiency and lower capital costs. Normally the demethanizer has a side reboiler and bottom reboiler integrated in the inlet gas heat exchanger train to recover the refrigeration and also reduce the external heating requirements. The low to medium pressure methane-rich cold residue gas is heat exchanged with the high pressure inlet gas as described above to recover the refrigeration. This residue gas is usually recompressed with the turboexpander-driven compressor. The residue gas is finally compressed to a pipeline pressure using additional compressors. In addition, the front-end facility may include H2S/CO2 removal and mercury removal depending on the level of these components present in the inlet gas and the recovery level for the ethane. Aker Solutions designed the high ethane recovery process using the turboexpander for Petronas in Malaysia, Enron in the U.S, and Santos Ltd. in South Australia. The processes for these locations have been proven in the field as designed.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 2 Gas Processing Capabilities (cont.)


The high ethane recovery processes designed by Aker Solutions are one of the best in the industry. They are well proven processes. Our thermodynamic and physical property data in processes for light hydrocarbons are mature and proven over the last 15 years. It is important to recognize the thermodynamic behavior at high pressure and low cryogenic temperatures for the high ethane recovery processes. The coldest temperatures in the process vary from -140oF to -160oF. At these cold temperatures it is also important to understand the CO2 freezing characteristics. The feed gas pressure and composition also play a predominant role in the process design. Apart from feed gas compositions and conditions, the amount of impurities, the product specifications and the recovery level play an important role in the process selection. Our experience in the NGL and LPG extraction plants, especially in the high ethane or propane recovery processes from the natural gas using the turboexpander, is built around the ability to meet the challenges of the industry.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 3 Gas Processing Technology


The following text is a summary of Aker Solutions resources and capabilities in gas processing technology. Some of the proprietary and open-art technologies in gas processing that we have been involved in are described below. Additionally, Aker Solutions has excellent NGL/LPG fractionation expertise. Aker Solutions has also executed various projects in past utilizing third party proprietary process technology such as Ortloff in the NGL and LPG liquid extraction area. One of the recent projects completed for PETRONAS and PTT joint venture in Thailand where Aker Solutions engineered and managed construction utilized Ortloff OHR licensed process. Proprietary and Open Art Technologies The following description provides Aker Solutions experience in the gas processing, especially cryogenic liquids recovery (ethane and/or propane recovery) technologies: High Pressure Absorber This design, developed by Aker Solutions, was utilized for the Statoil Kollsnes gas processing plant expansion. It is a cryogenic expander plant for NGL/LPG extraction. The process is energy efficient and allows utilization of a single train approach for inlet capacities over 1.4 BSCFD. The process can tolerate higher CO2 in the inlet gas feed as well as much lower overall compression power compared to many other technologies at present. The design configuration allows a larger capacity train while keeping the process energy efficient. Aker Solutions designed the plant, taking the availability and constructability of larger equipment into consideration. The selection of materials of construction for large vessels and columns was developed consistent with large vessels and columns constructability at higher design pressure and cryogenic temperatures. The plant also utilized large compressors for high pressure gas compression using variable speed electric motor drivers. Methane Recycle This design was used in the PETRONAS Gas SDN BHD project. The process design for two trains, 700 MMSCFD each, was developed by Aker Solutions engineers to achieve very high ethane recovery combined with high demethanizer pressure to achieve significant tolerance to CO2 in the plant feed. The process design for this facility also included the flexibility to run in an ethane rejection mode with very high propane recovery, as well as minimum liquids recovery for dewpoint control only. Cold Separator Split Similar to Ortloffs GSP design, this process was developed by Aker Solutions (previously John Brown) in the early 1980s and successfully installed in Santos Ltds Moomba Gas Plant in South Australia. This plant processed 900 MMSCFD of rich, high CO2 gas with an ethane recovery in excess of 80%.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Section 3 Gas Processing Technology (cont.)


GSP This design has been used in a number of Aker Solutions projects. In Enrons Eunice Gas Processing plant, it served to improve ethane recovery, while in the Teesside Plant in the U.K. it was used for high propane recovery. This design has in the past been protected by a number of patents; however, most of these have expired. Pre-rectifier This is an expander process design for high propane recovery in which recoverable hydrocarbons are absorbed from the expanded feed gas using light hydrocarbons as absorption medium. Among others, Aker Solutions used this design in the ethane rejection mode of the PETRONAS Gas SDN BHD project listed above. Refrigeration Under certain circumstances, especially on upstream projects, Propane Refrigeration may be the most economical process. Aker Solutions has successfully executed many of these projects including the Shell Yellowhammer Plant. The revamp of TransCanadas Eunice Gas Plant included debottlenecking of a 250 MMSCFD cryogenic liquids recovery plant that utilizes ethane refrigeration to generate demethanizer reflux. Aker Solutions has a long successful history of gas plant design and has built gas plants using a wide variety of liquid recovery processes. In addition to those listed above, these include Double-Expander, LSP, and Packed HP Separator. Most of these processes are no longer considered competitive or are applicable only in very specific circumstances. Aker Solutions also has extensive experience with Lean Oil Absorption plants. While in most new gas processing plants cryogenic designs have replaced lean oil absorption, in special circumstances absorption is still viable, and Aker Solutions has recently designed lean oil absorption plants. Furthermore, Aker Solutions has been involved in debottlenecking and the expansion of existing lean oil plants, some of which were originally built by Dresser Engineering, which became part of John Brown, a predecessor of todays Aker Solutions. Grass roots Lean Oil Absorption Plant designs include:

Lean Oil Absorption facility for Nasr Petroleum Company, Suez, Egypt (1997-1999). This
project is a vapor recovery unit in a hydrocracking complex. It recovers 85% of mixed LPGs from the hydrocracking units off-gas. Lean Oil Absorption facility for Statoil in a confidential location in the FSU. Aker Solutions performed conceptual and basic design as well as a TIC estimate. Capacity was 400 MMSCFD, with propane recovery of 70%. Refrigerated Lean Oil Absorption facility (Khuff Gas Development Project, Abu Dhabi, UAE) for Abu Dhabi National Oil Company (ADNOC). Plant capacity is 540 MMSCFD. Butane recovery was 85%-95%, with a maximum propane content of 35%. Condensate vapor pressure was 8 psi maximum.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

10

Section 3 Gas Processing Technology (cont.)


Debottlenecking and Front-End Projects include:

Refrigerated Lean Oil Absorption Facility (Eunice Gas Plant, Louisiana) for TransCanada.
Capacity of the lean oil plant was approximately 400 MMSCFD. Aker Solutions scope included debottlenecking for additional throughput as well as optimization. The plant recovered 35%-40% of feed ethane and 90% propane. Refrigerated Lean Oil Plant (Henry Gas Plant, Louisiana) for Texaco. This plant was originally built by Dresser Engineering. Aker Solutions performed process design work for Texaco including simulation of the lean oil plant. The plant has a capacity of 1,000 MMSCFD in two trains. It recovers 40% ethane and 93% propane. Refrigerated Lean Oil Absorption Plant (Gregory Plant, Texas) for Enron. Aker Solutions developed the simulation model for this facility for troubleshooting and optimization. The plant recovered 85% propane with mild refrigeration (20F).

