You are on page 1of 566

GACC

GUIDE TO THE APPOINTMENT OF


CONSULTANTS & CONTRACTORS
SECOND EDITION
F E B R U A R Y 1 9 9 8
G
U
I
D
E
HOME
GACC
EDITION 2: FEB 1998
ACKNOWLEDGEMENTS
The development of the Guide to the Appointment of Consultantsand Contractors( GACC) wasfacilitated
byPACE Central Advice Unit under the direction of the interdepartmental Joint User Group ( JUG) .
The membersof the Sub-Group formed to provide an oversight of the drafting were:
Mr S Dilcock Mr S Dilcock Mr S Dilcock Mr S Dilcock Mr S Dilcock Emplo Emplo Emplo Emplo Employment Ser yment Ser yment Ser yment Ser yment Service vice vice vice vice
Mr P Gollop Mr P Gollop Mr P Gollop Mr P Gollop Mr P Gollop Benef Benef Benef Benef Benefits its its its its Agency Estates Agency Estates Agency Estates Agency Estates Agency Estates
Mr JHogg Mr JHogg Mr JHogg Mr JHogg Mr JHogg Cour Cour Cour Cour Court Ser t Ser t Ser t Ser t Service vice vice vice vice
Mr P Ridgeon Mr P Ridgeon Mr P Ridgeon Mr P Ridgeon Mr P Ridgeon The Buying The Buying The Buying The Buying The Buying Agency Agency Agency Agency Agency
Mr R Reed Mr R Reed Mr R Reed Mr R Reed Mr R Reed D epar D epar D epar D epar D epartment of tment of tment of tment of tment of T TT TTr rr rranspor anspor anspor anspor ansport tt tt
Mr M Sha Mr M Sha Mr M Sha Mr M Sha Mr M Shaw ww ww Cabinet O ff Cabinet O ff Cabinet O ff Cabinet O ff Cabinet O ffice ice ice ice ice
Mr JGbadebo Mr JGbadebo Mr JGbadebo Mr JGbadebo Mr JGbadebo P PP PPA AA AACE CE CE CE CE Centr Centr Centr Centr Central al al al al Advice Unit Advice Unit Advice Unit Advice Unit Advice Unit
The Sub-Group waschaired by a representative from PACE Central Advice Unit.
The substantive drafting wasundertaken by Mr R A Palles-Clark with assistance from Mr P JEyre and
Mr P McGivern of JamesR Knowles, Construction Consultants, 53 Bedford Square, London, WC1B 3DP.
Telephone: 0171 580 3536
Facsimile: 0171 436 4860
Crown Copyright 1998
Construction
Contracts
Consultants
HOME
GACC
EDITION 2 REV 2: JAN 2000
Thisguide issuitable for use under the Scottish legal system aswell as
that of England and Wales.
Where there are substantial legal differencesor procedural
requirementsbetween the English and Scottish systems, separate
sectionshave been written.
The relevant Scottish sectionsare numbered with the suffix SCO T, for
example:
LE 1.2 SIMPLE CO NTRACTS ( English version)
LE 1.2( SCO T) SIMPLE CO NTRACTS ( Scottish version)
To facilitate even easier identification the relevant Scottish sectionsare
printed on green paper. If there isonly one section ( with no SCO T
suffix) then it can be taken asapplicable under both legal systems.
The amendmentsmade to enable the guide to be compatible with the
Scottish legal system were developed in conjunction with Scottish
Executive and their legal advisers.
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 1
CONTENTS
PAGE NO.
ACKNOWLEDGEMENTS
INTRODUCTION (INT)
CONTENTS
INTRODUCTION INT 1.0
BACKGRO UND INT 1.1
GUIDE TO THE APPO INTMENT O F CO NSULTANTS AND CO NTRACTO RS INT 1.2
PURPO SE O F THE GUIDE INT 1.3
STRUCTURE O F THE GUIDE INT 1.4
USE O F THE GUIDE INT 1.5
LIST O F RELATED REFERENCE DO CUMENTS INT 1.6
ABBREVIATIO NS AND DEFINITIO NS INT 1.7
PRINCIPAL TERMS AND CO NCEPTS IN THE CO NSTRUCTIO N INDUSTRY INT 1.8
PROCUREMENT STRATEGIES (PS)
CONTENTS
GENERAL PRINCIPLES PS 1.0
T HE PRO CUREMENT PRO CESS PS 1.1
T HE INTELLIGENT CUSTO MER AND THE RO LE O F CAU/ PS 1.2
PRINCIPLES O F BEST PRACTICE CLIENT PS 1.3
T HE CO NDUCT O F STAFF PS 1.4
MAN AGEMENT RO LES PS 1.5
EFFECTIVE DECISIO N-MAKING PS 1.6
FO CUS O N O UTPUT VALUE PS 1.7
HOME
Page 2
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
PROJECT REQUIREMENTS PS 2.0
PRO JECT IDENTIFIC ATIO N PS 2.1
DEFINING PRO JECT O BJECTIVES PS 2.2
RISK MAN AGEMENT PS 2.3
CO NTRACT STRATEGY PS 2.4
DEFINING THE PRO JECT BRIEF PS 2.5
PROCURING AND MANAGING THE TEAM PS 3.0
T HE NEED FO R A PRO JECT MAN AGER PS 3.1
DEFINING THE PRO JECT T EAM PS 3.2
APPO INTMENT THRO UGH CO MPETITIO N PS 3.3
FO STERING T EAMWO RK PS 3.4
PERFO RMANCE INCENTIVES PS 3.5
MO NITO RING PERFO RMANCE PS 3.6
RECO RD KEEPING PS 3.7
PERFORMANCE EVALUATION PS 4.0
EVALUATING PERFO RMANCE PS 4.1
PRO JECT CRITIQ UES PS 4.2
OTHER ISSUES PS 5.0
PARTNERING PS 5.1
PRIVATE FINANCE INITIATIVE PS 5.2
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 3
PAGE NO.
LEGAL ENVIRONMENT (LE)
CONTENTS
LEGAL FRAMEWORK LE 1.0
PRINCIPLES CO VERING THE LAW O F CO NTRACT IN ENGLAND & WALES LE 1.1
PRINCIPLES CO VERING THE LAW O F CO NTRACT IN SCO TLAND LE 1.1( SCO T)
SIMPLE CO NTRACTS LE 1.2
SIMPLE CO NTRACTS LE 1.2( SCO T)
CO NTRACTS BY DEED LE 1.3
SELF-PRO VIN G CO NTRACTS LE 1.3( SCO T)
PERFO RMANCE AND DETERMINATIO N LE 1.4
PERFO RMANCE AND TERMINATIO N LE 1.4( SCO T)
DISCHARGE O F A CO NTRACT LE 1.5
MISTAKE AND MISREPRESENTATIO N LE 1.6
MISTAKE ( ERRO R) AND MISREPRESENTATIO N LE 1.6( SCO T)
BREACH O F CO NTRACT LE 1.7
DAMAGES FO R BREACH O F CO NTRACT LE 1.8
LIMITATIO N LE 1.9
PRESCRIPTIO N LE 1.9( SCO T)
EVIDENCE O F CO NTRACT LE 1.10
EVIDENCE O F CO NTRACT LE 1.10( SCO T)
ASSIGNMENT LE 1.11
ASSIGNATIO N LE 1.11( SCO T)
N O VATIO N LE 1.12
T RANSACTIO NS WITH O UTSIDE BUSINESSES LE 1.13
PARENT CO MPANY GUARANTEES LE 1.14
PERFO RMANCE BO NDS LE 1.15
STAMP DUTY LE 1.16
PRO CEEDINGS INSTITUTED AGAINST LE 1.17
PRO CEEDINGS INSTITUTED AGAINST LE 1.17( SCO T)
HOME
Page 4
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
INSO LVENCY AND BANKRUPTCY LE 1.18
INSO LVENCY AND BANKRUPTCY LE 1.18( SCO T)
RESERVATIO N O F TITLE LE 1.19
RESERVATIO N O F TITLE LE 1.19( SCO T)
UN FAIR CO NTRACT TERMS ACT 1977 LE 1.20
LEGAL ADVICE LE 1.21
LEGAL ADVICE LE 1.21( SCO T)
OTHER ISSUES LE 2.0
HEALTH & SAFETY ( CDM) LE 2.1
T RANSFER O F UNDERTAKINGS ( TUPE) LE 2.2
RACIAL DISCRIMINATIO N LE 2.3
FAIR EMPLO YMENT ( N O RTHERN IRELAND) ACTS LE 2.4
INTELLECTUAL PRO PERTY, CO PYRIGHT , AND RO YALTIES ETC. LE 2.5
INTELLECTUAL PRO PERTY, CO PYRIGHT , AND RO YALTIES ETC. LE 2.5( SCO T)
PRO PRIETARY CO MPO NENTS/ARTICLES LE 2.6
FIRM PRICE AND VARIATIO N O F PRICE LE 2.7
LIQ UIDATED AND ASCERTAINED DAMAGES LE 2.8
T HE HO USING GRANTS, CO NSTRUCTIO N & REGENERATIO N ACT 1996 LE 2.9
T HE ARBITRATIO N ACT 1996 LE 2.10
ARBITRATIO N ( SCO TLAND ) LE 2.10( SCO T)
CO NSTRUCTIO N INDUSTRY T AX SCHEME LE 2.11
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 5
PAGE NO.
EC PROCUREMENT PROCEDURES (EPP)
CONTENTS
THE SCOPE OF APPLICATION OF THE EC PROCUREMENT
RULES EPP 1.0
GENERAL EPP 1.1
T HE DIRECTIVES EPP 1.2
DECIDING WHICH DIRECTIVE APPLIES EPP 1.3
EX CLUSIO NS EPP 1.4
T HRESHO LDS EPP 1.5
ESTIMATING THE VALUE O F CO MMISSIO NS AND AGGREGATIO N EPP 1.6
PUBLICITY AND THE TYPES O F NO TICE REQ UIRED EPP 1.7
PRO CEDURE FO R ADVERTISING AND AWARDING CO NTRACTS EPP 1.8
ACCELERATED TIMESC ALES EPP 1.9
MO DEL NO TICES AND T HEIR CO NTENT EPP 1.10
N UMBER O F T ENDERERS EPP 1.11
T ENDERER SELECTIO N EPP 1.12
AWARD CRITERIA EPP 1.13
CO NTRACT NO TICE, DECLINE AND DEBRIEFING EPP 1.14
EC/GATT REPO RTING REQ UIREMENTS EPP 1.15
AN N EX EPP 1.1 CATEGO RIES O F SERVICES Annex
EPP 1.1.1
EPP 1.2 NO TICES REQ UIRED UNDER EC PUBLIC PRO CUREMENT Annex
RULES EPP 1.2.1
EPP 1.3 PRO CEDURES AND TIMESC ALES FO R ADVERTISING AND
AWARDING CO NTRACTS Annex
EPP 1.3.1
EPP 1.4 WO RKS CO NTRACTS - MO DEL CO NTRACT N OTICES Annex
EPP 1.4.1
EPP 1.5 SERVICES CO NTRACTS - MO DEL NO TICES Annex
EPP 1.5.1
HOME
Page 6
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
CONSULTANTS (CST)
CONTENTS
COMMISSIONING STRATEGIES CST 1.0
PRO CUREMENT PRO CESS AND PRO GRAMME CST 1.1
APPLIC ATIO N O F EC PUBLIC PRO CUREMENT RULES CST 1.2
PRO PERTY MAN AGEMENT TYPE CO MMISSIO NS CST 1.3
INDIVIDUAL PRO JECT MAN AGEMENT TYPE CO MMISSIO N CST 1.4
INDIVIDUAL DISCIPLINE CO MMISSIO NS CST 1.5
T ERM CO MMISSIO NS CST 1.6
COMMISSION FILE CST 2.0
IDENTIFIC ATIO N CST 2.1
SUB FILES CST 2.2
RETENTIO N PERIO DS CST 2.3
RETENTIO N PERIO DS CST 2.3( SCO T)
CONSULTANT SELECTION CST 3.0
SELECTIO N O F FIRMS CST 3.1
N EW Q UALIFICATIO N SYSTEM ( NQ S) CST 3.2
T HE LO NG LISTING PRO CESS CST 3.3
IDENTIFY PRE-SELECTIO N CRITERIA CST 3.4
PRE-SELECTIO N INFO RMATIO N CST 3.5
CO MPILATIO N O F SHO RT LISTS CST 3.6
T HE NUMBER O F T ENDERERS CST 3.7
Q UALITY PRICE MECHANISM CST 3.8
PRE-TENDER INTERVIEW STAGE CST 3.9
SINGLE TENDER CST 3.10
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 7
PAGE NO.
TENDER PROCESS CST 4.0
GENERAL CST 4.1
FO RMS O F TENDERING CST 4.2
T ENDER DO CUMENTS CST 4.3
T ENDER PERIO DS CST 4.4
T ENDER BO X ES CST 4.5
SECURE INFO RMATIO N CST 4.6
DO CUMENTATIO N STANDARDS CST 4.7
DISPATCH O F T ENDERS CST 4.8
Q UERIES BY T ENDERERS CST 4.9
T ENDER BO ARDS CST 4.10
O PENING THE T ENDER BO X CST 4.11
O PENING O F T ENDERS CST 4.12
T HE TENDER RECO RD BO O K CST 4.13
LATE T ENDERS CST 4.14
TENDER EVALUATION CST 5.0
EVALUATIO N CRITERIA CST 5.1
FEE SCHEDULES CST 5.2
INCENTIVE FEES CST 5.3
EVALUATIO N PRO CEDURE CST 5.4
T ENDER ANO MALIES CST 5.5
Q UALIFIED TENDERS CST 5.6
AMENDED T ENDERS CST 5.7
AMENDED TENDER DO CUMENTS CST 5.8
RE-INVITATIO N O F TENDERS CST 5.9
RECO MMENDATIO N FO R ACCEPTANCE CST 5.10
HOME
Page 8
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
AWARDING COMMISSIONS AND DECLINING TENDERS CST 6.0
LEGAL CO NTRACT FO RMATIO N CST 6.1
ACCEPTANCE O F TENDER CST 6.2
LETTER O F ACCEPTANCE CST 6.3
DECLINE O F UNSUCCESSFUL TENDERS CST 6.4
EX ECUTIO N O F FO RMAL AGREEMENT CST 6.5
DEBRIEFING CST 7.0
REQ UEST FO R DEBRIEFING CST 7.1
DEBRIEFING INTERVIEWS CST 7.2
MANAGEMENT OF COMMISSIONS CST 8.0
RO LES AND RESPO NSIBILITIES O F THE CO MMISSIO N MAN AGER/THE PRO JECT SPO NSO R CST 8.1
CO NSULTANT AND SUB-CO NSULTANTS CST 8.2
PRO FESSIO NAL INDEMNITY INSURANCE CST 8.3
BILL PAYING AND CHECKING PRO CEDURES CST 8.4
DETERMINATIO N/TERMINATIO N PRO CEDURES CST 8.5
DETERMINATIO N/TERMINATIO N DUE TO DEFAULT CST 8.6
CLAIMS AND DISPUTES CST 9.0
HANDLING O F CLAIMS BY AND AGAINST THE CST 9.1
CLAIMS ARISING FRO M DEFAULT O R NEGLIGENCE BY A CST 9.2
CO NSULTANT O R CO NTRACTO R
ALTERNATIVE DISPUTE RESO LUTIO N PRO CEDURES CST 9.3
ARBITRATIO N CST 9.4
WRITS AND SUMMO NSES CST 9.5
EX GRATIA CLAIMS CST 9.6
PERSO NAL INJURY CLAIMS CST 9.7
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 9
PAGE NO.
PERFORMANCE REPORTING CST 10.0
PERFO RMANCE REPO RTING GENERALLY CST 10.1
PERFO RMANCE REPO RTING TO THE NEW Q UALIFIC ATIO N SYSTEM ( NQ S) CST 10.2
CO NSULT NO TICES WITHIN NQ S CST 10.3
CONTRACTORS (CRS)
CONTENTS
CONTRACTING STRATEGIES CRS 1.0
PRO CUREMENT PRO CESS AND PRO GRAMME CRS 1.1
APPLIC ATIO N O F EC PUBLIC PRO CUREMENT RULES CRS 1.2
INTRO DUCTIO N TO THE CHO ICE O F CO NTRACT CRS 1.3
CO NTRACTS USING BILLS O F Q UANTITIES CRS 1.4
CO NTRACTS USING SCHEDULES O F RATES CRS 1.5
SIMPLE LUMP SUM CO NTRACTS CRS 1.6
T RADITIO NAL LUMP SUM CO NTRACTS CRS 1.7
DESIGN AND BUILD CO NTRACTS CRS 1.8
PRIME CO ST CO NTRACTS CRS 1.9
MAN AGEMENT CO NTRACTS CRS 1.10
CO NSTRUCTIO N MAN AGEMENT CO NTRACTS CRS 1.11
DESIGN AND MAN AGE CO NTRACTS CRS 1.12
EX TENSIO N CO NTRACTS AND VARIATIO NS CRS 1.13
T ERM CO NTRACTS CRS 1.14
STANDARD GO VERNMENT CO NTRACTS CRS 1.15
GC/WO RKS/1 ( 1998) - LUMP SUM WITH Q UANTITIES CRS 1.15.1
GC/WO RKS/1 ( 1998) - LUMP SUM WITHO UT Q UANTITIES CRS 1.15.2
GC/WO RKS/1 ( 1998) - SINGLE STAGE DESIGN AND BUILD VERSIO N CRS 1.15.3
GC/WO RKS/1 ( 1999) - T WO STAGE DESIGN AND BUILD VERSIO N CRS 1.15.4
GC/WO RKS/1 ( 1999) - WITH Q UANTITIES CO NSTRUCTIO N MAN AGEMENT TRADE
CO NTRACT CRS 1.15.5
WITHO UT Q UANTITIES CO NSTRUCTIO N MAN AGEMENT TRADE
CO NTRACT
HOME
Page 10
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
GC/WO RKS/2 ( 1998) - BUILDING AND CIVIL ENGINEERING MINO R WO RKS CRS 1.15.6
GC/WO RKS/3 ( 1998) - M ECHANICAL AND ELECTRICAL ENGINEERING WO RKS CRS 1.15.7
GC/WO RKS/4 ( 1998) - BUILDING, CIVIL ENGINEERING, MECHANIC AL AND ELECTRIC AL
WO RKS CRS 1.15.8
GC/WO RKS/6 ( 1999) - DAYWO RK TERM CO NTRACT CRS 1.15.9
GC/WO RKS/7 ( 1999) - MEASURED TERM CO NTRACT CRS 1.15.10
GC/WO RKS/8 ( 1999) - SPECIALIST TERM CO NTRACT FO R MAINTENANCE O F EQ UIPMENT CRS 1.15.11
GC/WO RKS/9 ( 1999) - O PERATIO N , REPAIRS AND MAINTENANCE CO NTRACT FO R
MECHANIC AL AND ELECTRIC AL PLANT, ELECTRICAL PLANT,
EQ UIPMENT AND INSTALLATIO NS, ETC. CRS 1.15.12
C1303 - WINDO W CLEANING AND CRS 1.15.13
C1304 - CHIMNEY SWEEPING
C1306 - MAINTENANCE O F GARDENS, GRO UNDS, ETC. AND CRS 1.15.14
C1312 - SUPPLY AND APPLIC ATIO N O F HERBICIDES, ETC.
C1804 - REPAIR O F PLANT CRS 1.15.15
CONTRACTS FILE CRS 2.0
IDENTIFIC ATIO N CRS 2.1
SUB-FILES CRS 2.2
RETENTIO N PERIO DS CRS 2.3
RETENTIO N PERIO DS CRS 2.3( SCO T)
CONTRACTOR SELECTION CRS 3.0
SELECTIO N O F FIRMS CRS 3.1
N EW Q UALIFICATIO N SYSTEM ( NQ S) CRS 3.2
T HE LO NG LISTING PRO CESS CRS 3.3
PRE-SELECTIO N PRO CEDURES CRS 3.4
CO MPILATIO N O F SHO RT LISTS CRS 3.5
T HE NUMBER O F T ENDERERS CRS 3.6
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 11
PAGE NO.
TENDERING PROCESS CRS 4.0
DO CUMENTATIO N CRS 4.1
INSTRUCTIO NS/NO TICES TO TENDERERS/TENDER PERIO DS CRS 4.2
MID TENDER INTERVIEWS CRS 4.3
T ENDER BO ARDS CRS 4.4
O PENING O F T ENDERS CRS 4.5
T HE TENDER RECO RD BO O K CRS 4.6
LATE T ENDERS CRS 4.7
TENDER EVALUATION CRS 5.0
GENERAL CRS 5.1
CRITERIA FO R EVALUATIO N CRS 5.2
Q UALIFIED TENDERS CRS 5.3
ALTERNATIVE O FFERS CRS 5.4
AMENDED T ENDERS CRS 5.5
ERRO RS IN PRICED BILLS CRS 5.6
PO ST TENDER N EGO TIATIO N CRS 5.7
RE-INVITATIO N O F TENDERS CRS 5.8
T ENDER REPO RTING CRS 5.9
AWARDING CONTRACTS & DECLINING TENDERS CRS 6.0
LEGAL CO NTRACT FO RMATIO N CRS 6.1
ACCEPTANCE O F TENDER CRS 6.2
LETTERS O F ACCEPTANCE CRS 6.3
DECLINE O F UNSUCCESSFUL TENDERERS CRS 6.4
EX ECUTIO N O F FO RMAL AGREEMENT CRS 6.5
HOME
Page 12
GACC
EDITION 2 REV 2: JAN 2000
PAGE NO.
DEBRIEFING CRS 7.0
REQ UESTS FO R DEBRIEFING CRS 7.1
DEBRIEFING INTERVIEWS CRS 7.2
NOMINATION OF SUB-CONTRACTORS CRS 8.0
N O MINATIO N PRO CEDURES CRS 8.1
PRIME CO STS CRS 8.2
ARRANGING A NO MINATED SUB-CO NTRACT CRS 8.3
ESTABLISHING A CO NTRACT CRS 8.4
LIQ UIDATIO N O F A NO MINATED SUB-CO NTRACTO R CRS 8.5
SELECTED O R APPRO VED SUB-CO NTRACTO RS CRS 8.6
MANAGEMENT OF CONTRACTS CRS 9.0
RO LE O F THE PRO JECT MAN AGER CRS 9.1
RO LE O F THE PRO JECT SPO NSO R CRS 9.2
BILL PAYING CRS 9.3
CHECKING PRO CEDURES CRS 9.4
DETERMINATIO N/TERMINATIO N PRO CEDURES CRS 9.5
CLAIMS & DISPUTES CRS 10.0
GENERAL CRS 10.1
CO NTRACT CLAIMS AGAINST THE DEPARTMENT CRS 10.2
AVO IDANCE O F CLAIMS CRS 10.3
MAN AGIN G CLAIMS CRS 10.4
PRESENTATIO N O F CLAIMS CRS 10.5
CLAIMS AGAINST CO NTRACTO RS CRS 10.6
ARBITRATIO N CRS 10.7
EX GRATIA CLAIMS CRS 10.8
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 13
PAGE NO.
MATTERS ARISING ON COMPLETION CRS 11.0
LIQ UIDATED AND ASCERTAINED DAMAGES CRS 11.1
MAINTENANCE PERIO DS CRS 11.2
PAYMENTS CRS 11.3
O VERPAYMENTS CRS 11.4
HANDO VER CRS 11.5
PERFORMANCE REPORTING CRS 12.0
GENERAL CRS 12.1
PERFO RMANCE REPO RTING TO NQ S CRS 12.2
HOME
INT 1.0 INTRODUCTION
INT 1.1 BACKGRO UND
INT 1.2 GUIDE TO THE APPO INTMENT O F CO NSULTANTS AND CO NTRACTO RS
INT 1.3 PURPO SE O F THE GUIDE
INT 1.4 STRUCTURE O F THE GUIDE
INT 1.5 USE O F THE GUIDE
INT 1.6 LIST O F RELATED REFERENCE DO CUMENTS
INT 1.7 ABBREVIATIO NS AND DEFINITIO NS
INT 1.8 PRINCIPAL TERMS AND CO NCEPTS IN THE CO NSTRUCTIO N INDUSTRY
HOME
GACC
EDITION 2: FEB 1998
INT 1.0 INTRODUCTION
INT 1.1 BACKGROUND
O n 1 April 1996 Departmentstook over from Property Holdings
responsibility asprincipalsfor the property they occupy. At the same
time Property Holdingswasdisbanded and replaced by the new
executive agency PropertyAdvisersto the Civil Estate ( PACE) . PACE
would;
co-ordinate the Governmentsactivity on the Civil Estate;
promote rationalisation of the Estate;
provide Departmentswith a body of off-the-shelf advice and
support;
provide intelligent customer support; and
provide management of the Governmentsvacant properties.
INT 1.1
HOME
GACC
EDITION 2: FEB 1998
INT 1.2 GUIDE TO THE APPOINTMENT OF CONSULTANTS AND
CONTRACTORS - EDITION 2
The first edition of the Guide issued in September 1996 provided
essential advice and guidance to assist Departmentsand Agenciesin
discharging their responsibilitiesfor the management of their property-
related procurement.
Thissecond edition hasbeen developed by the PACE Central Advice
Unit ( C AU) to reflect the variouschangesin legislation, systemsand
accepted practiceswhich have occurred since then. It also takes
account of interim changesin the organisation of other departmental
advice providers.
INT 1.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
INT 1.3 PURPOSE OF THE GUIDE
The Guide hasbeen written to assist Departmentsin their role asthe
intelligent customer whereby they are required to have sufficient
intelligent customer support to be able to brief, appoint and monitor
consultantsor contractorsin a clear and cost effective manner.
Departmentsmay either rely on their own in-house expertise or buy in
such support from PACE. Whichever route they choose Departments
will retain the final responsibility for all decisionson the propertiesthey
occupy.
The Guide isintended to provide guidance on procurement in the
context of property management. Much of the work to be procured in
thiscontext will therefore involve the management and maintenance of
existing facilitiesrather than the procurement of projectsinvolving large
scale development, redevelopment or extension work. Such work does
however fall under the general heading of property management and is
considered in the Guide.
Itspurpose isto encourage the most efficient and cost effective means
of engaging consultantsand contractorsto carry out necessary services
and works. In particular the Guide promotesthe procurement of
serviceson the basisof best value for money, where quality isa major
criteria for selection and service providersare not commissioned solely
on the basisof the cheapest price. It promotesa view of procurement
which embracesthe overall long-term objectivesof a project and gives
consideration to whole-life costs.
It isrecognised that there isa wide variation in the number, experience
and qualification of procurement staff within the departments. For this
reason the Guide isintended to be a practical document for use by
administrative and professional staff at all levelsand hasbeen written
specifically to assist informed lay personsand asan aide memoire. The
Guide isgenerally not mandatory and given proceduresmay be adapted
to suit the specific requirementsof any particular commission or project.
The Guide will be updated from time to time when necessary and the
C AU will publish Information Notesgiving detailsof any important
changes.
INT 1.3
HOME
GACC
EDITION 2 REV 1: JAN 1999
INT 1.4 STRUCTURE OF THE GUIDE
It isdivided into five main sections: Procurement Strategies, Legal
Environment, EC Procurement Procedures, ConsultantsSection and
ContractorsSection. Each section isfurther divided into subjects( e.g.
general principles) , headingsand where necessary subheadings. The
contentspagesare structured to allow direct accessto heading
references. Alternatively, there isa fully cross-reference index at the back
of the Guide.
The top of the page carriesthe heading and any subheading together
with an index card icon confirming the pageslocation in the context of
the whole Guide. At the bottom of the page isthe page reference. The
reference system isin numerical order based on section prefix followed
by the section reference. The abbreviationsdenote the main sectionsas
follows:-
PS Procurement Strategies
LE Legal Environment
EPP EC Procurement Procedures
CST Consultants Section
CRS ContractorsSection
The right hand margin contains, where appropriate, iconsrelating to the
adjoining text. These are shown below:
Thiswarning triangle indicateswhere particular care should be taken to
ensure that departmentsor their advisersare taking relevant action.
Generally, thiswill relate to situationswhere specialist advice may need
to be sought on particular issues.
Thisblue icon isthe cross-referencing code to other related sectionsof
the Guide. The reference isin the abbreviated code found at the bottom
of the page.
Thisicon indicateswhere a cross-reference to other documentsor
further reading ismade.
Where it isappropriate to do so, a topic isconcluded with a list of
actionsor pointsfor consideration under the heading Key Points.
The footer to each page also containspublishing information consisting
of the edition number and the date of issue.
L
! !! !!
CRS 3.1

INT 1.4
HOME
GACC
EDITION 2: FEB 1998
Volume 2 isnot procedural but isintended to give Departments
best examples of commissioning documentation and Tender
packages. It isonly available on CD Rom disk.
It containsthe following:
PACE Docunentation:
Property Management Commission ( CU version)
EstatesManagement Commission
WorksManagement Commission
The PMC Guide ( CU version)
Term WorksCommission
EstatesCommission
Term EstatesCommission
Term Audit Commission
Project Advisor Commission
PH Legal ServicesContract
Governnent Forns of Contract
There are variousGovernment formsof contract available. For
ease of reference a copy of section CRS 1.15.1.1 to 1.15.14.1 is
incorporated into volume 2, asisa copy of contract formsC910,
C1102, C1301, C1303, C1304, C1306, C1312, C1401, C1501
and C1804. The GC formsreferred to in CRS 1.15.1 to 1.15.6
are obtainable from HMSO .
5tandard Fire Precautions for Contractorsengaged on crown
works( 1995 Edition) : applicable to contractorsengaged on works
for Crown Civil and Defence Estates.
5cottisb Office (Leitb) FM Contract CIeaning Contract
EnpIoynent 5ervice 5ecurity 5ervices Contract
Duties of CIerk of Works
Property HoIdings BuiIding ControI ConpIiance
Cbecking Connission
All relevant suppIenentary conditions aslisted in Section CRS
1.15.15 of GACC
Example schedules used by Employment Service
Schedule for window cleaning for use with c1303 form of contract.
Schedule for clerk of work contract.
Schedule for legal servicescontract.
Schedule for office cleaning contract.
INT 1.4.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
INT 1.5 USE OF THE GUIDE
The Guide coversgeneral advice and recommended proceduresthat
may be followed in connection with the selection, appointment and
management of consultantsand contractors. Assuch, it necessarily
includesmaterial on EC procurement requirements, purchasing policy,
strategic issuesand procedural advice. In short, it coversa range of
issueswith which Departmentsshould be familiar when taking on and
managing consultantsand contractors. It isone of a family of CAU
produced guidance material which hasbeen, or isin the processof
being, compiled. They are:
The EstatesServicesGuide ( ESG) 3rd Edition ( England/Wales
version) published in June 1999 providesadvice relating to property
management under the subject headings; Strategic, Acquisition,
General Estate Management and Disposal;
The PremisesManagement Guide ( PMG) 2nd Edition published in
September 1999 providesadvice on policy and functionsassociated
with premisesmanagement.
The Fire Safety Guide, published in March 1998, providesclear and
concise guidance on current fire safety legislation and Government
policy in thisarea.
Crown Fire Standards, published in December 1997, provides
guidance to those involved in the design of new buildingsand in the
refurbishment and alteration of existing buildings.
BusinessContinuity Planning Guide, published in May 1998, assists
Departmentsin discharging their responsibilitiesfor the
management of their propertiesand the activitieswhich are carried
out at those properties. It guidestowardsthe most efficient and cost
effective meansof enabling managersand usersto plan against, and
recover from, the effectsof an incident affecting individual
properties.
Guide to Requirementsfor O ffice Buildings, and itsassociated
schedule, highlight the requirementswhich normally should be
incorporated in office schemes. Two versionsexist:
- Version 1 dealswith the physical standards/requirementsfor new
projectsand refurbishmentsprocured asPrivate Developer
Schemes;
- Version 2 coversthe standardsfor Crown Build type schemes.
INT 1.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
INT 1.6 LIST OF RELATED REFERENCE DOCUMENTS
SHO R SHO R SHO R SHO R SHO RT T T T T T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE PUBLISHED PUBLISHED PUBLISHED PUBLISHED PUBLISHED
Application of The Procurement of Construction
Competitive Professional Services: Industry Council,
Tendering ( CIC) Guidelinesfor the Application London, ( 1992)
of Competitive Tendering
Construction Construction Procurement by TSO , London
Procurement by Government: An Efficiency ( 1995)
Government Unit Scrutiny
Procurement Essential Requirementsfor HM Treasury
Group Guidance Construction Procurement
No. 1
Procurement Value for Money in HM Treasury
Group Guidance Construction Procurement
No. 2
Procurement Appointment of Consultants HM Treasury
Group Guidance and Contractors
No. 3
Procurement Teamworking, Partnering and HM Treasury
Group Guidance Incentives
No. 4
Procurement Procurement Strategies HM Treasury
Group Guidance
No. 5
Procurement Financial Aspectsof Projects HM Treasury
Group Guidance
No. 6
Setting New Setting New Standards: A TSO , London
Standards Strategy for Government ( 1995)
Procurement
INT 1.6.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
SHO R SHO R SHO R SHO R SHO RT T T T T T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE T IT LE PUBLISHED PUBLISHED PUBLISHED PUBLISHED PUBLISHED
The Latham Constructing the Team by Sir HMSO , London
Report Michael Latham; Final Report ( 1994)
of the Government/Industry
Review of Procurement and
Contractual Arrangementsin
the UK Construction Industry.
Thinking About Thinking About Building The Business
Building Round Table,
London, ( 1995)
Thinking About Thinking About Facilities The Business
Facilities Management Round Table,
Management London ( 1996)
Value Assessment The Procurement of Construction
of Competitive Professional Services: Guidelines Industry Council,
Tenders( CIC) for the Value Assessment of London, ( 1994)
Competitive Tenders
Value by Value by Competition; A Guide CIRIA, London
Competition to the Competitive ( 1994)
( CIRIA) Procurement of Consultancy
Servicesfor Construction
INT 1.6.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
1.7 ABBREVIATIONS AND DEFINITIONS
CAU Central Advice Unit
CDM Construction ( Design & Management)
Regulations1994
commission Any servicesor worksrequired to be procured to
satisfy a particular property management
requirement.
commission/ O fficer, other than a project sponsor, who is
contract responsible for the delivery of a consultancy
manager contract or workscontract
CUP * Central Unit on Procurement
Department Department or Authority with procurement
responsibilities
DETR Department of Environment Transport and the
Regions
GACC Guide to the Appointment of Consultantsand
Contractors
GATT General Agreement on Tariffsand Trade
legal adviser Solicitor/Contracts Consultant
PACE Property Advisersto the Civil Estate
PFI Private Finance Initiative
project Work of a type which requiresthe appointment
of a project sponsor such asdevelopment,
redevelopment or large scale extension projects.
project sponsor O fficer responsible for the delivery of a project
INT 1.7.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
the Secretary of the Secretary of State for the Environment,
State Transport and the Regions
TUPE The Transfer of Undertakings( Protection of
Employment) Regulations1981
works Contractsfor physical construction work rather
than consultancy or servicescommissions.
Note: * HM TreasurysCentral Unit on Procurement hasnow changed
itsname to Procurement Practice and Development. However, for the
time being at least, the seriesof CUP Guidance Noteswill retain their
current CUP referencesand numbers.
INT 1.7.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
INT 1.8 PRINCIPAL TERMS AND CONCEPTS IN THE CONSTRUCTION
INDUSTRY
There are technical termswhich are generally accepted in the building
industry but which not all readersmay be familiar with. These are
explained below:
( 1) Bill of Approximate Quantities (BAQs) - contains
correctly described itemsof work but only estimated or
approximate quantities. It isbased on provisional or assumed
information before the design isfully developed. The work
subsequently ordered ismeasured and priced on the basisof
the BAQ sin order to arrive at the final cost of the contract.
( 2) Bill of Quantities (BQs) - containscorrectly described
itemsand accurate quantitiestaken from firm and detailed
information at the completion of the design. It may contain
some sectionsmarked provisional where there isno firm
design information but thisshould be minimal. Re-measurement
only takesplace on those sectionsof the bill which are
provisional, or are the subject of variation, or where there isa
discrepancy between the bill and the drawingsissued to the
contractor.
( 3) Design and Construct - or design and build describesthe
method of procuring workscontractswhich involve the
contractor in developing a detailed design solution based on a
set of employersrequirementsand then building to the design.
The contractor therefore assumesboth design and
construction risks.
( 4) Facilities Management (FM) - isan integrated approach to
maintaining, improving and adapting the buildingsof an
organisation in order to create an environment that strongly
supportsthe primary objectivesof that organisation.
Treasury guidance identifiesFM asContracting for Strategic
Services.
( 5) Joint Ventures - - - - - these are usually only used on very large
projectswhere a single contractor lacksthe technical or
financial resourcesto handle the project alone. Two or more
companiesset up a consortium for the execution of the
contract, after which it isdissolved, so arrangementsmust be
made to ensure that servicesare available to deal with any
mattersarising once the final certificate issigned and the works
handed over.
INT 1.8.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
( 6) Liquidated and Ascertained Damages (LADs) - -- --
Contractual damages( stated in the contract) to be paid by the
contractor to the employer for any period of delay to the
completion of a project for which the contractor isnot entitled
to extensionsof time.
( 7) Partnering - isabout fostering open and co-operative
relationshipsbetween membersof the construction team, the
contractor and the Department.
O ne of the principal objectivesisto reduce or avoid conflict. The
principle isgenerally appropriate but not limited to the forging of
longer-term relationshipswith supplierswhich are based on
mutual trust and a joint aim to produce a product from which
both benefit.
( 8) Prime Cost ltems/5ums (PC) - where a specialist service
cannot be fully described in the specification the estimated cost
isincluded asa PC item. The PC sum isdeducted from the
contract figure and the actual cost of the service included.
( 9) Project Hanager (PH) - the PM isusually appointed by a
Department to act asthe Departmentsrepresentative in
dealingswith other membersof the construction team. The PM
may also directly supervise the construction works.
( 10) Project 5ponsor (P5) - - - - - the PS for any major project should
be an executive from within the Department. The PS need not
have a background in construction/contract management but
should have a clear understanding of the organisations
requirementsand approvalsprocedure. The PS must have the
delegated responsibility to act quickly and effectively. The prime
project related tasksof the PS are:
( a) to establish a clear statement of objectives;
( b) to be responsible for the definition of the project at each
stage approval decisionsare required;
( c) to ensure that funding isavailable when required and all
necessary approvalsare obtained;
( d) to establish the day-to-day requirement for project
management and professional servicesfor the project
including delegationsto the project manager and
reporting requirements;
INT 1.8.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
( e) to manage and monitor the performance of the project
manager; where it isdeemed appropriate to appoint one;
( f) to provide the sole source of contact and decision-making
to all partiesconcerned with the project from outside the
Department, and to provide decisionsasrequired by the
programme. The PS isresponsible for the completion of
the project to programme within the budget, and to the
required level of quality.
( 11) Provisional 5ums - - - - - A sum included when it hasnot been
decided whether work may or may not be required to be
carried out. Thisprovisional sum isdeleted from the contract
figure and the actual cost ( if required) isincluded when
appropriate. Provisional and PC sumsare included in order to
ensure that all contractorstender on the same basisand parity
of tender isobtained. Provisional sumsare either known, or
undefined - where the workscope isunknown.
( 12) 5chedule of Rates or Prices - where the requirement is
indeterminate, or it isnot necessary to quantify components, a
list of correctly described itemsare shown. Any variationsare
based on the cost shown against described items.
( 13) 5equential Tendering - -- -- the somewhat misleading name used
for a system in which PC sumsare used to cover more than half
of the work, and in which the corresponding sub-contract tender
invitations/nominationsare made in a planned sequence after
the main contract hasstarted. Competition for the main contract
isbased on the price tendered for those partsof the work, on
which design work iscomplete ( usually just the foundationsand
mainframe of the building) .
( 14) Turnkey Projects - - - - - a type of design and construct in which
even the basic design isentrusted to the single turnkey
contractor ( or equipment manufacturer where the building
concerned islessimportant than itscontents) . In turnkey
projectsthe Department commissionsa specialist manufacturer
to design a project and to execute the works. The Department
then expectsto be only minimally involved until it receivesthe
completed project i.e., all it hasto do isturn the key.
INT 1.8.3
HOME
GACC
EDITION 2 REV 1: JAN 1999
( 15) Variation Orders or lnstructions - a written document
given to the contractor changing or varying the contract e.g., in
relation to the design of the works, or how they may be
executed. Variouscontract formsuse different terms, and allow
different opportunitiesfor the contractor to claim payment over
and above itstendered sum or rates. Instructionsmay be given
orally but must usually be confirmed in writing in order to be
effective.
( 16) Variation of Price (VOP) - - - - - when the contract pricesare
adjusted by meansof an updating index or by reference to
invoiced current prices( generally the former) . Thuscontracts
incorporating VO P provisionsrecompense the contractor for
inflationary costsduring the period of the workscontract.
INT 1.8.4
HOME
PS 1.0 GENERAL PRlNClPLE5
PS 1.1 THE PRO CUREMENT PRO CESS
PS 1.2 THE INTELLIGENT CUSTO MER AND THE RO LE O F C AU/PACE
PS 1.3 PRINCIPLES O F BEST PRACTICE CLIENT
PS 1.4 THE CO NDUCT O F STAFF
PS 1.5 DEPARTMENTAL MANAGEMENT RO LES
PS 1.6 EFFECTIVE DECISIO N-MAKING
PS 1.7 FO CUS O N O UTPUT VALUE
PS 2.0 PROjECT REQUlREMENT5
PS 2.1 PRO JECT IDENTIFICATIO N
PS 2.2 DEFINING PRO JECT O BJECTIVES
PS 2.3 RISK MANAGEMENT
PS 2.4 CO NTRACT STRATEGY
PS 2.4.1 GENERAL
PS 2.4.2 PRO PERTY MANAGEMENT FUNCTIO NS
PS 2.4.3 FACILITIES MANAGEMENT STRATEGIES
PS 2.4.4 WO RKS CO NTRACT STRATEGIES
PS 2.5 DEFINING THE PRO JECT BRIEF
PS 3.0 PROCURlNG AND MANAGlNG THE TEAM
PS 3.1 THE NEED FO R A PRO JECT MANAGER
PS 3.2 DEFINING THE PRO JECT TEAM
PS 3.3 APPO INTMENT THRO UGH CO MPETITIO N
PS 3.4 FO STERING TEAMWO RK
PS 3.5 PERFO RMANCE INCENTIVES
PS 3.6 MO NITO RING PERFO RMANCE
PS 3.7 RECO RD KEEPING
HOME
PS 4.0 PERFORMANCE EVALUATlON
PS 4.1 EVALUATING PERFO RMANCE
PS 4.2 PRO JECT CRITIQ UES
PS 5.0 OTHER l55UE5
PS 5.1 PARTNERING
PS 5.2 PRIVATE FINANCE INITIATIVE
HOME
GACC
EDITION 2: FEB 1998
PS 1.0 GENERAL PRINCIPLES
PS 1.1 THE PROCUREMENT PROCESS
To procure meansto obtain by care and effort. It takescare, effort,
judgement and clear decision-making to procure construction services.
There isa high level of service in any construction commission, and
there are a number of featuresof serviceswhich make the
procurement decision a difficult one. Servicesare:
intangible - they cannot be stored, displayed, sampled before
use, or easily communicated;
frequently - pricesare difficult to set and standardisation is
non-standard difficult to achieve;
inseparable - the consumer isinvolved to some extent in the
production. Servicesare sold first and then
produced and consumed simultaneously.
The quality of a service product istherefore difficult to evaluate before
it isdelivered. It istherefore essential to have in place effective, well
structured and well managed procurement systemswhich enable the
management and control of the risksinherent in any procurement
decision.
The procurement processisa circular processwhich involvesthe
general stepsset out in Figure 1.1 on the next page:
THE PROCUREMENT PROCESS
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.1.1
HOME
GACC
EDITION 2: FEB 1998
DEFINE BUSINESS NEED AND
PRO JECT O BJECTIVES
DECIDE CO NTRACT
STRATEGY
DEFINE THE BRIEF O BTAIN ADVICE O N
AND/O R UNDERSTAND
MARKET CAPABILITY DEFINE TENDER LIST
INVITE TENDERS
EVALUAT E AND REFINE
TENDERS
AWARD CO NTRACT
AND DEBRIEF
REVIEW PERFO RMANCE
AND FEEDBACK
ADMINISTER
AND MANAGE
CO NTRACT
Fig 1.1 The Procurement Process
The performance review and feedback isan important step in the
process. It ismost useful if it isa formal process. If in the form of a
critique it helpsprocurement staff to consider lessonsthat can be
learnt by the Department from the commission asa whole aswell asa
close examination of the performance of each consultant or contractor.
The feedback isan all important part of improving Departmental
knowledge and expertise in the intelligent customer role.
Departmentscan make the greatest contribution to the enhancement
of the competitivenessof suppliersby managing their own
procurement intelligently and well. An important element of thisisto
combine competition and co-operation in an optimum way.
Key Points
Effective procurement isabout having a clear set of objectives,
defining the scope and content of what isrequired from the supplier
and being clear about and managing expectations. Improvement in
thisarea will have a direct effect in reducing the scope for disputes.
THE PROCUREMENT PROCESS
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.1.2
HOME
GACC
EDITION 2: FEB 1998
PS 1.2 THE INTELLIGENT CUSTOMER AND THE ROLE OF
CAU/PACE
PS 1.2.1 Intelligent Customer Role
In devising the appropriate procurement strategy to suit Departmental
operationsit isessential to appreciate the minimum requirementsfor
the in-house ( within Government) role. The Treasury requires
Departmentsto retain sufficient competent intelligent customer
support resource to be able to brief and manage professionals, ask the
right questions, know when the correct answersare being given and
decide what further action to take. The required expertise can be
achieved by:
training in-house administrative staff to the appropriate level of
competency; or
employing the requisite professionalsin-house; or
retaining PACE.
Buying the intelligent customer support from the private sector under a
framework agreement or contract isnot an option open to
Departments.
To help Departmentsassesstheir resource needssome amplification of
the role isset out below.
The term intelligent customer relatesto a residual function that
remainswith the purchaser of the servicesonce the provision of such
serviceshasbeen out sourced. It isa role that must remain within
Government. Whatever the source of supply the purchaser of property
related procurement or supply functionsneedsto retain sufficient in-
house knowledge, experience or expertise relating to those functions
to plan, specify, commission and subsequently to manage the services
being procured to ensure best value for money isobtained.
THE INTELLIGENT CUSTOMER ROLE
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.2.1.1
HOME
GACC
EDITION 2: FEB 1998
The scope of the intelligent customer capability will necessarily be a
matter of judgement based not only on the nature of Departments
property management but also itsapproach to property management.
Whilst it might for example be possible in some areasto set a
consultant to judge other consultants, and therefore reduce the
number of in-house purchasing and contract management staff, that is
not alwaysfeasible. Ultimately, there remainswith Departmentsthe
residual responsibility for both sound management and public
accountability.
Purchasersmust be able to demonstrate value for money in the
servicesprocured through the management of budgets, monitoring of
expenditure and benchmarking of services.
Key Points
Ensure that in deciding procurement strategiesfull account istaken
of the associated intelligent customer role and itseconomic
provision.
THE INTELLIGENT CUSTOMER ROLE
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.2.1.2
HOME
GACC
EDITION 2: FEB 1998
PS 1.2.2 THE ROLE OF CAU/PACE
O n 1 April 1996, Property Holdingswasdisbanded and succeeded by
PropertyAdvisersto the Civil Estate ( PACE) . The principal role of
PACE isto co-ordinate Departments activitieson the civil estate and
provide intelligent customer support. It isalso responsible for the
management of all Governmentsvacant space/properties.
The Central Advice Unit ( CAU) isa part of PACE but wasset up on 1
April 1995 to provide adequate advice and support to Departmentsto
help them assessthe impact of the activitieswhich they would become
responsible for in April 1996 and deal with issuesthat flow from
transfer of responsibility. The scrutiny team clearly saw the provision of
advice and support asa key component of the new executive agency
( PACE) .
The aim of the CAU isto provide central property guidance to
Departments.
Itsobjectivesare:
to assessthe need for and provide user friendly general guidance on
property matters;
to provide early notice and appraisal of key issues, including
forthcoming property legislation and other consultation documents:
and to act asa focal point for feedback from Departments;
to provide quality advice on the acquisition, management and
disposal of property and associated services; and
to facilitate the sharing of best practice through a network of
Departments/agencies.
The Guide isone of a number of guideswhich have been prepared in
furtherance of these objectives.
THE ROLE OF CAU/PACE
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.2.2.1
HOME
GACC
EDITION 2: FEB 1998
Key Points
The C AU ishere to help you.
If you have any queriesor require advice in respect of the Guide or
any mattersnot specifically covered by the Guide, please contact
the C AU at:
Central Advice Unit
Property Advisersto the Civil Estate ( PACE)
5th Floor
Trevelyan House
Great Peter Street
London SW1P 2BY
Tel: 0171 271 2756/2833
Fax: 0171 271 2715
THE ROLE OF CAU/PACE
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.2.2.2
HOME
GACC
EDITION 2: FEB 1998
PS 1.3 PRINCIPLES OF BEST PRACTICE CLIENT
Government policy isthat Departmentswill strive for best practice
procurement performance. It isintended that thisshould be a central
element in Departments businessat all management levels. The aim is
to achieve best value for money, whilst ensuring that the objectivesof
any commission are properly met.
Construction Procurement by Government at paragraph 29 gives
guidance on where Departmentsshould focustheir attention in order
to attain and surpassthe best in the private sector. Departments
should focuson:
quality of supplies, materialsand results;
the value of the finished product to the business;
life-cycle costsnot just initial costs; and,
appointing, retaining and improving the best team to manage and
deliver a project.
Departmentsare a major construction industry client and have a key
role to play in leading the way with improvementsin procurement and
industry performance.
Action point 5 of The Latham Report suggeststhat thismay be done
by:
- openly finding out which designers,contractors or specialist suppliers
are the best;
- tendering with the aimof getting those who offer the best service;
- working with their people as a teamnot opponents;and
- making no compromises with people or suppliers who are unco-
operative or adversarial.
These are all activitieswhich are carried out by leading or best practice
industry clients.
PRINCIPLES OF BEST PRACTICE CLIENT
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.3
HOME
GACC
EDITION 2: FEB 1998
PS 1.4 THE CONDUCT OF STAFF
The activitiesof Departmentsinclude the expenditure of public funds
for which they are accountable. Such Departmentsare therefore
frequently subjected to close scrutiny.
In addition, best practice clientsand in particular Departmentsare and
should be seen to be associating with honest suppliers. Since it is
important that competitorsare able to compete on a level playing field,
it isessential that Departmentsprocure and are seen to procure
suppliesin an ethical and honest way.
The aim should be that organisationsand the people they employ
should be trusted by those with whom they deal, and they should
conduct their businessin a fair and reasonable manner.
Key Points
Self-discipline must be exercised if offersof hospitality, giftsetc., are
received from supplierswith whom staff deal in the course of their
official duties.
Ruleson the acceptance of giftsand hospitality are normally set out
in Departmental hand-books, and it isessential that the procedures
and requirementsset out therein are followed.
Circular letter DAO ( GEN) 17/96 concerning the prevention of
fraud and irregularity wasissued to Departmentsby HM Treasury
on 18 December 1996. It remindsthem of the risksand outlines
some key principlesof control to minimise the possibility of
fraudulent activitiesoccurring.
THE CONDUCT OF STAFF
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
L
! !! !!
PS 1.4
HOME
GACC
EDITION 2: FEB 1998
PS 1.5 DEPARTMENTAL MANAGEMENT ROLES
Commitment by senior management to a project and to the project
sponsor or staff directly responsible for the execution of a commission
isan important factor in the successof a project or commission.
In respect of anyproject or commission, it isbest practice to ensure
that:
the commission manager isempowered with sufficient authority and
knowledge to make quick and effective decisions;
the chain of management command isshort and accessible to
commission managers;
there isonly one commission manager who dealswith the
commission from start to finish to ensure continuity and to avoid
conflicting instructionsto suppliers.
In the context of workscontractswhere a project sponsor is
appointed, the Construction Procurement by Government report
statesthat project successdependsupon the fulfilment of three key
management tasks. These are:
investment decision maker - at the head of the Department capable
of making informed investment decisions;
project owner - a senior manager in the businessline who is
responsible for strategic management of the project;
project sponsor - a single person who hasresponsibility for the day
to day management of the Departmentsinterest in the project.
The report also saysthat the first two or the last two rolesmay be
combined in one person but one person should not be responsible for
all three roles.
The role of the investment decision-maker isto approve the project
and to demonstrate senior management commitment to it. Thisperson
will also give guidance or re-approval in the event of threatsor
proposed changesto the project which might affect the original
approval.
DEPARTMENTAL MANAGEMENT ROLES
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.5.1
HOME
GACC
EDITION 2: FEB 1998
The project owner should report to the investment decision-maker
and should manage all inputsfrom the top and act asa channel for
reportsto and from the project sponsor. The project owner should also
be accessible to and foster good relationswith senior users.
The project ownersresponsibility should be to:
oversee the preparation of the businesscase and budget, ensure
that proposalsrealistically meet businessobjectives, and seek
approval from the investment decision-maker;
ensure that usersare involved with and committed to the project;
appoint, manage and support the project sponsor;
ensure that the brief, when developed, clearly reflects project
objectives;
hold regular progressmeetingswith the project sponsor and
maintain a strategic overview of the development of the project;
act asarbiter for disputeson the Department side;
approve changesto project scope and where necessary seek the
approval of top management; and
ensure that a post completion critique iscarried out and considered
by all project stake-holders.
The project sponsor must be the focal point for the intelligent
customer role and should have clear responsibility for ensuring delivery
of the project in accordance with the project objectives. The scope of
the project sponsorsdutiesismore fully set out in the introduction to
the Guide at Section 1.7. The project sponsor isin effect the clearing
house for all Departmental and construction team inputsand outputs.
DEPARTMENTAL MANAGEMENT ROLES
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
INT 1.7

PS 1.5.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Key Points
Each project should have clearly identified responsibilitiesfor each of
the management tasks, namely investment decision-maker, project
owner and project sponsor.
The project sponsor should be empowered to make effective and
informed decisionsand actively monitor and review the
performance of the membersof the project team.
HM Treasury are in the processof issuing a number of guidance
documentscovering the clients role in the construction
procurement process. They are aimed at anyone who isundertaking
or hasinvolvement with the Government client role in construction;
particularly those exercising the key rolesof investment decision
maker, project owner and project sponsor. The guidance documents
making up the family of construction best practice advice will be
numbered 1 to 9 and are structured to follow the logical sequence
from the broader level aspectsto the more specific. Six documents
have so far been issued:
- No. 1 - Essential Requirementsfor Construction Procurement.
- No. 2 - Value for Money in Construction Procurement.
- No. 3 - Appointment of Consultantsand Contractors
- No. 4 - Teamworking, Partnering and Incentives
- No. 5 - Procurement Strategies
- No. 6 - Financial Aspectsof Projects.
Copiescan be obtained from:
Public Enquiry Unit
Room 89/2
HM Treasury
Parliament Street
London SW1P 3AG
Tel: ( STD) 020 ( GTN) 7270 4558
http: //www.hm-treasury.gov.uk
DEPARTMENTAL MANAGEMENT ROLES
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.5.3
HOME
GACC
EDITION 2: FEB 1998
PS 1.6 EFFECTIVE DECISION-MAKING
In order for Departmentsto ensure best value for money it isessential
that commission managersare able to make quick, informed and
effective decisions. They should also be able to make commercial
decisionswhich in the long-run may substantially reduce the ultimate
commission or project cost and risk. Thisisparticularly so when it
comesto managing and settling disputes.
There isa perception and indeed direct experience by those in the
private sector that some Departmentsare hampered by proceduresor
systemswhich either impair or prevent effective decision-making.
Guidance isoften mistaken asprescriptive and isoften followed to the
letter to the detriment of flexible and creative thinking.
Asexplained in the introduction, the Guide isintended to be an aide
memoire, not a set of procedureswhich must be rigidly adhered to.
Some stepsin the Guide may be unnecessary for certain typesof
commission for example. An element of judgement istherefore
required in their application.
In addition best practice procurement requiresquality judgementsto
be made.
Key Points
Commission managersshould be allowed and encouraged to use
their judgement in both the procurement and management of
commissions.
The application of judgement or informed decision-making requires
knowledge and experience. Where appropriate, commission
managers skillsshould be enhanced through training.
Where they require support for their procurement, management or
commercial decisions, commission managersshould seek advice
from their managers, or C AU, or from professional procurement
advisers.
EFFECTIVE DECISION MAKING
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 1.7

PS 1.6
HOME
GACC
EDITION 2: FEB 1998
PS 1.7 FOCUS ON OUTPUT VALUE
It isimportant for Departmentsto focusnot on the construction
processitself or each commission in itself but upon the benefit of the
completed project or commission to the overall businessobjectivesof
the Department.
Project or commission objectiveswill be set and strategiesformulated
to ensure that the value added to the businessactivitiesof the
Department ismaximised.
Thismeanstaking a broader view and a longer term view of the
importance of the construction procurement process.
Competitive tendering isthe only way of establishing a price range for
the commission to be procured, and generally the only unbiased way to
find the cheapest price.
However, price isonly one of the project criteria by which the success
of a commission ismeasured. It isfar more important that the
commission meetsthe objectivesset by the Department.
A cut-price offer can mean a cut-price service. If a Department pays
too little, then it may be that what isdelivered failsto provide the
Department with what it set out to obtain.
Accordingly Government policy on procurement byDepartmentsis
that a supplier isselected on the basisof an offer which representsthe
best value for money. Thismeansusing a procurement system which
givesweight to quality aswell asprice. Q uality judgementsare
therefore an essential part of good procurement practice.
With major worksprojectsin particular, price must be considered in
the context of the life cycle cost of the project.
The capital cost of a building istypically only say 10-20% of the cost of
owning and operating it over itsexpected life. Professional feesmight
be around 10-15% of the capital cost and therefore represent 1 or 2%
of the life cycle cost. Therefore the relatively minor additional cost of
procuring higher quality services, in particular design serviceswhich
focuson optimising the balance between capital cost and maintenance
costs, will be far outweighed by long-term savings.
FOCUS ON OUTPUT VALUE
PROCUREMENT STRATEGIES
GENERAL PRINCIPLES
PS 2.2

PS 1.7.1
HOME
GACC
EDITION 2: FEB 1998
Whatever the scale and value of the commission it isacceptable to
choose a tenderer who upon evaluation offersthe best value for
money, even though it may not have offered the cheapest price. Thisis
a view confirmed by the National Audit O ffice.
The Guide setsout proceduresfor the assessment and evaluation of
suppliersin termsof the quality they offer aswell asthe price they
quote.
The Guide suggestsuse of an evaluation method which involves
deciding which quality criteria are most important to the Department,
giving each a weighting totalling 100 and then deciding on the relative
importance of quality to price. For example the more complex the
project or commission the greater the importance that islikely to be
attached to quality. A total score isthen calculated for each tenderer
and the tendersranked in order of preference.
An important advantage of thisarithmetical approach isthat it
producesa logical and visible meansof evaluation. However, in itself it
requiresa fair degree of judgement, and it isultimately only an aid to
decision-making.
The final choice will inevitably involve considerable value judgementsby
the Department, but it isessential to think carefully about the service
the Department needsand how it isto be delivered, prior to arriving
at thisvalue judgement.
FOCUS ON OUTPUT VALUE
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 1.7.2
HOME
GACC
EDITION 2: FEB 1998
PS 2 PROJECT REQUIREMENTS
PS 2.1 PROJECT IDENTIFICATION
Before the Department considersthe procurement of professional
servicesor contract worksit must first identify a need, and set down as
clearly aspossible what it isthat hasto be achieved and why.
Maintenance or alteration to existing premisesand in particular
construction of new premisestakestime to procure both in the lead-in
prior to work commencing and in the carrying out of the work itself.
Such work can be highly disruptive to a Department and may result in
the use of substantial Departmental resources. Thisimpliesthe need for
careful future planning and an allowance for such work in
Departmental strategic businessplans.
Government property requirementsmust be driven first and foremost
by the operational needsof Departments.
There may be an immediately identified need which requiresthe
appointment of consultantsand/or workscontractors, but hopefully
needswill be future needswhich have been identified asa result of the
strategic planning process. In the case of future needs, there isan
opportunity to give more consideration to the need and the options
available to meet the need, aswell astaking a planned approach to the
procurement process.
It istherefore beneficial to Departmentsto produce plansfor the
ongoing development and maintenance of their estates.
When a current or future need isidentified then an officer should be
appointed to drive the commission forward. The processwill begin with
a clear definition of the need. The optionsfor satisfying the need will
then be identified and considered.
PROJECT IDENTIFICATION
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.1.1
HOME
GACC
EDITION 2: FEB 1998
The principal needsrequired to satisfy the property management
function, will, for many Departments, relate to the management and
maintenance of their facilities. It will be necessary to decide on:
the nature of the management and maintenance required for the
facility in the context of the Departmentsbusinessobjectives;
the extent of management and maintenance servicesrequired;
how the servicesshould be provided or procured.
Where the Department hasidentified the need for new or altered
property the optionsfor satisfying premisesneedsare typically as
follows:
maintain and extend existing premises;
move to new premises;
construct premiseswhich precisely meet the new or changing needs
of the Department.
The feasibility of these optionsshould be considered in the context of
the benefits, risksand financial constraintsthey represent, and specific
optionsidentified. These optionsare then put in order of benefitsand
feasibility and a decision istaken at the appropriate level on whether in
principal the project isnecessary or feasible.
Key Points
The identification and consideration of optionsisa very important
part of the procurement process. It isparticularly important to
precisely define the nature and scope of the need.
Where commission managersare not confident about carrying out
feasibility studies, they should seek advice from a professional
adviser. The professional adviser may come from any of the
recognised construction professions, but should be able to
demonstrate a strong experience and understanding of different
procurement methodsand project feasibility processes. Accordingly,
project manager, quantity surveying and specialist firmsof
construction contractsconsultantsmay be best suited to thisrole.
Where a project manager isappointed, the work of the adviser
should cease when the project manager isappointed. There is
benefit therefore in retaining an independent professional adviser
who isnot viewed byproject managersand other consultantsasa
competitor, particularly when it comesto them disclosing bid
information.
PROJECT IDENTIFICATION
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.2

PS 2.1.2
HOME
GACC
EDITION 2: FEB 1998
PS 2.2 DEFINING PROJECT OBJECTIVES
Defining a clear set of objectivesfor the project or commission isthe
foundation for setting a clear brief and for deciding on an appropriate
contract strategy. Time spent on getting thisright at the project
inception stage will pay significant dividendswhen the work getsunder
way. When substantial resourcesare committed to the work, the risk of
cost escalation due to delay or late changesby the Department islikely
to be high. Setting clear objectivesand defining realistic expectations
doesmuch to avoid disputesand substantially reducesthe scope for
cost escalationsover and above approved cost estimates.
In the case of a building, a clear statement of the project objectives
should be prepared in termsof:
nature of the buildingsuse;
number of people that are to occupy it together with their space
requirements;
quantification of equipment or machine space requirements;
location of building, ( i.e. geographical etc.) ;
budgets, ( i.e. amount available) ;
programme, ( i.e. when it needsto be in operation) ;
life span, ( i.e. how long isthe economic life) ;
how it fitsinto the corporate plan, ( i.e. it may be part of a larger
planned development) .
Some indication should also be established on:
the relative quality/price needs;
environmental issues;
visual impact; and
planning and any other constraints.
Key Points
The project objectivesshould be carefully defined asearly in the
decision-making processaspossible.
DEFINING PROJECT OBJECTIVES
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4

PS 2.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
PS 2.3 RISK MANAGEMENT
All commissionsfor consultancy and workscontractsinvolve some
degree of risk to one, other or both parties. Some risksare easily
foreseeable at the outset whereasothersmay not be so obvious. Risk
management requiresthe identification of risks, consideration of when
and how they might occur and what action must be taken to minimise
their effect and maximise value for money.
Asan introduction to risk management, it isuseful to think of standard
formsof contract asformal agreementswhich allocate to, or specify the
balance of anticipated risk eventsbetween one or other party to the
contract. A common aspect of standard formsof construction contract
isthat there are provisionsfor extensionsof time to the contractor, and
for liquidated damageswhich may be payable to the Department asa
result of inexcusable delay on the part of the contractor. Standard
formsof contract generally anticipate and allocate responsibility for all
typesof time related risk. Exceptionally adverse weather isfor example
nearly alwaysa shared risk, the employer takesthe risk of delay to
project completion but the contractor takesthe risk of any additional
cost it incursasa result of the delay.
Different standard formsare designed to allocate different risk to
varying degrees. The choice of risk allocation largely dictatesthe
selection of a particular standard form for procuring the construction
works.
Risk management isfar more than risk allocation. It isa processwhich
should begin far earlier in the procurement cycle than at the stage of
choosing the form of contract. It isa processof management which
should continue until the project isfinally complete.
RISK MANAGEMENT
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Risk management involvesthe following elements:
risk identification;
risk assessment and analysis;
risk response ( policieswhich lead to risk reduction and control) .
There are five strategiesfor responding to risk:
- avoidance,
- reduction,
- transfer,
- sharing,
- absorption;
ongoing monitoring and control of risksthroughout the life of the
project.
Risk identification generally requiresan understanding of all of the
project or commission requirementsat all stagesfrom inception to
completion. It involvesreviewing the potential sourcesof risk and
identifying and listing those riskswhich are likely to affect the project or
commission in question.
In the whole life context of a worksproject there are four generic
typesof risk:
departmentsspecial risks, including external riskssuch asthose that
arise from the economic, legal or political environments;
design risks;
construction risks;
operational risks.
RISK MANAGEMENT
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.3.2
HOME
GACC
EDITION 2: FEB 1998
The principal causesof contractual prolongations, overspend, and
disputesin respect of workscommissionsare asfollows:
Pre-Contract
incomplete pre-contract design;
poor tender documentation;
complex building works/novel design/lack of buildability;
inadequate pre-qualification process- inexperienced/unsuitable
consultantsand contractors;
lay clients;
opting for the cheap alternative;
restricted/occupied site;
too many parties- designers/projectsmanagers;
inadequate co-ordination of design/production information/tender
documentation;
contractor/Department, and contractor/professional latent conflict;
inadequate programme;
non-standard contracts;
amendmentsto standard contracts;
legal/contractual inconsistencies generally;
RISK MANAGEMENT
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.3.3
HOME
GACC
EDITION 2: FEB 1998
On Site
excessive changes, lotsof variations;
poor documentation - inconsistenciesand errors;
evolving design, late information;
inadequate design, supervision and co-ordination of construction
and services;
poor management by professional team;
tender price too low;
claimsconsciouscontractor;
weak contract administrator/Project Manager;
junior quantity surveying staff;
force majeure/adverse weather conditions;
fire/other insured risks;
bad workmanship;
late delivery of materials;
contractorsfailure to manage/supervise sub-contractors;
payment disputes:
- contractor/Department
- contractor/sub-contractor;
inadequate resourceson site;
untidy site/disorganisation.
Many of these problem areasapply to any type of commission whether
worksor services. An awarenessof these problemsor sourcesof risk is
essential in order to give focusto specific aspectsof the procurement
process. How these factorsare to be dealt with will heavily influence
the choice of contract strategy.
RISK MANAGEMENT
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.3.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
Asdescribed earlier, risk response strategieslead to the choice of a
particular procurement strategy, but should also be part of the ongoing
management of the project. It isimportant to strike a balance between
the threat of risk and the chance of an outcome which will result in
better value for money.
Risk management isfor most procurersof servicesa subconscious
process. However, it ishere suggested that it ismade a formal and
inherent part of the procurement process. Thiswill be particularly
essential if private finance isto be considered for the procurement of a
project in line with the Private Finance Initiative. A key feature of PFI
projects, isthe identification and genuine transfer of risksto the private
sector.
Key Points
Risk management should be a consciousprocessaspart of the
management ethosof any commission or project from inception to
completion.
Risk management isan inherent part of considering the
procurement of projectsto be funded by PFI.
Further reading on risk management can be found in Procurement
Group Guidance No. 2, available from:
Public Enquiry Unit
Room 89/2
HM Treasury
Parliament Street
London SW1P 3AG
Tel: 020 7270 4558
http://www.hm-treasury.gov.uk
RISK MANAGEMENT
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 5.2

PS 2.3.5
HOME
GACC
EDITION 2: FEB 1998
PS 2.4 CONTRACT STRATEGY
PS 2.4.1 General
The choice of contract strategy isone of the most important decisions
to be made by the commission manager or project sponsor, and will be
the outcome of a seriesof decisionsmade in the early stagesof the
commission or project.
Contract strategy isabout choosing the right contract for allocating
commission or project risksto the party who isbest able to deal with
them, in a way which isconsistent with the Departmentsobjectivesfor
the commission or project. The contract strategy will therefore depend
on the objectivesof the commission or project and how the
Department wishesto manage risks.
With anycommission or project, the Department should be seeking to
secure the right quality of work at the right time and at a cost which
representsbest value for money. The three main typesof objectives
which must be set for the procurement of anycommission are
therefore:
Quality
Cost Time
Q uality here representsthe standard to which the work isdone and
the extent to which it meetsthose objectivesother than cost or time.
It should be recognised that:
a change in one of these main objectivesisvery likely to have an
effect on one or both of the other objectives( for example, a
reduction in cost and/or time islikely to adversely affect quality) ;
if tight targetsare set for all objectivesthen the likelihood of
meeting them all issmall;
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.1.1
HOME
GACC
EDITION 2: FEB 1998
since an improvement in one objective islikely to be at the expense
of othersit isimportant for the Department to focuson which are
the most important and to establish the right balance between
them by choosing an appropriate contract strategy.
The contract strategy should also reflect the technical ability of the
commission manager or project sponsor and the extent to which the
Department wishesto be involved with or have direct control over the
commission or project.
The principal stepsrequired to decide on the contract strategy are:
Identify need for commission or project
Appoint Commission Manager or Project Sponsor
Appoint professional advisor where necessary
Define objectivesand prioritise them
If project management, feasibility design or cost
advice isneeded then make temporary
Re-evaluate and prioritise objectives
Decide an appropriate contract strategy in
light of objectives
In the case of a worksproject, the last step above would involve the
appointment of a project manager who would develop the detailed
contract strategy, by evaluating the optionsfor the contract strategy
and the alternative typesof contract available, resulting in the
recommendation of a particular form of contract.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.1.2
HOME
GACC
EDITION 2: FEB 1998
The formulation of a detailed contract strategy will involve the
consideration of the following issues:
factorsoutside the control of the project team ( e.g. inflation,
legislation, etc.) ;
sponsor resources( or Departmental resources) ;
project characteristics;
ability to make changes;
risk management;
funding;
cost issues;
timing;
quality and performance.
The commission manager or project sponsor will want to review their
control of the above factorsdepending upon their relative importance.
Key Points
The choice of contract strategy isone of the most important
decisionsfacing the commission manager or project sponsor.
It may be advisable to seek advice from a professional procurement
advisor or project manager on the choice of strategy.
In the case of worksprojectsthe chosen strategy will dictate which
consultantsare required to be procured and how, aswell ashow
the workscontractorsare to be procured.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.1.3
HOME
GACC
EDITION 2: FEB 1998
PS 2.4.2 Property Management Functions
There are a number of functionswhich have to be fulfilled in order for
the Department to manage and utilise itsfacility or facilities. These are
principally asfollows:
Gener Gener Gener Gener Generall all all all ally yy yy
Management Function;
Estate Servicesincluding:
- lease renewals,
- rent reviews,
- valuations,
- optionsappraisal,
- acquisition of existing properties,
- disposal of properties;
Maintenance Services, including:
- mechanical and electrical plant and building services,
- lift maintenance,
- ground maintenance,
- general building maintenance, doors, windows, redecoration, etc.
- fire alarms,
- security system,
- computer maintenance;
Domestic Services, including:
- security,
- general office cleaning,
- window cleaning,
- catering,
- office furniture relocation services;
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.2.1
HOME
GACC
EDITION 2: FEB 1998
BusinessSupport Services, including:
- typing,
- finance,
- admin support,
- messenger service,
- copying and graphicsservices;
Statutory Compliance Services, including:
- fire consultancy,
- health and safety consultancy,
- legal advice;
Minor Minor Minor Minor Minor W WW WWor or or or orks ks ks ks ks
Major alter Major alter Major alter Major alter Major alterations and new ations and new ations and new ations and new ations and new projects projects projects projects projects
Project Management;
Design Servicesincluding:
- architect,
- structural engineer,
- M & E engineer,
- other specialists, such aslighting and interior designers,
- landscape designers,
- specialist contractor design input;
Cost Consultancy Services;
Estate Services;
Legal/Procurement Advice;
WorksContractors;
Specialist WorksContractors.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.2.2
HOME
GACC
EDITION 2: FEB 1998
There are a wide variety of alternative meansavailable to the
Department to provide or procure these functions. There are also
therefore a number of alternative typesof organisation structure which
represent these alternatives.
When there isan identified need for worksor servicesthen the
Department must decide how best to secure them to the maximum
cost benefit of the Department. The Department must decide whether
the servicesrequired to satisfy the property management function
should be:
provided in-house;
obtained externally and managed in-house; or
obtained and managed externally under the supervision of a
commission manager.
The choice will be influenced by:
the extent and typesof servicesto be provided;
what representsthe best value for money to the Department;
the size of the Department, and whether scale economiescan be
achieved through central purchasing;
the level of in-house service available to the Department;
the qualificationsand experience of the Departmentsproperty
management staff.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.1

PS 2.4.2.3
HOME
GACC
EDITION 2: FEB 1998
The most common model to describe the way in which Departments
organise their property management functionsisasfollows:
Fig 2.4.2.1 O rganisation of the Property Management Function
It isdifficult to try to anticipate all of the possibilitieswhich might be
appropriate for all Departments. The attached grid of servicesand
contract strategieshastherefore been included in order to try to
illustrate some of the different possibilities.
Departmentswith small and/or scattered estate should explore the
possibilitiesof using other Departmentsexisting property and legal
contracts.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
Departmental Headguarters
Property Management Division
Property Management
Commissions (PMCs)
for each area
Scope of PMC coversall
property management,
including EstatesServices,
Maintenance Services,
Statutory Compliance
Servicesand Works
Departmental Property
Manager
for each area
Business Support
Services
( usually in-house)
Domestic Services
( usually direct
service)
PS 2.4.2.4
HOME
GACC
EDITION 2 REV 1: JAN 1999
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
CO N T RA CO N T RA CO N T RA CO N T RA CO N T RACT ST RA CT ST RA CT ST RA CT ST RA CT ST RAT EG IES FO R PR T EG IES FO R PR T EG IES FO R PR T EG IES FO R PR T EG IES FO R PRO CUREM EN T O F PR O CUREM EN T O F PR O CUREM EN T O F PR O CUREM EN T O F PR O CUREM EN T O F PRO PER O PER O PER O PER O PERT Y T Y T Y T Y T Y
M A N A M A N A M A N A M A N A M A N AG EM EN T G EM EN T G EM EN T G EM EN T G EM EN T A N D A N D A N D A N D A N D W WW WWO RKS FUN CT IO N S O RKS FUN CT IO N S O RKS FUN CT IO N S O RKS FUN CT IO N S O RKS FUN CT IO N S
CO N T RA CO N T RA CO N T RA CO N T RA CO N T RACT ST RA CT ST RA CT ST RA CT ST RA CT ST RAT EG IES T EG IES T EG IES T EG IES T EG IES
PR PR PR PR PRO PER O PER O PER O PER O PERT Y M A N A T Y M A N A T Y M A N A T Y M A N A T Y M A N AG EM EN T FUN CT IO N S G EM EN T FUN CT IO N S G EM EN T FUN CT IO N S G EM EN T FUN CT IO N S G EM EN T FUN CT IO N S
G EN ERA LL G EN ERA LL G EN ERA LL G EN ERA LL G EN ERA LLY YY YY
Management Function
Estate Services
lease renewals
rent reviews
valuations
optionsappraisals
acquisition of existing properties
disposal of properties
Maintenance Services
mechanical and electrical plant and building services
lift maintenance
ground maintenance
general building maintenance, doors, windows,
redecoration, etc.
computer maintenance
fire alarms
securitysystem
Domestic Services, including:
security
general office cleaning
window cleaning
catering
office furniture relocation services
BusinessSupport Services
typing
finance
admin support
messenger service
copying and graphicsservices
Statutory Compliance Services
fire consultancy
health and safety consultancy
legal advice
M IN O R M IN O R M IN O R M IN O R M IN O R W WW WWO RKS O RKS O RKS O RKS O RKS
P
r
o
v
i
d
e
d

I
n
-
H
o
u
s
e
P
r
o
p
e
r
t
y

M
a
n
a
g
e
m
e
n
t
C
o
m
m
i
s
s
i
o
n
F
a
c
i
l
i
t
i
e
s

M
a
n
a
g
e
m
e
n
t
T
e
r
m

C
o
m
m
i
s
s
i
o
n
T
e
r
m

C
o
m
m
i
s
s
i
o
n

E
s
t
a
t
e
s
E
s
t
a
t
e
s

C
o
m
m
i
s
s
i
o
n
(
o
n
e
-
o
f
f

f
u
n
c
t
i
o
n
s
)
T
e
r
m

S
e
r
v
i
c
e

C
o
n
t
r
a
c
t
s
M
e
a
s
u
r
e
d

T
e
r
m

C
o
n
t
r
a
c
t
s
S
p
e
c
i
a
l
i
s
t

T
e
r
m

C
o
n
t
r
a
c
t
s
(
p
l
a
n
n
e
d

m
a
i
n
t
e
n
a
n
c
e
)
PS 2.4.2.5
HOME
GACC
EDITION 2 REV 1: JAN 1999
In line with the organisational structure illustrated in Figure 2.4.2.1, the
most common approach to procuring the property management
functionsis:
the Department retainsstrategic management control;
the Department generally providesbusinesssupport servicesin-
house;
the Departmentscentral office procuresregional or national
Property Management Commissions( PMCs) ;
the Department directly employsdomestic service supplierssuch as
security, office cleaning, window cleaning, etc.
The typesof consultant commission which will generally be required to
satisfy the property management function are described in more detail
in the Consultants chapter of the Guide.
The varioustypesof Government workscontractsare described in
more detail in the Contractors chapter of the Guide.
Key Points
In considering the way to procure property management functions
and businesssupport services, it isimportant for the Department to
consider in detail what it wantsand why and whether there isscope
for improvement in existing systems.
It may be appropriate to consider the appointment of a facilities
management company.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
CST 1.6

CST 1

CRS 1

PS 2.4.3

PS 2.4.2.6
HOME
GACC
EDITION 2: FEB 1998
PS 2.4.3 Facilities Management Strategies
Facilitiesmanagement ( FM) isan extension of the property
management role, to the extent that itsscope often coversall non-
core businessactivitiesassociated with the facility and with supporting
the businessunit occupying the facility. FM isthe continuousprocessof
tuning all such activitiesor servicesto satisfy businessneeds. Treasury
( CUP) identify FM asstrategic servicesin their literature.
All Departmentsare involved to a greater or lesser degree in FM and a
consultant who undertakesa Property Management Commission on
behalf of a Department isundertaking facilitiesmanagement services
on itsbehalf.
The reason for including thissection however isbecause of the
development in recent yearsof a separate professional FM discipline.
There are now numerousorganisationswho offer FM serviceson the
basisfor example that they will:
review businessobjectives;
take control of and manage the facility and all non-core functions;
rationalise non-core functions;
save the Department money whilst maintaining the level of service
required to satisfy businessobjectives;
maximise value for money.
Three examplesof organisational structuresfor the appointment of an
FM company are asfollows:
Fig 2.4.3.1 Department Agent
With the client agent arrangement the facilitiesmanager issimply a
manager. The Department contractsdirectly with service providersand
retainsthe cost risk.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
Department
FacilitiesManager
Cleaning Building
Management
Security Etc
..................................................................................................................
....................................................................
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
PS 2.4.3.1
HOME
GACC
EDITION 2: FEB 1998
Fig 2.4.3.2 FacilitiesManagement Contracting
The management contracting arrangement isa hybrid between the
client agent arrangement and total FM. The FM company isappointed
for a fee and then the packagesare let separately but in contract with
the FM company. Warrantiesare commonly executed between package
suppliersand the Department where appropriate.
Fig 2.4.3.3 Total FM
With total FM the Department paysa lump sum to the FM company
who takesdirect responsibility for all servicesand therefore all of the
risk. It isclearly essential with thisarrangement for the Department to
very clearly specify minimum levelsof service requirements.
Before considering the appointment of an FM company the
Department should look carefully at itsbusinessobjectivesand how
they are currently being met.
There isa very helpful guide called Thinking About Facilities
Management which setsout stepsfor successful FM, planning for
effective FM and choosing the appropriate path. Thisisavailable from
The BusinessRound Table Ltd, 18 Devonshire Street, London, W1N
1FS ( 0171 636 6951) .
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
Department
Cleaning Building
Management
Security Etc
FacilitiesManager
Department
FM:
- Cleaning
- Building
- Security
- Etc
PS 2.4.3.2
HOME
GACC
EDITION 2: FEB 1998
Thinking About FacilitiesManagement setsout a number of areas
where Departmentsshould take care, including:
Departmentsshould not lose control of servicesby outsourcing,
and should retain the strategic management function in-house;
Departmentsshould not expect servicesto run themselves, service
quality dependson good management;
Departmentsshould not invite bidsfrom the commercial sector
without first rationalising their FM requirements; the Departments
businessoperationsneed to be aslean aspossible to reduce the
cost of outsourcing.
Key Points
Facilitiesmanagement isaimed at optimising the value of the
facilitiesand organisational support servicesin such a way asto
maximise value for money whilst meeting the strategic business
needsof the Department.
Read Thinking About FacilitiesManagement.
Included in volume 2 of the Guide isan example FM contract that
hasbeen developed by the Scottish O ffice.
HM Treasury hasissued detailed guidance on the documentation
needed in the procurement processfrom appraising suppliers
through to award of contract. It isin four parts:
- Guidance Note No. 59A : Model Appraisal Q uestionnaire;
- Guidance Note No. 59B : Pre-Q ualification;
- Guidance Note No. 59C : Model Invitation to Tender; and
- Guidance Note No. 59D : Model Conditionsof Contract.
A copy/copiescan be obtained from HM Treasury, Allington Towers,
19 Allington Street, London SW1E 5EB ( tel: 0171 270 4558) .
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.3.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
PS 2.4.4 Works Contract Strategies
Workscontractsare required for the procurement of construction
work, whether alteration, refurbishment or new construction work.
Workscontractsare generally divided into:
minor workscontracts; and
major workscontracts.
The distinction isusually a cost threshold which islikely to be individual
to each Department. Minor workscontractshave the following
characteristics:
a typical threshold for minor workscontractsiscontractslessthan
50,000;
they require lessconsultant input;
they can be carried out by smaller contractorsgenerally with a
smaller variety of specialist input;
they require simpler formsof contract which are easier to
administer.
The varioustypesof workscontract are more fully described in the
ContractorsSection.
The form of contract chosen dictatesthe scheme of risk allocation as
well aswhich consultantsneed to be procured and when. There will
generally be more than one way to procure the works.
The variousalternativeswill be more or lesssuccessful in achieving
project objectives. For major worksprojectsa project sponsor will be
appointed and the choice of procurement strategy will be decided in
conjunction with an appointed project manager or procurement
adviser.
CRS 1

CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.4.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
The suggested procedure for selecting a contracting strategy isbriefly
summarised asfollows:
appoint a project manager to develop a fuller contract strategy in
parallel with the outline design;
the project manager formally reportsto the project sponsor setting
out the recommended strategy;
identify and analyse the riskswith the optionsconsidered;
the project sponsor considersthe report and challengesthe
recommendation and ultimately agreeson a suitable strategy.
In 1995 the BusinessRound Table re-launched the Thinking About
Building procurement guide. Thinking About Building providesa
checklist for identifying the variousprocurement optionsavailable and a
systematic procedure for deciding on a particular procurement path.
The procurement checklist isintended asan aid to decision-making and
isreproduced overleaf with permission from the BusinessRound Table.
The table listson the left-hand side the principal objectivesaffecting
contract choice. Each type of contract can be scored in one of three
alternative ways:
the total number of bulletswhich coincide with the objectives;
each objective isnumerically weighted and the weighting is
substituted for a bullet where it coincideswith the objective;
each contract isgiven a relative score in place of the bullet point,
and each objective isweighted and the two are multiplied together
to give a weighted average score.
Key Points
Read CUP Guidance Note 12 - Contractsand Contract
Management for Construction Works.
Read Procurement Guidance Note No. 6, available from HM
Treasury.
Read Thinking About Building.
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.4.4.2
HOME
GACC
EDITION 2: FEB 1998
CONTRACT STRATEGY
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
S e q u e n t i a l
A c c e l e r a t e d
D i r e c t
D e v e l o p a n d
C o n s t r u c t
M a n a g e m e n t
C o n t r a c t i n g
C o n s t r u c t i o n
M a n a g e m e n t
C o m p e t i t i v e
C o n t r a c t o r
P r o j e c t
M a n a g e r
C o n s u l t a n t
P r o j e c t
M a n a g e r
I
D
E
N
T
I
F
Y
I
N
G

I
D
E
N
T
I
F
Y
I
N
G

I
D
E
N
T
I
F
Y
I
N
G

I
D
E
N
T
I
F
Y
I
N
G

I
D
E
N
T
I
F
Y
I
N
G

YY YYY
O
U
R

P
R
I
O
R
I
T
I
E
S
O
U
R

P
R
I
O
R
I
T
I
E
S
O
U
R

P
R
I
O
R
I
T
I
E
S
O
U
R

P
R
I
O
R
I
T
I
E
S
O
U
R

P
R
I
O
R
I
T
I
E
S
L
u
m
p

S
u
m
D
e
s
i
g
n

a
n
d

B
u
i
l
d
F
e
e

C
o
n
s
t
r
u
c
t
i
o
n
D
e
s
i
g
n

a
n
d

M
a
n
a
g
e
A
T
i
m
i
n
g
H
o
w

i
m
p
o
r
t
a
n
t

i
s

e
a
r
l
y
C
r
u
c
i
a
l
1

c
o
m
p
l
e
t
i
o
n

t
o

t
h
e

s
u
c
c
e
s
s
I
m
p
o
r
t
a
n
t
2

o
f

y
o
u
r

p
r
o
j
e
c
t
?
N
o
t

a
s

i
m
p
o
r
t
a
n
t

a
s

o
t
h
e
r

f
a
c
t
o
r
s
3

B
C
o
n
t
r
o
l
l
a
b
l
e
D
o

y
o
u

f
o
r
e
s
e
e

t
h
e

n
e
e
d
Y
e
s
4

V
a
r
i
a
t
i
o
n
t
o

a
l
t
e
r

t
h
e

p
r
o
j
e
c
t

i
n

a
n
y
D
e
f
i
n
i
t
e
l
y

n
o
t
5

w
a
y

o
n
c
e

i
t

h
a
s

b
e
g
u
n

o
n
s
i
t
e
,
f
o
r

e
x
a
m
p
l
e

t
o
u
p
d
a
t
e

m
a
c
h
i
n
e
r
y

l
a
y
o
u
t
s
?
C
C
o
m
p
l
e
x
i
t
y
D
o
e
s

y
o
u
r

b
u
i
l
d
i
n
g

(
a
s
Y
e
s
6

d
i
s
t
i
n
c
t

f
r
o
m

w
h
a
t

g
o
e
s

i
n
M
o
d
e
r
a
t
e
l
y

s
o
7

i
t
)

n
e
e
d

t
o

b
e

t
e
c
h
n
i
c
a
l
l
y
N
o
,
j
u
s
t

s
i
m
p
l
e
8

a
d
v
a
n
c
e
d

o
r

h
i
g
h
l
y
s
e
r
v
i
c
e
d
?
D
Q
u
a
l
i
t
y

L
e
v
e
l
W
h
a
t

l
e
v
e
l

o
f

q
u
a
l
i
t
y

d
o
B
a
s
i
c

c
o
m
p
e
t
e
n
c
e
9

y
o
u

s
e
e
k

i
n

t
h
e

d
e
s
i
g
n
G
o
o
d

b
u
t

n
o
t

s
p
e
c
i
a
l
1
0

a
n
d

w
o
r
k
m
a
n
s
h
i
p
?
P
r
e
s
t
i
g
e
1
1

E
P
r
i
c
e
D
o

y
o
u

n
e
e
d

t
o

h
a
v
e

a
Y
e
s
1
2

C
e
r
t
a
i
n
t
y
f
i
r
m

p
r
i
c
e

f
o
r

t
h
e

p
r
o
j
e
c
t
A

t
a
r
g
e
t

p
l
u
s

o
r

m
i
n
u
s

w
i
l
l

d
o
1
3

c
o
n
s
t
r
u
c
t
i
o
n

b
e
f
o
r
e

y
o
u
c
a
n

c
o
m
m
i
t

i
t

t
o

p
r
o
c
e
e
d
?
F
C
o
m
p
e
t
i
t
i
o
n
D
o

y
o
u

n
e
e
d

t
o

c
h
o
o
s
e
C
e
r
t
a
i
n
l
y

f
o
r

a
l
l

w
o
r
k
s

c
o
n
t
r
a
c
t
o
r
s
1
4

y
o
u
r

c
o
n
s
t
r
u
c
t
i
o
n

t
e
a
m
W
o
r
k
s

a
n
d

c
o
n
s
t
r
u
c
t
i
o
n

m
a
n
a
g
e
m
e
n
t

t
e
a
m
1
5

b
y

p
r
i
c
e

c
o
m
p
e
t
i
t
i
o
n
?
N
o
,
o
t
h
e
r

f
a
c
t
o
r
s

a
r
e

m
o
r
e

i
m
p
o
r
t
a
n
t
1
6

G
M
a
n
a
g
e
m
e
n
t
C
a
n

y
o
u

m
a
n
a
g
e

s
e
p
a
r
a
t
e
C
a
n

m
a
n
a
g
e

s
e
p
a
r
a
t
e

f
i
r
m
s
1
7

c
o
n
s
u
l
t
a
n
c
i
e
s

a
n
d
M
u
s
t

h
a
v
e

o
n
l
y

o
n
e

f
i
r
m

f
o
r

e
v
e
r
y
t
h
i
n
g
1
8

c
o
n
t
r
a
c
t
o
r
s
,
o
r

d
o

y
o
u
w
a
n
t

j
u
s
t

o
n
e

f
i
r
m

t
o

b
e
r
e
s
p
o
n
s
i
b
l
e

a
f
t
e
r

t
h
e
b
r
i
e
f
i
n
g

s
t
a
g
e
?
H
A
c
c
o
u
n
t
a
b
i
l
i
t
y
D
o

y
o
u

w
a
n
t

d
i
r
e
c
t
N
o
t

i
m
p
o
r
t
a
n
t
1
9

p
r
o
f
e
s
s
i
o
n
a
l

a
c
c
o
u
n
t
a
b
i
l
i
t
y
Y
e
s
2
0

t
o

y
o
u

f
r
o
m

t
h
e

d
e
s
i
g
n
e
r
s
a
n
d

c
o
s
t

c
o
n
s
u
l
t
a
n
t
s
?
I
R
i
s
k
D
o

y
o
u

w
a
n
t

t
o

p
a
y
N
o
,
p
r
e
f
e
r

t
o

r
e
t
a
i
n

c
o
n
t
r
o
l

a
n
d

t
h
e
r
e
f
o
r
e

r
i
s
k
2
1

A
v
o
i
d
a
n
c
e
s
o
m
e
o
n
e

t
o

t
a
k
e

t
h
e

r
i
s
k
P
r
e
p
a
r
e
d

t
o

s
h
a
r
e

a
g
r
e
e
d

r
i
s
k
s
2
2

o
f

c
o
s
t

a
n
d

t
i
m
e

s
p
i
l
l
a
g
e
Y
e
s
2
3

f
r
o
m

y
o
u
?
TT TTT
OO OOO
TT TTT
A
L
S
A
L
S
A
L
S
A
L
S
A
L
S
PS 2.4.4.3
HOME
GACC
EDITION 2: FEB 1998
PS 2.5 DEFINING THE PROJECT BRIEF
The project brief isa formal statement of the objectivesand functional
and operational requirementsof the finished project.
Thisisa very important document. It should be in sufficient detail to
enable the construction team to execute the detailed design and
specification of the work, and it istherefore an essential reference for
the construction team.
It isthrough the brief that the Department must effectively
communicate itsneedswhether for a major worksproject or for a
term maintenance contract or a consultancy commission of some
description.
A project brief might typically contain the following:
project aim and objectives;
the functional/operational requirementsof the completed project;
the project budget:
- capital costs,
- operating and maintenance costs;
the project programme and, in particular, whether the project isto
be carried out asa whole or divided into distinct parts;
the standardsrequired:
- overall quality standards,
- construction standards,
- standardsspecific to end-use;
environmental factors;
statutory controls;
special requirements.
DEFINING THE PROJECT BRIEF
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.5.1
HOME
GACC
EDITION 2: FEB 1998
The Department must go to great painswithin itsown organisation to
ensure that it clearly defineswhat it and any other affected parties
require in order to deliver work which satisfiesthe overall business
objectivesof the Department. In the case of a major worksproject, this
may require an extensive consultative process.
The development of the brief isan interactive processand the brief
should become progressively more defined asthe Departmentsneeds
become clearer and conflictsare resolved.
The project manager and designerswill usually assist the Department
in the formulation of the brief to ensure that itsscope issufficient for
design development.
Typically the brief will develop through three stagesbefore detailed
design commences:
preparing the businesscase;
concept design;
scheme design.
When the scheme design hasbeen developed ( ideally in close co-
operation with the Department) then it should be reviewed and signed
off by the Department. Thishelpsto confirm the commitment of all
partiesto the brief, and to reduce changes.
During concept design many of the key strategic decisionsare taken
which affect buildability, long-term maintenance and value for money.
Commonly alternative design solutionswill be tested.
The project manager will generally select appropriate designers.
Depending on the contract strategy, designersmay need to be
appointed to carry out the concept design before the rest of the
construction team isappointed.
DEFINING THE PROJECT BRIEF
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.5.2
HOME
GACC
EDITION 2: FEB 1998
Key Points
The brief iscentral to defining the Departmentsneedsand should
be comprehensive and clearly articulated.
The project brief should be signed off at the completion of scheme
design.
It isimportant to ensure that the designer hassufficient resourcesto
ensure design development to programme. Ideally resource levels
should be defined at the outset.
It isstrongly recommended that general and specialist contractors
are involved in design development of worksprojectswhere
appropriate.
DEFINING THE PROJECT BRIEF
PROCUREMENT STRATEGIES
PROJECT REQUIREMENTS
PS 2.5.3
HOME
GACC
EDITION 2: FEB 1998
PS 3.0 PROCURING AND MANAGING THE TEAM
PS 3.1 THE NEED FOR A PROJECT MANAGER
A common approach to project appraisal, and evaluation isfor the
Department to obtain a professional procurement adviser, who will
advise on appraisal, assist in formulating the contract strategy and be
responsible for assisting in procuring a project manager. Thereafter, the
advisor will be disengaged.
When the course of the project isknown, and project managershave
been appointed, they will then take up management responsibilitiesand
co-ordinate and organise the procurement of the required consultants.
They will then push the project through design and construction to
completion.
The appointment of a project manager should not, however, be an
automatic decision. For example, it isunlikely that a project manager
will be required for maintenance work. It islikely that the management
role may be carried out by private sector estate manager under a
Property Management Commission.
It may also be the case that the Department and itsproject sponsors
feel sufficiently confident to appoint and manage the design team
directly. If thisisso then a design team leader should be appointed to
ensure overall design co-ordination. Thisalso hasthe advantage that in-
house project managerswill clearly have authority to make decisions.
In any event it isgenerally inappropriate for a Department to rely solely
on a project manager. The impetusand drive for suppliersto hit
deadlinesisat itsmost effective when it comesdirectly from the
Project Sponsor.
A further point isthat the chosen contract strategy may be design and
build - where a large amount of risk istransferred to the contractor,
which might arguably negate the need for a project manager.
THE NEED FOR A PROJECT MANAGER
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
CST 1.4

PS 3.1
HOME
GACC
EDITION 2: FEB 1998
PS 3.2 DEFINING THE PROJECT TEAM
The size of the team will of course depend on the nature of the work
being undertaken. In respect of property management and
maintenance work for example it may be that just two estate
management consultant practiceswill be appointed each to manage
different partsof the estate.
In respect of workscontracts, the number and disciplinesof the
consultantson the team will depend on the nature and scope of the
work and also on the chosen contract strategy. O nce a project is
underway there will commonly be a project manager appointed to
move the project forward and ensure it meetsthe Departmental
project objectives. Under a traditional lump sum form of contract such
asGC/Works/1( 1998) the Department might typically expect to
employ the following professionals:
Architect Principal Designer
Structural Engineer Structural Design
Mechanical and Electrical M&E Design
Engineer
Q uantity Surveyor Cost control
Planning Supervisor Required byCDM regulations
to prepare health & safety plan
and possibly also:
Communicationsor computer
specialist
PartyWall Surveyor Party wall agreements
Interior Designer
Landscape Designer For external worksdesign
Under the management contracting route, the contractor joinsthe
team earlier in the processto advise on buildability. In construction
management the Department contractsdirectly with each specialist
workscontractor, and the construction manager isalso on the team at
an earlier stage. Conversely with the design and build strategy, the
Department may engage professionalsto develop outline designsbut
the contractor when engaged then takeson full design responsibility as
well asresponsibility for construction. The Departmentsdesignersmay
at that stage be disengaged or novated to the contractor.
DEFINING THE PROJECT TEAM
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 3.2.1
HOME
GACC
EDITION 2: FEB 1998
Key Points
However the team isstructured, the best practice clientstake time
to assessthe qualitiesof each potential team member and put time
into getting the right team.
It ishighly advisable to insist on meeting the individualswho a
tenderer actually proposesusing for the specific commission.
DEFINING THE PROJECT TEAM
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 3.2.2
HOME
GACC
EDITION 2: FEB 1998
PS 3.3 APPOINTMENT THROUGH COMPETITION
It isgenerally accepted that best value for money isachieved through
competition, provided that quality and price are considered together in
the final choice of supplier.
Competition providesa systematic approach to selecting the most
suitable consultant or contractor, but it must be done in an impartial,
fair and reasonable way, and must provide a level playing field for
competitors.
It may be appropriate to appoint a supplier without competition if
there isonly one supplier who hasthe required expertise.
The majority of the Guide isdevoted to providing recommended
proceduresfor the procurement of professional and contract works
servicesin such a way asto ensure asfar aspossible best value for
money through competition.
APPOINTMENT THROUGH COMPETITION
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 3.3
HOME
GACC
EDITION 2: FEB 1998
PS 3.4 FOSTERING TEAMWORK
The complexity and fragmentation inherent in the construction process
make it essential to foster a culture of teamworking asearly aspossible.
Thisisbest achieved through the enthusiasm and direction of the
project sponsor or commission manager.
Teamworking isfacilitated by preparing briefsto professionalswhich are
clear and unambiguous, and avoid gapsand overlapsbetween
professionals. It isalso facilitated by regular team building meetingsat
which those present are encouraged to take a stake in the successof
the project aswell asto see their positive contribution to satisfy the
Departmentsneeds.
Teamwork may also be encouraged from within the team by giving one
or all of itsmembersperformance incentivesto which they should
work.
Key Points
Teamworking requiresleadership. Thisshould come from the
project manager where one isappointed, but the project sponsor or
commission manager also hasan important part to play.
Partnering isa relatively new approach in the construction industry
to develop non-adversarial relationshipsbetween Departmentsand
contractors.
FOSTERING TEAMWORK
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 5.1

PS 3.4
HOME
GACC
EDITION 2: FEB 1998
PS 3.5 PERFORMANCE INCENTIVES
There are two principal formsof incentive:
Tine ReIated - where the contractor isgiven incentivesto
complete the whole of the worksearlier than it iscontractually
bound to do or to complete certain critical elementsof the works
early. For certain typesof commission it may be appropriate to
provide consultantswith incentivesfor early performance.
Cost ReIated - where the contractor or consultant isencouraged
to make savingsto project cost whilst ensuring that other project
objectivesare still met.
Time Related Incentives
An effective meansof encouraging good performance from
professionalsand contractorsisto change conventional payment
mechanismssuch that performance milestonesare identified. Payment
isthen made on the basisof an agreed payment schedule which defines
sumsto be paid when milestonesare reached. The contractor is
therefore encouraged to use good management and innovative
solutionsto ensure good cashflow. Thisapproach should not result in
any extra cost to the Department.
Where early completion of the whole or part of the work isdesirable,
and the Department standsto save money by having early completion
then it may be appropriate to consider cash bonusesto the contractor
or consultant for early completion. The Department or itsadvisersmay
take the view that in any event it isworth offering such bonuses. It is
possible to pay bonusesfor early completion of stagese.g. on early
completion of roof, but thismay achieve little if the worksare
subsequently not completed on time. It isgenerally better to allow
bonusesfor the completion of the whole or part of the works. Thiscan
work in a number of ways, examplesof which are asfollows:
the contractor ispaid 0.1% of the value of any section of the works
handed over before the completion date or an applicable sectional
completion date up to a maximum of say 5% of the whole contract
value;
the contractor ispaid a fixed sum per day for each day that the
worksare complete before the completion date. See option Q -
Bonusfor Early Completion in the Engineering and Construction
Contract ( 2nd Edition) . ( Formerly the New Engineering Contract.)
PERFORMANCE INCENTIVES
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 3.5.1
HOME
GACC
EDITION 2: FEB 1998
PERFORMANCE INCENTIVES
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
Conversely liquidated damagesclausesserve asa disincentive for a
contractor to incur culpable delay.
Cost Related Incentives
Where there isa need to ensure that cost limitsare not exceeded
then it isappropriate to consider the use of incentivesfor the
contractor or consultant to save costs.
Some organisationsoffer membersof the consultant team half the
savingsit isable to make asa result of value engineering, in order to
encourage reduction in project cost. Clearly thisshould be done with
care. Consultantsshould not be given the opportunity to set high initial
budgetsand then make windfall gainsasthey go through design
development securing cost savings.
The following are exampleswhere the contractor to a workscontract
isgiven an incentive to secure cost savings:
The contractor and the Department share equally in any cost
savingsachieved by the contractor. See clause 38 of
GC/Works/1( 1998) .
In the Engineering and Construction Contract 2nd Edition: Target
Contract with Activity Schedule, the contractor receivesan agreed
percentage share of any actual saving on the target cost of each
activity in the activity schedule. Conversely if the actual cost exceeds
the target cost then the contractor must pay that same percentage
share by way of contribution to the overspend.
Key Points
Contract incentivesmay produce real benefitsfor the Department,
in achieving time and cost targetsand in encouraging closer co-
operation between membersof the team.
Contract incentivesmay require amendmentsto standard forms
where such formsare to be used. Such changesshould be carefully
considered.
HM Treasury Guidance Note No. 58 providesa detailed background
to the principlesof incentivisation. A copy/copiescan be obtained
from HM Treasury, Allington Towers, 19 Allington Street, London
SW1E 5EB ( tel: 0171 270 4558) .
LE 2.8

PS 3.5.2
HOME
GACC
EDITION 2: FEB 1998
PS 3.6 MONITORING PERFORMANCE
Performance monitoring isan important part of the ongoing
management of commissionsand workscontracts. It particularly
focusesthe mind of team membersif monthly meetingsare held
directly with the project sponsor or commission manager at which he
or she showsan interest in the performance by each consultant of its
tasksagainst the programme.
It isbetter to discussproblemsat the time they arise rather than let
customer dissatisfaction fester and let team membersbelieve there is
no problem. Consultantsvalue positive and honest feedback so that
they know what isexpected of them and so that they know how to do
better next time. If there are problemsthen they should be resolved as
soon aspossible. Thisultimately benefitsthe Department and isan
inherent part of risk management.
Key Points
Active performance monitoring can improve performance.
If consultantsdo not measure up it ishelpful for them and the
Departmentsto know why.
MONITORING PERFORMANCE
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
PS 3.6
HOME
GACC
EDITION 2: FEB 1998
PS 3.7 RECORD KEEPING
Record keeping and archiving isa discipline in itself, but there are a
number of important general pointsabout record keeping which are
worth raising from a strategic point of view:
The commission and contractsfilesshould be kept asa record of
the procurement practice adopted, and made available so that the
procurement processcan be audited if required.
Key documentssuch ascontracts, specifications, design drawingswill
need to be retained. It should be noted that the CDM regulations
are now fully in force and place a statutory obligation on
Departmentsto have prepared a health and safety file for the vast
majority of projects. Thiscontainsspecification drawings, product
sheetsand methodsof construction. Thismust be retained for the
life of the building and passed on in the event of disposal of the
asset. The file must also be accessible.
It isalso advisable for the project sponsor or commission manager
to ensure that they obtain and retain sufficient recordsto support
or defend claimsagainst or by consultantsor contractors. It istrue
to say that the quality of a parties recordscan substantially
influence the quality of any case advanced by it and the quality of a
response to claimsbrought against it. It isimportant to keep good
recordsof the following:
- consultantsand contractorsactual progressagainst planned
progress;
- a schedule of when and what information and approvalswere
given by the project sponsor to any membersof the
construction team;
- the datesof commencement and duration of delaysto progress
and reasonsfor any such delays;
- the causesof cost escalation if not time related.
The existence of thistype of evidence may well help to deter parties
from bringing claimsagainst the Department.
RECORD KEEPING
PROCUREMENT STRATEGIES
PROCURING AND MANAGING THE TEAM
CST 2

CRS 2

PS 3.7
HOME
GACC
EDITION 2: FEB 1998
PS 4.0 PERFORMANCE EVALUATION
PS 4.1 EVALUATING PERFORMANCE
O ne of the key initiativespromoted by the Latham Report isthe need
to improve the efficiency of the construction industry and the quality of
the service it provides. To secure high performance from their suppliers,
best practice clientscontinually monitor and evaluate the performance
of their suppliers. They keep themselvesinformed asto which
companiesoffer good performance and good value for money.
A performance evaluation resultsin a report on the performance of
the contractor or consultant which isuseful for future reference,
particularlywhen repeat projectsare anticipated.
Departmentshave accessto a central database to assist them in
selecting suppliers. It isrun by the DETR and isknown asthe New
Q ualification System ( NQ S) .
Returning performance evaluationsto these organisationsought to be
a critical factor in their ongoing success.
If suppliersare aware that their performance will be evaluated and that
thismay affect their chancesof selection on other Government
contractsthen they are much lesslikely to deliver sub-standard
performance on contractsthey might consider to be one-off projects.
More detailed consideration isgiven to performance evaluation in the
consultantsand contractssection of the Guide.
EVALUATING PERFORMANCE
PROCUREMENT STRATEGIES
PERFORMANCE EVALUATION
CST 3.2

CRS 3.2

CST 10

CRS 12

PS 4.1
HOME
GACC
EDITION 2: FEB 1998
PS 4.2 PROJECT CRITIQUES
Any construction work givesrise to some degree of learning on the
part of itsparticipants. Thisarisesfrom the fact that the majority of
projectsare unique and because rarely isa project team ever the same,
by virtue of the personalitiesinvolved.
It isoften useful therefore to evaluate the performance of the whole
project rather than just that of the suppliers. Indeed such a review is
essential if the contract isa stage in an overall programme, or part of a
serial or maintenance contract.
The idea of a critique isnot to attribute blame for problemsbut to
engender positive feedback. It should examine what went right and the
critical successfactorswhich achieved that state of affairsaswell as
what went wrong and why, so that lessonslearned may be applied to
future projects.
Thiscan be seen asthe final step in the risk management processfor a
detailed critique might typically re-examine the risksidentified at the
outset of the project aswell asthose unexpected riskswhich may have
materialised during the projects. The difference at thisstage isthat the
outcomesare known. Some risksmay not have materialised at all,
othersmay have been more seriousthan expected. The critique can
examine the effectivenessof the risk management strategiesadopted
to deal with those risks.
PROJECT CRITIQUES
PROCUREMENT STRATEGIES
PERFORMANCE EVALUATION
PS 2.3

PS 4.2.1
HOME
GACC
EDITION 2: FEB 1998
Some key issueswhich might be considered in a critique of a works
project are asfollows:
Departmental Risks
- wassufficient support and guidance available to the project
sponsor or commission manager,
- were linesof communication effective,
- wasthe project sponsor empowered to make informed and
effective decisions,
- wasliaison with usersco-ordinated effectively,
- were decisionsand information provided to the construction
team when required,
- were complaintsmanaged effectively,
- were there personality problems,
- wasthe project sponsor sufficiently involved to engender the
good performance of the construction team,
- were claimsdealt with promptly,
- were the project objectivesclear and realisable;
Design Risks
- wasthe design brief consistent,
- wasthe design adequately co-ordinated asbetween professional
disciplinesand specialist sub-contractors,
- were there problemswith boundariesbetween different rolesin
the design team,
- were expectationsand dutiesclear,
- were sufficient resourcesemployed by consultants;
PROJECT CRITIQUES
PROCUREMENT STRATEGIES
PERFORMANCE EVALUATION
PS 4.2.2
HOME
GACC
EDITION 2: FEB 1998
Construction Risks
- were risksactively managed,
- did the contractor understand what the Department wanted,
- did the contractorstermsof contract adequately match that
expectation,
- were problemsidentified and dealt with early enough,
- were claimsdealt with promptly,
- were the contractorsmanagement systemseffective,
- how effectively were quality, cost and time criteria met,
- were sufficient resourcesdedicated to health and safety,
- were commissioning and handover proceduresdefined and
effective,
- were complaintsdealt with effectively and satisfactorily,
- did the Department get what it wanted.
Key Points
A project critique isessential for certain typesof work, especially
stage or repeat contracts.
A project critique can be distilled into a non-personal case study
which can be distributed for the benefit of all interested parties.
PROJECT CRITIQUES
PROCUREMENT STRATEGIES
PERFORMANCE EVALUATION
PS 4.2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
PS 5.0 OTHER ISSUES
PS 5.1 PARTNERING
Partnering isa managerial approach used by two or more organisations
to achieve specific businessobjectivesby maximising the effectiveness
of each participantsresources. Thisapproach isbased on shared mutual
objectives; agreed methodsof resolving problems; shared risks
according to who can best manage them; and an active search for
continuousmeasurable improvements.
Because of the scope for reducing adversarial relationships, partnering
isconsistent with procuring best value for money services. Partnering
arrangementsmay be used by the public sector and are consistent with
EC procurement regulationsprovided certain conditionsare met. These
are set out at paragraph 7.4 of Setting New Standards, and paragraph
240 of the Construction Procurement by Government. The conditions
which must be met are:
the initial procurement of the supplier must be through competition;
the clientsneedsand objectivesmust be clearly stated and there
must be a clear definition of both partiescontracted responsibilities;
and
in the case of strategic partnering contractsthere should be specific
milestonesfor improved performance with the contract being for a
specific period and periodically re-let in competition.
There are two formsof partnering:
Strategic Partnering
Strategic partnering occurswhere individual awardsare made
throughout the duration of a partnering contract. Thistype of
arrangement isoften used by Departmentswhen engaging consultants
on a term or call-off contract basis. Thisarrangement hasalso been
very successful in relation to maintenance contractsand capital
schemes.
PARTNERING
PROCUREMENT STRATEGIES
OTHER ISSUES
PS 5.1.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Further advice on the principlesbehind Strategic Partnering can be
found in CUP Guidance Note No. 57 and Procurement Guidance Note
No. 4, available from HM Treasury ( tel: 020 7270 4558) .
Project Partnering
With Project Partnering the collaborative arrangement isestablished
after the contract hasbeen awarded and isproject specific. Further
information on Project Partnering can be found in the Construction
Industry Boardsreport Partnering the Team ( ThomasTelford
ISBN: 0 7277 2551 3) and the European Construction Institutes
publication Partnering in the Public Sector ( ISBN: 1 873844 34 4) .
Key Points
Partnering isa challenging approach to procurement that requires
high levelsof commitment from both sides. It isnot a universal
panacea;
Properly managed partnering hasbeen shown to effectively reduce
adversarial relationships, but partnersmust be procured through
competition;
Such arrangementsshould work equally well with situationswhere
there isa specific need for a definable service over a specific period
of time, and for specific one off projects;
Strategic Partnering arrangementshave been effective in reducing
lead-timeswhere elementsof a work programme must be procured
and completed;
Although a non-contractual option partnering must still be
supported by appropriate documentation, such asa Charter or
Agreement and a joint workshop agenda. The effect on the formal
contract termswill need to be assessed, and the need for
consequential amendmentsto reflect the partnering arrangements
may vary asbetween Strategic and Project Partnering.
PARTNERING
PROCUREMENT STRATEGIES
OTHER ISSUES
PS 5.1.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
PS 5.2 PRIVATE FINANCE INITIATIVE
Since the launch of the Private Finance Initiative by the Chancellor in
November 1992, there hasbeen increasing impetusfrom Central
Government for all Departmentsto consider thisprocurement option.
The objective of PFI isto use private sector finance, flair, management
skillsand resourcesto secure the best possible value for money for the
taxpayer to deliver capital intensive servicesto the public sector.
PFI funded projectstypically involve a consortia of private sector design,
construction and operator companieswho take a stake in the life cycle
cost of the asset. The private sector typically takeson both construction
and programme risksaswell asoperational and economic risks. The
public sector becomesa purchaser of serviceson the basisof the
usage, availability and performance of the asset during itslife. The public
sector incursno capital expenditure.
Private finance in respect of Government premisesfor example might
result in the private sector taking design and construction risksbut also
operational risksin running and maintaining the premises. The Landlord
will therefore have considerable interestsat stake in ensuring the
ongoing satisfactory performance of the premises. The public sector
Department would typically be expected to pay a premium for risk
transfer, but might get in return certainty of cost and flexibility of
occupation.
There are two fundamental requirementsfor a PFI project:
there must be a genuine transfer of risk to the private sector; and
value for money must be demonstrated for public sector
expenditure.
It isintended that risksare transferred to those best able to manage
them. Certain type of public sector risk may not be capable of being
transferred.
PFI operateswithin the same policy and legal frameworksasother
procurement methods. Ascontracting authoritiesidentify specific needs,
the procurement option appraisal must be conducted on the basisof
fitnessfor purpose and value for money.
PRIVATE FINANCE INITIATIVE
PROCUREMENT STRATEGIES
OTHER ISSUES
PS 5.2.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
If thisappraisal concludesthat PFI isthe chosen procurement route, the
contracting authority hascertain responsibilitiesbefore launching a
competition ( through O JEC if appropriate) . Many of these stem from
the review of PFI conducted by Malcolm Batesin May and June 1997.
The Government hasaccepted hisrecommendationswhich take into
account:
the formation of a new HM Treasury taskforce, the project arm of
which will review all significant projectsprior to their release to
competition;
the requirement that the new taskforce should sign off the
commercial viability of all significant projectsbef bef bef bef before ore ore ore ore the
procurement processcommencesby way of publication in the
O fficial Journal;
contracting authoritieswill continue to be responsible and
accountable for their own procurement decisions.
The definition of what isa significant project will clearly influence the
direction and handling of the procurement exercise. The Taskforce
projectsteam will decide what constitutesa significant project in
conjunction with relevant departmentsand agencies. The definition will
probably comprise several different elements( eg. importance in a
policy or national context or the fact that a project isthe first of a
series) . The underlying purpose isto prevent flawed projectsbeing
placed before the market - thushelping to avoid nugatory costsbeing
incurred on either side.
Key Points
Contracting authoritieswho feel that their PFI project( s) may fall
into the significant category should contact the PFI Taskforce
projectsteam assoon aspossible at:
HM Treasury
Parliament Street
London SW1P 3AG
Tel: 020 7270 4865
The PFI Task Force haspublished a Standardisation of PFI
Contracts which Departmentscan use asa model on any PFI
projectsthey may be pursuing. A copy can be obtained from HM
Treasury ( ISBN 0-406-92879-7) .
PRIVATE FINANCE INITIATIVE
PROCUREMENT STRATEGIES
OTHER ISSUES
PS 5.2.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Thischapter of the guide concernslegal mattersand seeksto address
both English and Scottish law.
Where there are substantial legal differencesor procedural
requirementsbetween the English and Scottish systems, separate
sectionshave been written.
The relevant Scottish sectionsare numbered with the suffix SCO T
following them. An example isshown below:
LE 1.2 SIMPLE CO NTRACTS ( English version)
LE 1.2( SCO T) SIMPLE CO NTRACTS ( Scottish version)
To facilitate even easier identification the relevant Scottish sectionsare
printed on green paper. If there isonly one section ( with no SCO T
suffix) then it can be taken asapplicable under both legal systems.
Thischapter hasbeen developed in conjunction with Scottish
Executive and their legal advisers.
HOME
LE 1.0 LEGAL FRAMEWORK
LE 1.1 PRINCIPLES CO VERING THE LAW O F CO NTRACT IN ENGLAND AND
WALES
LE 1.1( SCO T) PRINCIPLES CO VERING THE LAW O F CO NTRACT IN SCO TLAND
LE 1.2 SIMPLE CO NTRACTS
LE 1.2( SCO T) SIMPLE CO NTRACTS
LE 1.3 CO NTRACTS BY DEED
LE 1.3( SCO T) SELF-PRO VING CO NTRACTS
LE 1.4 PERFO RMANCE AND DETERMINATIO N
LE 1.4( SCO T) PERFO RMANCE AND T ERMINATIO N
LE 1.5 DISCHARGE O F A CO NTRACT
LE 1.6 MISTAKE AND MISREPRESENTATIO N
LE 1.6( SCO T) MISTAKE ( ERRO R) AND MISREPRESENTATIO N
LE 1.7 BREACH O F CO NTRACT
LE 1.8 DAMAGES FO R BREACH O F CO NTRACT
LE 1.9 LIMITATIO N
LE 1.9( SCO T) PRESCRIPTIO N
LE 1.10 EVIDENCE O F CO NTRACT
LE 1.10( SCO T) EVIDENCE O F CO NTRACT
LE 1.11 ASSIGNMENT
LE 1.11( SCO T) ASSIGNATIO N
LE 1.12 NO VATIO N
LE 1.13 TRANSACTIO NS WITH O UTSIDE BUSINESSES
LE 1.14 PARENT CO MPANY GUARANTEES
LE 1.15 PERFO RMANCE BO NDS
LE 1.16 STAMP DUTY
LE 1.17 PRO CEEDINGS INSTITUTED AGAINST DEPARTMENTS
LE 1.17( SCO T) PRO CEEDINGS INSTITUTED AGAINST DEPARTMENTS
LE 1.18 INSO LVENCY AND BANKRUPTCY
LE 1.18( SCO T) INSO LVENCY AND BANKRUPTCY
LE 1.19 RESERVATIO N O F TITLE
LE 1.19( SCO T) RESERVATIO N O F TITLE
LE 1.20 UN FAIR CO NTRACT T ERMS ACT 1977
LE 1.21 LEGAL ADVICE
LE 1.21( SCO T) LEGAL ADVICE
HOME
LE 2.0 OTHER ISSUES
LE 2.1 HEALTH & SAFETY ( CDM)
LE 2.2 TRANSFER O F UNDERTAKINGS ( TUPE)
LE 2.3 RACIAL DISCRIMINATIO N
LE 2.4 FAIR EMPLO YMENT ( NO RTHERN IRELAND) ACTS
LE 2.5 INTELLECTUAL PRO PERTY, CO PYRIGHT, AND RO YALTIES ETC.
LE 2.5( SCO T) INTELLECTUAL PRO PERTY, CO PYRIGHT, AND RO YALTIES ETC.
LE 2.6 PRO PRIETARY CO MPO NENTS/ARTICLES
LE 2.7 FIRM PRICE AND VARIATIO N O F PRICE
LE 2.8 LIQ UIDATED AND ASCERTAINED DAMAGES
LE 2.9 THE HO USING GRANTS, CO NSTRUCTIO N & REGENERATIO N ACT
1996
LE 2.10 THE ARBITRATIO N ACT 1999
LE 2.10( SCO T) ARBITRATIO N
LE 2.11 CO NSTRUCTIO N INDUSTRY TAX SCHEME
HOME
GACC
EDITION 2 REV 1: JAN 1999
LE 1.0 LEGAL FRAMEWORK
LE 1.1 PRINCIPLES COVERING THE LAW OF CONTRACT IN
ENGLAND AND WALES
General
The procurement of consultantsand contractorsrequiresofficialsin
Departmentsto initiate and prepare appropriate contracts. A lot of
time and expertise hasalready been invested in the preparation of
standard formsof contract, in order to ensure clear and consistent
drafting. See the GovernmentsGC WorksSeriesof Contractsand
CUP Guide 42 for standard termsand conditionsfor servicescontracts.
It istherefore recommended that standard formsare used without
amendment.
O ccasionally it may be necessary to adapt a standard form to satisfy the
specific needsof a commission. It isimperative in the carrying out of
thistask that the contract conditionsand insertionsare drafted with
clarity and that there are no intrinsic conflictswithin the contract itself,
and/or between the contract and associated documentation.
Amendmentsto standard formsare one of the areasof risk which
commonly give rise to disputes. It isrecommended that legal advice
should be sought for the drafting of amendmentsor to audit any
amendmentsproposed by the Department. O fficialsinvolved in the
preparation of workscontractsshould therefore have an understanding
of elementary legal principlesand the meaning of legal terms
commonly used which issufficient for them to know when legal advice
should be sought. The following sectionsset out the basic principlesto
be understood in contract preparation.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PRINCIPLES COVERING THE LAW OF CONTRACT IN ENGLAND AND WALES
PS 2.3

L
! !! !!
L
! !! !!
LE 1.1.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
Essential Elements for Formation of a valid contract
A contract isan agreement intended by the partiesto it to have legal
consequencesand to be legally enforceable, the essential elements
being:
offer by one party and acceptance by the other;
intention to create legal relations;
agreement about the same thing i.e. genuine agreement;
capacity of the parties;
legality of objects;
possibility of performance;
certainty of terms;
in the case of simple contractsnot by deed, the presence of valuable
consideration, i.e. some right, interest, profit, or benefit accruing to
one party or some forbearance, detriment, lossof responsibility
given, suffered or undertaken by the other.
O nly the partieswho enter into the agreement are bound by it and a
person who isnot a party to the agreement cannot normally enforce
the rightsand liabilitiescreated by a contract entered into by others,
although the contract may have reference to the interestsof that
person. Thisprinciple isknown asthe doctrine of privity of contract.
Third partiesmay however acquire rightsand liabilitiesby way of
collateral contracts.
Contractsare divided into two main classes:
simple contracts( contractsmade orally or in writing) ;
contractsby deed ( contractsmade in writing) .
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PRINCIPLES COVERING THE LAW OF CONTRACT IN ENGLAND AND WALES
LE 1.2

LE 1.3

LE 1.1.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.0 LEGAL FRAMEWORK
LE 1.1(SCOT) PRINCIPLES COVERING THE LAW OF CONTRACT IN
SCOTLAND
General
The procurement of consultantsand contractorsrequiresofficialsin
Departmentsto initiate and prepare appropriate contracts. A lot of
time and expertise hasalready been invested in the preparation of
standard formsof contract, in order to ensure clear and consistent
drafting. See the GovernmentsGC/WorksSuite of Contractsand CUP
Guide 59D for standard termsand conditionsfor servicescontracts. It
istherefore recommended that standard formsare used without
amendment.
Note that the Scottish Building Contract Committee ( SBCC) amend
the JCT range of contractsfor use in Scotland.
O ccasionally it may be necessary to adapt a standard form to satisfy the
specific needsof a commission. It isimperative in the carrying out of
thistask that the contract conditionsand insertionsare drafted with
clarity and that there are no intrinsic conflictswithin the contract itself,
and/or between the contract and associated documentation.
Amendmentsto standard formsare one of the areasof risk which
commonly give rise to disputes. It isrecommended that legal advice
should be sought for the drafting of amendmentsor to audit any
amendmentsproposed by the Department. O fficialsinvolved in the
preparation of workscontractsshould therefore have an understanding
of elementary legal principlesand the meaning of legal terms
commonly used which issufficient for them to know when legal advice
should be sought. The following sectionsset out the basic principlesto
be understood in contract preparation.
PS 2.3

I
! !! !!
I
! !! !!
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PRINCIPLES COVERING THE LAW OF CONTRACT IN SCOTLAND
LE 1.1.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Essential Elements for Formation of a valid contract
A contract isan agreement intended by the partiesto it to have legal
consequencesand to be legally enforceable, the essential elements
being:
offer by one party and unqualified acceptance by the other;
intention to create legal relations;
agreement about the same thing i.e. genuine agreement;
capacity of the parties;
legality of objects;
possibility of performance;
certainty of terms.
In the ordinary case where a contract ismade between two partiesit is
they alone who acquire rightsunder and have liabilitiesimposed on
them by it. O ne of the most important exceptionsto thisrule isthat,
where it appearsthat the object of the contract wasto benefit a third
party, the contract may be held to confer a jus quaesitumtertioon that
person. Such a right will be held to have been conferred if the third
party isnamed, or referred to, or isone of a distinct identifiable class
referred to, in the contract. In the fieldsof contract and procurement,
instancesin which such a right existsare firstly, where money isplaced
on deposit receipt made payable to the third party, where that third
party can uplift the sum on deposit, and secondly, where third parties
acquire rightsand liabilitiesby way of collateral contracts.
Contractsare divided into two main classes:
simple contracts( i.e. made orally or in writing) ;
self-proving contracts( i.e. made in writing) .
Note that contractsin respect of devolved functionswill run in the
name of the Scottish Ministers, whilst contractsin respect of reserved
functionswill run in the name of a Minister of the Crown ( usually the
Secretary of State for the Environment, Transport and the Regions) .
Contractsshould never be in the name of a Department asthey have
no legal personality. If however a departmental identity isdesired the
contract may run in the name of the Scottish Ministers/Secretary of
State, acting through [name of Govt. Dept. or Agency].
LE 1.2

LE 1.3

LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PRINCIPLES COVERING THE LAW OF CONTRACT IN SCOTLAND
LE 1.1.2(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.2 SIMPLE CONTRACTS
Simple contractsinclude all contractswhich are not deeds. They may
be made orally, in writing, or by implication from conduct, but must
possessthe essential elementsfor formation of a valid contract.
Most workscontractsare simple contractsand are nearly alwaysin
writing, although they vary in form and comprise contractsmade by
exchange of letters( e.g., the contractorstender and the departments
letter of acceptance) and also contractsin the shape of a formal
agreement ( e.g., contractsfor electricity suppliessigned on behalf of the
Secretary of State are under hand and not by deed) .
The essential elementsof a simple contract should be borne in mind
with particular regard to the following:
Need for Consideration
simple contracts( ascontrasted with contractsby deed) require
there to be consideration;
a gratuitouspromise isnot normally enforceable, and the presence
of consideration demonstratesthat the promise isnot gratuitous;
in every simple contract each partyspromise isthe consideration
for the other partyspromise. In other wordsthere isan exchange
of promises;
past consideration will not create an enforceable contract since the
reciprocal promise will not be present.
Form of Consideration
Consideration can take the form of:
an act;
a forbearance not to carry out an act; or
a promise.
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.1

LE 1.2.1
HOME
GACC
EDITION 2: FEB 1998
Examplesof valid consideration would therefore be the payment of
money, a promise to pay money, an agreement to provide a product or
service, or forbearance from deducting liquidated damages. The
monetary value of the consideration isnot material, aslong asit does
have some value. Therefore a trifling payment which doesnot
necessarily represent the true value of work or service provided will be
sufficient consideration for the formation of a valid contract.
Communication of Offer and Acceptance
the offer, and acceptance of the offer, must be communicated by the
one party to the other;
the contract isbrought into existence upon communication of the
acceptance;
the act of acceptance createsthe contract and once communicated
the acceptance cannot be revoked;
an exception to the general rule will be where the post isused as
the medium of communication between the parties. The posting of
the letter of acceptance issufficient communication, even though
the letter may fail to reach itsdestination.
Time Allowed for Acceptance
Acceptance must be made:
within the time prescribed e.g., an offer may be made subject to
acceptance within fifteen days; or
within a reasonable time if no time hasbeen prescribed.
The question asto what isa reasonable time isnot capable of general
definition and isdependent upon the circumstancesof the individual
case. To avoid the situation where a contractor disputesa Departments
right to hold the contractor to the termsof the original offer, if there is
any doubt whatsoever about the length of time elapsed since the offer
wasmade, the Department should contact the contractor to obtain
confirmation that the offer still stands.
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
L
! !! !!
LE 1.2.2
HOME
GACC
EDITION 2: FEB 1998
Acceptance to be Identical with Offer
An agreement doesnot give rise to a contract unlessitstermsare
certain or capable of being made certain, and a contract isnot brought
into existence by acceptance unlessthe acceptance isabsolute and
identical with the offer. Asthe Secretary of State isusually in the
position of acceptor ( of offersmade by contractorsin response to
invitationsto tender) it isimportant to be satisfied that the offer has
been expressed with precision and that the unconditional acceptance is
in accordance with the Departmentsrequirementsand intentions.
Conditional acceptance doesnot create a contract but amountsto a
counter-offer needing unconditional acceptance by the contractor
before a binding contract arises.
Similarly, when it isdesired to make an offer on behalf of the Secretary
of State itstermsmust be carefully drafted in the knowledge that a
definite and unconditional offer becomesa binding promise upon
acceptance by the party to whom the offer ismade.
Withdrawal or Revocation of Offer
An offer can be revoked at any time before it isaccepted. Revocation
or withdrawal can take place before the time that the offeror has
prescribed for acceptance if such time for acceptance hasbeen
prescribed.
To be effective, withdrawal or revocation must come to the knowledge
of the other party before the offer isaccepted and isnot sufficiently
communicated by the posting of a letter, bearing in mind thismay well
be received after the posting of the acceptance of the original offer.
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
L
! !! !!
L
! !! !!
LE 1.2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.2(SCOT) SIMPLE CONTRACTS
Simple contractsinclude all contractswhich are not self-proving. They
may be made orally, in writing, or by implication from conduct, but must
possessthe essential elementsfor formation of a valid contract.
Most workscontractsare simple contractsand are nearly alwaysin
writing, although they vary in form and comprise contractsmade by
exchange of letters( e.g. the contractorstender and the departments
letter of acceptance) and also contractsin the shape of a formal
agreement ( e.g. contractsfor electricity suppliessigned on behalf of the
Scottish Ministers( for devolved functions) or the Secretary of State
( for reserved functions) ) .
The essential elementsof a simple contract should be borne in mind
with particular regard to the following:
Communication of Offer and Acceptance
the offer, and acceptance of the offer, must be communicated by the
one party to the other;
the contract isbrought into existence upon communication of the
acceptance;
the act of acceptance createsthe contract and once communicated
the acceptance cannot be revoked;
an exception to the general rule will be where the post isused as
the medium of communication between the parties. The posting of
the letter of acceptance issufficient communication. Whilst however
the offerer may be contractually bound for a few daysbefore the
offer isactually received, it isdoubtful whether, in Scotslaw, a
contract would be held to have been concluded if the letter
ultimately failsto reach itsdestination;
offerersmay stipulate the meansof communication by which the
acceptance isto be communicated. If, e.g., acceptance by letter,
recorded delivery mail or fax isstipulated, then thismust be adhered
to - it isa condition of the offer.
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.1

LE 1.2.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Time Allowed for Acceptance
Acceptance must be made:
within the time prescribed e.g. an offer may be made subject to
acceptance within fifteen days; or
within a reasonable time if no time hasbeen prescribed
otherwise the offer will terminate.
Where a time-limit for acceptance hasbeen prescribed the offer
automatically fallsat the expiry of that time. Note however that the
offerer may waive the time-limit if desired.
The question asto what isa reasonable time isnot capable of general
definition and isdependent upon the circumstancesof the individual
case. To avoid the situation where a contractor disputesa Departments
right to hold the contractor to the termsof the original offer, if there is
any doubt whatsoever about the length of time elapsed since the offer
wasmade, the Department should contact the contractor to obtain
confirmation that the offer still stands.
Acceptance to be Identical with Offer
An agreement doesnot give rise to a contract unlessitstermsare
certain or capable of being made certain, and a contract isnot brought
into existence by acceptance unlessthe acceptance isabsolute and
identical with the offer. Asthe Scottish Ministersor the Secretary of
State are usually in the position of acceptor ( of offersmade by
contractorsin response to invitationsto tender) it isimportant to be
satisfied that the offer hasbeen expressed with precision and that the
unconditional acceptance isin accordance with the Departments
requirementsand intentions.
Conditional acceptance doesnot create a contract but amountsto a
counter-offer needing unconditional acceptance by the contractor
before a binding contract arises.
Similarly, when it isdesired to make an offer on behalf of the Scottish
Ministersor the Secretary of State itstermsmust be carefully drafted in
the knowledge that a definite and unconditional offer becomesa
binding promise upon acceptance by the party to whom the offer is
made.
I
! !! !!
I
! !! !!
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.2.2(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Recall or Withdrawal of Offer
To be effective, withdrawal or revocation must come to the knowledge
of the other party before the offer isaccepted and isnot sufficiently
communicated by the posting of a letter, bearing in mind thismay well
be received after the posting of the acceptance of the original offer.
The main rulesasto recall or withdrawal of an offer summed up are:
if the offerer undertakesto keep the offer open for a definite
period, that promise isbinding. The offer cannot be recalled within
that time;
if the offerer statesthat acceptance must be made within a specified
time, and acceptance isnot made within that time, the offer is
automatically recalled;
if the offerer doesnot state a time within which acceptance must be
made, the offer remainsopen, not indefinitely, but only for a
reasonable time ( see previously) , and if not accepted within a
reasonable time it isautomatically recalled;
where there isno promise to keep an offer open for a specified
time, the offerer can recall hisoffer at any time before it hasbeen
accepted. Aslong asthe partiesare still at the stage of negotiation,
and a contract hasnot yet been formed, either party hasthe right
to resile or draw back. An offer cannot be withdrawn after it has
been accepted.
I
! !! !!
SIMPLE CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.2.3(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.3 CONTRACTS BY DEED
Contractsof thisclassmust be made in a formal written agreement ( i.e.
a single document executed by the partiesby deed) and not, for
example by exchange of documentsor letterswhich isthe normal
practice for workscontracts.
The written document in which a contract by deed isformally
executed isknown asa deed. A deed becomesoperative when sealed
and delivered by the partiesto it. Where an individual isa party to a
contract under seal, that partyssignature isalso necessary.
Execution of a deed by a company istraditionally by affixation of the
company seal, although if it ismade very clear that the document is
being executed asa deed, the affixation of the seal isnot necessary.
Key Points
Because of the form in which they are expressed, contractsby deed
are legally enforceable even though they are sometimesmade
without valuable consideration.
The right of action arising out of a contract executed by deed
continuesfor twelve yearsrather than the six year period that
appliesto simple contracts.
By law certain contractsmust be executed by deed. Typically these
include documentssuch asthose for the conveyance of land. Deeds
may be used if desired for any other contracts, however
unimportant, particularly where a longer limitation period may be
required.
CONTRACTS BY DEED
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.9

LE 1.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.3(SCOT) SELF-PROVING CONTRACTS
Self-proving ( probative) contractsmust be made in a formal written
agreement ( i.e. a document executed by the parties; and witnessed if
signing asindividualsor partnerships, or properly for the company if a
company) and not, for example by exchange of documentsor letters
which isthe normal practice for workscontracts.
The advantage to, or reason for, using probative writing isthat if
challenged, the contract carriesa presumption of authenticity and
provesitsown date. It istherefore for the other party to prove it isnot
genuine.
Where additional documents, e.g. schedulesor appendices( often
comprising the conditionsof contract in one, and the specification in
another) , or plans/drawings, are to form part of the formal contract
document they must be properly incorporated into that contract. In
order to be properly incorporated into the contract, such annexations
must be both referred to individually in the contract and identified on
the face of each asbeing the annexation referred to in the contract
( generally by the wording Thisis[Schedule [A]]/[Plan [A]] referred to
in the foregoing contract between X and Y for .... handwritten or typed
at the top of the first page of each such schedule/plan) .
Key Point
By law certain contractsmust be self-proving. Typically these include
documentssuch asthose for the conveyance of land. Self-proving
may be used if desired for any other contracts, however
unimportant.
SELF-PROVING CONTRACTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.3(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.4 PERFORMANCE AND DETERMINATION
A party to a contract isentitled to have the contract performed in the
manner described in the contract. That party cannot be compelled to
accept a different mode of performance even though equally beneficial
to that party. Whether what hasbeen done constitutesperformance of
the contract isa question depending in each case on the construction
of the termsof the contract and/or the factsof the case. The parties
may by agreement or waiver substitute a different mode of
performance for that originally agreed and by so doing create a new
contract, providing that valuable consideration ispresent in so doing.
Contractual stipulationsasto the time for performance are not
generallyconstrued asbeing essential such that failure to perform by
the time for performance entitlesthe innocent party to elect to
terminate the contract. The general principle isthat performance must
be carried out within a reasonable time. The exceptionsto the general
principle arise where time ismade of the essence in the following
situations:
where the partieshave expressly stipulated in their contract that the
time fixed for performance must be exactly complied with, or have
expressed that time isof the essence;
where the circumstancesof the contract or nature of the subject
matter imply a requirement for performance by an exact time e.g.
the sale of businessland or the exercise of an option for the
purchase of property;
where time wasnot originally of the essence of the contract and
one party hasbeen guilty of undue delay, the innocent party may
give notice requiring the contract to be performed within a
reasonable time, in which case time becomesof the essence of the
contract for both parties.
Determination
Where one party to a contract failsor refusesto perform the contract
demonstrating an intention no longer to be bound by the contract, the
other party may treat such conduct asrepudiation and determine the
contract by acceptance of the repudiation.
Alternatively, the conduct may be such asto entitle the injured party to
operate a contractual determination clause which normally brings
about the same end to further contractual performance aswould an
acceptance of repudiation.
PERFORMANCE AND DETERMINATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.5

LE 1.4.1
HOME
GACC
EDITION 2: FEB 1998
A party who purportsto operate a contractual determination clause
when not entitled to do so islikely to be held to have repudiated the
contract.
Contractual determination clausesdo not exclude common law
remediesavailable upon repudiation unlessthe agreement expressly
providesthat the contractual rightsare to be the exclusive remedy for
the breachesin question.
Contractual determination clauseswill normally set out precise
conditionsto be fulfilled with respect to notice periods, along with
practical requirementsfor the conclusion of performance. Some
contracts, particularly consultancy agreements, allow for contractual
determination to take place without default on the part of either party.
Clausesof thisnature do not, however, normally expressly entitle the
Department determining the contract to recover damagesfrom the
other party. The Department must therefore recover any damages
incurred by way of a claim in common law.
Key Points
Determination of a contract isa seriousmatter, and a commission
manager or project sponsor considering such an action should
obtain authorisation from an officer with the appropriate delegated
authority.
The Department should be very clear about itsgroundsfor
determining a contract and should follow all contractual
requirementsregarding notice before doing so. ( See for example
Clause 56 of GC/Works1/( 1998) ) .
The benefitsof removing a contractor or consultant who isnot
performing must be balanced against the following factors:
it takestime to procure a replacement contractor or consultant
to complete the work, and they themselvesrequire a learning
curve and mobilisation time;
whilst extra costscan be claimed from the defaulting party it will
commonly require legal action to secure recovery of such costs;
the liability for defectscan become very difficult to attribute to
the defaulting party or to the party engaged to complete the
work unlessthere isa clear demarcation between their work.
A very clear record ( ideally photographic and measured) should be
made of the state of the work asof the date of determination, and
the site should be secured.
PERFORMANCE AND DETERMINATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
L
! !! !!
LE 1.4.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.4( SCO T) PERFORMANCE AND TERMINATION
A party to a contract isentitled to have the contract performed in the
manner described in the contract. That party cannot be compelled to
accept a different mode of performance even though equally beneficial
to that party. Whether what hasbeen done constitutesperformance of
the contract isa question depending in each case on the construction
of the termsof the contract and/or the factsof the case. The parties
may by agreement or waiver substitute a different mode of
performance for that originally agreed and by so doing create a new
contract.
Contractual stipulationsasto the time for performance are not
generally construed asbeing essential such that failure to perform by
the time for performance entitlesthe innocent party to rescind the
contract. The general principle isthat performance must be carried out
within a reasonable time. The exceptionsto the general principle arise
where time ismade of the essence in the following situations:
where the partieshave expressly stipulated in their contract that the
time fixed for performance must be exactly complied with, or have
expressed that time isof the essence;
where the circumstancesof the contract or nature of the subject
matter imply a requirement for performance by an exact time e.g.
the sale of land or the exercise of an option for the purchase of
property;
where time wasnot originally of the essence of the contract and
one party hasbeen guilty of undue delay, the innocent party may
give notice requiring the contract to be performed within a
reasonable time, in which case time becomesof the essence of the
contract for both parties.
Termination
Where one party to a contract failsor refusesto perform the contract
demonstrating an intention no longer to be bound by the contract, the
other party may treat such conduct asrepudiation and rescind the
contract by acceptance of the repudiation. For repudiation, there must
be a breach of contract, but note that not every breach will constitute
a repudiation.
PERFORMANCE AND TERMINATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.5

LE 1.4.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Alternatively, the conduct may be such asto entitle the injured party to
operate a contractual termination clause which normally bringsabout
the same end to further contractual performance aswould an
acceptance of repudiation.
A party who purportsto operate a contractual termination clause
when not entitled to do so islikely to be held to have repudiated the
contract.
Contractual termination clausesdo not exclude common law remedies
available upon repudiation unlessthe agreement expressly provides
that the contractual rightsare to be the exclusive remedy for the
breachesin question.
Contractual termination clauseswill normally set out precise conditions
to be fulfilled with respect to notice periods, along with practical
requirementsfor the conclusion of performance. Some contracts,
particularly consultancy agreements, allow for contractual termination
to take place without default on the part of either party. Clausesof this
nature do not, however, normally expressly entitle the Department
terminating the contract to recover damagesfrom the other party. The
Department must therefore recover any damagesincurred by way of a
claim in common law.
Key Points
Termination of a contract isa seriousmatter, and a commission
manager or project sponsor considering such an action should
obtain authorisation from an officer with the appropriate delegated
authority.
The Department should be very clear about itsgroundsfor
terminating a contract and should follow all contractual
requirementsregarding notice before doing so. ( See for example
Clause 56 of GC/Works1/( 1998) ) . For thisreason it isstrongly
recommended that legal advice from the Departmentslegal adviser
also be obtained to ensure that the contract may be terminated.
The consequencesfor wrongful termination can be serious.
PERFORMANCE AND TERMINATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
I
! !! !!
LE 1.4.2(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
The benefitsof removing a contractor or consultant who isnot
performing must be balanced against the following factors:
it takestime to procure a replacement contractor or consultant
to complete the work, and they themselvesrequire a learning
curve and mobilisation time;
whilst extra costscan be claimed from the defaulting party it will
commonly require legal action to secure recovery of such costs;
the liability for defectscan become very difficult to attribute to
the defaulting party or to the party engaged to complete the
work unlessthere isa clear demarcation between their work.
A very clear record ( ideally photographic and measured) should be
made of the state of the work asof the date of termination, and the
site should be secured. Remember that these may be required as
evidence in any subsequent arbitration or court action.
LE 1.4.3(S)
PERFORMANCE AND TERMINATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.5 DISCHARGE OF A CONTRACT
There are a number of waysin which the partiesmay be released from
further performance, or in other wordsthe manner in which the
contract ends. The partiesmay be released:
by performance ( by both parties) in accordance with the termsof
the contract; in the case of part performance by a contractor of an
entire contract, the contractor would not be entitled to any
payment; an entire contract isone where the performance to be
provided by the provider ( supplier) isrequired to be complete in its
entirety before payment must be made by the purchaser/client
( Department) - for example the delivery and installation of a
functioning refrigerator; however, discharge can result from partial
performance being voluntarily accepted by the purchaser/client
where the purchaser/client had freedom of choice;
by mutual agreement;
by novation, where a fresh contract on the same subject may
expressly or impliedly discharge the original one;
where unforeseen eventsdestroy the basisof contract, making
performance impossible, impracticable or radically different from that
originally intended by the parties( frustration) ;
by material breach of a contract condition; what isa material breach
will vary from case to case, but in the case of material breach of
contract the innocent party may rescind the contract and claim
damages;
by mora, taciturnity and acquiescence, i.e. delay, silence and consent,
inordinate delay by both partieswhich may justify the inference that
the contract hasbeen abandoned or that any rightsunder it have
prescribed;
by operation of an expresscontractual provision which providesfor
the contract to be discharged.
DISCHARGE OF A CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12

LE 1.4

LE 1.5
HOME
GACC
EDITION 2: FEB 1998
LE 1.6 MISTAKE AND MISREPRESENTATION
Mistake
The courtswill not seek to rectify a mistake in the ordinary sense of
the word, for example, to mend a bad bargain made by one or either
party. However, there are situationswhere the courtswill nullify or
rescind the contract asa result of mistake by the partiesconcerning the
contract. These situationsare asfollows:
where there isa fundamental or radical difference between the
document actually signed and what the signer believed it to be, and
the signer hasnot been careless, the signer may raise the plea that
the document isvoid; thisplea isonly likely to be successful in very
limited circumstances;
where the partiesenter into contract on the basisof a false and
fundamental assumption; thismay be because the subject matter of
the agreement doesnot exist or hasceased to exist, unknown to
the partiesat the time;
where one party ismistaken asto the identity of the other party,
and the identity of the other party isof crucial importance, the
contract may be void at common law and of no effect.
Where the contract hasbeen reduced to writing and the contract fails
to reflect the intentionsof the parties, the court will rectify the
contract so asto carry out such intentions. Evidence of a contrary
intention may be adduced by production of written or parol evidence.
( Thisisa general exception to the parol evidence rule, which isthat
evidence of oral undertakingsmade by either of the partiesisnot
normally admissible to add to or vary the termsof an agreement
expressed in writing.) The courtswill not seek to rectify a written
agreement because the partiessimply overlooked a matter, since there
wasno intention expressed in respect of such a matter.
MISTAKE AND MISREPRESENTATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.6.1
HOME
GACC
EDITION 2: FEB 1998
Misrepresentation
Statementsmade during pre-contract negotiation can be either:
incorporated into the contract asa term in which case the remedy
for non-compliance with that term isan action for breach of
contract;
a representation not incorporated into the contract; if the
representation provesfalse, the remedy will lie in an action for
rescission and/or damagesfor actionable misrepresentation;
rescission meansthat the contract isset aside with the object of
putting the partiesback in the position they would have been in had
the contract never been made.
The essential ingredientsof actionable misrepresentation are:
a false statement of fact made by one party to the other; and
inducement of the other party to enter into contract asa result of
the false statement of fact.
The remedy available for actionable misrepresentation will depend
upon the nature of the representation, since a representation can be
fraudulent, negligent or innocent.
Rescission isavailable whether the misrepresentation isfraudulent,
negligent or innocent, although in some circumstancesthe injured party
may lose the right to rescind e.g. if the partiescannot be restored to
their original position. Damagesfor misrepresentation are available for
fraudulent and negligent misrepresentation but not for wholly innocent
representation. In most casesthe injured party will claim damagesfor
negligent misrepresentation under 52(i) of tbe Misrepresentation
Act 1967, and if liability isestablished the injured party will be able to
recover asa minimum the out of pocket expenses incurred.
MISTAKE AND MISREPRESENTATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.7

LE 1.6.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.6(SCOT) MISTAKE AND MISREPRESENTATION
Mistake (Error)
The courtswill not rectify a mistake or error in the ordinary sense of
the word, for example, to mend a bad bargain made by one or other
party. However, there are situationswhere the courtscan intervene,
outlined below:
Errorsmay be of expression or of intention.
In the former case, if the courtsaccept the evidence, they will
reform the contract to make it truly expressthe bargain ( for
example, if by a slip of the pen, an offer of 100 wasrecorded as
10 and the other knew 100 wasmeant) .
In the latter case, if one or both partieslaboured under a
misapprehension which induced him or them to contract, such that
had the true factsbeen known, no contract, or a different contract
would have been made, two situationsarise:
if only one party wasin error, then, unlessit wasso vital an error
asto exclude consent ( e.g. identity, subject-matter or price) or
unlessthe error wasmaterial and wasinduced by the other
partysstatement, the courtswill not come to hisrescue;
where both partiesare in error, the question of whether the
contract isreducible dependson the nature of the error. If the
error was, for example, of identity, subject-matter or price, then
the contract will be void ( null and void) . There may, however, be
other errors, important but not vital, which may render the
contract voidable ( capable of being made void) at the instance of
either party ( e.g. a house destroyed by fire before completion of
the bargain) .
MISTAKE AND MISREPRESENTATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.6.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Misrepresentation
Thismay be innocent or fraudulent.
An innocent misrepresentation isone made in the honest belief
that it istrue ( e.g. an art dealer believesa painting to be original
when it isreally a forgery) .
The essence of fraudulent misrepresentation isan intention to
deceive. Asthe law putsit, a misrepresentation, to be fraudulent,
must be made in the knowledge that it isuntrue or else it must be
made recklessly, carelesswhether it be true or false. There must be a
moral wrong. A statement might be made negligently but provided
the person making it believed it to be true ( asopposed to not
knowing if it wastrue or false) then there isno fraud. The
misrepresentation must be made with the intention of bringing
about the contract and, so far asreduction isconcerned, must be
made by one contracting party to the other.
The contracting party injured by fraudulent misrepresentation may ask
for reduction of the contract and/or damages. If reduction ispossible
and he hassuffered no loss, then although he will be able to reduce the
contract, he will not be entitled to damages. If reduction hasbecome
impossible and no losshasbeen sustained, he will continue to be
bound by the contract and will not be entitled to damages. If, however,
losshasbeen sustained, damageswill be awarded based upon the
actual loss.
If the misrepresentation wasinnocent, then no claim for damagescan
arise. The only remedy of the party to whom the misrepresentation
wasmade isto seek to have the contract reduced, if that isstill possible.
If it hasbecome impossible he hasno remedy.
MISTAKE AND MISREPRESENTATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.6.2(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.7 BREACH OF CONTRACT
Breach of contract occurswhere one ( or both) of the partiesfailsto
perform itsobligationsunder the contract.
Breachesof contract are material or non-material. Remediesavailable
to the innocent party depend upon the materiality of the breach ( i.e.
degree of seriousnessor importance) .
Non-material Breach
O ne remedy for a non-material breach of contract in Common Law is
damagesby way of compensation, such damagesbeing intended to
compensate the one party rather than to punish the other. The
innocent party may alternatively choose to use retention and lien, i.e.
withholding delivery of goodsor services, retaining possession of goods
belonging to the party in breach etc. Another option isto go to the
courtsto force the other party to fulfil itsobligationsin an action
known asspecific implement. Lastly, the simplest and most common
action for breach of contract isan action for payment asmoney
( usually the contract price) through the courts.
Material Breach
In the case of material breach, in addition to the remedy of damages,
the innocent party may also break off the contractual relationship ( that
isto say, that asa result of the material breach, the contract hasbeen
repudiated and the innocent party may rescind the contract or treat it
asrepudiated) .
The question of what ismaterial in a breach situation isalwaysa matter
of circumstancesand fact to be determined in each case.
Damages
Where the amount of compensation claimed isto be assessed by the
court, the damagesclaimed are termed unliquidated damages
( see LE 1.8) .
BREACH OF CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.7.1
LE 1.8