Nitrogen Rejection Technology Aker Solutions also had one patented cryogenic Nitrogen Rejection Technology; however, the patent will soon expire and there is no plan to renew or resubmit at this time. Aker Solutions personnel have executed some projects in this area using other proprietary and open art technologies. Molecular Sieves Aker Solutions designed numerous plants using molecular sieve in gas and liquids service. Plant capacities up to 1,500 MMSCFD were included. Our experience includes high and low pressure regeneration as well as with and without mercury removal. We are experienced in the design of molecular sieve units with 3A and 4A mole sieve for gas dehydration. We have design experience with specialized operations for reduction in COS formation. Some of our past design experience includes special design considerations during regeneration of molecular sieve beds in which small amount of sulfur and oxygen is present in the inlet feed gas. TEG Aker Solutions has carried out many designs involving TEG as a drying medium. Some projects included using stripping gas or proprietary process enhancements such as Cold Finger, which was used in BPs Cupiagua project/Columbia and Amocos Bairoil CO2 Cycling plant. The Drizo process was considered for the design of the Enron Teeside facility and ARCOs China offshore project. Ethylene Glycol Injection Aker Solutions has used this simple design to achieve dewpoint suppression in less demanding services. This method was used for ethane drying for the PETRONAS Gas SDN BHD project.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

11

Section 3 Gas Processing Technology (cont.)


Methanol Injection This method of hydrate control has been used in several subsea pipeline projects. Aker Solutions design included methanol recovery, reconcentration, storage, and export to the offshore injection location. Projects include the 290 MMSCFD Caister/Murdoch onshore facility and the 210 MMSCFD Pickerill Gas Terminal (Conoco, U.K.). The following are mercury removal technologies with which Aker Solutions has experience. Mercury removal has been part of most of the cryogenic gas processing plant projects. Mercury Removal As part of feed pretreatment, it is necessary to remove mercury if present in the feed gas to avoid corrosion with brazed aluminum heat exchangers. Aker Solutions has designed many mercury removal systems (MRS) since 1990. Our experience with MRS includes the following:

Sulfur impregnated activated carbon adsorbents Metal sulfide systems Metal sulfide/oxide systems
Most of our systems for MRS from natural gas are based on sulfur impregnated activated carbon absorbents. The liquid systems MRS are based on metal sulfide on alumina or carbon substrate or metal oxide/sulfide based systems. We evaluated gas and liquid phase regenerable molesieve (zeolite) systems for MRS, but in most cases these systems were not installed. Experience Using Licensed Technologies Aker Solutions experience with gas processing technologies is described in the previous section. To our knowledge the methane recycle process is not proprietary. GSP, LSP, and DoubleExpander designs were patented by Ortloff Engineers, Ltd.; however, these patents have expired. It is possible that certain configurations of the pre-rectifier process may be covered by patents in some countries. The Lean Oil Absorption Processes are not proprietary. Cold Finger Technology is licensed by Gas Conditioners International Co. Drizo is licensed by OPC Drizo Inc. We utilized these technologies on BPs Cupiagua and Enrons Teesside projects, respectively.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

12

Section 4 Project Experience


Section 4.1 Section 4.2 Section 4.3 Section 4.4 Section 4.5 Section 4.6 Section 4.7 Worldwide Project Locations Onshore Oil & Gas Scope & Project Type Table LPG/NGL/LNG Project Experience Acid Gas Removal, Sulfur Recovery, and Tail Gas Treating Units Compressors/Turbines and Compressor Station Experience Select Coal Degasification Projects Project Profiles

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

13

Section 4 Project Experience (cont.)


Section 4.1 Worldwide Project Locations

j
Norway Norsk Hydro - Ormen Lange Statoil - Kollsnes Saudi Arabia Saudi Aramco - Hawtah Field Develop - S. Area Plant Upgrade Kazakhstan OCL - 2 P/L ORYX - FEED

Sakhalin Island Exxon Sakhalin I - Chayvo - OPF - Transportation China Phillips - 24-1 - Xijiang Amoco - Liuhua ARCO - Yacheng Thailand PTT-Petronas

Italy RasGas - Adriatic LNG Syria Conoco Al Furat - 8 projects North America Sempra Energy LNG Distrigas LNG Shell Yellowhammer Enron 63 projects TransCanada Pecten (Shell) PEMEX Amoco 2 projects Anardako 2 projects Marathon Koch Northwest Pipeline BP Alaska GTL U.S. Dept of Energy Internorth Oxy San Miguez PSI 2 projects Reynolds Mustang Island Santa Fe High Islands Sonat Mustang Islands Texas Eastman High Islands Transco High Islands Union Oil Zachry Quarters Venezuela Pequiven SINCOR India Enron - LNG ONGC - 23 projects Dubai Dubai Petroleum - 3 projects Malaysia Petronas - 2 projects

Colombia BP Colombia - Cuisiana - Cupiagua - Covenas Chile Methanex - 2 projects Sipetrol Africa Mobil Nigeria - EDOP - UBIT QIT I&II Chevron Angola - Sanha - Malongo - Block 14 Chevron - EGP3 Elf - IME-Edikan - Odudu NNPC - Pipeline - Depots Sasol - Pipeline

Ecuador Techint/Garon Conoco

Indonesia P.T. Trans-Pacific Gulf Oil Mobil - BD Field

Africa (contd) Ranger Oil - Ivory Coast - platform Benin - Saga - topsides - Kerr McGee - deepwater Texaco Angola - LNG Study - Pipeline - Offsites Study

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

14

Section 4 Project Experience (cont.)


Section 4.2 Onshore Oil & Gas Scope & Project Type Table

U.S. and Europe Onshore Oil & Gas Projects


Project Aker Solutions Activities Contract Scope Plant
Pumping/Compression Management Services Civil Work/Building

Engineering

GULF LNG

LNG REGASIFICATION AND RECEIVING TERMINAL CATS TERMINAL EMM FEDERAL CONTRACT UNDERGROUND STORAGE LNG REGASIFICATION AND RECEIVING TERMINAL EMM WYTCH FARM PROJECT GAS TRANSMISSION SYSTEM 2/4 SLUG CATCHER ORMEN LANGE GAS PROCESSING PLANT

PASCAGOULA, MS, USA UK THE NETHERLANDS HACKBERRY, LA, USA UK NIGERIA

2011

BP CONFIDENTIAL SEMPRA LNG

2008 2008
2008

BP NIGERIA LNG

2007 2007
2007

NORSK HYDRO

AUKRA, NORWAY

COLUMBIA NATL. ACID GAS REMOVAL RESOURCES STATOIL/ GASSCO HHI/ONGC PTTPETRONAS STATOIL KOLLSNES GAS PLANT EXPANSION MUT PIPELINE PROJECT SONGKHLA GAS SEPARATION PLANT VESTPROCESS MONGSTAD EXPANSION PROJECT 3 PIPELINE PROJECT DABHOL LNG TERMINAL ONSHORE GAS FACILITY

WEST VIRGINIA, USA 2006 WEST COAST NORWAY WEST COAST INDIA SONGKHLA, THAILAND NORWAY

2006 2005
2005 2004

BHGL/ONGC ENRON CAIRN ENERGY INDIA LTD

WEST COAST INDIA INDIA INDIA

2004
2002

2001

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

15

Completion

Client

Plant

Location

Storage/Loading

Site Supervision

Commissioning

Process Units

Construction

Procurement

Pipelines

Utilities

Section 4 Project Experience (cont.)


Section 4.2 Onshore Oil & Gas Scope & Project Type Table

U.S. and Europe Onshore Oil & Gas Projects


Project Aker Solutions Activities Contract Scope Plant
Pumping/Compression Management Services Civil Work/Building

Engineering

ARAMCO BP CONOCO DISTRIGAS SINCOR CHEVRON CHEVRON ADCO ADNOC CONOCO ESSO

SOUTHERN AREA PLANTS UPGRADE D250 GAS-TO-LIQUIDS INTEGRATED DEZ GAS PROJECT LNG REVAPORIZATION SULFUR COMPLEX MALONGO TERMINAL GAS PLANT SANHA CONDENSATE RECOVERY OILFIELD FACILITIES KHUFF ONSHORE/ OFFSHORE GAS FAC.