LE 2.8

HOME
GACC
EDITION 2 REV 2: JAN 2000
The partiesmay, however, choose to pre-determine or liquidate the
amountspayable in the event of breach. These amountsare commonly
termed liquidated and ascertained damages. To be enforceable such
amountsmust be a genuine pre-estimate of the losslikely to be
suffered asa result of the particular breach and not a penalty. Where
the estimated amount issubsequently found not to be a genuine pre-
estimate the court will not award damagesasa liquidated sum but may
pay an alternative assessment asunliquidated damages. ( Further
information on damagesisat LE 1.8.)
BREACH OF CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.7.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.8 DAMAGES FOR BREACH OF CONTRACT
A party to a contract who sufferslossasa result of a breach of the
other party will be entitled to an award of damages. Note however
that a party seeking damagesmust be able to show not only that there
hasbeen a breach, but also that that breach isdirectly linked to the loss
claimed. If the breach occurswhen work hasbeen partially completed
then the injured party may bring a quantum meruit ( asmuch asit is
worth) claim for the benefit of work partially completed.
Damagesare normally awarded on the basisof putting the innocent
party into the position that party would have been in but for the
breach. The measuring tool in calculating damageshowever isthe loss
to the innocent party, not the gain to the party in breach.
Limitation on Damages
The damagesthat can be awarded are subject to the limitation
imposed by the rulespreventing claimsfor losseswhich are deemed to
be too remote from the breach. The test established in the case of
Hadley v Baxendale will generally be satisfied if:
the damage or lossarisesaccording to the usual course of things
from such breach of contract, i.e. naturally;
the damage or lossarisesasmay reasonably be supposed to have
been in the contemplation of both parties, at the time they made
the contract, asa probable result of the breach of it; thismay occur
in situationswhere one party specifically drawsto the attention of
the other, a particular lossthat may be suffered asa result of a
breach, at the time of making the contract.
In addition to the above the injured party isrequired to take
reasonable stepsto reduce the lossand avoid taking action which may
increase the losssuffered ( i.e. to mitigate their loss) . The onusof proof
of whether the innocent party hasindeed mitigated itslossison the
party in breach.
DAMAGES FOR BREACH OF CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.7

LE 1.8
HOME
GACC
EDITION 2: FEB 1998
LE 1.9 LIMITATION
The courtswant to avoid stale claims. Legal actionsmust therefore be
commenced or originated within time limits. These time limitsare
contained in variousLimitation Acts. If proceedingsare not
commenced within the relevant time limit, the action will be statute
barred and cannot normally be brought, regardlessof the meritsof
the case. The law of limitation has, over recent yearsbecome an
increasingly complex subject, culminating in the Latent Damage Act
1986. The basic limitation rulesare set out below. However, asa result
of the above Act, the period may be extended significantly in respect of
non-personal injury actionsin negligence, so if there isany doubt, legal
advice should be sought.
PersonaI lnjury. The basic rule isthat an action must be brought
within three yearsof the negligence or breach of contract which
caused the injury. The basic period may be extended in certain cases
where the injury islatent, i.e. if the injured person could not have
known that he had been injured within the three year period.
Contract. An action must be brought within 6 yearsfrom the date of
the breach of contract. If the contract isby deed, the period is12 years.
If there hasbeen a breach of contract there may also be a cause of
action in negligence which may produce a longer limitation period.
NegIigence in Tort. The rulesregarding limitation periodsfor
actionsin negligence are more complex than for contract, and in some
casesallow more time. The basic rule isthat the period of limitation
expiressix yearsafter the damage occursor comesinto existence.
Alternatively, in accordance with the Latent Damage Act 1986, the
period isthree yearsfrom the earliest date, ( in very simple terms) ,
when the plaintiff knew:
that the damage wassufficiently seriousto justify proceedings;
that the damage wasattributable to the alleged negligence; and
the identity of the defendant.
The above two periodsrelating to negligence are subject to an overall
15 year longstop running from the date of the act or omission which is
alleged to constitute the negligence, after which such actionsshall not
be brought even if the cause of action hasnot yet accrued or the
starting date for the three year period hasnot yet arrived.
LIMITATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.9
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.9(SCOT) PRESCRIPTION
The principle of prescription governsthe length of time for which
obligationssubsist. The need for such a role isclear. Rightscannot exist
forever.
Prescription isthe term used to describe the processwhereby a
contractual obligation may simply extinguish itself by the passage of
time during which no action istaken in respect of it. The same process
in other areasof law may be used to establish legal rights( e.g. rightsof
way) , and thisoperatesso asto create a positive prescription. The main
effect of the processin the law of contract, however, isto extinguish
legal rightsby meansof negative prescription.
The Prescription and Limitation ( Scotland) Act, 1973 establishestwo
negative prescriptions, the long negative prescription ( 20 years) and
the short negative prescription ( five years) . According to which
category a particular obligation fallswithin, it may be extinguished after
five or twenty years, if the remaining essential conditionsare satisfied.
Some rightsare said to be imprescriptible, and are therefore immune
from both periods( e.g. real rightsto ownership of land) .
The vast majority of all contractual obligationswill expire under the
short negative prescription, i.e. after five yearsif the necessary
conditionsare satisfied.
However, before an obligation will prescribe, the relevant period of
time must have passed without any relevant claim by the creditor, or
any relevant acknowledgement by the debtor:
A relevant claim isa claim in a court of law, or in an arbitration, or a
lodgement of a claim in the debtorssequestration or liquidation.
Also classed asa relevant claim will be the execution of any
diligence in pursuit of the debt, or the enforcement of the
obligation.
for a relevant acknowledgement to occur, there must be some
performance on the part of the debtor which indicatesthat he
regardsthe obligation asstill existing, or an unequivocal admission in
writing, by or on behalf of the debtor, to the creditor or hisagent.
PRESCRIPTION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.9.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
If neither of these eventsoccurswithin the relevant prescriptive period,
then the obligation isextinguished by prescription. However, excluded
from the computation of thisperiod isany time during which the
making of a claim wasdelayed due to fraud on the part of the debtor,
or an error on the part of the creditor included by the debtor. Also
excluded isany period during which the creditor wasunder a legal
disability.
The prescriptive period beginsto run from the date when the
obligation becomesenforceable.
Legal advice should be sought in relation to thissubject.
With regard to personal injury the basic rule isthat an action must be
brought within three yearsof the incident giving rise to the claim. The
basic period may be extended in certain caseswhere material factsof
a decisive character were not known until a later date ( in which case
the time runsfrom that date) .
PRESCRIPTION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.9.2(S)
I
! !! !!
HOME
GACC
EDITION 2: FEB 1998
LE 1.10 EVIDENCE OF CONTRACT
Government contractsshould alwaysbe made or confirmed in writing
irrespective of legal need for the use of written documents. It may be
unavoidable, in very exceptional circumstances, to make oral
arrangementswhich create contractual liabilities. It ismost important
that any necessary authority issought and that the termsof such
arrangementsare confirmed in writing at the earliest possible moment
in order that the rightsand obligationsof both contracting partiesmay
be clearly defined.
Where written documentshave been used the evidence of the
contract isthe documentsthemselves, and all contract problemsshould
be considered from the starting point of the documentsconstituting
the offer and acceptance and establishing the precise agreement
between the parties.
O ral evidence and extrinsic documentsnot forming part of the
contractual offer and acceptance are not normally admissible for the
purpose of giving a different interpretation to alleged contract
documentsor to prove any subsequent variation of a contract which is
required by law to be in writing, but it isallowed:
to set aside a written contract on groundsof fraud or mistake;
to explain a latent ambiguity, trade custom; or
to show that a written document doesnot contain the whole
agreement.
O riginal contract documentsshould alwaysbe retained in a safe place
( i.e. a locked safe) and should be kept separate from day to day job
files.
EVIDENCE OF CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.10
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.10(SCOT) EVIDENCE OF CONTRACT
Government contractsshould alwaysbe made or confirmed in writing
irrespective of legal need for the use of written documents. It may be
unavoidable, in very exceptional circumstances, to make oral
arrangementswhich create contractual liabilities. It ismost important
that any necessary authority issought and that the termsof such
arrangementsare confirmed in writing at the earliest possible moment
in order that the rightsand obligationsof both contracting partiesmay
be clearly defined. Should a dispute later arise asto the scope of the
obligationsundertaken by a party, the intention of the partieswill be
looked at. In the absence of writing therefore, what the partiessaid
( rather than what obligation they thought they had undertaken) will
be the crucial point. If any aspect or term of the agreement wasnot
discussed and agreed therefore, e.g. termination and duration, then this
will not readily be implied. O ral contractscan be very risky therefore
and, particularly for larger such contracts, are not to be recommended.
Where written documentshave been used the evidence of the
contract isthe documentsthemselves, and all contract problemsshould
be considered from the starting point of the documentsconstituting
the offer and acceptance and establishing the precise agreement
between the parties.
O ral evidence and extrinsic documentsnot forming part of the
contractual offer and acceptance are not normally admissible for the
purpose of giving a different interpretation to alleged contract
documentsor to prove any subsequent variation of a contract which is
required by law to be in writing. Some contractsalso specifically
exclude all prior communicationsbetween the partiesby including an
Entire Agreement clause which statesthat the contract constitutesthe
entire understanding between the partiesand supersedesall prior
writingsand negotiations.
O riginal contract documentsshould alwaysbe retained in a safe place
( i.e. a locked safe) and should be kept separate from day to day job files.
Remember that contractual obligationsdo not expire under the short
negative prescription for five years. The original contract documentswill
still be of importance therefore during that period.
EVIDENCE OF CONTRACT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.10(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.11 ASSIGNMENT
In law, a party to contract cannot assign any of itsliabilitiesor
obligations( burdens) under a contract although that party may be
able to assign itsrightsor some of them ( benefits) . In view of the
ability of a contractor or consultant to legally assign rightsunder the
contract to a third party, it isnormally advisable for the Department to
include a term within the contract prohibiting assignment or the right
to assign. Alternatively it may be stipulated that assignment can only be
effected with the consent of the Department.
Key Points
Care should be exercised in drawing up and executing contractsto
ensure that the Departmentsrightsto assignment are not
prohibited.
Most of the standard formsfor construction workscontain a clause
preventing assignment or transfer of the contract or of any part,
share or interest under it without the consent in writing of the
Department. Clause 61 of GC/Works1/( 1998) , for example,
containssuch provision.
ASSIGNMENT
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.11
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.11(SCOT) ASSIGNATION
The general rule in Scotslaw isthat rightsand obligationsunder a
contract may be assigned or sub-contracted to another party provided
that the original contract doesnot involve delectuspersonage ( i.e. that
the choice of one particular person to perform a particular task
excludesall other persons- element of personal choice) . Generally
contractsfor servicesare held not to be assignable due to thisconcept,
but each contract must be considered individually to ascertain whether
it isassignable ( and, if so, the extent to which it isassignable) . Each
dependson itsterms, subject and all other relevant circumstances.
By the Contractor
In view of the ability of a contractor or consultant to legally assign
rightsunder the contract to a third party, it isnormally advisable for the
Department to include a term within the contract prohibiting
assignation or the right to assign. Alternatively it may be stipulated that
assignation can only be effected with the prior written consent of the
Department.
By the Department
Care should be exercised in drawing up and executing contractsto
ensure that the Departmentsrightsto assignation are not prohibited.
Key Point
Most of the standard formsfor construction workscontain a clause
preventing assignation or transfer of the contract or of any part,
share or interest under it without the consent in writing of the
Department. Clause 61 of GC/Works1/( 1998) , for example,
containssuch provision.
ASSIGNATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.11(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.12 NOVATION
Subject to the limitationsdiscussed in Section LE 1.11, third partiesmay
acquire rightsunder existing contractsby way of assignment/assignation.
Alternatively, third partiescan acquire rightsand liabilitiesby way of a
new contract with one of the original contracting parties. The substitute
agreement makesprovision for the discharge of all obligationsunder
the original agreement.
Examplesof the use of novation are asfollows:
asan option to secure completion of the worksin the event of
insolvency of a contractor;
in the case of a design and build contract where the Department
procuresan outline architectsdesign and then novatesit to the
design and build contractor.
Key Points
It isimportant for the partiesin the new agreement to define
clearly the responsibilitiesor liabilitiesof the original contractor to
be assumed by the substitute third party.
An example of an English and Scottish Government agreement for
the novation of a consultant commission isprovided overleaf
( Standard Form LE1/SF1) .
Seek advice before proceeding.
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.18

CRS 1.8

L
! !! !!
LE 1.12.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 1
EXAMPLE NOVATION AGREEMENT (ENGLAND & WALES)
THIS AGREEMENT ismade this[ ] day of ....................... 200[ ]
between .................................................................................. ( herein called the Consultant) of the first
part, ................................................. ( herein called the Substituted Consultant) of the second part,
and the Secretary of State for [asappropriate] acting through [Department] ( herein called
the Authority) of the third part.
WHEREAS
1. ThisAgreement issupplemental to the following Commission ( herein called the
Commission) between the Consultant and the authority.
Commission: ..........................................................................................
[Department] Reference No. ....................................................................
Consultant Reference No. ........................................................................
Asset out in the correspondence between the Authority and the Consultant dated
[.................................................................................................].
2. The Consultant desiresto be released and discharged from the Commission and the
Authority hasagreed to release and discharge them on condition that the substituted
consultant undertakesto perform and be bound by the Commission.
IT IS NO W AGREED asfollows:
1. The Substituted Consultant undertakesto perform the Commission and to be bound
by the termsof the Commission asif they were party to them in place of the
Consultant.
2. The Consultant assignsand releasesall benefitsand liabilitiesunder the Commission to
the Substituted Consultant.
3. The Authority releasesand dischargesthe Consultant from all claimsand demands
whatsoever in respect of the Commission and agreesto be bound by the termsof the
Commission asif the Substituted Consultant were a party to them in place of the
Consultant.
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12.2
LE1/SF1
HOME
GACC
EDITION 2: FEB 1998
4. The Authority shall pay the Consultant all amountsdue under the Commission for
work carried out satisfactorily by the Consultant before the date hereof.
5. All work carried out under the Commission by the Consultant and all paymentsmade
under the Commission by the Authority to the Consultant shall be treated respectively
aswork done by the Substituted Consultant and paymentsmade by the Authority to
the Substituted Consultant.
Signed by ..............................................................................................
Name .....................................................................................................
O n behalf of the Consultant.
Signed by ..............................................................................................
Name .....................................................................................................
O n behalf of the Substituted Consultant.
Signed by ..............................................................................................
Name .....................................................................................................
O n behalf of the Authority.
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 1
EXAMPLE NOVATION AGREEMENT (SCOTLAND)
NO VATIO N AGREEMENT
among
[ ] ( the Consultant) of the first part
[ ] ( the Substituted Consultant) of the second part
and
THE SCO TTISH MINISTERS acting through [Department] ( the Authority) of the third
part.
WHEREAS
1. ThisAgreement issupplemental to the following Commission ( herein called the
Commission) between the Consultant and the Authority.
Commission: ..........................................................................................
[Department] Reference No. ....................................................................
Consultant Reference No. ........................................................................
Asset out in [the correspondence]/[an agreement] between the Authority and the
Consultant dated
[.................................................................................................].
2. The Consultant desiresto be released and discharged from the Commission and the
Authority hasagreed to release and discharge them on condition that the Substituted
Consultant undertakesto assume the obligationsof the Consultant under the
Commission and to perform and be bound by the Commission.
3. The Substituted Consultant hasagreed to assume the obligationsof the Consultant
under the Commission.
NO W THEREFO RE the partieshereto AGREE asfollows:
1. The Substituted Consultant acceptsthe liabilities, rightsand obligationsof the
Consultant under the Commission and undertakesto perform the Commission and all
the dutiesand to discharge all the obligationsof the Consultant under it and to be
bound by the termsof the Commission asif they were party to them in place of the
Consultant, and that with effect from [ ] ( the Effective Date) .
LE1/SF1
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12.2(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
2. With effect from the Effective Date, the Consultant assignsitswhole rights, obligationsand
liabilitiesunder the Commission to the Substituted Consultant.
3. With effect from the Effective Date, the Authority releasesand dischargesthe Consultant
from further performance of the Consultantsobligationsunder the Commission and from all
claimsand demandswhatsoever in respect of the Commission and agreesto be bound by the
termsof the Commission asif the Substituted Consultant were a party to them in place of
the Consultant.
4. The Authority shall pay the Consultant at the Effective Date all amountsdue under the
Commission for work carried out satisfactorily by the Consultant before the Effective date.
5. All work carried out under the Commission by the Consultant and all paymentsmade under
the Commission by the Authority to the Consultant shall be treated respectively aswork
done by the Substituted Consultant and paymentsmade by the Authority to the Substituted
Consultant.
6. ThisAgreement shall be governed by, and construed in accordance with, the law of Scotland
and the partiesprorogate the jurisdiction of the Scottish courtsso far asnot already subject
thereto: IN WITNESS WHEREO F these presentsconsisting of thisand the [insert no]
preceding page( s) [together with the Schedule annexed hereto] are executed asfollows:
for and on behalf of [insert name of consultant] (Consultant)
at .................... on .................... 200[ ] by:
........................................................ ( Directorssignature) .................................. ( Director/Co Secssignature)
........................................................ ( full name) ................................................. ( full name)
for and on behalf of [insert name of substituted consultant] (Substituted Consultant)
at .................... on .................... 200[ ] by:
........................................................ ( Directorssignature) .................................. ( Director/Co Secssignature)
........................................................ ( full name) ................................................. ( full name)
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12.3(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
The Scottish Ministers (Authority)
at .................... on .................... 200[ ] by:
........................................................ ( signature)
........................................................ ( full name)
........................................................ ( title)
in the presence of:
........................................................ ( signature of witness)
........................................................ ( full name)
........................................................ ( address)
NB. Need to ensure that in any formal agreement at least part of the text of the
agreement appearson the same page asthe signatures. Do not have the
signatureson a separate page from the foregoing text.
NOVATION
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.12.4(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.13 TRANSACTIONS WITH OUTSIDE BUSINESSES
General
Departmentsmay carry out transactionswith the following typesof
businessassociations:
Sole traders;
Partnerships;
Companies.
Each of the above type of association isconsidered in relation to
contractual capacity and liability.
Sole Traders
Sole trader isthe name given to a person who setsup in businessand
tradesin their own name. No formalitiesare required to set up asa
sole trader. The debtsof the businessare the liability of the sole trader
personally. There isno statutory requirement on the sole trader to
keep accountsin any particular form.
The contractual capacity of the trader will be determined by the
general rulesfor contractual capacity of the individual in the law of
contract.
The sole trader will be personally liable for breachesof contract
committed by employeesin the course of business.
Partnerships
A partnership isthe relationship between personscarrying on a
businessin common, with expressor implied agreement asto the
nature of the business, with a view to profit. The sharing of profit will
not, however, of itself create a partnership. No formalitiesare required
to form a partnership. The partnersjointly and severally have unlimited
personal liability for the firmsdebts.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
TRANSACTIONS WITH OUTSIDE BUSINESSES
LE 1.13.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Aswith sole traders, there isno limit on the contractual capacity of
partnersexcept the general rulesof contract law. Employeesof the
firm will be agentsof it when acting in the course of their employment
and the partnerswill be liable for their acts.
The partnership isa legal person distinct from the partnersof whom it
iscomposed and may therefore sue or be sued in the firmsown name.
Companies
The term company isusually used to mean a corporation created by
registration under the CompaniesAct 1985. O n formation, a company
becomesa legal person separate and distinct from itsmembers. A
number of documentsmust be filed with the Registrar of Companies
before a company may commence trading, including the Memorandum
of Association which setsout the purpose for which the company is
formed and limitsthe scope of itscontractual capacity.
The most important effect of registration isthat the membersof the
company ( shareholders) are not liable for the debtsof the company
and their liability to contribute to the companysassets, to enable it to
pay itscreditors, may be limited by share or by guarantee.
The company asa separate legal entity can contract in itsown name,
with limitson itscapacity asfollows:
it hasno capacity before incorporation and any person purporting
to act on itsbehalf before thisdate will be personally liable on the
contract;
any contract not authorised by the objectsclause isultra viresand
void, although the scope of thislimitation isnarrowed considerably
by Sections35, 35A and 35B of the CompaniesAct 1985 ( as
amended by the CompaniesAct 1989) . The effect of these
provisionsisthat the companysconstitution cannot limit or call into
question, the validity of a transaction or act, unlessthe person
dealing with the company actsin bad faith. That person isnot bound
to enquire asto whether that act or transaction ispermitted by the
companysmemorandum, or asto any limitation on the powersof
the board of directorsto bind the company or authorise othersto
do so.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
TRANSACTIONS WITH OUTSIDE BUSINESSES
LE 1.13.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Key Points
Departmentsshould be aware, when procuring works, asto the
type of businessassociation with which it isproposed to enter into
a contract.
Departmentsshould consider when procuring works, whether the
person with whom the transaction isbeing discussed, hasauthority
to bind that association in contract with that Department. Ensure
that documentsare signed correctly by that association according to
itstype in order that contractsare valid and binding. If in doubt asto
how to have a document executed, or whether an outside body has
executed it correctly, Departmentsshould contact their legal adviser.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
TRANSACTIONS WITH OUTSIDE BUSINESSES
LE 1.13.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.14 PARENT COMPANY GUARANTEES
Guarantees - Generally
There are two typesof guarantee:
parent company guarantee;
performance bond.
Both are mechanismsdesigned to provide some extra-contractual
protection to the Department generally in respect of works
contractors.
Where the Department doesmake it a requirement for a tenderer to
provide a guarantee or bond then thisrequirement must be clearly
stated in the tender documentsso that the tenderer hasnotice of the
requirement and isable to price for it.
Parent Company Guarantees
Thisform of guarantee isgiven by a parent company or holding
company to guarantee the proper performance of a contract by one of
itssubsidiaries( the contractor) . The guarantee may require that the
parent company completesthe obligationsof the subsidiary in the
event of default by the subsidiary. The liability of the parent company
can take several formsincluding a financial guarantee of completion of
the project itself or the employment of another contractor to complete
the project.
A parent company guarantee will only be of value if the parent
company itself isfinancially strong and itsfinancial resourcesare largely
independent of those of the contractor. These mattersshould be
generally scrutinised in the overall vetting of the contractor by the
Department. In addition the form of wording of any parent company
guarantee isusually complicated and legal advice should be sought.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.15

I
! !! !!
I
! !! !!
LE 1.14.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Examplesof English and Scottish financial parent company guarantees
follow thissection. They are:
individual guarantee - ( standard form LE1/SF2) for one-off
appointmentsor where a blanket guarantee hasnot already been
obtained;
blanket guarantee - ( standard form LE1/SF3) for all contracts
awarded to that tenderer.
Ideally a blanket guarantee should be sought and a Departmental
register kept of those companiesfrom whom such guaranteeshave
been obtained.
Key Points
A parent company guarantee will not normally have a cost
implication for the tenderer nor therefore the Department.
Where there isa parent company or ultimate holding company it is
recommended that a parent company guarantee issought asa
matter of course.
The requirement for a guarantee should be stated in the tender
documentsand made a condition of acceptance of the tender.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 2
INDIVIDUAL GUARANTEE (100%) - DRAFT AGREEMENT
THIS AGREEMENT ismade the ....................... day of ............................. O ne Thousand Nine
Hundred and Ninety ............................. BETWEEN ...............................................................................PLC/LTD
whose registered office issituated at ............................................................................... ( hereinafter called
the Guarantor) of the one part and the Secretary of State for [asappropriate] acting
through [Department] whose office isat
..............................
...................................................................................................................
( hereinafter called the Employer) of the other part.
WHEREAS
A. .............................................................................................. PLC/LTD ( hereinafter called the
Contractor) hassubmitted a tender dated ............ offering to carry out certain workson
the .............................................. to the Employer.
B. The Guarantor hasagreed in the event of the Contractorstender being accepted, to
guarantee the due performance by the Contractor of such works( hereinafter called
the Contract) in manner hereinafter appearing:
NO W THE GUARANTO R AGREES WITH THE EMPLOYER asfollows:
1) If the Contractor ( unlessrelieved from the performance by any clause of the Contract
or by statute or by the decision of a tribunal of competent jurisdiction) shall in any
respect fail to execute the Contract or commit any breach of itsobligationsthereunder
then the Guarantor will pay to the Employer and itssuccessorsthe amount of all losses,
damages, costsand expenseswhich may be incurred by the Employer by reason of any
default on the part of the Contractor in performing and observing the agreementsand
provisionscontained in the Contract to the extent that such losses, damages, costsand
expensesare or would otherwise be recoverable by the Employer.
2) THE Guarantor FURTHER AGREES with the Employer that it shall not in any way be
released from liability hereunder by any alteration in the termsof the contract made by
agreement between the Employer and the Contractor or in the extent or nature of the
worksto be constructed, completed and maintained thereunder or by any allowance of
time or forbearance or forgivenessin or in respect of any matter or thing concerning
the Contract or by any other matter or thing whereby ( in the absence of thispresent
provision) the Guarantor would or might be released from liability hereunder, and for
the purposesof thisAgreement any such alteration shall be deemed to have been
made with the consent of the Guarantor and Clause 1 hereof shall apply in respect of
the contract so altered.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE1/SF2
LE 1.14.3
HOME
GACC
EDITION 2: FEB 1998
IN WITNESS of which the Guarantor hasexecuted thisAgreement asa deed and has
delivered it on the day and year first before written.
THE CO MMO N SEAL O F ........................................................... PLC/LTD wasaffixed to thisdeed in
the presence of:
.........................................................................................................
Director
.........................................................................................................
Director/Secretary
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.4
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 3
BLANKET GUARANTEE
THIS AGREEMENT ismade the ......................... day of ........................... O ne Thousand Nine
Hundred and Ninety ............................. BETWEEN ................................................................................PLC/LTD
whose registered office issituated at ............................................................................... ( hereinafter called
the Guarantor) of the one part and the Secretary of State for [asappropriate] whose
office isat ....................................................................................................................................... ( hereinafter called
the Employer) of the other part.
WHEREAS
A. Tendersfor certain work may from time to time be invited by the Employer or by
[Department] acting asitsagents( hereinafter called Agents) and
............................................................................ PLC/LTD ( hereinafter called the Contractor) may
submit such tendersto the Employer or asthe case may be itsAgents.
B. The Guarantor hasagreed in respect of each such tender accepted by the Employer or
one of itsAgents( hereinafter called the relevant Agent) ( such accepted tendersbeing
hereinafter individually called the relevant Contract) to guarantee the due
performance by the Contractor of the Contract in manner hereinafter appearing:
NO W THE GUARANTO R HEREBY AGREES WITH THE EMPLO YER asfollows:
1) If the Contractor ( unlessrelieved from the performance by any clause of the relevant
contract or by statute or by the decision of a tribunal of competent jurisdiction) shall in
any respect fail to execute the relevant Contract or shall commit any breach of its
obligationsthereunder then the Guarantor will pay to the Employer and itssuccessors
the amount of all lossesdamagescostsand expenseswhich may be incurred by the
Employer by reason of any default on the part of the Contractor in performing and
observing the agreementsand provisionscontained in the relevant Contract to the
extent that such lossesdamagescostsand expensesare or would otherwise be
recoverable by the Employer or the relevant Agent from the Contractor under the
relevant Contract.
2) THE Guarantor FURTHER AGREES with the Employer that it shall not in any way be
released from liability hereunder by any alteration in the termsof the relevant Contract
made by agreement between the Employer or the relevant Agent and the Contractor
or in the extent or nature of the worksto be constructed completed and maintained
thereunder or by any allowance of time or forbearance or forgivenessin or in respect
of any matter or thing concerning the relevant Contract or by any other matter or thing
whereby ( in the absence of thispresent provision) the Guarantor would or might be
released from liability hereunder.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE1/SF3
LE 1.14.5
HOME
GACC
EDITION 2: FEB 1998
AS WITNESS of which the Guarantor hasexecuted thisAgreement asa deed and has
delivered it on the day and year first before written.
THE CO MMO N SEAL O F ................................................................ PLC/LTD )
)
wasaffixed by order of their Board in )
the Presence of: )
..........................................................................................................................................................
Director
..........................................................................................................................................................
Director/Secretary
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.6
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 2
INDIVIDUAL GUARANTEE (100%) - DRAFT AGREEMENT (SCOTLAND)
GUARANTEE AND UNDERTAKING
by
[ ] PLC/LTD, having their registered office at [ ]
( the Guarantor) of the one part
in favour of
THE SCO TTISH MINISTERS acting through [Department] ( the Employer) of the other
part
WHEREAS
A. .............................................................................................. PLC/LTD ( hereinafter called the Contractor)
hassubmitted a tender dated ............ offering to carry out certain workson the
.............................................. to the Employer.
B. The Guarantor hasagreed in the event of the Contractorstender being accepted, to
guarantee the due performance by the Contractor of such works( hereinafter called
the Contract) in manner hereinafter appearing:
NO W THEREFO RE THE GUARANTO R UNDERTAKES TO THE EMPLO YER asfollows:
1) If the Contractor ( unlessrelieved from the performance by any clause of the Contract
or by statute or by the decision of a tribunal of competent jurisdiction) shall in any
respect fail to execute the Contract or commit any breach of itsobligationsthereunder
then the Guarantor will pay to the Employer and itssuccessorsthe amount of all losses,
damages, costsand expenseswhich may be incurred by the Employer by reason of any
default on the part of the Contractor in performing and observing the agreementsand
provisionscontained in the Contract to the extent that such losses, damages, costsand
expensesare or would otherwise be recoverable by the Employer.
2) That the Guarantor shall not in any way be released from liability hereunder by any
alteration in the termsof the Contract or in the extent or nature of the worksto be
constructed, completed and maintained thereunder or by any allowance of time or
forbearance or forgivenessin or in respect of any matter or thing concerning the
Contract or by any other matter or thing whereby ( in the absence of thispresent
provision) the Guarantor would or might be released from liability hereunder, and for
the purposesof thisGuarantee and Undertaking any such alteration shall be deemed to
have been made with the consent of the Guarantor and Clause 1 hereof shall apply in
respect of the Contract so altered.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.3(S)
LE1/SF2
HOME
GACC
EDITION 2 REV 2: JAN 2000
3) ThisGuarantee and Undertaking shall be governed by and construed in accordance
with the law of Scotland and the partieshereto prorogate the jurisdiction of the
Scottish courtsso far asnot already subject thereto: IN WITNESS WHEREO F this
Guarantee and Undertaking consisting of thispage and the [ ] preceding page( s) is
executed on behalf of the Company asfollows:
......................................................................................... .........................................................................................
Director Director/Secretary
......................................................................................... .........................................................................................
Name in Capitals Name in Capitals
......................................................................................... .........................................................................................
Place of Signature Place of Signature
......................................................................................... .........................................................................................
Date of Signature Date of Signature
NB. Need to ensure that in any formal agreement at least part of the text of the
agreement appearson the same page asthe signatures. Do not have the
signatureson a separate page from the foregoing text.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.4(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 3
BLANKET GUARANTEE (SCOTLAND)
GUARANTEE AND UNDERTAKING
by
[ ] having itsregistered office at [ ] ( the
Guarantor) of the first part
in favour of
THE SCO TTISH MINISTERS acting through [Department] ( the Employer) of the second
part.
WHEREAS
A. Tendersfor certain work may from time to time be invited by the Employer and
............................................................................ PLC/LTD ( hereinafter called the Contractor) may
submit such tendersto the Employer.
B. The Guarantor hasagreed in respect of each such tender accepted by the Employer
( such accepted tendersbeing hereinafter individually called the relevant Contract) to
guarantee the due performance by the Contractor of the Contract in manner
hereinafter appearing:
NO W THEREFO RE THE GUARANTO R HEREBY UNDERTAKES TO THE EMPLO YER as
follows:
1) If the Contractor ( unlessrelieved from the performance by any clause of the relevant
contract or by statute or by the decision of a tribunal of competent jurisdiction) shall in
any respect fail to execute the relevant Contract or shall commit any breach of its
obligationsthereunder then the Guarantor will pay to the Employer and itssuccessors
the amount of all lossesdamagescostsand expenseswhich may be incurred by the
Employer by reason of any default on the part of the Contractor in performing and
observing the agreementsand provisionscontained in the relevant Contract to the
extent that such lossesdamagescostsand expensesare or would otherwise be
recoverable by the Employer from the Contractor under the relevant Contract.
2) That the Guarantor shall not in any way be released from liability hereunder by any
alteration in the termsof the relevant Contract made by agreement between the
Employer and the Contractor or in the extent or nature of the worksto be
constructed completed and maintained thereunder or by any allowance of time or
forbearance or forgivenessin or in respect of any matter or thing concerning the
relevant Contract or by any other matter or thing whereby ( in the absence of this
present provision) the Guarantor would or might be released from liability hereunder.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE1/SF3
LE 1.14.5(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
3) ThisGuarantee and Undertaking shall be governed by and construed in accordance
with the law of Scotland and the partieshereto prorogate the jurisdiction of the
Scottish courtsso far asnot already subject thereto: IN WITNESS WHEREO F this
Guarantee and Undertaking consisting of thispage and the [ ] preceding page( s) is
executed on behalf of the Company asfollows:
......................................................................................... .........................................................................................
Director Director/Secretary
......................................................................................... .........................................................................................
Name in Capitals Name in Capitals
......................................................................................... .........................................................................................
Place of Signature Place of Signature
......................................................................................... .........................................................................................
Date of Signature Date of Signature
NB. Need to ensure that in any formal agreement at least part of the text of the
agreement appearson the same page asthe signatures. Do not have the
signatureson a separate page from the foregoing text.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PARENT COMPANY GUARANTEES
LE 1.14.6(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.15 PERFORMANCE BONDS
A bond isa legally enforceable financial guarantee given by a third party
( the guarantor) to a purchaser ( the Department) to guarantee the
obligationsof a supplier of goods, worksor services( the contractor)
under a contract. The guarantor agreesto pay the Department a sum
of money ( usually expressed as10% of the contract sum) if the
contractor defaultson itsobligations. The purpose of requiring a bond
isto allow the Department to offset the extra expensesof remedying
the default and/or completing the contract.
It isnot common practice for a Department to require a bond. The
decision to obtain one from a tenderer will normally be a high level
Departmental decision. A bond may be required if:
there isno parent company or holding company and the value of
the contract isa significant proportion of the companysturnover;
the company appearsfinancially weak and there isa risk of its
collapse.
O btaining a bond cannot serve asa substitute for thorough scrutiny of
contractorsfinancial standing and assessment of the contractorsability
to meet the termsand conditionsof the contract satisfactorily. Any
reasonable doubtsshould be followed through, since a contractor with
inadequate financial resourcesmay present a consequent risk to
exchequer funds. A decision to require a bond must be part of an
overall approach to risk management and should take account of
available measuresto reduce the risk of default, including a proper pre-
qualification of tenderers.
The wording of commercial bondscan vary depending on which
organisation isproviding the bond, who isinvolved in drawing it up, and
what the bond isexpected to deliver. The courtshave recently been
very critical of bondscontaining archaic language and termsfound in
traditional standard formsprovided by banksor surety companies.
Legal advisersshould alwaysbe involved in their preparation and
negotiation. A model form of bond waspublished in September 1995
by the Association of British Insurersto addressthe criticismsof
standard form bonds.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PERFORMANCE BONDS
L
! !! !!
LE 1.15.1
HOME
GACC
EDITION 2: FEB 1998
Characteristics of Performance Bonds
Performance bondsshould generally have an expiry date and should
contain a mechanism for amendment in the event that the value of the
contract increasesor the duration of the contract extends.
Classification of Performance Bonds
There are two basic formsof performance bond, the conditional
on-defauIt bond and the much more onerousconditional
on-denand bond.
Conditional On-Default Performance Bonds
Usually these can be called only following a seriousbreach by the
contractor of the agreed termsand conditionsof the contract ( which
will include the contractor going into liquidation/receivership or
becoming bankrupt) . Departmentsshould seek legal advice that the
wording clearly expressesthe true transaction and not assume that a
traditional form of wording will be appropriate.
Conditional On-Demand Bonds
Thisisan onerousform of bond which isnot normally used by
Departments. Although thisbond in essence isone that can technically
be called at any time on-demand, it should contain:
a procedural mechanism for calling the bond;
a requirement for the Department to identify the reason for calling
the bond; and
a cooling off period ( during which the contractor may remedy the
default) .
The place for use of such bondsiswhere the costsor other
consequencesof default by the contractor are very high and there isa
need for payment without risk of dispute. Thisbeing said, the
imposition of conditionsshould prevent the Department from acting in
an arbitrary or unreasonable way and protect the contractor from the
bond being called without the due and proper consideration of
responsible people in the Departmentsorganisation.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PERFORMANCE BONDS
L
! !! !!
LE 1.15.2
HOME
GACC
EDITION 2: FEB 1998
Requirement for both Performance Bonds and Parent Company
Guarantees
It will not normally be desirable or necessary for a contractor to
provide both performance bondsand parent company guarantees,
particularly when the cost of obtaining a performance bond will be
passed on to the Department. A decision asto which form of
protection isrequired must be taken aspart of an overall approach to
risk management.
Key Points
The requirement for a bond will be an exception rather than the
norm, and will normally require a high level Departmental decision.
A bond will have a cost implication for the tenderer and therefore
for the Department. The Department should be satisfied that this
additional protection isnecessary and worth paying for.
When the decision istaken to request a bond, legal advice should
be sought to ensure that a suitable form of bond isobtained.
The requirement for a bond should be stated in the tender
documentsand the contract should not be formally awarded to the
successful tenderer until the bond hasbeen secured and provided
to the Department.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
PERFORMANCE BONDS
LE 1.15.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.16 STAMP DUTY
Principally by virtue of Section 55 of the Finance Act 1987 no stamp
duty ischargeable on any conveyance, transfer or lease, made or agreed
to be made to a Minister of the Crown or the Scottish Ministers.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
STAMP DUTY
LE 1.16
HOME
GACC
EDITION 2: FEB 1998
LE 1.17 PROCEEDINGS INSTITUTED AGAINST DEPARTMENTS
Civil legal proceedingsagainst the Crown are instituted in accordance
with the Crown ProceedingsAct 1947.
The Act specifiesthat proceedingsshould be instituted against the
appropriate authorised Department. The list published under Section
17 of the Act specifiesthe variousDepartmentswhich are authorised
to receive proceedingsfor the purposesof the Act and the name and
addressfor service of the person who isto be treated asthe solicitor
for each such Department. While most Departmentsare represented
bythe Treasury Solicitor, there are Departmentswhich have their own
legal advisersacting for them. Further, there are a number of public
bodieswho have market tested the provision of legal servicesand put
the work out to the private sector: in such cases, proceedingsshould
be served on their private sector solicitors.
Proceedingsmay also be instituted against the Attorney General.
Key Points
Proceedingsshould be served on the solicitor retained to represent
the Department. Thiswill be the Treasury solicitor unlessa private
sector legal adviser hasbeen engaged.
Crown Departmentsmay not sue other Crown Departments.
PROCEEDINGS INSTITUTED AGAINST DEPARTMENTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.17
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.17(SCOT) PROCEEDINGS INSTITUTED AGAINST DEPARTMENTS
Civil legal proceedingsagainst the Crown ( either in right of Her
MajestysGovernment in the United Kingdom or in right of the Scottish
Administration) are instituted in accordance with the Crown
ProceedingsAct 1947.
The Act specifiesthat proceedingsshould be instituted against the
appropriate authorised Department. The list published under Section
17 of the Act specifiesthe variousDepartmentswhich are authorised
to receive proceedingsfor the purposesof the Act and the name and
addressfor service of the person who isto be treated asthe solicitor
for each such Department. While most devolved function Departments
are represented by the Solicitor to the Scottish Executive, there are
Departmentswhich have their own legal advisersacting for them.
Reserved function Departmentsmay also be represented by the
Solicitor to the Scottish Executive acting on an agency basis, or by the
Solicitor to the Advocate General, or again by their own legal advisers
acting for them. Further, there are a number of public bodieswho have
market tested the provision of legal servicesand put the work out to
the private sector: in such cases, proceedingsshould be served on their
private sector solicitors.
Proceedingsmay also be instituted in Scotland against the Lord
Advocate ( where the action, suit or proceeding ison behalf of or
against any part of the Scottish Administration) , and the Advocate
General for Scotland ( in any other case) .
Key Points
Proceedingsshould be served on the solicitor retained to represent
the Department. Thiswill normally be the Solicitor to the Scottish
Executive unlessa private sector legal adviser hasbeen engaged or
the Solicitor to the Advocate General isacting.
Ministersof the Crown may not sue other Ministersof the Crown.
Since 1 July 1999 however, rightsand liabilitiesmay arise between
the Crown in right of Her MajestysGovernment in the United
Kingdom and the Crown in right of the Scottish Administration by
virtue of a contract, by operation of law or by virtue of an
enactment asthey may arise between subjects. The Scottish
Ministersmay therefore sue, and be sued by, Ministersof the Crown.
Notwithstanding this, every attempt should be made by
Departmentsto resolve disputeswithout recourse to court
proceedings.
PROCEEDINGS INSTITUTED AGAINST DEPARTMENTS
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LE 1.17(S)
HOME
GACC
EDITION 2: FEB 1998
LE 1.18 INSOLVENCY AND BANKRUPTCY
Insolvency isa legal term which coversthe financial failure of
individualsand companiesand their position before and after the start
of a formal insolvency procedure. Insolvency may be experienced in the
short term or long term. Short term insolvency usually meansa cash
flow crisiswhere insufficient money iscoming in to meet the companys
outgoings. Long term insolvency relatesto the situation where liabilities
exceed assetseven though the company may be able to meet its
outgoings. In accordance with the Insolvency Act 1986 if a company
failseither the going concern test or the balance sheet test then it
will be insolvent.
General
In situationswhere individuals, partnershipsor companiesrun into
financial crisesthere are formal proceduresfor dealing with the
situation. The proceduresare different for individualsand companies;
bankruptcy for example only appliesto individuals. The proceduresare
asfollows:
For an individual:
deed of arrangement whereby the debtor may agree with creditors
asto how debtswill be paid;
administration order in the county court;
voluntary arrangementswhereby the insolvent debtor hasan
agreement with creditors, approved by a proportion of creditors, to
an arrangement for repayment supervised by a qualified insolvency
practitioner;
bankruptcy asa result of creditors or debtors petition.
For a partnership:
winding up the insolvent partnership asan unregistered company;
winding up the partnership asabove and petitioning for the
bankruptcy of two or more insolvent partners;
insolvency proceedingsagainst some but not all of the partners;
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.18.1
HOME
GACC
EDITION 2: FEB 1998
For companies:
receivership, whereby a receiver isappointed by a debenture holder
( usually a bank) to take control of the assetssubject to the charge;
the administrative receiver may be invested with wide power to
carry on the businessto trade the company out of financial crisesor
to hive the company down;
appointment by the court of an administrator who hassimilar
powersto an administrative receiver; the role of the administrator is
principally to trade the company out of itsdifficulties;
voluntary arrangements, little used and complex arrangement;
liquidation, which can be voluntary or compulsory; either way the
liquidator isappointed to realise the assetsand pay off debts.
Departmental Procedures
Upon being notified of the insolvency of a workscontractor it is
recommended that the following procedure should be adopted ( many
of the stepswill be the same for any type of commission) :
arrange to have the site secured cost effectively, to prevent
vandalism and unauthorised removal of any materials;
establish the type of insolvency ( since not all proceduresresult in
the liquidation and cessation of trading by the company) ;
inform the lead consultant and any other professionalsinvolved in
the project;
consider obtaining legal advice;
clearly record ( preferably with photographs) the state of the work
at the date of insolvency; and
with the assistance of the lead consultant or an appointed Q S,
establish the value of worksexecuted at the time of insolvency
including all materialson and off site;
instruct the lead consultant to negotiate with the contractor to
establish whether the contractor will be able to continue with the
works. If the contractor can, arrange accessto the site for the main
and sub-contractors;
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.18.2
HOME
GACC
EDITION 2: FEB 1998
establish the position regarding unpaid certificates, retention,
performance bondsand other contractual arrangements;
establish the position regarding claimsin title of materialson and off
site. Thisisa very important point and must not be overlooked;
establish a programme for completion;
establish the estimated cost for completion;
liaise with the insolvency practitioner, arrange meetingsas
appropriate;
establish the next step and way forward, with critical dates, to
achieve the satisfactory financial, contractual, chronological and
physical conclusion of the project.
Options for Completion
There are essentially three optionsavailable for the completion of the
project:
novation;
completion by the insolvent contractor; or
completion by another contractor.
Key Points
In situationswhere a contractor or consultant failsand the
liquidator or receiver decidesnot to proceed with the contract, any
case of dispute over ownership of goodsresulting from the use of
retention clausesshould be referred immediately for legal advice.
Any attemptsby a supplier of the main contractor to remove goods
should be discouraged.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.12

LE 1.19

L
! !! !!
LE 1.18.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.18(SCOT) INSOLVENCY AND BANKRUPTCY
Insolvency isa legal term which coversthe financial failure of
individualsand companiesand their position before and after the start
of a formal insolvency procedure. Insolvency may be experienced in the
short term or long term. Short term insolvency usually meansa cash
flow crisiswhere insufficient money iscoming in to meet the companys
outgoings. Long term insolvency relatesto the situation where liabilities
exceed assetseven though the company may be able to meet its
outgoings. In accordance with the Insolvency Act 1986 if a company
failseither the going concern test or the balance sheet test then it
will be insolvent.
General
In situationswhere individuals, partnershipsor companiesrun into
financial crisesthere are formal proceduresfor dealing with the
situation. The proceduresare different for individualsand companies;
bankruptcy for example only appliesto individuals. The proceduresare
asfollows:
For an individual or partnership:
deed of arrangement whereby the debtor may agree with creditors
asto how debtswill be paid;
voluntary arrangementswhereby the insolvent debtor hasan
agreement with creditors, approved by a proportion of creditors, to
an arrangement for repayment supervised by a qualified insolvency
practitioner;
bankruptcy asa result of creditors or debtors petition.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.18.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
For companies:
receivership, whereby a receiver isappointed by a floating charge
holder ( usually a bank) to take control of the assetssubject to the
charge; the receiver may be invested with wide power to carry on
the businessto trade the company out of financial crisesor to hive
the company down;
appointment by the court of an administrator who hassimilar
powersto a receiver; the role of the administrator isprincipally to
trade the company out of itsdifficulties;
voluntary arrangements, little used and complex arrangement;
liquidation, which can be voluntary or compulsory; either way the
liquidator isappointed to realise the assetsand pay off debts.
Departmental Procedures
Upon being notified of the insolvency of a workscontractor it is
recommended that the following procedure should be adopted ( many
of the stepswill be the same for any type of commission) :
arrange to have the site secured cost effectively, to prevent
vandalism and unauthorised removal of any materials;
establish the type of insolvency ( since not all proceduresresult in
the liquidation and cessation of trading by the company) ;
inform the lead consultant and any other professionalsinvolved in
the project;
consider obtaining legal advice;
clearly record ( preferably with photographs) the state of the work
at the date of insolvency; and
with the assistance of the lead consultant or an appointed Q S,
establish the value of worksexecuted at the time of insolvency
including all materialson and off site;
instruct the lead consultant to negotiate with the contractor to
establish whether the contractor will be able to continue with the
works. If the contractor can, arrange accessto the site for the main
and sub-contractors;
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.18.2(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
establish the position regarding unpaid certificates, retention,
performance bondsand other contractual arrangements;
establish the position regarding claimsin title of materialson and off
site. Thisisa very important point and must not be overlooked;
establish a programme for completion;
establish the estimated cost for completion;
liaise with the insolvency practitioner, arrange meetingsas
appropriate;
establish the next step and way forward, with critical dates, to
achieve the satisfactory financial, contractual, chronological and
physical conclusion of the project.
Options for Completion
There are essentially three optionsavailable for the completion of the
project:
assignation or novation;
completion by the insolvent contractor; or
completion by another contractor.
Key Points
In situationswhere a contractor or consultant failsand the
liquidator or receiver decidesnot to proceed with the contract, any
case of dispute over ownership of goodsresulting from the use of
retention clausesshould be referred immediately for legal advice.
Any attemptsby a supplier of the main contractor to remove goods
should be discouraged.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
INSOLVENCY AND BANKRUPTCY
LE 1.18.3(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.19 RESERVATION OF TITLE
The subject of title to materialsand goodsdelivered to construction
sitesand intended for their incorporation into the Worksisa complex
area of the law. In general termsthere are two sidesto the problem:
Suppliersof work and construction goodsoften seek to retain title
in their productsuntil they receive proper payment for them, at
which time title passes. Thisisdone by meansof a retention of title
clause in the conditionsof supply such asthat which formed the
subject of the case of AluminiumIndustrie Vaasen BV -v- Romalpa
AluminiumLtd. The Romalpa clause washeld to be effective even
though goodshad been mixed in with other goodsafter delivery,
forming other products.
The Department doesnot want to be in the position of having paid
the contractor or nominated sub-contractorsfor materialsstored
on or off-site if the contractor doesnot have title to them. If it does
so and the contractor goesinto liquidation then the supplier might
be able to recover materialsor goodsfor which the Department
haspaid, and the Department may end up paying for them twice.
It isa general common law principle that once materials( moveable
property) have been permanently fixed to the heritage ( immoveable or
fixed property) they become part of the ground ( title thuspassing to
the Department) . Although thisprinciple might limit the Departments
risk to only unfixed materialsit may neverthelessbe possible for a sub-
contractor to have an effective retention of title clause which also gives
the supplier a right of accessto the property in the event of non-
payment.
The general rule with regard to title isexpressed by the legal maxim
nemo dat quod non habet, which meansthat a party cannot passtitle
to another party if it doesnot itself have title.
Clause 30 of GC/Works1/( 1998) providesthat all goodsand materials
intended for incorporation into the worksand all goodsand materials
necessary to facilitate their incorporation into the worksshall become
the property of and vest in the authority. Thisdoesnot make provision
for situationswhere sub-contractorsor suppliersare using retention of
title clauses.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
RESERVATION OF TITLE
LE 1.19.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
However, paymentsmade in accordance with clause 48 ( Alternative A)
of GC/Works/1 ( 1998) are on the basisof stage paymentsfor work
completed to the satisfaction of the Project Manager. There are no
specific provisionsfor the payment for materialson or off-site. In theory
stage paymentsare only in respect of workmanship and materialsfixed
to the site, thusprotecting the Department asfar aspossible from
retention of title clauses.
Where materialson site are to be included in an interim payment then
it isrecommended that the Department ensuresthat the contractor
hasgood title to any such materials.
Payment for Materials Stored Off-Site
O ccasionally, a Department may receive a request for advanced
payment for materialsstored off-site. It isrecommended that such a
request isresisted. The contractor already hasa liability to finance off-
site activitiesunlesscaused by delay on the part of the Department.
It may exceptionally be appropriate to pay for materialsoff-site if:
there will be some real financial benefit to the Department, for
example steel or mechanical plant may be given over to another
contractor unlesspayment issecured in advance, thusavoiding
remanufacturing delay for example;
the contractor or sub-contractor can demonstrate good title;
the materialsare secure and protected from damage and bad
weather;
the goodsare clearly marked asthe property of the Department.
Note however that payment for materialsmust only be against a
specific legal agreement. If by reason of the nature of the work carried
out by a Department, paymentsfor materialsoff-site are necessary
then the Department should consider commissioning the redraft of
these conditionsto suit their specific requirements.
Key Points
Seek advice before considering any paymentsfor materialsheld off-
site.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
RESERVATION OF TITLE
I
! !! !!
I
! !! !!
LE 1.19.2
HOME
GACC
EDITION 2: FEB 1998
To provide additional protection in such situations, Departments
generally make use of an instrument called a WharfingersWarrant.
Thisisa warranty signed by the contractor or sub-contractor
depending on who isholding the materials, which confirmsthat the
contractor or sub-contractor hasgood title to the material and that,
upon payment, title of the listed materialshaspassed to the
Department. A WharfingersWarrant wasused in conjunction with the
following supplementary conditionsto GC/Works1/( Edition 2) :
207 - vesting of goodsand materialsnot on-site;
208 - advanceson account including goodsand materialsheld
off-site.
These conditionshave not been updated for use with GC/Works1/
( 1998) .
If by reason of the nature of the work carried out by a Department,
paymentsfor materialsoff-site are necessary then the Department
should consider commissioning the redrafting of these conditionsto
suit their specific requirements.
Key Points
Seek advice before considering any paymentsfor materialsheld off-
site.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
RESERVATION OF TITLE
LE 1.19.3
HOME
GACC
EDITION 2: FEB 1998
LE 1.20 UNFAIR CONTRACT TERMS ACT 1977
The Unfair Contract TermsAct 1977 reducesthe effectivenessof, or
nullifiessome contract termsand noticeswhich seek to exclude or limit
liability for negligence or breach of contract. It hasno significant
implicationsfor the unamended provisionsof standard conditionsof
contract such as, the GC/Works, JCT, ICE, forms.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
UNFAIR CONTRACT TERMS ACT 1977
LE 1.20
HOME
GACC
EDITION 2: FEB 1998
LE 1.21 LEGAL ADVICE
Responsibility for legal servicesto Departmentsin England and Walesis
divided between the Treasury Solicitor and the Legal Adviser/Solicitor
to the relevant Department. The Legal Adviser/Solicitor to the
Department will consult with the Treasury Solicitor asnecessary.
Furthermore, there are a number of public bodieswho have put the
provision of legal servicesout to the private sector following market
testing and it may be necessary to obtain advice from these private
sector solicitors.
Key Points
Refer to Departmental proceduresabout seeking legal advice.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LEGAL ADVICE
LE 1.21
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 1.21(SCOT) LEGAL ADVICE
Except asotherwise arranged, responsibility for the provision of legal
advice in Scotland restswith the O ffice of the Solicitor to the Scottish
Executive ( O SSE) for devolved functions. For reserved functions,
responsibility in Scotland restswith the O ffice of the Solicitor to the
Advocate General ( O SSAG) , although generally the larger O SSE will
act for O SSAG on an agency basisin contract, procurement and
intellectual property matters.
Where it hasbeen arranged that O SSE ( or O SSAG) do not represent
a particular public body, it may be necessary to obtain advice from the
solicitorsacting for thisbody. If in doubt, check first with O SSE.
Key Points
Refer to Departmental proceduresabout seeking legal advice.
LEGAL ENVIRONMENT
LEGAL FRAMEWORK
LEGAL ADVICE
LE 1.21(S)
HOME
GACC
EDITION 2: FEB 1998
LE 2.0 OTHER ISSUES
LE 2.1 HEALTH AND SAFETY (CDM)
The Health and Safety at Work etc. Act 1974 Part I makesprovision for
securing the health, safety and welfare of personsat work and for
protecting othersagainst risksto health or safety in connection with
the activitiesof personsat work. There are variousregulationsand
codesof practice ( some of which are enforceable under the Act)
covering aspectsof health, safety and welfare.
The principal dutiesimposed by Part I of the Act are:
( 1) O n the Employer ( i.e., the contractor) to ensure, so far asis
reasonably practicable the health and safety of the contractors
employeesand of other persons( i.e., supervisory officers, occupiers
or visitors) who may be affected by the way the contractor
conductsitsundertaking. While the Authority in the contract is
sometimesreferred to asthe employer of the contractor, its
function assuch isnot that of an employer within the termsof the
Act.
( 2) O n a Person ( i.e., agent, occupying department, contractor or sub-
contractor) who has, to any extent, control of premiseswhich are
made available asplace of work for personswho are not employees
( e.g., sub-contractors employees) , to take such measuresasare
reasonably practicable, to provide that the premisesand plant ( and
substances) thereon are safe and without risk to the health of such
persons.
O n 31 March 1995 the Construction ( Design and Management)
Regulations1994 ( CDM regulations) were introduced, in the form of
regulationsand an approved code of practice. The regulationswere
made under section 16( 1) of The Health and Safety at Work etc. Act
1974 and concern the management of health and safety on temporary
or mobile construction sites. O n 1 January 1996 the transitional
provisionscame to an end and all the regulationsnow apply to all
qualifying projects. The CDM regulationsplace specific dutiesupon
clients, designersand contractorsand are designed to bring about the
careful consideration and management of health and safety risks
throughout the construction processfrom inception through to
completion.
LEGAL ENVIRONMENT
OTHER ISSUES
HEALTH & SAFETY (CDM)
LE 2.1.1
HOME
GACC
EDITION 2: FEB 1998
The regulationsrelate to the carrying out of any building, civil
engineering or engineering construction work, which includes
redecoration, maintenance and demolition works. ( See Regulation 2 for
definition of construction work) .
The CDM regulationsdo not apply to projectsbeing carried out for
domestic clients.
The regulationswill not apply to non-domestic construction work if the
following conditionsapply.
the project isnot notifiable to the Health and Safety Executive
( HSE) ( i.e. the work isexpected to last lessthan 30 working days
( Approved Code of Practice condition 27) ) ; and
where the largest number of personsat work at any time isless
than 5.
The CDM regulationsapply to construction work which involvesthe
demolition or dismantling of a structure regardlessof duration or the
number of workersrequired.
The regulationstherefore apply to the majority of construction
projects.
Where the regulationsapply, the Department hasthe following
principal obligations:
to make a declaration to the HSE that the Department or agent
will act asclient for the purpose of the regulationsin respect of a
particular project ( Regulation 4) ;
to appoint a planning supervisor, ( Regulation 6) who will be
responsible for:
notifying the project to the HSE ( Regulation 7) ,
developing a health and safety plan for the design and planning
phase and prior to the commencement of work on site by the
contractor ( Regulation 15) ,
advising the Department on the satisfactory allocation or
resourcesfor health and safety ( Regulation 14) , and
preparing a health and safety file ( Regulation 14) ;
LEGAL ENVIRONMENT
OTHER ISSUES
HEALTH & SAFETY (CDM)
L
! !! !!
L
! !! !!
LE 2.1.2
HOME
GACC
EDITION 2: FEB 1998
to provide the planning supervisor with all information necessary for
him to carry out the planning supervisorsduties( Regulation 11) ;
to appoint a principal contractor, who isresponsible for developing
the health and safety plan which should be the basisof the health
and safety management of the construction phase ( Regulation 6) ;
to be reasonably satisfied that the planning supervisor, designersand
contractorsare competent to carry out their duties( Regulation 8) ;
to be reasonably satisfied that the planning supervisor, designersand
contractorshave allocated or will allocate sufficient resourcesto
deal with Health and Safety mattersin compliance with the CDM
regulations( Regulation 9) ;
to keep available for inspection the health and safety file once it has
been prepared ( Regulation 12) .
Key Points
The CDM regulationsplace statutory criminal and civil law
obligationson Departments. These must be complied with.
It isnot necessary for the planning supervisor to be a separate
professional from the designers, but arguably, benefitsmay derive
from having a third party with a different perspective.
In theory more practical and safer designscould result from a more
active management of health and safety riskswhich could also
benefit the client.
Read the CDM regulationsand Approved Code of Practice.
LEGAL ENVIRONMENT
OTHER ISSUES
HEALTH & SAFETY (CDM)
LE 2.1.3
HOME
GACC
EDITION 2: FEB 1998
LE 2.2 TRANSFER OF UNDERTAKINGS (TUPE)
Purpose of TUPE
The Transfer of Undertakings( Protection of Employment) Regulations
1981 asamended ( TUPE) are the regulationswhich brought about
the implementation in the UK of the 1977 EC Acquired Rights
Directive. The purpose of the Directive and therefore of TUPE isto
protect employeesrightson the change of the operator of a business
or undertaking. Thismay include the contracting out of services.
Thisisa difficult and developing area of law. The European Court of
Justice isthe main determinant asto whether the directive and
therefore TUPE appliesin a particular case.
Effect of TUPE Applying
Where TUPE appliesthen in caseswhere the employeescontract of
employment would otherwise come to an end on termination of the
employerscontract, the general principle isthat employees, their terms
and conditionsof employment, acquired rightssuch asaccumulated
holidays, bonusesand redundancy rightsare transferred from the
outgoing consultant or contractor ( the transferor) to the incoming
consultant or contractor ( the transferee) .
Determining Whether or Not TUPE Applies
Since TUPE wasintroduced in 1981, case law haswidened the
interpretation of itsprovisionsso asto include an increasing variety of
commercial situationsincluding:
contracting out ( outsourcing) ;
replacement of a service provider.
It isnot possible to give definite guidance on whether TUPE will apply
to a particular situation. Application will turn on all the circumstances
of a particular transaction.
LEGAL ENVIRONMENT
OTHER ISSUES
TRANSFER OF UNDERTAKINGS (TUPE)
LE 2.2.1
HOME
GACC
EDITION 2: FEB 1998
The test to be applied wasset out in the judgement in Spijkers -v-
Gebroeders Benedik Abattoir [1986] 2 CMLR 296 in which it wasstated:
The decisive criterion for establishing whether there is a transfer within
the meaning of the Directive is whether the business in question retains
its identity as would be indicated, in particular,by the fact that its
operation was continued or resumed ...
The factorsto be assessed in satisfying the test will include:
the type of businessor undertaking concerned;
whether or not tangible assetshave been transferred and the value
of such assets;
the value of intangible assetstransferred ( e.g. contracts, goodwill,
etc.) ;
whether or not the majority of employeesare taken over;
whether or not customersare transferred;
the degree of similarity between the pre and post transfer activities;
the duration of any period during which those activitiesare
suspended.
Situations Where TUPE is Likely/Unlikely to Apply
The following guidance hasbeen given in relation to the outsourcing of
works:
Unlikely to apply where:
the new employer conductsthe operation substantially differently;
the identity of the previousundertaking issubstantially changed or
restructured.
LEGAL ENVIRONMENT
OTHER ISSUES
TRANSFER OF UNDERTAKINGS (TUPE)
LE 2.2.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Likely to apply where:
the new employer employssubstantially the same staff;
key employeesare required to carry out the work;
the new employer takeson substantially the same employeesas
recognisably the same organisational unit;
there isan understanding between the partiesthat the new
employer will continue to use the same employeesfor the same
work;
in a change in the arrangementsfor property management and
maintenance contacts.
Restrictions on the Widening Scope of TUPE
The trend to widen the scope of application of TUPE in cases
interpreting itsapplication hasbeen reversed in the recent case of
Rygaard v Stro Molle Akustik A/S,C48/94 [1986] IRLR 51 ECJwhere the
European Court of Justice held:
In order to be a transfer of an undertaking,business or part of a
business within the meaning of Article 1(1) of EEC Directive 77/187,
the transfer must relate to a stable economic entity whose activity is not
limited to performing one specific works contract.That is not the case
where there is a transfer fromone undertaking to another of building
works with a view to their completion,and the transfer or undertaking
merely makes available to the new contractor certain workers and
material for carrying out the works in question.Such a transfer could
come within the terms of the Directive only if it included the transfer of
a body of assets enabling activities of the transferor undertaking to be
carried on in a stable way.
The Court in thisinstance did not consider that the transfer created
the necessary stability.
It isperhapstoo early to say whether the Rygaard case representsa
permanent reversal of the widening trend.
LEGAL ENVIRONMENT
OTHER ISSUES
TRANSFER OF UNDERTAKINGS (TUPE)
LE 2.2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
The Practical Effect of TUPE for Departments
The consequencesof TUPE applying are not likely to directly affect
the Department requiring performance of the service, since TUPE
providesthat responsibilitiesand obligationsin respect of employees
are either owed by the transferor ( the outgoing consultant or
contractor) or the transferee ( the incoming contractor) .
TUPE is, however, likely to indirectly affect Departmentsin the
following areas:
consideration of what reference if any should be made to the
application or otherwise of TUPE when inviting tenders; it may be
appropriate merely to include a notice in the tender document
warning potential biddersof the possible application of TUPE and
advising tenderersthat they should seek their own legal advice;
the Department asclient should take stepsto ensure that existing
contractorsco-operate in the provision of information in relation to
their employeesso that prospective bidderswill not be discouraged
for lack of information concerning the extent of any TUPE liability;
consideration should also be given to ensuring that any new
contractor isobliged to co-operate and supply information towards
the end of itscontract;
asa result of Regulationswhich came into force on 1 March 1996,
consultation must take place with trade unionsor elected
representativesof the affected employees.
Key Points
The matter of TUPE isa complex subject and each case must be
treated on itsmerits. It isessential that legal advice isobtained
before final action istaken in every case.
LEGAL ENVIRONMENT
OTHER ISSUES
TRANSFER OF UNDERTAKINGS (TUPE)
I
! !! !!
I
! !! !!
LE 2.2.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.3 RACIAL DISCRIMINATION
There isno direct legislation imposing upon Departmentsa duty to
stipulate compliance by contractorsand supplierswith the provisionsof
the Race RelationsAct 1976.
The standard conditionsof Government formsof contract do, however,
contain conditionsrequiring that the contractor or supplier shall not
unlawfully discriminate within the meaning and scope of the provisions
of the Race RelationsAct 1976 or any statutory modification or re-
enactment of it. See for example clause 23 of GC/Works1/( 1998) .
Government contractswere amended to incorporate thisprovision as
a result of a written answer given in parliament by Mr Roy Jenkinson
22 O ctober 1969 which reflected consideration of how Government
influence asa major purchaser of goodsand servicescould best be
used in the interestsof discouraging racial discrimination.
When inviting tendersspecific departmental proceduresshould be
consulted for selection criteria to be requested concerning findingsof
unlawful discrimination.
It isworthwhile noting that the Race RelationsAct 1976 doesnot
apply to Northern Ireland.
LEGAL ENVIRONMENT
OTHER ISSUES
RACIAL DISCRIMINATION
LE 2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.4 FAIR EMPLOYMENT (NORTHERN IRELAND) ACTS
Asa result of the provisionsof the Fair Employment ( Northern Ireland)
Actsof 1976 and 1989, Departmentsand public authoritiesare
prohibited from entering into contractswith companiesor partnerships
operating in Northern Ireland who have been notified asdisqualified
by virtue of default under the Act.
Where a contract hasalready been entered into, the Department shall
take all such stepsasare reasonable upon notification to secure that no
work isexecuted or goodsor servicessupplied for the purposesof the
contract.
An aggrieved party claiming that a contravention by a Department in
placing or continuing with such a contract hasoccurred will have
recourse to the courts, asking them to require the Department to
comply with the prohibition.
The scheme of the Fair Employment Actsisto ensure balance in
employment trendsand to encourage equal opportunity by requiring
employersin Northern Ireland to monitor and review the composition
of their workforces. The 1989 Act created the Fair Employment
Commission for Northern Ireland and the Fair Employment Tribunal for
Northern Ireland to monitor compliance and administer sanctionsfor
non compliance.
The sanction available to the Commission whereby notice isserved on
an employer stating that the employer isnot qualified to enter into
public workscontractsalong with the unwelcome publicity that it
attracts, isa powerful way of endeavouring to ensure compliance.
The Act appliesto any contract, whether or not:
it isgoverned by the law of Northern Ireland; or
the contract isto be procured by competitive tender or other
means.
The Act isdrafted to allow the Commission to serve noticeson
subsidiariesor connected people, thereby preventing an employer on
whom notice hasbeen served from benefiting from public contracts
indirectly through those subsidiariesor connected people.
LEGAL ENVIRONMENT
OTHER ISSUES
FAIR EMPLOYMENT (NORTHERN IRELAND) ACTS
LE 2.4.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
The prohibition on entering into contractswith unqualified persons
doesnot apply in situationswhere the Secretary of State, the Scottish
Ministers, the Department, or the relevant Northern Ireland
department hascertified in writing that the fulfilment of the contract is
necessary or desirable for reasonsof:
national security;
public interest;
disproportionate expense.
In view of the above, it istherefore necessary for Departmentswhen
seeking to procure contractsfrom contractorsor suppliersoperating
from, or with a connection to, Northern Ireland to check for relevant
notificationsfrom the Fair Employment Commission for Northern
Ireland.
Departmentswill generally be advised of unqualified employersby the
Fair Employment Commission. A list of unqualified employerswill also
be published on the first daysof February, May, August and November
in the Belfast Gazette, The Belfast Telegraph, the NewsLetter and the
Irish News.
LEGAL ENVIRONMENT
OTHER ISSUES
FAIR EMPLOYMENT (NORTHERN IRELAND) ACTS
I
! !! !!
LE 2.4.2
HOME
GACC
EDITION 2: FEB 1998
LE 2.5 INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
Definitions
Definitionsof the varioustermsare:
i) lnteIIectuaI Property - isthe term which should be taken to
include patents, registered and unregistered designs, copyrights,
trade marksand analogousrightssuch asplant breeders rights. The
owner of intellectual property possessa proprietary right in the
object, design or work which can be asserted against third parties.
ii) 'Letters Patent' are granted by the Patent O ffice to the patentee
to prevent othersfrom manufacturing, using, exercising or vending
the invention which isthe subject of the patent. Invention here
meansbroadly a new manner of manufacture and includesnew
methodsof processing or testing applicable to the improvement or
control of manufacture. The patentee isable at their discretion to
grant a licence to othersto exploit the invention commercially on
termsacceptable to him, and the very act of granting a patent gives
publicity to the invention.
iii) A Registered Design differsfrom a patent in that itssubject must
not be an invention but a design defined asfeaturesof shape,
configuration, pattern or ornament applied to an article by any
industrial processor means, being featureswhich are judged solely
by the eye but excluding a method or principle of construction of
featuresof shape or configuration dictated solely by itsfunction.
Registration of a design givesthe ownersthe exclusive rightsin the
UK to make or import for sale or use for the purpose of any trade
or business, or to sell, hire or offer for sale or hire any article of
which the design isregistered. Registration isadministered by the
Patent O ffice.
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
LE 2.5.1
HOME
GACC
EDITION 2: FEB 1998
iv) [Copyrigbt' describesthe protection granted to literary, artistic,
dramatic and musical works( including drawingsand photographs
and in certain circumstancesmodelsand samples) , sound
recordings, filmsand broadcasts. No application, registration or grant
isnecessary to establish copyright whether the work ispublished or
not. The right conferred isto prevent copying asdistinct from the
right conferred by the registration of an industrial design which isto
prevent the production of a similar article whether by copying or
not.
A Design Right subsistsin an original design comprising any aspect
of the scope or configuration of the whole or part of an article,
whether or not it haseye appeal. It needsto be recorded asa
design document but isnot subject to registration. It hassimilarity
with copyright but copyright will take precedence over design right
when both may subsist in a document.
v) Crown copyrigbt isvested in the Controller of HMSO and
appliesto published or unpublished material produced under the
control or direction of a Department or public authority.
vi) RoyaIties are paid to the ownersof patents, designsor copyrights
by those wishing to make use of them. They may be charged a flat
rate, or on a sliding scale with reduction beyond a certain initial
quantity or a lump sum irrespective of the extent of use.
Protection of Copyright by Departments
All drawings/sketchesor original design should be dated at the time of
drafting and copiesretained.
In any event drawingsor sketches, of which the copyright isowned by
the Crown by virtue of original design or of contractual right, should
have the following wordsprinted or stamped on them before issue to a
contractor or outside body:
( C) CRO WN CO PYRIGHT ( date of production of drawing e.g.,
14.10.96) SUPPLIED STRICTLY IN CO NFIDENCE TO RECIPIENT
O NLY FO R ( Name of Department) WO RKS CO NTRACT
PURPO SES. THIS DRAWING SHO ULD NO T BE REPRO DUCED
O R DISCLO SED TO THIRD PARTIES WITHO UT WRITTEN
AUTHO RITY FRO M ( Name of Department) .
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
LE 2.5.2
HOME
GACC
EDITION 2: FEB 1998
The endorsement of the drawingsdoesnot confer any protection in
itself. It drawsattention to the fact that copyright subsistsin the
drawingsand that action could be taken against anyone who copies
them without permission. Copyright isinherent in the work and isnot
registrable in the UK. Itsprotection islimited to actual copying and
would not apply in the case of independent production of the same
work.
Evidence of the date of production of the drawing or sketch or part of
same isimportant on refuting any third party claimsin respect of
identical designs.
Crown Use of Processes or Designs Owned by Contractors or
Individuals
The PatentsActsand the Registered Design Act give the Government
Department or authorised contractorsthe right to use any patentsor
registered designsfor the servicesof the Crown and to negotiate
royaltiesbefore or after use. Exercise of thisright isstrictly for the
servicesof the Crown and cannot be extended to bodiesother than
the Exchequer departmentslisted by the Treasury.
The Crown isliable to an action for infringement of copyright and has
no statutory rightsto copy and use for Government purposesdrawings
or documentary material belonging to others, the law on copyright
being thusquite different from that on patentsor registered designs. It
followsthat any rightsto make use of drawingsor documentsare
restricted to those acquired by a Department by contract or
agreement. Any unauthorised use of such drawingsmay give rise to
legal action against a Department.
Drawingsor design, etc., owned by one firm should not normally be
copied and given or shown to another firm or company for tendering
or contract purposes. Contravention could result in action being taken
against a Department for infringement and misuse of confidential
information. Where it isconsidered essential, permission from the firm
or company owning the design should be obtained.
Information such asdrawings, specifications, reportsand manufacturing
data proprietary to a person or firm which issupplied to a Department
without a contract isregarded asbeing supplied in confidence. To use
such information for a purpose other than that for which it was
supplied isan infringement of the ownersrightsand any such use must
have the ownerswritten consent. Such considerationsalso apply to
similar information supplied by foreign or Commonwealth
Governments.
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
L
! !! !!
LE 2.5.3
HOME
GACC
EDITION 2: FEB 1998
Protection of Designs and Processes by Use of Standard
Contract Supplementary Conditions
Departmentsmay wish to consider the use of standard supplementary
conditionsin order to reinforce preservation of rightsin inventions,
processesor designs.
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
LE 2.5.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.5( SCO T) INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
Definitions
Definitionsof the varioustermsare:
i) Intellectual Property - isthe generic term which should be
taken to include patents, registered and unregistered designs,
copyrights, trade marksand analogousrightssuch asplant breeders
rights. The owner of intellectual property rightshasexclusive rights
asto certain actswhich that owner can do, or authorise othersto
do, in relation to such objects, design or work. These rightscan be
asserted against third parties. Given that intellectual property rights
are simply property rights, the owner can also do with them ashe
or she chooses, including exploiting that ownership by either ( a)
licensing another person to carry out certain activitiesin relation to
those objects, designsor works, or ( b) assigning, ie transferring
ownership of all or part of the rights, eg the copyright.
ii) Letters Patent are granted by the Patent O ffice to the patentee
to prevent othersfrom manufacturing, using, exercising or vending
the invention which isthe subject of the patent. Invention here
meansbroadly a new manner of manufacture and includesnew
methodsof processing or testing applicable to the improvement or
control of manufacture. The patentee isable at their discretion to
grant a licence to othersto exploit the invention commercially on
termsacceptable to him, and the very act of granting a patent gives
publicity to the invention.
iii) A Registered Design differsfrom a patent in that itssubject must
not be an invention but a design defined asfeaturesof shape,
configuration, pattern or ornament applied to an article by any
industrial processor means, being featureswhich are judged solely
by the eye but excluding a method or principle of construction of
featuresof shape or configuration dictated solely by itsfunction.
Registration of a design givesthe ownersthe exclusive rightsin the
UK to make or import for sale or use for the purpose of any trade
or business, or to sell, hire or offer for sale or hire any article of
which the design isregistered. Registration isadministered by the
Patent O ffice.
LE 2.5.1(S)
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
HOME
GACC
EDITION 2 REV 2: JAN 2000
iv) Copyright describesthe protection granted to literary, artistic,
dramatic and musical works( including drawingsand photographs,
computer programsand databases, and in certain circumstances
modelsand samples) , sound recordings, filmsand broadcasts. No
application, registration or grant isnecessary to establish copyright
whether the work ispublished or not. The right conferred isto
prevent copying asdistinct from the right conferred by the
registration of an industrial design which isto prevent the
production of a similar article whether by copying or not.
A Design Right subsistsin an original design comprising any aspect
of the scope or configuration of the whole or part of an article,
whether or not it haseye appeal. It needsto be recorded asa
design document but isnot subject to registration. It hassimilarity
with copyright but copyright will take precedence over design right
when both may subsist in a document.
v) Crown copyright wastraditionally vested in the Controller of
HMSO and appliesto published or unpublished material produced
under the control or direction of a Department or public authority.
In Scotland, however, since 1 July 1999, the Q ueen'sPrinter for
Scotland hasbeen established to act on behalf of Her Majesty in
connection with, amongst other things, Crown copyright in works
made by Scottish Administration staff or copyright assigned to the
Crown in worksmade in connection with the exercise of the
functionsof such staff. Copyright in work created by staff of the
Scottish Administration ( ie Scottish civil servants) will still therefore
vest in the Crown, only itscontroller having changed.
vi) Royaltiesare paid to the ownersof patents, designsor copyrights
by those wishing to make use of them. They may be charged a flat
rate, or on a sliding scale with reduction beyond a certain initial
quantity or a lump sum irrespective of the extent of use.
Protection of Copyright by Departments
All drawings/sketchesor original design should be dated at the time of
drafting and copiesretained.
LE 2.5.2(S)
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
HOME
GACC
EDITION 2 REV 2: JAN 2000
In any event drawingsor sketches, of which the copyright isowned by
the Crown by virtue of original design or of contractual right, should
have the following wordsprinted or stamped on them before issue to a
contractor or outside body:
( C) CRO WN CO PYRIGHT ( date of production of drawing e.g.,
14.10.96) SUPPLIED STRICTLY IN CO NFIDENCE TO RECIPIENT
O NLY FO R ( Name of Department) WO RKS CO NTRACT
PURPO SES. THIS DRAWING SHO ULD NO T BE REPRO DUCED
O R DISCLO SED TO THIRD PARTIES WITHO UT WRITTEN
AUTHO RITY FRO M ( Name of Department) .
The endorsement of the drawingsdoesnot confer any protection in
itself. It drawsattention to the fact that copyright subsistsin the
drawingsand that action could be taken against anyone who copies
them without permission. Copyright isinherent in the work by virtue of
statute and isnot registrable in the UK. Itsprotection islimited to
certain stipulated restricted acts, including actual copying and would not
apply in the case of independent production of the same work.
Evidence of the date of production on the face of the drawing or
sketch or part of same isimportant on refuting any third party claimsin
respect of identical designs.
Crown Use of Processes or Designs Owned by Contractors or
Individuals
The PatentsActsand the Registered Design Act give the Government
Department or authorised contractorsthe right to use any patentsor
registered designsfor the servicesof the Crown and to negotiate
royaltiesbefore or after use. Exercise of thisright isstrictly for the
servicesof the Crown and cannot be extended to bodiesother than
the Exchequer departmentslisted by the Treasury.
The Crown isliable to an action for infringement of copyright and has
no statutory rightsto copy and use for Government purposesdrawings
or documentary material belonging to others, the law on copyright
being thusquite different from that on patentsor registered designs. It
followsthat any rightsto make use of drawingsor documentsare
restricted to those acquired by a Department by contract or
agreement. Any unauthorised use of such drawingsmay give rise to
legal action against a Department.
LE 2.5.3(S)
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
HOME
GACC
EDITION 2 REV 2: JAN 2000
It isimportant therefore to ensure that intellectual property rightsare
dealt with properly in the contract conditions, generally in the
supplementary or special conditionsto the standard building
conditions. Note too that if commissioning work, eg a design from a
consultant, the creator of the work will still have copyright in it unless
the Department providesotherwise. Thisisoften not appreciated.
Drawingsor design, etc., owned by one firm should not normally be
copied and given or shown to another firm or company for tendering
or contract purposes. Contravention could result in action being taken
against a Department for infringement and misuse of confidential
information. Where it isconsidered essential, permission from the firm
or company owning the design should be obtained.
Information such asdrawings, specifications, reportsand manufacturing
data proprietary to a person or firm which issupplied to a Department
without a contract isregarded asbeing supplied in confidence. To use
such information for a purpose other than that for which it was
supplied isan infringement of the ownersrightsand any such use must
have the ownerswritten consent. Such considerationsalso apply to
similar information supplied by foreign or Commonwealth
Governments.
Protection of Designs and Processes by Use of Standard
Contract Supplementary Conditions
The standard contract conditionsdo not deal sufficiently with
protection of intellectual property rightsasthey are obviously drafted
for broad-based use and cannot therefore cover every contractual
situation. Departmentsmay therefore wish to consider the use of
standard supplementary conditionsin order to reinforce preservation
of rightsin inventions, processesor designs. Legal advice should be
sought for assistance in drawing up suitable supplementary conditions.
LE 2.5.4(S)
INTELLECTUAL PROPERTY, COPYRIGHT AND ROYALTIES ETC.
LEGAL ENVIRONMENT
OTHER ISSUES
I
! !! !!
HOME
GACC
EDITION 2: FEB 1998
LE 2.6 PROPRIETARY COMPONENTS/ARTICLES
It iscontrary to the requirementsof the Procurement Regulationsand
to good procurement practice to limit by specification the supply of
goodsto those of a particular named manufacturer or supplier where
thiscan be avoided, asthisdeniesalternative suppliersthe opportunity
to tender and restrictscompetition.
Wherever possible specificationsshould be performance based rather
than relying on prescription in termsof chemical/material composition
and build. Asa consequence, each selected supplier will be able to offer
a trade pattern range of product which meetsthe particular
performance parameters.
Where it isimpracticable to provide descriptionswhich are sufficiently
precise and intelligible by reference to objective standards, the use of
proprietary namesispermitted to make the description precise and
intelligible. However the EC Directivesstate that the description
containing the proprietary name should be qualified by adding the
wordsor equivalent ( no variation from thiswording ispermissible) .
Departmentsusing outside agentsto prepare worksspecificationsmay
need to impose suitable constraintson the specification of proprietary
articles, which iscommon practice in the private sector. Such agents
should be advised to use the wordsor equivalent even when the use
of proprietary articlesisagreed or in case other supplierssubsequently
become available or in case other suppliershave to be used in the
event of the specified proprietary product( s) ceasing to be available.
Where the purchase of proprietary components/articlesisunavoidable
Departmentswill need to check that the price tendered isfair and
reasonable and not lessfavourable to the Department than trade
pricesfor similar products.
In caseswhere difficulty islikely in establishing the reasonablenessof
the pricese.g., the trade list price isnot known, or the trade price of a
comparable product cannot be established, or where adequate
guidance isnot provided by the experience of previouspurchases,
Departmentsshould consider including asa supplement to the price
schedule for signature by the tenderer a declaration to the effect that
the pricesquoted to the Department are equal to or more favourable
than priceswhich are available to the trade.
LEGAL ENVIRONMENT
OTHER ISSUES
PROPRIETARY COMPONENTS/ARTICLES
LE 2.6
HOME
GACC
EDITION 2 REV 1: JAN 1999
LE 2.7 FIRM PRICE AND VARIATION OF PRICE
Firm price and variation of price ( VO P) are termswhich describe the
allocation of the risk of construction cost inflation to one or other of
the partiesto worksor maintenance contractsasfollows:
Firm price - meansa contract where the contractor hasto price for
the risk of construction cost inflation in advance of the cost being
incurred; effectively thisisa contractorsrisk item for which the
Department paysa premium;
VO P - meansa contract where the contractor doesnot have to
price for future inflation and the Department paysthe actual
additional costsif they materialise.
The standard formsof contract are drafted on the premise that the
contractor will tender a firm price, and supplementary conditionsmust
be incorporated if a VO P agreement isrequired. VO P agreementsdo
not generally apply to the appointment of consultants.
The decision asto whether or not to transfer inflation risk isa matter
for early risk management and the formulation of the contract strategy.
The decision will depend on:
current economic conditions;
duration of contract;
projected economic conditions;
value of contract.
O ne of the advantagesof a firm price contract isthat the inflation risk
issecured under the pressure of competition. In addition it ismore
expensive to administer a VO P contract.
Asa general guide, it isrecommended that Departmentsenter into
firm price contractsfor contractsof 2 yearsor lesswhere the work is
considered to be sufficiently defined to enable tenderersreasonably to
assesscost increasesduring the contract.
In stable economic conditionsin which price risesare reasonably
predictable it isappropriate to consider firm price contractsfor 3 years,
thisbeing the period recommended for term commissionsreferred to
in the Guide.
LEGAL ENVIRONMENT
OTHER ISSUES
FIRM PRICE AND VARIATION OF PRICE
PS 2.3

PS 2.4

PS 2.4

LE 2.7.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
Note that the GC/Works( 1999) measured term contractsare based
on a schedule of ratesto which a VO P updating percentage isapplied.
There isno period during which the price isfirm.
An imprecise aspect of firm price tendering from the contractors
viewpoint isthe period of time between submission of the offer and
the point when the contractor commenceswork on site. During the
part of that period prior to acceptance of the offer, the contractor may
withdraw or propose amendmentsto the offer and can, therefore,
control, to a certain extent, the extent to which the risk continues.
However, after acceptance the contractor isbound by itsoffer. To assist
tendering contractorsto assessthe period of time between acceptance
and commencement of work, invitationsto tender for firm price
contractswhich do not otherwise specify the date when
commencement of work isexpected should contain a footnote in the
following form: tenderersshould note that it isexpected that a period
of ... weekswill elapse between the date of acceptance and the date
when possession of the site or the order to commence will be given.
Immediately prior to acceptance the date for the possession of site or
the order to commence should be checked and confirmed. If
confirmation isnot available, acceptance should be delayed until the
period can be honoured.
It isunwise for a single work service to be divided to enable each part
to be dealt with asa firm price contract asthe overall cost of the
service could well be increased by such action. The possibility of
grouping jobsto obtain better pricesshould, however, alwaysbe borne
in mind.
VOP Conditions
The scope of VO P isnot a fixed quantity, but dependson the particular
wordsof the VO P condition used. There are variousstandard methods
and formulae available. For JCT forms, for example, three basic methods
exist:
a minimum provision which coverscontribution, levy and tax
fluctuations;
a labour, materialsand tax fluctuation provision covering fluctuating
costson work termsin full, but ignoring preliminaries;
a full fluctuation provision based on a monthly index figure but
allowing for part of the contract sum to be non-adjustable ( usually
10% ) .
LEGAL ENVIRONMENT
OTHER ISSUES
FIRM PRICE AND VARIATION OF PRICE
LE 2.7.2
HOME
GACC
EDITION 2: FEB 1998
VO P provisions, and mechanisms, are complex and are best
administered by professional staff or consultants, but a general
understanding of how they work isuseful for all staff involved in
significant contract decisions. The general approach to the valuation of
VO P ison a formula basisusing indices.
The object of Formula VO P isto compensate the contractor reasonably
for cost increases( and the Department for cost decreases) and to
reduce delaysin payment associated with actual cost VO P and the
labour in producing and checking an actual cost VO P claim. Formula
reimbursement resultsfrom changesin the indicesasfrom the base
index defined in the contract documents, irrespective of the actual cost
( or savings) incurred by the contractor or sub-contractor.
Price fluctuationsunder Formula VO P are assessed by use of the indices
asfollows:
The formula for building work usesindicescovering labour, materials
and plant for similar or associated itemsof work;
The formula for specialist M&E Engineering work usesseparate
indicesfor labour and materials, the respective weightingsof which
must be prescribed by the tender documents;
The formula for civil engineering worksusesindicesrelating to the
cost of labour, plant and nine basic materialsincluding fuel, plant and
structural steel.
The concept of the Base Month isimportant to the condition. The
Base Month isthe calendar month stated in the tender documents,
the index numbersof which are deemed to equate to the price levels
represented by the ratesand pricescontained in the tender. Under
normal circumstancesthe Base Month will be the calendar month
prior to that in which the tender isdue to be returned. For example, a
tender returnable in July will quote June asthe Base Month.
Exceptionally, it may be necessary to call for a quotation during the
currency of the contract for work which cannot be priced from the
tender because it isof different character from work described therein.
If the contract still hasa long period to run and the work will take
some time to complete, it may be unreasonable to insist on a firm price
quotation. In thiscase it may be convenient to set a new Base Month
for the variation concerned so that any work performed under it can
be subject to separate price adjustment calculated from the agreed
Base Month.
LEGAL ENVIRONMENT
OTHER ISSUES
FIRM PRICE AND VARIATION OF PRICE
LE 2.7.3
HOME
GACC
EDITION 2: FEB 1998
References
There are a number of publicationswhich are available for
Departmentsor their advisersin securing and valuing VO P contracts:
Schedulesof Rates
There are a number of schedulesof ratesintended for use by
Departmentsin inviting tendersfor small worksand maintenance
contracts. These can be obtained from HMSO ( 0171 873 9090) and
are asfollows:
PSA Schedule of Ratesfor Building Works, 7th Edition ( 1995)
...Mechanical Works( 1990)
...Electrical Works( 1990)
...Painting and Decorating ( 1991)
...Landscape Management ( 1991)
These are extensive schedulesof ratesused either to estimate the
cost of work or to invite tendersfrom contractorswho essentially
tender a percentage uplift or discount on these rates.
VO P Indicesfor Maintenance Contracts
The VO P indicesfor adjustment of the above schedulesare
published in a monthly bulletin called Adjustment for Measured
Term Contracts- UPDATING PERCENTAGES. Thisisavailable for
an annual subscription of 50 or for 5 per copy from:
Construction Research CommunicationsLtd
151 RoseburyAvenue
London
EC1R 4Q X
Tel: 0171 505 6622
Thispublication includes:
maintenance cost indicesfor building and civil engineering and
MQ E maintenance;
daywork indices;
other indices.
LEGAL ENVIRONMENT
OTHER ISSUES
FIRM PRICE AND VARIATION OF PRICE
LE 2.7.4
HOME
GACC
EDITION 2: FEB 1998
VO P Indicesfor WorksContracts
The VO P indicesfor the adjustment of Government Works
contracts( historically known asNEDO indices) are published in a
monthly bulletin called Price Adjustment Formula for Construction
Contracts: Monthly Bulletin of Indices. Thisisavailable for an
annual subscription of 96 or for 9.75 per copy, and can be
obtained from HMSO . Thisincludesboth the SeriesII and SeriesIII
indices, the latter having a base year of 1990 with extended work
categories.
An extensive Guide on the application of these indicesisavailable for
40 from HMSO . Thisiscalled Price Adjustment Formula for
Construction Contracts: UsersGuide, 1990 Seriesof Indices.
LEGAL ENVIRONMENT
OTHER ISSUES
FIRM PRICE AND VARIATION OF PRICE
LE 2.7.5
HOME
GACC
EDITION 2: FEB 1998
LE 2.8 LIQUIDATED AND ASCERTAINED DAMAGES
Damagesare said to be liquidated when the amount to which one
party isentitled in the event of breach of contract by the other is
predetermined and defined in the contract itself.
Liquidated damagesare usually, but need not be limited to, damages
agreed in respect of culpable delay on the part of the contractor.
Liquidated damagesmust be a genuine pre-estimate of the extra costs
likely to be incurred by the Department, generally in the event of delay,
e.g. rent and extra running coststhat might be incurred whilst
occupation of the worksisprevented. Provided the damagesare a
genuine pre-estimate then they will be valid even though the actual loss
in the event may be greater or less.
If damagescannot be shown to be a genuine pre-estimate then a
contractor may be successful in arguing that the damagesare a penalty
and therefore unenforceable.
Thisdoesnot however prevent the Department from claiming
unliquidated damages, i.e. the actual lossit incursasa result of delay.
Thismay involve legal action and itsattendant costs, and may negate
the whole point of liquidating the damagesin the first place.
Historically Government policy wasto include a provision for the
recovery of liquidated damagesfor larger workscontractsof 150,000
or more. Some cases, however, may arise where it isconsidered
desirable to provide for liquidated damagesin a contract which is
smaller in value but of sufficient importance to warrant safeguards
against delay in completion e.g., where the completion affectsthe
progressof a larger or more important contract.
LEGAL ENVIRONMENT
OTHER ISSUES
LIQUIDATED AND ASCERTAINED DAMAGES
LE 1.7

LE 2.8.1
HOME
GACC
EDITION 2: FEB 1998
Key Points
Liquidated and ascertained damagesare a contractual remedy
usually for culpable delay by the contractor.
The level of damagesmust be a genuine pre-estimate of the loss.
Keep recordsof the calculation of the pre-estimate of loss.
The Department isnot legally entitled to deduct liquidated damages
if the extension of time provisionshave not been properly
exercised; in particular if the Department hasfailed to ensure that
further time hasbeen granted to the contractor for causeswhich
are the responsibility of the Department.
The Department may choose not to deduct liquidated damages
immediately the contractor beginsthe period of culpable delay. In
thissituation the Department should alwaysreserve itsright to do
so in the future, since such damagesmay be used asa bargaining
chip to counter a claim from the contractor. Seek advice on this
point.
LEGAL ENVIRONMENT
OTHER ISSUES
LIQUIDATED AND ASCERTAINED DAMAGES
L
! !! !!
LE 2.8.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.8(SCOT) LIQUIDATED AND ASCERTAINED DAMAGES
Damagesare said to be liquidated when the amount to which one
party isentitled in the event of breach of contract by the other is
predetermined and defined in the contract itself.
Liquidated damagesare usually, but need not be limited to, damages
agreed in respect of culpable delay on the part of the contractor.
Liquidated damagesmust be a genuine pre-estimate of the extra costs
likely to be incurred by the Department, generally in the event of delay,
e.g. rent and extra running coststhat might be incurred whilst
occupation of the worksisprevented. Provided the damagesare a
genuine pre-estimate then they will be valid even though the actual loss
in the event may be greater or less. Until recently, the courtsin
Scotland accepted a percentage of the contract price if it wasrealistic,
but the feeling now isthat actual figuresshould be calculated on the
basisof a realistic assessment of the damage expected to be incurred.
Asthe sum( s) fixed should be a genuine pre-estimate of loss, there isa
legal presumption that a clause will be unenforceable if a single lump
sum ispayable on the occurrence of several events, some seriousand
otherslessso. In those circumstances, damagesshould be brought
down, ie different obligationsshould have different damage clauses.
If damagescannot be shown to be a genuine pre-estimate then a
contractor may be successful in arguing that the damagesare a penalty
( ie a sum intended to punish the other party) and therefore
unenforceable by the courts.
Thisdoesnot however prevent the Department from claiming
unliquidated damages, i.e. the actual lossit incursasa result of delay.
Thismay involve legal action and itsattendant costs, and may negate
the whole point of liquidating the damagesin the first place.
O n some contractsit may be impossible to estimate the LADs. Note,
however, that merely inserting the word nil in the contract hasthe
effect of preventing any claim for damages, both liquidated damages
under the contract and general damagesat common law. If, therefore,
liquidated damagesare not to be appropriate, the Department should
delete that clause or write not applicable against it, inserting an
alternative clause stating that the employer reservesthe right to claim
general damagesfor delay.
LEGAL ENVIRONMENT
OTHER ISSUES
LIQUIDATED AND ASCERTAINED DAMAGES
LE 1.7

LE 2.8.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Historically Government policy wasto include a provision for the
recovery of liquidated damagesfor larger workscontractsof 150,000
or more. Some cases, however, may arise where it isconsidered
desirable to provide for liquidated damagesin a contract which is
smaller in value but of sufficient importance to warrant safeguards
against delay in completion e.g., where the completion affectsthe
progressof a larger or more important contract.
Key Points
Liquidated and ascertained damagesare a contractual remedy
usually for culpable delay by the contractor.
The level of damagesmust be a genuine pre-estimate of the loss.
Keep recordsof the calculation of the pre-estimate of loss.
The Department isnot legally entitled to deduct liquidated damages
if the extension of time provisionshave not been properly
exercised; in particular if the Department hasfailed to ensure that
further time hasbeen granted to the contractor for causeswhich
are the responsibility of the Department.
The Department may choose not to deduct liquidated damages
immediately the contractor beginsthe period of culpable delay. In
thissituation the Department should alwaysreserve itsright to do
so in the future, since such damagesmay be used asa bargaining
chip to counter a claim from the contractor. Seek advice on this
point.
LEGAL ENVIRONMENT
OTHER ISSUES
LIQUIDATED AND ASCERTAINED DAMAGES
I
! !! !!
LE 2.8.2(S)
HOME
GACC
EDITION 2: FEB 1998
LE 2.9 THE HOUSING GRANTS, CONSTRUCTION AND
REGENERATION ACT 1996
Part II of the Act laysdown a framework for key termsin construction
contractsto deal with payment and resolution of disputesand stems
from the recommendationsof Sir Michael Latham in his1994 report
Constructing the Team. In the case of the GC/Workssuite of
contracts, the requirementsof the Act have been met by the
publication of new documentsor amendmentscirculated by PACE. The
guidance note to the GC/Worksvolumes( published as
Commentaries) containsa full discussion on the practical implications
of the adjudication and payment proceduresaffected by the Act.
Summary of the Acts Provisions
The essential provisionsof Part II of the Act are:
A construction contract isdefined asan agreement in writing, or
evidenced in writing, for carrying out or arranging for the carrying
out of construction operations. It includes, specifically, agreements
for architectural, design, surveying, engineering or other professional
servicesin relation to such operations. The Act appliesto England,
Walesand Scotland ( separate action will be needed for Northern
Ireland) . The Act doesnot set a minimum project value.
Construction operations are defined to cover most formsof non-
domestic construction, alteration, repair, maintenance, extension,
demolition or dismantling of buildings, civil/mechanical and electrical
engineering works, and ancillary or preparatory works. Specific
exclusionsinclude oil drilling work, power generation, plant supply
contracts( without installation) and artistic works.
Partieshave a right to refer any dispute to adjudication. The
timetable must enable referral within 7 daysand a decision within a
further 28 ( which can be extended by agreement) . Adjudicators
must be impartial and be able to take the initiative in ascertaining
factsand the law. The adjudicator will be immune from legal
proceedings( other than in casesof fraud or bad faith) and his
decision will bind the partiesuntil any further arbitral or legal
proceedingsare concluded. The partiesmay however accept the
adjudication asfinal if they wish.
LEGAL ENVIRONMENT
OTHER ISSUES
HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
CRS 1.15

LE 2.9.1
HOME
GACC
EDITION 2: FEB 1998
Payment clausesmust contain a clear mechanism for determining
the amount and timing of payments, with interim paymentsa matter
of right for contractsover 45 daysduration, and a clear final date
for payment specified for each payment. The payer must give
notice, not later than a prescribed period before the final date for
payment, of hisintention to withhold payment, specifying the
amount to be withheld and the groundsfor withholding. The parties
may agree the period to be prescribed in the contract. The payer
must also give notice, not more than 5 daysafter a sum isdue,
specifying how much he haspaid or intendsto pay and the basisof
the calculation. Partiesmay suspend performance of the contract if
sumsdue are not paid without any prior notice of intention to
withhold payment having been duly given. Pay-when-paid clauses, by
which payment may be withheld down the contractual chain until
receipt of payment from a third party, are made ineffective unless
the third party isinsolvent.
Any contract that failsto meet the requirementsof the Act will be
overridden by the 5tatutory 5cbene For Construction
Contracts, wbicb wiII autonaticaIIy inpIy appropriate
provisions into tbe contract tbat eitber party wiII be
entitIed to reIy on.
Practical Implications of the Act
Relationship to arbitration etc
Although adjudication isnot a new concept the Act will represent a
new approach for most formsof contract. An important point is
that the adjudication procedure islaid down in the contract. This
contrastswith arbitration which isa separate processwith the
procedure largely laid down in statute. The Latham Report
envisaged adjudication asa quick-fix, allowing the worksto proceed
without festering disputes. If the adjudicator concludesthat either
party needsto provide additional money or resourcesaspart of the
settlement then thisshould be done, albeit without necessarily
committing either side to accept the decision in the longer term.
But subsequent eventswill have to unfold within the context set by
the adjudication, and the contract may, asin the GC forms,
expressly bar arbitration, whether directly or following an
adjudication until after certified completion of the works. If new
evidence or circumstancesarose after an adjudication suggesting
that the decision wasmistaken eg asregardsa dispute about quality,
then if the partiescould not agree a different settlement it would
require a new adjudication.
LEGAL ENVIRONMENT
OTHER ISSUES
HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
LE 2.9.2
HOME
GACC
EDITION 2: FEB 1998
Scope of Adjudication
Thismust cover any difference of opinion about any decision taken
by either party, or by a representative such asthe architect, project
manager or engineer. No substantial contractual restraint can now
be placed on the referral of any dispute to an independent and
impartial adjudicator. However contractsmay specify only money
remediesfor those areasof dispute which cannot realistically be re-
opened by an adjudicator, such asdetermination or security
decisions.
Adjudication mechanics
The very tight statutory timescalesmake it likely that in most cases
adjudicatorswill need to be appointed before a contract isawarded.
Fall-back provisionswill be needed to settle how a fresh adjudicator
might be appointed should thisbe unavoidable. To allow
adjudicatorsto take independent expert advice the termsof
appointment will need to deal expressly with the point, and what
stepsare expected of the adjudicator if any dispute isso large,
complex or unusual that he feelsunable to deal with it in the limited
time envisaged. The adjudicator must however actually resolve the
dispute, and not seek to shelve-it by placing a disputed sum with a
stakeholder or propose a nominal split-the-difference solution, since
these stepswould not amount to a genuine decision.
Adjudication cost
The most appropriate arrangement islikely to be a 50/50 split on
feesand for each side to bear their own costs. The adjudicator could
be empowered to rule on cost and fee liability asbetween the
partieswithin hisdecisionson particular disputes( a possible
deterrent to tactical and mischievouscallsfor adjudication) . A
standing fee or retainer for the pre-appointed adjudicator islikely to
be warranted only in exceptional cases.
Adjudicator commonality
To enable consolidation of related disputesacrossthe whole project
it may be appropriate for the main contract to specify that the
subcontract termsshould name the main contractor adjudicator as
also acting in subcontract disputes.
LEGAL ENVIRONMENT
OTHER ISSUES
HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
LE 2.9.3
HOME
GACC
EDITION 2: FEB 1998
Payment periods
Partieswill be free to agree the amountsof interim paymentsand
the intervals, if any, that may become due. However the contract
termswill need to be precise asto periodsboth for certification of
advanceson account and payment following certification.
Set-off from sums due
The Act imposesa broad framework covering all withholding of
payment. Set-off will only be effective after notice hasbeen given of the
amount and reasonsfor withholding money. The contract can state
what the period of notice should be. The Act will not alter the general
law on rightsto set-off paymentson one contract against moniesdue
on another; thisisexpressly allowed under the GC formsof contract.
Key Points
The Act isnot retrospective and will therefore not apply before the
Statutory Scheme for Construction Contractscomesinto effect.
All construction contractsasdefined by the Act are covered by its
provisions.
The Act cannot be contracted-out; formsof contract which are not
amended to take account of the Act will be subject to the
requirementsof the Scheme for Construction Contracts.
LEGAL ENVIRONMENT
OTHER ISSUES
HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
LE 2.9.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.9( SCO T) THE SCHEME FOR CONSTRUCTION CONTRACTS
(SCOTLAND) REGULATIONS 1998
In Scotland, the characteristicsand featuresof the systemsof dispute
resolution are different from those in England and Wales. The Scottish
tradition hasbeen to rely more on contractual or conventional
arrangementsthan on arrangementsregulated by statute. The Act
therefore containsprovisionsenabling a separate Scheme for
Construction Contractsto take account of Scottish law, practice and
procedure and apply to construction contractsin Scotland. Accordingly,
the Scheme for Construction Contracts( Scotland) Regulations1998
were introduced.
The purpose of the statutory Scheme isto remedy deficienciesin
construction contractsrelating to adjudication ( section 108( 5) of the
Act) and payment ( sections109( 3) , 110( 3) , 111( 3) and 113( 6) ) . Where
any of the Scheme'sprovisionsapply they shall have effect asimplied
termsof contract between the parties, thusoperating ascontractual
provisionsconstituting obligationsunder the contract:
for adjudication, unlessa construction contract containsadjudication
provisionswhich satisfy all the requirementsof section 108( 1) -( 4) ,
then Part 1 of the Scheme shall apply in itsentirety
for payment the situation isdifferent. Where a construction contract
doesnot meet the individual requirementsof the payment
provisionsin the Act then only the relevant provisionsof Part 2 of
the Scheme shall apply.
The Scheme'sprovisionsare free-standing and were drafted to operate
acrossa broad range of typesof construction contracts. It isfelt by
many, including some of the Institutes, that it may therefore not meet
the detailed requirementsof the partiesto any particular contract.
For example, for adjudication, the Scheme makesadjudication of any
dispute available to any party to the contract at any time. The Act,
on the other hand, allowspartiesa considerable degree of discretion
and flexibility in their contractual arrangements.
Consequently, where partiesto a contract do not wish that the
Scheme be imposed on that contract, they must ensure that in drafting
the contract they meet the requirementsof the Act. Alternatively, some
Institutes, such asICE, have developed their own alternative scheme
intended to meet the requirementsof the Act but avoid some of the
difficultieswhich they perceive asinherent in the Government Scheme.
LEGAL ENVIRONMENT
OTHER ISSUES
SCHEME FOR CONSTRUCTION CONTRACTS (SCOTLAND)
LE 2.9.1(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
Key Point
If the conditionsof any particular construction contract do not
comply with the requirementsof the Act, then the provisionsof the
Scheme will apply to that contract.
LEGAL ENVIRONMENT
OTHER ISSUES
SCHEME FOR CONSTRUCTION CONTRACTS (SCOTLAND)
LE 2.9.2(S)
HOME
GACC
EDITION 2: FEB 1998
LE 2.10 THE ARBITRATION ACT 1996
The 1996 Arbitration Act isa technical and procedural measure which
reflectsthe recommendationsof the Department of Trade and
IndustrysDepartmental Advisory Committee on Arbitration Lawwhich
concluded that the 1950, 1975 and 1979 Arbitration Actsrequired
consolidation and reform so asto:
incorporate principlesestablished by common law
give greater party autonomy
make clearer the supportive role of the courts
use a more friendly format and language.
The provisionsof the new Act are quite separate from the mandatory
adjudication proceduresintroduced into construction contractsby Part
II of the Housing Grants, Construction and Regeneration Act 1996. The
relationship between adjudication and arbitration for the settlement of
disputesmust be fixed by individual contracts.
Relevance to Construction Contracts Disputes
Building contract disputes, especially on major projects, tend to involve
many different partiesand therefore sometimesrequire consolidation
and coordination in a way that isnormal within the litigation process.
Under the previouslaw the courtswere able to apply discretion when
considering applicationsfor a stay of legal proceedingseven though a
valid arbitration agreement wasin existence. Under the new Act the
court will no longer have thisdiscretion and must uphold the
arbitration agreement unlessit isnull and void, inoperative or incapable
of being performed.
The 1998 editionsof the GC/Workscontractshave enhanced
arbitration clauseswhich take account of the requirementsof the Act.
These ensure that multi-party disputescan, where necessary, be
properly coordinated acrossa range of different contractsapplying to a
project, without relying on the courts.
Key Points
The new Act isnot retrospective and only appliesto arbitrations
which commenced on or after 31 January 1997 even if the basic
contract and arbitration agreement wasentered into before that
date.
LEGAL ENVIRONMENT
OTHER ISSUES
THE ARBITRATION ACT 1996
LE 2.9

LE 2.10
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.10(SCOT) ARBITRATION
Unlike England, the rulesgoverning arbitration in Scotland are based
almost wholly on the common law ( ie case law) . The Arbitration
( Scotland) Act 1894 did, however, give courtspower to appoint arbiters
should the partiesin certain circumstancesfail to agree an arbiter. More
recently statute hasprovided that arbitersmay, on the application of
one of the parties, and must if directed by the Court of Session, state a
case for the opinion of the Court of Session on any question of law ( ie
not fact) which arisesin the arbitration.
Note that the Arbitration Act 1996 only appliesto Scotland in so far as
consumer arbitration agreementsare concerned.
LEGAL ENVIRONMENT
OTHER ISSUES
ARBITRATION
LE 2.10(S)
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.11 CONSTRUCTION INDUSTRY TAX SCHEME
The Scheme
The Construction Industry Tax Scheme wasintroduced in 1971 to
counter tax evasion by the lump. The Scheme wasrevised in 1999 and
from 1 August 1999 Government Departmentsare deemed to be
Contractors. Inland Revenue requirescontractors to make a
deduction on account of tax from all the labour elementsof payments
to construction sub-contractorsunlessan exemption certificate is
produced. The contractor isalso required to make a monthly return to
the Inland Revenue of paymentsto sub-contractorsunder each
contract. These returnsalso record the certificate number. At the end of
each tax year there isa requirement to make a consolidated annual
return to the Inland Revenue covering each sub-contractor individually.
Paymentscannot be made grossto an unregistered sub-contractor in
respect of construction work. In these casesnot only tax but National
Insurance deductionsmust also be made. These deductionsmust be
remitted to Inland Revenue.
The requirement on Government Departments
From 1 August 1999 Government Departmentsand Agenciesare
treated ascontractors under the Scheme. Thisembracesany role in
the direct commissioning of construction worksand also where an
agent actson behalf of a Department. The authority isrequired to
make a deduction in respect of tax unlessthe contractor hasan
exemption certificate. Also, there isa requirement to make monthly
and annual returnsto the Inland Revenue of all paymentsto sub-
contractorsusing the Inland Revenue prescribed forms.
Contractors' registration
A primary requirement before placing any contract isto find out
whether contractorshold a current registration card ( CIS4) or a tax
certificate ( CIS5 or CIS6) . The Department must ask to see the sub-
contractor'scertificate or registration documentsand then record its
number and expiry date on the relevant contract file. If there isany
doubt about the validity of the documentation presented the sub-
contractor initially should be regarded asbeing a non-certificate holder
and the case papersreferred to Inland Revenue for evaluation/
adjudication.
LEGAL ENVIRONMENT
OTHER ISSUES
CONSTRUCTION INDUSTRY TAX SCHEME
LE 2.11.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Any sub-contractor holding a Registration Card isonly entitled to
payment net ( that is, with the Department deducting an element for
tax and national insurance contributions) . The Department is
responsible for passing these deductionsdirect to Inland Revenue at
the same time giving the sub-contractorsa copy of the Tax Payment
Voucher ( CIS25) each month for their records. Sub-contractorswho
are holdersof Tax Certificates( CIS5 and CIS6) are entitled to receive
their paymentsgross. In these casesa GrossPayment Voucher ( CIS24)
must be completed for each payment made. These are then passed to
the sub-contractor to add their taxpayer'sreference number. The sub-
contractor then returnsone part to the Department whilst the other
copy issent direct to Inland Revenue. It isessential that originalsof
vouchersare retained on the contract file asan annual return hasto be
made to the Inland Revenue.
Scope of the Scheme
Identifying precisely what work iscovered by the Scheme iscomplex.
Inland Revenue leaflet IR14/15 ( 1998) givesdetailed guidance. For ease
of reference, the following guidelineshave been agreed with the Inland
Revenue:
if only part of the contract work fallswithin the Scheme, the whole
value of the contract should be counted for tax purposes;
small contractsfor construction operations, amounting to lessthan
1,000 ( excluding the cost of materials) , may be excluded from the
Scheme so long asthey are not a product of disaggregation and
have been duly authorised asexcluded by Inland Revenue.
The excluded categoriesof work are:
routine servicing and maintenance of heating, lighting, air
conditioning, liftsequipment or other related plant;
routine external cleaning of buildings( other than painting and
decorating) . Thiswill include annual contractsto clean drains, gutters,
changing luminariesand groundsmaintenance.
Included categoriesof work are:
installation of M&E equipment, including lifts, pumps, boilers,
ventilation fans, electrical switchgear;
LEGAL ENVIRONMENT
OTHER ISSUES
CONSTRUCTION INDUSTRY TAX SCHEME
LE 2.11.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
all new building or alterations. Thiswill include demolition of
partitions/walls, alterationsto counters, installation or re-hanging of
doors, upgrading accommodation standardsto meet fire precaution
requirements, installation of general plumbing and general electrical
works, major roofing works;
all painting and decorating, including both initial decoration and
re-decoration and wallpapering.
When a job includesboth excluded and included categoriesof work it
isregarded asa mixed contract and all work within it should be
included under the Scheme. If there isdoubt about a particular
construction activity, it initially should be included in the tax return. The
sub-contractor can subsequently gain a rebate from the Inland Revenue
if they agree the item isexempt.
The Inland Revenue deadlinesfor the completion and return of forms
are very strict. All completed formsshould be sent promptly at monthly
intervalsto the AccountsBranch who will collate the Department's
annual return.
LEGAL ENVIRONMENT
OTHER ISSUES
CONSTRUCTION INDUSTRY TAX SCHEME
LE 2.11.3
HOME
EPP 1.0 THE 5COPE OF APPLlCATlON OF THE EC
PROCUREMENT RULE5
EPP 1.1 GENERAL
EPP 1.2 THE DIRECTIVES
EPP 1.3 DECIDING WHICH DIRECTIVE APPLIES
EPP 1.4 EX CLUSIO NS
EPP 1.5 THRESHO LDS
EPP 1.6 ESTIMATING THE VALUE O F CO MMISSIO NS AND AGGREGATIO N
EPP 1.7 PUBLICITY AND THE TYPES O F N OTICE REQ UIRED
EPP 1.8 PRO CEDURE FO R ADVERTISING AND AWARDING CO NTRACTS
EPP 1.9 ACCELERATED T IMESCALES
EPP 1.10 MO DEL NO TICES AND THEIR CO NTENT
EPP 1.11 NUMBER O F TENDERERS
EPP 1.12 TENDERER SELECTIO N
EPP 1.13 AWARD CRITERIA
EPP 1.14 CO NTRACT NO TICE, DECLINE AND DEBRIEFING
EPP 1.15 EC/GATT REPO RTING REQ UIREMENTS
ANNEX
EPP 1.1 CATEGO RIES O F SERVICES
EPP 1.2 NO TICES REQ UIRED UNDER EC PUBLIC PRO CUREMENT RULES
EPP 1.3 PRO CEDURES AND TIMESC ALES FO R ADVERTISING AND AWARDING
CO NTRACTS
EPP 1.4 WO RKS CO NTRACTS - MO DEL CO NTRACT NO TICES
EPP 1.5 SERVICES CO NTRACTS - MO DEL NO TICES
HOME
GACC
EDITION 2: FEB 1998
EPP 1.0 THE SCOPE AND APPLICATION OF THE
EC PROCUREMENT RULES
EPP 1.1 GENERAL
The term EC procurement rules used in the Guide isa reference to
the EC public procurement directivesand in particular to the relevant
UK regulationsintroduced by way of statutory instruments. This
chapter givesguidance on the scope and application of the rules.
There are a number of important general pointsof guidance which
should be kept in mind in caseswhere the EC procurement rulesapply.
These are:
the principlesof the EEC Treaty ( The Treaty of Rome) apply to all
public procurement;
the four cornerstonesof the EEC Treaty are the free movement of
goods, persons, servicesand capital, and Article 7 of the Treaty
prohibitsdiscrimination on the groundsof nationality; the
establishment of the common market therefore involvesthe
elimination of all obstaclesto intra-community trade;
one of the principal objectivesbehind the EC public procurement
rulesistherefore to prevent the use of pre-determined shortlistsof
tenderers, which in effect represent restrictive or anti-competitive
practice;
the EC procurement rulesgenerally apply only to single contracts
above a specified threshold value, however in a number of casesthe
valuesof more than one contract must be added together for
deciding whether the threshold ismet;
the application of the rulesrequiresspecial consideration at various
stagesof the procurement cycle and may place an additional
administrative burden on the procuring Department;
there isa requirement to publish noticesin the O fficial Journal of
the European Union ( O J) ;
GENERAL
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.1.1
HOME
GACC
EDITION 2: FEB 1998
there are specific minimum time limitswhich must be observed and
which can prolong the procurement process;
there isa high chance of receiving applicationsfrom a large number
of companies; it istherefore essential that the Department hasin
place a system which providesa fair and unbiased meansof
reducing the list to a reasonable number of tenderers, generally on
the basisof a paper sift;
there are three procedureswhich may be adopted, the open
procedure, restricted procedure and the negotiated procedure:
- under the open procedure anyone may tender,
- under the restricted procedure anyone may apply to be
considered for invitation to tender,
- under the negotiated procedure direct discussionstake place
between the contracting authority and one or more contractors/
suppliers/ service providersof itschoice.
in order to provide for competition, and for the fair selection of a
short list, it will be appropriate to follow the restricted procedure in
almost every case;
it should be borne in mind that the Department may receive
expressionsof interest from firmsof which they have had no prior
experience; conversely the Department may have to exclude firms,
which they may wish to include on a short list, because the firms
have failed to respond to the O Jnotice either in the prescribed
fashion, or at all;
in accordance with the UK Regulations, each Department must
send to Treasury not later than 31 July each year for suppliesand
every alternate year for worksand services, a report which setsout
information about all contractswhich have been let since the last
report; all such reportsare then collated into a statistical report
( which must be provided to the European Commission by each
member state) ;
finally the Department isunder an obligation to comply with the
Directivesand UK Regulations; failure to do so may give rise to
court action resulting in an order for the Department to pay
damagesto a wronged party.
GENERAL
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
L
! !! !!
EPP 1.1.2
HOME
GACC
EDITION 2: FEB 1998
Principles Behind the Regulations
ConpIeteness of coverage - which meansthat all purchasesby
public sector bodies, above the thresholdsestablished in the
legislation, will be subject to public purchasing proceduresunder
one of the key Directives.
Access to infornation - meansthat free and equal accessto a
pre-defined minimum amount of information should be available to
all contractorsfrom the EU. Thisincludesinformation on planned
procurements, specific contractsand tender proceduresand the
resultsof those procedures.
EquaIity of treatnent - thismeansthat all tenderers, regardless
of origin within the EU should have their offersconsidered on a fair
and equitable basisand that criteria should not be used to evaluate
offersthat have the effect of unfairly excluding foreign suppliers.
Rigbts of redress - meansthat tendererswho believe they have
been discriminated against should have accessto remediesthat can
be readily applied that compensate them for their losses, whilst
deterring future infractionsof the rules. Thisincludesactionsin the
High Court for suspension of contract award and changes. Thisin
turn requirespurchasersto record and document their decisions
and to produce statisticsthat can be used to identify possible biasin
contract awards.
Available Rights of Redress
The principal meansof enforcement for a breach of the Regulations
and other enforceable EC law such asthe Treaty are:
action by suppliersor contractorsagainst individual purchasersin
the High Court; and
action by the Commission against the Member State in the
European Court of Justice.
Either way the result might be:
the suspension of an incomplete contract award procedure; or
the setting aside of a decision in an incomplete contract award
procedure.
GENERAL
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.1.3
HOME
GACC
EDITION 2: FEB 1998
The Court of Justice hasdemonstrated that, in appropriate
circumstances, it isprepared to overturn a contract.
The High Court also haspowersto award damages. In caseswhere a
contract hasbeen entered into, an award of damagesisthe only
remedy which the High Court can provide. The Regulationsset out the
proceduresto be followed.
GENERAL
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.1.4
HOME
GACC
EDITION 2: FEB 1998
EPP 1.2 THE DIRECTIVES
The EC ruleson public procurement arise from European Community
Directives. EC Directivesare known assecondary level legislation,
because they are secondary to the Treaty of Rome. The EC Directives
on public procurement have been incorporated into UK law by way of
a number of Statutory Instruments( SIs) .
The EC Directivesand their associated UK SIswhich set out the public
procurement rulesand their scope are asfollows:
Tbe 5uppIies Directive ( UK SI 201/ The Public Supply
ContractsRegulations1995) - the supply, lease, rental or hire
purchase of goods.
Tbe Works Directive ( UK SI 2680/ The Public WorksContracts
Regulations1991) - the supply of capital work.
Public worksconcession contractsare the subject of regulations25
and 26. These are contractsunder which the consideration given by
the public authority consistsof or includesthe right to profit from
the worksto be carried out under the contract, ( for example a toll
bridge) . These regulationsare not considered in any detail in this
Chapter.
Tbe 5ervices Directive ( UK SI 3228/ The Public Services
ContractsRegulations1993) - the supply of services. A distinction is
made between part A services, also known aspriority services, to
which all of the regulationsapply, and part B services, also known as
residual services, to which only selected regulationsapply. ( See
Annex EPP 1.1 ( at the end of thischapter) for the servicesincluded
under each category) .
Design contestsare the subject of regulation 24 which setsout
when the regulationsapply and the special procedureswhich must
be followed. Thisregulation isnot considered in any detail in this
chapter.
Tbe UtiIities Directive ( UK SI 3279/1992, amended by SI 3227/
1993) - the supply of goods, worksand servicesto the Utilities
sector. Thisconcernsnationalised industriesand private sector
companieswithin the water, energy, telecommunicationsand
transport industries. Departmental purchaseswill not normally be
affected by thisDirective and no further mention of it ismade in
thissection.
THE DIRECTIVES
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
Annex 1.1

EPP 1.2.1
HOME
GACC
EDITION 2: FEB 1998
Tbe ConpIiance Directive - to enforce the other four
Directives. ThisDirective hasbeen embodied in the UK SIsfor
supplies, worksand servicesunder the section entitled Applications
to Court. Under thissection the courtsare given specific power to
ensure compliance with EC procurement rules, including the right to
award damagesto a wronged supplier.
The Directivesapply in the following circumstances:
Where the procurer isa contracting authority asdefined by
regulation 3 of each of the supplies, worksand servicesregulations.
ThisincludesDepartments. The regulationsalso apply to goods,
worksand serviceswhich are being procured by a third party on
behalf of a contracting authority.
Where the nature of the contract isnot such asto be excluded by
the EC procurement rules.
Where the value of the contract isabove the relevant threshold
( see EP 1.5) .
Key Points
Section EPP 1 of thisChapter isintended asa summary of the key
pointsrelating to public procurement. Many of the provisions
contained in the supplies, worksand servicesregulationsare
common and use similar or identical wording. Where there are
differences, the principal oneshave been identified in the sections
that follow.
It isrecommended that you read each of the relevant SIslisted in
thissection.
THE DIRECTIVES
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.4

EPP 1.5

L
! !! !!
EPP 1.2.2
HOME
GACC
EDITION 2: FEB 1998
EPP 1.3 DECIDING WHICH DIRECTIVE APPLIES
In general it isclear which directive appliesfor the procurement of a
particular type of work.
It will be seen by reference to Annex EPP1.1 that in relation to services
contracts, construction design and related professional servicesare
category A - priority servicesto which all of the servicesregulations
apply.
The choice may be lessclear where, asiscommonly the case, the
scheme involvesa combination of works, servicesand/or supplies. The
regulationsare not comprehensive in dealing with thisissue.
5uppIies and 5ervices
Some assistance may be found under the definition of public supply
contract in the Public Supply ContractsRegulations1995. This
statesthat where a contract involvesthe supply of goodsaswell as
the provision of services, then the supply regulationsapply only if
the value of the goodssupplied and any siting or installation of the
goodsisgreater than the value of the serviceselement of the work;
otherwise the servicesregulationsapply.
Works and 5ervices
In respect of worksand servicesthe EC Commissionsown
guidance statesthat where the value of the workselement of a
contract exceedsthe value of the serviceselement, then it should
be categorised asa public workscontract.
The servicesgenerally required for construction projectswill be
categorised aspublic servicescontracts.
However, if these servicesform part of a single design and build or
managed construction contract to be awarded to a main or
managing contractor, the work will be classified asa public works
contract.
Where the Department decides, for good commercial reasons, to
award separate contractsfor these servicesin advance of the main
contract ( for example where initial design isnovated to a design
and build contractor) , then the servicesregulationswill apply.
DECIDING WHICH DIRECTIVE APPLIES
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.3.1
HOME
GACC
EDITION 2: FEB 1998
5uppIies and Works
Contractsfor the supply of mechanical plant for example, which are
part of a main workscontract, will be subject to the works
regulations. Contractsfor the early procurement of any itemswhere
thisisappropriate, would be classed aspublic supply contracts. The
itemsmay then be issued free to the contractor. Note that the
value of free issue equipment etc. hasto be included with the value
of the workscontract for the purpose of assessing overall value
against the workscontract threshold.
Key Points
The general rule isthat a contract should be classified according to
which ever element ( supplies, services, works) hasthe greatest
value.
No attempt should be made to select an unnatural combination or
to sub-divide contractsmerely to ensure that the likely pricesof
individual partsfall below the threshold valuesof their respective
directives.
It costsa lot more to prepare an invitation to tender and place a
contract than to insert an advertisement in the O JEC. First costs
alone can never justify employing additional contractsto beat the
threshold. When in doubt, advertise.
DECIDING WHICH DIRECTIVE APPLIES
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.3.2
HOME
GACC
EDITION 2: FEB 1998
EPP 1.4 EXCLUSIONS
There are a number of typesor classesof work which are specifically
excluded from the application of the EC public procurement rules.
These may be found at regulation 6 of each of the supplies, works, and
servicesregulations.
A common exclusion from all three setsof regulationsisany contract
which isclassified assecret or where the carrying out of the supply,
worksor servicesin connection with it must be accompanied by special
security measuresin accordance with the laws, regulationsor
administrative provisionsof any part of the UK or when the protection
of the basic interestsof the security of the UK require it.
5uppIies
The principal exclusion from suppliescontractsisthose contracts
which fall under the utilitiesregulations.
Works
The principal exclusionsfrom workscontractsare in respect of
offersbeing sought:
- by a contracting authority which isexercising the functionsof a
courier by land, air, sea or inland waterway;
- which concernsthe production, transport or distribution of
drinking water;
- by a contracting authority whose principal activity isthe
production or distribution of energy.
EXCLUSIONS
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.4.1
HOME
GACC
EDITION 2: FEB 1998
5ervices
The principal exclusionsfrom the servicesregulationsare in relation
to the following:
- contractsfor the purchase or rental of land or buildings- but not
contractsrelating to financing for such transactions;
- contractsfor broadcasting material or broadcasting time;
- contractsfor voice or radio telephony, telex, paging or satellite
services;
- arbitration and conciliation services;
- securitiescontractsrelating to the issue, sale, purchase or
transfer of securitiesor other financial instrumentsand central
bank services
- contractsfor central banking services
- R&D service contracts( other than those where the benefit
accruesexclusively to and iswholly paid for by the contracting
authority)
5ubsidised Contracts
In the case of public workscontracts( regulation 23) and public
servicescontracts( regulation 25) the regulationsneed not apply
where a contracting authority contributeslessthan one half of the
contract consideration to a subsidised body. If the contribution is
greater than one half then the authority must make it a condition of
the contribution that the regulationsare observed by the subsidised
body asif they were a contracting authority.
EXCLUSIONS
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.4.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
EPP 1.5 THRESHOLDS
The EC procurement rulesdo not apply if the estimated value of the
contract (net of value added tax) islessthan the threshold specified
in the regulations.
The intention behind the thresholdsisto exclude from the EC
requirementscontractswhich can be assumed to attract only local
competition and where the application of the requirementswould
cause unnecessary bureaucracy. It should be borne in mind that
whether or not the threshold applies, the EEC Treaty still prohibits
discrimination or national preference.
The thresholdsare set by reference to:
EC public procurement directives
The General Agreement on Tariffsand Trade ( GATT) rules.
The GATT wassigned in 1947 and providesan agreed framework of
rulesfor the conduct of trade between member statesworld-wide.
Essentially the rulesprovide that lower thresholdsapply to GATT
contracting entitiesthan non-GATT entities. The GATT rulesare
incorporated into the UK SIs. Until recently the GATT rulesonly
affected supply contracts, but the ruleshave now been extended to
include servicescontracts, for which the lower level appliesexcept for
R&D servicesand Part B residual services.
A list of GATT entities( Departments) can be found in Schedule 1 to SI
201 - The Public Supply ContractsRegulations1995.
THRESHOLDS
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.5.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
THRESHOLDS
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.5.2
The table below setsout the thresholdswhich apply to the varioustypesof
contract.
THRESHOLDS - PUBLIC SECTOR:
1 JANUARY 2000 TO 31 DECEMBER 2001
Supplies Services Works
GATT Entities
1
93,896 93,896
2
3,611,395
3
( SDR130,000) ( SDR130,000) ( SDR5,000,000)
( ECU139,312) ( ECU139,312) ( ECU5,358,153)
O ther public 144,456 144,456
2
3,611,395
3
sector ( SDR200,000) ( SDR 200,000) ( SDR5,000,000)
contracting ( ECU214,326) ( ECU214,326) ( ECU5,358,153)
authorities
Indicative 505,500 505,500 3,611,395
Notices ( ECU750,000) ( ECU750,000) ( ECU5,358,153)
Small Lots not applicable 53,920 674,000
( ECU80,000) ( ECU1,000,000)
1
Schedule 1 of the Public Supply ContractsRegulations1995 lists
central government bodiessubject to the World Trade O rganisation
GPA. These thresholdswill also apply to any successor bodies.
2
With the exception of the following serviceswhich have a threshold
of 134,800 ( ECU200,000) :
Part B ( residual) services
Research & Development Services( Category 8)
The following Telecommunicationsservicesin Category 5:
- CPC 7524 - Television and Radio Broadcast services
- CPC 7525 - Interconnection services
- CPC 7526 - Integrated telecommunicationsservices
Subsidised servicescontractsunder Regulation 25 of the Public
ServicesContractsRegulations1993.
3
With the exception of subsidised workscontractsunder Regulation
23 of the Public WorksContractsRegulations1991 which have a
threshold of 3,370,000 ( ECU5,000,000) .
HOME
GACC
EDITION 2: FEB 1998
EPP 1.6 ESTIMATING THE VALUE OF COMMISSIONS AND
AGGREGATION
The EC thresholdsand the rulesthat a contracting authority must
follow in deciding whether a particular contract exceedsthe
appropriate advertising threshold are set out in regulation 7 of each of
the supplies, worksand servicesregulations.
A fundamental rule within each of the regulationsisthat the
requirement for work or a quantity of suppliesor servicesmay not be
split up in order to avoid the application of the EC procurement rules,
and there must therefore be no deliberate underestimating in order to
avoid complying with the regulations.
A contracting authority cannot break the work down into phases, for
example, in order deliberately to avoid exceeding the thresholds.
Where there isa single requirement for goods, worksor services, and
the contracting authority intendsto let the work in a number of
discrete parts, then the consideration calculated for comparison to the
threshold must generally be the aggregate value of all of those parts.
In respect of workscontracts, the general rule isthat where the
contract isone of a number of contractsor Lots entered into for the
purpose of carrying out a work then it must be aggregated with all the
other associated contractsin deciding whether the threshold applies. It
isnecessary to look at the result of the operation to see if it servesa
single purpose. Hence separate contractsto build or extend different
partsof a single construction such asa road project with bridges,
should be aggregated.
In general, the total cost of any suppliesor servicesrequired for a
worksproject, and for which separate contractsare awarded under
either the suppliesor servicesdirectives, should be included in the total
cost of the project when calculating itsvalue against the threshold.
The exception here would be where separate service contractsare let
well in advance of the main construction contract, for preparation of
tendersfor example.
ESTIMATING THE VALUE OF COMMISSIONS AND AGGREGATION
CONTRACTORS
CONTRACTING STRATEGIES
EPP 1.6.1
HOME
GACC
EDITION 2: FEB 1998
Reference ismade in the table to EPP 1.5 to thresholdsin respect of
small lotsprovisionsfor public worksand public servicescontracts. This
providesfor the non-application of the regulationsto a contract for
part of a project requirement which would normally be aggregated
together with other like contractsfor evaluation against the advertising
threshold. Non-application can only be relied upon if the contract value
islessthan the small lotsprovision threshold, and islessthan 20% of
the aggregate value of all of the contractsto be entered into in order
to fulfil the total requirement
The aggregation rulesmay also require the aggregation of contractslet
by different Departmental units. Generally the rule isthat where the
contracting authority traditionally purchasescentrally, the threshold
appliesto the aggregated total. But where a discrete unit purchases
locally itspurchasesneed not be aggregated with those of another unit
and the threshold appliesto the value of the local purchase only.
Depending on delegation levels, a Department may be deemed to
have discrete operational units( DO U) . A DO U isreferred to in the
suppliesand servicesregulations. A DO U may avoid the aggregation
rulesreferred to above if:
contracting decisionshave been devolved to it; and
it hasthe power to make contracting decisionsindependently of any
other part of the contracting authority.
Unlessthese conditionsare met a unit within a contracting authority
cannot be regarded asa DO U and would be subject to the aggregation
rules.
Contracts for the supply of goods or services over a period
of time
There are special valuation rulesfor public supply and public services
contractswhere a contracting authority hasa requirement over a
period of time for either a seriesof contractsor for a contract which is
renewable.
EPP 1.5

EPP 1.6.2
ESTIMATING THE VALUE OF COMMISSIONS AND AGGREGATION
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2: FEB 1998
The value of the contractsin respect of such a requirement shall be
calculated by either:
taking the total value of such work carried out in the previous
financial year or previous12 months, and if future requirementsare
likely to increase, then the value must be adjusted upwards
accordingly; or
taking the expected value of the worksto be carried out in a period
of 12 monthsfrom the first date on which the goodsor serviceswill
be delivered, or for the term of the contract where the contract is
of a definite term in excessof 12 months.
Where goodsor servicesare to be provided over a period in excessof
4 yearsthen the value shall be calculated by multiplying the amount
expected to be incurred in respect of each month of the period by 48.
Key Points
There must be no deliberate dis-aggregation of requirementsin
order to avoid complying with the public procurement regulations.
It costsmore to prepare an invitation to tender and place a contract
than it doesto place an advert in the O J. Thiscost cannot therefore
justify the deliberate dis-aggregation of contracts.
If there isany uncertainty about whether the procurement rules
apply or not, it isrecommended that they be applied.
EPP 1.6.3
ESTIMATING THE VALUE OF COMMISSIONS AND AGGREGATION
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 1: JAN 1999
EPP 1.7 PUBLICITY AND THE TYPES OF NOTICE REQUIRED
O ne of the key elementsof the public procurement regime isthat
apart from the negotiated procedure without prior contract notice, all
contractscaught under it must be advertised and contractorsinvited to
tender in the O fficial Journal of the European Community ( the O J) .
Thisisknown asmaking a call for competition. O nce the contract has
been awarded, detailsof the award must be published in the O J.
Varioustypesof notice to cover different circumstancesmust be
published in the O J, each in standard format. They should also appear in
the EC computer-based information system available on a subscription
basis, TendersElectronic Daily or TED. These are described here, for
ease of reference:
Periodic (or prior) information notice (PlN): contracting
authoritiesmust publish a notice setting out detailsof suppliesor
part A servicescontractsto be awarded in the next 12 monthsin
each product area or service category where the total value of the
contractsexceedsthe financial threshold which currently standsat
750,000 ECUs. All major workscontractsmust be advertised by a
PIN assoon asthe decision to proceed with them hasbeen made.
Notice on the existence of a qualification list: thisnotice
only appliesto contractsregulated under the UtilitiesDirective.
Contract notice thisisthe most important of the procurement
notices, advertising individual contractsto be awarded by
contracting authorities.
Contract award notice: once a contract hasbeen awarded the
contracting authority must publish the result in the O J.
The chart in Annex EPP 1.2 at the end of thischapter isa summary of
the noticeswhich must be given in accordance with the public
procurement rules.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
PUBLICITY & THE TYPES OF NOTICE REQUIRED
EPP 1.11

Annex 1.2

EPP 1.7.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
Official Journal of the EC
The notice must not exceed 650 wordsand should be sent or faxed to:
The O fficial Journal of the European Community
2 Rue Mercier
L-2985 Luxembourg
Tel: 00 352 2929 1 ( switchboard)
Fax: 00 352 2929 42670
00 352 2929 44623
00 352 2929 44619
The O Jhastwelve daysfrom receipt of the notice to ensure
publication.
Advertisement Elsewhere
Contractsmust not be advertised in the UK before contract notices
are dispatched to the O fficial Journal of the EC. Subsequent
advertisementsin the UK may not contain greater detailsthan those
published in the O fficial Journal.
Key Points
For each new commission caught by the regulationsthe appropriate
noticesmust be published in the O J.
If commission requirementschange, or if time lapseswithout taking
any further procurement action, then the commission should be re-
advertised.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
PUBLICITY & THE TYPES OF NOTICE REQUIRED
EPP 1.7.2
HOME
GACC
EDITION 2: FEB 1998
EPP 1.8 PROCEDURE FOR ADVERTISING AND AWARDING
CONTRACTS
The three different procedureswhich public authoritiesmust choose
between when awarding contractsare termed the open, restricted
and negotiated procedures. O f these, all the Directivesother than that
for utilitiesencourage use of either the open or restricted procedure,
specifying situationswhere the negotiated procedure ispermitted. The
UtilitiesDirective allowsany procedure to be chosen.
Open procedure - all interested suppliersmay tender. Anyone
interested in tendering who submitsa compliant tender to the
authority within the appropriate time limit, in response to itscall for
competition, will be considered for the job.
Restricted procedure - only those suppliersinvited to
participate by the contracting authority may submit a tender. Where
the restricted procedure isused, the tender processhastwo distinct
stages. After a call for competition hasbeen made in the O J,
applicantsmust submit their requeststo be selected to tender
within a specified period. The contracting authority then considers
these expressionsof interest and excludesnon-compliant
respondents, - those who are unable to fulfil the technical
specifications, or who fail to meet the eligibility criteria - before
sending the written invitationsto tender with contract
documentation to short-listed candidates. Generally, a sufficient
number of candidatesmust be selected to tender to ensure
adequate competition. The short listed candidatesmust then submit
their tendersbefore a second deadline. In casesof urgency, the
contracting authority may follow an accelerated programme with
shorter time limits. Generally, however, the minimum time limitsfor
the restricted procedure are longer than for the open procedure,
counter-balancing to some extent the attraction of being able to
select tenderers.
The restricted procedure isrecommended for use by Departments.
It should be noted that in practice the number of expressionsof
interest can be very high making it impossible to carry out extensive
pre-selection procurement procedures, such aspre-selection
interviews. Pre-selection will invariably have to be on the basisof a
paper sift and therefore the contract notice should specify the
groundson which pre-selection will be made.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
ADVERTISING & AWARDING CONTRACTS
L
! !! !!
EPP 1.8.1
HOME
GACC
EDITION 2: FEB 1998
Negotiated procedure - direct discussionsand negotiationswill
take place between the contracting authority and one or more
suppliersof itschoice. If the authority makesa call for competition,
the first half of the processwill be identical to that used in the
restricted procedure and the strict time limitswill apply. In a few
casesthe negotiated procedure can be used without a call for
competition being made. In these instancesno time limitsapply.
Use of the Negotiated Procedure
The negotiated procedure ( see above) may be used, without a call for
competition published in the O J, in the following cases:
if no ( suitable) tenderswere received when the same contract was
put to tender under the open or restricted procedure;
if, for technical or artistic reasons, or because of the protection of
exclusive rights, only a limited number of service providerscan fulfil
the contract;
if the contract followsa design contest and must be awarded to the
successful candidate or one of the successful candidates;
in casesof extreme urgency resulting from un-foreseeable events;
for additional ( previously un-foreseeable) serviceswhich cannot
practically be separated from the original contract, or which are
strictly necessary for completion, so long asthey do not exceed half
the amount of the original contract;
for repeat serviceswithin three yearsof the original contract which
conform to a basic project for which the first contract wasawarded
by open or restricted procedure.
Furthermore, even where there hasbeen a call for competition, the
negotiated procedure may still be used in certain prescribed
circumstances. For example:
when the nature of the servicessuch asintellectual or financial
servicesissuch that the contract specificationscannot be drawn
sufficiently precisely to permit use of the open or restricted
procedures.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
ADVERTISING & AWARDING CONTRACTS
EPP 1.8.2
HOME
GACC
EDITION 2: FEB 1998
Timescales
Minimum timescalesor, if appropriate, maximum timescalesare laid
down for:
expressionsof interest to be lodged following publication of the
contract notice;
the tender period;
the publication of a contract award notice.
The timescalesdepend on the procedure being followed. The
procedure and timescalesare summarised in the diagramscontained in
Annex EPP 1.3 asfollows:
Diagram 1 O pen procedure
Diagram 2 Restricted procedure
Diagram 3 Negotiated procedure with prior contract notice
Diagram 4 Negotiated procedure without prior publication of
notice.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
ADVERTISING & AWARDING CONTRACTS
Annex 1.3

EPP 1.8.3
HOME
GACC
EDITION 2: FEB 1998
EPP 1.9 ACCELERATED TIMESCALES
In respect of supplies, worksand servicescontracts, it ispossible to use
reduced timescalesfor the restricted procedure ( see Annex EPP 1.3 -
Diagram 2) and for the negotiated procedure with prior contract notice
( see Annex EPP 1.3 - Diagram 3) .
The accelerated timescalesmay only be used where the normal timescales
are rendered impracticable by reason of urgency.
Key Points
Accelerated proceduresshould not be used to circumvent normal time
limits. The proper pre-planning of requirements, taking into account the
time needed to implement EC Directivesshould make casesin which
accelerated proceduresare used, the exception rather than the rule.
ACCELERATED TIMESCALES
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.9
HOME
GACC
EDITION 2: FEB 1998
EPP 1.10 MODEL NOTICES AND THEIR CONTENT
A general description of the noticeswhich must be published in the O J
isgiven in section EPP 1.7 of the Guide.
The structure and content of these noticesdiffer according to the
regulation under which they are issued, and according to the chosen
procedure for advertising and awarding the contract.
Model noticesare given at the end of each of the setsof regulations.
These are repeated with some enhancementsin Annex EPP 1.4 for
workscontracts, and EPP 1.5 for service contracts. The workscontract
model noticesare asfollows:
Reference Description
4A PRIO R INFO RMATIO N
4B CO NTRACT NOTICE - O PEN PRO CEDURE
4C CO NTRACT NOTICE - RESTRICTED PRO CEDURE
4D CO NTRACT NOTICE - NEGO TIATED PRO CEDURE
4E CO NTRACT AWARD NOTICE
4F MO DEL NOTICE O F PUBLIC WO RKS
CO N CESSIO N S
4G MO DEL NOTICE O F WO RKS AWARDED BY THE
CO N CESSIO N N AIRE
The service contract model noticesare asfollow:
Reference Description
5A INDICATIVE NO TICE
5B CO NTRACT NOTICE - O PEN PRO CEDURE
5C CO NTRACT NOTICE - RESTRICTED PRO CEDURE
5D CO NTRACT NOTICE - NEGO TIATED PRO CEDURE
5E CO NTRACT AWARD NOTICE
5F DESIGN CO NTEST NO TICE
5G RESULT O F DESIGN CO NTEST
5H MO DEL CANCELLATIO N NOTICE ( ALL SECTO RS
AND ALL PRO CEDURES
MODEL NOTICES AND THEIR CONTENT
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.7