SAUDI ARABIA ALASKA SYRIA MASSACHUSETTS, USA JOSE, VENEZUELA ANGOLA ANGOLA

2001 2001 2001 2001


2001

2000 2000

BU HASA, ABU DHABI 1998 ABU DHABI

1998

THEDDLETHORPE SITE THEDDLETHORPE, ALLIANCE SUPPORT UK NATUNA ONSHORE/ OFFSHORE INDONESIA BACTON AND ZEEBRUGGE MALAYSIA

1998
1998 1998

INTERCONNECTOR GAS TERMINAL

PETRONAS SANTOS LTD. TRANSCANADA BP AMOCO PEDEC

NATURAL GAS PROCESSING PLANT

1998 1998 1998


1997

BALLERA GAS CENTRE SW QUEENSLAND AUSTRALIA NGL PLANT DF OFFGAS PROJECT WASTE GAS TIMT ONSHORE/OFFSHORE FACILITIES LOUISIANA, USA HULL, UK IRAN

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

16

Completion

Client

Plant

Location

Storage/Loading

Site Supervision

Commissioning

Process Units

Construction

Procurement

Pipelines

Utilities

Section 4 Project Experience (cont.)


Section 4.2 Onshore Oil & Gas Scope & Project Type Table

U.S. and Europe Onshore Oil & Gas Projects


Project Aker Solutions Activities Contract Scope Plant
Pumping/Compression Management Services Civil Work/Building

Engineering

BP AMOCO GAS

OPRN & MAINT SUPPORT OF GAS TERMINAL CUPIAGUA FIELD CSM FACILITIES UPGRADE

TEESIDE, UK

1996
1996 1996 1995

BP COLOMBIA CONOCO ARAMCO TRANSCANADA BP CONOCO ENRON THAPPLINE BP KINNEIL AL FURAT CONOCO TRANSCANADA BP CONOCO SAGASCO CQNG

COLOMBIA THEDDLETHORPE, UK

CENTRAL ARABIA DEV. HAWTAH FIELD, PROGRAM SAUDI ARABIA NGL PLANT GAS TERMINAL DEWPOINT CONTROL PICKERILL COMPRESSION LPG PLANT MULTI-PRODUCTS PIPELINE OIL & GAS PROCESSING OMAR OIL RECOVERY FACILITIES CAISTER MURDOCH GAS TERMINAL LPG PLANT MILLER GAS RECEPTION PICKERILL GAS TERMINAL BEHARRA SPRINGS GAS PLANT LOUISIANA, USA DIMLINGTON, UK THEDDLETHORPE, UK TEXAS, USA THAILAND UK SYRIA THEDDLETHORPE, UK LOUISIANA, USA PETERHEAD, UK THEDDLETHORPE, UK WESTERN AUSTRALIA

1995 1994
1994

1994
1994

1993 1993
1993

1993
1992 1992

1992 1991

DENISON TROUGH GAS QUEENSLAND, PROJECT AUSTRALIA

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

17

Completion

Client

Plant

Location

Storage/Loading

Site Supervision

Commissioning

Process Units

Construction

Procurement

Pipelines

Utilities

Section 4 Project Experience (cont.)


Section 4.2 Onshore Oil & Gas Scope & Project Type Table

U.S. and Europe Onshore Oil & Gas Projects


Project Aker Solutions Activities Contract Scope Plant
Pumping/Compression Management Services Civil Work/Building

Engineering

PETROFINA SHELL TEXACO AL FURAT OSOCO TEXACO STEG CONOCO YPF PETROLAND SHELL S.C.O.P. BRITISH GAS BRITISH GAS SANTOS LTD. SHELL BP

REFINED PROD PIPELINE YELLOWHAMMER GAS PLANT LPG PLANT

HUMBER-HERTS, UK ALABAMA, USA OKLAHOMA, USA

1991

1991 1991 1990 1990 1990 1989


1988

OMAR N / SHAHEL GAS SYRIA GATHERING SHUKEIR GAMMA GOSP EGYPT NGL PLANT GAS TREATMENT/ COMPRESSION PLANT VIKING GAS TERMINAL GAS TREATMENT PLANT GAS TREATMENT GAS TERMINAL EXPANSION OIL EXPORT PIPELINE SYSTEM GAS TERMINAL GAS TERMINAL COOPER BASIN LIQUIDS PROJECT GAS TERMINAL OKLAHOMA, USA EL BORMA, TUNISIA THEDDLETHORPE, UK LATA OIL FIELD, ARGENTINA HARLINGTON, NETHERLANDS ST. FERGUS, UK IRAQ MORECAMBE BAY, UK MORECAMBE BAY, UK MOOMBA, SOUTH AUSTRALIA MOSSMORRAN, UK

1988
1987

1986
1985 1984

1984 1984 1984 1983

KINNEIL GAS TREATING GRANGEMOUTH, UK PLANT

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

18

Completion

Client

Plant

Location

Storage/Loading

Site Supervision

Commissioning

Process Units

Construction

Procurement

Pipelines

Utilities

Section 4 Project Experience (cont.)


Section 4.2 Onshore Oil & Gas Scope & Project Type Table

U.S. and Europe Onshore Oil & Gas Projects


Project Aker Solutions Activities Contract Scope Plant
Pumping/Compression Management Services Civil Work/Building

Engineering

BRITISH GAS BP CHEVRON

COMPRESSION STATION GAS TERMINAL PROCESS UNITS OIL REFINERY EXPANSION

AYLESBURY, UK SULLOM VOE, UK PERTH AMBOY, NJ USA MONT BELVIEU, TX USA BATON ROUGE, LA USA ALRAR/ARZEW, ALGERIA USSR ST. FERGUS/ NIGG BAY UK BATON ROUGE, LA USA RUMAILA, IRAQ FAWLEY, UK SKIKDA, ALGERIA

1983
1982 1982 1982 1981 1980 1980

CITIES SERVICES NGL FRACTIONATION EXXON SONATRACH TECHMASHIMPORT MOBIL EXXON BASRAH PETROLEUM ESSO SONATRACH BP BRITISH GAS SONATRACH MICHIGAN GAS OFFGAS COMPRESSION GAS, LPG & COND PIPELINES ETHYLENE PIPELINES (2) GAS & NGL PLANTS DEBUTANIZER OIL EXPORT EXPANSION C4 STORAGE COMPRESSION STATIONS (2) DALMENY OIL TERMINAL COMPRESSION STATION LPG TREATING PLANT UNDERGROUND GAS STORAGE

1979
1978 1977

1977
1976

FIRTH OF FORTH, UK 1975 CAMBRIDGE, UK ARZEW, ALGERIA MICHIGAN USA HONOR RANCHO, CALIF., USA 1975 1973

SOUTHERN UNDERGROUND GAS CALIFORNIA GAS STORAGE

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

19

Completion

Client

Plant

Location

Storage/Loading

Site Supervision

Commissioning

Process Units

Construction

Procurement

Pipelines

Utilities

Section 4 Project Experience (cont.)