EPP 1.10.1
HOME
GACC
EDITION 2: FEB 1998
Cancellation
Note that if for any reason, there are significant changesto the contract
requirementsat any stage then thiscould invalidate the procedure and
necessitate re-commencement of a procedure. If it becomesnecessary
for any reason to abandon a project in itsentirety or to restart a
procedure then it will be necessary to publish a cancellation notice in
the form given in Annex EPP 1.5H. Firmswho have submitted tenders
under the open procedure or submitted expressionsof interest under
the restricted procedure should be informed by letter.
Definition and Use of Official Language
In order to promote the greatest clarity in describing the works,
productsand servicesto be purchased specialised vocabulariesand the
use of technical standardshave been defined. These must be used in
drafting contract noticesand tender specifications.
Standards and Technical Specifications
Technical specificationswhich define the characteristicsof a purchase,
including safety, performance, dimensionsand quality levelsshould be
included in contract noticesand tender specifications. The Directives
require contract authoritiesto use a Britisb 5tandard
inpIenenting European 5tandards where such a standard exists,
or Connon TecbnicaI 5pecifications.
Brand or Process Names
Referencesto goodsof specific make, source or processwhich have
the effect of favouring specific suppliersor productsmust be not be
used unlessthe specificationsare strictly justified by the subject of the
contract. If one cannot otherwise describe the purchasesin a
sufficiently detailed and tangible way, referencesto trade marks, patents
or brandsmay only be made provided the wordsor equivaIent are
added afterwards.
When thisisthe case one must consider variantsto what hasbeen
specified in the notice. O ffersresulting from such noticescannot be
rejected solely on the groundsthat they have been drawn up using
different technical specificationsfrom those used in the United
Kingdom, provided that the tender meetsthe requirementsset out in
the contract documents.
MODEL NOTICES AND THEIR CONTENT
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.10.2
HOME
GACC
EDITION 2: FEB 1998
Community Procurement Vocabulary (CPV)
In order to establish the greatest accuracy and clarity in the
management of public procurement the Commission hasdeveloped a
Common Procurement Vocabulary. Itsmain purpose isto ensure speed
and consistency in translation of procurement notices. Thisvocabulary,
which isupdated from time to time, containstechnical descriptionsof
works, productsand services, accompanied by numeric codeswhich
establish their position in the system. These codesand classifications
should be used in describing the supplies, worksand servicesto be
purchased and should appear in the published notices.
Key Points
The noticeswhich must be published in the O Jmust have
information provided in a standard from of language under standard
headings.
It may be advisable to subscribe to the O Jto monitor the
publication of the Departmentsown noticesand to see examples
of notices.
MODEL NOTICES AND THEIR CONTENT
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.10.3
HOME
GACC
EDITION 2: FEB 1998
EPP 1.11 NUMBER OF TENDERERS
The number of tendererswhich will be selected to tender isspecified
in each of the supplies, worksand servicesregulations. These are as
follows:
Open procedure
An unlimited number, i.e. whoever applies.
Restricted procedure
The requirementsare the same in each of the regulationsasfollows:
( 6) The contracting authority may pre-determine the
range within which the number of personsit
intendsto invite to tender for the contract shall be
fixed but only if:
( a) the lower number of the range isnot lessthan 5
and the higher number not more than 20,
( b) the range isdetermined in the light of the
nature of the servicesto be provided under the
contract, and
( c) the range isspecified in the contract notice.
( 7) The number of personsinvited to tender shall be
sufficient to ensure genuine competition.
Negotiated Procedure
Where there isa sufficient number of personswho are suitable to
be selected to negotiate the contract, the number selected to
negotiate shall not be lessthan three.
NUMBER OF TENDERERS
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.11
HOME
GACC
EDITION 2: FEB 1998
EPP 1.12 TENDERER SELECTION
After publication of the contract notice, and receipt of responses, the
contracting authority may exclude tenderersfrom the remainder of the
processon certain specified grounds.
Respondentsto contract noticesshould be able to demonstrate their
commercial, technical and financial ability to meet the requirementsof
the commission and the contract notice must specify what references
are required in thisrespect.
Note that those placing noticesshould not prejudge the responses
expected.
It islikely that some firmswill also respond to indicative ( prior
information) noticesand it isgood practice to initiate an appraisal of
such firmsassoon asthe response isreceived.
When using the restricted procedure, all candidateswho respond to
the contract notice should be appraised but only those qualified to
meet the criteria set out in the notice need be invited to tender.
The selection criteria are set out in similar regulationsin respect of
each of the supplies, worksand servicesregulations. These are:
Regulation 14 - Criteria for rejection of supplies, worksor
servicesproviders
Regulation 15 - Information asto economic and financial
standing
Regulation 16 - Information asto ability and technical capacity
Regulation 17 - Supplementary information.
In respect of the open, restricted and negotiated proceduresa tenderer
or a firm expressing an interest in tendering or negotiating may only be
excluded if the firm may be treated asineligible on the grounds
specified in regulation 14 or failsto satisfy minimum standardsto be
evaluated in accordance with regulations15, 16 and 17.
TENDERER SELECTION
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.12.1
HOME
GACC
EDITION 2: FEB 1998
The groundsgiving rise to ineligibility in regulation 14 include such
mattersas:
The company or individual isbankrupt
An administrator or receiver hasbeen appointed
A criminal offence hasbeen committed
Failure to pay social security payment, or taxes
The firm or person isnot licensed in a member state
In accordance with regulation 15, evaluation of economic and financial
standing may be made only in connection with the following
information.
Statementsfrom the firmsbankers. ( Including evidence of PI
insurance in the case of service providers) .
Statementsof accountsor extractstherefrom
Statement of overall turnover and turnover in the previous3
financial yearsin respect of the specific supply, worksor services
sought.
In accordance with regulation 16, evaluation of ability and technical
capacity may be made only in connection with specified criteria. This
differsslightly between regulations, but the criteria include such matters
as:
Education and professional qualification.
Experience.
Techniciansand technical bodieswhich may be utilised.
Previouswork and track record.
Toolsplant and technical equipment available.
Technical specificationsfor products.
Compliance with BS5750.
TENDERER SELECTION
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.12.2
HOME
GACC
EDITION 2: FEB 1998
EPP 1.13 AWARD CRITERIA
The contract notice must specify the contract award criteria aseither:
the lowest price only, or
the most economically advantageoustender.
The latter criteria isthe appropriate one for evaluating tenderson the
basisof quality and price, particularly when obtaining tendersfor
services.
Where the latter criteria isto be applied, the criteria to be used for the
selection shall be stated, where possible in descending order of
importance, in the contract notice or the contract documents.
O nly the award criteria specified either in the contract notice or in the
tender documentsmay be applied in the subsequent evaluation of
tendersand in the debriefing of unsuccessful tenderers.
Variations
Where a contracting authority decidesthat it will exclude all tenders
which contain variations, it must state thisfact in the contract notice.
A contracting authority may otherwise take account of offers
containing variationsif:
the offer meetsthe minimum requirement of the contracting
authority; and
it hasstated in the contract documentsthe minimum requirements
and any specific requirementsfor the presentation of an offer
offering variations.
AWARD CRITERIA
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EPP 1.13
HOME
GACC
EDITION 2: FEB 1998
EPP 1.14 CONTRACT NOTICE, DECLINE AND DEBRIEFING
O nce a tenderer hasbeen selected, a contract award notice must be
published. See Annex EPP 1.4 for workscontractsnoticesand Annex
EPP 1.5 for servicescontractsnotices.
There isno specific obligation to write decline lettersto unsuccessful
tenderers, but it isrecommended that thisisdone within 7 daysof
publication of the notice.
Debriefing
In accordance with Regulation 22 of the Worksand Services
Regulations, and Regulation 23 of the Supply Regulations, there isan
obligation to respond within 15 daysof receipt of a request from an
unsuccessful tenderer for further information. The debriefing letter
should set out the following:
the reasonswhy the tenderer wasunsuccessful;
the name of the successful tenderer.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
CONTRACT NOTICE, DECLINE & DEBRIEFING
EPP 1.14
HOME
GACC
EDITION 2: FEB 1998
EPP 1.15 EC/GATT REPORTING REQUIREMENTS
By 31 July each year for suppliesand every alternate year from
1995 for worksand services, each Department isrequired to
provide reportsto Treasury which show the following
information:
for each contract awarded under the scope of the Directives:
- itsvalue,
- the award procedure used,
- if the negotiated procedure wasused, the reason,
- the type or category ( classification) of goods/worksor
services,
- nationality of the party contracted with;
for contractsawarded outside the scope of the Directives:
- the aggregate value.
Treasury use thisinformation to collate a statistic report which
each member state must compile and submit to the European
Commission.
It followsthat each discrete purchasing unit and Department
must keep a running record of all contractsin order to be in a
position to provide reportspromptly. The recordsmust also be
auditable since the European Commission can at any time ask
for information on individual contracts, any such enquiriesbeing
passed through Treasury. Reportsin response to such enquiries
must include the following:
name and addressof contracting authority;
subject and value of the contract;
namesof candidatesor tendererssubmitted and the reasons
for selection;
namesof candidatesor tenderersrejected and the reasons
for rejection;
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
EC/GATT REPORTING REQUIREMENTS
EPP 1.15.1
HOME
GACC
EDITION 2: FEB 1998
the name of the successful tenderer and the reasonsfor the
selection of the tender. Also if known, any share of the contract the
successful tenderer may sub-contract to a third party;
for negotiated procedures, the circumstanceswhich justify itsuse;
for accelerated procedures, the circumstanceswhich justify itsuse.
Key Points
Careful recordsmust be kept of all purchasing decisionsincluding
those which exclude purchasesfrom the EC procurement rules,
such asthreshold calculations.
EC PROCUREMENT PROCEDURES
THE EC PROCUREMENT RULES
CONTRACT NOTICE, DECLINE & DEBRIEFING
EPP 1.15.2
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.1
EC PROCUREMENT PROCEDURES
ANNEX EPP 1.1
CATEGORIES OF SERVICES
Referred to in Regulation 5 of the Public ServicesContractsRegulations1993.
( SI 3228/1993)
Annex EPP 1.1.1
HOME
GACC
EDITION 2: FEB 1998
PART A
Category
Reference Service CPC Reference
#
1 Maintenance and repair of vehiclesand equipment. 6112, 6122, 633,
886
2 Transport by land, including armoured car services 712 ( except
and courier servicesbut not including transport of 71235) , 7512,
mail and transport by rail. 87304
3 Transport by air but not transport of mail. 73 ( except 7321)
4 Transport of mail by land, other than by rail, and 71235, 7321
by air.
5 Telecommunicationsservicesother than voice 752
telephony, telex, radiotelephony paging and satellite
services.
6 Financial services 81 ( Part) , 812, 814
( a) Insurance services
( b) Banking and Investment servicesother than
financial services* in connection with issue, sale,
purchase or transfer of securitiesor other
financial instruments, and central bank services
7 Computer and related services 84
8 R&D serviceswhere the benefitsaccrue exclusively 85
to the purchaser for itsuse in the conduct of itsown
affairsand the servicesare to be wholly paid for by
the purchaser.
9 Accounting, auditing and book-keeping services 862
10 Market research and public opinion polling services 864
ANNEX EPP 1.1
EC PROCUREMENT PROCEDURES
Annex EPP 1.1.2
HOME
GACC
EDITION 2: FEB 1998
Category
Reference Service CPC Reference
#
11 Management consultancy servicesand related
services, but not arbitration and conciliation services. 865, 866
12 Architectural services: engineering servicesand 867
integrated engineering services: urban planning and
landscape architectural services: related scientific
and technical consulting services: technical testing
and analysisservices.
13 Advertising services. 871
14 Building-cleaning servicesand property 874, 82201 to
management services. 82206
15 Publishing and printing serviceson a fee or 88442
contract basis
16 Sewerage and refuse disposal service: sanitation 94
and similar services
#
CPC standsfor the Central Product Classification of the United Nations
* Thisexception doesnot apply in the utilitiessector
ANNEX EPP 1.1
EC PROCUREMENT PROCEDURES
Annex EPP 1.1.3
HOME
GACC
EDITION 2: FEB 1998
PART B
Category
Reference Service CPC Reference
#
17 Hotel and restaurant services 64
18 Transport by rail 711
19 Transport by water 72
20 Supporting and auxiliary transport services 74
21 Legal services 861
22 Personnel placement and supply services 872
23 Investigation and security services, other than 873, ( except
armoured car services 87304)
24 Education and vocational education services 92
25 Health and social services 93
26 Recreational, cultural and sporting services 96
27 O ther services
#
CPC standsfor the Central Product Classification of the United Nations
* Thisexception doesnot apply in the utilitiessector
ANNEX EPP 1.1
EC PROCUREMENT PROCEDURES
Annex EPP 1.1.4
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.2
NOTICES REQUIRED UNDER EC PUBLIC PROCUREMENT RULES
ANNEX EPP 1.2
EC PROCUREMENT PROCEDURES
Annex EPP 1.2.1
HOME
GACC
EDITION 2: FEB 1998
NoticesRequired Under EC Procurement Rules
Contract Notices
Restricted Procedure:
Works
Supplies
Priority Services
and Design
Contests
Contract Notices
Negotiated
Procedure:
Works
Supplies
Priority Services
and Design
Contests
Indicative Notices:
Supplies
Services
Prior Information
Notice for Works
Voluntary Notices
Below Thresholds
Contract Notices
O pen Procedure:
Works
Supplies
Priority Services
and Design
Contests
Award Notices:
Works
Supplies
Services
- Priority
- Non-Priority
ANNEX EPP 1.2
EC PROCUREMENT PROCEDURES
Annex EPP 1.2.2
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.3
PROCEDURES AND TIMESCALES FOR ADVERTISING AND AWARDING
CONTRACTS
ANNEX EPP 1.3
EC PROCUREMENT PROCEDURES
Annex EPP 1.3.1
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.3
EC PROCUREMENT PROCEDURES
Annex EPP 1.3.2
Prepare contract Notice and Documents
Send Notice to O JEC
Notice Issued in O JEC
SuppliersRespond to Notice
Send Contract Documentsto Suppliers
SuppliersReturn Tender
SuppliersAppraisal/Tender Evaluation
Award Contract
Send Contract Award Notice to O JEC
Note: * Minimum of 36 daysif pre-information or indicative noticeshave been issued
under the Worksand ServicesDirectives.
Minimum
52 Calendar
Days*
Maximum
6 Days
Maximum
48 Days
DIAGRAM 1
Open Procedure
HOME
GACC
EDITION 2: FEB 1998
DIAGRAM 2
Restricted Procedure
ANNEX EPP 1.3
EC PROCUREMENT PROCEDURES
Annex EPP 1.3.3
* Prepare contract notice and documents
* Decide range of tenderssought ( between
5 and 20)
AcceIerated NornaI
Send Notice to O JEC
Notice issued to O JEC
Suppliersrespond to notice
Undertake Supplier Appraisal
Invite Tendersfrom Q ualified Suppliers
SuppliersReturn Tender
Award Contract
Send Contract Award Notice to O JEC
Note: * Minimum of 26 daysif prior indicative noticeshave been issued under the Works
and ServicesDirectives.
Minimum
15 Days
Minimum
37 Days
Minimum
10 Days
Minimum
40 Days*
Minimum
1 Day
Maximum
48 Days
HOME
GACC
EDITION 2: FEB 1998
DIAGRAM 3
Negotiated Procedure with Prior Contract Notice
AcceIerated NornaI
ANNEX EPP 1.3
EC PROCUREMENT PROCEDURES
Annex EPP 1.3.4
Minimum
15 Days
Minimum
37 Days
Departmental approval
Prepare contract notice/documentation
Contract notice to O JEC
Contract notice published
Suppliersrespond to notice
Reassesssupplier appraisal
Negotiate with qualified suppliers( must include at
least 3 unlessthere are insufficient qualifed
candidates)
Award Contract
Send contract award notice to O JEC
Maximum
48 Days
HOME
GACC
EDITION 2: FEB 1998
DIAGRAM 4
Negotiated Procedure without Prior Publication of Notice
ANNEX EPP 1.3
EC PROCUREMENT PROCEDURES
Annex EPP 1.3.5
Departmental Approval ( including draft report for
commission)
Select Q ualifed Suppliers
Negotiate with Suppliers
Award Contract
Send Contract Award Notice to O JEC
Maximum
48 Days
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.4
WORKS CONTRACTS
Model Notices
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Reference Description
4A PRIO R INFO RMATIO N
4B CO NTRACT NOTICE - O PEN PRO CEDURE
4C CO NTRACT NO TICE - RESTRICTED PRO CEDURE
4D CO NTRACT NO TICE - NEGO TIATED PRO CEDURE
4E CO NTRACT AWARD NO TICE
4F MO DEL NO TICE O F PUBLIC WO RKS CO NCESSIO NS
4G MO DEL NO TICE O F WO RKS AWARDED BY THE
CO NCESSIO NNAIRE
Annex EPP 1.4.1
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
WORKS CONTRACTS - MODEL CONTRACT NOTICES
4A PRIOR INFORMATION
1 Name, address, telephone number, telegraphic address, telex and facsimile
numbersof the contracting authority.
2 ( a) Site.
( b) Nature and extent of the servicesto be provided and, where relevant, main
characteristicsof any lotsby reference to the work.
( c) If available, an estimate of the cost range of the proposed services.
3 ( a) Estimated date for initiating the award proceduresin respect of the contract
or contracts.
( b) If known, estimated date for the start of the work.
( c) If known, estimated timetable for completion of the work.
4 If known, termsof financing of the work and of price revision and/or referencesof
the provision in which these are contained.
5 O ther information.
6 Date of dispatch of the notice.
7 Date of receipt of the notice by the O ffice for O fficial Publication of the European
Communities.
Annex EPP 1.4.2
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
4B CONTRACT NOTICE - OPEN PROCEDURE
1 Name, address, telephone number, telegraphic address, telex and facsimile
numbersof the contracting authority.
2 ( a) Award procedure chosen.
( b) Nature of the contract for which tendersare being requested.
3 ( a) Site.
( b) Nature and extent of the servicesto be provided and general nature of
the work.
( c) If the work or the contract issubdivided into several lots, the size of
the different lotsand the possibility of tendering for one, for several or
for all of the lots.
( d) Information concerning the purpose of the work or the contract where
the latter also involvesthe drawing up of projects.
4 Any time limit for completion.
5 ( a) Name and addressof the service from which the contract documents
and additional documentsmay be requested.
( b) Where applicable, the amount and termsof payment of the sum to be
paid to obtain such documents.
6 ( a) Final date for receipt of tenders.
( b) Addressto which tendersmust be sent.
( c) Language in which tendersmust be drawn up.
7 ( a) Where applicable, the personsauthorised to be present at the opening
of tenders.
( b) Date, hour and place of opening of tenders.
Annex EPP 1.4.3
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
8 Any deposit and guaranteesrequired.
9 Main termsconcerning financing and payment and/or referencesto the
provisionsin which these are contained.
10 Where applicable, the legal form to be taken by the grouping of contractors
to whom the contract isawarded.
11 Minimum standardsof economic and technical standing and technical capacity
required of the contractor to whom the contract isawarded.
12 Period during which the tenderer isbound to keep open itstender.
13 Criteria for the award of the contract. Criteria other than that of the lowest
price shall be mentioned where they do not appear in the contract
documents.
14 Where applicable, prohibition on variants.
15 O ther information.
16 Date of publication of the prior information notice in the official journal of the
European communitiesor reference to itsnon-publication.
17 Date of dispatch of the notice.
18 Date of receipt of the notice by the O ffice for O fficial Publication of the
European Communities.
Annex EPP 1.4.4
HOME
GACC
EDITION 2: FEB 1998
4C CONTRACT NOTICE - RESTRICTED PROCEDURE
1 Name, address, telephone number, telegraphic address, telex and facsimile
numbersof the contracting authority.
2 ( a) Award procedure chosen.
( b) Where applicable, justification for the use of the use of the shorter
time limits( accelerated procedure) .
( c) Nature of the contract for which tendersare being requested.
3 ( a) Site.
( b) Nature and extent of the servicesto be provided and general nature of
the work.
( c) If the work of the contract issubdivided into several lots, the size of
the different lotsand the possibility of tendering for one, for several or
for all of the lots.
( d) Information concerning the purpose of the work or the contract where
the latter also involvesthe drawing up of the projects.
4 Any time limit for completion.
5 Where applicable, the legal form to be taken by the grouping of contractors
to whom the contract isawarded.
6 ( a) Final date for receipt of requeststo participate.
( b) Addressto which requestsmust be sent.
( c) Language or languagesin which requestsmust be drawn up.
7 Final date for despatch of invitationsto tender.
8 Any deposit and guaranteesrequired.
9 Main termsconcerning financing and payment and/or the provisionsin which
these are contained.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.5
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.6
10 Information concerning the contractorspersonal position and minimum
standardsof economic and financial standing and technical capacity required of
the contractor to whom the contract isawarded.
11 Criteria for the award of the contract where they are not mentioned in the invitation
to tender.
12 Where applicable, prohibition on variants.
13 O ther information.
14 Date of publication of the prior information notice in the O fficial Journal of the
European Communitiesor reference to itsnon-publication.
15 Date of dispatch of the notice.
16 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
HOME
GACC
EDITION 2: FEB 1998
4D CONTRACT NOTICE - NEGOTIATED PROCEDURE
1 Name, address, telephone number, telegraphic addresstelex and facsimile
numbersof the contracting authority.
2 ( a) Award procedure chosen.
( b) Where applicable, justification for the use of the use of the shorter
time limits( accelerated procedure) .
( c) If the work or the contract issubdivided into several lots, the size of
the different lotsand the possibility of tendering for one, for several or
for all of the lots.
( d) Information concerning the purpose of the work or the contract where
the latter also involvesthe drawing up of projects.
3 ( a) The site.
( b) The nature and extent of the servicesto be provided and general
nature of the work.
( c) If the work or the contract issubdivided into several lots, the size of
the different lotsand the possibility of tendering for one, for several or
for all of the lots.
( d) Information concerning the purpose of the work or the contract where
the latter also involvesthe drawing up of projects.
4 Any time limit.
5 Where applicable, the legal form to be taken by the grouping of contractors
to whom the contract isawarded.
6 ( a) Final date for receipt of tenders.
( b) Addressto which tendersmust be sent.
( c) Language or languagesin which tendersmust be drawn up.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.7
HOME
GACC
EDITION 2: FEB 1998
7 Any deposit and guaranteesrequired.
8 Main termsconcerning financing and payment and/or provisionsin which
these are contained.
9 Information concerning the contractorspersonal position and information and
formalitiesnecessary in order to evaluate the minimum standardsof economic
and financial standing and technical capacity required of the contractor to
whom the contract isawarded.
10 Where applicable, prohibition on variants.
11 Where applicable, name and addressof suppliersalready selected by the awarding
authority.
12 Where applicable, date( s) of previouspublicationsin the O fficial Journal of the
European Communities.
13 O ther information.
14 Date of publication of the prior information notice in the O fficial Journal of the
European Communities.
15 Date of Dispatch of notice.
16 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.8
HOME
GACC
EDITION 2: FEB 1998
4E CONTRACT AWARDS
1 Name and addressof contracting authority.
2 Award procedure chosen.
3 Date of award of contract.
4 Criteria for award of contract.
5 Number of offersreceived.
6 Name and addressof successful contractor( s) .
7 Nature and extent of the servicesprovided, general characteristicsof the finished
structure.
8 Price or range of prices( minimum/maximum) paid.
9 Where appropriate, value and proportion of the contract likely to be subcontracted
to third parties.
10 O ther information.
11 Date of publication of the tender notice in the O fficial Journal of the European
Communities.
12 Date of dispatch of the notice.
13 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.9
HOME
GACC
EDITION 2: FEB 1998
4F MODEL NOTICE OF PUBLIC WORKS CONCESSIONS
1 Name, address, telephone number, telegraphic address, telex and facsimile numbers
of the contracting authority.
2 ( a) Site.
( b) Subject of the concession, nature and extent of the servicesto be provided.
3 ( a) Final date for receipt of candidatures.
( b) Addressto which candidaturesmust be sent.
( c) Language or languagesin which candidaturesmust be drawn up.
4 Personal, technical and financial conditionsto be fulfilled by the candidates.
5 Criteria for award of contract.
6 Where applicable, the minimum percentage of the workscontractsawarded to third
parties.
7 O ther information.
8 Date of dispatch of the notice.
9 Date of receipt of the notice by the office for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.10
HOME
GACC
EDITION 2: FEB 1998
4G MODEL NOTICE OF WORKS AWARDED BY THE CONCESSIONAIRE
1 ( a) Site.
( b) The nature and extent of the service to be provided and the general nature
of the work.
2 Any time limit for the completion of the works.
3 Name and addressof the service from which the contract documentsand additional
documentsmay be requested.
4 ( a) The final date for receipt of requeststo participate and/or for receipt of
tenders.
( b) The addressto which they must be sent.
( c) The language or languagesin which they must be drawn up.
5 Any deposit and guaranteesrequired.
6 The minimum standardsof economic and financial standing and technical capacity
required of the contractor.
7 The criteria for the award of the contract.
8 O ther information.
9 Date of despatch of the notice.
10 Date of receipt of the notice by the office for official publicationsof the European
Communities.
ANNEX EPP 1.4
EC PROCUREMENT PROCEDURES
Annex EPP 1.4.11
HOME
GACC
EDITION 2: FEB 1998
ANNEX EPP 1.5
SERVICE CONTRACTS
Model Notices
Standard form responses, where they are relevant, have been included in italicsbeneath
the relevant sectionsof each notice.
Reference Description
5A INDICATIVE NO TICE
5B CO NTRACT NO TICE - O PEN PRO CEDURE
5C CO NTRACT NO TICE - RESTRICTED PRO CEDURE
5D CO NTRACT NO TICE - NEGO TIATED PRO CEDURE
5E CO NTRACT AWARD NO TICE
5F DESIGN CO NTEST NO TICE
5G RESULT O F DESIGN CO NTEST
5H MO DEL CANCELLATIO N NO TICE ( ALL SECTO RS AND ALL
PRO CEDURES)
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.1
HOME
GACC
EDITION 2: FEB 1998
SERVICES CONTRACTS - MODEL NOTICES
5A INDICATIVE NOTICE
1 Name, address, telegraphic address, telephone, telex and fax numbersof the
contracting authority and of the service from which additional information may be
obtained.
2 Intended total procurement in each of the service categorieslisted in Part A of
Schedule 1 of the ServicesRegulations( see Annex 1) .
3 Estimated date for initiating the award procedures, per category.
4 O ther information.
5 Date of dispatch of the notice.
6 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
5B CONTRACT NOTICE - OPEN PROCEDURE
1 Name, address, telephone, telex and fax numbersof the contracting authority.
2 Category of service and description. CPC reference number.
3 Place of delivery.
4 ( a) Indication of whether the provision of the service isreserved by law,
regulation or administrative provision to a particular profession.
( b) Reference of the law, regulation or administrative provision.
( c) Indication of whether legal personsshould indicate the namesand
professional qualificationsof the staff to be responsible for the execution of
the service.
5 Indication of whether service providerscan tender for some or all of the services
required.
6 Where applicable, prohibition on variants.
7 Period of contract or time limit, if any, for completion of the service.
8 ( a) Name and addressof the service from which the contract and additional
documentsmay be requested.
( b) Final date for making such requests.
( c) Where applicable, the amount and termsof payment of any sum payable for
such documents.
Not applicable
9 ( a) Personsauthorised to be present at the opening of tenders.
( b) Date, time and place of the opening.
10 Where applicable, any depositsand guaranteesrequired.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
11 Main termsconcerning financing and payment and/or referencesto the relevant
provisions.
12 Where applicable, the legal form to be taken by the grouping of service providersto
whom the contract isawarded.
No special legal form required but each service provider will be
required to become jointly and severally responsible for the
contract before acceptance
13 The information and formalitiesnecessary for an appraisal of the minimum standards
of economic and financial standing, ability and technical capacity required of the
servicesprovider.
14 Period during which the tenderer isbound to keep open itstender.
15 Criteria for the award of the contract ( and if possible their order of importance) .
Criteria other than that of the lowest price shall be mentioned where they do not
appear in the contract documents.
16 O ther information.
Tenders and all supporting documents must be priced in sterling and
all payments to be made under the contract shall be in sterling. The
contract shall be considered as a contract made in [England/Scotland]
and according to [English/Scots] Law and subject to the exclusive
jurisdiction of the [English/Scottish] Courts.
17 Date of dispatch of the notice.
18 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
5C CONTRACT NOTICE - RESTRICTED PROCEDURE
1 Name, address, telegraphic address, telephone, telex and fax number of the
contracting authority.
2 Category of service and description. CPC reference number.
3 Place of delivery.
4 ( a) Indication of whether the provision of the service isreserved by law,
regulation or administrative provision to a particular profession.
( b) Reference of the law, regulation or administrative provision.
( c) Indication whether legal personsshould indicate the namesand professional
qualificationsof the staff to be responsible for the provision of the services.
5 Indication of whether the service provider can tender for a part or all of the services
concerned.
6 If known, the number of servicesproviderswhich will be invited to tender or the
range within which that number isexpected to fall.
7 Where applicable, prohibition on variants.
8 Duration of contract, or time limit for completion of the service.
9 Where applicable, the legal form to be assumed by the grouping of service providers
to whom the contract isawarded.
No special legal form required but each service provider will be
required to become jointly and severally responsible for the contract
before acceptance
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
10 ( a) Where applicable, justification for the use of shorter time limits( accelerated
procedure) .
( b) Final date for the receipt of requeststo participate.
( c) Addressto which they must be sent.
( d) Language( s) in which they must be drawn up.
English
11 Final date for the despatch of invitationsto tender.
12 Where applicable, any depositsand guaranteesrequired.
13 The information and formalitiesnecessary for an appraisal of the minimum standards
of economic and financial standing, ability and technical standardsrequired of the
servicesprovider.
14 Criteria for the award of the contract. Criteria other than that of lowest price shall
be mentioned where these do not appear in the contract documents.
15 O ther information.
Tenders and all supporting documents must be priced in sterling and
all payments made under the contract will be in sterling. The
contract shall be considered as a contract made in [English/Scots] Law
and subject to the exclusive jurisdiction of the [English/Scottish]
Courts.
16 Date of dispatch of the notice.
17 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.6
HOME
GACC
EDITION 2: FEB 1998
5D CONTRACT NOTICE - NEGOTIATED PROCEDURE
1 Name, address, telegraphic address, telephone, telex and fax number of the
contracting authority.
2 Category of service and description. CPC reference number.
3 Place of delivery.
4 ( a) Indication of whether the provision of the service isreserved by law,
regulation or administrative provision to a particular profession.
( b) Reference of the law, regulation or administrative provision.
( c) Indication of whether legal personsshould indicate the namesand
professional qualificationsto the staff to be responsible for the provision of
the service.
5 Indication of whether the service providerscan tender for some or all of the services
required.
6 If known, the number of service providerswhich will be invited to tender or the
range within which that number isexpected to fall.
7 Where applicable, non-acceptance of variants.
8 Duration of contracts, or time limit for completion of the service.
9 Where applicable, the legal form to be assumed by the grouping of service providers
to whom the contract isawarded.
'No specol legol [orm requred but eoch servce provder wll be
requred to become jontly ond severolly responsble [or the controct
be[ore occeptonce'
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.7
HOME
GACC
EDITION 2: FEB 1998
10 ( a) Where applicable, justification for the use of the shorter time limits
( accelerated procedure) .
( b) Final date for the receipt of requeststo participate.
( c) Addressto which they must be sent.
( d) Language( s) in which they must be drawn up.
'nglsh'
11 Where applicable, any depositsand guaranteesrequired.
12 The information and formalitiesfor an appraisal of the minimum standardsof
economic and financial standing, ability and technical capacity required of the services
provider.
13 Where applicable, the namesand addressesof service providersalready selected by
the contracting authority.
14 O ther information.
15 Date of dispatch of the notice.
16 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
17 Datesof Previousof publicationsin the O fficial Journal of the European
Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.8
HOME
GACC
EDITION 2: FEB 1998
5E CONTRACT AWARD NOTICE
1 Name and addressof the contracting authority.
2 ( a) Award procedure chosen.
( b) Where applicable, justification for the use of negotiated procedure without
prior publication of a tender notice, ( Article 11( 3) ) .
3 Category of service and description. CPC reference number.
4 Date of award of the contract.
5 Criteria for award of the contract.
6 Number of tendersreceived.
7 Name( s) and address( es) of service provider( s) .
8 Price or range of prices( minimum/maximum) paid.
9 Where appropriate, value and proportion of the contract which may be
subcontracted to third parties.
10 O ther information.
11 Date of publication of the contract notice in the O fficial Journal of the European
Communities.
12 Date of despatch of the notice.
13 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
14. In the case of contractsfor servicesspecified in Part B of Schedule 1, agreement by
the contracting authority to publication of the notice ( Article 16( 3) ) .
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.9
HOME
GACC
EDITION 2: FEB 1998
5F DESIGN CONTEST NOTICE
1 Name, address, telegraphic address, telephone, telex and fax numbersof the
contracting authority and of the service from which additional documentsmay be
obtained.
2 Project description.
3 Nature of the contest: open or restricted.
4 In the case of open contests: final date for receipt of plansand designs.
5 In the case of restricted contests:
( a) the number of participantsenvisaged;
( b) where applicable, namesof participantsalready selected;
( c) criteria for the selection of participants;
( d) final date for receipt of requeststo participate.
6 Where applicable, indication of whether participation isreserved to a particular
profession.
7 Criteria to be applied in the evaluation of projects.
8 Where applicable, namesof the selected member of the jury.
9 Indication of whether the decision of the jury isbinding on the contracting authority.
10 Where applicable, number and value of prizes.
11 Where applicable, detailsof paymentsto all participants.
12. Indication of whether any follow-up contractswill be awarded to one of the winners.
13 O ther information.
14 Date of dispatch of the notice.
15 Date of receipt of the notice by the O ffice for O fficial Publicationsof the European
Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.10
HOME
GACC
EDITION 2: FEB 1998
5G RESULT OF DESIGN CONTEST
1 Name, address, telegraphic address, telephone, telex and fax numbersof the
contracting authority.
2 Project description.
3 Total number of participants.
4 Number of foreign participants.
5 Winner( s) of the contest.
6 Where applicable, the prize( s) awarded.
7 O ther information.
8 Reference to publication of the design contest notice in the O fficial Journal of the
European Communities.
9 Date of dispatch of the notice.
10 Date of receipt of the notice by the O ffice for O fficial Publicationsof the
European Communities.
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.11
HOME
GACC
EDITION 2: FEB 1998
5H MODEL CANCELLATION NOTICE (ALL SECTORS AND ALL PROCEDURES)
By corrigendum to tender notice.
1 Name and addressof contracting authority.
2 Nature and brief description of purchase ( ie works, supply or services) .
3 Date of publication and number of the tender notice in the O fficial Journal of the
European Communities.
4 O ther information.
'Ths controct hos been concelled.'
ANNEX EPP 1.5
EC PROCUREMENT PROCEDURES
Annex EPP 1.5.12
HOME
CST 1.0 COMMISSIONING STRATEGIES
CST 1.1 PRO CUREMENT PRO CESS AND PRO GRAMME
CST 1.2 APPLICATIO N O F EC PUBLIC PRO CUREMENT RULES
CST 1.3 PRO PERTY MAN AGEMENT TYPE CO MMISSIO NS
CST 1.4 INDIVIDUAL PRO JECT MAN AGEMENT T YPE CO MMISSIO NS
CST 1.5 INDIVIDUAL DISCIPLINE CO MMISSIO NS
CST 1.6 TERM CO MMISSIO NS
CST 2.0 COMMISSION FILE
CST 2.1 IDENTIFIC ATIO N
CST 2.2 SUB FILES
CST 2.3 RETENTIO N PERIO DS
CST 2.3( SCO T) RETENTIO N PERIO DS
CST 3.0 CONSULTANT SELECTION
CST 3.1 SELECTIO N O F FIRMS
CST 3.2 DETR N EW Q UALIFIC ATIO N SYSTEM ( NQ S)
CST 3.3 THE LO NG LISTING PRO CESS
CST 3.4 IDENTIFY PRE-SELECTIO N CRITERIA
CST 3.5 PRE-SELECTIO N INFO RMATIO N
CST 3.6 CO MPILATIO N O F SHO RT LISTS
CST 3.7 THE NUMBER O F TENDERERS
CST 3.8 Q UALITY PRICE MECHANISM
CST 3.9 PRE-TENDER INTERVIEW STAGE
CST 3.10 SINGLE T ENDER
HOME
CST 4.0 TENDER PROCESS
CST 4.1 GENERAL
CST 4.2 FO RMS O F T ENDERING
CST 4.3 TENDER DO CUMENTS
CST 4.4 TENDER PERIO DS
CST 4.5 TENDER BO X ES
CST 4.6 SECURE INFO RMATIO N
CST 4.7 DO CUMENTATIO N STANDARDS
CST 4.8 DISPATCH O F TENDERS
CST 4.9 Q UERIES BY TENDERERS
CST 4.10 TENDER BO ARDS
CST 4.11 O PENING THE TENDER BO X
CST 4.12 O PENING O F TENDERS
CST 4.13 THE T ENDER RECO RD BO O K
CST 4.14 LATE TENDERS
CST 5.0 TENDER EVALUATION
CST 5.1 EVALUATIO N CRITERIA
CST 5.2 FEE SCHEDULES
CST 5.3 INCENTIVE FEES
CST 5.4 EVALUATIO N PRO CEDURE
CST 5.5 TENDER ANO MALIES
CST 5.6 Q UALIFIED T ENDERS
CST 5.7 AMENDED TENDERS
CST 5.8 AMENDED TENDER DO CUMENTS
CST 5.9 RE-INVITATIO N O F TENDERS
CST 5.10 RECO MMENDATIO N FO R ACCEPTANCE
HOME
CST 6.0 AWARDING COMMISSIONS AND DECLINING
TENDERS
CST 6.1 LEGAL CO NTRACT FO RMATIO N
CST 6.2 ACCEPTANCE O F A T ENDER
CST 6.3 LETTER O F ACCEPTANCE
CST 6.4 DECLINE O F UNSUCCESSFUL TENDERS
CST 6.5 EX ECUTIO N O F FO RMAL AGREEMENT
CST 7.0 DEBRIEFING
CST 7.1 REQ UEST FO R DEBRIEFING
CST 7.2 DEBRIEFING INTERVIEWS
CST 8.0 MANAGEMENT COMMISSIONS
CST 8.1 RO LES AND RESPO NSIBILITIES O F THE CO MMISSIO N MAN AGER/
THE PRO JECT SPO NSO R
CST 8.2 CO NSULTANT AND SUB-CO NSULTANTS
CST 8.3 PRO FESSIO NAL INDEMNITY INSURANCE
CST 8.4 BILL PAYING AND CHECKING PRO CEDURES
CST 8.5 DETERMINATIO N/TERMINATIO N PRO CEDURES
CST 8.6 DETERMINATIO N/TERMINATIO N DUE TO DEFAULT
CST 9.0 CLAIMS AND DISPUTES
CST 9.1 HANDLING O F CLAIMS BY AND AGAINST THE DEPARTMENT
CST 9.2 CLAIMS ARISING FRO M DEFAULT O R NEGLIGENCE BY A DEPARTMENT,
CO NSULTANT O R CO NTRACTO R
CST 9.3 ALTERNATIVE DISPUTE RESO LUTIO N PRO CEDURES
CST 9.4 ARBITRATIO N
CST 9.5 WRITS AND SUMMO NSES
CST 9.6 EX GRATIA CLAIMS
CST 9.7 PERSO NAL INJURY CLAIMS
HOME
CST 10.0 PERFORMANCE REPORTING
CST 10.1 PERFO RMANCE REPO RTING GENERALLY
CST 10.2 PERFO RMANCE REPO RTING TO THE NEW Q UALIFICATIO N SYSTEM
( NQ S)
CST 10.3 CO NSULT N O TICES WITHIN NQ S
HOME
GACC
EDITION 2: FEB 1998
Determine requirementsand develop detailed brief
Identify capable consultantsto form a long list or if EC regulations
apply, advertise contract notice to invite expressionsof interest
Undertake pre-selection interviewswhere appropriate or if EC
regulationsapply, carry out pre-selection paper sift
Compile short listsfor tendering
Develop tender documentswhich clearly define the brief
Pre-tender interviewsaspart of quality assessment
Invite tendersfrom short listed consultants
Hold mid-tender interviewswhere appropriate
Evaluate tenders
Make the award and if EC regulationsapply publish contract award
notice
De-brief unsuccessful tenderswhere necessary
Post tender performance evaluation
PS2.1-2.5

CST 3.3

CST 3.5

CST 3.6

CST 4.3

CST 3.9

CST 4

CST 4.9

CST 5

CST 6

CST 7

CONSULTANTS SECTION
COMMISSIONING STRATEGIES
PROCUREMENT PROCESS & PROGRAMME
CST 10

CST 1.0 COMMISSIONING STRATEGIES


CST 1.1 PROCUREMENT PROCESS AND PROGRAMME
A guide to the stepsinvolved in the procurement of professional
servicesisasfollows:
CST 1.1.1
HOME
GACC
EDITION 2: FEB 1998
It should be borne in mind that thisisonly a guide to the steps
involved. The more complex or costly the service being procured then
the greater the amount of time and care that should be taken in the
pre-selection and selection processes.
Where the EC procurement rulesapply then the pre-selection process
with the restricted procedure will necessarily require a paper sift to
reduce what islikely to be an otherwise unmanageable number of
expressionsof interest.
A similar approach isrequired where a large number of consultantsare
invited to tender in order to establish a panel of consultantson the
basisof frameworksagreements, thisbeing a strategy that some
Department have successfully adopted. A panel isa set of consultants
who are selected for a term, without any guarantee of work, and might
be established by seeking tendersfor all regionsat once.
The form and basisof competition will need to be determined early in
the procurement process. Thiswill involve deciding upon which
proceduresit isappropriate to follow, and most importantly the
evaluation criteria which will be used to determine the successful
tenderer. In particular the basison which the price will be sought and
the way in which quality will be evaluated should be decided at the
outset.
Procurement Programme
It isrecommended that careful consideration isgiven to the production
of a procurement programme immediately following identification of
commission or project objectives. Clearly thisprogramme should be
developed in the context of the overall objectivesand timetable. The
procurement programme will to a large extent depend upon the
procurement strategy which isto be followed, and should be updated
at each stage of the procurement process. The Department should
ensure that there issufficient time allowed in the programme and
expertise isavailable to carry out each of the above steps.
EPP 1.8

CST 3.1

CST 3.8

CONSULTANTS SECTION
COMMISSIONING STRATEGIES
PROCUREMENT PROCESS & PROGRAMME
CST 1.1.2
HOME
GACC
EDITION 2: FEB 1998
It isrecommended that the greater the complexity of the commission,
then the greater the time that should be allowed to tenderersto
consider, price and submit their tender bids. Tender periodswhich are
too short can lead to an inadequate consideration of the requirements
of the commission by tendererswhich may lead to under-pricing or
over-pricing and possibly to unwanted misunderstandings.
Where the EC procurement directivesapply, then specific procedures
apply and there are specific minimum or maximum time limitsfor the
variousstagesof the processdepending on which procedure is
followed. These will need to be reflected in the procurement
programme.
Anx EPP 1.3

CONSULTANTS SECTION
COMMISSIONING STRATEGIES
PROCUREMENT PROCESS & PROGRAMME
CST 1.1.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 1.2 APPLICATION OF EC PUBLIC PROCUREMENT RULES
It ismandatory that EC public procurement rulesare complied with
where they are applicable. It isalso essential that consultantsapply the
ruleson behalf of the Department, where they are dealing with sub-
consultants. A clear obligation to do so should be included in the terms
of appointment of such consultants( see for example service A1.2.16
for the project manager in the Consultant Commissioning
Documentation - GC/Works/5 - General Conditionsfor the
Appointment of Consultants( 1998) ( ISBN 0-11-7023108) .
The EC procurement rules, govern the procurement of most of the
servicesrequired by Government bodies.
A commission will be subject to the ServicesDirective if:
the buyer isa contracting authority subject to the regulations;
the value of the contract isabove the threshold. The construction
servicesgenerally procured by Departmentswill fall under Part A of
the Public ServicesContractsRegulationsto which the GATT
threshold of 130,000 SDR applies. The pound sterling equivalent is
revised every two years, and asof 1 January 2000 thisfigure is
93,896;
it isnot the subject of one of the exclusions.
It isillegal to split the contract into two or more partsor breakdown
what isnormally a centrally purchased aggregated contract to avoid the
application of the rules. In addition there should be no deliberate
underestimating to avoid compliance.
Key Points
If the value of the commission exceeds93,896 ( asof 1 January
2000) the EC servicesregulationsmay apply.
A more detailed consideration of whether the regulationsapply is
given in chapter EPP - EC Procurement Procedures, which also sets
out the specific timetablesand recommended procedures, for
inviting and evaluating tendersin accordance with the rules.
EPP

EPP 1.5

EPP 1.4

EPP 1

EC PUBLIC PROCUREMENT RULES


CONSULTANTS SECTION
COMMISSIONING STRATEGIES
L
! !! !!
CST 1.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 1.3 PROPERTY MANAGEMENT TYPE COMMISSIONS
The Property Management Commission will usually be awarded to a
consultant for a three year term.
The property manager will effectively take control of all functions
including:
estatesservices;
maintenance;
works.
CONSULTANTS SECTION
COMMISSIONING STRATEGIES
PROPERTY MANAGEMENT TYPE COMMISSIONS
CST 1.3
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 1.4 INDIVIDUAL PROJECT MANAGEMENT TYPE COMMISSIONS
A project manager ( PM) will generally be appointed for major Works
Projectsand will be appointed to take overall control of the Project.
The PM isrequired at two discrete stages:
for feasibility studiesand development of the Departmentsbrief;
for managing the workson site.
It isgenerally recommended that the two stagesare fulfilled by two
separate project management organisations.
CONSULTANTS SECTION
COMMISSIONING STRATEGIES
INDIVIDUAL PROJECT MANAGEMENT TYPE COMMISSIONS
CRS 9.1

CST 1.4
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 1.5 INDIVIDUAL DISCIPLINE COMMISSIONS
Where there are specific or one-off requirementsfor consultant
servicesit isnot appropriate to appoint consultantson a term contract.
Termsand conditionsin respect of the following servicesare contained
in the WorksCommission consultant documentation - GC/Works/5
General Conditionsfor the Appointment of Consultants( 1998) - ISBN
0-11-7023108:
project manager or lead consultant
architect/building surveyor
quantity surveyor
structural engineer
building servicesengineer
INDIVIDUAL DISCIPLINE COMMISSIONS
CONSULTANTS SECTION
COMMISSIONING STRATEGIES
CST 1.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 1.6 TERM COMMISSIONS
A term commission can be used where there isdefinable and expected
repetitive work over a period of time. The recommended duration for
term commissionsisthree years.
The principal advantagesof term commissionsare:
three year termsreduce the cost to the Department of the
procurement activity;
consultantswill bid competitively if they can be assured of a
continuousflow of work for a known period;
consultantshave time to develop a clear understanding of the
Departmentsneedsand should be able to work more effectively to
satisfy those needs.
The typesof activitieswhich are generally appropriate for term
commissionsare:
property management commissions;
project management and design and cost serviceswhere there isan
ongoing building programme;
audit services;
legal services.
GC/Works/5, General Conditionsof Appointment of Consultants:
Framework Agreement ( 1999) ( ISBN 0-11-7023329) issuitable for
appointing a range of construction professionalsfor a period of three
to five yearson a call off basis.
TERM COMMISSIONS
CONSULTANTS SECTION
COMMISSIONING STRATEGIES
CST 1.6
HOME
GACC
EDITION 2: FEB 1998
CST 2.0 COMMISSION FILE
CST 2.1 IDENTIFICATION
Each Department islikely to have an existing system for numbering
identifying and opening new commission files. Thissection istherefore
provided by way of guidance and describespointsof general
importance and application. When the need for a commission hasbeen
identified, consideration should be given to the following important
points:
each commission should have a reference code assigned to it. It
should identify the Department aswell asa unique reference
number for the commission;
it isgenerally common practice to open a registered file which is
assigned the commission reference number, and which containsall
of the papersrelating to the commission;
it isgood practice to use the unique reference number in all
correspondence relating to the commission, and to insist that all
partiesto the commission also use the reference number in their
correspondence;
it islikely that the commission file will comprise a number of files
and sub filesand all such filesshould also be assigned the unique
reference number;
an important aspect of the commissioning file isthat it providesa
record of procurement practice adopted. The file or filesare then
available to demonstrate that stepshave been taken to procure
servicesin a way which aimsto achieve best value for money.
The documentsin the commission file are likely to include:
recordsof meetingsat which mattersaffecting the setting up of the
commission were discussed;
minutesrequesting and giving financial and contractual approval to
further action;
recordsof the pre-selection processfor choosing the firms( copies
of the corporate brochure or general information about a firm need
not be retained on the commission file) ;
IDENTIFICATION
CONSULTANTS SECTION
COMMISSION FILE
CST 2.1.1
HOME
GACC
EDITION 2: FEB 1998
recordsof formal interviewsand recommendationstherefrom;
recordsof EC advertisement and replies, if applicable;
the businesscase including:
- a record of the pre-tender estimate;
- a schedule of potential project risks;
- a record of the consideration of PFI alternatives, where
appropriate;
a record of the proposed tender evaluation criteria;
a set of the tender documentsasissued to tenderers( other than
standard printed documents) ;
copiesof correspondence during the tender period;
admissible tendersreceived, placed in a folder;
the tender summary sheet;
any correspondence pertaining to consideration of the tenders;
the evaluation report and recommendation to accept a tender;
the appropriate delegated approval to accept a tender;
a copy of the acceptance letter together with the acknowledgement
of acceptance by the successful tenderer;
a copy of the decline letter sent to unsuccessful tenderers;
copiesof any requestsfor debriefing by unsuccessful tenderers
together with the Departmentsresponse.
Key Points
Recordsare required to demonstrate that best value for money has
been sought.
Recordsmay also be essential to demonstrate that tenderershave
not been unfairly excluded in the event that EC Procurement
procedureshave to be followed, and a challenge israised by an
unsuccessful tenderer.
IDENTIFICATION
CONSULTANTS SECTION
COMMISSION FILE
CST 2.1.2
HOME
GACC
EDITION 2: FEB 1998
CST 2.2 SUB FILES
Each stage of the commission processcan produce bulky documents
( firms presentation documents, tender documents, firms bids, and
evaluation reportsetc.) . It istherefore recommended that, where such
documentsmay be easily separated from the main file, sub filesare
created to hold these documents.
Each sub file should carry the unique commission reference number,
and it iscommon to give each sub file an alphabetical suffix. Where sub
filesare created, it isrecommended that an index of sub filesisheld at
the front of the main file.
SUB FILES
CONSULTANTS SECTION
COMMISSION FILE
CST 2.2
HOME
GACC
EDITION 2: FEB 1998
CST 2.3 RETENTION PERIODS
There are four principle reasonsfor retaining commission files:
1. To provide recordsfor use asan aide memoire for future projects.
2. To provide a record for auditing purposes, especially in respect of
commissionsprocuredin accordance with EC public procurement
rules.
3. To comply with legal obligationsto do so. In accordance with the
CDM Regulationsthe Department isunder an obligation to keep
available for inspection a health and safetyfile for what amountsto
the entire life ofthe building.
4. To provide evidence of the agreement and of the conduct of the
commission in the event of legal action, which either the
Department feelsappropriate to take, or against whichthe
Department isrequired to mount a defence.
In the case of legal action the periodsfor which the Department may
have legal liability are limited by statute, and vary depending on the
circumstances.
The minimum period issix yearsfrom the date of the breach. If the
contract isby deed, however, the period is12 years. The position is
more complex in respect of liability for negligence where the periodsof
liability may be determined by reference to the Latent DamagesAct
1986. Dutiesof care may be owed by the project manager, the
designersand the contractor for periodsof up to 15 years, and in some
casesbeyond. Thisshould therefore be taken into account when
assessing the retention period for all documentsrelating to major
worksprojects.
It isrecommended that documentsrelating to unsuccessful tenders
should be retained until completion of the commission.
LE 2.1

LE 1.9

RETENTION PERIODS
CONSULTANTS SECTION
COMMISSION FILE
CST 2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
LE 2.1

LE 1.9

RETENTION PERIODS
CONSULTANTS SECTION
COMMISSION FILE
CST 2.3(S)
CST 2.3( SCO T) RETENTION PERIODS
There are four principle reasonsfor retaining commission files:
1. To provide recordsfor use asan aide-memoire for future projects.
2. To provide a record for auditing purposes, especially in respect of
commissionsprocured in accordance with EC public procurement
rules.
3. To comply with legal obligationsto do so. In accordance with the
CDM Regulationsthe Department isunder an obligation to keep
available for inspection a health and safety file for what amountsto
the entire life of the building.
4. To provide evidence of the agreement and of the conduct of the
commission in the event of legal action, which either the
Department feelsappropriate to take, or against which the
Department isrequired to mount a defence.
In the case of legal action the periodsfor which the Department may
have legal liability are limited by statute, and vary depending on the
circumstances.
Remember that the vast majority of all contractual obligationswill
expire under the short negative prescription, ie after five yearsfrom
the date when the obligation becomesenforceable, if the necessary
conditionsare satisfied. Before an obligation prescribes, however, the
relevant period of time must have passed without any relevant claim
( see LE 1.9) by the creditor, or anyrelevant acknowledgement ( again,
see LE 1.9) by the debtor.
It isrecommended that documentsrelating to unsuccessful tenders
should be retained until completion of the contract.
LE 1.9

HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.0 CONSULTANT SELECTION
CST 3.1 SELECTION OF FIRMS
The principle aim of the procurement processisto select a consultant
which offersthe best value for money. Thiswill nearly alwaysinvolve a
processof competitive tendering. Value for money for a particular
commission meansoptimising the balance between best performance
or quality of service and lowest price. The aim isalwaysto secure and
maintain the quality of service received.
To avoid complacency and therefore secure ongoing competitive
performance, aswell asavoiding questionsof favouritism, it is
recommended that the frequent use of the same consultant or the
same list of consultantsisavoided. Care must also be taken to enforce
standard conditionsof consultancy contractsif an ex-employee of a
Department iscontracted with, and thisshould only be asthe result of
an open tender. Aswith using the same consultant frequently, such
consultanciescan be viewed with suspicion, resulting in accusationsof
favouritism or nepotism. Finally, it should be kept in mind that
consultantsare not employeesof the Department, and should
therefore be maintained at arm'slength contractually.
It may be that in exceptional circumstancesthe timescale or the type of
commission necessitate the appointment of a consultant on the basisof
a single tender action. Thismeansthat the competitive processisnot
followed and generally that the contract and in particular price are
negotiated with one consultant. Where such a procedure isunavoidable
it will normally be necessary to obtain the appropriate delegated
authority before proceeding.
Because of the difficulty of assessing and evaluating quality prior to
delivery of the service, it isimportant to have in place procurement
procedureswhich provide asearly aspossible to the Department, as
much information aspossible about the likely quality of the service
offered by tenderers.
It should also be borne in mind that if any consultant hasa role in the
direct commissioning of construction worksor where he actson behalf
of a Department, he will be covered by the Construction Industry Tax
Scheme.
CST 3.10

SELECTION OF FIRMS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.1.1
LE 2.11

HOME
GACC
EDITION 2 REV 2: JAN 2000
Keep a list of
consultantswho
serve you well or
have served you
well in the past
Gather market
intelligence about
consultants
including
references
regarding past
performance
Confirm consultantsinterest
Identify pre-selection criteria
For larger commissionseg
for project management,
request a statement of
interest in the form of a
questionnaire
Where unfamiliar with
consultantsarrange pre-
selection interviewsto
assessbasic abilities
Evaluate pre-selection data and form short list
Inform consultantsof outcome
The following stepsare therefore recommended in order to obtain a
short-list of suitable consultantsfor tender:
Where the EC procurement rulesapply then the pre-selection process,
using the restricted procedure, will be asfollows:
SELECTION OF FIRMS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.1.2
Consult DETR
Constructionline
Register ( NQ S)
for development
of the long list
Identify long list
HOME
GACC
EDITION 2 REV 2: JAN 2000
O Jcontract notice and UK advertisementsspecifying the basison
which the pre-selection will be carried out.
Initial paper sift
Appraisal of expressionsof interest
O ffice visits( optional)
Financial checks
Pre-qualification interview ( optional)
Pre-qualification scoring
The next stage of the selection processisthe invitation of tendersand
choice of consultant. The following stepsare recommended in order to
select a consultant from the short list:
Decide on award criteria, in particular weighting of quality
and price
Send out tender documentsincluding detailed brief requesting a
submission by consultant of method statement prior to attending a
pre-tender interview
Decide on need for pre-tender interview at which quality of service
required and understanding of the brief isconsidered
(continued
overleaf)
SELECTION OF FIRMS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.1.3
Check consultant tendersfor conformity and evaluate price and
quality against stated criteria
Award contract
HOME
GACC
EDITION 2 REV 2: JAN 2000
Advise all consultants
Debrief if requested
The stepsinvolved in obtaining a short list and in selecting the
successful consultant set out above need not be rigidly adhered to in
every case.
Simple or small standard commissionsmay not require either pre-
selection or pre-tender interviewsfor example.
The remainder of part CST 3 and partsCST 4-7 of thissection give
detailed guidance in relation to each of the above steps.
In certain circumstancesthe negotiated procedure, with advertising,
may be used instead of the restricted procedure if one or more of the
following derogationsapply:
exceptionally, when the nature of the servicesto be provided, or the
risksattaching thereto, are such asnot to permit prior overall
pricing;
when the nature of the servicesto be provided, in particular in the
case of intellectual servicesor financial servicesspecified in category
6 of Part A of Schedule 1 of the Public ServicesContracts
Regulations, issuch that specificationscannot be drawn up with
sufficient precision to permit the award of the contract using the
open or restricted procedure.
Under the negotiated procedure the processisthe same asthe
restricted procedure up to pre-qualification scoring. Following this, the
contracting authority may negotiate the termsof the contract with
those companiesit hasselected. These negotiationsshould be
consistent with the agreed award criteria. Authoritiescan choose to
invite initial proposalsand further sift the candidates, following which
they may invite tendersor even, if they so choose, negotiate down
from the short list to a single provider and ask him to submit a bid.
Key Point
A consultant iscovered by the Construction Industry Tax Scheme if
he hasa role in the direct commissioning of construction worksor
where he actson behalf of a Department in thiscontext.
SELECTION OF FIRMS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.1.4
LE 2.11

HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.2 NEW QUALIFICATION SYSTEM (NQS - FORMERLY CONREG)
Constructionline isthe name of the service which utilisesthe NQ S
database. Where the EC procurement rulesdo not apply, then the long
list of contractorscan normally be obtained from the NQ S.
Itspurpose isto validate prior to tender, the financial standing,
managerial capability, technical competence and resource capacity of
bona fide firmswishing to undertake a wide variety of construction and
property related services. The NQ S isfree of charge to clientsand isa
powerful tool designed to minimise the risk of the user against
company failure, poor workmanship and fraud. The data helpsto ensure
that public bodiesonly deal with reputable firmsand financially sound
companiesand savestime and valuable resourcesin the vetting of firms
being considered for an invitation to tender.
The NQ S includesdetailsof a firmsstaffing, specialismsof work a
consultant can undertake, current and completed work recorded as
feedback by the users, and an assessment of the maximum individual
contract value a firm may accommodate ( the notation) .
Departmentscan accessthe NQ S on-line, under the auspicesof a BT
managed telecommunicationsservice. The IT Helpdesk and client
liaison responsibility are located in Edinburgh.
Anydepartment, agency or NDPB wishing to accessthe NQ S will
need to do so via an on-line computer link. Any requestsfor Access
Packsor additional information/advice can be obtained from the
contactslisted overleaf.
Key Point
More detailed information on the NQ S iscontained in CAU
Information Note 27/98. A copy can be obtained by phoning the
C AU Helpdesk on 020 7271 2833.
CONSULTANTS SECTION
CONSULTANT SELECTION
NEW QUALIFICATION SYSTEM (NQS)
CST 3.2.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
CONSULTANTS SECTION
CONSULTANT SELECTION
NEW QUALIFICATION SYSTEM (NQS)
CST 3.2.2
Organisation Structure of Constructionline
Head O ffice for Constructionline and the processing responsibility for
firmsbased in England, Wales, Scotland and Northern Ireland islocated
at:
Constructionline
Great West House
Great West Road
Brentford
Middlesex
TW8 9DF Tel: 020 8380 4600
Constructionline Director: ChrisLeggett
Development Director: Colin Garton
O perationsManager: Paula Beresford
* Client helpdesk and technical support iscurrently located at:
Constructionline
The Basement
17 Atholl Crescent
Edinburgh
EH3 8HA Tel: 0131 229 9449
*Note:the processing responsibility for firms based in Scotland moved to
the Brentford office in October 1998 but the client helpdesk and technical
support responsibilities have been retained.
IT Helpdesk Tel: 0870 607 1602
Client ServicesManager Tel: 0870 607 1602
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.3 THE LONG LISTING PROCESS
The production of the long list isthe first step towardsestablishing a
viable tender list which will ensure genuine competition among capable
suppliers.
The long list will be compiled from the following possible sources:
NQ S;
market intelligence gathered by the Department;
list of consultantswho have serviced the Department well in the
past.
It isrecommended that the long list be limited to 10 in number.
The key criteria for selection of firmsfor the long list are:
experience in the general area of the commission;
track record on similar commissions.
It may be useful at thisstage to ask firmswho are not known to the
Department to provide brochuresand possibly referencesto confirm
experience and track record.
When the long list hasbeen fixed, a preliminary enquiry should be sent
to each firm on the list to ask them to confirm without obligation that
they are interested, that they have the resourcesand that they will
submit a tender if asked.
It isrecommended that repliesare requested in writing and by a given
date.
Key Points
An example preliminary enquiry isgiven in the form of CST/SF1
overleaf.
THE LONG LISTING PROCESS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 1 - LETTER
Preliminary Enquiry Letter
Dear Sir
PRELIMINARY ENQUIRY RE [TITLE OF PROJECT]
The [Scottish Ministers]/[Secretary of State] acting through [ Department] intend( s) to
commission [state professional service] in connection with the above project. Brief
particularsare [enclosed/asfollows:]
The following isthe proposed procurement programme in connection with this
commission:
Date of invitation to tender: ..............................................................................
Date of contract award: ........................................................................................
Commencement of Commission: ...................................................................
Duration of Commission: .....................................................................................
You are invited to confirm in writing your interest in being included in the tender list by
....................... [Date]. Please also advise usof any special reasonswhich you consider support
the inclusion of your company on the tender list.
You should note that a negative response will not prejudice your companysprospectsof
being invited to tender in the future.
Please also note that the detailsgiven in thispreliminary enquiry may change and neither
thisenquiry nor your positive reply to it in any way guarantee that you will be included on
the final tender list or that the commission will proceed at all. In addition the above
information isto be treated asstrictly confidential.
Yoursfaithfully
CST3/SF1
THE LONG LISTING PROCESS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.3.2
HOME
GACC
EDITION 2: FEB 1998
CST 3.4 IDENTIFY PRE-SELECTION CRITERIA
In order to form a final short list, it isnecessary to establish the criteria
to be applied in evaluating those firmson the long list, and to decide
which criteria are most important given project requirement. The
greater the extent to which the brief hasbeen defined, then the more
focused the pre-selection evaluation can be.
The key criteria for pre-selection are asfollows:
track record on similar commissions, in termsof:
- approach ( method of working, management, client liaison) ,
- technical ability,
- performance to quality, time and cost constraints,
- professional resourcesand support facilitiesavailable;
qualification of key staff;
financial standing;
adoption of a quality management system;
outline suggestionsfor approaching the commission, in termsof:
- experience of the proposed project manager/team leader,
- how the commission will be organised and managed,
- technical, managerial or design method;
and anyproject specific requirementssuch as:
location of consultantsoffices;
specific expertise, such asknowledge of language or procedures.
O nce these criteria have been established then the pre-selection
information must be obtained for evaluation.
IDENTIFY PRE-SELECTION CRITERIA
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.4
HOME
GACC
EDITION 2: FEB 1998
CST 3.5 PRE-SELECTION INFORMATION
Having compiled the long list and decided upon the pre-selection
criteria to be used to evaluate those on the list, pre-selection
information must be gathered.
Where the Department isunfamiliar with a firm on the long list, or
uncertain about the firmsabilitiesin a certain field, then the best means
of gathering information isby arranging a pre-selection interview.
A brief should have been developed by thisstage, and more value can
be obtained from the meeting if the project specific brief isprovided to
the consultant before the meeting. Specific questionscan be asked
about the firmsinitial viewson how they would approach the
commission and who might be expected to do the work. If a
preliminary enquiry hasbeen sent, and the firm hasresponded
positively, then standard form 2 - Request for preliminary interview may
be sent enclosing the brief. ( See CST3/SF2) .
It isrecommended the two membersof the Department attend the
interview. Neither member should have any conflict of interest with the
firm being visited.
The meeting should be arranged with the firmskey personnel at the
consultantsoffices. Much information may be gathered from such a
meeting, such as:
overall expertise;
the range of work that the firm would be interested in doing;
any special areasof Consultant expertise;
resourcesand support facilities;
use of IT;
financial soundness;
apparent efficiency of staff and the way the office isrun;
nature of staff employed;
office size and location.
PRE-SELECTION INFORMATION
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.5.1
HOME
GACC
EDITION 2: FEB 1998
The purpose of the interview isfor the Department to assessthe
suitability of the firm for Government work in the required area. It is
also an opportunity for the firm to get to know you and find out more
about your specific needs, potential work programme, and way of
working.
For larger type commissionsit isadvisable to prepare a questionnaire
which specifically addressesthe chosen pre-selection criteria. A
response should be requested by a specific date. The consultant should
be asked to give information about each of the pre-selection criteria
and specifically to indicate likely team size, membersand relevant
experience.
Key Points
Pre-selection interviewsare a useful way of finding out about
companiesand the market generally.
PRE-SELECTION INFORMATION
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.5.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 2 - LETTER
Request for Pre-Selection Interview
Dear Sir
[TITLE OF PROJECT]
Thank you for you positive response to our preliminary enquiry dated [date].
A copy of the provisional brief isenclosed. We will shortly be inviting competitive bidsfor
thiscommission and intend to select a short list of consultantsfor the competition. We
would therefore like to meet you at your officesto discussthe type of work you undertake
and to assessyou suitability for thiscommission in termsof the following:
For example:
overall expertise and experience;
the range of work that you are interested in doing;
special areasof consultant expertise;
expertise and experience relevant to thisproject;
resourcesand support facilities;
use of IT;
financial soundness.
Please contact me to arrange a suitable appointment
Yoursfaithfully
CST3/SF2
PRE-SELECTION INFORMATION
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.5.3
HOME
GACC
EDITION 2: FEB 1998
CST 3.6 COMPILATION OF SHORT LISTS
When all pre-selection information hasbeen gathered, and evaluated,
the short-list can be produced. The number of tenderersselected for
the short list will depend on the size and complexity of the project.
Those who are not short listed should be advised in writing. Standard
Form 3 - exclusion notification, may be sent ( see CST 3/SF3) . There are
two alternative paragraphsdepending on whether or not a pre-
selection interview washeld.
CST 3.7

COMPILATION OF SHORT LISTS


CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.6.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 3 - LETTER
Exclusion Notification
Dear Sirs
[TITLE OF PROJECT]
Thank you for your letter of [date] expressing an interest in being invited to tender for the
above contract.
[or, ( if attended pre-selection interview) : Thank you for the opportunity of meeting you on
[date] to discussyour firm and the above project].
After careful consideration I must advise you that on thisoccasion the Department does
not intend to invite you to tender.
Please be assured that thisdecision in no way affectsthe prospect of you being invited to
tender for suitable work in the future.
Yoursfaithfully
CST3/SF3
COMPILATION OF SHORT LISTS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.6.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.7 NUMBER OF TENDERERS
O ther than in very unusual circumstances, contractorsand consultants
are not directly reimbursed for the coststhey incur in preparing
tenders. Thisisan overhead to the businessin question. O ne of the
waysof contributing to increased industry efficiency encouraged by the
Latham Report, isto reduce the cost of tendering. Departmentsmay
make an important contribution in thisrespect by keeping to a
minimum the number of firmswho are invited to tender.
The number of firmsselected for the short list would depend on the
type and size of commission, but it isgenerally recommended that 3 or
4 firmsare selected.
Where the EC rulesapply and the restricted procedure isbeing used,
the contracting authority may specify the range in the Contract Notice
from within which the number of tendererswill be invited to bid. The
lower number of the range must not be lessthan 5 and the higher
number not more than 20.
If an authority choosesnot to specify a range then it isfree to invite
any number of biddersprovided it issufficient to ensure genuine
competition ( normally not lessthan 3) .
It isrecommended that in any event no more than 6 consultantsare
invited to tender.
Where the Department isseeking to establish a national panel of say
10 architectural consultantson the basisof framework agreements
then it isappropriate to invite tendersfrom say 30 consultantsin one
go. Clearly thisisthe equivalent of 10 separate commissionsand so the
ratio of three tenderersto one contract ismaintained.
EPP 1.11

NUMBER OF TENDERERS
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.7
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.8 QUALITY PRICE MECHANISM
The final decision asto which consultant offersthe best value for
money will be determined by:
the size and scope of the commission;
the complexity of the commission;
quality considerationsof tenderers, such asqualifications, experience
and track record etc.;
the pricesoffered by tenderers.
In coming to a final decision it isworth bearing in mind that the
labourer isworthy of hisor her hire. Best practice private sector clients
and Departmentshave all learnt to their cost that the cheapest bid
doesnot necessarily result in overall long term best value for money.
Cut price tendersusually result in cut price inputs, where more work is
carried out by lessexperienced professionalsor technicians, and the
Department suffersasa result of a lessattentive service provider.
It istherefore important to consider both quality and price during the
evaluation. The term best value for money meansselecting a consultant
who offersthe optimum combination of quality and price. Hence, these
factorsshould be considered in the final choice of consultant.
A very useful approach to tender evaluation isto use a quality/price
mechanism which isbased on a numerical scoring and weighting
system. The advantagesof thisare that:
it formaliseswhat can be a very subjective evaluation process;
it requiresforethought asto what are the most important criteria
for selection;
it can be transparent;
it can be audited.
QUALITY PRICE MECHANISM
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.8.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
The quality/price mechanism should be decided upon at the outset of
consultant procurement. The Tender Board should be appointed at this
stage for thispurpose. If the brief continuesto be developed it may be
necessary to change some of the evaluation criteria and or their
weightings, but the mechanism should be finalised before pre-tender
interviewscommence.
The finalisation of the quality/price mechanism involvesdeciding upon
the following:
the quality criteria which will be used; standard form CST3/SF7 isan
example of quality marking sheet;
the weighting which should be attached to each of the chosen
criteria;
the quality price ratio; in other wordsthe relative importance of
quality and price.
The weighting of quality against price will be influenced by the
complexity of the project and the degree of creativity or flexibility that
isrequired in itsexecution. For example the more complex the project,
the harder the project will be to manage and control; the more unusual
the project the harder it will be to make predicationsabout resource
levelsand the more skill that will be required of the consultant.
Experience, technical competence, management skill and management
systemswill take on a far more significant level of importance for
complex projects. For the quality/price mechanismsto reflect thisshift
in balance, more weight should be given to quality criteria than to
price.
Indicative quality/price ratiosfor consultant servicesare asfollows:
Type of project Indicative quality/price ratio
Feasibility studies 80/20 to 90/10
Innovative projects 70/30 to 85/15
Complex projects 60/40 to 80/20
Straightforward projects 30/70 to 60/40
Repeat projects 10/90 to 30/70
CST 4.10

CST 3.9

QUALITY PRICE MECHANISM


CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.8.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
QUALITY PRICE MECHANISM
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.8.3
Key Points
The final selection should be based both on quality and price.
The numerical/price mechanism isa useful decision support tool but
there may be good reasonswhy the final choice may nevertheless
require some subjective judgement.
Any decision asto the final choice of consultant must be justifiable
on the basisthat the consultant offersoverall long-term best value
for money.
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 3.9 PRE-TENDER INTERVIEW STAGE
Purpose
The pre-tender interview stage isthe first of a two part tender
evaluation process. The purpose behind the pre-tender interview isto
provide for the separate initial evaluation of quality. The short list may
be further reduced asa result of thisquality evaluation, and only those
who satisfy the quality requirements/quality threshold of the
commission will be invited to submit a price.
Enquiry
A date and time should be arranged for pre-selection interviewswith
each of the short listed consultants. Each consultant should be
contacted to confirm their availability to attend a meeting at the
required time.
It isessential that the consultant, or principal consultants, who will be
expected by the consultant firm to carry out the commission is/are
actually available to attend the interview. If the consultant already has
the brief then thisshould be stipulated at the time of arranging the
meeting. If not then thisshould be confirmed after the consultant has
received the full tender documentsreferred to below.
Send out Tender Documents
Having determined availability to attend the pre-tender interview, an
invitation letter issent ( see CST3/SF4) . The consultant isnot actually
invited to tender at thisstage, but isprovided with the brief and
conditionsof engagement so that the consultant may give detailed
consideration to the project requirementsand determine which
resourcesare appropriate to carry out the commission. If any of the
consultantshave not already done so then they should be provided
with a questionnaire to be completed and returned prior to the
interview. ( An example questionnaire isprovided in the form of
CST3/SF5) .
CST 4.3

PRE-TENDER INTERVIEW STAGE


CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Reasonable time should be allowed for the following:
consultantspreparation of their submission;
consultantsresponse to the questionnaire;
consideration of submissionsand any questionnaire by the proposed
membersof the interview panel ( usually three membersof the
Department) ;
confirming attendance of each consultantsproposed team.
When submissionsare received they should be circulated to all
membersof the panel for their scrutiny. The panel should focuson any
areasof weaknesses, and highlight the need for specific questionsin the
interview.
Although optional, a Department may choose to carry out a
preliminary scoring of each of the consultantssubmissionsprior to
interview, on a score sheet ( See CST/SF7) . These scorescan then be
re-visited post-interview.
The Interview
The pre-tender interviewsshould be held at the Departmentsoffices.
It isrecommended that consultantsare kept from meeting one-another,
otherwise thismay affect pricessubsequently submitted.
It isalso recommended that the pre-tender interview isattended by a
panel of three membersof the Department, one of whom is
nominated chairman to lead the meeting, and that the meeting is
limited to a duration of one hour. For an example of an agenda see
CST3/SF6.
It isadvisable to allow sufficient time between interviewsto allow for
an overrun in interview time and to allow for the quality scoring of the
consultant by each panel member.
Each consultant should be treated fairly and equally and each
interviewer should be objective. Prior to the interviews, the panel
should set aside time to discussand agree the nature of questionsand
specific questionsto be asked of each consultant.
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Within the framework of the example agenda ( see CST3/SF6) , the
principal areaswhich should be covered in the interview are:
the consultantsunderstanding of the commission;
the way in which the consultant might expect to handle the
commission;
the clarification of ambiguitiesby either side;
the clarification of any particular areasof concern amongst panel
members;
the development of a clearer understanding of each others
requirements.
Q uestionsshould be directed to ensure that each panel member has
sufficient information to score each consultant. An example score sheet
isgiven at CST3/SF7, and thiswill be completed by each panel member
at the conclusion of each interview. Note that thissheet hasexamples
of weightingsfor each criteria, but that each one isscored out of 100.
The weightingsare subsequently applied to determine the overall
weighted average quality score.
It isalso essential that one of the panel memberskeepsnotesof who
attended, answersto questions, and in particular any undertakingsgiven
by a consultant.
At the completion of all interviews, the chairman leadsa review of the
comparative findingsof the panel, and producesa summary sheet for
each consultant which consolidatesthe marksof individual panels
members. An example summary sheet isgiven at CST3/SF8. Formal
recommendation will than be prepared which identifiesthose which
should be included on the final tender list.
It isnot the intention of thisprocessto result in the selection of a final
short list of consultantswho all have an equal quality score, but merely
to exclude those who are considered unsuitable or fall short of a pre-
determined quality threshold.
If it isdecided to exclude any firmsfrom the short list at thisstage then
they should be sent a decline letter in the form suggested by CST3/SF9.
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
Key Points
The purpose of the pre-tender interview isto assessquality not
price.
Each consultant should be treated equally and fairly.
It isessential to keep recordsof all questions, scoring and decisions
so that an audit trail isavailable.
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 4 - LETTER
INVITING CONSULTANT TO ATTEND FORMAL INTERVIEW
Dear Sirs
[TITLE OF PROJECT]
The [Scottish Ministers]/[Secretary of State] acting through [ Department] intend( s) to
commission ........................... [state professional service] in connection with the above .
The provisional brief and Conditionsof Engagement for the commission isenclosed, and it
isanticipated that the following services, asdefined in the conditionsof appointment
described above, will be required:
It must not be assumed that conditionsare unchanged from previouseditions.
It isexpected that the fee competition for thiscommission will be on the basisof a
..................................... [specify either lump sum, or time chargesor percentage of the project
value].
You are invited to attend a selection interview which will last an hour with representatives
of [ Department] on ....................[date] at ...................... [time] in ..................................... [address] to
discusshow you would propose to carry out the servicesrequired, your experience of
similar projectsthe structure and available resourcesof your practice, workloads, facilities,
special expertise and the detailsof the principal and senior staff whom you propose would
be responsible for the project. The [Department] will detail itsrequirementsand method of
working and will answer questionsyou may have during the interview. [A questionnaire is
enclosed which I would be grateful if you would complete and return to me by ................].
Following the interviews, [selected] consultantswill be invited to submit their fee proposals
which will be taken into account when deciding which consultantsshould be awarded the
commission.
Will you please confirm assoon aspossible that the proposed date and time for the
interview isconvenient to you and let me know who will be attending. It isof course, for
you to decide who should attend the interview but we would expect to meet the
proposed account manager and senior consultant who will be responsible for the day to
day operation of thiscommission.
Please note the [ Department] isnot bound to accept your proposal.
Yoursfaithfully
CST3/SF4
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 5 - QUESTIONNAIRE
FOR COMPLETION AND SUBMISSION BY CONSULTANT PRIOR TO
ATTENDING PRE-TENDER INTERVIEW
QUESTIONNAIRE
Please give detailsof the following:
( 1) O utline how the brief would be tackled.
( 2) The structure, resources, organisation, and location of the office which would
undertake the commission.
( 3) Name, qualificationsand summary of relevant experience of Partner/Principal/
Director proposed asresponsible for the commission and any other Partners/
Principals/Directorswho may be involved and the anticipated extent of their
involvement.
( 4) Namesand qualificationsof senior staff likely to have involvement with the
commission and the input they are likely to have over the life of the commission.
( 5) Experience of commissionsof comparable size, complexity and nature in UK and
overseas.
( 6) Previousexperience in working for Departmentsand other public authorities.
( 7) Confirmation of whether all the specialist experience or expertise necessary for this
commission isavailable from within the practice. If thisspecialist experience or
expertise isnot so available how and from whom it would be obtained.
( 8) Computer facilitiesand experience which are available, highlighting any specialist
techniques.
( 9) Insurances, indemnities, securitieswhich are held; or would be taken out for this
commission. The level of insurance must meet the [Departments] requirements.
( 10) What Q uality Assurance schemes/systemsoperate.
CST3/SF5
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.6
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 6 - AGENDA
SAMPLE AGENDA FOR FORMAL INTERVIEW OF CONSULTANTS
AGENDA
( Allow maximum of 1 hour to complete)
a) Chairman welcomesFirms representativesand introducesinterviewing panel
members.
b) Chairman outlinespurpose and structure of interview and time to be allowed.
c) Firms presentation ( approx. 20 mins)
d) Interview panel questions( approx. 30 mins)
e) Q uestionsfrom Firm/Clarification of any point.
f) Chairman to close
CST3/SF6
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.7
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 7 - SCORE SHEET
INTERVIEW ASSESSMENT FORM
Commission Commission Commission Commission Commission T itle T itle T itle T itle T itle

Firm: Firm: Firm: Firm: Firm:


Represented by: Represented by: Represented by: Represented by: Represented by:

Panel Member: Panel Member: Panel Member: Panel Member: Panel Member:

CST3/SF7
Connents
1. Appreciation of the commission
2. Calibre of relevant professional staff.
Accounting and management skills
and depth of experience
3. Q uality of account manager ( for the
whole commission)
4. Approach to undertaking the
commission, including resources
allocated and ability to cope with
peak workloads
5. Experience of similar commissions
(A)
Weigbt in g
20
20
20
20
5
(B)
Marks
(out of 100)
(A) (B)
weigbted
narks
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.8
HOME
GACC
EDITION 2: FEB 1998
Connents
6. Experience of public sector work
7. Q uality Assurance/Checking systems
8. Specialist advice to be bought in
(A)
Ma
5
10
N/A
(B)
Marks
(out of 100)
N/A
(A) (B)
weigbted
narks
N/A
Mark awarded 100
SIGNATURE: DATE:
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.9
HOME
GACC
EDITION 2: FEB 1998
CST3/SF8
STANDARD FORM 8 - SCORE SHEET
INTERVIEW SUMMARY SHEET
1. Name of Company: ...................................................................................................................................................
2. Represented By: ...........................................................................................................................................................
3. Name of Commission: .............................................................................................................................................
4. Commission Ref No: ................................................................................................................................................
5. Date of Interview: ......................................................................................................................................................
6. Time of Interview: ......................................................................................................................................................
7. Summary of O verall Assessment Markings: ..............................................................................................
P PP PPAN EL M EM BERS AN EL M EM BERS AN EL M EM BERS AN EL M EM BERS AN EL M EM BERS MARKIN G MARKIN G MARKIN G MARKIN G MARKIN G T TT TTO OO OO T TT TTA LS A LS A LS A LS A LS
( WEIGHT ED SCO RE) ( WEIGHT ED SCO RE) ( WEIGHT ED SCO RE) ( WEIGHT ED SCO RE) ( WEIGHT ED SCO RE)
PANEL MARKING TOTAL
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.10
HOME
GACC
EDITION 2: FEB 1998
8. Comments: ..........................................................
..........................................................
..........................................................
..........................................................
9. ChairmansSignature: ..........................................................
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.11
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 9 - LETTER
MODEL LETTER TO UNSUCCESSFUL SHORT LISTED FIRMS
Dear Sir
[TITLE OF PROJECT]
Thank you for attending at these officesfor interviewson
After careful evaluation of your proposal I must advise you that yourswasunsuccessful and
you will not be invited to provide a fee bid on thisoccasion.
Please be assured that thisdecision in no way affectsthe prospect of you being invited to
tender for suitable work in the future.
Yoursfaithfully
CST3/SF9
PRE-TENDER INTERVIEW STAGE
CONSULTANTS SECTION
CONSULTANT SELECTION
CST 3.9.12
HOME
GACC
EDITION 2: FEB 1998
CST 3.10 SINGLE TENDER
In the case of some specialist worksor work of an experimental
nature, competition may not alwaysbe possible or practicable. In such
situationssingle tender action may be unavoidable.
Before single tender action issanctioned, special care should be taken
to ensure that other consultantsare not capable of providing the
required service.
It should be remembered that single tender action maynot lead to the
best possible value for money.
Single tender action must be sanctioned by the appropriate authority in
accordance with the laid down delegations.
The submission for authority to proceed with single tender action
should give clear and convincing reasonsfor taking such action and a
copy of that submission and subsequent approval must be kept on the
commission file for future reference.
The EC ServicesDirective setsrestrictionson negotiated commissions
which exceed the EC thresholdsand these must be considered prior to
approving single tender action.
Key Points
It may be acceptable in exceptional circumstancesto pursue a single
tender action procurement route, but thiswill usually require
obtaining the appropriate delegated authority.
SINGLE TENDER
CONSULTANTS SECTION
CONSULTANT SELECTION
EPP 1.8

CST 3.10
HOME
GACC
EDITION 2: FEB 1998
CST 4.0 TENDER PROCESS
CST 4.1 GENERAL
The tender processinvolvesthe invitation by the Department to
tenderersto submit their price in respect of the proposed commission.
Where the consultant procurement proceduresrecommended by the
guide are being followed, then the quality assessment will already have
been carried out. If thisisthe case, then during the tender period the
consultant will have only to review the level of resourcesrequired and
submit the price. However, the price itself may have implications
regarding resourcing. Since resourcing isa quality issue thisaspect in
particular may necessitate a re-appraisal of the quality score arrived at
after completion of pre-tender interview.
The principal stagesin the tender processare asfollows:
Determine sufficient time for tender period
Issue tender invitation and tender documentsto tenderersenclosing
label and specific date time and addressfor return
Deal with tenderersqueriespromptly - and advise all other
tenderersof information given
Place all tendersreceived in the tender box
Sort tenderersby name or preferably by price and assign a unique
tender number to each
List tendersreceived, not received, on tender summary sheet
Prepare clear, consistent and comprehensive tender documents
Facilitate any site visitsrequired by tenderers
List tender number, opening date, name and price in tender
record book
GENERAL
CONSULTANTS SECTION
TENDER PROCESS
CST 4.1.1
HOME
GACC
EDITION 2: FEB 1998
By way of introduction, the following are the key pointswhich relate to
the tender invitation and operating process:
the guidance given here appliesnot only to the Department but to
any consultantsprocuring consultant commissionson behalf of the
Department;
it may be appropriate to check tenderersagainst NQ sto ensure
that there hasbeen no change of statussince the longlist was
prepared;
in order to ensure consistency of information provided to tenderers
it isrecommended that only one person in the Department actsas
a contact; thishelpsto ensure the fair treatment of all tenderers;
it isrecommended that tendersare alwaysreturned to the
Departmentsoffices, where they should be kept securely ( in a
tender box) until they are opened;
from the time of opening to award of contract, tendersshould be
kept securely and all tender information treated asstrictly
confidential;
a clear audit trail should be established.
The proceduresfor tender receipt, opening and evaluation which
follow may seem onerous, but it isessential to have proceduresin place
which protect the individualsinvolved from claimsof corruption or
impropriety, and which ensure that the tenderersare participating in a
fair competition.
Key Points
Tendersshould be kept secure from the time of receipt until the
final award of contract.
Clear recordsmust be kept of each step.
GENERAL
CONSULTANTS SECTION
TENDER PROCESS
CST 3.2

CST 4.1.2
HOME
GACC
EDITION 2: FEB 1998
CST 4.2 FORMS OF TENDERING
The intention behind the pre-tender interview stage isto evaluate
quality separately from and ahead of price, before a final decision which
combinesthe two.
Although not the preferred approach, there isan alternative method of
keeping tendererssubmissionson quality and price separate. Thisis
known asthe double - envelope method. Where the quality and price
elementsof the tender are submitted in separate envelopes. Thismay
take two different forms:
the common approach isfor all consultantstechnical envelopesto
be opened and evaluated; all consultantsprice envelopesare then
opened and evaluated separately; the consultant with the most
favourable combination isthen selected;
the alternative approach isthat selection ison quality only; i.e. only
one price envelope isopened, that of the best quality tenderer; the
price envelopesof the unsuccessful tenderersare returned.
The problem with the latter option isthat there isno way of ranking all
consultantsby combination of quality and price and therefore no way
of knowing whether the selected tender offersthe best value for
money option.
FORMS OF TENDERING
CONSULTANTS SECTION
TENDER PROCESS
CST 3.9

CST 4.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 4.3 TENDER DOCUMENTS
The tender documentsshould specify the Departmentsrequirements
aswell asthe consultantsobligations, particularly since thisinformation
isthe basisof the contract price.
The tender documentation will therefore consist of the following main
elements:
the conditionsof engagement;
the specific dutiesrequired of the consultant;
the brief related to the commission.
The conditionsof engagement or contract will define the allocation of
risks, obligationsof the parties, the basison which the price isto be
tendered ( e.g. hourly rates, lump sum, ad valorem ( percentage of overall
capital cost) remediesin the event of failure by a party to perform its
obligationsetc.
The specific dutiesare normally a schedule of duties, in the form of a
shopping list which the consultant will be expected to carry out. These
will obviously vary according to the scope of the commission and the
type of consultant being engaged.
The brief can be considered asa specification of the Departments
needsin respect of the work required. In the case of a major works
commission thiswill normally be a fairly detailed specification of
premisesneeds, service requirementsetc. In the case of estatesservices
commissionsthe brief would commonly set out a schedule of premises,
lease terms, anticipated rent review periodsand property management
requirements.
Lack of clarity or ambiguity in documents, create weaknessesor
opportunitieswhich the consultant may exploit in order to increase the
final cost and/or delay the time for delivery.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
It isimportant therefore that the tender documentssatisfy the
following essential requirements:
the documentsshould be specific about what isrequired;
the documentsshould be without ambiguity; these and any
documentswhich are a record of negotiationsthat are subsequently
incorporated ascontract documents, should all be consistent with
one another;
the conditionsmust clearly allocate risksasbetween consultant and
Department and specify who must pay what in the event of
variationsor delay.
Documentation for inviting tenderswhether compiled by the
consultant or the Department, should ideally comprise the following:
invitation letter;
the brief;
list of tender documents;
conditionsof engagement;
notesfor tenderers;
standard acknowledgement slip ( See CST4/SF1) ;
instructionsfor submitting tenders;
tender offer form;
tender return Label ( See CST4/SF2) .
Note that the instructionsto tenderersshould include information
about a point of contract ( the premisesmanager for example) with
whom tendererscan make arrangementsto visit a site or building,
where thisisthe subject of a commission.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.2
HOME
GACC
EDITION 2: FEB 1998
To minimise the risk and impact of individual consultants, or members
of a consultantsteam, switching employersduring a construction
related negotiation and re-appearing asan adviser to the opposing side,
precautionary measuresshould be put in place. Thismight be especially
pertinent, for example in the case of a claimsnegotiation on a building
contract or during lease or rent negotiations.
Therefore Departmentsshould ensure that conditionsof engagement
for property or worksconsultantsinclude a requirement for each
individual member of the consultantsteam to sign a confidentiality
undertaking before commencing work in connection with the
commission.
A model clause isshown at CST4/SF3 whilst a model undertaking is
shown at CST/SF4.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.3
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 1
ACKNOWLEDGEMENT SLIP
Tenderersare requested to complete thisslip and return it to
....................................................................................................................................................................................................
[Departmental address] immediately upon receipt of the tender documents.
PRO JECT/CO MMISSIO N TITLE: ..........................................................................................................................
DEPARTMENT REFERENCE NO : .......................................................................................................................
DEPARTMENT LIAISO N O FFICER: ...................................................................................................................
( asstated in the invitation letter)
1. I acknowledge receipt of tender documentsfor the above project/commission.
( either) *
2. I will submit my tender by the due date.
( or) *
2. I do not wish to tender on thisoccasion and return the documentsherewith.
Signed: ........................................................................................................................
For and on behalf of ..........................................................................................
..........................................................................................................................................
..........................................................................................................................................
Date: ...........................................................................................................................*
*Delete asappropriate
CST4/SF1
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.4
HOME
GACC
EDITION 2: FEB 1998
C
S
T
4
/
S
F
2
A
F
F
I
X
P
O
S
T
A
G
E
S
T
A
M
P
S
H
E
R
E
D
E
P
A
R
T
M
E
N
T
A
L

A
D
D
R
E
S
S
T
e
n
d
e
r
F
O
R

C
O
N
T
R
A
C
T

N
O
:
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
R
e
t
u
r
n
a
b
l
e

n
o
t

l
a
t
e
r

t
h
a
n

1
1
.
0
0

h
r
s

o
n
:
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
N
o
t
e
s
:
1
.
T
h
e

e
n
v
e
l
o
p
e

t
o

w
h
i
c
h

t
h
i
s

l
a
b
e
l

i
s

a
t
t
a
c
h
e
d

m
u
s
t

n
o
t
b
e
a
r

a
n
y

i
n
d
i
c
a
t
i
o
n

o
f

t
h
e

t
e
n
d
e
r
e
r

s

n
a
m
e
.
2
.
I
t

i
s

t
h
e

t
e
n
d
e
r
e
r
s

r
e
s
p
o
n
s
i
b
i
l
i
t
y

t
o

e
n
s
u
r
e

t
h
a
t

t
h
e
t
e
n
d
e
r

i
s

d
e
l
i
v
e
r
e
d

b
y

t
h
e

d
u
e

t
i
m
e
.

T
e
n
d
e
r
s

r
e
c
e
i
v
e
d
a
f
t
e
r

t
h
i
s

t
i
m
e

w
i
l
l

n
o
t

b
e

c
o
n
s
i
d
e
r
e
d
.
3
.
T
e
n
d
e
r
s

t
o

b
e

d
e
l
i
v
e
r
e
d

b
y

h
a
n
d

a
r
e

t
o

b
e

h
a
n
d
e
d

i
n

a
t
t
h
e

r
e
c
e
p
t
i
o
n

d
e
s
k

a
n
d
/
o
r

p
l
a
c
e
d

i
n

t
h
e
[
D
E
P
A
R
T
M
E
N
T

S
]

T
E
N
D
E
R

B
O
X
.
S
T
A
N
D
A
R
D

F
O
R
M

2
T
E
N
D
E
R

R
E
T
U
R
N

S
L
I
P
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.5
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 3
CONFIDENTIALITY
Each party:
a) shall treat asconfidential all information obtained from the other
Party under or in connection with the Contract;
b) shall not disclose any of that information to any third party without
the prior written consent of the other Party, except to such persons
and to such extent asmay be necessary for the performance of the
Contract; and
c) shall not use any of that information otherwise than for the
purposesof the Contract.
The Contractor shall take all necessary precautionsto ensure that all
information obtained from the Authority under or in connection with
the Contract:
a) isgiven only to the minimum number of Staff and then only to the
extent necessary for each member of Staffsactivitiesin the
provision of the Services; and
b) istreated asconfidential and not disclosed ( without prior Approval)
or used by any Staff otherwise than for the purposesof the
Contract.
Where it isconsidered necessary in the opinion of the Authoritys
Representative, the Contractor shall ensure that Staff sign a
confidentiality undertaking before commencing work in connection
with the provision of the Services.
The provisionsof thisCondition shall not apply to any information:
a) which isor becomespublic knowledge ( otherwise than by breach of
thisCondition) ; or
b) which isin the possession of the Party concerned, without
restriction asto itsdisclosure, before receiving it from the disclosing
Party; or
c) which isreceiving from a third party who lawfully acquired it and
who isunder no obligation restricting itsdisclosure.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST4/SF3
CST 4.3.6
HOME
GACC
EDITION 2 REV 2: JAN 2000
Nothing in thisCondition shall prevent the Authority:
a) disclosing such information relating to the outcome of the
procurement processfor the Contract asmay be required to be
published in the Supplement to the O fficial Journal of the European
Communitiesin accordance with EC directivesor elsewhere in
accordance with requirementsof Scottish Government and/or
United Kingdom government policy on the disclosure of information
relating to government contracts;
b) disclosing any information obtained from the Contractor:
i) to any Scottish Minister, Minister of the Crown, government
agency or department ( including the Comptroller and Auditor
General, National Audit O ffice, the Auditor General for Scotland
and Audit Scotland) , regulatory or fiscal body, or the Scottish
Parliament or the United Kingdom Parliament ( including, in both
cases, itscommittees) , each of whom may disclose the
information in their reports. For the avoidance of doubt, the
Authority shall have no responsibility for Confidential
Information which appearsin reportsof the activitiesor
proceedingsof any of the foregoing; or
ii) to any Person engaged in providing any servicesto the Authority
for any purpose relating to or ancillary to the Contract, provided
that in disclosing information under sub-paragraph ( i) or ( ii) the
Authority disclosesonly the information which isnecessary for
the purpose concerned and requiresthat the information is
treated in confidence and that a confidentiality undertaking is
given where appropriate.
Nothing in thisCondition shall prevent either Party from using any
techniques, ideasor know-how gained during the performance of the
Contract in the course of itsnormal business, to the extent that this
doesnot result in a disclosure of confidential information or an
infringement of any Intellectual Property Rights.
The Contractor shall not use any confidential information obtained
from the Authority for the solicitation of businessfrom the Authority
or any other part of the Crown in right of Her Majesty'sGovernment
in the United Kingdom or in right of the Scottish Administration.
The obligationsimposed by thisCondition shall continue to apply after
the expiry or termination of the Contract.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.7
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 4
CONFIDENTIALITY UNDERTAKING
In connection with a contract between [..................................] and
[..................................] for the provision of .................................. services. To be
signed by personsemployed in providing the servicesbefore being
given accessto Government information.
I am employed by [name of Consultant]. I have been informed that I
may be required to work for my employer in providing servicesto the
[full name of Authority].
I understand that information in the possession of the [..................................]
or obtained from the [..................................] must be treated asconfidential.
I hereby give my formal undertaking, asa solemn promise to the
[..................................], that:
1 I will not communicate any of that information, or any other
knowledge I acquire about the [..................................] in the course of my
work, to anyone who isnot authorised to receive it in connection
with that work.
2 I will not make use of any of that information or knowledge for any
purpose apart from that work.
I acknowledge that thisappliesto all information that isnot already a
matter of public acknowledge and that it appliesto both written and
oral information.
I also acknowledge that thisundertaking will continue to apply at all
timesin the future, even when the work hasfinished and when I have
left my employment.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST4/SF4
CST 4.3.8
HOME
GACC
EDITION 2 REV 2: JAN 2000
I have also been informed that I will be bound by the provisionsof the
O fficial SecretsActs1911 to 1989. I am aware that under those
provisionsit isa criminal offence to disclose information which has
been provided by [ Department] in connection with the above contract.
I am aware that seriousconsequencesmay follow any breach of those
provisions.*
SIGNED: ................................................................
Surname: ................................................................
Forenames: ................................................................
Date: ................................................................
ConsultantsName ................................................................
Contract Reference No. ................................................................
*Thisoptional paragraph may be deleted if the consultant isunlikely to
come into contact with material which carriesa security classification.
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.3.9
HOME
GACC
EDITION 2 REV 2: JAN 2000
MODEL SIGNATURE FORMAT FOR USE UNDER SCOTTISH REGIME
1 I acknowledge and agree that thisUndertaking shall be governed by, and construed in
accordance with, the law of Scotland and the partiesprorogate the jurisdiction of the
Scottish courtsso far asnot already subject thereto: IN WITNESS WHEREO F these
presentsconsisting of thisand the [ insert no] preceding page( s) are executed asfollows:
for and on behalf of [insert name of consultant] (Consultant)
at .................................. on .................................. 200[ ] by:
....................................... ( Director'ssignature) .................................. ( Director/Co Sec'ssignature)
....................................... ( full name) .................................... ( full name)
(use style above if company) / (use style below if individual or firm)
by the Consultant:
At .................................. on .................................. 200[ ]
.................................................................... ( signature)
.................................................................... ( full name)
.................................................................... ( title)
in the presence of:
.................................................................... ( signature of witness)
..................................................................... ( full name)
...................................................................... ( address)
.......................................................................
CST 4.3.10
TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER PROCESS
HOME
GACC
EDITION 2: FEB 1998
CST 4.4 TENDER PERIODS
The time allowed from issue of tender documentsto the date by which
the tenderersoffer must be returned isknown asthe tender period.
The tender period allowed to tenderersto submit their bid will depend
on the nature and complexity of the project. A minimum of 2 weeks
and a maximum of 6 weeksshould be allowed for tendering depending
on the size and complexity of the services. Allowance should be made
for the need for site visitsor for gathering information or quotations
necessary to prepare the offer, aswell asfor public holidays.
If pre-tender interviewshave been held then consultantswill already
have given consideration to the requirementsof the commission and
the resourcesthey anticipated will be required to carry out the
commission. If thisisso then, subject to the need for information
gathering, the lower end of the range i.e. 2-3 weeksought to be
adequate time for consultantsto submit their price.
Where the EC procurement rulesapply, minimum tender periodsare
stipulated.
Key Points
It issuggested that the tender period should be a minimum of 2
weeksand a maximum of 6 weeks.
It may be advisable to contact tenderersbefore hand to ensure that
tender periodsare feasible.
TENDER PERIODS
CONSULTANTS SECTION
TENDER PROCESS
EPP 1.8

CST 4.4
HOME
GACC
EDITION 2: FEB 1998
CST 4.5 TENDER BOXES
Arrangementsshould be made for a suitably-sized tender box to be
provided marked [Department] TENDER BO X . The box should be
designed so that it issecure and all tendersreceived can be placed in
the box and remain there until the date and time for opening.
Tendersreceived should be stamped with the date and time received
before being placed in the tender box.
The box should be solidly built and be large enough to hold all the
tenderslikely to be received during the period between tender boards,
bearing in mind that tenderersoften include large or bulky documents
aspart of their submission.
The box should be fitted with two separate locksand the keysshould
be held by two different individualsnominated by the commission
manager/project sponsor. The box should have a letter-box type
opening so that tenderscan be inserted but cannot be taken out
without opening the locks.
TENDER BOXES
CONSULTANTS SECTION
TENDER PROCESS
CST 4.5
HOME
GACC
EDITION 2: FEB 1998
CST 4.6 SECURE INFORMATION
No classified information should be disclosed in tender documentsor
drawingsunlessthe disclosure isabsolutely necessary for the
preparation of tenders. In such casesthe tender documentsshould be
drawn up so that documentscontaining classified information may
easily be identified and isolated.
Classified documentsshould be transmitted in accordance with the
instructionsin the Departmental Security Handbook and consultants
should be acquainted with these procedureswhere applicable.
SECURE INFORMATION
CONSULTANTS SECTION
TENDER PROCESS
CST 4.6
HOME
GACC
EDITION 2: FEB 1998
CST 4.7 DOCUMENTATION STANDARDS
All tender documentation must be type-written and documentsthat
are required to be completed and returned with the tender SHO ULD
BE ISSUED IN DUPLIC ATE with an instruction to the tenderer to
retain a copy for itsrecords.
An adhesive tender return label showing the tender reference number
together with the time, addressand date of return should be issued
with the invitation documents. An example of a tender label isshown
at CST4/SF2.
In the case of single tendersthere should be nothing either in the
tender documentsor on the return label to indicate to the tenderer
that it isa single tender.
DOCUMENTATION STANDARDS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.7
HOME
GACC
EDITION 2: FEB 1998
CST 4.8 DISPATCH OF TENDERS
The current addressesof all tenderersshould be established before
sending out tenders. It isalso important that the tender ismarked for
the attention of the correct person within each organisation, otherwise
the tenderer may lose valuable time in preparing the tender.
The sendersname and address( either the Departmentsor the
Consultantsaddress) should be entered on the back of each
dispatched tender envelope to ensure the quick return of any tender in
the event of non-delivery. A locally produced rubber stamp could be
used for thispurpose.
If a tenderersdocumentation isreturned by the Post O ffice marked
GO NE AWAY, enquiriesshould be made to try and ascertain the
correct address.
O nce thishasbeen established, the NQ S should be notified so that the
relevant database can be updated.
Dependant on the speed with which the tender hasbeen returned,
consideration should be given to dispatching the tender again to the
correct address, and perhapsconsideration given to extending the
tender period.
DISPATCH OF TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 3.2

CST 4.8
HOME
GACC
EDITION 2: FEB 1998
CST 4.9 QUERIES BY TENDERERS
All firmsshould be dealt with in exactly the same way. They should be
given the same documentation and the same accessto further
information.
Ideally there should be a clarification period following the issue of the
tender documentsduring which the Department may provide further
information in response to queriesby tenderers. The answer to a query
from a tenderer, should be confirmed in writing and any supplementary
information which hasto be issued asa result, should be copied
simultaneously to all other tenderers, without making reference to the
questions.
Although it isintended that questionspertaining to the commission
should be dealt with during the pre-tender interview, it may be
appropriate to hold mid-tender interviews. Mid-tender interviewscan
be very useful for exchanging information. The Department can
frequently benefit from the questionsposed by tenderersand any
constructive comment from them. Mid-tender interviewsshould be
held separately with each tenderer. Avoid allowing tenderersto attend
the officesat the same time or to see other namesin a signing-in book.
Where queriesresult in a significant change then an extension of the
tender period should be considered.
Viewing of Properties
If tenderersask to view propertiesduring the tender period, thismay
be arranged by the Department through the premisesmanager for the
building in question.
Standard form CST4/SF5 isan example letter that may be sent to a
premisesmanager instructing him or her to co-ordinate appointments
to view the property. Any queriesshould be referred back to the
departmental representative responsible for inviting tenders.
Key Points
All tenderersshould be dealt with equally and fairly.
Additional information should be provided in writing to all
tenderers.
QUERIES BY TENDERERS
CONSULTANTS SECTION
TENDER PROCESS
L
! !! !!
CST 4.9.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 5 - LETTER
LETTER TO PREMISES MANAGERS REGARDING VIEWING OF PROPERTIES BY
TENDERERS
COMMERCIAL-IN-CONFIDENCE
Dear ............................................................................................................................
[PremisesManager]
................................................................................................................................................................................................................
[Title of Project/Commission]
1. You may be aware that it isthe intention of [Department] to appoint a consultant
to undertake the above mentioned project/commission.
2. Following recent selection interviews....... companies, namely .............................................. ......
.................................................................................................................................................................................................
.................................................................................................................................................................................................
.................................................................................................................................................................................................
.................................................. [list tendersnames] will be invited to tender. During the
tender period [state tender period included dates] the selected firmsmay wish to
view the following properties:
............................... .................................................................................................................................................................
............................................................... [list properties].
The firmswill be given your name asa contact point and asked to contact you to
arrange a convenient time to view.
3. You will appreciate that during the tender period, the list of companiesinvited to
tender must remain confidential and that in order to ensure parity of tendering,
tenderersmust be allowed to inspect the propertiesindividually. Tenderersshould
not be brought into contact with one another.
4. The person responsible for showing tenderersaround the property should
therefore be made aware of the need for maintaining confidentiality with regard to
the namesof other tenderersand should resist pressure from tenderersto divulge
information that may be to the tenderers advantage but which isnot given in the
tender documents. The [Department] commission manager/project sponsor for this
commission is...................... [name] who should be contacted immediately if any
problemsare encountered during thisperiod.
5. May I take thisopportunity to thank you for you co-operation in thismatter.
Yourssincerely
COMMERCIAL-IN-CONFIDENCE
QUERIES BY TENDERERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.9.2
CST4/SF5
HOME
GACC
EDITION 2: FEB 1998
CST 4.10 TENDER BOARDS
A tender board, typically comprising three people should be appointed
to open and record bids. It isrecommended that the following
conventionsbe followed:
one member should be a senior chairperson;
one member should be completely independent from the
commission; thishelpsto establish the credibility of the board, as
impartial;
total impartiality isachieved through choosing different tender
board membersfrom those on the tender evaluation panel.
To promote propriety, it helpsif a member of the board appointsno
more than one other member, i.e. chairman appointsthe secretary, the
secretary appointsthe third person.
It isthe responsibility of the senior board member to ensure that all
membersare conversant with tender board and tender opening
proceduresand the tender documents.
TENDER BOARDS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.10
HOME
GACC
EDITION 2: FEB 1998
CST 4.11 OPENING THE TENDER BOX
Tendersshould be opened on the same day asthe date for return and
shortly after the hour specified for return.
If, asisrecommended, a tender box isbeing used, then the joint key
holderswill have to first open the tender box. O nly those tenders
relevant to the commission in question should be removed.
Late Tenders
The tender box should be checked daily after the required tender
return date to check for late tenders. Late tendersshould be dealt with
in accordance with section CST 4.14.
OPENING THE TENDER BOX
CONSULTANTS SECTION
TENDER PROCESS
CST 4.14

CST 4.11
HOME
GACC
EDITION 2: FEB 1998
CST 4.12 OPENING OF TENDERS
Prior to the opening of tenders, the commission manager/project
sponsor should provide the tender board with a list of all those invited
to tender. Thisenablesthe tender board to identify those who have not
submitted tendersor subsequently those whose tendersare received
late.
When the tender box isopened, the unopened tendersshould be
passed directly to the tender board, and to no-one else.
The following stepsshould then be followed by the tender board:
tenderersshould ideally be opened in a locked room with no
working telephone;
if the tender board isdealing with tendersfor a number of
commissionsthen it will need to sort tendersby their unique tender
number and deal separately with the tendersfor each commission;
opened tendersfor a commission should be sorted according to
price or in the alphabetical order of the tenderers name;
any unpriced tendersare not complete tendersand should
therefore be rejected and returned stating the reason for rejection;
where a tender document hasa tendererssignature at the end of it,
each page of that document should be signed by the senior
member of the tender board; thismay be speeded up by the use of
a personal facsimile signature stamp;
each tender should then be given a sequential number to prevent
later insertion of other tenders.
a tender summary sheet should then be completed ( CST4/SF6) ; on
the sheet should be listed the sequential tender numbersnamesof
tenderersfrom whom tenderswere received and their price; names
of those who did not submit tenders, should also be given together
with the reason if known;
the tender summary sheet relatesto the tendersfor a particular
commission and should be completed and signed by the senior
tender board officer;
the tender summary sheet and opened tendersshould be delivered
by hand or, if necessary sent by registered post to a member of the
tender evaluation panel.
OPENING OF TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.12.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 6
TENDER SUMMARY SHEET
[Department]
TENDERS - SUMMARY SHEET
Commission/Contract File No:
...................................................................................................................................................................................
........................................................
LO CATIO N
NAME O F CO NTRACT/CO MMISSIO N
ESTIMATED CO ST
DATE
Tendersaslisted below, have today been opened and authenticated by the Tender O pening
Board. Also listed are the namesof those firmsthat did not wish to tender, together with
those that did not respond to the tender invitation
To:
...................................................................................................................................................................................
..................................................................
Will you please examine the enclosed tendersand provide your recommendation assoon
aspossible
Signed: ..............................................................................................................................................................................................
Senior Tender Board O fficer
CST4/SF6
OPENING OF TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.12.2
HOME
GACC
EDITION 2: FEB 1998
CST 4.13 THE TENDER RECORD BOOK
A Tender Record Book isa proforma book used for recording all
tendersfor all commissionsopened on a given day. It istherefore a
running record of all tendersopened. An example format isgiven at
CST4/SF7.
The Tender Record Book isinvaluable for senior officersand auditors,
asthe first step in any review of tendering activity since it providesa
complete reference record of allocated tender numbers.
It isimportant that the sequence of numbersshould remain unbroken.
Tender board membersshould sign the tender record book once
tender opening hasbeen completed, confirming the next number in
the sequence.
Thispreventsany irregularitiessuch asthe addition of a late tenderer
to the tender list without prior approval of the tender board and
without clear reasonsfor so doing.
THE TENDER RECORD BOOK
CONSULTANTS SECTION
TENDER PROCESS
CST 4.14

CST 4.13.1
HOME
GACC
EDITION 2: FEB 1998
S
T
A
N
D
A
R
D

F
O
R
M

7
T
e
n
d
e
r

R
e
c
o
r
d

B
o
o
k
C
O
M
M
E
R
C
I
A
L
-
I
N
-
C
O
N
F
I
D
E
N
C
E
T
E
N
D
E
R

R
E
C
O
R
D

B
O
O
K
[
D
E
P
A
R
T
M
E
N
T
]
S
E
R
I
A
L

N
O
C
O
N
T
R
A
C
T
/
T
I
T
L
E

O
F
N
A
M
E

O
F
T
E
N
D
E
R
D
A
T
E

A
N
D

T
I
M
E
N
O
T
E
S

O
N
S
I
G
N
A
T
U
R
E

O
F
O
F

T
E
N
D
E
R
S
C
O
M
M
I
S
S
I
O
N

N
O
C
O
N
T
R
A
C
T
/
C
O
M
M
I
S
S
I
O
N
F
I
R
M
P
R
I
C
E
T
E
N
D
E
R
S

O
P
E
N
E
D
C
O
M
P
L
E
T
E
N
E
S
S

O
F
T
E
N
D
E
R

B
O
A
R
D
(
S
E
E

N
O
T
E

2
)
T
E
N
D
E
R
I
N
G
T
E
N
D
E
R
/
M
E
M
B
E
R
S
I
R
R
E
G
U
L
A
R
I
T
I
E
S
N
o
t
e
s
:
1
.
D
e
t
a
i
l
s

o
f

a
l
l

C
o
n
t
r
a
c
t
o
r
s
/
C
o
n
s
u
l
t
a
n
t
s

w
h
o

w
e
r
e

i
n
v
i
t
e
d

t
o

t
e
n
d
e
r

m
u
s
t

b
e

i
n
c
l
u
d
e
d
.
T
e
n
d
e
r

p
r
i
c
e
s

s
h
o
u
l
d

b
e

e
n
t
e
r
e
d

w
h
e
r
e

i
t

i
s

c
l
e
a
r

f
r
o
m

t
h
e

t
e
n
d
e
r
d
o
c
u
m
e
n
t
s
,
o
t
h
e
r
w
i
s
e

s
e
e

t
e
n
d
e
r


s
h
o
u
l
d

b
e

e
n
t
e
r
e
d
.
2
.
B
e
l
o
w

t
h
e

l
a
s
t

t
e
n
d
e
r

n
u
m
b
e
r

e
n
t
e
r

N
e
x
t

T
e
n
d
e
r

N
u
m
b
e
r

T
o

B
e

U
s
e
d


a
n
d

i
n
s
e
r
t

T
e
n
d
e
r

N
o
.
C
S
T
4
/
S
F
7
THE TENDER RECORD BOOK
CONSULTANTS SECTION
TENDER PROCESS
CST 4.13.2
HOME
GACC
EDITION 2: FEB 1998
CST 4.14 LATE TENDERS
Late tendersare not acceptable and should be rejected. However, it
may be unfair to reject a posted tender if it hasbeen held up in the
post. The tender board should be re-commenced on receipt of late
tenders. Late tendersmight be accepted in the following circumstances:
first cIass posted tenders - the date stamp should be at least
one day before tenderswere due to return;
second cIass posted tenders - the date stamp should be at least
two daysbefore tenderswere due to return.
If the date stamp or classof postage are difficult to ascertain - treat as
second classpostage. If the date stamp and classare made with the
tenderersfranking machine, the tender should be rejected.
Tendersshould not be accepted by facsimile under any circumstances.
A record of all rejected tendersshould be kept at the back of the
tender record book, and the price should not be recorded or disclosed.
( See CST4/SF8)
Should the tender opening board decide to admit a late tender into
competition it should be inserted in sequence into the list of tenders
and given a suffix to the preceding number i.e.:
Tender nunbers Tenderer's Price
248 JBloggs 265,498
249 JSmith 265,501
249A* T Jones 270,995
250 F Black 276,222
251 B White 292,543
* admitted late tender
The envelope of any rejected tenderer should be retained and should
be endorsed with the tenderersname together with the reasonsfor
rejection and signed by a senior member of the tender evaluation
board. The contentsshould then be returned to the tenderer with a
short explanation for rejection ( see CST4/SF9) .
The envelopesfor admitted and rejected late tenderersshould be filed
and used if the decision ischallenged.
LATE TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.14.1
HOME
GACC
EDITION 2: FEB 1998
S
T
A
N
D
A
R
D

F
O
R
M

8
R
e
c
o
r
d

o
f

R
e
j
e
c
t
e
d

T
e
n
d
e
r
s
C
O
M
M
E
R
C
I
A
L
-
I
N
-
C
O
N
F
I
D
E
N
C
E
R
E
C
O
R
D

O
F

R
E
J
E
C
T
E
D

T
E
N
D
E
R
S
[
D
E
P
A
R
T
M
E
N
T
]
C
O
N
T
R
A
C
T
/
T
I
T
L
E

O
F
N
A
M
E

O
F
D
A
T
E
D
A
T
E

A
N
D

T
I
M
E
R
E
A
S
O
N

F
O
R

R
E
J
E
C
T
I
O
N
S
I
G
N
A
T
U
R
E

O
F
C
O
M
M
I
S
S
I
O
N
C
O
N
T
R
A
C
T
/
C
O
M
M
I
S
S
I
O
N
F
I
R
M
T
E
N
D
E
R
S
T
E
N
D
E
R
S
O
F

T
E
N
D
E
R
T
E
N
D
E
R

B
O
A
R
D
N
O
D
U
E
R
E
C
E
I
V
E
D
M
E
M
B
E
R
S
C
S
T
4
/
S
F
8
LATE TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.14.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 9 - LETTER
REJECTION AND RETURN OF TENDER
[Department]
O ur Ref
Your Ref
Date
Dear Sirs
Location: ................................................................................................................................................................................
Commission: ................................................................................................................................................................................
Thank you for your tender for the above contract. It isvery much regretted that it was
received after the time appointed for delivery and therefore cannot be considered. It is
returned herewith.
Should further opportunitiesarise for you to tender, it would be appreciated if you would
ensure that your offersarrive in time to be admitted.
Yoursfaithfully
CST4/SF9
LATE TENDERS
CONSULTANTS SECTION
TENDER PROCESS
CST 4.14.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 5.0 TENDER EVALUATION
CST 5.1 EVALUATION CRITERIA
The chosen quality/price mechanism will have established the relative
weighting that isto be given to quality and price.
Although quality will already have been evaluated at the pre-tender
interview, receipt of the full tender from each consultant may
necessitate a rescoring of quality using a form similar to CST5/SF1. This
isan example of a tender assessment sheet which takesaccount of the
quality/price ratio and providesfor the calculation of a score which
combinesquality and price.
Quality Scoring
The score for each quality attribute should be an absolute score out of
100 and ismultiplied by the weighting. It may be that failure to achieve
a minimum level in key criterion will result in rejection, aswill a failure
to satisfy the quality threshold.
Price Scoring
The price score iscalculated for each tender by reference to the lowest
tenderer, which isgiven a score of 100. O ne point isdeducted from the
other tenderersfor each percentage point above the lowest. The
formula for the score istherefore:
100 x ( 1 - ( ( a - b) /b) )
a = price of tenderer being evaluated
b = lowest tender price.
EVALUATION CRITERIA
CONSULTANTS SECTION
TENDER EVALUATION
CST 3.8

CST 5.1.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
When scoring price it isrecommended that the following factorsbe
considered:
price should only be considered after the tenderer hassatisfied the
quality threshold;
very low tendersshould be carefully scrutinised to ensure that this
isnot asa result of failure to understand the commission; note that
thisshould have been resolved at the pre-tender stage;
compare resourcing levelsand cost aslow tendersmay be under -
resourced;
tendersmust be comparable; an essential aspect of tender
evaluation isto confirm that tendersare on a par, i.e. that deliberate
amendmentsto the conditions, or qualification have not created
anomaliesbetween tenders.
Final Choice
O nce each tender hasbeen scored, they should be ranked by score,
the tenderer with the highest overall score chosen.
Key Point
The price scoring and quality scoring systemsshould be compatible
with each other. There are a number of optionsand the formula
outlined earlier in thissection would be suitable for evaluating
consultantsin many circumstances.
A further option would be to use the mean price ( rather than the
lowest price) . A point would be deducted from the score of each
tenderer for each percentage point above the mean. Conversely a
point would be added for each percentage point below the mean. This
option would be even lesslikely to be subject to distortion if it utilised
the average of the three lowest tenders.
EVALUATION CRITERIA
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.4

CST 5.5

CST 5.6

CST 5.1.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM CST5/SF1
TENDER A55E55MENT 5HEET
ConfidentiaI- not for pubIic distribution
Project Q uality Weighting: 65% Project: .........................................
Project Price Weighting: 35% Tenderer: ...................................
Q ualityThreshold: 65 ( to be compared Assessor: ....................................
with total quality score)
QuaIity Criteria Project Marks Weigbted
Weigbting Awarded Marks
(A) (B out (A B)
of 100)
1. Appreciation of the 20
commission.
2. Calibre of relevant 20
professional staff.
Accounting and management
skillsand depth of
experience.
3. Q uality of account manager 20
( for the whole commission) .
4. Approach to undertaking the 20
commission, including
resourcesallocated and
ability to cope with peak
workloads.
EVALUATION CRITERIA
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.1.3
HOME
GACC
EDITION 2: FEB 1998
QuaIity Criteria Project Marks Weigbted
Weigbting Awarded Marks
(A) (B out (A B)
of 100)
5. Experience of similar 5
commissions
6. Experience of public sector 5
work.
7. Q uality Assurance/checking 10
systems.
8. Specialist advice to be bought in. N/A N/A
Total Q uality Score ( Q )
Price Criterion
Tender Price........................................................
Price Score ........................................................ ( P) .................................................
OveraII Assessnent
Q uality Weighting x Q uality Score 65% x ...................... ( Q ) = ......................
Price Weighting x Price Score 35% x ...................... ( P) = ......................
O verall Score = ..........
SIGNATURE: DATE:
EVALUATION CRITERIA
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.1.4
HOME
GACC
EDITION 2: FEB 1998
CST 5.2 FEE SCHEDULES
The use of fee schedulesin commission contract documentsishighly
recommended. These provide for structured headingsand price
categories. They make pricing and subsequent evaluation and
comparison of pricesconsiderably easier.
The tender documentsshould make it clear on what basisthe price is
sought:
hourly rates;
lump sum;
ad valorem ( percentage of workscontract price) .
The tender should be priced by the tenderer on the basisrequired.
FEE SCHEDULES
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.2
HOME
GACC
EDITION 2: FEB 1998
CST 5.3 INCENTIVE FEES
It should be noted that the documentation for PMCs, EMCsand estate
surveying term and individual commissionsoften invite the tenderer to
submit proposalsfor alternative incentive fee proposalsfor lease
renewalsand rent reviewstogether with their compliant bid.
These will necessitate careful evaluation to ascertain the bid that offers
the most economically advantageousdeal, bearing in mind the likely
incidence of such negotiationsand transactionsduring the life of the
commission.
INCENTIVE FEES
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.3
HOME
GACC
EDITION 2: FEB 1998
CST 5.4 EVALUATION PROCEDURE
The sequence of activity for the evaluation of bidsisusually asfollows:
check all bidsfor completenessand arithmetic accuracy;
compare the proposal document with that originally received; check
and reconcile significant differences;
undertake a section by section analysisof the bidsincluding cost
evaluation of alternative incentive fee proposalsand sensitivity
analysis;
compare most satisfactory bid with initial estimate and funding
available;
make recommendation for acceptance, non-acceptance or re-
tender.
Circumstancesmay arise where consideration must be given to either
requesting further information from tenderersor recommending re-
invitation.
EVALUATION PROCEDURE
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.4
HOME
GACC
EDITION 2: FEB 1998
CST 5.5 TENDER ANOMALIES
Anomalieswithin a tender bid may be taken up with the tenderer
concerned in writing provided that such clarification doesnot put
other tendersat a disadvantage or distort the competition element of
the tender. Any written enquiry should alwaysinclude the expression
Thisletter doesnot imply, expressly or otherwise, acceptance of your
tender.
TENDER ANOMALIES
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.5
HOME
GACC
EDITION 2: FEB 1998
CST 5.6 QUALIFIED TENDERS
Q ualified tendersare difficult if not impossible to compare with others,
and for thisreason they should be actively discouraged. It may be
decided for example to state in the invitation to tender that qualified
bidswill be automatically disqualified, ( except where alternativesare
sought) . Where the EC procurement rulesapply, the procurer hasthe
option of stating in the contract notice that qualified tenderswill not
be considered.
If a qualified tender isreceived, the tenderer should be given the
opportunity to withdraw the qualification without amendment to its
tender price. Thisshould be done through correspondence, copiesof
the Departmentsletter and the tenderersreply being kept on the
commission file.
Should a tenderer refuse to withdraw itsqualification, then the
importance of the qualification and the effect on the tender price will
need to be assessed asprecisely aspossible.
The file should show a fully reasoned explanation if an otherwise good
offer ispassed over due to a qualification, and likewise if an offer is
recommended for acceptance despite a qualification.
QUALIFIED TENDERS
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.6
HOME
GACC
EDITION 2: FEB 1998
CST 5.7 AMENDED TENDERS
Legally, a tender can be withdrawn or amended at any time before
acceptance ( i.e. the posting of the letter of acceptance) . The
Department isnot obliged however, to accept such an amendment for
consideration if received outside the tender period.
Tendersmust, asfar aspossible, be evaluated on the same basisand to
allow amendmentsto a bid after the tender period could call into
question the propriety of both the Department and the tenderer.
If an amendment flowsfrom a genuine error or unforeseeable
circumstance that impliesno advantage to the tenderer, such
amendmentsmay be considered. It isrecommended that the reason
for amendment should be considered credible, beyond doubt and the
full history recorded on the commission file.
Key Points
Different Departmentshave different policieson the treatment of
post-tender negotiations. Commission managersshould refer to
their Departmental handbooks.
Post tender negotiationsare only likely to be permissable on the
groundsthat the selected tenderers offer still representsbest value
for money.
AMENDED TENDERS
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.7
HOME
GACC
EDITION 2: FEB 1998
CST 5.8 AMENDED TENDER DOCUMENTS
It isrecommended that deliberate amendmentsto tender documents
are not accepted without good reason. These are not alwayseasily
detectable e.g. firmstyping out their own fee offer in order to distort
certain bandings, and accordingly, amendmentsto tendersshould
alwaysbe made clearly in writing, adjacent to the amended item, and
signed by the tenderer.
If tendersare rejected on these grounds, then the tenderer should be
reminded that only tendersbased on the documentsissued will be
considered in future.
AMENDED TENDER DOCUMENTS
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.8
HOME
GACC
EDITION 2: FEB 1998
CST 5.9 RE-INVITATION OF TENDERS
If no tender isconsidered acceptable, then all tendersshould be
declined and formal re-tendering undertaken ( including EC/O fficial
Journal advertising if applicable) .
If malpractice issuspected amongst those invited to tender then,
subject to departmental procedure, a report should be made to the
officer with the appropriate delegation to deal with irregularitiesand
re-invitation. If re-invitation isrecommended due to sharp practice
amongst tenderers, then all the tenderersinvolved may be dropped
from the new tender list.
Tendererswho are re-invited to bid should be advised asto why the
original offer wasnot acceptable asnot to do so may lead tenderersto
question the value of submitting further bids.
RE-INVITATION OF TENDERS
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.9
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 5.10 RECOMMENDATION FOR ACCEPTANCE
O nce the Tender Board hascompleted itsevaluation, it should report
itsrecommendationsto the Budget Holder for approval and
subsequent acceptance.
The evaluation report should include:
an explanation of the background to and scope of the commission;
a summary of the recommendation;
a description of the pre-qualification criteria;
a description of the tender evaluation criteria;
a description of the sensitivity analysisundertaken or reasonswhy
not;
the reasonsfor rejection of unsuccessful bids;
an indication of the cost implicationsof the recommended bid;
a comparison with pre-tender estimate and confirmation that funds
are available;
a confirmation that the tenderer satisfied the quality threshold at
interview stage.
The objective of competitive tendering isto achieve value for money.
RECOMMENDATION FOR ACCEPTANCE
CONSULTANTS SECTION
TENDER EVALUATION
CST 5.10
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 6.0 AWARDING COMMISSIONS AND
DECLINING TENDERS
CST 6.1 LEGAL CONTRACT FORMATION
The legal processof contract formation isset out at Section LE 1.2 -
Simple Contracts. Provided that all of the other elementsof formation
exist, then an unqualified acceptance of an offer givesrise to a legally
binding contract.
It should be noted that unlessan offer isopen for acceptance for a
specified period it may be withdrawn at any time up until acceptance.
To ensure proper formation of contract it isrecommended that the
following conventionsbe observed:
all qualificationsto the tender should have been removed
( negotiated out) ;
the offer must be capable of acceptance ( an unqualified yes) ;
the offer must not have lapsed; the offer may be stated asbeing
open for acceptance within a specified period; if thishaselapsed
then confirmation must be sought from the tenderer that the offer
remainsopen for acceptance;
all subsequent undertaking by the tenderer and amendmentsto the
tender must be confirmed in writing; it isrecommended that at the
very least all such amendmentsbe aggregated into a schedule of
amendmentswhich can be referred to in the acceptance; with time
permitting it isbetter to incorporate amendmentsdirectly into the
contract and initial them;
the tender must represent best value for money;
it isrecommended that a departmental procedure isin place which
requiresapproval by an officer with the appropriate delegation prior
to accepting an offer.
LEGAL CONTRACT FORMATION
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
LE 1.2

CST 5.6

CST 6.1
HOME
GACC
EDITION 2: FEB 1998
CST 6.2 ACCEPTANCE OF TENDER
O nce the requirementsrelating to the tender have been satisfied then
the offer may be accepted. To ensure proper acceptance of the tender
the following conventionsshould be followed:
acceptance must be unqualified; purported acceptance with
qualificationsrepresentsa counter-offer which may be accepted by
the consultant; thismay lead to unnecessary argument about how
and when acceptance occurred and what isor isnot part of the
contract; thisshould alwaysbe avoided;
acceptance should be communicated in writing; in law, the postal
rule isthat acceptance iscommunicated when the letter isposted
not when it isreceived; proof of posting can be ensured by sending
the acceptance by Registered Post;
acceptance should be notified with the minimum delay following
receipt of tenders.
Key Points
Acceptance should be unqualified.
Acceptance should be in writing.
ACCEPTANCE OF TENDER
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.1

CST 6.3

CST 6.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 6.3 LETTER OF ACCEPTANCE
A suggested letter of acceptance isgiven at CST6/SF1.
It isbest practice in the letter to list by reference all documentswhich
are to be incorporated into the agreement and which form the basisof
the acceptance. An alternative isto attach a schedule, but it isessential
that thisisgiven a recognisable and unique reference number.
It isessential that any correspondence or referencesto negotiationson
feesor alteration to the serviceswhich have been agreed with the
tenderer are referred to in the letter of acceptance.
For the avoidance of doubt it isrecommended that the successful
tenderer isasked to complete and return a confirmation of receipt slip
on receipt of the letter of acceptance.
Note that it isusual for the tenderer, in the form of tender, to give an
undertaking to execute the formal conditionsof contract, when they
are provided for signing.
Contract documentsshould be prepared and provided to the tenderer
with the letter of acceptance or assoon aspossible thereafter.
LETTER OF ACCEPTANCE
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 1 - LETTER CST6/SF1
LETTER OF ACCEPTANCE
Dear Sirs
[TITLE OF PROJECT]
[CONTRACT/TENDER NUMBER]
Further to our invitation to tender dated ............................................................... and your tender
submission provided under cover of your letter of..........................................................., I accept on
behalf of the [.................................], your offer to carry out [.................................] in connection with
the above project.
The [following documentsor the documentsreferred to in Schedule [Contract No]/1]
attached are the basisof thisacceptance; and together with thisletter of acceptance form a
binding contract between us.
[LIST DOCUMENTS SUCH AS:
Invitation to tender
Instructionsto tenderers
Schedule of duties
Brief
Tender submission from tenderer
Schedule of amendmentsor price schedule and basisof payment
Correspondence/minutesconfirming undertakingsby tenderer
Relevant correspondence from Department.]
Will you please contact ........................................................................................................ [Project Sponsor/
CommissionsManager] assoon aspossible to make arrangementsfor the formal
execution of contract documents, and subsequently for commencing work. Will you please
complete and return the attached acknowledgement slip.
Yoursfaithfully
LETTER OF ACCEPTANCE
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.3.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 1 - LETTER CST6/SF1 Contd
LETTER OF ACCEPTANCE
Confirmation of Receipt Slip
[TITLE OF PROJECT]
[CONTRACT/TENDER NUMBER]
I acknowledge receipt of your letter of acceptance dated ............................... .
Name: .......................................................................... ( name in block capitals)
Signed: ..........................................................................
in the capacity of ...................... authorised to sign for and on behalf of .......................................................
Date: ....................................................................... Telephone No.: ...................................................................
Address: ..........................................................................
..........................................................................
..........................................................................
LETTER OF ACCEPTANCE
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.3.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 6.4 DECLINE OF UNSUCCESSFUL TENDERS
It isadvisable to notify the successful tenderer of the intention to
accept their offer before sending decline lettersto unsuccessful
tenderers. Following confirmation from the successful tenderer, decline
lettersshould be sent immediately to all unsuccessful tenderers.
Standard Form CST6/SF2 isan example decline letter. To an extent the
wording of the letter will be determined by the type of procurement
effected and what issueswere subsumed within the evaluation.
There are two principal reasonsfor responding asfully aspossible:
it givesconsultantsconfidence in the process;
it givesconsultantsmarket information which helpsto encourage
competitive market performance.
DECLINE OF UNSUCCESSFUL TENDERS
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.4.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 2 - LETTER CST6/SF2
Decline Letter
Dear Sirs
[TITLE O F PRO JECT/CO MMISSIO N] ........................................................................................................................
Your tender for the above mentioned project/commission hasbeen evaluated but I must
inform you that you were not successful on thisoccasion. The successful tenderer
was........................................................................................................................................................................................................
Thiswasthe successful tenderer because...................................................................................................................
I would like to take thisopportunity to thank you for your considerable effortsin
submitting a tender and for your interest.
Yoursfaithfully
DECLINE OF UNSUCCESSFUL TENDERS
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.4.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 6.5 EXECUTION OF FORMAL AGREEMENT
Although the posting of the letter of acceptance should result in the
formation of a legally binding contract, it isessential that for the
avoidance of doubt a set of contract documentsisproperly executed
by both parties.
There ought to be no reason why thiscannot be done at the time of
acceptance, such contract documentsshould be prepared in
anticipation of thisevent. It ishowever essential that the contract
documentsare signed before commencement of any work by the
consultant. The scope for negotiation, if any isstill required, is
significantly reduced after thistime.
EXECUTION OF FORMAL AGREEMENT
CONSULTANTS SECTION
AWARDING COMMISSIONS & DECLINING TENDERS
CST 6.5
HOME
GACC
EDITION 2: FEB 1998
CST 7.0 DEBRIEFING
CST 7.1 REQUEST FOR DEBRIEFING
Debriefing isthe only way in which unsuccessful tenderersare able to
find out why they were not selected, and therefore to obtain information
about areaswhere they need to improve their future performance. This
positive feedback encouragescompetitive performance and istherefore
recognised asbest practice.
CUP Guidance Note No.45 providesuseful guidance on debriefing.
O n receipt of a decline letter either at interview stage or tender stage a
consultant may request more information regarding their performance,
so that they may:
addressparticular problems;
improve competitivenessof future bids.
A letter requesting further information should be answered with a letter
offering the tenderer the opportunity for a formal debriefing interview.
Where the EC procurement rulesapply then a request for debriefing
must be responded to within 15 daysof receipt of the request
Dealing with a Telephone Call
A consultant who hasreceived a decline letter islikely to make a
telephone call to the Department.
Thisshould be handled with care. It isrecommended that the following
conventionsbe observed:
do not discussthe performance of other tenderers; bear in mind that
the solutionsand price offered by other contractorsare confidential;
offer a confirmation of the pointsmade in the decline letter;
confine the information given to mattersthat would be covered in a
debriefing interview;
keep a record of the conversation.
REQUESTS FOR DEBRIEFING
CONSULTANTS SECTION
DEBRIEFING

CST 6.4

CST 7.2

EPP 1.14

CST 7.1
HOME
GACC
EDITION 2: FEB 1998
DEBRIEFING INTERVIEWS
CONSULTANTS SECTION
DEBRIEFING
CST 7.2.1
CST 7.2 DEBRIEFING INTERVIEWS
If unsuccessful tenderersrequest a debriefing interview, thisshould be
agreed to if possible. Any such interview should be undertaken assoon
after the contract/commission award date aspracticable, generally
between three to six weeks.
Debriefing interviewsfor commissionsare conducted by the
commission manager/project sponsor but debriefing interviewsfor
contractsmay be conducted by the consultant who invited and
subsequently evaluated the tenders.
Valuable time and money isspent in debriefing, but should alwaysbe
considered worthwhile on large contracts/commissionsasthere are
certain long term benefits. These are:
to establish a reputation in the market place asa strictly fair, honest
and ethical Department, which will encourage the best firmsto
submit their best offer first time around;
to offer unsuccessful tendererssome return for the time and money
expended in preparing their tenders;
to assist firmsto improve their performance.
Interview Format
The agenda for the interview will be dependent upon the individual
commission/contract but generally the person conducting the interview
should be accompanied by at least one other person and an agenda
agreed between them prior to the meeting. If possible the agenda
should follow the evaluation criteria set out prior to receipt of tenders
and where applicable, listed in the EC/O fficial Journal advertisement.
The meeting should allow sufficient time for the unsuccessful tenderer
to be told the reasonsfor failure in thisinstance and for the firm to ask
any questionsthat they feel are relevant.
The interviewersshould be aware that the reason for the interview is
diplomatically to convey to the tenderer weaknessesand strengths
within cost, schedule, design, delivery, experience etc. It must be made
clear that only the unsuccessful tender will be discussed and not a
comparison with the other tenderersor competitors.
HOME
GACC
EDITION 2: FEB 1998
Formal minutesare not distributed following the meeting but it is
recommended that a copy of notestaken at the meeting should be
kept on the commission file for future reference by the Department.
DEBRIEFING INTERVIEWS
CONSULTANTS SECTION
DEBRIEFING
CST 7.2.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 8.0 MANAGEMENT OF COMMISSIONS
CST 8.1 ROLES AND RESPONSIBILITIES OF THE COMMISSION
MANAGER/THE PROJECT SPONSOR
The primary role of the commission manager isto ensure that the
requirementsof the commission are delivered.
It isstrongly recommended therefore that consultants/service providers
are actively managed and monitored. It may be unwise to leave
consultantsto their own devices. It issuggested that the best results
can be achieved by doing the following:
ensuring that Department expectationsand timescalesare properly
defined and communicated;
monitor performance in termsof time and cost against the agreed
programme;
holding regular review meetingswith the consultant and review
progressof interim activities; thiscan include the requirement for
the consultant to produce reportsbefore progressmeetings; thisis
especially important in the case of projectssuch asmajor works
where the activitiesof othersare reliant on timely performance by
the consultant;
keep the consultantsperformance up to the required standards;
ensure that the termsof the commission are followed;
provide clear and documented evidence when necessary to invoke
the default provisionsin the commission;
provide a clear assessment that value for money isbeing obtained;
anticipate problemsand assessproposed solutions.
The commission manager isthe representative of the Department. The
Department will have specific obligationsin accordance with the terms
of the commission agreement. The rolesand responsibilitiesof the
commission manager will therefore depend to some extent upon the
consultantstermsof appointment. Thissection makesreference to
commissionslet under GC/Works/5 General Conditionsfor the
Appointment of Consultants( 1998) - available from TSO .
ROLES & RESPONSIBILITIES
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.1.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
The commission manager role isoften set out in the termsand
conditionsof Property Management Commissionsasfollows:
The commission manager isauthorised to receive and conduct all
communicationsbetween the Managing Agent or the Account
Manager and the Department, and hasauthority to act on behalf of
the Department for all purposesconnected with the Commission.
Within the Consultant Commissioning Documentation the project
sponsor isusually designated asthe Department representative with
the following role:
The Department representative ...... shall act on behalf of the
Department in issuing instructionsto the consultantsand for
receiving reports, notices, requests, statementsor in dealing with any
other matter concerning the Consultantscommission.
In principle, a project sponsor fulfilsthe same functionsasa commission
manager and the general principlesput forward in thissection are
therefore applicable to both postsunlessotherwise stated,.
Key Points
Effective management meanssetting clear specific, measurable and
achievable objectives, and motivating and monitoring consultantsto
deliver the service to the best of their ability.
ROLES & RESPONSIBILITIES
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.1.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
CST 8.2 CONSULTANT AND SUB-CONSULTANTS
For any type of commission, the consultant isrequired to name one or
more ( asspecified in the termsand conditionsof the commission)
membersof their staff to act astheir representative for the purposesof
the particular commission ( for Property Management commissionsthis
person isknown asthe account manager) .
Since thisperson islikely to have been one of the factorsconsidered in
the quality evaluation of the tender bid, any change in such personnel
must only be effected with the prior approval of the commission
manager/project sponsor.
The commission manager/project sponsor must arrange to be provided
with regular progressreportsfrom the consultant asspecified in the
commission documentation. These reportsshould cover the areasof
financial management, worksmanagement and, in the case of property/
estate management commissions, estate management.
Face-to-face meetingswith the consultant should be arranged asoften,
but not more often than necessary. Within the property management
documentation it isstated that meetingswill be monthly. No such
specification isgiven in project documentation but it must be
remembered that meetingsdemand a cost in both time and money
from all participantsand should not be held if they are unnecessary or
have no identifiable purpose. ( The purpose should be determined and
communicated in advance) .
At the time of submitting the tender, the consultant should also list
those companieswhom they propose to employ assub-consultants
and obtain the commission manager/project sponsorsapproval of
those companies.
At all timesthe consultant isdeemed responsible for the actionsof any
nominated sub-consultantsand for the payment of moniesto the sub-
consultant.
CONSULTANT & SUB-CONSULTANTS
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.2.1
HOME
GACC
EDITION 2 REV 1: JAN 1999
Key Points
The Department isentitled to expect continuity of consultant staff.
Since the quality of such staff islikely to have been important in
winning the tender, any change of staff, especially after time hasbeen
spent on complex commissions, should be strongly resisted.
CONSULTANT & SUB-CONSULTANTS
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.2.2
HOME
GACC
EDITION 2: FEB 1998
CST 8.3 PROFESSIONAL INDEMNITY INSURANCE
Professional Indemnity Insurance ( PII) isa form of specialised cover
directed at damage or lossarising from negligence in the provision of
professional services. Liability isnot limited to the Department but is
also extended to third parties.
PII workson a claims-made basisin that insurance must be held when
the claim ismade not when the culpable act took place. PII is
mandatory for all building-worksconsultantscommissioned by
Departmentsand insurance to the level prescribed in the commission
documentation must be maintained for the period of the commission
and six yearsbeyond.
The consultant must be able to produce a certificate of their
professional indemnity insurance, and any further particularsasmay be
required by the Department.
If the consultant failsto maintain indemnity insurance in accordance
with the termsof the commission, the Department may, in itsown or
in the consultantsname, take out and maintain a policy of indemnity
insurance in reasonably equivalent termsand shall be entitled to
recover all coststhereby incurred from the consultant. ( There should
be a clause in the conditionswhich providesfor thisright.)
If a situation ariseswhere a consultant isunable to obtain or maintain
sufficient cover in the commercial market a report should immediately
be sent to the Department.
Key Points
If the consultant failsto maintain cover, the Department may obtain
such cover and charge the consultant.
PROFESSIONAL INDEMNITY INSURANCE
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 8.4 BILL PAYING AND CHECKING PROCEDURES
It isessential that the Department hasin place effective systemsfor
checking billsand for paying them promptly.
In general it issuggested that the following principlesapply:
the bill should be checked; depending on the number of bills, either
all billsshould be checked or at least a representative but
RANDO M sample; there must be a contract which givesrise to
Departmental liability; the bill, e.g. rates, must be in accordance with
the termsof the contract; and the work said to have been done,
must have been done to the satisfaction of the Department;
cash flow isthe life-blood of the industry; late payment or failure to
pay may affect the health of the businessbeing employed, which
could seriously affect the commission being undertaken;
where the contract specifiesperiodsfor payment, these should be
honoured;
the Late Paymentsof Commercial Debts( Interest) Act 1998
introducesa statutory right to interest on late payment of a debt.
Additionally there may be a contractual right to interest ( e.g. on late
payment of a certificate for Government workscontracts) ; late
payment in thissituation clearly affectsthe project cost and
approved budget;
the Government iscommitted to ensuring that where there isno
contractual provision or other understanding or accepted practice
governing the timing of payment, payment should be made within
30 daysof receipt of a valid invoice or similar demand for payment.
Key Point
A consultant iscovered by the Construction Industry Tax Scheme if he
hasa role in the direct commissioning of construction worksor where
he actson behalf of a Department in thiscontext.
BILL PAYING & CHECKING PROCEDURES
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.4
LE 2.11

HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 8.5 DETERMINATION/TERMINATION PROCEDURES
Determination/termination of a commission will generally arise by
reason of one of the following:
bankruptcy or liquidation of consultant firm;
the committing of an act of bribery or corruption by the consultant
in connection with Government contracts;
default on the part of the consultant in respect of one or more of
itscontractual obligations;
in exceptional circumstanceswhere for example because of
budgetary considerationsit becomesnecessary not only for the
Department to suspend work but also to cease it.
In standard formsof contract there are usually contractual provisions
which set out circumstancesin which either one or both partiesmay
determine/terminate the contract.
It isimportant to note that there isalso the common law doctrine of
material breach of a contract condition ( see LE 1.4 and LE 1.5 for other
groundsfor termination) .
It istherefore essential that contractual proceduresfor determination/
termination are followed and that the specified groundsfor
determination/termination are properly established. Wrongful
determination/termination may in itself amount to a material breach
giving rise to an entitlement on the part of the consultant to claim
damagessuch aslost profit etc.
The determination/termination provisionscommonly provide for the
following:
notice to be served on the defaulting party stating the nature of the
default and specifying a period within which the default should be
rectified;
if the default persistsbeyond the specified duration, notice may be
sent by registered post to the defaulting party confirming
determination/termination of the contract;
any costsarising from obtaining a new consultant to complete the
commission may be set off against any outstanding moniesowed or
become payable asa debt to the Department.
DETERMINATION/TERMINATION PROCEDURES
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
CST 8.5.1
LE 1.4
LE 1.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
It iscommon for term commissionsto contain a break clause which
may or may not allow a notice period and which enablesthe
Department to determine/terminate the contract without cause or
default on the part of the consultant.
Key Points
Seek advice before proceeding.
Where there are contractual provisionswhich entitle the
Department to determine/terminate the contract, and there is
occasion to operate them, the provisionsin question should be
followed to the letter.
L
! !! !!
CST 8.5.2
DETERMINATION/TERMINATION PROCEDURES
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 8.6 DETERMINATION/TERMINATION DUE TO DEFAULT
In casesof default due to breach of the termsof a commission, an
official notice should be served on the consultant advising that should
the instructionsgiven in the notice fail to be carried out within a
specified period then the commission will be determined.
Great care must be taken in drafting noticesof default to ensure that
the Departmentsrightsare not unwittingly prejudiced by the termsof
the notice. It isimportant that the wording of the condition under
which the notice isissued should be reflected exactly in the notice and
it issuggested therefore that legal advice be sought.
If the giving of a notice of default isactually followed by determination/
termination of the commission, arrangementsshould be made to
complete the commission without delay asthe amount of any
additional costswhich may be claimed from the original consultant may
be reduced if it can be shown that unreasonable delay hasincreased
these costs.
Commission managers/project sponsorsshould ensure that for each
commission within their control, they are aware of the timescalesfor
giving notice to consultants, the proceduresfor determining/terminating
the commission and the method of calculating feesdue to a consultant
whose commission hasbeen determined/terminated since these may
vary from commission to commission.
When a commission isdetermined/terminated due to default, it is
recommended that a full report should be sent to the appropriate
senior departmental officer. An adverse performance report should be
sent to NQ S assoon aspossible.
Key Points
Seek legal advice before issuing a notice of default.
The Department should be sure of itsgroundsbefore serving a
notice and clearly communicate them in the notice.
CST 8.5

L
! !! !!
CST 8.6
DETERMINATION/TERMINATION DUE TO DEFAULT
CONSULTANTS SECTION
MANAGEMENT OF COMMISSIONS
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 9.0 CLAIMS & DISPUTES
CST 9.1 HANDLING OF CLAIMS BY AND AGAINST THE
DEPARTMENT
Types of Claim
Claimsinclude all mattersfrom a routine request for additional time to
complete, to a major allegation of breach of contract. In fact a claim is
simply a demand by one party on the other that a particular
entitlement isdue. Not all claimssignify a dispute. But where a claim is
not met in full and there isdisagreement by one party asto the
entitlement of the other then unlessagreement can be reached
through negotiation, it can be said that a dispute or difference has
arisen between the parties.
The majority of claimsarise from a failure or an alleged failure of one
party fully to comply with the requirementsof the contract or in some
instancesconditionsimplied by the common law. The remedy sought to
an alleged breach isusually damages.
Claimsgenerally fall into the categorieslisted below ( examplesare
given of each) :
Contractual Claims( specific entitlement in accordance with the
termsof the contract) :
for delay/additional time for specified reasonssuch as:
- issue of variationsexpanding the scope of the contract,
- late issue of information and/or variations,
for the additional cost of variations;
for disruption or lost productivity due to interference by the
Department;
HANDLING OF CLAIMS
CONSULTANTS SECTION
CLAIMS & DISPUTES
LE 1.7

LE 1.8

CST 9.1.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Common Law Claims( ex-contractual claims) :
damagesfor breach of contract;
damagesin tort/delict ( e.g. negligence - breach of a duty of care) ;
damagesfor breach of copyright;
Third Party Claims:
personal injury claims;
employee claims;
estatesclaims;
Quantum Meruit Claims:
Ex Gratia Claims(out of kindness).
From the Departmentsviewpoint claimsshould be avoided if only
because financial control becomesextremely difficult, especially for
claimsproduced long after the event.
In practice it isdifficult to avoid claims, but it ispossible to deal with
them intelligently and expeditiously so asto avoid disputes.
Stepsto minimise the likelihood of a dispute are asfollows:
ensure that the brief iswell defined and contractual requirements
are consistent;
ensure that the consultant hasthe information required, preferably
before he or she requiresit;
avoid variations;
where variationsare required, agree time and cost increasesprior to
instruction or assoon aspossible thereafter;
keep good recordsof all eventswhich may lead to a claim;
insist on compliance with the contract where contractual claimsare
being made and evaluate them asquickly aspossible;
negotiate with the consultant.
HANDLING OF CLAIMS
CONSULTANTS SECTION
CLAIMS & DISPUTES
LE 1.8

CST 9.6

CST 9.1.2
HOME
GACC
EDITION 2: FEB 1998
If a dispute doesarise or the Department iscontemplating making a
claim against a consultant then the following principlesshould be
noted:
there must be a basisfor the claim in law, either under the contract
or otherwise;
there must be some losswhich arisesby reason of the legal right to
claim;
the connection between the legal right and the damagessought
must asfar aspossible be proven by the party claiming the damages;
the mattersin dispute should be set down on paper assoon as
possible and communicated in a cogent and persuasive manner;
if in receipt of a claim, evaluate it, determine the value of any
counter-claim the Department may wish to make and make a
realistic offer assoon aspossible.
Key Points
A claim ismore often than not an expression of the additional
entitlement of a party specifically provided for under the termsof
the contract for specified matters.
The better the Departmentsrecords, the better itsability to make
and defend claimsand to negotiate them.
The legal principlesinvolved in making or defending claimscan be
complex and the preparation of a good claim document isan art. If
in any doubt seek professional advice.
HANDLING OF CLAIMS
CONSULTANTS SECTION
CLAIMS & DISPUTES
L
! !! !!
CST 9.1.3
HOME
GACC
EDITION 2: FEB 1998
CST 9.2 CLAIMS ARISING FROM DEFAULT OR NEGLIGENCE BY
A DEPARTMENT, CONSULTANT OR CONTRACTOR
Claimsgenerally represent an unbudgeted increase in cost to the
Department. In addition, unlessthey are based on good groundsthey
can represent a fruitlessexercise, and a substantial cost risk. It is
important that the effort and cost of resolving a dispute iskept in
proportion with the amount in dispute.
A substantial cost risk may arise where:
the Department unreasonably objectsto a claim from a consultant
where the claim hassome merit;
the Department pursuesa claim where the claim haslittle merit, or
more particularly representsdifficultiesin proving the case on the
balance of probabilities.
For these reasonsit isrecommended that the following proceduresbe
followed:
contractual claimsshould be dealt with quickly and expeditiously
and negotiated bythe commission manager; the appropriate senior
officer should be kept advised, and budgetary provision made for
the claim;
claimsrelating to professional negligence should be referred to the
appropriate senior officer, and legal advice sought;
any claim that appearsto be sensitive novel or to have political
implicationsshould be referred to the appropriate senior officer;
any undisputed contractual claimswhich do not require
consideration of mattersof law should be evaluated and paid
immediately.
CLAIMS ARISING FROM DEFAULT OR NEGLIGENCE
CONSULTANTS SECTION
CLAIMS & DISPUTES
L
! !! !!
CST 9.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 9.3 ALTERNATIVE DISPUTE RESOLUTION PROCEDURES (ADR)
ADR isa method of dispute resolution which hasbeen imported from
the United States. ADR isa generic term to describe methodsof
dispute resolution in which the aim isthat a third party isinstrumental
in bringing about a quick and effective resolution to a dispute. ADR can
be an effective meansof dispute resolution asa pre-cursor to
arbitration or litigation. An ADR clause can be included in the contract,
or ADR may be used by subsequent agreement between the parties.
The variousADR proceduresare:
Mediation/Conciliation - a private voluntary dispute resolution
procedure in which a mediator facilitatesdialogue between the
parties; helpseach party to see the strengthsand weaknessesof its
case and encouragessettlement. Mediationsare without prejudice
to further negotiations. The partiesmay ask the mediator to provide
a written evaluation or recommendation. If settlement isreached
then it isadvisable for the partiesto draw up a settlement
agreement.
Mini Trial - a more formalised mediation involving a panel
comprising the mediator and a senior executive from each party.
Representationsare made to the panel by each party and the panel
retiresto mediate the dispute. The procedure isalso private and
voluntary with no formal rules. Again the dispute isonly resolved by
agreement between the parties.
Judicial Appraisal - whereby the partiesagree in advance to
submit their respective cases, including oral submissionsif preferred,
to a senior legal figure such asa Q C for him to carry out a review
and prepare a written appraisal of the case before him. The parties
can agree to be bound by the appraisal or it may simply ease the
way for further negotiations. Thiscan be very effective in helping to
resolve any pointsof law which are central to the dispute.
Early Neutral Evaluation - thisissimilar in nature to the judicial
appraisal, but iscarried out by an independent expert where
technical issuesare at the centre of the dispute.
ALTERNATIVE DISPUTE RESOLUTION PROCEDURES
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Adjudication - involvesthe appointment of an adjudicator who is
commonly a valuer or expert and who receiveswritten and/or oral
submissionsbefore coming to a decision. The adjudicatorsdecisions
are binding on the parties.
Part II of the Housing Grants, Construction and Regeneration Act
1996 requiresthat a party to any construction contract hasa right
to refer any dispute for impartial adjudication. Any such adjudication
must be effected within a certain timescale during the contract.
Dispute Review Board - a panel of expertswho are appointed
by the partiesat the outset of the worksto monitor and resolve
claims. They are there to foster good relationsbetween the parties.
Thisismost appropriate on large complex projects.
Key Points
For ADR to be effective, the partiesmust be willing to submit to
and be influenced by the process.
ALTERNATIVE DISPUTE RESOLUTION PROCEDURES
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.3.2
LE 2.9

LE 2.9

HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 9.4 ARBITRATION
If a resolution to a claim cannot be reached following negotiationsand/
or Alternative Dispute Resolution, it may be appropriate to refer the
dispute to a third party for determination. In fact where the form of
contract hasprovided for arbitration thismay be a necessary pre-
condition to litigation.
For arbitration to be an option there must be a written agreement in
the contract to arbitrate ( an arbitration clause) ; or there may be
subsequent written agreement to arbitrate.
The advantagesof arbitration are asfollows:
the partiesmay choose the arbitrator/arbiter;
confidentiality - arbitration isprivate;
should be faster;
flexibility - partiesmay agree to relax procedural rulesor rulesof
evidence;
the partiesdo not have to be represented by counsel;
limited appeals( on pointsof law) ;
no reliance on Rulesof Court.
The conditionsof contract usually set out the procedure to be adopted
for the arbitration however, the partiesare free to agree on their own
procedures.
O nce an arbitration notice hasbeen issued by either party, failure to
respond may be a breach of contract.
Key Points
Arbitration isa meansof dispute resolution by the decision of a
third party.
The service of a notice of arbitration may be a very effective means
of encouraging settlement, however, it isnot a step that should be
taken lightly. There must be a case to argue, and there must be a
reasonable prospect of success.
ARBITRATION
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.3

CST 9.4.1
LE 2.10

HOME
GACC
EDITION 2 REV 2: JAN 2000
It isoften cheaper and lesstime consuming to try to settle disputes
through a settlement or ADR.
Seek professional advice before issuing a notice of arbitration or
upon receipt of one.
L
! !! !!
ARBITRATION
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.4.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 9.5 WRITS AND SUMMONSES
The receipt of an initial writ or summonsgenerally attacheswith it a
strict timetable for response or action and must be complied with.
The appropriate senior officer within the Department should be
advised immediately by the solicitorsrepresenting the Department as
to the receipt of an initial writ or summons, and appropriate legal
advice asto actionsand strategy given.
If the Department isconsidering the service of a writ in contemplation
of litigation, then thisislikely only to follow the failure of other means
of dispute resolution and should only be done in the context of clear
legal advice on the matter in dispute.
Key Point
A Minister of the Crown may not sue another Minister of the
Crown. However, since 1 July 1999, rightsand liabilitiesmay arise
between the Crown in right of Her Majesty'sGovernment in the
United Kingdom and the Crown in right of the Scottish
Administration by virtue of a contract, by operation of law or by
virtue of an enactment asthey may arise between subjects. The
Scottish Ministersmay therefore sue, and be sued by, Ministersof
the Crown. Notwithstanding this, every attempt should be made by
Departmentsto resolve disputeswithout recourse to court
proceedings. Thiswould in any case only arise where the Scottish
Ministerscontract with a Minister of the Crown, if perhapsusing an
English Department asconsultants, or vice versa.
WRITS & SUMMONSES
CONSULTANTS SECTION
CLAIMS & DISPUTES
LE 1.17

CST 9.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
CST 9.6 EX GRATIA CLAIMS
These claimsusually arise where the claimant hasno grounds( other
than possibly moral) for additional costs.
Ex-gratia paymentsare generally made in exceptional circumstances
and with the agreement of the finance section of the Department.
EX GRATIA CLAIMS
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.6
HOME
GACC
EDITION 2: FEB 1998
CST 9.7 PERSONAL INJURY CLAIMS
Departmentsshould have their own proceduresin place for dealing
with personal injury claims( usually dealt with by the finance division) . A
full report should be prepared by the Department or consultants
representing them on all circumstancessurrounding the claim.
Claimsfor personal injury which arise by reason of negligence on the
part of a consultant or contractor acting for the Department, may also
give rise to contractual claimsand copy papersshould be provided to
the commission manager.
PERSONAL INJURY CLAIMS
CONSULTANTS SECTION
CLAIMS & DISPUTES
CST 9.7
HOME
GACC
EDITION 2: FEB 1998
CST 10.0 PERFORMANCE REPORTING
CST 10.1 PERFORMANCE REPORTING GENERALLY
Performance reporting isthe last stage in the procurement processand
closesthe procurement cycle by providing feedback into the long-listing
processfor future work.
The advantagesof performance evaluation and reporting are:
feedback for future procurement;
feedback to NQ S;
a sharing of knowledge with other Departments;
i ii iit representsadditional pressure on consultantsto perform well.
The performance evaluation should also involve a separate critique of
the Departmentsown performance in respect of the consultant
commission so that lessonslearnt may be used asa resource for future
projects.
PERFORMANCE REPORTING GENERALLY
CONSULTANTS SECTION
PERFORMANCE REPORTING
CST 10.2

CST 10.1
HOME
GACC
EDITION 2: FEB 1998
CST 10.2 PERFORMANCE REPORTING TO THE NEW QUALIFICATION
SYSTEM (NQS)
NQ S isa computerised database of information on consultants
approved asbeing eligible for the provision of servicesto Departments.
Applicationsto the ConsultantsRegister for a list of suitable
consultantsfor long-listing isbriefly described at Section CST 3.2.
Commissionsfeedback isa crucial part of the NQ S system. It is
therefore important to ensure that all tendering and performance
information ispassed to NQ S for entry onto the database. Standard
feedback formsshould be completed promptly and forwarded through
Headsof Division to provide information on:
all offersreceived, in addition to the commission award details;
the performance of the consultantsat the appropriate stage
( interim/final) .
It isrecommended that these formsshould be used on all new
commissionsand on all existing commissionswhere reportshave not
already been submitted. They also represent a useful internal appraisal
record and resource for the tendering of subsequent commissions.
The NQ S Performance Report providesseparate assessment tablesfor
either building servicesor estatescommissions; onlyone table should
be completed for each commission. Thiswill enable future enquirersof
NQ S to obtain more relevant performance detailsaccording to the
type of commission.
When completing the report for a Property Management Commission,
the commission manager should assesswhether the commission has
included a predominance of worksmanagement or estate management
servicesand complete the relevant table.
In the longer term, NQ S are looking into the possibility of including the
detailed performance breakdown on the computerised system but in
the meantime, such detailscan be requested from NQ Ssmanual
recordsfor particular consultants.
REPORTING TO THE NEW QUALIFICATION SYSTEM
CONSULTANTS SECTION
PERFORMANCE REPORTING
CST 3.2