Section 4.3 LPG/NGL/LNG Project Experience
The following list includes LPG/NGL/LNG projects:

Aker Solutions LNG/LPG/NGL Projects


Client Gulf LNG Ingleside Energy Center LLC Sempra Energy ExxonMobil/QP Norsk Hydro Columbia Natl. Resources Statoil/GASSCO ChevronTexaco Location Pascagoula, MS USA Ingleside, Texas USA Cameron, Louisiana, USA Offshore Italy Aukra, Norway West Virginia, USA Description LNG Receiving & Regasification Terminal LNG Receiving & Regasification Capacity MM SCFD 1,500 1,000 Scope Permitting, FEED, EPC Pre-FEED, EPC (On Hold) EPC FEED/EPC M FEED/EPC MA EPCM E FEED TIC $MM Conf 665 Product LNG LNG/LPG /NGL LNG LNG NGL/LPG Acid Gas Removal LPG LNG Year Comp. 2011 2011

LNG Regasification and Receiving Terminal GBS LNG Regasification Facility Ormen Lange Onshore Gas Processing Plant Acid Gas Removal Unit

1,500 750 2,400 1,500GPM 1,400 2000/750

700 900 2,000 Conf --1,000

2008 2007 2007 2006 2006 2006

West Coast Norway Kollsnes Gas Plant Expansion Gulf of Mexico & Offshore Baja, California Port Pelican & Baja GBS LNG Facilities Snohvit LNG Plant Gas Separation Plant LNG Regasification Facility/Energy Hub

Linde AG (Statoil) Melkya, Norway PTT-PETRONAS Gas Freeport McMoRan Thailand Gulf of Mexico

540 425

EPCS PMC/FEED PreFEED/C E/ Permit Support

100 250 Conf

LNG LPG LNG/LPG /NGL

2005 2005 2004

ExxonMobil Shell Enron* Aramco Services Co. CMS Conoco Syria Distrigas

Gulf of Mexico Offshore Northeast USA India Saudi Arabia Equatorial Guinea Deir Ez Zor, Syria Everett, Massachusetts, USA Hackberry, Louisiana, USA

GBS LNG Import Terminal GBS LNG Regasification Facility Dabhol LNG Receiving Terminal Southern Area Gas Plants Upgrade LNG Liquifaction Production Facility Integrated DEZ Gas Project LNG Revaporization Expansion

1,250 1,000 --800 4MM TPA 500 600

S/CE S/CE EC FEED S/CE FEED/EPC FEED/EP

Conf Conf 250 128 NA 180 125

LNG LNG LNG NGL LNG/LPG LPG LNG

2003 2003 2002 2001 2001 2001 2001

Dynegy

LNG Import Terminal Onshore Liquefaction Facilities (PRICO Technology) Sanha Secondary Recovery Condensate/ Development Project

750 800 600

S/CE Pre-FEED FEED/E

NA Conf 1,500

LNG LNG/LPG LPG

2001 2001 2000

Texaco/Sonangol Angola Chevron Overseas Petroleum Offshore Angola, West Africa

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

20

Section 4 Project Experience (cont.)


Section 4.3 LPG/NGL/LNG Project Experience Aker Solutions LNG/LPG/NGL Projects
Client Shell Gazprom/Yamal Location Kollsnes, Norway Russia Description Gas Processing & Commissioning Plant LNG Export Terminal 28,000 BPD 60 200 750 600 200 1,000 250 ----Capacity MM SCFD 1300 Scope FEED/EPC S FEED/E/SU TIC $MM 512 NA 4 Product NGL/LPG LNG NGL Year Comp. 1996 1995 1995

TransCanada Gas Geismar, Louisiana, Riverside Fractionation Plant Processing USA Debottlenecking (Enron) Enron TransCanada Enron Enron Shell Offshore, Inc. Texaco British Gas Texaco YPF Agua Dulce, Texas, Magnolia City Gas Plant USA Expansion Cameron, Louisiana, USA Argentina Teesside, UK Mobile Bay, Alabama, USA Erath, Louisiana, USA Tunisia USA Argentina Sabine Pass Gas Plant EASA Gas Processing Facility Teesside Gas Processing Plant Yellowhammer Gas Plant Henry Gas Plant Miskar Gas Plant Maysville NGL Plant Gas Treatment Plants 1 & 2

FEED/EC/S U FEED/ECM/ SU FEED FEED PM/EPCM SIM/E S/CE EPC E

NA .5 NA 40 70 NA 350 NA NA

NGL NGL NGL LPG NGL NGL **CGP NRU NGL NGL

1994 1993 1992 1991 1991 1991 1990 1990 1990

SCOPE E P C PMC CM CMA = = = = = = Engineering Procurement Construction Program Management Contractor Construction Management Construction Management Assistance SU PM SIM S CE NA = = = = = = Start-up Project Management Simulation Study Cost Estimate Not Available

The Houston office provided engineering support to our UK office NRU Nitrogen Rejection Unit NGL Natural Gas Liquid LPG Liquified Petroleum Gas LNG Liquified Natural Gas

** CGP Cryogenic Gas Plant

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

21

Section 4 Project Experience (cont.)


Section 4.4 Acid Gas Removal, Sulfur Recovery, and Tail Gas Treating Units
Aker Solutions experience in acid gas removal, CO2 and H2S handling, transportation and safety systems design is an accumulation of many years of experience in conceptual process development, front end engineering design and development of facilities which includes PreFEED and FEED studies, detailed engineering, construction of the facilities including modularization concepts where economically attractive in this specific area. Aker Solutions experience, as indicated in the following table, includes acid gas removal from the facilities design in natural gas production (both offshore and onshore). Our experience also includes the gas clean-up from refineries and synthesis gas production in which similar facilities are required. The experience in this area includes a wide range of applications in which the inlet gas contains over 65% CO2 with small amounts of H2S to less than 1% or less CO2 with higher amounts of H2S. As you will note from the experience table, the application in acid gas removal systems involve different types of solvent systems that includes primary, secondary and tertiary amine systems, formulated amines for bulk CO2 or selective H2S removal and physical solvents involving selexol, methanol, etc. In addition, we have also been involved in bulk CO2 removal using membranes, cryogenic processes and a few H2S scavenger and fixed-bed processes such as molecular sieve. The examples are noted in the table as an indication of our involvement in this specific area over the last 30 years. In many of these applications, the starting point has been in the front end conceptual process development in which the process selection and optimization has been the key part of our experience internally as well as working with appropriate vendors of formulated solvents and membrane (where applicable) in achieving the desired outcome for the process selection. The acid gas removal or clean-up applications in natural gas treatment has mainly involved the following purposes or objectives: Removal of CO2 and H2S to meet natural gas pipeline specifications Removal of CO2 and H2S to meet cryogenic gas plant for natural gas liquids (NGL) extraction as well as process constrains to avoid CO2 freeze-up. Removal of CO2 to a low ppm levels to meet liquefied natural gas (LNG) plant process constraints, again for the CO2 freeze-up concern. Removal of CO2 and H2S from ethane product to meet petrochemical feed stock specification requirements where catalyst poisoning has been a concern Removal of CO2 to a very low ppm levels depending on the specification for downstream chemical production such as Ammonia synthesis. Again, the following table reflects our broad-based experience and know-how which helps us optimize the new as well as existing plant applications in which the upgrades are necessary for increased throughput volumes or changes in the inlet gas conditions.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

22

Section 4 Project Experience (cont.)