CST 10.2
HOME
GACC
EDITION 2: FEB 1998
CST 10.3 CONSULT NOTICES WITHIN NQS
A CO NSULT notice shown against a firm on the database indicates
that NQ S need to be consulted before tender invitationsare sent out.
There may be several reasonswhy a firm hassuch a notice against it. It
could be for financial reasonswhere the firmsaudited accountsshow
the firm to be financially unstable; the firm could be reorganising itself; it
could be under investigation, or it could be overloaded with work.
A CO NSULT notice may simply ensure a referral to NQ S because
there may be additional information that the Budget Holder should
consider before inviting the consultant to tender.
A CO NSULT notice against a firm should not be regarded asa
prohibition on dealing with the firm and in some casesthe firm may still
be invited to tender. CO NSULT noticesagainst consultantson NQ S
should be treated confidentially and should not be disclosed to any
consultant without the authority of NQ S.
CONSULT NOTICES WITHIN NQS
CONSULTANTS SECTION
PERFORMANCE REPORTING
CST 10.3
HOME
CRS 1.0 CONTRACTlNG 5TRATEGlE5
CRS 1.1 PRO CUREMENT PRO CESS AND PRO GRAMME
CRS 1.2 APPLICATIO N O F EC PUBLIC PRO CUREMENT RULES
CRS 1.3 INTRO DUCTIO N TO THE CHO ICE O F CO NTRACT
CRS 1.4 CO NTRACTS USING BILLS O F Q UANTITIES
CRS 1.5 CO NTRACTS USING SCHEDULES O F RATES
CRS 1.6 SIMPLE LUMP SUM CO NTRACTS
CRS 1.7 TRADITIO NAL LUMP SUM CO NTRACTS
CRS 1.8 DESIGN AND BUILD CO NTRACTS
CRS 1.9 PRIME CO ST CO NTRACTS
CRS 1.10 MAN AGEMENT CO NTRACTS
CRS 1.11 CO NSTRUCTIO N MAN AGEMENT CO NTRACTS
CRS 1.12 DESIGN AND MAN AGE CO NTRACTS
CRS 1.13 EX TENSIO N CO NTRACTS AND VARIATIO NS
CRS 1.14 TERM CO NTRACTS
CRS 1.15 STANDARD GO VERNMENT CO NTRACTS
CRS 1.15.1 GC/WO RKS/1 ( 1998) - LUMP SUM WITH Q UANTITIES
CRS 1.15.2 GC/WO RKS/1 ( 1998) - LUMP SUM WITHO UT Q UANTITIES
CRS 1.15.3 GC/WO RKS/1 ( 1998) - SINGLE STAGE DESIGN AND BUILD
VERSIO N
CRS 1.15.4 GC/WO RKS/1 ( 1999) - TWO STAGE DESIGN AND BUILD
VERSIO N
CRS 1.15.5 GC/WO RKS/1 ( 1999) - WITH Q UANTITIES CO NSTRUCTIO N
MAN AGEMENT T RADE CO NTRACT
-WITHO UT Q UANTITIES
CO NSTRUCTIO N MAN AGEMENT
TRADE CO NTRACT
CRS 1.15.6 GC/WO RKS/2 ( 1998) - BUILDING AND CIVIL ENGINEERING
MINO R WO RKS
CRS 1.15.7 GC/WO RKS/3 ( 1998) - MECHANIC AL AND ELECTRIC AL
ENGINEERING WO RKS
CRS 1.15.8 GC/WO RKS/4 ( 1998) - BUILDING, CIVIL ENGINEERING,
MECHANIC AL AND ELECTRICAL
WO RKS
CRS 1.15.9 GC/WO RKS/6 ( 1999) - DAYWO RK TERM CO NTRACT
CRS 1.15.10 GC/WO RKS/7 ( 1999) - MEASURED TERM CO NTRACT
HOME
CRS 1.15.11 GC/WO RKS/8 ( 1999) - SPECIALIST TERM CO NTRACT FO R
MAINTENANCE O F EQ UIPMENT
CRS 1.15.12 GC/WO RKS/9 ( 1999) - O PERATIO N , REPAIRS AND
MAINTENANCE CO NTRACT FO R
MECHANIC AL AND ELECTRICAL
PLANT, EQ UIPMENT AND
INSTALLATIO NS, ETC.
CRS 1.15.13 C1303 - WINDO W CLEANING AND
C1304 - CHIMNEY SWEEPING
CRS 1.15.14 C1306 - MAINTENANCE O F GARDENS, GRO UNDS, ETC. AND
C1312 - SUPPLY AND APPLIC ATIO N O F HERBICIDES, ETC.
CRS 1.15.15 C1804 - REPAIR O F PLANT
CRS 2.0 CONTRACT5 FlLE
CRS 2.1 IDENTIFIC ATIO N
CRS 2.2 SUB-FILES
CRS 2.3 RETENTIO N PERIO DS
CRS 2.3( SCO T) RETENTIO N PERIO DS
CRS 3.0 CONTRACTOR 5ELECTlON
CRS 3.1 SELECTIO N O F FIRMS
CRS 3.2 NEW Q UALIFIC ATIO N SYSTEM ( NQ S - FO RMERLY CMIS)
CRS 3.3 THE LO NG LISTING PRO CESS
CRS 3.4 PRE-SELECTIO N PRO CEDURES
CRS 3.5 CO MPILATIO N O F SHO RT LISTS
CRS 3.6 THE NUMBER O F TENDERERS
CRS 4.0 TENDERlNG PROCE55
CRS 4.1 DO CUMENTATIO N
CRS 4.2 INSTRUCTIO NS/N O TICES T O TENDERERS/TENDER PERIO DS
CRS 4.3 MID TENDER INTERVIEWS
CRS 4.4 TENDER BO ARDS
CRS 4.5 O PENING O F TENDERS
CRS 4.6 THE T ENDER RECO RD BO O K
CRS 4.7 LATE TENDERS
HOME
CRS 5.0 TENDER EVALUATlON
CRS 5.1 GENERAL
CRS 5.2 CRITERIA FO R EVALUATIO N
CRS 5.3 Q UALIFIED T ENDERS
CRS 5.4 ALTERNATIVE O FFERS
CRS 5.5 AMENDED TENDERS
CRS 5.6 ERRO RS IN PRICED BILLS
CRS 5.7 PO ST TENDER NEGO TIATIO N
CRS 5.8 RE-INVITATIO N O F TENDERS
CRS 5.9 TENDER REPO RTING
CRS 6.0 AWARDlNG CONTRACT5 & DECLlNlNG TENDER5
CRS 6.1 LEGAL CO NTRACT FO RMATIO N
CRS 6.2 ACCEPTANCE O F T ENDER
CRS 6.3 LETTER O F ACCEPTANCE
CRS 6.4 DECLINE O F UNSUCCESSFUL TENDERS
CRS 6.5 EX ECUTIO N O F FO RMAL AGREEMENT
CRS 7.0 DEBRlEFlNG
CRS 7.1 REQ UESTS FO R DEBRIEFING
CRS 7.2 DEBRIEFING INTERVIEWS
CRS 8.0 NOMlNATlON OF 5UB-CONTRACTOR5
CRS 8.1 NO MINATIO N PRO CEDURES
CRS 8.2 PRIME CO STS
CRS 8.3 ARRANGING A NO MINATED SUB-CO NTRACT
CRS 8.4 ESTABLISHING A CO NTRACT
CRS 8.5 LIQ UIDATIO N O F A N O MINATED SUB-CO NTRACTO R
CRS 8.6 SELECTED O R APPRO VED SUB-CO NTRACTO RS
HOME
CRS 9.0 MANAGEMENT OF CONTRACT5
CRS 9.1 RO LE O F THE PRO JECT MAN AGER
CRS 9.2 RO LE O F THE PRO JECT SPO NSO R
CRS 9.3 BILL PAYING
CRS 9.4 CHECKING PRO CEDURES
CRS 9.5 DETERMINATIO N/TERMINATIO N PRO CEDURES
CRS 10.0 CLAlM5 & Dl5PUTE5
CRS 10.1 GENERAL
CRS 10.2 CO NTRACT CLAIMS AGAINST THE DEPARTMENT
CRS 10.3 AVO IDANCE O F CLAIMS
CRS 10.4 MAN AGIN G CLAIMS
CRS 10.5 PRESENTATIO N O F CLAIMS
CRS 10.6 CLAIMS AGAINST CO NTRACTO RS
CRS 10.7 ARBITRATIO N
CRS 10.8 EX GRATIA CLAIMS
CRS 11.0 MATTER5 ARl5lNG ON COMPLETlON
CRS 11.1 LIQ UIDATED AND ASCERTAINED DAMAGES
CRS 11.2 MAINTENANCE PERIO DS
CRS 11.3 PAYMENTS
CRS 11.4 O VERPAYMENTS
CRS 11.5 HANDO VER
CRS 12.0 PERFORMANCE REPORTlNG
CRS 12.1 GENERAL
CRS 12.2 PERFO RMANCE REPO RTING TO NQ S
HOME
GACC
EDITION 2: FEB 1998
CRS 1.0 CONTRACTING STRATEGIES
CRS 1.1 PROCUREMENT PROCESS AND PROGRAMME
A guide to the stepsinvolved in the procurement of workscontractors
isasfollows:
Determine requirement, develop detailed brief and decide on
contract strategy
Identify capable contractorsto form a long list or if EC regulations
apply, advertise contract notice to invite expressionsof interest
Undertake pre-selection interviewswhere appropriate or if EC
regulationsapply, carry out pre-selection paper sift
Complile short listsfor tendering
Develop tender documentswhich define the brief
Invite tendersfrom short-listed consultants
Hold mid-tender interviewswhere appropriate
Evaluate tenders
Make the award and if EC regulationsapply publish contract award
notice
De-brief unsuccessful tenderswhere necessary
Post tender performance evaluation
PROCUREMENT PROCESS AND PROGRAMME
CONTRACTORS
CONTRACTING STRATEGIES
PS 2.1-2.5

PS 2.4

CRS 3.3

CRS 3.4

CRS 3.5

CRS 4.1

CRS 4

CRS 4

CRS 5

CRS 6

CRS 7

CRS 12

CRS 1.1.1
HOME
GACC
EDITION 2: FEB 1998
It should be borne in mind that thisisonly a guide to the steps
involved. The more complex or costly the work being procured then
the greater the amount of time and care that should be taken in the
pre-selection and selection processes.
Where the EC procurement rulesapply then the pre-selection process
with the restricted procedure will necessarily require a paper sift to
reduce what islikely to be an otherwise unmanageable number of
expressionsof interest.
A similar approach isrequired where a large number of contractorsare
invited to tender in order to establish a panel of contractorson the
basisof framework agreements, thisbeing a strategy that some
Department have successfully adopted. A panel isa set of contractors
who are selected for a term, without any guarantee of work, and might
be established by seeking tendersfor all regionsat once.
The form and basisof competition will need to be determined early in
the procurement process. Thiswill involve deciding upon which
proceduresit isappropriate to follow, and most importantly the
evaluation criteria which will be used to determine the successful
tenderer. In particular the basison which the price will be sought and
the way in which quality will be evaluated should be decided at the
outset.
Procurement Programme
It isrecommended that careful consideration isgiven to the production
of a procurement programme immediately following identification of
the objectivesof the project or workscontract. Clearly thisprogramme
should be developed in the context of the overall objectivesand
timetable. The procurement programme will depend upon the contract
procurement strategy which isto be followed, and should be updated
at each stage of the procurement process. The Department should
ensure that there issufficient time allowed in the programme and
expertise isavailable to carry out each of the above steps.
It isrecommended that the greater the complexity of the contract,
then the greater the time that should be allowed to tenderersto
consider, price and submit their tender bids. Tender periodswhich are
too short can lead to an inadequate consideration of the requirements
of the contract by tendererswhich may lead to under-pricing or over-
pricing and possibly to unwanted misunderstandings.
PROCUREMENT PROCESS AND PROGRAMME
CONTRACTORS
CONTRACTING STRATEGIES
EPP 1.8

CRS 3.1

CST 3.8

CRS 1.1.2
HOME
GACC
EDITION 2: FEB 1998
Where the EC procurement directivesapply, then specific procedures
apply and there are specific minimum or maximum time limitsfor the
variousstagesof the processdepending on which procedure is
followed. These will need to be reflected in the procurement
programme.
PROCUREMENT PROCESS AND PROGRAMME
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.1.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.2 APPLICATION OF EC PUBLIC PROCUREMENT RULES
It ismandatory that EC public procurement rulesare complied with
where they are applicable. It isalso essential that consultantsapply the
ruleson behalf of the Department, where they are dealing with
contractors. A clear obligation to do so should be included in the terms
of appointment of such consultants( see for example service A1.2.16
for the project manager in GC/Works/5 - General Conditions for the
Appointment of Consultants( 1998) , ISBN 0-11-7023108) .
The WorksDirective and UK Regulationsgovern the procurement of
workscontractsrequired by Government bodies.
A commission will be subject to the WorksRegulationsif:
the buyer isa contracting authority subject to the regulations;
the aggregated value of the contract together with any other
contractsassociated with a single work isabove the threshold,
which for workscontractsis5,358,153 ECU. The pound sterling
equivalent isrevised every two years, and asof 1 January 2000 this
figure is3,611,395;
it isnot the subject of one of the exclusions.
It isillegal to split the contract into two or more partsor breakdown
what isnormally a centrally purchased aggregated contract to avoid the
application of the rules. In addition there should be no deliberate
underestimating to avoid compliance.
Key Points
If the value of the commission exceeds3,611,395 ( asof 1 January
2000) the EC WorksRegulationsmay apply.
A more detailed consideration of whether the regulationsapply is
given in chapter EPP - EC Procurement Procedures, which also sets
out the specific timetablesand recommended procedures, for
inviting and evaluating tendersin accordance with the rules.
EC PUBLIC PROCUREMENT RULES
CONTRACTORS
CONTRACTING STRATEGIES
EPP

EPP 1.6

EPP 1.5

EPP 1.4

L
! !! !!
EPP 1

CRS 1.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.3 INTRODUCTION TO THE CHOICE OF CONTRACT
Guidance on the choice of contract strategy isgiven in the Procurement
Strategieschapter of the Guide.
The remainder of CRS 1 isdevoted to explaining in more detail each of
the principal typesof workscontract, when it might be appropriate to
use them and their advantagesand disadvantages. Guidance isalso
given in the Procurement Guidance Note No. 5, available from HM
Treasury ( tel. 020 7270 4558) .
There are two aspectsto the type of contract which may be adopted
for a particular workscontract or project strategy:
the basison which the price isto be sought; using:
- billsof quantities,
- schedulesof rates, or
- simple lump sum contracts;
the type of contract including:
- traditional lump sum contracts,
- design and build contracts,
- prime cost contracts,
- management contracts,
- construction management contracts,
- design and manage contracts,
- extension contractsand variations,
- term contracts.
INTRODUCTION TO THE CHOICE OF CONTRACT
CONTRACTORS
CONTRACTING STRATEGIES
PS 2

CRS 1.7

CRS 1.4

CRS 1.5

CRS 1.6

CRS 1.8

CRS 1.9

CRS 1.10

CRS 1.11

CRS 1.12

CRS 1.13

CRS 1.14

CRS 1.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
There are a number of bodieswho produce familiesof standard forms
of contract which include to a greater or lesser extent those listed
above. These bodiesinclude:
The GovernmentsGC Contracts( excluding management,
construction management and design and manage) ;
Joint ContractsTribunal ( JCT) Contracts( excluding construction
management and design and manage) ;
Institute of Civil Engineers( ICE) 5th and 6th Edition Contracts( bill
of approximate quantitiesformsfor civil engineering work) ;
The ICE Engineering and Construction Contract ( 2nd Edition)
Series( formerly the New Engineering Contract) ;
The Institute of Chemical Engineers( IChemE) Contracts;
The Association of Consultant Architects( AC A) Contracts;
The British Property Federation ( BPF) Contracts;
The Scottish Building Contract Committee ( SBCC) Contracts; and
others.
Having decided on which type of contract ismost appropriate, it must
then be decided which standard form ismost appropriate.
Many of the above bodiesprovide similar typesof contact, for example,
traditional lump sum contractsbased on firm billsof quantities; but they
have their differencesin termsof:
risk allocation;
payment mechanisms;
variation instruction and valuation mechanisms;
lossand expense or costsprovisions; and
others.
CRS 1.15

INTRODUCTION TO THE CHOICE OF CONTRACT


CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.3.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
It isnot the place of the Guide to attempt to analyse all the relative
advantagesand disadvantagesof each form, but the following
recommendationsare given:
each standard form isproduced by different bodieswhose interests
are reflected in their form;
provided the form satisfiesthe required scheme of risk allocation
and the project objectives, it isbetter to use a form with which the
Department and professional team are familiar than one with which
they are not;
the GovernmentsGC contractsare recommended for use by
Departmentsbecause they:
- were drafted by Government for Government and generally
represent the best interestsof Departments,
- are relatively simple to understand and administer,
- are lessprone to litigation than other more complex forms,
- contractorsonce familiar with the formsgenerally know where
they stand.
It should be noted that the 1998 and 1999 editionsof the GC/Works
contractshave been amended to take account of the CDM regulations.
Usersof the earlier editionsshould refer to Information Note ( No.6/
95) which advisesDepartmentsof the amendmentsnecessary to
enable these formsto take account of the CDM regulations.
Key Points
The choice of contract form dependson the basison which the
price isto be sought, ( whether by bill of quantitiesor otherwise) ,
and upon the contract strategy which best meetsthe project
objectives.
The GovernmentsGC contractsare generally recommended for
use by Departments.
INTRODUCTION TO THE CHOICE OF CONTRACT
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.1

CRS 1.3.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
Some standard conditions( eg ICE) contain clausesproviding for
application of Scotslaw to the contract where the worksare
situated in Scotland. If the standard conditionsto be used do not
contain such a provision, then a suitable clause must be inserted in
the supplementary or special conditionswhich form part of the
contract. Even if such a condition doesappear in the standard
conditions, there isno harm in a belt and braces approach by also
providing for thisin the supplementary conditions. If in doubt asto
wording, seek legal advice.
CRS 1.3.4
HOME
GACC
EDITION 2: FEB 1998
CRS 1.4 CONTRACTS USING BILLS OF QUANTITIES (BQ)
General
The use of a BQ in support of a contract isthe traditional and proven
meansof securing a lump sum price for undertaking the works. BQ s
may be:
firm;
approximate;
provisional.
The firmer the quantities, in other wordsthe more precisely the work
ismeasured and itemised, the more reliable isthe tender price. In
theory, were there no design development or departmental changes,
then a firm BQ would provide a price at the tender stage which would
equal the final cost. In practice there are changes, and the BQ provides
a good basisfor cost control since the direct cost of changesto the
contract can be assessed with reference to the BQ rates. Such changes
from the tender drawingsto the final construction detail are known as
variations. The firmer the BQ the better it isasa meansof post-
contract financial control. BQ salso provide one of the best resources
for estimating the value of future work.
A BQ isan itemised list of all the work required to carry out the
contract works. The BQ generally comprisesthe following sections:
PreIininaries - which describe the project particulars, the
drawingsupon which the BQ isbased, the site, the work in general,
the form of contract and any supplementary conditions, the
Departmentsrequirements, and all of the contractorsgeneral cost
itemsincluding management and staff, site accommodation, services
and facilities, mechanical plant, and temporary worksitems.
PreanbIes - contain the descriptionsof materialsand
workmanship applicable to the measured items, and generally more
fully describe what work isincluded in abbreviated descriptions,
including any special methodsof measurement. The preambleshave
to be read in conjunction with the measured itemsand significantly
reduce the need for long and full descriptionsof materialsand
standard of work.
CONTRACTS USING BILLS OF QUANTITIES
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.13

CRS 1.4.1
HOME
GACC
EDITION 2: FEB 1998
Measured Work - isthe main part of the BQ which listsall of the
itemsof work to be undertaken under separate sectionsfor each
element or trade such asbrickwork or joinery etc. Each item
comprisesa description of labour and/or materialswith a quantity
measured asfinished work taken from the completed design
drawingsand specification.
ProvisionaI 5uns - are included for any itemsof work which
might be anticipated but for which no firm design hasbeen
developed.
Prine Cost 5uns - are sumsallowed for specialist work such as
mechanical and electric work which iscarried out by nominated
sub-contractors, provided for under some standard formsof
contract such asJCT80.
Contingency 5un - it isoften tempting for a quantity surveyor to
include in the BQ a specific sum for contingencies( say 5% ) in
respect of unexpected expenditure. It isrecommended that
contingency sumsare allowed for, but that they be kept within the
knowledge of the Department.
Recommended Value
A firm BQ will normally be prepared when full design information is
available. The firmer the BQ the longer and more costly the
preparation time. BQ scan be produced for work of any value, but the
time and cost of doing so must be looked at in light of the level of
post-contract cost control that isrequired.
It will normally be appropriate to use BQ sfor work in excessof
500,000 in value.
Approximate BQs
Approximate or provisional BQ sare used when there isinsufficient
detail to prepare firm BQ sor where it isdecided that the time or cost
of a firm BQ isnot warranted. Such contractsdo not provide a lump
sum price, but rather tender totals, since the quantitiesare subject to
re-measurement on completion by the quantity surveyor. These
contractsare usually subject to greater variation than lump sum
contractsand therefore should only be used where time isa limiting
factor or where there isgreat uncertainty in respect of certain
elementssuch asmajor excavation and earthworks.
The initial resource cost of approximate BQ sislikely to be lower than
for a firm BQ , but the need for re-measurement invariably resultsin a
higher overall resource cost.
CONTRACTS USING BILLS OF QUANTITIES
CONTRACTORS
CONTRACTING STRATEGIES
CRS 8.1-8.3

L
! !! !!
CRS 1.4.2
HOME
GACC
EDITION 2: FEB 1998
CRS 1.5 CONTRACTS USING SCHEDULES OF RATES
Schedulesof ratesare generally used in one of two ways:
they are prepared by a contractor in support of itsprice, based on
specification and drawings, when tendering for lump sum contracts
without quantities; and
published standard schedulesor bespoke schedulesare provided to
the contractor who tendersa percentage adjustment to the
schedule; thisapproach being used for measured term contracts
covering such work asrepair and maintenance.
In the former case the contractor providesthe schedule, which isthen
used asa basisfor valuing post-contract variations. Thiseffectively
transfersthe work and cost of quantifying the worksonto the
contractor and usually requiresa longer tender period which is
sufficient to reflect the extra effort required of the contractor to
prepare the tender.
Schedules of Rates with Measured Term Contracts
Schedulesof ratesfor measured term contractsare available for a
variety of typesof work and are generally extensive to cover most
work items.
The precise quantity of work isunknown at tender stage. Neither the
Departmentsquantity surveyor nor the contractor produce a bill of
quantitiesor otherwise quantify the work, resulting in a shorter
procurement programme than otherwise.
The value of any work carried out in accordance with such contractsis
ascertained on completion of the work by measurement and valuation
in accordance with the ratesin the schedule, any percentage
adjustment tendered by the contractor and the updating percentages
to cover inflation.
CONTRACTS USING SCHEDULES OF RATES
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.7

LE 2.7

CRS 1.5
HOME
GACC
EDITION 2: FEB 1998
CRS 1.6 SIMPLE LUMP SUM CONTRACTS
With a simple lump sum contract the contractor commitsitself to a
price on the basisof the work shown on the drawingsand in the
specification. A quantity surveyor isnot usually employed and BQ sare
not used; thismeansthat preliminary cost forecasting, budgeting, and
valuing of changesin the scheme may be unsatisfactory. However,
where the Departmentsrequirementsare firm, and the drawingsand
specification are fully developed, thisisa very simple and effective
contractual basis.
It isgenerally only appropriate to use thistype of arrangement for small
schemes, otherwise it may be difficult to obtain pricesin competition.
SINGLE LUMP SUM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.6
HOME
GACC
EDITION 2: FEB 1998
CRS 1.7 TRADITIONAL LUMP SUM CONTRACTS
With thistype of contract the design team are engaged directly by the
Department to fully develop the design prior to going out to tender. A
firm BQ isgenerally prepared which ispriced by the contractor to give
a fixed price at the outset of the contract. ThisBQ also formsthe basis
of post contract cost control. The contract iswith a main contractor
who hasresponsibility only for the construction works.
Thisisa medium risk strategy for the Department, since the
Department takesthe responsibility and risk for design team
performance and the contractor takesresponsibility and financial risk
for the building workswhich it pricesin advance of carrying them out.
The contractor isresponsible for workmanship aswell asfor meeting
the programme.
If the design hasbeen fully developed and sufficient time hasbeen
devoted to the production of a firm BQ , then in theory thistype of
contact should lead to a high level of cost certainty at tender stage. In
addition, if the design hasbeen fully co-ordinated and there are no
clashesor other variationsdue to design development, then it might be
possible to avoid delaysand thusconstruct the worksmore quickly.
The development of a full design pre-tender istime consuming and
often an ideal which isnot consistent with meeting frequently very
tight timescalesfor workscontracts. O ften the extra time isnot
warranted and other typesof contract can be cost effective whilst
meeting shorter timescales.
It ispossible to have an accelerated traditional contract strategy by
overlapping some design with construction. Thisisoften done with the
early appointment of enabling contractorsto carry out such work as:
demolition;
site levelling;
piling;
infrastructure worksincluding service mainsand roads, etc.
TRADITIONAL LUMP SUM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.4

CRS 1.7.1
HOME
GACC
EDITION 2: FEB 1998
Such work islet and carried out whilst the design for the rest of the
work iscarried out. Thisapproach, whilst shortening the overall
programme, can create two principal problems:
Departmentsmay be unwilling to commit to such work prior to
overall project cost being clearly defined; and
the main contractor isvery unlikely to be prepared to assume the
risk of workscarried out by others, especially foundations.
Examplesof thistraditional type of contract are:
GC/Works/1 ( 1998) ( with quantities)
JCT80 Local AuthoritiesEdition ( with quantities)
Advantages of Traditional Lump Sum Contracts:
the Department maintainscontrol over the design team and cost
consultant through direct contractual relationshipswith them;
the Department hasa direct contract with the contractor and is
able to some extent to influence the contractorsperformance;
it ispossible to achieve high levelsof design and construction
quality;
liquidated damagesprovisionsprovide for the recovery of fundsdue
to culpable delay by the contractor;
the BQ providesone of the best basesfor post-contract cost
control.
TRADITIONAL LUMP SUM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.1

LE 2.8

CRS 1.7.2
HOME
GACC
EDITION 2: FEB 1998
Disadvantages:
the Department must have the appropriate expertise to ensure
effective management of the design risk, the timely provision of
accurate design information being essential to avoid claims;
the contractor isseparated from the design phase, which means
that there is:
- no design input from the contractor, which can otherwise lead
to design solutionswhich are more buildable and possibly
cheaper,
- the possibility of the traditional barriersbetween consultantsand
the contractor giving rise to poor co-operation;
the overall programme may be longer than for other contract
strategiesbecause of the time taken for full design development and
preparation of BQ s.
TRADITIONAL LUMP SUM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.7.3
HOME
GACC
EDITION 2: FEB 1998
CRS 1.8 DESIGN AND BUILD CONTRACTS (D&B)
General
With thisprocurement strategy, the contractor takesresponsibility and
risk for both the design and the construction of the worksfor a fixed
price lump sum.
The D&B strategy generally representsthe lowest risk strategy for
Departments, and the D&B contractor offersa single point of
responsibility. For certain typesof work such aspiling, it may be more
appropriate to engage specialist contractorson a D&B basissince they
may be better able to provide the required design expertise.
Thisprocurement strategy hasvariantsdepending on the statusof the
design, such as:
Direct - where a designer/contractor isappointed without
competition on account of prior knowledge or commercial
expediency. Thisisgenerally not the recommended approach, and
would only be used in exceptional circumstances.
Conpetitive - where a limited number of contractorsare invited
to submit designsand pricesin competition on the basisof
documentsdefining the project. These may be prepared by in-house
professional advisorsor by consultants.
DeveIop and Construct - where consultants( or in-house
designersasappropriate) are appointed to design the project to a
certain stage including securing any planning permission. Tendersare
then invited from contractorsto develop and complete the design
and construction of the building. Thismay be undertaken by the
contractorsown design team, or if design continuity isimportant, it
may be stipulated that the design team originally appointed be
transferred ( in the case of external design consultants) to the
contractor, for completion of the design under the responsibility of
the contractor. Thisprocessiscommonly known asnovation.
DESIGN AND BUILD CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
LE 1.12

CRS 1.8.1
HOME
GACC
EDITION 2: FEB 1998
The project brief and the requirementsof the Department are set out
in a document called the EmployersRequirements or Authoritys
Requirements. Thisisa key tender document and isthe basison which
the D&B contractor providesthe contractorsproposalsand itstender
price and developsand completesthe detailed design.
If the requirementsare not properly developed and defined with clarity
then thiscan be very costly, since any requirementswhich are not
specified or are changed will be variationsto the contract. Thisstrategy
worksbest when there are few variationsor changesto the
Departmentsrequirements, since such changestend to be more
expensive than other strategies.
Because the design risk istransferred to the contractor, the
Department losessome control over the project. It should be borne in
mind that D&B contractssecured under competition lead to the
contractor adopting the simplest and cheapest specificationsrequired
to meet the Departmentsrequirements. There isgenerally a trade-off
between the time saving and risk transfer, and quality control. The
Departmentsrequirementsshould therefore include performance
specificationsand clearly state the minimum acceptable standardsof
design and specification.
For the reasonsstated above, the use of the D&B strategy isgenerally
not recommended for complex buildingsor for work where the
Department wish to have a high level of involvement in design
development.
Design Liability
There are two alternative standardsof design liability which are implied
by law or expressly required by the contract:
reasonable skill and care; and
fitnessfor purpose.
Fitnessfor purpose isa greater obligation than the use of reasonable
skill and care. Generally the professional designer isunder an implied
obligation to exercise reasonable skill and care in carrying out itsdesign
duties. O n the other hand a builder who undertakesboth the design
and the construction of work will be under an implied duty to ensure
that the work isfit for the purpose for which it wasintended ( unless
stated otherwise in the contract) .
DESIGN AND BUILD CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.8.2
HOME
GACC
EDITION 2: FEB 1998
If thingsgo wrong, a professional designer may be able to show that it
used reasonable skill and care, i.e. the ordinary skill of an ordinary
competent man exercising that particular art. In other wordsthe test is
by reference to the level of skill and care which would reasonably by
expected of other professionalsof that discipline. In addition,
consultantsmay rely upon the state of the art defence - that specified
materialswhich are subsequently found to be inadequate were at the
time of being specified untried and untested but that their specification
wasneverthelessreasonable.
A contractor, whose standard of design liability isfitnessfor purpose
cannot rely on such defences, and for example a contract for the
design, supply and installation of a radio mast must result in a radio
mast which standsup aswell asoperatesasa radio mast. In the event
of a failure of the mast the contractor will be responsible for providing
or paying for a replacement which isfit for itspurpose. The contractor
cannot rely, asit would under the traditional contract strategy, on the
fact that the Departmentsdesigner specified the mast and that it may
have been the specification which led to the failure rather than the
method of installation.
Because contractorsare generally unwilling to accept design liability on
the basisof fitnessfor purpose, the commonly used standard formsof
D&B contract specify a duty of reasonable skill and care.
Single Stage D&B Contracts
These contractsare widely used for standardised relatively simple
buildingssuch ashousesand individual units.
O n the basisof the Departmentsrequirements, it isnecessary for
tenderersto undertake a certain amount of design in order to submit a
tender for thisapproach. It iscommon practice to invite no more than
3 tenderersfollowing an interview with 6 or more firms. The purpose
of restricting the tender list to 3 isto avoid, asmuch aspossible, the
abortive tendering cost arising from design production by unsuccessful
tenderers.
DESIGN AND BUILD CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 3.4

CRS 1.8.3
HOME
GACC
EDITION 2: FEB 1998
Two Stage D&B Contracts
These contractsare recommended for projectsof a more complex
nature where the Department may require a higher standard of quality
and prestigiousfinishes. Thisprocessrequiresa clearly defined brief
from the outset to achieve the requisite level of quality.
Stage 1 - the Department should invite tendersrequesting the
following submissions:
- outline design
- price for completion of design
- estimated price for construction
- outline programme showing estimated start and finish dates.
The tendererswhose proposalsare judged to be the most
economically advantageousare awarded the first stage contract.
Stage 2 - If at the end of Stage 1 the contractor hasproduced an
acceptable design and offersan acceptable price for construction
they are awarded Stage 2. In Stage 2 the contractor isrequired to
complete the contract within the agreed programme and cost.
The contractor may attempt to price the construction work above
their estimated price after they have won Stage 1. In order to combat
thisit isrecommended that the Department should:
specify in the Stage 1 conditionsof contract that the Department is
entitled to use the design for tendering the workscontract;
employ a Q S to control the cost of transition from Stage 1 to
Stage 2;
ensure that the Stage 1 design isreadily capable of being built by
another contractor.
The Department should also guard against any undue interference with
the contractorsdesign which may lead to an unwanted transfer of
design liability.
DESIGN AND BUILD CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.8.4
HOME
GACC
EDITION 2: FEB 1998
Examplesof D&B contractsare:
GC/Works/1( 1998) - Single Stage Design and Build Version;
JCT81 - with ContractorsDesign.
Advantages of D&B contracts:
the risk of design, cost and time are transferred to the contractor
who representsa single point of responsibility in the event of
problems;
completion may be achieved earlier because there isscope for
overlapping design and construction;
price certainty isobtained at tender stage, provided the
Departmentsrequirementsare adequately drafted and there are no
changes;
it ispossible to require of the contractor a greater duty of care than
would normally be required of a design consultant.
Disadvantages:
the Department losescontrol over design development and quality;
contractorsare likely to opt for minimum cost design solutions;
variationscan be more costly;
price certainty may not be asattractive asit seemsif, for example,
the contractor failsproperly to understand and manage the design
process, and/or exploitsuncertaintiesin the clientsrequirements;
the strategy isnot recommended for complex buildings.
DESIGN AND BUILD CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.3

CRS 1.8.5
HOME
GACC
EDITION 2: FEB 1998
CRS 1.9 PRIME COST CONTRACTS
General
With prime cost, or cost pluscontractsthe Department paysthe prime
cost of the work carried out, plusa fee to the contractor. The
contractor doesnot tender a contract price but instead tendersa
percentage fee, and possibly plant rates. The final cost istherefore
whatever it costsplus the contractorsfee.
Prime cost contracting representsa high risk strategy for a
Department, since the final cost isopen-ended and post contract cost-
control isdifficult. Because of the uncertainty of the final cost, it is
generally recommended that the use of prime cost contractsisavoided
unlessabsolutely necessary.
Exceptionally it may be necessary to use prime cost contractswhere
the requirementsof the work are not known in detail either because
of:
the nature of the work, such asemergency maintenance or damage
repair, e.g. fire damage; and/or
an acute shortage of time.
Prime cost contractswill generally only be used where it isnecessary
to procure a contractor very quickly. Normal procurement procedures
are not normally possible and it isrecommended that the selected
contractor isone which hasa proven track record with the
Department for reliability and integrity.
Prime cost contractsoften have the following characteristics:
since the scope of work isill-defined the specification and quantity
of work isoften vague;
resource limitsand time limitsare agreed, although they are often
revised when more information isavailable;
the contractor undertakeswork through instructionsfrom the
supervising officer or the project manager;
they are expensive to administer because of the amount of checking
of invoicesand supporting paperwork.
PRIME COST CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.9.1
HOME
GACC
EDITION 2: FEB 1998
It isessential to clearly define what isincluded in the prime cost and
what isincluded in the fee. Typically the split will be asfollows:
prime cost items:
- material costssupported by invoices,
- labour costssupported by labour returns, salary slipsetc.,
- servicesand chargessuch asinsurances,
- sub-contracted work,
- plant costs( time or usage ratespossibly tendered by contractor) ;
contractorstendered fee to include such thingsas:
- management costs,
- temporary site accommodation and office equipment etc.,
- small tools,
- consumables,
- overheadsand profit.
With a simple percentage plus fee, it isvery much in the contractors
interest to expend asmuch prime costsaspossible. O ther than the
contractorsgoodwill, there isno incentive for the contractor to use
resourceseffectively or to keep coststo a minimum. Better cost
control should be achieved by changing the basisof the fee. The
following are examples:
fixed lump sum fee - the contractor gainsnothing by increasing the
cost, ( see for example the JCT Prime Cost PlusFixed Fee Contract) ;
a problem with thisapproach isthat the contractor may be unfairly
penalised if the scope of the work increases;
sliding scale fee - the percentage addition for the fee reducesasthe
prime cost increases;
target cost pluscontractorspercentage fee.
PRIME COST CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.9.2
HOME
GACC
EDITION 2: FEB 1998
Target Cost
Target cost contracting requiresthe agreement of target costsfor each
of the elementsof the work to be carried out. Thistherefore
necessitatesa reasonable knowledge of the work required and
estimatesof the likely cost. The target cost comprisesthe estimated
prime cost plusthe contractorsfee. The incentive for reducing costs
comesby allowing the contractor a percentage share of any saving to
the target cost. If the actual cost exceedsthe target then the
contractor may receive full payment for the excessor have to pay a
percentage contribution to the excessdepending on the basisof the
contact. An example of a target cost contract isthe Engineering and
Construction Contract ( 2nd Edition) - Target Contract with Activity
Schedule.
Advantages of Prime Cost Contracts:
they enable a very quick mobilisation of the contractor before the
workscope isdefined or designed.
Disadvantages:
the final cost isnot known until the work iscomplete;
costsare difficult to control;
it costsmore for the Department to administer, since all invoices
etc. have to be checked;
timescalesmay be difficult to define.
PRIME COST CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.9.3
HOME
GACC
EDITION 2: FEB 1998
CRS 1.10 MANAGEMENT CONTRACTS
A management contract iswhere a management contractor is
appointed by the Department to manage the overall contract worksin
return for a management fee ( usually a percentage of the cost of the
works) . The idea behind management contracting isthat the
management contractor isappointed early, before the design is
complete, to advise on buildability, programme, sequencing and
procurement of workspackages, and isintended to have a closer
relationship with the Department.
Thisisa fast track procurement strategy whereby the early packages
are let before the rest of the design iscomplete. Workspackagesare
commonly secured on a lump sum basiswith a bill of quantitiesor
schedule of rates. Thismeansthat cost certainty isnot achieved until
the last package islet.
The Department engagesthe design team, and therefore retainsthe
risk of design development and it also engagesthe management
contractor. The management contractor procuresand contractswith
each of the workscontractorswhose packagesare designed and let in
order of construction and in accordance with a detailed package
procurement programme. The management contractor might provide
site officesand other common services, such aswelfare and site
cleaning, etc., but doesnot otherwise carry out any of the work. The
management contractor will normally have joint responsibility with the
quantity surveyor for developing and managing the budget and for
post-contract cost control.
Whilst it may appear that the management contractor takesthe
financial risk of construction, it iscommon for management contracts
to contain a provision to the effect that in the event of a default by a
workspackage contractor, the Department will be liable for the cost of
that default to the extent that the management contractor isunable to
recover such costsfrom the defaulting workscontractor itself. In this
way the management contractor hasto manage failuresand do all it
can to resolve them, but the Department may foot the bill if the
management contractor would otherwise be out of pocket. Thisisthe
trade-off for securing the management contractorsexpertise aspart of
the professional team.
MANAGEMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.10.1
HOME
GACC
EDITION 2: FEB 1998
Because of the sequenced way of letting packages, procurement and
therefore workspackage costscan be adversely affected by design
delays, design development, and changing market conditions. Good
management and in particular design and cost management istherefore
essential to reap the maximum advantage of the time saving that this
procurement method can provide. Thisstrategy requiresmore effort
and involvement from the quantity surveyor in preparing tender
documentsof workspackagesand in monitoring and managing costs.
Therefore where thisstrategy isopted for, it isrecommended that
consultantsshould be so advised at the time they are procured.
By way of general guidance, thisstrategy isgenerally appropriate for
major worksschemesin excessof say 5 million in value.
Management contractors feesvary around 2 % -3% of total works
package costs. Site facilitiesetc. are usually reimbursed at cost. The
quality of the management contractorsteam istherefore probably the
single most important factor in choosing a firm in a competition.
Selecting a firm who offersthe lowest price could be a very poor
decision and provide poor value for money in the long term.
If the management contracting strategy ischosen it isimportant to
note that there isno standard set of Government conditions. Examples
of standard formsare:
the JCT87 Standard Form of Management Contract;
the Engineering and Construction Contract ( 2nd Edition) -
Management Contract;
many contractorsprovide their own forms.
Advice should be sought on the choice of form to be adopted since
standard formsmay not provide the Department with the safeguards
and risk transfer it requires.
MANAGEMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.10.2
HOME
GACC
EDITION 2: FEB 1998
Advantages of Management Contracting:
the overlapping of design and construction providesfast track
development;
the management contractor bringsitsconstruction expertise to the
design team earlier, when design, buildability and programming and
management can be of most value;
it can be used for complex buildings;
the Department retainscontrol of design development and design
quality;
changescan be accommodated in later packages;
the management contractor takessome of the risk for the
performance of workscontractors.
Disadvantages:
the cost isnot known with any certainty until the last package islet;
careful and effective management of the design team isrequired,
design development in particular hasto be closely controlled;
higher standardsof cost management are required;
there isno direct contractual relationship between works
contractorsand the Department, possibly requiring the use of
warranties;
the Department must have the expertise and/or resourcesto
administer the management contractor aswell asthe design team.
MANAGEMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.10.3
HOME
GACC
EDITION 2: FEB 1998
CRS 1.11 CONSTRUCTION MANAGEMENT CONTRACTS
Construction management isgenerally applicable for use with complex
major worksprojectswhere the Department hasthe need and the
expertise and resourcesto have a high level of involvement in both the
design development and the construction of the work.
A construction manager isappointed for a fee to provide buildability
and design input advice, and to programme and co-ordinate the design
and construction activities, aswell asmanaging key dateswhen input
from the Department isrequired. Trade contractorshave a direct
contract with the Department and the construction manager carries
out only planning, site management and co-ordination of the trade
contractors.
The construction manager effectively hasthe role of managing the
construction work with no financial risk.
Thisisalso a fast track procurement method since packagesare let, on
a lump sum basis, before the design for subsequent packageshasbeen
let. For the Department thisisa high risk strategy, but one which
enablesa high level of Departmental influence. For social contracts
such asHousing Action Trust work, thislevel of involvement may ideally
suit a Trustsobjectives.
The construction manager should be selected for hisor her skillsin
programming, management and control and for an ability clearly to
understand and align with the objectivesof the Department.
Effectively thisstrategy enablesshorter programmes, and secureshigh
quality buildingswith high levelsof input from the Department, but at
the expense of cost certainty.
There are no standard formsof construction management contract,
although many construction management companieshave developed
their own forms.
CONSTRUCTION MANAGEMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.11.1
HOME
GACC
EDITION 2: FEB 1998
Advantages of Construction
Management Contracts:
fast track development ispossible because design and construction
can be overlapped;
it can be used for complex buildings- LondonsBroadgate
development wasconstructed using thisstrategy for example;
the Department retainshigh levelsof involvement and influence;
the Department retainsdirect control over the design team and
over output quality;
advantage can be gained from procuring the expertise of specialist
contractorsin providing early design input advice;
the project manager and construction manager can better develop
relationshipswith the trade contractors, rather than a main
contractor, in order to create close co-operation and direct
resolution of problemsand claims;
information flow can be quicker and therefore more effective;
thisisa flexible strategy where, for example, elementsof design can
be included in some packagesand not others;
changescan be accommodated in later packages;
the construction manager iseffectively a member of the professional
team and more closely aligned to the Department.
Disadvantages:
the construction manager takesno financial risk in the construction
project;
the level of risk transfer to the construction manager and trade
contractorsislower than traditional contract strategies, because the
Department isresponsible for delaysby one trade contractor which
may affect others, ( although the Department can claim against a
trade contractor who causesdelay to others) ;
price certainty isnot achieved until the last package islet;
the Department must have the resourcesand expertise to
administer the design team and each of the trade contractors.
CONSTRUCTION MANAGEMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.11.2
HOME
GACC
EDITION 2: FEB 1998
CRS 1.12 DESIGN AND MANAGE CONTRACTS
A design and manage strategy issimilar to management contracting.
The difference isthat the management contractorsfee also coversthe
responsibility for design aswell asfor managing the workscontract
packages.
Thisisalso a fast track method but one which providesfor design risk
transfer. Where the work isnot overly complex and where quality is
not a major issue, then it may be more appropriate to consider the use
of a design and build contract. Some of the differencesbetween the
design and manage approach and the design and build strategy are:
design and manage can be used for complex buildingswhereas
design and build isnot recommended for such buildings;
the design and manage contractor isunlikely to take full financial risk
in the way that a design and build contractor does;
with design and manage, quality ismore controllable and design
development ismore flexible than design and build but at the
expense of losing cost certainty until much later in the project.
There are no standard formsof design and manage contract.
Advantages of Design and Manage Contracts:
the contractor takesresponsibility for integrating design and
construction, thusovercoming the traditional design team/
contractor barriers;
the contractor offersa single point of responsibility;
completion can be achieved earlier because of the scope for
overlapping design with construction;
it can be used for complex buildings.
Disadvantages:
price certainty isnot achieved until the last package islet;
the Department losesdirect control over design quality;
there isno direct contractual relationship between works
contractorsand the Department, possibly requiring the use of
warranties.
DESIGN AND MANAGE CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.10

CRS 1.8

CRS 1.12
HOME
GACC
EDITION 2: FEB 1998
CRS 1.13 EXTENSION CONTRACTS AND VARIATIONS
General
These contractsare also referred to ascontinuity contracts, whereby a
contractor already present on site isinstructed to undertake
modification or additional work under a variation instruction. In order
for a variation to be valid under the contract, the work should not be
beyond the scope of the original contract, such that it would represent
a substantial departure from the original contract in termsof character,
extent and time. If the additional worksare beyond the scope of the
original contract then they should be let under a separate contract.
Provided that the work can be agreed satisfactorily between the
Department and the contractor, the work will be subject to the original
conditionsof contract and valued in accordance with the rulesfor
valuation of variationsappropriate to that contract.
Claims and Cost Control
Instructing additional work will present the contractor with scope to
claim extra time and additional cost due to increased preliminaries
( prolongation) and disruption to the contract works. Q uite often the
contractor can successfully sustain itsargument since there isa limit to
the amount variationswhich can be absorbed without affecting the
completion date. Perhapsthe best method for controlling the cost of
variationsisto agree the time and cost implication asa lump sum
quotation ahead of the work being carried out, which for example may
be instructed under Condition 40( 5) GC/Works/1 ( 1998) . This
approach hasbeen further endorsed in the Engineering and
Construction Contract ( 2nd Edition) , ( formerly the New Engineering
Contract) asa way of reducing conflict under contracts.
It isrecommended that Departmentshave in place effective change
control procedureswhich ensure that the Department hasthe final say
over the issue of significant variations( by setting a value threshold for
example) and that time, cost and quality issuesare properly evaluated
and balanced against the benefit of instructing the variations.
EXTENSION CONTRACTS AND VARIATIONS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.13.1
HOME
GACC
EDITION 2: FEB 1998
Forms of Contract
Thisprocesscan be initiated on all contractscontaining variation
provisions. The ascertainment of the value of the variation isgenerally
easier where the contract isbased on a firm BQ , and potentially more
difficult with specification and drawingscontracts.
EXTENSION CONTRACTS AND VARIATIONS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.13.2
HOME
GACC
EDITION 2: FEB 1998
CRS 1.14 TERM CONTRACTS
General
Term contractsare often referred to ascall-off contractsand they are
usually suitable where a continuousprogramme of work isrequired of
a particular type for which the scope can be approximately defined in a
schedule of rates. The term or duration of these contractstend to run
for 3 to 5 yearsbut can often be terminated by notice by either party.
These type of contractsare often favoured byDepartmentswhich
have a continuousrequirement for maintenance or minor work at
either regular or irregular intervals.
It isrecommended that a break clause isincluded which enablesthe
Department to bring the contract to an end in the event of a change
of requirementsor because of budgetary constraints.
Term contractsgenerally exhibit the following characteristics:
the contract isusually for a particular type of work i.e. general
repairs, stating the maximum and minimum order value;
the contract statesspecific response timesto variouscategoriesof
order e.g. urgent repairs;
the contract isusually confined to a geographic area;
the value of the work isascertained in accordance with agreed
ratesand pricesusually on the basisof a schedule of rates;
the cost of setting up and administering these contractstend to be
comparatively lower than the cost of a seriesof one-off contracts.
TERM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.14.1
HOME
GACC
EDITION 2: FEB 1998
Advantages of Term Contracts:
the procurement cycle isshort and the costsof preparing tender
documentsislow;
the cost of work isfixed in advance, with some allowance for
fluctuations;
procurement costsare cheap because only one contractor is
secured for the term;
one contractor isin place to carry out the work whenever required;
a continuity of labour reducesthe burden on security clearance.
Disadvantages:
since no guarantee of work isgiven, the contractorsperformance
can deteriorate if the contract isnot much used by the Department;
it isdifficult to estimate resource costsand therefore to accurately
predict the rate to undertake a particular element of work where
future quantitiesand costsare unknown;
schedulesof rates/pricestend to encompassa wide range of items.
When the contractorsprofit isspread over these items, especially
where many of the itemsare never required, the contractor may
find these pricesuneconomical over the term and may issue notice
of termination;
on a long running term contract, the convenience and expediency
may take precedence over commercial considerationsi.e. the cost
of undertaking the work may be cheaper on an ad hoc basisdue to
changesin the market conditions;
all worksmust be inspected by the supervising officer and the value
of each order re-measured on completion.
It isrecommended that the market should be regularly tested to
monitor fluctuationsin market conditionsand therefore the continuing
competitivenessof any ratesor prices.
TERM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.7

CRS 1.14.2
HOME
GACC
EDITION 2 REV 1: JAN 1999
Types of Term Contracts
Heasured Term Contracts - these contractsare often based on
a schedule of ratesor prices;
5pecialist Term Contracts - these contractsare often based on
lump sum quotationsfor worksof a specialist nature e.g. lift
maintenance, window cleaning etc.;
Daywork Term Contracts - thisarrangement isoften used for
small workswhere the work ispaid for on a prime cost basis.
Measured Term Contract (MTC)
The featuresof an MTC are asfollows:
They are usually based on a schedule of rates, which are often
published on standard forms. Tendersare obtained by firmsquoting
percentage adjustmentsi.e. addition to or deductionsfrom the
schedule of rates.
The percentage adjustment appliesto all ordersissued pursuant to
the MTC . However, Government contractsfor electrical services,
mechanical servicesand groundsmaintenance allow differing
percentage adjustmentsto different categoriesof item in the
schedule of rates.
In order to provide the contractor with some basisfor pricing and in
order not to over stretch the contractor, it isusual to specify in the
contract minimum and maximum order values. Under the
Governmentsstandard form GC/Works/7( 1999) any order ispriced
at the net value of measured work which comprisesthe contractors
tendered adjustment applied to the ratesin the schedule.
To allow for labour and material cost inflation, the ratesare adjusted
each month by the appropriate Updating Percentagesfor MTCs.
The resulting value isthen identified asthe Net Updated Value of
measured work. It should be noted that the Schedule of Ratesand
Updated Percentagesonly reflect national price levelsnot regional
levels.
The Departmentsposition isprotected asfar aspossible by
provisionswhich provide for each order to specify a completion
date and an obligation on the contractor to proceed regularly and
diligently with the work so asto complete by the completion date
on the order. The work isrequired to be carried out to the
satisfaction of the supervising officer.
TERM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.7

CRS 1.15.12

LE 2.7

L
! !! !!
CRS 1.14.3
HOME
GACC
EDITION 2 REV 1: JAN 1999
An MTC can accommodate a Lump Sum Maintenance Element
( LSME) i.e. where the contractor operates, maintainsand repairs
plant, usually for an annual sum. The lump sum isadjusted annually
on the anniversary of the commencement date in accordance with
the variation of price ( VO P) formula set out in the conditionsof
contract. Payment of the annual lump sum isusually paid in 12 equal
monthly instalments. LSME isoften used for the following works:
- heating and air-conditioning in a crown court etc.;
- domestic boilerson a married quarterssite;
- specialist equipment in a hangar etc.
Aswith any lump sum contract, there isa danger that the contractor
will carry out minimal repairswhich may result in the plant
deteriorating more rapidly than otherwise. Consequently continual
performance monitoring and supervision isrequired to reduce thisrisk.
Specialist Term Contracts
These contractsare particularly useful for the servicing and inspection
of M&E plant and the like. The contractor hasthe primary responsibility
to maintain the plant through routine servicing and in the event of
breakdown or failure the contractor carriesout the necessary repairs
without reference to the Department.
The contractor quotesannual lump sumsfor the tasksand ispaid 12
equal monthly payments. The Department must ensure that the work is
carried out in accordance with the contract, by monitoring and
checking the plant and site recordsetc.
TERM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.14.4
HOME
GACC
EDITION 2: FEB 1998
Daywork Term Contracts
Thiscontracting strategy isrecommended only where order valuesare
likely to be low and where security and familiarity with the site is
necessary. The two major reservationswith thisapproach are:
contractorstend to complete tasksmore slowly than they would for
a lump sum contract due to the lack of incentive;
supervision of the worksisnecessary to verify accounts.
Thistype of contract can be a license to print money for a contractor
and should be used with great care.
In order for contractsto operate successfully the Department should
carry out all necessary checksand auditsto the contractorsdaywork
sheetsand records. These include:
checking that there isno double counting i.e. same person on 2
separate sitesat the same time;
verifying the hourscharged against office pay records;
checking the reasonablenessof the hoursand materialsused;
ensuring that the ratesare correct;
making sure that travel time ischargeable.
TERM CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
L
! !! !!
CRS 1.14.5
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15 STANDARD GOVERNMENT CONTRACTS
All GC/Worksformsof contract are essentially developed from the
GC/Works/1 Edition 3 version ( Revised 1990) which wasfirst
published in 1989. Edition 3 wasa more management-orientated
contract than itspredecessor ( Edition 2) and makesspecific provision
for administration of the contract by a Project Manager on behalf of
the Employer.
GC/Works/1 contract formscan be used to procure major building and
civil engineering worksand are suitable for use on either major
refurbishment or new worksprojects. Six versionsare available
together with a comprehensive Model Formsand Commentary
volume, asfollows:
GC/Works/1 ( 1998) Lump Sum with Q uantities;
GC/Works/1 ( 1998) Lump Sum without quantities;
GC/Works/1 ( 1998) Single Stage Design & Build;
GC/Works/1 ( 1999) Two Stage Design & Build;
GC/Works/1 ( 1999) With Q uantitiesConstruction Management
Trade Contract;
GC/Works/1 ( 1999) Without Q uantitiesConstruction Management
Trade Contract.
GC/Works/1 ( 1998) Model Formsand Commentary;
Each of the individual versionsissuitable for use in conjunction with a
particular procurement strategy selected by a Department.
O ther standard property-related Government formsof contract are:
GC/Works/2 ( 1998) For use with Building and Civil
Engineering Minor Works
GC/Works/3 ( 1998) For use with Mechanical and Electrical
Engineering Works
GC/Works/4 ( 1998) For use with Building, Civil Engineering,
Mechanical and Electrical Small Works
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
GC/Works/5 ( 1998) For Appointment of Consultants( Single
Project) ( see CST 1.5)
GC/Works/5 ( 1999) For Appointment of Consultants:
Framework Agreement ( see CST 1.6)
GC/Works/6 ( 1999) Daywork Term Contract
GC/Works/7 ( 1999) Measured Term Contract
GC/Works/8 ( 1999) Specialist Term Contract for Maintenance
of Equipment
GC/Works/9 ( 1999) O peration, Repair and Maintenance
Contract for M & E Plant, Equipment and
Installationsetc
C1303 Window Cleaning
C1304 Chimney Sweeping
C1306 Maintenance of Gardens, Grounds, etc
C1312 Supply and Application of Herbicidesetc
C1804 Repair of Plant.
A brief commentary on the major featuresof each of these standard
Government formsisoutlined in sections1.15.1 to 1.15.15 with the
exception of GC/Works/5 ( which relatesto the appointment of
consultants, CST 1.5 and 1.6 refer) .
Note: An approximate quantities version of GC/Works/1 iscurrently
being tested on a number of trial .
A new GC/Works/Subcontract form, suitable for use between the Main
Contractor and hisSubcontractor, isin the processof being developed.
It isdue to be published by March 2000.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.2
HOME
GACC
EDITION 2 REV 2: JAN 2000 CRS 1.15.1.1
CRS 1.15.1 GC/WORKS/1 (1998) - LUMP SUM WITH QUANTITIES
(TSO - ISBN 0-11-702186-5)
Recommended Value
Value thresholdswill be a matter of policy for each Department and
will depend on the scale of work normally carried out by the
Department.
By way of general guidance, it isrecommended that where the chosen
strategy isthe traditional lump sum contract strategy, then it is
appropriate to use the with quantities version of thiscontract where
the workselement of major alterationsrefurbishment or new work
exceeds250,000.
Major Features
The major featuresof thiscontract are asfollows:
the contract isadministered by a Project Manager ( PM) on behalf of
the Employer;
Condition 1A imposesa duty on all of the partiesto the contract to
deal fairly with each other and asa team;
in line with Constructing the Team recommendation that there be
flexibility in payment methods, Condition 48 ( Advances on account)
hasbeen amended to offer three alternative payment methods. The
alternativesare stage paymentsbased on the contractorsprogress
measured against hislatest accepted programme, paymentsbased
on the achievement of Milestonesby the contractor which have
been agreed pre-contract and recorded in the Milestone Payment
Chart and payment based on the measurement and validation of
work executed and materialson site;
the contractor ispaid 95% of the total sum payable in each month;
a 5% reserve iswithheld from each interim payment assecurity in
respect of defects( see Condition 21) ;
a new optional condition hasbeen introduced which enablesthe
Employer to make paymentsto the contractor to cover high
mobilisation costs( see Condition 48B) ;
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000 CRS 1.15.1.2
a new optional condition hasbeen introduced allowing payment to
be made for thingsoff site ( see Condition 48C ( not applicable in
Scotland) ) ;
there isa heavy focuson valuing variationsat the time they arise
and preferably before the worksare carried out;
in order to reduce the scope for claimsafter the majority of the
workshave been completed, in accordance with Condition 41( 2)
the value of variationsisto include any disruption to or
prolongation of both varied and unvaried work;
in accordance with Condition 42( 6) if in the opinion of the Q S a
variation hasa disruptive effect on other work then the Q S may
adjust the ratesfor such work to make due allowance for the
disruptive effect;
the recovery of expensesincurred because of prolongation and
disruption caused by such mattersaslate issue of information is
dealt with by Condition 46;
the obligationsimposed by the Construction ( Design and
Management) Regulations( 1994) have been incorporated in the
contract ( see Condition 11) ;
finance chargesare excluded from the contractorslossor
disruption costs, but are paid instead ( at a rate decided by the
Employer) on any sumsoutstanding, only if the Employer or Project
Manager have failed to comply with any time limitsin the contract
or if the Q S revalueswork, provided such failure isnot consequent
on further particularspresented by the contractor;
Condition 33 now requiresthe contractor to submit hisprogramme
with histender. The little used Edition 3 provision for submission of
the programme post award hasbeen dropped. The programme
must show the sequence of work and must be in sufficient detail to
enable effective monitoring of the progress. It must allow reasonable
periodsfor the provision of information and identify any events
which are critical to completion of the work. The programme
cannot include any float time, and it can only be varied by
agreement;
the contractor isgiven possession of the site by specific notice in
accordance with Condition 34;
the contractor isentitled to an extension of time in accordance
with Condition 36;
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.1

HOME
GACC
EDITION 2 REV 2: JAN 2000
provision ismade in Condition 55 for the Employer to deduct or
seek the payment of liquidated damagesfor culpable delay;
a measure of design liability isimposed on the contractor by
Condition 10, in recognition of the fact that contractorsare often
involved in the design;
time limitsand notice requirementshave been placed throughout
the contract which fully comply with the requirementsof Part II of
the Housing Grants, Construction and Regeneration Act 1996 ( for
example see Condition 50A) ;
Condition 51 providesthat defectsnotified to the contractor which
the Employer believesto be the responsibility of the contractor
must be remedied; if the contractor can show that any defect was
not due to hisdefault then he will be entitled to payment for the
remedy;
Condition 52 allowsthe contractor to suspend work on the
contract due to non-payment by the Employer;
the adjudication proceduresintroduced in Edition 3 have been
amended to bring them into line with the requirementsof Part II of
the Housing Grants, Construction and Regeneration Act 1996 ( see
Condition 59) ;
acceleration isprovided for should it be required;
Condition 56( 8) allowsthe Employer to determine the contract at
any time without reason. Thismight be useful if, for example, policy
ischanged or fundsare withdrawn with little or no notice;
optional Condition 66 enablesthe Employer to require the
contractor to maintain a performance bond;
optional Condition 67 enablesthe Employer to require the
contractor to provide a Parent Company Guarantee.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.1.3
LE 1.4

HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms
The following contract specific model formsare included in the
document;
abstract of contract particulars;
Invitation to Tender and Schedule of Drawings;
Tender and Tender Price Form;
Contract Agreement.
O ther formsand detailed guidance required by thisand other versions
of the GC/Works/1 ( 1998) are included in the Model FormsVolume
( GC/Works/1 ( 1998) - Contract for Building and Civil Engineering
Major Works- Model Formsand commentary: TSO
ISBN 0-11-702184 -9)
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.1.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.2 GS/WORKS/1 (1998) - LUMP SUM WITHOUT QUANTITIES
(TSO ISBN-0-11-702185-7)
Thisisthe traditional lump sum contract for large value refurbishment
and new worksprojectsbased on a lump sum without quantities.
Recommended Value
Value thresholdswill be a matter of policy for each Department.
By way of general guidance it isrecommended that where the chosen
strategy isthe traditional lump sum contract strategy, then it is
appropriate to use the without quantitiesversion of thiscontract
where the value of the workselement of major alterations,
refurbishment or new work exceeds250,000.
Major Features
The principal differencesbetween thisand the with quantitiesversion
are:
the without quantitiesversion issupported by a schedule of rates
provided by the contractor with the tender and which isused for
valuing variationsin accordance with Clause 41;
all reference to billsof quantitiesisremoved including Clause 3 in
the with quantitiesversion which dealswith errorsand omissions
etc. in billsof quantities.
O therwise the other conditionsof contract are essentially the same as
the with quantitiesversion.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.2.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms
These conditionsinclude the following model forms;
abstract of contract particulars;
Invitation to Tender and Schedule of Drawings;
Tender and Tender Price Form;
Contract Agreement.
O ther formsrequired by thisand the other versionsof the
GC/Works/1 ( 1998) are included in the Model Formsand commentary.
CRS 1.15.1

STANDARD GOVERNMENT CONTRACTS


CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.2.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.3 GC/WORKS/1 (1998) - SINGLE STAGE DESIGN AND
BUILD VERSION
(TSO - ISBN 0-11-702187-3)
Thisisa lump sum design and build contract which envisagesa single
stage tender procedure. Single stage meansthat a separate design stage
isnot anticipated.
Thisstandard form isbased on the with quantitiesversion of
GC/Works/1 ( 1998) . The main changesfrom the with quantitiesversion
are described in the Model formsand CommentaryVolume. Some of
the principal differencesare asfollows:
Condition 1 - New Definitions:
The AuthoritysRequirements- thisdocument ( which may include
drawings) replacesspecification and drawings. It isthisdocument
that must describe the requirementsand objectivesof the authority
in sufficient detail to enable the contractor to submit the tender. It
should also define the site boundary.
The ContractorsProposals- thisisthe response to the authoritys
requirementswhich must include drawingsand specification and
describe how the contractor proposesto satisfy the authoritys
requirements.
The Design - thisisdefined asbeing the sum total of the accepted
contractorsproposalsand subsequent design documents.
Design Document - any document prepared by the contractor asa
result of the design processand subject to a procedural process
detailed within Condition 10a.
Pricing Document - thisdocument givesdetailsof the build up of
the contractorslump sum offer.
Note that the pricing document replacesthe billsof quantitiesand is
the basisfor valuing variationsin accordance with Clause 42.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.3.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Condition 2 - Contract Documents
Thiscondition dealswith mismatch within and between contract
documents. It ismade clear that should there be a discrepancy
between the authoritysrequirementsand the contractors
proposals, it isthe Employersrequirementswhich will prevail.
Discrepanciesin or between the Employersrequirementsand any
statutory requirement, building regulation or planning permission are
resolved by the Project Manager.
Condition 3 - Pricing Document
Under thiscondition, any errorsfound in the billsof quantitiesafter
the contract hasbeen awarded cannot be amended.
Condition 8A - Insurance for Design Indemnity
A contractorsnormal insurance cover doesnot extend to design
liability. Thisform therefore includesa condition requiring the
contractor to hold professional indemnity insurance in respect of its
design.
Condition 10 - Design of the Works
Thiscondition imposesa duty upon the contractor to use all
reasonable skill and care when carrying out design work.
Condition 10a - Design Documents
Thiscondition dealswith the procedure for issuing design
documentsby the contractor to the project manager. It isimportant
that contractorsare aware that they cannot start any work for
which a design document hasbeen prepared until the
manager hashad an opportunity to be satisfied that the authoritys
requirementswill be met, to raise queriesand receive satisfactory
explanations. The liability in respect of any design document remains
firmly with the contractor. The contractor must submit two copiesof
each design document to the project manager and a basic quality
control procedure for queriesand changesisbuilt-in to the
condition.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.3.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Condition 33 - Programme
The authoritysrequirementsshould specify that the contractor
must submit a programme with the tender. Aswell asforming part
of the tender evaluation the programme isrequired in order to
review ( or negotiate) the actionswhich involve the authority/
project manager ( e.g. sequence of delivery and periodsfor
examination of design documents) prior to tender acceptance.
There istherefore no provision in thiscontract for the contractor to
submit the programme within 21 daysafter acceptance of itstender.
The programme must incorporate the design activity and identify
when possession of the site isrequired. Periodsof time for the
project manager to examine design documentsmust also be shown.
Condition 36 - Extensions of Time
The entitlement for an extension for any delay caused by the
execution of modified or additional work, hasbeen replaced by an
entitlement only where there isa change in the authoritys
requirements.
Condition 40 - Project Managers Instructions
The project manager may issue variationsin the form of a change in
the authoritysrequirements.
Condition 63 - Nomination
Thiscondition hasbeen omitted from thisversion of the
GC/Works/1 ( 1998) contract.
Condition 63A - Insolvency of Nominated Sub-contractors or
Suppliers
Thiscondition from the with quantitiesversion of GC/Works/1
( 1998) hasbeen omitted asa natural consequence of the omission
of Condition 63 - Nomination.
Condition 64 - Provisional Sums
Thiscondition omitted from the Edition 3 Design and Build version
of the contract hasbeen reinstated into the 1998 edition asa
meansof incorporating sumsinto the contract for the work of
statutory undertakersundertaking their statutory duties.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.3.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
Amendments to the Conditions of Contract
Any amendmentsor additionsto the standard form of contract to
suit particular circumstancesmust, to comply with Condition 2( 1) ,
be incorporated by the use of supplementary conditions. They are
incorporated into the conditionsby listing in the abstract of
particulars. Copiesshould be included with the tender documents.
Stage Payment Chart - General Note
A stage payment chart will need to be compiled to suit each
particular project and included with the invitation to tender. Ready
prepared chartsmay be commercially available but it may be
appropriate to require the contractor to prepare and present a
stage payment chart aspart of itstender submission. Thisshould be
supported by a resourced draft programme together with
calculations.
Model Forms
These conditionsinclude the following model forms;
abstract of contract particulars;
Invitation to Tender and Schedule of Drawings;
Tender and Tender Price Form.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.3.4
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.4 GC/WORKS/1 (1999) TWO STAGE DESIGN AND BUILD
VERSION
(TSO - ISBN 011 702326 4)
The GC/Works/1 Design and Build ( 1998) contract isa lump sum form
described in CRS 1.15.3 and isintended to support a single stage
tendering procedure, without a separate design stage. It issufficiently
flexible to allow for varying amountsof design input from the
Contractor. The Employer providesEmployersRequirements, to which
the Contractor respondswith ContractorsProposals, and the
Contractor developsthe detailed design on the basisoutlined in those
documents.
ThisTwo Stage Design and Build form supportsa separate design
stage. It isalso a lump sum form of contract but the lump sum is
arrived at in two stages, asexplained below.
Naturally, the two documentsare very similar. The new featuresof
GC/Works/1 Two Stage Design and Build ( 1999) are asfollows:
at the time the Contract isentered, the Contract Sum isnot
ascertained, owing to the lack at that time of design and other
information upon which to base the Contract Sum. However, a
separate Design Fee isascertained at that time and the Contractor
will have submitted a Pricing Document asan aid to the subsequent
ascertainment of the Contract Sum
a Design ProcessEvent isidentified. Thisconsistsof two distinct
elements:
- determination of the Contract Sum during the design stage
either by agreement of the partiesor, in the absence of
agreement, by the Q S ( subject to later adjudication and
arbitration at the instance of the Contractor)
- achievement of a certain design progressmilestone. Thismay
be completion of the Design, or some earlier design stage,
which must be identified in the entry in the Abstract of
Particularsrelating to the new Condition 10B ( Design
processand Contract Sum)
the Contractor proceedswith site and/or soil investigationsand the
Design, but generally with no other work until given notice of
possession of the Site
CRS 1.15.4.1
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
the Contractor ispaid the Design Fee monthly, without retention
under Condition 10B( 10) ( Design processand Contract Sum) , the
PM certifieswhen the Design ProcessEvent hasbeen achieved
the Employer electsat hisabsolute discretion whether or not to
proceed with the Contract and give the Contractor notice of
possession of the Site. If he doesnot do so within a limited time, the
Contract isdeemed determined, and the Contractor isentitled to
be paid for work done to that time
if the Employer electsto let the Contract determine, but later
decidesto proceed with the Works, he may use the initial
Contractorsdesign, whether or not he further employsthat
Contractor in connection with the Works
if the Employer electsto give notice of possession of the Site, the
time for the Contractor to provide the performance bond, retention
payment bond and mobilisation payment bond ( if any) runsfrom
the giving of that notice.
CRS 1.15.4.2
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.5 GC/WORKS/1 WITH QUANTITIES CONSTRUCTION
MANAGEMENT TRADE CONTRACT (1999)
(TSO ISBN 011 702327 2)
GC/WORKS/1 WITHOUT QUANTITIES CONSTRUCTION
MANAGEMENT TRADE CONTRACT (1999)
(TSO ISBN 011 702401 5)
These two formsadapt the respective GC/Works/1 With and
Without Q uantitiesformsfor use in construction management, a
contractual structure under which:
there isno single main contractor
the Employer entersinto a number of direct contracts( usually
called Trade Contracts) with several separate contractors( usually
called Trade Contractors) for separate workspackagestogether
comprising a larger
the Employer instructsa construction manager to run the .
These Construction Management Contractsdiffer from the
GC/Works/1 ( 1998) With and Without Q uantitiescontractsin the
following areas:
Condition 1 (Definitions)
The definition of Principal Contractor hasbeen amended to reflect
that the Contractor may not be the Principal Contractor for the
Purposesof the Construction ( Design and Management)
Regulations1994 and their Northern Ireland equivalent;
A new definition hasbeen added - the Project. Thisrelatesto the
project which are described in the Abstract of Particularsof which
the Worksunder the particular Trade Contract form a part.
Condition 8 (Insurance)
Thiscondition haseffectively been edited to adopt the provisionsof
Alternative C under Condition 8 ( Insurance) of GC/Works/1 With
Q uantities( 1998) . Under that alternative, the Employer assumes
responsibility for construction all risks and public liability insurance;
and, while the Crown isthe Employer, the Employer doesnot have
to insure, but may assume the relevant risks- the Crown asa
matter of policy, generally doesnot effect insurance.
CRS 1.15.5.1
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
Condition 13 (Protection of Works)
ThisCondition hasbeen amended to reflect that the Contractor
under Construction Management can only be responsible for his
own Work and Things( asdefined under the Contract) . If the
Contractor isto have wider responsibilitiesin respect of the whole
Site, these must be specified by the contract.
Condition 21 (Defects in Maintenance Periods)
Whilst thisCondition isunamended variouschangeshave been
introduced into the Abstract of Particularsrelating to it which
enable the Employer to set specific maintenance periodsin relation
to the Works.
Condition 22 (Occupiers and Employers rules and regulations)
The title of thisCondition hasbeen amended to refer to the
Employers, aswell asthe occupiersrulesand regulation, and the
Condition assumesvery great importance under CM. It isnot an
optional Condition asunder the GC/Works/1 With and Without
Q uantities( 1998) contracts.
Condition 26 (Site admittance)
ThisCondition hasbeen amended to reflect that each Contractor
under Construction Management cannot be responsible for the
admittance of personsto the Site. Therefore, the Contractor is
required to take the stepsspecified by the Contract, or Instructed
by the PM to prevent unauthorized personsbeing admitted to the
Site.
Condition 34 (Commencement and completion)
ThisCondition hasbeen amended to reflect that under
Construction Management the Contractor isonly given accessto
the Site rather than possession. The Condition also placesa
responsibility on the Contractor to keep hisarea of the worksclear
of debrisand rubbish.
Condition 46 (Prolongation and disruption)
ThisCondition hasbeen amended in recognition that under
Construction Management there isa greater risk of the activitiesof
other Worksadversely affecting the Contractor'swork.
CRS 1.15.5.2
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
Condition 55 (Damages for delay)
ThisCondition hasbeen amended to enable the Employer to claim
either liquidated damagesor damagesat large in respect of the
Contractor'sfailure to complete the Workson time.
Condition 65 (Other works)
ThisCondition assumesgreat importance under Construction
Management asall the other Trade Contractorswill be working in
accordance with it.
CRS 1.15.5.3
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.6 GC/WORKS/2 (1998) - BUILDING AND CIVIL ENGINEERING
MINOR WORKS
(TSO - ISBN 0-11-702152-0)
GC/Works/2 ( 1998) isa new edition of the standard Government
form of contract for minor UK building, civil engineering and demolition
works, replacing General Conditions of Government contracts for Building
and Civil Engineering Minor Works:FormGC/Works/2 (incorporating
amendments 1 to 5) Edition 2 1990 and General Conditions of Contract
for demolition Works:FormC1010 (September 1990)
GC/Works/2 ( 1998) isfor use where lump sum tendersare to be
invited on the basisof the specification and drawingsonly, with an
Employersoption to require the contractor to provide a schedule of
ratesin order to value variationsordered.
Recommended Value
Value thresholdswill be a matter of policy for each Department.
By way of general guidance it issuggested that thistype of contract is
suitable for building and civil engineering workswith a value between
25,000 and 200,000 and demolition contractsof any value.
Major Features
the contract isadministered by the person designated asthe Project
Manager ( PM) by the Employer;
in accordance with Condition 1A, the partiesto the contract are
required to deal fairly, in good faith and in mutual cooperation with
each other;
in accordance with Condition 30, the contractor isentitled to apply
for monthly payments, provided the application issupported by a
valuation which isto be agreed by the PM; the contractor ispaid 97
percent of the value of the work executed on site to the satisfaction
of the PM and of things( materials) brought to site for incorporation
into the works;
the 3 per cent reserve isheld assecurity in respect of any defects
which may arise in the maintenance period ( see Condition 19) ;
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.6.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
the PM may issue instructionsto vary or further explain the works
in accordance with Condition 25. All instructionsare to be
confirmed in writing;
variationsare valued in accordance with Condition 26 and on the
basisof either fair ratesto be agreed between the Department and
the contractor or on the basisof the contractorsschedule of rates
if one wasrequested;
Condition 6 incorporatesinto the contract the obligationsimposed
by the Construction ( Design and Management) Regulations1994;
Condition 23 providesfor extensionsof time to the contractor for
any matterswhich are wholly beyond the control of the contractor;
for example unforeseen ground conditions( only if certified assuch
by the PM under Condition 4) ;
Condition 28 allowsthe contractor to receive additional fundsfor
delay provided he can satisfy the requirementsimposed by 28( 1)
and ( 3) ;
under Condition 29 the contractor hasa right to interest payments
at the rate specified in the Abstract of Particularsdue to the
circumstanceslisted in Condition 29( 1) ;
Condition 37 introducesthe employersright to claim liquidated
damagesin the event of lossbeing incurred due to delay by the
contractor;
optional Condition 47 enablesthe Employer to require the
contractor to maintain a performance bond;
optional Condition 48 enablesthe Employer to require the
contractor to provide a Parent Company Guarantee.
Model Forms and Commentary
A separate volume isavailable, entitled GC/Works/2 ( 1998) Contract
for Building and Civil Engineering Minor Works- Model Formsand
Commentary ( TSO ISBN 0-11-702153-9) ) , which includesmodel
formssuch as:
Invitation to Tender and Schedule of Drawings;
AdjudicatorsAppointment;
Certificate of Completion; and
detailed guidance on each of the conditions.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.1