Section 4.4 Acid Gas Removal, Sulfur Recovery, and Tail Gas Treating Units Aker Solutions Acid Gas Removal, Sulfur Recovery and Tail Gas Treating Experience
Year
2009

Client/Project
ExxonMobil Natuna Gas Field Development, Offshore, Indonesia. Inlet gas volume 2400 MMSCFD, 65% CO2 and 0.5% H2S, multiple trains Baard Energy, CO2 compression and injection for EOR application Bharat Oman Refinery (BORL) Project, Madhya Pradesh, India 2 x 90 MTPD Sulfur Recovery Units (SRU) (1 x 330 TPH Amine Regeneration Unit (ARU) Statoil Claus Unit for Sulfur Recovery for SMIL Project, Mongstad, Norway Max Petroleum, Astrakhanskiya Field, Kazakhstan. Initial gas production 150 MMSCFD, later year 600 MMSCFD with 20% H2S and 10% CO2 in the sour gas. High reinjection pressure SES/Consol Northern Appalachia Fuel Project, Benwood, West Virginia. Synthesis gas containing 25% CO2 and 1.3% H2S, Acid Gas removal (2000 gpm circulation), sulfur plant approx. 150 TPD, single train with tail gas treatment unit Chennai Petroleum Corp. Ltd., Chennai, India. 2 trains (45.5 & 35 TP) sour water stripper units (SWS) American Lignite Energy (ALE) CTL Project, North Dakota. Synthesis gas containing 32% CO2 and 0.3% H2S. Acid gas removal (11000 gpm solvent circulation) and sulfur plant (3X50%) trains with single train tail gas treating unit. Sulfur production approx. 200 TPD Faustina Hydrogen Products, Louisiana. Synthesis gas containing 40% CO2 and 1.4% H2S. Acid gas removal (5500 gpm solvent circulation) and third party sulfur plant (2 X 220 LTPD) with a single tail gas treating unit Indorama Ammonia Plant Damietta, Egypt. Feed gas containing 17% CO2 and no H2S. Columbia Natural Resources, West Virginia, Acid gas removal from High (25%) CO2 field. 1500 gpm circulation, revamp of existing unit

Solvent Type
Cryogenic Process N/A Selexol

Aker Solutions Scope


Technology comparison, front end process development, layout, cost estimate Technology comparison, cost estimate, life cycle cost analysis EP

2009 2009

2008 2008

AMDEA Activated MDEA based solvent comparison Selexol

Basic Engineering & EPC Feasibility and conceptual study, cost estimate

2008

Feasibility study

2007

N/A

FEED

2007

Rectisol (Methanol)

Feasibility, Pre-FEED design and cost estimate support

2007

Selexol

FEED design, cost estimate support

2006 2006

GAS/SPEC CS-Plus Selexol

Plant relocation, engineering and CM Conceptual, detailed engineering, procurement assistance, construction management

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

23

Section 4 Project Experience (cont.)


Section 4.4 Acid Gas Removal, Sulfur Recovery, and Tail Gas Treating Units Aker Solutions Acid Gas Removal, Sulfur Recovery and Tail Gas Treating Experience
Year
2006 2006

Client/Project
Siirtec Nigi/Sulphur Recovery Unit at MOL Oil and Gas Plc., Hungary. 90 tons/day unit Duke Energy Gas Transmission, Canada, Kwoen Acid Gas Plant, acid gas plant expansion QNI Syngas, Queensland, Australia. Synthesis gas containing 15% CO2 and no H2S Westcoast Energy Inc., Canada, Kwoen Gas Plant, Sour gas processing facility designed to remove 28MMSCFD of acid gas from a stream of 300MMSCFD Chennai Petroleum Corporation Ltd., India, Sulphur Recovery Unit SINCOR Sulfur Complex, Venezuela, refinery gas treating, two identical trains. Solvent circulation rate: 2200 gpm each (DEA). Also one train of 1850 gpm (MDEA) for tail gas clean-up. Three trains of 400 tons/day each Claus sulfur plant. Westcoast Gas Services, Inc., Jedney II Gas Processing Plant, 78MMSCFD Gas Sweetening (800 USGPM amine)

Solvent Type
MDEA Morphysorb

Aker Solutions Scope


Detailed engineering and procurement assistance Engineering design, procurement assistance and construction support Existing plant revamp process and equipment re-rated with new process conditions Design, procurement, fabrication and field construction

2005

Benfield

2002

Selexol

2002 2001

MDEA DEA/MDEA

Detailed engineering and procurement assistance Detailed engineering, procurement and construction

2000

Ucarsol LE-703

Design, procurement, fabrication, field construction

2000

Elf Exploration and production,Lacq Field, Southern Cryogenic and Technology comparison, front end engineering study, cost Membrane France, Inlet volume 3.5 MM Sm3/day, 22% H2S, estimate Process 11.5% CO2, field redevelopment BP Refining, Australia, revamp of Sulfur Recovery and Amine Unit to increase capacity of unit from 25t/d to 35 t/d and improve efficiency of unit Kochi Refineries Ltd., Sulphur Recovery Unit at Kochi, India. 2 trains of 72 tons/day units BP/BOP Pox unit, Australia, Syngas Treating for CO2 Removal, Solvent circulation rate: 280 gpm TransCanada (formerly Enron) Eunice Plant, Louisiana, ethane product treating for high CO2 and traces of H2S removal. Solvent circulation rate: 250 gpm MDEA Front end engineering, process design and program management Detailed engineering and procurement assistance Basic engineering package, detailed engineering, construction management Basic, detailed engineering, procurement, CM support, plant operators training, start-up support

2000

1999 1999

MDEA BASF Activated MDEA Ucarsol

1997

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

24

Section 4 Project Experience (cont.)


Section 4.4 Acid Gas Removal, Sulfur Recovery, and Tail Gas Treating Units Aker Solutions Acid Gas Removal, Sulfur Recovery and Tail Gas Treating Experience
Year
1996 1995

Client/Project
Texas Eastman, Texas, treating of 15 MMSCFD of syngas for CO2. Solvent circulation rate: 500 gpm TransCanada (formerly Enron) Riverside Plant, Louisiana, ethane product treating for high CO2 removal with traces of H2S removal. Revamp of existing 250 gpm amine treating unit (conversion from MEA to Ucarsol) and installation of new 125 gpm Ucarsol unit Petronas Gas Bhd., Malaysia. Natural gas treating containing high CO2 and traces of H2S removal. Solvent circulation rate: 19,000 gpm

Solvent Type
MEA Ucarsol

Aker Solutions Scope


Basic, detailed engineering, start-up support Conceptual, basic and detailed engineering, procurement, startup assistance

1994

BASF Activated MDEA

Conceptual studies, process optimization cost estimate, technical support for detailed engineering and start-up

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

25

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience
Aker Solutions has engineered many compressor systems for services including hydrocarbons involving natural gas, process and synthesis gas as well as various refrigerant and air compressors, ranging in size from under 100 hp to over 65,000 hp. These installations involved reciprocating, centrifugal, hyper, screw and liquid ring compressors with various types of drivers, including gas fired turbines, gas and diesel engines, electric motors and steam turbines. Our experience in design of reciprocating compressors includes units with up to five stages as well as centrifugal units with multiple process stages. The following table provides details of our compressor and driver design and installations. A majority of our compressor station experience comes from onshore and offshore oil & gas installations. Our compressor station experience includes natural gas compression at various locations in the oil & gas production, gathering, processing and pipeline transportation process. Aker Solutions recent experience includes the design of six (6) compressor stations for Conoco Dez Gas in Syria. The design involved multiple compressor stations located in the field at the gas gathering stations. The compressor stations were designed and placed at appropriate locations. The gas is separated from the inlet condensate, compressed to a pipeline pressure using multistage, positive displacement reciprocating compressors. The condensate separated at low and medium pressure levels is pumped to pipeline pressure. The condensate, in most cases, was combined with high pressure gas for transportation to a central gas processing plant using a multi-phase pipeline. The condensed water is separated in the three phase separators at various stages and the pressure level was combined and then pumped for re-injection. The compressor stations were designed with maximum modularization using skid mounted separation and pumping equipment, packaged reciprocating compressors with drivers, coolers and other associated equipment. A separate system was designed to provide fuel gas treatment. A majority of the interconnecting piping was prefabricated for easy installation in the field. All of the compressor stations were self-contained with required utilities and other facilities such as air, pig launchers/receivers and metering, as well as compressor auxiliaries such as lube oil. Aker Solutions also designed pipeline compressor stations for the pipeline gas transportation of the Conoco Dez Gas Syria project. Here the dry lean gas from the central gas processing facility was compressed for pipeline transportation to the sales gas pipeline as well as excess gas for reinjection. The pipeline compressors in this case were centrifugal compressors with turbine drivers. Multiple compressors were required to provide the overall compression duty. The export gas pipeline compressor stations were part of the central gas processing facility. In addition to the above project, Aker Solutions experience also includes the design of compressor stations for the Norsk Hydro Orman Lange project in Norway. This facility, as part of the large onshore gas processing complex, utilized large compressors for transportation of the dry gas export pipeline from northwest of the Norwegian continental shelf to the UK, a 1200 km 42
long pipeline.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

26

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience
The compressors were driven by one of the largest electrical motor drivers with 40 MW motors each. Aker Solutions has faced many similar challenges in the past in designing the compressor stations where the pipeline pressure has ranged from 600# ANSI systems to 1500# ANSI systems. Aker Solutions has also designed various compression systems to 6600 psig discharge pressure level where the gas is re-injected. In addition, Aker Solutions experience also includes pipeline booster stations where the compressor stations are designed to provide a pressure boost with low compression ratio at high pipeline pressure located along the export gas pipeline. Most of these compressor stations involved centrifugal compressors with turbine or electric motor drivers to provide pressure boost in the export gas pipeline. Our experience includes both offshore and onshore pipeline boosting stations. Most of these stations are highly automated and self- supported with all of the utilities and required compressor and turbine auxiliaries with the system design for high reliability. A recent example is the Exxon Mobile Sable project in Canada where the large Dresser Rand compressor with RB211turbine driver was utilized. In many of the compressor stations, especially in the gas gathering and wellhead level field locations, modularization is a key design consideration. In summary, Aker Solutions experience includes engineering, procurement and installation of many different types of compressor systems including various types of compressor stations for natural gas processing. Again, the following list provides examples of our compressors and drivers design, as well as our experience in the design of compressor stations.

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

27

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience

Gas Compression Projects


Client
Gulf LNG Energy

Plant Location
Pascagoula, Mississippi

Completion
In Progress

Services Performed
EPC service for liquefied natural gas (LNG) receiving terminal including two LNG storage tanks and a regasification facility consists of three 1,400 hp IHI boil off gas compressors. Also includes one 2,000 hp Ariel pipeline compressor, and two 200 hp Atlas Copco vapor return blowers. EPC service for offshore concrete liquefied natural gas terminal and regasification facility consists of two trains of 750 hp Dresser-Rand cryogenic boil off gas compressors. EPC services for liquefied natural gas receipt terminal and associated facilities consists of three 600 hp Burckhardt cryogenic boil off gas compressors, one 1,200 hp Ariel pipeline compressor and two 200 hp Atlas Copco vapor return blowers. Design for Gas Compression Platform Topsides consists of one 35,000 hp, 6 stage centrifugal, Dresser-Rand export gas pipeline compressor, driven by a Rolls Royce RB-211 turbine driver. Detailed engineering services for offshore oil and gas production with LPG extraction plant consists of four 30,000 plus hp each Dresser Rand reinjection compressors driven by RB-211 turbine drivers and compressing the gas to 6,600 psig pressure. Also includes two trains of 16,000 hp Dresser Rand separation compressors driven by solar Titan turbines compressing associated gas. The makeup gas compressors consists of three solar turbines (2 Mars and 1 Taurus) ranging in hp from 6,000 to 13,000 hp. The platform also includes smaller stabilizer overhead compressors. Detailed engineering for offshore production and compression platform consists of vapor recovery and six 12,000 hp Nuovo Pignone booster compressors with turbine drivers, compressing the gas to pipeline pressure for delivery to onshore.

Exxon Mobil

Offshore, Porto Viro, Italy

In Progress

Sempra LNG

Cameron, Louisiana

2009

Exxon Mobil

Sable Island, Canada

2004

Chevron Overseas Petroleum Company

Offshore Block 0, Angola, West Africa Sanha Project

2004

Pemex Exploration & Production

Offshore Mexico, Canteral Field

2003

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

28

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience

Gas Compression Projects


Client
Conoco Syria Dez Gas Ltd.

Plant Location
Syria

Completion
2001

Services Performed
EPC services for infield gas gathering with compressor stations and an onshore gas processing facility. Detailed engineering and construction for total of six multi-stage centrifugal compressors with Nuovo Pignone PGP10B gas turbine drivers site rated at 11,000 hp each for residue and gas reinjection services. The maximum discharge pressure for gas reinjection is 5,000 psig. Also includes seven reciprocating single and multi-stage Aeriel compressors, sizes ranging from 250 hp to 4,100 hp electric motor driven with some variable frequency motors for natural gas services including gas gathering and pipeline. The facility also includes three multi-stage centrifugal propane compressors, 2,000 hp each for refrigeration service. Engineering for offshore production facility includes gas compression studies and selection of gas compressors for produced and associated gas for reinjection and gas lift. The selection includes solar Mars turbine-driven multi-stage centrifugal compressors with discharge. Engineering for onshore low pressure gas gathering and compression for LPG recovery and gas conditioning plant. Three solar Saturn turbines with centrifugal compressors for multi-stage high MW natural gas. FEED engineering for offshore gas gathering including one 16,000 hp and four 34,000 hp gas turbine-driven centrifugal compressors for gas compression to 6,600 psig. EPC for multi-stage, centrifugal barrel type Dresser Rand syngas compressor, 41,700 hp, Mitsubishi multistage multi-valve passout/condensing steam turbine driver. EPC plant revamp including installation of 1,000 hp engine-driven reciprocating compressor. Also modernized the overall control system for the multiple (5) solar compressors and turbines. EPC for crude oil gathering and gas reinjection facility including two GE Frame 5, 28,000 hp gas turbinedriven Nuovo Pignone centrifugal compressors for reinjection to 6,600 psig.

Chevron Overseas Petroleum Company

Offshore Angola Block 14, West Africa

2000

Chevron Overseas Petroleum Company Chevron Overseas Petroleum Company Methanex Corporation, Chile TransCanada Gas Processing

Onshore Angola Malongo Terminal, West Africa

2000

Offshore Angola Block 0 Sanha, West Africa Punta Arenas, Chile

2000

1999

Eunice, Louisiana

1998

BP Exploration & Cupiagua, Columbia Production

1997

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

29

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience

Gas Compression Projects


Client
Methanex Corporation, Chile

Plant Location
Punta Arenas, Chile

Completion
1996

Services Performed
EPC for multi-stage, centrifugal barrel type Dresser Rand syngas compressor, 41,700 hp, Mitsubishi multistage multi-valve passout/ condensing steam turbine driver. EPC for crude oil gathering and gas reinjection facility including one GE Frame 6, 32,000 hp gas turbinedriven Nuovo Pignone centrifugal compressor for reinjection to 6,600 psig. EP services for offshore gas compression platform including GE 25,000 hp gas turbine driven centrifugal compressor for reinjection to 3,000 psig. EPC for replacement of an existing Dresser-Rand multi-stage compressor, 16,300 hp and upgrade of the multi-stage backpressure steam turbine. One 3-stage, centrifugal compressor, one 3-stage Demag HVK-10 centrifugal compressor in tandem with one Demag VK-50 4-stage centrifugal compressor. Both compressors driven by an existing 15,000 hp synchronous motor. Two Demag VK80-Z, 2-stage, centrifugal integrally geared compressors with 7,500 hp each synchronous motor driver. Plant revamp including two 800 hp and one 1,000 hp engine-driven reciprocating compressor EPC for one Delaval multi-stage, barrel type compressor with 4,500 hp induction motor driver and speed increasing gearbox. Definition and detailed engineering of four 1,000 hp Ariel JGK compressors. Engineering services for two 4,000 hp I-R electric drive compressors. Lump sum turnkey construction to add solar Centaur turbines and other modifications at four existing compressor stations. EP services for one 3,000 hp Cooper Pennsylvania process and one 1,500 hp Cooper Superior reciprocating compressor. Detailed design, engineering and construction management for 3,110 hp reciprocating 2-stage gas pipeline compressors.

BP Exploration & Cupiagua, Columbia Production

1996

Mobil

Nigeria

1996

Sterling Chemicals

Texas City, Texas

1996

Amoco Chemical Texas City, Texas

1995

Miles (Bayer)

Baytown, Texas

1995

TransCanada Gas Processing Coastal Chemicals ARCO Oil & Gas Company ARCO Oil & Gas Company El Paso Natural Gas Company Texaco E&P Inc.

Riverside, Louisiana Cheyenne, Wyoming

1995 1993

Wilburton, Oklahoma Denver City, Texas Arizona, New Mexico and Colorado Andrews County, Texas Canton, Texas

1992 1992 1992

1992

Trident NGL, Inc.

1992

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

30

Section 4 Project Experience (cont.)


Section 4.5 Compressors/Turbines and Compressor Station Experience

Gas Compression Projects


Client
Trident NGL, Inc. Northwest Pipeline Company Amoco Production Company El Paso Natural Gas Shell Offshore

Plant Location
Myrtle Springs, Texas Utah, New Mexico, Washington Durango, Colorado

Completion
1992 1991

Services Performed
Engineering services for two 1,440 hp CooperBessemer GMVC-8C reciprocating compressors. Process engineering, detailed engineering and procurement to add solar Centaur turbines at five compressor stations. Engineering and construction of 205 MMSCFD natural gas processing plant. Includes five 5,000 hp motor driven field compressors and two 5,000 hp motor driven residue boosters. Engineering and construction of a natural gas parallel residue compression station. Includes one 5,000 hp motor driven residue compressor. Process design, detailed engineering, procurement and construction of a 200 million SCFD natural gas plant to process raw and sour gas from offshore wells for pipeline distribution.

1990

Durango, Colorado

1990

Mobile, Alabama

1990

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

31

Section 4 Project Experience (cont.)


Section 4.6 Select Coal Degasification Projects

El Paso Natural Gas Company Florida River Coal Degasification Project Florida River, Colorado Scope of work:..........................EPC Contract value: .........................USD 10 million General description: This facility was part of the coal degasification (coal bed methane production) project involving 220 MMSCFD peak capacity compression facilities where the low pressure gas was boosted in pressure to deliver the gas to the pipeline. The facility includes total installed compression of 15,000 HP and other miscellaneous small water treatment.

Amoco Production Company San Juan Basin Coal Degasification Project San Juan, Colorado Scope of work:..........................EPC Contract value: .........................USD 63 million General description: The overall scope of work includes the following:

Coal degasification facility gathering system The processing facility with peak capacity 220 MMSCFD DEA gas treating unit for CO2 separation TEG dehydration Field gas compression from low pressure to pipeline delivery pressure with total installed compression of 20,000 HP Water treating and other miscellaneous facilities

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

32

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles Conoco Syria Dez Gas Ltd. Integrated Dez Gas Project Deir Ez Zor, Syria
Description: This 450 MM SCFD grass roots facility included gas gathering, pipelines, compression, gas processing, offices and living quarters. Specific details of this scope include:

Inlet gas compression and cooling Gas gathering pipeline system Gas compressor stations (6) Inlet condensate separation and transportation to pipeline Dry gas chilling, condensate separation Fractionation of mixed LPG product Propane, butane and C5+ condensate Butane storage Export pipeline ( 250 KM of 18 .375 wt) Truck loading facility Lean residue gas recompression for gas reinjection High and low pressure flare systems Hot oil, cooling water and other utility system Low level propane refrigeration system requiring propane compression from near atmospheric pressure

Scope of Work:

Engineering, procurement, construction, and precommissioning. Bid, Concept Development & FEED (Technip): 9 months February 1999 January 2001 April 1999 September 2001

Duration: Engineering Start: Finish: Construction Start: Construction Completion: Manhours:

Approximately 400,000 engineering/design manhours Mumbai: 250,000 manhours detailed design Houston: 80,000 manhours including coordination & support Syria: 55,000 manhours buildings, pipeline systems $430 million TIC. Aker Solutions portion was U.S. $180 million. Safety: Total construction manhours exceeded 4 million. Project achieved over 3 million manhours without LTI.

TIC:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

33

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles

Norsk Hydro Ormen Lange Onshore Gas Processing Plant Aukra, Northwest Coast of Norway
Description: The Ormen Lange Gas Field is located 120 kilometres northwest of Kristiansund. It is being developed with subsea production facilities in 800-1100 metres water depth hooked up to the onshore sales gas processing and export plant at Aukra. The Ormen Lange development also involves the most extensive gas export pipeline system form the Norwegian continental shelve to the UK, a 1200 km long 42 pipeline. The installation also includes cavern storage for condensate and export by tanker.

Technical Data: Gas export capacity: 70 M Sm3/d Possibility for future upgrade to 80 M Sm3/d without major shutdown Condensate storage: 150,000 m3 Scope of Work: Performance of FEED, detailed engineering and follow-up engineering, procurement, and construction management assistance for the gas plant. Main interface contractor for overall system responsible for the total Ormen Lange project including subsea facilities, community power from national grid, and transport to consumers in the UK and Europe. Project Value: Contract value of onshore gas processing plant is NOK 950 million. Total TIC of project is NOK 66 billion. TIC of onshore facilities is NOK 16 billion. March 2003

Award:

Production Start: October 2007 Status: Operational

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

34

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles Saudi Aramco Southern Area Gas Plants
Description: The Maintain Gas Compression Capacity Project provided for the installation of Compression Train B at Abqaiq Plant 499. The primary purpose of this project was to provide a reliable, efficient and safe gas compression system at the Abqaiq Plants, which have sufficient capacity to process the low pressure gases in a manner that complies with current environmental regulations. This project also allowed the retirement of old inefficient fired steam boilers and provided for efficient generation of high pressure steam with the installation of heat recovery steam generations (HRSGs), as well as diversification of the flare system to reduce the risk of business interruption through the strategic location of existing flare equipment and correction of deficiencies in the standby flare. This project also allowed for the retirement of Plant 332, which was approximately 35 years old. Machine units in this plant were no longer being manufactured and the equipment became unreliable with low efficiency. The Abqaiq Plants had eight gas compression trains to compress gasses that have been removed in the spheroids and stabilization process at the Abqaiq Plants and in Intermediate Pressure (IP) and Low Pressure (LP) traps at Abqaiq GOSPs 5 and 6. The compressed gas and the NGL liquids recovered in the compression process are shipped to downstream facilities for treating and sales product separation. Under a previously completed project, a new compression train with a design capacity of 100 MMSCFD and NGL stripper facilities were installed in Plant 499 Train A commissioned in 1999. This compression train allows Abqaiq Plants to process offgas from Shaybah crude stabilization and to retire the old NGL Plant 337 commissioned in 1965. This facility consists of a gas compression train having two compression stages that are operated in tandem and driven by a common CGT driver. The new NGL stripper installed with Train A has spare capacity to handle future expansion in Plant 499 that will be installed under this project (Plant 499 Train B).

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

35

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles
The boilers at the Abqaiq Plants were also aging, and some existing boilers were in need of major repairs. The Master Plan for Abqaiq Plants is the recommendation that heat recovery projects be implemented to reduce the need for replacing these boilers. Heat recovery projects include the installation of heat recovery steam generators, which will use the waste heat from the exhaust of the combustion gas turbine drivers to provide additional highpressure steam. Heat recovery steam generation units were also installed on the existing Train A as well as the proposed Train B being installed under this project. Additionally, a second plant flare system, sized for a capacity of 700MM SCPD was designed for the project. Support facilities required for the Compression Train B included a new electrical substation as well as a team building and operator shelter. Numerous engineering studies were conducted in conjunction with the preliminary design effort. They included electrical studies for load flow, short circuit and motor starting analysis and protective device coordination, operability and maintainability studies for the combustion gas turbine and flare installations, constructability studies for all facilities, a team building risk assessment and a motor control center load list, an environmental assessment of the Train B facilities as well as the new flare system, and a preliminary process hazards analysis of both facilities. Duration: Conceptual work was awarded in July 2000 under a reimbursable General Services Agreement with Aramco Services Company. Conceptual engineering for the gas compression train and flare system was completed March 2001. The LSTK project detail design, procurement and construction was awarded to others in July 2001 with completion expected in 2003. Conceptual design, optimization studies, preliminary engineering, and detailed FEED package of the total project and detail design of the 69kV substation. Conceptual work consisted of generating the following deliverables:

Scope of Work:

Generate Definitive Scope of Work and EPC Schedules Generate Project Proposal Books Perform the ER Estimate for the Total Installed Costs of the Project Generate the LSTK Contract Bid Packages

HO Manhours: Project Value:

37,000 manhours TIC: $128 million

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

36

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles PETRONAS Gas Sdn. Bhd. Gas Processing Plants 5 & 6 Terengganu, Peninsular Malaysia
Description: Cryogenic expander plant & NGL fractionation. 1,000 MMSCFD net sales gas, approximately 1400 MMSCFD inlet gas. The grass roots facility includes two cryogenic expander units. Each unit has a capacity of 700 MMSCFD. The plant extracts over 90% ethane and over 99% of propane and heavier components from the inlet gas using Aker Solutions developed high ethane recovery process. In addition to the cryogenic expander plant, the design also includes the following: Scope of Work: Acid Gas (CO2) removal using BASF activated MDEA process Mercury removal from the inlet gas stream Molecular sieve dehydration NGL treating Inlet condensate stabilization Two NGL fractionation trains, 100,000 BPD capacity each Ethane, propane, butanes and gasoline separation Refrigerated and pressurized storage for different products Environmental and utilities design

Program Management Consultant (PMC) scope including design basis development, conceptual design, basic engineering package, EPC bid evaluation support, detail engineering supervision at contractors office on behalf of client and technical support during construction and commissioning. 100,000 engineering/design manhours Estimated installed cost of the project is U.S. $800 million. Aker Solutions services value at $8 million.

Manhours: Value:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

37

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles Shell Offshore Inc. Yellowhammer Gas Plant Mobile, Alabama
Description: Refrigerated NGL recovery plant, sour gas treating and sulfur plant with capacity of 200 MMSCFD. This 200 MMSCFD facility consisted of sour gas treating unit to remove H2S using sulfinol solvent, Claus sulfur recovery unit and a SCOT tail gas unit. The facility also included a refrigerated NGL recovery unit and an NGL treating unit to produce approximately 2500 BPD of NGL, produced water stripping, gas turbine electric cogeneration unit, waste heat boilers, product storage and truck loading facilities. Project management, detailed engineering, procurement and construction management. 220,000 manhours Estimated installed cost for the project was U.S. $70 million.

Scope of Work:

Manhours: Value:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

38

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles TransCanada Gas Processing Inc. Eunice Gas Processing Plant Expansion Eunice, Louisiana
Description: Lean oil and two cryogenic expander plants with NGL fractionation facility. Plant capacity of 1050 MMSCFD. The existing plant expansion included basic engineering of the existing refrigerated lean oil extraction plant, two cryogenic expander plants, one of which was designed for 95% ethane recovery from the inlet gas and NGL fractionation facility. The process study also included the UCARSOL treating unit evaluation for CO2 removal from the ethane product, existing equipment evaluations, additional equipment requirements to meet future change in feed stock with increased throughput of 100 MMSCFD, new two phase pipeline hydraulics and cost estimate for additional equipment to eliminate the plant bottlenecks. Gas plant revamp detailed engineering for the work included: Scope of Work: Fractionation column revamp for capacity increase Refrigeration system (propane) expansion Steam system revamp Cooling tower addition Amine Unit addition Propane treater addition Various vessels, exchangers and pumps addition for capacity expansion Plant flare and thermal oxidizer debottleneck Complete modernization of the plant and advanced control implementation

Design basis development, basic engineering, detailed engineering, procurement and start-up support. 125,000 engineering/design manhours Estimated installed cost of the project was U.S. $40 million. Aker Solutions services value U.S. $8 million.

Manhours: Value:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

Eunice Gas Plant with High Pressure 39 Demethanizer

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles TransCanada Gas Processing Inc. Riverside Fractionation Plant Debottlenecking Geismar, Louisiana
Description: NGL fractionation facility with plant capacity of 28,000 BPD demethanized liquid. The scope of work included the debottlenecking of the existing fractionation facility which included the deethanizer, depropanizer, debutanizer, and iso-normal butane splitter columns. The plant throughput was increased from approximately 15,000 BPD of lower ethane containing feed to 28,000 BPD of higher ethane and much higher CO2 containing demethanized liquids. Aker Solutions also provided the advanced control configuration and optimization for four distillation columns which reduced the energy consumption (Btu/gallon) of the fractionation facility by 20%. Debottlenecking of the facility also included revamping the existing amine treating (UCARSOL) unit and addition of new parallel unit to remove the CO2 from ethane product. Design basis development, basic engineering package, detailed engineering and plant start-up support. 12,000 engineering/design manhours Estimated installed cost of the project was U.S. $4 million

Scope of Work:

Manhours: Value:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

40

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles TransCanada Gas Processing Inc. Sabine Pass Gas Plant Cameron, Louisiana
Description: Cryogenic expander plant with plant capacity of 200 MMSCFD. The scope of work included the debottlenecking of the existing cryogenic expander plant for CO2 freeze-up problems in the demethanizer due to the increased CO2 in the inlet feed. Aker Solutions developed the process to achieve the solution to the problem for this existing plant without the addition of an amine unit to remove the CO2 from the inlet gas. The solution was achieved by addition of minimum equipment, piping and instrumentation within the cryogenic plant and saved substantial capital cost compared to the solutions under consideration. Design basis development, basic engineering package, detailed engineering, construction management and plant start-up support 3,000 manhours Estimated cost U.S. $0.5 million.

Scope of Work:

Manhours: Value:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

41

Section 4 Project Experience (cont.)


Section 4.7 Project Profiles YPF Gas Treatment Plant I and II Nequen Province, Argentina
Description: Refrigerated gas plant which included two straight refrigerated NGL recovery plants. The facility included inlet gas cooling using the cold lean gas and external propane refrigeration, gas dehydration with ethylene glycol injection, condensate stabilization and hot oil heating system for all the process heating requirements. The stabilized NGL product was delivered to a high pressure pipeline. The low pressure gas from the stabilizer was compressed to a high pressure and sent to the gas pipeline. Process design, detail engineering support to Tauro engineering in Argentina and start-up assistance. 7,000 manhours

Scope of Work:

Manhours:

G:/Sales_Materials/Qual files/Natural Gas Processing/20100601NGPQual.pdf

42