CRS 1.15.6.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.7 GC/WORKS/3 (1998) CONTRACT FOR MECHANICAL AND
ELECTRICAL ENGINEERING WORKS
(TSO - ISBN 0-11-702153-9)
GC/Works/3 ( 1998) isa new standard form of contract for UK
mechanical and electrical engineering worksreplacing General
Conditions of Contract for Minor Mechanical & Electrical Services and Plant:
FormC1020 (September 1990) and General Conditions of Contract for
Mechanical & Electrical Services and Plant:FormC1030 (September
1990). Because C1020 wasalmost aslong and complex asC1030, it
wasconsidered unnecessary to continue publication of separate forms
of contract respectively for minor and major mechanical and electrical
engineering work.
GC/Works/3 General Conditionsare based upon GC/Works/1 With
Q uantities( 1998) . GC/Works/3 isfor use on lump sum contractsfor
UK mechanical and electrical engineering worksof any value based
upon a Specification and Drawings, with the optional use of Billsof
Q uantitiesor a Schedule of Rates. O ptionsare also given for liquidated
damagesat large in respect of delay in completion of the works.
Recommended Value
Value thresholdswill be a matter of policy for each Department.
By way of general guidance, it issuggested that thistype of contract is
suitable for workscontractsof any value.
GC/Works/3 ( 1998) differsfrom GC/Works/1 With Q uantities( 1998)
in the following areas:
Condition 1 Definitions
Billsof Q uantities definition expanded to reflect their optional use;
in the definition of Contract the words( if used) after Specification
have been deleted asthe specification isan essential item for
mechanical and electrical engineering works;
definition of Programme expanded to reflect that itsuse isoptional
in GC/Works/3;
definition of Schedule of rates added;
definition of testson and after completion have been added.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.7.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Condition 9 Setting Out and as built drawings
New paragraph ( 3) hasbeen added to thiscondition which requires
the contractor to supply asbuilt drawingsto the Employer within
14 daysof a section of, or all of the worksbeing signed off as
complete. Failure to comply with thiscondition allowsthe Employer
to withhold further payments.
Condition 10 Design
Paragraph ( 1) refersto the design of the whole or any part of the
Works.
Condition 33 Programme
Thiscondition isoptional.
Condition 39 Tests on Completion and certifying work
Paragraphs1-5 are new and deal with the Making of Testson
completion and the issue by the Project Manager of certificatesof
satisfactory completion in respect of all or any part of the works.
Repeated failure of Testson Completion isa ground for
determination of the contract by the Employer under Condition 56.
Condition 39A Tests after Completion
Thisnew optional condition setsout the proceduresfor testing the
worksafter completion, with liquidated damagesfor shortfall in
performance.
Condition 55 Damages for Delay
Thiscondition providesalternativesrespectively for liquidated
damagesand damagesat large.
Condition 56 Determination by Employer
Paragraph ( 6) ( i) isnew to reflect Condition 39 and enablesthe
Employer to determine the contract due to repeated test failureson
completion.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.7.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms and Commentary
A separate volume entitled GC/Works/3 ( 1997) Contract for
Mechanical and Electrical Engineering Works: Model Formsand
Commentary ( TSO ISBN 0-11-702153-9) isalso available. This
includesall of the model formsrequired to successfully utilise the
GC/Works/3 contract and includes:
Tender and Tender Price Form;
Contract Agreement;
Retention Payment Bond; together with detailed guidance on each
of the conditions.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.7.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.8 GC/WORKS/4 (1998) CONTRACT FOR BUILDING, CIVIL
ENGINEERING, MECHANICAL AND ELECTRICAL SMALL
WORKS
(TSO - ISBN 0-11-702154-7)
GC/Works/4 ( 1998) isa new edition of the Standard Government
form of contract for small UK building, civil engineering, mechanical and
electrical worksand replacesGeneral Conditions of Government Contract
for Building, Civil Engineering, Mechanical & Electrical Small Works:Form
C1001 (September 1990).
Recommended Value
Value thresholdswill be a matter of policy for each Department.
By way of general guidance it isrecommended that thistype of
contract issuitable for contractswith a maximum value of 75,000.
Although GC/Works/4 ( 1998) isintended for use on low value
projects, Departmentsmay occasionally need to consider using
GC/Works/2 ( 1998) asthisincorporatesa number of conditionswhich
do not feature in GC/Works/4 ( 1998) . For example, under
GC/Works/4 neither the contractor or the Employer isrequired to
maintain insurance. The contractor isalso unable to claim additional
fundsor time due to delay caused by unforeseen ground conditions.
Major Features
The major featuresare asfollows:
the contract isadministered by the person designated asthe Project
Manager ( PM) ;
variation instructionsmay be issued by the PM in accordance with
Condition 17( 2) ;
in accordance with Condition 1A, the partiesto the contract are
required to deal fairly, in good faith and in mutual cooperation with
each other. Variationsare valued in accordance with Condition 18;
Condition 20 givesthe Employer the option of paying advanceson
account based on progress;
under Condition 28, both partieshave the right to refer disputesto
an adjudicator. In all cases, the adjudicatorsdecision isfinal and
cannot be subjected to arbitration post completion.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.8.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms and Commentary
A separate model formsand commentary volume isalso available for
GC/Works/4 1998 entitled Contract for Building, Civil Engineering,
Mechanical and Electrical Small Works: Model Formsand Commentary
( TSO ISBN 0-11-702154-7) ) .
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.8.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.9 GC/WORKS/6 (1999) - DAYWORK TERM CONTRACT
(REPLACES C1401 PUBLISHED 1990, REVISED 1993)
Thisisthe standard form of daywork term contract. The competition is
in the percentage on-cost quoted by the tenderers. Payment isbased
on hourly ratesfor labour which include the contractor'soverheads
etc. Materialsare paid for at cost plusa percentage addition.
It isintended that thisform be used for work of a jobbing nature.
Major Features
the contract isadministered by a Project Manager ( PM) ;
in accordance with Condition 7, the contractor isrequired to carry
out work described in the tender asordered by the PM;
in accordance with Condition 7, the contract may be determined by
either party following three monthsnotice;
payment for labour ismade in accordance with Condition 23, which
specifieswhat isdeemed to be included in the contractorshourly
rates; in accordance with Condition 17 the contractor must keep all
relevant time sheets;
Condition 24 statesthat the contractor isentitled to payment of
the prime cost of materials;
payment for plant isin accordance with Condition 24.
Model Forms
These conditionsinclude the following model forms:
invitation to tender ( specifying worksand paymentsetc.) ;
form of tender.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.9.1
CRS 1.14

HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.10 GC/WORKS/7 (1999) - MEASURED TERM CONTRACT
(REPLACES C1501, PUBLISHED 1990, REVISED 1993)
Thisisthe standard form of measured term contract, based on a
schedule of ratesprovided by the Department. The contractors
tendered price isa percentage addition or deduction from the ratesin
the schedule for ordersin three price ranges:
0 - 5,000;
5,000, and 50,000;
greater than 50,000.
The contract can be applied to multiple sites.
Major Features
the contract isadministered by a Project Manager ( PM) ;
the contract includesdutiesto be carried out by a quantity surveyor
who isappointed by the Employer;
each order issued in accordance with Condition 8 iseffectively a
separate contract for a specified task and statesthe date of
commencement and completion;
in accordance with Condition 7, the whole contract may be
terminated by either party provided three monthsprior notice has
been given;
under Condition 29, stage or interim paymentscan be made if the
total estimated value of an order exceedsthe sum stated in the
abstract of particularsor the duration of the worksexceeds45
calendar days;
there isno provision for a reserve assecurity in respect of defects;
ordersare valued in accordance with Condition 27, on the basisof
the net ratesin the schedule of rates, adjusted by the relevant
Updating Percentage and then adjusted by the contractors
tendered percentage adjustment;
Condition 26 setsout the procedure for measurement of the work
on site and submission by the contractor of itsaccount for work
carried out in connection with an order.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.14

LE 2.7

CRS 1.15.10.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms
These conditionsinclude the following model forms:
form of invitation;
form of tender;
abstract of particulars.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.10.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.11 GC/WORKS/8 (1999) - SPECIALIST TERM CONTRACT FOR
MAINTENANCE OF EQUIPMENT
(REPLACES C1301, PUBLISHED 1990)
Thisform of contract isa specialist term contract for use where
specified maintenance of equipment isrequired and can be costed per
task. O ne of the principal differencesbetween thisform and form
GC/Works/9 ( 1999) isthat under thisform a schedule of work is
priced by the contractor and interim paymentsare based on the
measured work actually carried out. The price isnot based on single
annual cost.
Main Features
the contract coversthe periodic servicing and inspection of
equipment ( including specialist plant) , repair of equipment due to
faultsdiscovered during inspection, and repairsordered by the
Project Manager ( PM) ;
the contract isadministered by the PM;
Condition 23 providesfor the valuation of work at the ratesand
pricesin the schedules;
Condition 24 providesfor the separate payment of travelling time;
the form of tender allowsfor price limitsto be set by the
Department for each repair in respect of routine minor repairsand
any repairsseparately ordered;
the pricesin the schedule will be subject to VO P adjustment in
accordance with the formula in Condition 25 and using the indices
in the DETR publication Price Adjustment Formula for Building
Contracts( Series2) ;
in accordance with Condition 27, separate monthly accountsare
submitted by the contractor for period servicing/inspection and for
minor repairs; accountsfor repairsseparately ordered are to be
submitted within 14 daysafter completion of each order;
Condition 22 providesfor emergency call-outs.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.11.1
CRS 1.14

LE 2.7

HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms
These conditionsinclude the following model forms:
invitation letter;
form of tender;
Schedule A: itemsof periodic servicing and inspection.
CRS 1.15.11.2
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.12 GC/WORKS/9 (1999) - OPERATION, REPAIR AND
MAINTENANCE CONTRACT FOR MECHANICAL AND
ELECTRICAL PLANT, EQUIPMENT AND INSTALLATIONS, ETC.
(REPLACES C910, PUBLISHED 1990)
Thisform of contract isa lump sum maintenance term contract for the
operation, maintenance and repair of fixed M&E plant, equipment and
installations, for a single establishment or complex of buildingsclose
enough to be conveniently covered by a single contract. The term of
the contract isfor a period of one to five yearsand the price includes
one-off repairsup to a specified maximum cost per repair. The price is
based on a performance based specification which setsout operational
requirementsand plant operating criteria.
Major Features
the contract isadministered by the Project Manager ( PM) ;
the contractor must appoint an agent in accordance with Condition
5 who will supervise the work and to whom directionsmay be
given by the PM;
the contract sum isa lump sum for the service to be provided in
the first year, to be paid in 12 equal monthly paymentscommencing
one month after the commencement date, in accordance with
Condition 26;
on the anniversary of the commencement date in each subsequent
year of the term, the annual lump sum isadjusted for inflation using
the VO P formula set out in Condition 25 and using the indices
published in the DETR publication Price Adjustment Formula for
Building Contracts( Series2) ;
in accordance with Condition 1, the contractor will not be entitled
to any additional payment for any repairswhich do not exceed the
cost threshold set for individual repairs.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
LE 2.7

CRS 1.15.12.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Model Forms
These conditionsinclude the following model forms:
invitation letter;
form of tender;
list of sitesand summary of tender;
abstract of contract particulars;
schedule of information to be supplied by the tenderer.
CRS 1.15.12.2
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.13 C1303 - WINDOW CLEANING
C1304 - CHIMNEY SWEEPING
(TSO - ISBN 0-11-671539-1)
These specialist term contractsare very similar and are both for use
where work isrequired at specified intervals. The contractor pricesa
schedule of work which setsout what hasto be cleaned and how
regularly.
Main Features
there isno Superintending O fficer; the Department takes
responsibility for contract management;
pricesremain fixed for the first year and are then negotiated at
twelve month intervalsthereafter;
the period of the contract may be from one to three years;
the contract may be determined by either party provided three
monthsnotice isgiven and the contract isnot determined before
the expiry of the first year;
the work shall be carried out at the timesstated in the schedule or
at such timesasthe Department may direct.
Model Forms
These conditionsinclude the following model forms:
invitation letter;
form of tender;
schedule of work.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.13
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 1.15.14 C1306 - MAINTENANCE OF GARDENS, GROUNDS, ETC.
C1312 - SUPPLY AND APPLICATION OF HERBICIDES, ETC.
(TSO - ISBN-0-11-671539-1)
These specialist term contractsare very similar to C1303 and C1304,
but they differ in the way in which pricesare updated. Both of these
contractsare for use where work isrequired at specified intervals. The
contractor pricesa schedule of work which specifieswhat hasto be
done at what locations, and how frequently.
Main Features
there isno Superintending O fficer; the Department takes
responsibility for contract management;
pricesremain fixed for the first year, and are adjusted at 12 monthly
intervalsthereafter;
- in the case of C1306, the price isadjusted in accordance with
a formula given at Condition 5,
- in the case of C1312, the price isadjusted in accordance with
the formula given at Condition 8 and the updating
percentagesspecified at Condition 5;
the contract period may be from one to three years;
the contract may be determined by either party provided three
monthsnotice isgiven and the contract isnot determined before
the expiry of the first year;
the work shall be carried out at the timesstated in the schedule or
at such timesasthe Department may direct.
Model Forms
These conditionsinclude the following model forms:
form of tender;
schedule of work.
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.14
LE 2.7

HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD GOVERNMENT CONTRACTS
CONTRACTORS
CONTRACTING STRATEGIES
CRS 1.15.7

CRS 1.15.12

CRS 1.15.15
CRS 1.15.15 C/804 - REPAIR OF PLANT
Thisisa standard form of contract for repair of plant. It isa non-
competitive two stage contract. The contractor stripsthe plant and
reportson the degree of repairsrequired. If the contractorsquotation
for repair isconsidered fair and reasonable the contractor can be
instructed to proceed. If it isnot considered reasonable the contractor
ismerely paid for the work carried out i.e. the stripping and report.
The repair work can then be carried out by alternative meanse.g.
GC/Works/4 ( 1998) , using the report asa basisfor the specification.
Alternatively it may be considered uneconomic to repair the plant and
it can be replaced by new.
Model Forms
These conditionsinclude the following model forms:
instructionsto proceed;
form for quotations, report, and detailsof replacement partsand
tests.
HOME
GACC
EDITION 2: FEB 1998
CRS 2.0 CONTRACTS FILE
CRS 2.1 IDENTIFICATION (THIS SECTION DUPLICATES CST 2.1)
Each Department islikely to have an existing system for numbering
identifying and opening new contract files. Thissection istherefore
provided by way of guidance and describespointsof general
importance and application. When the need for a contract hasbeen
identified, consideration should be given to the following important
points:
each contract should have a reference code assigned to it; it should
identify the Department aswell asa unique reference number for
the contract;
it isgenerally common practice to open a registered file which is
assigned the contract reference number, and which containsall of
the papersrelating to the contract;
it isgood practice to use the unique reference number in all
correspondence relating to the contract, and to insist that all parties
to the contract also use the reference number in their
correspondence;
it islikely that the contract file will comprise a number of filesand
sub filesand all such filesshould also be assigned the unique
reference number;
an important aspect of the contract file isthat it providesa record
of procurement practice adopted; the file or filesare then available
to demonstrate that stepshave been taken to procure servicesin a
way which aimsto achieve best value for money.
The documentsin the contract file are likely to include:
recordsof meetingsat which mattersaffecting the setting up of the
contract were discussed;
minutesrequesting and giving financial and contractual approval to
further action;
recordsof the pre-selection processfor choosing the companies
( copiesof the corporate brochure or general information about a
company need not be retained on the contract file) ;
IDENTIFICATION
CONTRACTORS
CONTRACTS FILE
CRS 2.1.1
HOME
GACC
EDITION 2: FEB 1998
recordsof formal interviewsand recommendationstherefrom;
recordsof EC advertisement and replies, if applicable;
the businesscase including:
- -- -- a record of the pre-tender estimate;
- a schedule of potential project risks;
- -- -- a record of the consideration of PFI alternatives, where
appropriate;
a record of the proposed tender evaluation criteria;
a set of the tender documentsasissued to tenderers( other than
standard printed documents) ;
copiesof correspondence during the tender period;
admissible tendersreceived, placed in a folder;
the tender summary sheet;
any correspondence pertaining to consideration of the tenders;
the evaluation report and recommendation to accept a tender;
the appropriate delegated approval to accept a tender;
a copy of the acceptance letter together with the acknowledgement
of acceptance by the successful tenderer;
a copy of the decline letter sent to unsuccessful tenderers;
copiesof any requestsfor debriefing by unsuccessful tenderers
together with the Departmentsresponse.
Key Points
Recordsare required to demonstrate that best value for money has
been sought.
Recordsmay also be essential to demonstrate that tenderershave
not been unfairly excluded in the event that EC Procurement
procedureshave to be followed, and a challenge israised by an
unsuccessful tenderer.
IDENTIFICATION
CONTRACTORS
CONTRACTS FILE
CRS 2.1.2
HOME
GACC
EDITION 2: FEB 1998
CRS 2.2 SUB FILES (THIS SECTION DUPLICATES CST 2.2)
Each stage of the contract processcan produce bulky documents
( companies presentation documents, tender documents, companies
bids, and evaluation reportsetc.) . It istherefore recommended that,
where such documentsmay be easily separated from the main file, sub
filesare created to hold these documents.
Each sub file should carry the unique contract reference number, and it
iscommon to give each sub file an alphabetical suffix. Where sub files
are created, it isrecommended that an index of sub filesisheld at the
front of the main file.
SUB-FILES
CONTRACTORS
CONTRACTS FILE
CRS 2.2
HOME
GACC
EDITION 2: FEB 1998
CRS 2.3 RETENTION PERIODS (THIS SECTION DUPLICATES CST 2.3)
There are four principle reasonsfor retaining contract files:
1. To provide recordsfor use asan aide memoire for future projects.
2. To provide a record for auditing purposes, especially in respect of
contractsprocured in accordance with EC public procurement rules.
3. To comply with legal obligationsto do so. In accordance with the
CDM Regulationsthe Department isunder an obligation to keep
available for inspection a health and safetyfile for what amountsto
the entire life of the building.
4. To provide evidence of the agreement and of the conduct of the
contract in the event of legal action, which either the Department
feelsappropriate to take, or against which a Department isrequired
to mount a defence.
In the case of legal action the periodsfor which the Department may
have legal liability are limited by statute, and vary depending on the
circumstances.
The periodsof liability are determined by reference to the Latent
DamagesAct 1986. The minimum period issix yearsfrom the date of
the breach. If the contract isby deed, however, the period is12 years.
The position ismore complex in respect of liability for negligence.
Dutiesof care may be owed by the project manager, the designersand
the contractor for periodsof up to 15 years, and in some casesbeyond.
Thisshould therefore be taken into account when assessing the
retention period for all documentsrelating to major worksprojects.
It isrecommended that documentsrelating to unsuccessful tenders
should be retained until completion of the contract.
RETENTION PERIODS
CONTRACTORS
CONTRACTS FILE
LE 2.1

LE 1.9

CRS 2.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 2.3( SCO T) RETENTION PERIODS
There are four principle reasonsfor retaining commission files:
1. To provide recordsfor use asan aide-memoire for future .
2. To provide a record for auditing purposes, especially in respect of
commissionsprocured in accordance with EC public procurement
rules.
3. To comply with legal obligationsto do so. In accordance with the
CDM Regulationsthe Department isunder an obligation to keep
available for inspection a health and safety file for what amountsto
the entire life of the building.
4. To provide evidence of the agreement and of the conduct of the
commission in the event of legal action, which either the
Department feelsappropriate to take, or against which the
Department isrequired to mount a defence.
In the case of legal action the periodsfor which the Department may
have legal liability are limited by statute, and vary depending on the
circumstances.
Remember that the vast majority of all contractual obligationswill
expire under the short negative prescription, ie after five yearsfrom
the date when the obligation becomesenforceable, if the necessary
conditionsare satisfied. Before an obligation prescribes, however, the
relevant period of time must have passed without any relevant claim
( see LE 1.9) by the creditor, or anyrelevant acknowledgement ( again,
see LE 1.9) by the debtor.
RETENTION PERIODS
CONTRACTORS
CONTRACTS FILE
LE 2.1

LE 1.9

CRS 2.3(S)
LE 1.9

HOME
GACC
EDITION 2 REV 1: JAN 2000
CRS 3.0 CONTRACTOR SELECTION
CRS 3.1 SELECTION OF FIRMS
The principle aim of the procurement processisto select a contractor
which offersthe best value for money. Thiswill nearly alwaysinvolve a
processof competitive tendering. Value for money meansthe most
economically advantageousto the contracting authority and not
lowest cost alone ( see PPD Guidance Note No. 3) .
Much of the work let in accordance with thischapter islikely to be of a
specialist service or maintenance type contract for a term of say 3
years. It isrecommended that the frequent use of the same contractor
or the same list of contractorsisavoided.
It may be that in exceptional circumstancesthe timescale or the type of
work necessitate the appointment of a contractor on the basisof a
single tender action. Thismeansthat the competitive processisnot
followed and generally that the contract and in particular price are
negotiated with one contractor. Where such a procedure isunavoidable
it will normally be necessary to obtain the appropriate delegated
authority before proceeding.
It will be appreciated that the precise stepsinvolved in procuring a
contractor or a number of contractorsdepend very much on the
selected contract strategy and whether or not the public procurement
rulesapply. The stepswhich are followed in thischapter assume a single
stage selective tendering process.
For the selection of contractors, the weight attached to quality islikely
to be lessthan it isfor consultants. The extent of quality evaluation will
vary from one contract strategy to another. It issuggested that with the
traditional strategy, pre-selection and short listing are when the
principal quality evaluation will be done. For certain strategies, in
particular construction management and to some extent management
contracting, it isrecommended that quality isfurther evaluated by
holding pre-tender interviews.
It should also be borne in mind that under the Construction Industry
Tax Scheme all firmsmust be in possession of a valid registration card
or tax certificate and produce it for inspection whenever requested to
do so.
SELECTION OF FIRMS
CONTRACTORS
CONTRACTOR SELECTION
CST 3.9

CRS 3.1.1
LE 2.11

HOME
GACC
EDITION 2 REV 2: JAN 2000
SELECTION OF FIRMS
CONTRACTORS
CONTRACTOR SELECTION
The adopted procedure should be transparent and auditable and
should operate fairly between each tenderer.
The following stepsare therefore recommended in order to obtain a
short-list of suitable contractorsfor tender:
Where the EC procurement rulesapply then the pre-selection process,
using the restricted procedure, will be asfollows:
Keep a list of
contractorswho
serve you well or
have served you well
in the past
Gather market
intelligence about
contractorsincluding
referencesregarding
past performance
Consult
New Q ualification
System ( NQ S) for
development of the
longlist
Identify long list
Confirm contractorsinterest
Identify pre-selection criteria
Where unfamiliar with contractorsarrange pre-selection interviewsto
assessbasic abilities
Evaluate pre-selection data and form short list
Inform contractorsof outcome
CRS 3.1.2
HOME
GACC
EDITION 2 REV 1: JAN 2000
SELECTION OF FIRMS
CONTRACTORS
CONTRACTOR SELECTION
O Jcontract notice and UK advertisementsspecifying the basison
which the pre-selection will be carried out
Initial paper sift
Appraisal of expressionsof interest
O ffice Visits( optional)
Financial checks
Pre-qualification interview ( optional)
Pre-qualification scoring
A paper sift will also be required if a large number of tendersare
sought in order to establish a panel of contractors.
The next stage of the selection processisthe invitation of tendersand
choice of contractor. The following stepsare recommended in order to
select a contractor from the short list:
CRS 3.1.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
SELECTION OF FIRMS
CONTRACTORS
CONTRACTOR SELECTION
Invite contractorsto submit prices
Hold mid-tender interviewsif appropriate
Check contractors tendersfor conformity and evaluate price
Advise all contractors
Debrief if requested
The stepsinvolved in obtaining a short list and in selecting the
successful contractor set out above need not be rigidly adhered to in
every case. Simple or small standard contractsmay not require pre-
tender interviewsfor example.
Key Point
The Construction Industry Tax Scheme requiresthat any firm must be
in possession of a valid registration card or tax certificate.
CRS 3.1.4
LE 2.11

HOME
GACC
EDITION 2 REV 1: JAN 2000
CRS 3.2 NEW QUALIFICATION SYSTEM (NQS - FORMERLY CMIS)
Constructionline isthe name of the service which utilisesthe NQ S
database. Where the EC procurement rulesdo not apply, then the long
list of contractorscan normally be obtained from the NQ S.
Itspurpose isto validate prior to tender, the financial standing,
managerial capability, technical competence and resource capacity of
bona fide firmswishing to undertake a wide variety of construction and
property related services. The NQ S isfree of charge to clientsand isa
powerful tool designed to minimise the risk of the user against
company failure, poor workmanship and fraud. The data helpsto ensure
that public bodiesonly deal with reputable firmsand financially sound
companiesand savestime and valuable resourcesin the vetting of firms
being considered for an invitation to tender.
The NQ S includesdetailsof a firmsstaffing, categoriesof work a
contractor can undertake, current and completed work recorded as
feedback by the users, and an assessment of the maximum individual
contract value a firm may accommodate ( the notation) .
Departmentscan accessthe NQ S on-line, under the auspicesof a BT
managed telecommunicationsservice. The IT Helpdesk and client
liaison responsibility are located in Edinburgh.
Anydepartment, agency or NDPB wishing to accessthe NQ S will
need to do so via an on-line computer link. Any requestsfor Access
Packsor additional information/advice can be obtained from the
contactslisted overleaf.
Key Point
More detailed information on the NQ S iscontained in CAU
Information Note 27/98. A copy can be obtained by phoning the CAU
Helpdesk on 020 7271 2833.
NEW QUALIFICATION SYSTEM
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.2.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Organisation Structure of Constructionline
Head O ffice for Constructionline and the processing responsibility for
firmsbased in England, Wales, Scotland and Northern Ireland:
Constructionline
Great West House
Great West Road
Brentford
Middlesex
TW8 9DF Tel: 020 8380 4600
Constructionline Director: ChrisLeggett
Development Director: Colin Garton
O perationsManager: Paula Beresford
* Client helpdesk and technical support iscurrently located at:
Constructionline
The Basement
17 Atholl Crescent
Edinburgh
EH3 8HA Tel: 0131 229 9449
*Note:the processing responsibility for firms based in Scotland moved to
the Brentford office in October 1998 but the client helpdesk and technical
support responsibilities have been retained.
IT Helpdesk Tel: 0870 607 1602
Client ServicesManager Tel: 0870 607 1602
NEW QUALIFICATION SYSTEM
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.2.2
HOME
GACC
EDITION 2: FEB 1998
CRS 3.3 THE LONG LISTING PROCESS
The production of the long list isthe first step towardsestablishing a
viable tender list which will ensure genuine competition among capable
suppliers.
Where the EC public procurement rulesapply, the long list will
generally be established through inviting expressionsof interest by
advertising in the O fficial Journal of the European Community. It is
recommended that such expressionsof interest are checked with NQ S
in respect of their financial position. O therwise, the long list will be
compiled from the following possible sources:
NQ S;
market intelligence gathered by the Department;
list of contractorswho have serviced the Department well in the
past.
It isrecommended that the long list be limited to 10 in number. The
key criteria for selection of firmsfor the long list are:
experience in the general area of construction work;
track record on similar work;
experience with the size of workscontract envisaged.
It may be useful at thisstage to ask firmswho are not known to the
Department to provide brochuresand possibly referencesto confirm
experience and track record.
When the long list hasbeen fixed, a preliminary enquiry should be sent
to each firm on the list to ask them to confirm without obligation that
they are interested, that they have the resourcesand that they will
submit a tender if asked.
It isrecommended that repliesare requested in writing and by a given
date.
Key Points
An example preliminary enquiry isgiven in the form of CRS3/SF1
overleaf.
THE LONG LISTING PROCESS
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.3.1
HOME
GACC
EDITION 2: FEB 1998
THE LONG LISTING PROCESS
CONTRACTORS
CONTRACTOR SELECTION
STANDARD FORM 1 - LETTER
Preliminary Enquiry Letter
Dear Sir
PRELIMINARY ENQUIRY RE [TITLE OF PROJECT]
The [Secretary of State] acting through [ Department] intendsto tender the construction
of the worksdescribed below. Particularsof the worksare
[enclosed/asfollows:]
Include detailssuch as:
project;
nature of work;
location;
estimated value;
contract period;
contract strategy;
proposed number of tenderers.
The following isthe proposed procurement programme in connection with this
commission:
Date of invitation to tender: ..................................................
Date of contract award: .............................................................
Commencement of works: .....................................................
Duration of works: .......................................................................
You are invited to confirm in writing your interest in being included in the tender list by
....................... [Date]. Please also advise usof any special reasonswhich you consider to
support the inclusion of your company on the tender list.
CRS3/SF1
CRS 3.3.2
HOME
GACC
EDITION 2: FEB 1998
THE LONG LISTING PROCESS
CONTRACTORS
CONTRACTOR SELECTION
You should note that a negative response will not prejudice your companys
prospectsof being invited to tender in the future.
Please also note that the detailsgiven in thispreliminary enquiry may change and
neither thisenquiry nor your positive reply to it in any way guarantee that you will
be included on the final tender list or that the work will proceed at all. In addition
the above information isto be treated asstrictly confidential.
Yoursfaithfully
CRS 3.3.3
HOME
GACC
EDITION 2: FEB 1998
CRS 3.4 PRE-SELECTION PROCEDURES
O nce the long list hasbeen formed, then pre-selection information is
gathered in order to produce the final short list of contractors. The
object of contractor pre-selection isto determine a short list of firms,
any one of which could be entrusted with the work. The final choice of
contractor on thisbasisistherefore simpler. The following criteria ( and
any other criteria considered appropriate to the contract) are among
the pointswhich should be considered in formulating the short list:
contractor staff: availability and track record of key personnel; note
that contractorswill tend to field their best team to win the job;
availability and ownership of plant;
ratio of contracted to permanent staff;
turnover of company in relation to project size and expenditure
profile;
company status: relationship to parent company, joint venturesetc.;
isit a shell company or dormant;
contractorspolicy with regard to sub-contract work;
safety policy and record;
attitude of contractor to claims: check referencesand other
experience;
capability, experience and standard proceduresin such areasas
project management, cost control, procurement, design servicesetc.
A full evaluation of these factorsshould generate a short list of
contractorssuitable for the works.
Where the EC public procurement rulesapply, and the restricted
procedure isbeing followed, then each of the expressionsof interest
will be evaluated on the basisof a paper sift in order to arrive at a
short list.
EPP 1

PRE-SELECTION PROCEDURES
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.4.1
HOME
GACC
EDITION 2: FEB 1998
Pre-Selection Interview
In certain circumstancesdepending on the size and importance of the
contract it may be necessary to carry out an interview of all the
potential biddersaspart of the pre-selection procedure. Thisallows
firmsto highlight their strengthsand for Departmentsto expose any
weaknessesand also to meet the firmsstaff.
It isrecommended that the following issuesare considered in respect
of pre-selection interviews:
plan the interview;
ensure each interviewer hasan agreed area on which to
concentrate and standard check listsare prepared covering these
areas;
have a standard agenda and a priority marking system;
analyse capability against a seriesof key areasfor the specific project;
take up other private or Department references;
determine resource strength in depth;
look for real experience and track record rather than impressive
presentational skills;
for contractssubject to the EC WorksDirective, make sure to stay
within the boundsof the evidence that isrequired; and
treat all contractorsidentically to avoid any hint of discrimination.
The interview providesan opportunity for the Department to learn
about the industry and market conditionsfirst hand. O ther issuesmay
be discussed such aspayment terms, insurance, pre-ordering materials,
subcontracting etc.
Key Points
The idea behind contractor pre-selection isto result in a short list of
contractorswhich can all be entrusted with the works.
PRE-SELECTION PROCEDURES
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.4.2
HOME
GACC
EDITION 2: FEB 1998
CRS 3.5 COMPILATION OF SHORT LISTS
When all pre-selection information hasbeen gathered, and evaluated,
the short list can be produced. The number of tenderersselected for
the short list will depend on the size and complexity of the works
contract.
Those who are not short listed should be advised in writing. Standard
Form 2 - Exclusion Notification, may be sent ( see CRS 3/SF2) . There
are two alternative paragraphsdepending on whether or not a pre-
selection interview washeld.
CST 3.6

COMPILATION OF SHORTLISTS
CONTRACTORS
CONTRACTOR SELECTION
CRS 3.5.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 2 - LETTER
Exclusion Notification
Dear Sirs
[TITLE OF PROJECT]
Thank you for your letter of [date] expressing an interest in being invited to tender
for the above contract.
[or, ( if attended pre-selection interview) : Thank you for the opportunity of meeting
you on [date] to discussyour firm and the above project].
After careful consideration I must advise you that on thisoccasion the Department
doesnot intend to invite you to tender.
Please be assured that thisdecision in no way affectsthe prospect of you being
invited to tender for suitable work in the future.
Yoursfaithfully
COMPILATION OF SHORTLISTS
CONTRACTORS
CONTRACTOR SELECTION
CRS3/SF2
CRS 3.5.2
HOME
GACC
EDITION 2 REV 1: JAN 2000
CRS 3.6 THE NUMBER OF TENDERERS
A balance must be struck between encouraging competition and
providing each tenderer with a reasonable chance of success. In respect
of major workscontractsit isrecommended that tenderersare invited
from six tenderers, however, it should generally be not lessthan three
and no more than ten for selective ( restricted) tendering. Each contract
should be decided on itsindividual merits, but the following isan
indicative guide for deciding on the number of tenderers.
B&CE
up to 1 million estimated value 5 or 6 firms
1 million and over 6 to 10 firms
M&E
up to 250,000 estimated value 4 to 6 firms
250,000 and over 6 to 8 firms
In respect of design and build contractswhere the contractor can be
involved in expensive design work aspart of the tender, it is
recommended that tendersare sought from no more than three
contractorsunlessthe EC public procurement rulesapply.
Where the EC rulesapply and the restricted procedure isbeing used,
the contracting authority may specify the range in the Contract Notice
from within which the number of tendererswill be invited to bid. The
lower number of the range must not be lessthan 5 and the higher
number not more than 20.
If an authority choosesnot to specify a range, then it isfree to invite
any number of biddersprovided it issufficient to ensure genuine
competition ( normally not lessthan 3) .
EPP 1.11

THE NUMBER OF TENDERERS


CONTRACTORS
CONTRACTOR SELECTION
CRS 3.6
HOME
GACC
EDITION 2: FEB 1998
CRS 4.0 TENDERING PROCESS
CRS 4.1 DOCUMENTATION
The information must be ascomprehensive aspossible and it must be
clear which elementsare meant to be contractual and which partsare
for information or guidance.
Thisdocumentation isthe basisof the contractorsprice. Lack of clarity
or ambiguity in documents, create weaknessesor opportunitieswhich
the contractor may exploit in order to increase the final cost and/or
delay the time for delivery.
It isimportant therefore that the tender documentssatisfy the
following essential requirements:
the documentsshould be specific about what isrequired;
the documentsshould be without ambiguity; these and any
documentswhich are a record of negotiationsthat are subsequently
incorporated ascontract documents, should all be consistent with
one another;
the conditionsmust clearly allocate risksasbetween contractor and
Department and specify who must pay what in the event of
variationsor delay.
The content of tender documentation for a workscontract will
typically comprise:
instruction to tenderers;
general conditionsof contract;
special conditionsof contract;
scope of work;
standardsand specifications;
schedulesand drawings;
pricing schedulesasrequired by the form of contract ( e.g. BQ s) ;
DOCUMENTATION
CONTRACTORS
TENDERING PROCESS
CRS 4.1.1
HOME
GACC
EDITION 2: FEB 1998
schedule of rates; and
administration procedures
standard acknowledgement slip ( see CRS4/SF1)
tender return label ( see CRS4/SF2)
Invitations to Tenderers
It issuggested that these should include, inter alia, the following
information ( when not included within the instructionsto tenderers) :
the point of contact to which queriesshould be sent by tenderers;
the addressto which tendersshould be returned;
the time and date of the return of tenderers;
the addresswhere additional documentsand information may be
inspected;
any expected delaysto possession of site or commencement of the
works;
timingsfor the appointment of nominated sub-contractors;
any key design phasesand timings;
qualification or amendmentsto standard conditionsof contract;
brief detailsof the Departmentsinsurances;
ratesfor liquidated damage ( where applicable) ;
length of maintenance period e.g. B&CE 6 months, M&E 12 months.
The Government formsof contract include standard formsof invitation
to tender and formsof tender which are recommended for use with
these forms.
DOCUMENTATION
CONTRACTORS
TENDERING PROCESS
CRS 4.1.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
INSTRUCTIONS
CONTRACTORS
TENDERING PROCESS
CRS 4.2 INSTRUCTIONS/NOTICES TO TENDERERS/
TENDER PERIODS
Instructions to Tenderers
These will usually not form part of the contract documentation since
their purpose isfor guidance to tenderersin submitting a compliant bid.
Typical guidance within the instructionsinclude:
advice on how to respond to the invitation to tender;
complete schedule of all tender documents;
a possible checklist for tender returns.
It issuggested that the instructionsmake it clear that the Department
isnot bound to accept the lowest price, in other wordsthe selection
criteria should be value for money. Additional information may include:
arrangementsfor the acceptance of telephoned, faxed or telexed
tenders- stating whether they are acceptable or not;
the criteria for accepting late tenders;
procedure for dealing with qualified tenders;
policy on alternative tenderswhich are non-compliant bids;
arrangementsfor receipt, opening and recording of bids;
procedure for dealing with arithmetical errors;
policy for debriefing unsuccessful tenderers;
instructionswith regardsto confidentiality of tendersi.e. to mark
clearly In confidence;
the requirement to be registered with Inland Revenue under the
Construction Industry Tax Scheme.
CRS 5.6

CRS 4.7

CRS 5.3

CRS 5.4

CRS 7.0

CRS 4.2.1
LE 2.11

HOME
GACC
EDITION 2 REV 2: JAN 2000
Tender Periods
The time allowed to prepare the bid must be adequate in order to
submit a comprehensive bid. For lump sum contracts( i.e. BQ s) it istime
consuming to estimate the cost of all the resourcesrequired to provide
the worksand where a design issought thisiseven more onerous.
Approximately six weeksisrecommended for traditional procurement,
however, the requirementsof each contract must be considered
separately. Minimum periodsare specified when the contract issubject
to the EC public procurement rules.
Extensions of Time
Tenderers, from time to time, may request an extension to time for
preparing their tender. In principle there isno justification for extending
the tender period. However, Departmentsmay wish to consider such
requestswhere, for example, there have been a change in the
circumstances, usually by way of a tender amendment.
Key Points
It issuggested that a tender period around six weeksisappropriate
for traditional procurement. Appropriate periodsvary according to
project value and complexity.
It may be advisable to contact tenderersbeforehand to ensure that
tender periodsare feasible.
INSTRUCTIONS
CONTRACTORS
TENDERING PROCESS
EPP 1.8

CRS 4.2.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 1
ACKNOWLEDGEMENT SLIP
Tenderersare requested to complete thisslip and return it to:
..................................................................................................................................................................................................
[Departmental address] immediately upon receipt of the tender documents.
PRO JECT/CO MMISSIO N TITLE: ....................................................................................................................
DEPARTMENT REFERENCE NO : ..................................................................................................................
DEPARTMENT LIAISO N O FFICER: ..................................................................................................................
( asstated in the invitation letter)
1. I acknowledge receipt of tender documentsfor the above project/commission.
( either) *
2. I will submit my tender by the due date.
( or) *
2. I do not wish to tender on thisoccasion and return the documentsherewith.
Signed: .................................................................................................
For and on behalf of .................................................................................................
.................................................................................................
.................................................................................................
Date: .................................................................................................
* Delete asappropriate
CRS4/SF1
INSTRUCTIONS
CONTRACTORS
TENDERING PROCESS
CRS 4.2.3
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 2
Tender Return Slip
CRS4/SF2
T
e
n
d
e
r
F
O
R

C
O
N
T
R
A
C
T

N
O
:
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
R
e
t
u
r
n
a
b
l
e

n
o
t

l
a
t
e
r

t
h
a
n

1
1
.
0
0

h
r
s

o
n
:
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
N
o
t
e
s
:
1
.
T
h
e

e
n
v
e
l
o
p
e

t
o

w
h
i
c
h

t
h
i
s

l
a
b
e
l

i
s

a
t
t
a
c
h
e
d
m
u
s
t

n
o
t

b
e
a
r

a
n
y

i
n
d
i
c
a
t
i
o
n

o
f

t
h
e

t
e
n
d
e
r
e
r

s
n
a
m
e
.
2
.
I
t

i
s

t
h
e

t
e
n
d
e
r
e
r

s

r
e
s
p
o
n
s
i
b
i
l
i
t
y

t
o

e
n
s
u
r
e
t
h
a
t

t
h
e

t
e
n
d
e
r

i
s

d
e
l
i
v
e
r
e
d

b
y

t
h
e

d
u
e

t
i
m
e
.
T
e
n
d
e
r
s

r
e
c
e
i
v
e
d

a
f
t
e
r

t
h
i
s

t
i
m
e

w
i
l
l

n
o
t

b
e
c
o
n
s
i
d
e
r
e
d
.
3
.
T
e
n
d
e
r
s

t
o

b
e

d
e
l
i
v
e
r
e
d

b
y

h
a
n
d

a
r
e

t
o

b
e
h
a
n
d
e
d

i
n

a
t

t
h
e

r
e
c
e
p
t
i
o
n

d
e
s
k

a
n
d
/
o
r

p
l
a
c
e
d
i
n

t
h
e

[
D
E
P
A
R
T
M
E
N
T

S
]

T
E
N
D
E
R

B
O
X
.
A
F
F
I
X
P
O
S
T
A
G
E
S
T
A
M
P
S
H
E
R
E
D
E
P
A
R
T
M
E
N
T
A
L

A
D
D
R
E
S
S
INSTRUCTIONS
CONTRACTORS
TENDERING PROCESS
CRS 4.2.4
HOME
GACC
EDITION 2: FEB 1998
CRS 4.3 MID-TENDER INTERVIEWS
Mid-tender interviewsare held with tenderersafter the tendershave
been invited. The interview should be timed such that tenderershave
had sufficient time to give detailed consideration to the requirements
of the tender.
The requirement for mid-tender interviewsisoptional. However, the
more complex the work the more likely it isthat a mid-tender
interview will be of value.
Mid-tender interviewsshould be held separately with each tenderer.
Avoid allowing tenderersto attend the officesat the same time or to
see other namesin a signing-in book.
The principle functionsof a mid-tender interview are that it provides:
a further opportunity for the Department and itsadvisersto meet
the tenderers;
an opportunity for contractorsto raise any specific queriesthey may
have concerning incomplete tender information or ambiguitiesin
the information;
an opportunity for contractorsto raise questionsabout potential
qualificationsor alternative tenders;
a chance for the Department to issue any further information, the
need for which may already have been flagged up by the design
team or tenderers.
The Department may gain very useful information about design
problemsand an insight into some of the risksit may not have fully
considered at the pre-tender stage. All requestsfor information should
be consolidated and all answersprovided to all tenderersto ensure
consistent and fair dealing.
Where queriesresult in a significant change then an extension of the
tender period should be considered.
Key Points
All tenderersshould be dealt with equally and fairly.
Additional information should be provided in writing to all
tenderers.
MID-TENDER INTERVIEWS
CONTRACTORS
TENDERING PROCESS
L
! !! !!
CRS 4.3
HOME
GACC
EDITION 2: FEB 1998
CRS 4.4 TENDER BOARDS
A tender board, typically comprising three people should be appointed
to open and record bids. It isrecommended that the following
conventionsbe followed:
one member should be a senior chairperson;
one member should be completely independent from the
commission; thishelpsto establish the credibility of the board, as
impartial;
total impartiality isachieved through choosing different tender
board membersfrom those on the tender evaluation panel.
To promote propriety, it helpsif a member of the board appointsno
more than one other member, i.e. chairperson appointsthe secretary,
the secretary appointsthe third person.
It isthe responsibility of the senior board member to ensure that all
membersare conversant with tender board and tender opening
proceduresand the tender documents.
TENDER BOARDS
CONTRACTORS
TENDERING PROCESS
CRS 4.4
HOME
GACC
EDITION 2: FEB 1998
CRS 4.5 OPENING OF TENDERS
O nce the tendershave been received they should be securely locked
away in a cabinet or tender box until they are due to be opened ( i.e.
the advertised time) .
Prior to the opening of tenders, the commission manager/project
sponsor should provide the tender board with a list of all those invited
to tender. Thisenablesthe tender board to identify those who have
not submitted tendersor subsequently those whose tendersare
received late.
When the tender box isopened, the unopened tendersshould be
passed directly to the tender board, and to no-one else.
The following stepsshould then be followed by the tender board:
tendersshould ideally be opened in a locked room with no working
telephone;
if the tender board isdealing with tendersfor a number of contracts
or commissionsthen it will need to sort tendersby their unique
tender number and deal separately with the tendersfor each
contract;
opened tendersfor a contract should be sorted according to price
or in the alphabetical order of the tenderers name;
any unpriced tendersare not complete tendersand should
therefore be rejected and returned stating the reason for rejection;
where a tender document hasa tendererssignature at the end of
it, each page of that document should be signed by the senior
member of the tender board; thismay be speeded up by the use of
a personal facsimile signature stamp;
each tender should then be given a sequential number to prevent
later insertion of other tenders;
a tender summary sheet should then be completed ( CRS4/SF3) ; on
the sheet should be listed the sequential tender numbersnamesof
tenderersfrom whom tenderswere received and their price; names
of those who did not submit tenders, should also be given together
with the reason if known;
OPENING OF TENDERS
CONTRACTORS
TENDERING PROCESS
CRS 4.5.1
HOME
GACC
EDITION 2: FEB 1998
the tender summary sheet relatesto the tendersfor a particular
contract and should be completed and signed by the senior tender
board officer;
the tender summary sheet and opened tendersshould be delivered
by hand or, if necessary sent by registered post to a member of the
tender evaluation panel.
OPENING OF TENDERS
CONTRACTORS
TENDERING PROCESS
CRS 4.5.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 3
Tender Summary Sheet
[Department]
TENDERS - SUMMARY SHEET
Commission/Contract File No: ........................................................................................................................................
LO CATIO N
NAME O F CO NTRACT/CO MMISSIO N
ESTIMATED CO ST
DATE
Tendersaslisted below, have today been opened and authenticated by the Tender
O pening Board. Also listed are the namesof those firmsthat did not wish to tender,
together with those that did not respond to the tender invitation
To:
........................................................................................................................................................................................................
Will you please examine the enclosed tendersand provide your recommendation assoon
aspossible
Signed: ...............................................................................................................................................................................................
Senior Tender Board O fficer
OPENING OF TENDERS
CONTRACTORS
TENDERING PROCESS
CRS4/SF3
CRS 4.5.3
HOME
GACC
EDITION 2: FEB 1998
CRS 4.6 THE TENDER RECORD BOOK
(THIS SECTION DUPLICATES CST 4.13)
A tender record book isa proforma book used for recording all
tendersfor all contractsopened on a given day. It istherefore a
running record of all tendersopened. An example format isgiven at
CRS4/SF4.
The tender record book isinvaluable for senior officersand auditors, as
the first step in any review of tendering activity since it providesa
complete reference record of allocated tender numbers.
It isimportant that the sequence of numbersshould remain unbroken.
Tender board membersshould sign the tender record book once
tender opening hasbeen completed, confirming the next number in
the sequence.
Thispreventsany irregularitiessuch asthe addition of a late tenderer
to the tender list without prior approval of the tender board and
without clear reasonsfor so doing.
CRS 4.7

THE TENDER RECORD BOOK


CONTRACTORS
TENDERING PROCESS
CRS 4.6.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 5
TENDER RECORD BOOK
CRS4/SF4
C
O
M
M
E
R
C
l
A
L

l
N

C
O
N
F
l
D
E
N
C
E
T
E
N
D
E
R

R
E
C
O
R
D

B
O
O
K
[
D
E
P
A
R
T
M
E
N
T
]
S
E
R
I
A
L

N
O
C
O
N
T
R
A
C
T
/
T
I
T
L
E

O
F
N
A
M
E

O
F
T
E
N
D
E
R
D
A
T
E

A
N
D

T
I
M
E
N
O
T
E
S

O
N
S
I
G
N
A
T
U
R
E

O
F
O
F

T
E
N
D
E
R
S
C
O
M
M
I
S
S
I
O
N

N
O
C
O
N
T
R
A
C
T
/
C
O
M
M
I
S
S
I
O
N
F
I
R
M
P
R
I
C
E
T
E
N
D
E
R
S

O
P
E
N
E
D
C
O
M
P
L
E
T
E
N
E
S
S
T
E
N
D
E
R

B
O
A
R
D
(
S
E
E

N
O
T
E

2
)
T
E
N
D
E
R
I
N
G
O
F

T
E
N
D
E
R
/
M
E
M
B
E
R
S
I
R
R
E
G
U
L
A
R
I
T
I
E
S
N
o
t
e
s
:
1
D
e
t
a
i
l
s

o
f

a
l
l

C
o
n
t
r
a
c
t
o
r
s
/
C
o
n
s
u
l
t
a
n
t
s

w
h
o

w
e
r
e

i
n
v
i
t
e
d

t
o

t
e
n
d
e
r

m
u
s
t

b
e

i
n
c
l
u
d
e
d
.

T
e
n
d
e
r

p
r
i
c
e
s

s
h
o
u
l
d

b
e
e
n
t
e
r
e
d

w
h
e
r
e

i
t

i
s

c
l
e
a
r

f
r
o
m

t
h
e

t
e
n
d
e
r

d
o
c
u
m
e
n
t
s
,

o
t
h
e
r
w
i
s
e

s
e
e

t
e
n
d
e
r


s
h
o
u
l
d

b
e

e
n
t
e
r
e
d
.
2
B
e
l
o
w

t
h
e

l
a
s
t

t
e
n
d
e
r

n
u
m
b
e
r

e
n
t
e
r

N
e
x
t

T
e
n
d
e
r

N
u
m
b
e
r

T
o

B
e

U
s
e
d


a
n
d

i
n
s
e
r
t

T
e
n
d
e
r

N
o
.
THE TENDER RECORD BOOK
CONTRACTORS
TENDERING PROCESS
CRS 4.6.2
HOME
GACC
EDITION 2: FEB 1998
CRS 4.7 LATE TENDERS
Late tendersare not acceptable and should be rejected. However, it
may be unfair to reject a posted tender if it hasbeen held up in the
post. The tender board should be re-commenced on receipt of late
tenders. Late tendersmight be accepted in the following circumstances:
first cIass posted tenders - the date stamp should be at least
one day before tenderswere due to return;
second cIass posted tenders - the date stamp should be at least
two daysbefore tenderswere due to return.
If the date stamp or classof postage are difficult to ascertain - treat as
second classpostage. If the date stamp and classare made with the
tenderersfranking machine, the tender should be rejected.
Tendersshould not be accepted by facsimile under any circumstances.
A record of all rejected tendersshould be kept at the back of the
tender record book, and the price should not be recorded or disclosed.
( See CRS4/SF5)
Should the tender opening board decide to admit a late tender into
competition it should be inserted in sequence into the list of tenders
and given a suffix to the preceding number i.e.:
Tender nunbers Tenderer's Price
248 JBloggs 265,498
249 JSmith 265,501
249A* T Jones 270,995
250 F Black 276,222
251 B White 292,543
* admitted late tender
The envelope of any rejected tenderer should be retained and should
be endorsed with the tenderersname together with the reasonsfor
rejection and signed by a senior member of the tender evaluation
board. The contentsshould then be returned to the tenderer with a
short explanation for rejection ( see CRS4/SF6) .
The envelopesfor admitted and rejected late tenderersshould be filed
and used if the decision ischallenged.
LATE TENDERS
CONTRACTORS
TENDERING PROCESS
CRS 4.7.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 6
RECORD OF REJECTED TENDERS
LATE TENDERS
CONTRACTORS
TENDERING PROCESS
C
O
N
T
R
A
C
T
/
T
I
T
L
E

O
F
N
A
M
E

O
F
D
A
T
E
D
A
T
E

A
N
D

T
I
M
E
R
E
A
S
O
N

F
O
R
S
I
G
N
A
T
U
R
E

O
F
C
O
M
M
I
S
S
I
O
N

N
O
C
O
N
T
R
A
C
T
/
C
O
M
M
I
S
S
I
O
N
F
I
R
M
T
E
N
D
E
R
S
T
E
N
D
E
R
S

R
E
C
E
I
V
E
D
R
E
J
E
C
T
I
O
N

O
F
T
E
N
D
E
R

B
O
A
R
D
D
U
E
T
E
N
D
E
R
M
E
M
B
E
R
S
C
O
M
M
E
R
C
l
A
L

l
N

C
O
N
F
l
D
E
N
C
E
R
E
C
O
R
D

O
F

R
E
J
E
C
T
E
D

T
E
N
D
E
R
S
[
D
E
P
A
R
T
M
E
N
T
]
CRS4/SF5
CRS 4.7.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 7 - LETTER
REJECTION AND RETURN OF TENDER
[Department]
O ur Ref
Your Ref
Date
Dear Sirs
Location: ................................................................................................................................................................................
Commission: ................................................................................................................................................................................
Thank you for your tender for the above contract. It isvery much regretted that it was
received after the time appointed for delivery and therefore cannot be considered. It is
returned herewith.
Should further opportunitiesarise for you to tender, it would be appreciated if you would
ensure that your offersarrive in time to be admitted.
Yoursfaithfully
LATE TENDERS
CONTRACTORS
TENDERING PROCESS
CRS4/SF6
CRS 4.7.3
HOME
GACC
EDITION 2: FEB 1998
GENERAL
CONTRACTORS
TENDER EVALUATION
CRS 5.0 TENDER EVALUATION
CRS 5.1 GENERAL
The most important principle with thisprocessisthat it must be open,
clear, systematic, fair, thorough and seen to be so.
The following are some of the key issuesto be considered:
the purpose of the evaluation isto identify the best value for money
by comparing the price against the assessed benefits( under EC
procurement thisisknown asthe most economically advantageous
tender) ;
parity of tendering must be observed, in other words, tender
documentsshould not generate tendersbased on unequal criteria;
correspondence should be channelled though a single officer to
ensure that a fair and consistent approach isadopted with all
tenderers; such correspondence should be allocated a unique
reference or job number since all amendmentsmust be clearly
referenced at contract award stage.
Procedure Prior to Evaluation
Prior to evaluation consideration should be given to the following
points:
ensure that the tender returnshave been signed;
the lowest tenderersshould be asked to provide their BQ assoon
aspossible;
incomplete tender returnsmust be taken up with the tenderer ( this
may be classed asa non-compliant bid and therefore unacceptable) .
It isrecommended that the invitation to tender should state that
the Department isunder no obligation to check the completeness
of a tender and that incomplete tendersmay be rejected;
arithmetical check on tender prices;
where bidsare not exactly comparable because, for example, of
different proposalsfrom contractors, then the tender board must
choose either to reject non-compliant bidsor to condition bidsas
far aspossible such that they are comparable.
CST 5.3

CRS 5.1.1
HOME
GACC
EDITION 2: FEB 1998
identification of qualified tendersand additional termsinserted;
isthe tender exceptionally low ( abnormally low in EC procurement
vocabulary) .
Key Points
The tendering processshould be fair and scrupulous.
Any contactswith tenderersshould be consistent and information
should be distributed to all tenderers.
GENERAL
CONTRACTORS
TENDER EVALUATION
CRS 5.1.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 5.2 CRITERIA FOR EVALUATION
It isimportant that the tender evaluation panel decide on the criteria
which are most important to the contract before tender opening and
preferably before invitation to tender. Each criterion should be
weighted and agreed before bidsare opened and if the contract is
subject to the EC WorksDirective the criteria must be stated in the
tender notice or bid documents.
The appropriate criteria will heavily depend on the chosen contract
strategy. The following are commonly used but there are others:
Lump Sum Tender
Technical
- -- -- checking for compliance with specification;
- -- -- resolving any stated deviationsfrom specification;
- -- -- evaluating benefitsof alternative proposals;
- -- -- if the biddersare to do any design, evaluating their design
capability and any design proposalsfor ease of construction and
operability.
Execution proposal
- -- -- evaluating proposed programme;
- -- -- evaluating execution proposals: e.g. management organisation
and support, resourcesof plant and labour proposed;
- -- -- plant and labour availability ( which may be very different) ;
- -- -- reviewing key project personnel.
Commercial
- -- -- reviewing sensitivity to changesimposed by Department;
- -- -- if the price includesa BQ do the ratesreflect the true costsof
the itemsconcerned, or are they unbalanced?;
- -- -- evaluating any exceptionsto conditionsof contract.
CRITERIA FOR EVALUATION
CONTRACTORS
TENDER EVALUATION
CRS 5.2.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
Cost Reimbursable Tenders
Technical
- -- -- quality and completenessof proposals;
- -- -- cost evaluation of benefitsof one proposal compared with
another;
- -- -- design office productivity particularly the use of modern
technology such ascomputer aided design ( CAD) and
derivatives;
- -- -- construction/supervision track record: labour management, sub-
contractor management, claimssettlement, construction
techniquesand experience on other jobsetc.;
- -- -- potential programme differences;
- -- -- personnel quality - thisisreally the key issue for reimbursable
cost or management contracts. The cost of management
personnel will typically represent some 5 to 15 percent of the
contract value but their level of competence will have an
enormouseffect on the end costs;
- -- -- reviewing all key postsand in particular looking at strength in
depth;
- -- -- taking up other private or Department references;
- -- -- procurement procedures;
- -- -- cost management procedures;
- -- -- evaluation of operating costsand overheads;
- -- -- comparing quoted fee with estimated man-hours;
- -- -- reviewing cost audit, reporting, and control mechanisms.
The evaluation exercise can then proceed following a similar method
and taking account of the principlesespoused in CST 5.1.
CRITERIA FOR EVALUATION
CONTRACTORS
TENDER EVALUATION
CRS 5.2.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
Key Points
Useful further guidance can be found in HM Treasury Procurement
Guidance ( No. 3) , available from:
HM Treasury
Public Enquiry Unit
Room 89/2
Parliament Street
London SW1P 3AG
Tel. 020 7270 4558
Within the document isan illustrative example of an award mechanism
which could be adopted. It would of course need to be amended to
suit the individual circumstancesof each project.
CRITERIA FOR EVALUATION
CONTRACTORS
TENDER EVALUATION
CRS 5.2.3
HOME
GACC
EDITION 2: FEB 1998
CRS 5.3 QUALIFIED TENDERS
Q ualified tendersare difficult if not impossible to compare with others,
and for thisreason they should be actively discouraged. It may be
decided for example to state in the invitation to tender that qualified
bidswill be automatically disqualified, unlessalternativesare sought.
Where the EC procurement rulesapply, the procurer hasthe option of
stating in the contract notice that qualified tenderswill not be
considered.
Although qualified tenderswill generally not be accepted, in certain
circumstancesit isadvisable that they are given consideration. If a
qualified tender isreceived, the tenderer should be given the
opportunity to withdraw the qualification without amendment to its
tender price. Thisshould be done through correspondence, copiesof
the Departmentsletter and the tenderersreply being kept on the
commission file.
Should a tenderer refuse to withdraw itsqualification, then the
importance of the qualification and the effect on the tender price will
need to be assessed asprecisely aspossible.
If the tenderer isotherwise in the running and the qualification isa
technical one imposed by a specialist company and offersthe possibility
of innovation and best value for money, professional advice will need
to be sought on the importance of the qualification. It may be possible
to give a fully reasoned explanation not to passover an otherwise
good offer containing an acceptable qualification, e.g. shorter
completion date. Sometimesa price reduction will be offered if such
qualificationsare accepted.
The file should show a fully reasoned explanation if an otherwise good
offer ispassed over due to a qualification, and likewise if an offer is
recommended for acceptance despite a qualification.
Key Points
It may be appropriate to consider qualificationsto tendersif they
provide best value for money.
QUALIFIED TENDERS
CONTRACTORS
TENDER EVALUATION
CRS 5.4

CRS 5.3
HOME
GACC
EDITION 2: FEB 1998
CRS 5.4 ALTERNATIVE OFFERS
Tendererswill sometimespropose an alternative offer, e.g. an
alternative material, method or specification, which they think could
meet the requirementsin a better, cheaper or faster way. Innovation by
tenderersshould not be discouraged.
Generally an alternative offer should be a separate, second offer, to the
main ( or compliant) bid. The alternative offer should not be qualified in
any way and will be fully priced to show clearly how and where costs
would differ from the price based on the original specification.
If the alternative offer demonstratessavingsand added value thiswill
have a bearing on itsacceptability.
The alternative offer may be exposed to competition especially if the
alternative offer isnot the lowest. Thismay however, discourage
tenderersfrom introducing further innovative ideas. In caseswhere the
alternative issubject to a patent thisisnot an issue. It isimportant to
consider whether the alternative fundamentally underminesthe original
pricing assumptions, in thiscase further competition may be regarded
asessential.
Key Points
It may be appropriate to consider alternative offersif they provide
best value for money.
ALTERNATIVE OFFERS
CONTRACTORS
TENDER EVALUATION
CRS 5.4
HOME
GACC
EDITION 2: FEB 1998
CRS 5.5 AMENDED TENDERS
Departmentsshould decide before evaluation of tendersbegins, the
extent to which they will permit tenderersto change bidsfollowing the
closing date for receipt. It isusual practice not to accept such
amendmentsand to ask the contractor either to:
absorb the effect of any errorsin pricing found post-tender; or
withdraw the offer.
Alternatively, Departmentsmay opt to admit amendmentsif they are
satisfied that the errorsare genuine and thereby maintain competition,
especially if the errorsrelate to what would otherwise be the preferred
tender.
If the amendment isdue to an alleged clerical error or
misinterpretation of specification or drawingsand isconsidered not to
be credible reasoning, then the tenderer should be told that itsoriginal
offer must stand, or be withdrawn.
Key Points
It isusual to refuse to accept amendmentsdue to errorsunlessit is
clearly a genuine error and/or that might seriously prejudice the
contractor.
The lowest tenderer should not be so advised at thisstage.
Provided the contractor isunaware of the other bids, then it will be
at itsrisk whether or not the contractor wantsto request an
amendment that may result in it not being the lowest.
AMENDED TENDERS
CONTRACTORS
TENDER EVALUATION
CRS 5.5
HOME
GACC
EDITION 2: FEB 1998
CRS 5.6 ERRORS IN PRICED BILLS
General
It isrecommended that Departmentsare clear on their policy for
handling obviouserrorsin BQ sor schedulesof ratesfound during
evaluation.
The object of examining pricesisto detect errorsin computation and
to avoid BQ sthat undermine the reliability of the tender rankings.
Errorsin pricing due to poor estimating would be absorbed by
contractorsif discovered after contract award, however it issensible
and professional practice to identify errorsin pricing. It isrecommended
that misplaced decimal pointsetc., or patent errorsin arithmetic, should
be notified to tenderersduring evaluation so they can either:
confirm their tender;
withdraw their tender;
amend their tender.
The Department should ensure that the chosen alternative isclearly
expressed in the Form of Tender.
Deliberate Errors
If the Department suspectsthat the error wasdeliberate to allow an
amended price or if it seemsto be so abnormally high or low, it is
recommended that they reject it and insist on the original bid being
confirmed or withdrawn.
Abnormally Low Tenders
In contractswithout BQ s, errorsresulting in abnormally low or
uneconomic bidsshould incorporate similar proceduresasabove, i.e.
challenge the price and allow amendment ( if the error issatisfactorily
explained) or the bid to be confirmed or withdrawn.
The rejection of abnormally low tendersisnot only highly
questionable in termsof best value for money, but also a contravention
to the EC Works/ServicesDirectives. The Directivesrequire that
tenderersbe provided with the opportunity to justify apparently
uneconomic bids.
CRS 5.5

ERRORS IN PRICED BILLS


CONTRACTORS
TENDER EVALUATION
CRS 5.6
HOME
GACC
EDITION 2: FEB 1998
CRS 5.7 POST TENDER NEGOTIATION
Post tender negotiation ( PTN) may exceptionally be appropriate or
necessary. It involvesthe negotiation of the leading tenderersbid with
the tenderer, and iscarried out after bid conditioning and bid
evaluation are complete.
Procedure
The purpose isto obtain an improvement in content and circumstances
which do not put the other tenderersat a disadvantage or distort
competition, and resultsin best value for money. If it isto be done then
it isrecommended that PTN iscarried out after receiving tendersand
before the letting of the contract.
PTN may be necessary where part of a specification needsclarification
or because there are insufficient fundsavailable to cover the price
submitted by the lowest acceptable tender. The aim of PTN, isto
secure value for money and definitely not to start a dutch auction.
All negotiationsshould be fully recorded or minuted so asto provide
an audit trail. PTN can be undertaken by revising drawingsor BQ setc.,
should negotiationsfounder, attemptscan be made to negotiate with
the next lowest tenderer and so on in ascending order of tendered
sums. It isrecommended that only the three lowest tenderersshould
be approached for negotiation.
EC Implication
Where PTN isbeing considered for projectsthat are subject to the EC
Directive, negotiationsare only permissible to clarify points; thisprocess
would be more correctly termed post tender clarification.
Key Points
Different Departmentshave different policieson the treatment of
post-tender negotiations. Project sponsorsshould refer to their
Departmental handbooks.
Post-tender negotiationsare only likely to be permissible on the
groundsthat the selected tenderersoffer still representsbest value
for money.
If negotiationsare required to reduce the scope of the work to
secure a price within budget, then it may be appropriate to re-
tender the works, if the scope hasto be changed significantly.
POST TENDER NEGOTIATION
CONTRACTORS
TENDER EVALUATION
CRS 5.8

CRS 5.7
HOME
GACC
EDITION 2: FEB 1998
CRS 5.8 RE-INVITATION OF TENDERS
Circumstances
O n the assumption that none of the tendersare acceptable then all
tenderswill need to be declined and formal re-tendering undertaken.
Some potential reasonsfor such an action are where:
a high number of short listed tenderersdrop out or fail to submit
bids;
the bidsare all substantially higher than expected in light of current
market conditions;
where significant changesin scope of the work are required in order
to obtain a price which might conform to budget;
collusive tendering.
It should be noted that the decision to re-tender should not be taken
lightly. The Department should be very certain of itsgroundsfor doing
so. Tenderscan cost contractorsa lot of money to prepare. A re-
tender situation causesmuch unhappinessamongst contractors, and
may prejudice a contractorsdesire to tender in the future, especially
when market conditionsare good.
Re-invitation of Original Tenderers
If the original tender list foundered largely because it wasnot feasible
to negotiate-in substantial changesto the Departmentsrequirements,
then the original tender list could stand. If
re-invitation isthe result of high tendersand unsuccessful
post-tender negotiation, then new firmsshould replace the highest
original bidderse.g., top 3 out of 6. Where re-invitation isdue to sharp
or corrupt practice amongst tendererse.g., the detection of collusive
bidding or cover-pricing, then all the firmsinvolved in the malpractice
should be dropped from the new tender list.
It isrecommended that re-invited firmsto tender should be provided
reasonsasto why the original offer wasnot acceptable so asto allow
tenderersto decide on the value of submitting further tenders.
RE-INVITATION OF TENDERS
CONTRACTORS
TENDER EVALUATION
L
! !! !!
CRS 5.8.1
HOME
GACC
EDITION 2: FEB 1998
Key Points
Re-invitation of tendersmay exceptionally be appropriate.
The Department should keep clear and auditable recordsof its
reasonsfor such an action.
It isrecommended that tenderersin the rejected round of tenders
should be advised of the reasonsfor re-tendering.
RE-INVITATION OF TENDERS
CONTRACTORS
TENDER EVALUATION
CRS 5.8.2
HOME
GACC
EDITION 2: FEB 1998
CRS 5.9 TENDER REPORTING
For all contracts, the tender evaluation team must formalise their
recommendation for the award of the contract. Thisprocessiscalled
tender reporting and it setsout the background and basisfor the
decision to provide an audit trail and opportunity for department
managersto ratify the recommendation. The tender report should
include:
an explanation of the background to the scope of the contract;
a summary of the recommendation;
a description of the pre-qualification criteria;
a description of the bid opening and initial position;
a description of the bid conditioning process;
a description of the tender evaluation criteria;
a description of any post-tender negotiation actions;
the reasonsfor rejection of unsuccessful bids;
summarise reasonsfor recommendation;
a comparison with the pre-tender estimate and confirmation that
fundsare available;
indicate cost and time implicationsfor the project.
TENDER REPORTING
CONTRACTORS
TENDER EVALUATION
CRS 5.9
HOME
GACC
EDITION 2: FEB 1998
CRS 6.0 AWARDING CONTRACTS & DECLINING
TENDERS
CRS 6.1 LEGAL CONTRACT FORMATION
(THIS SECTION DUPLICATES CST 6.1)
The legal processof contract formation isset out at Section LE1.2 -
Simple Contracts. Provided that all of the other elementsof formation
exist, then an unqualified acceptance of an offer givesrise to a legally
binding contract.
It should be noted that an offer may be withdrawn at any time up until
acceptance. To ensure proper formation of contract it isrecommended
that the following conventionsbe observed:
all qualificationsto the tender should have been removed
( negotiated out) ;
the offer must be capable of acceptance ( an unqualified yes) ;
the offer must not have lapsed; the offer may be stated asbeing
open for acceptance within a specified period; if thishaselapsed
then confirmation must be sought from the tenderer that the offer
remainsopen for acceptance;
all subsequent undertaking by the tenderer and amendmentsto the
tender must be confirmed in writing; it isrecommended that at the
very least all such amendmentsbe aggregated into a schedule of
amendmentswhich can be referred to in the acceptance; with time
permitting it isbetter to incorporate amendmentsdirectly into the
contract and initial them;
the tender must represent best value for money;
it isrecommended that a departmental procedure isin place which
requiresapproval by an officer with the appropriate delegation prior
to accepting an offer.
LE 1.2

CRS 5.3

CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
LEGAL CONTRACT FORMATION
CRS 6.1
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
ACCEPTANCE OF TENDER
CRS 6.2 ACCEPTANCE OF TENDER
When contractsare awarded following competitive tendering they are
usually placed with the lowest satisfactory tenderer who isconsidered
to provide the best value for money. Reasonsshould be given if the
lowest tender isnot accepted so asto defend any potential challenge.
O nce the requirementsrelating to the tender have been satisfied, the
offer may be accepted. To ensure proper acceptance of the tender the
following conventionsshould be followed:
acceptance must be unqualified; purported acceptance with
qualificationsrepresentsa counter-offer which may be accepted by
the contractor; thismay lead to unnecessary argument about how
and when acceptance occurred and what isor isnot part of the
contract; thisshould alwaysbe avoided;
acceptance should be communicated in writing; in law, the postal
rule isthat acceptance iscommunicated when the letter isposted
not when it isreceived; proof of posting can be ensured by sending
the acceptance by registered post;
acceptance should be notified with the minimum delay following
receipt of tenders.
Key Points
Acceptance should be unqualified.
Acceptance should be in writing.
CRS 6.1

CRS 6.3

CRS 6.2
HOME
GACC
EDITION 2: FEB 1998
CRS 6.3 LETTER OF ACCEPTANCE
(THIS SECTION DUPLICATES CST 6.3)
A suggested letter of acceptance isgiven at CRS6/SF1.
It isbest practice in the letter to list by reference all documentswhich
are to be incorporated into the agreement and which form the basisof
the acceptance, e.g. exchangesof correspondence prior to award. An
alternative isto attach a schedule, but it isessential that thisisgiven a
recognisable and unique reference number.
It isessential that any correspondence or referencesto negotiationson
feesor alteration to the serviceswhich have been agreed with the
tenderer are referred to in the letter of acceptance.
For the avoidance of doubt it isrecommended that the successful
tenderer isasked to complete and return a confirmation of receipt slip
on receipt of the letter of acceptance.
Note that it isusual for the tenderer, in the form of tender, to give an
undertaking to execute the formal conditionsof contract, when they
are provided for signing.
Contract documentsshould be prepared and provided to the tenderer
with the letter of acceptance.
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
LETTER OF ACCEPTANCE
CRS 6.3.1
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 1 - LETTER
LETTER OF ACCEPTANCE
Dear Sirs
[TITLE O F [TITLE O F [TITLE O F [TITLE O F [TITLE O F PR PR PR PR PRO JECT O JECT O JECT O JECT O JECT ] ]] ]]
[ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER]
Further to our invitation to tender dated .................... and your tender submission provided
under cover of your letter of...................., I accept on behalf of the [Secretary of State], your
offer to carry out [contract works] in connection with the above project.
The [following documentsor the documentsreferred to in Schedule [Contract No]/1]
attached are the basisof thisacceptance; and together with thisletter of acceptance form
a binding contract between us.
LIST DO CUMEN TS SUCH AS: LIST DO CUMEN TS SUCH AS: LIST DO CUMEN TS SUCH AS: LIST DO CUMEN TS SUCH AS: LIST DO CUMEN TS SUCH AS:
invitation to tender
instructionsto tenderers
form of tender
billsof quantities
specification
drawings
schedule of Work
abstract of contract particulars
tender submission from tenderer
schedule of amendmentsor price schedule and basisof payment
correspondence/minutesconfirming undertakingsby tenderer
relevant correspondence from Department.]
Will you please contact .................... [project sponsor/commissionsmanager] assoon as
possible to make arrangementsfor the formal execution of contract documents, and
subsequently for commencing work. Will you please complete and return the attached
acknowledgement slip.
Yoursfaithfully
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
LETTER OF ACCEPTANCE
CRS6/SF1
CRS 6.3.2
HOME
GACC
EDITION 2: FEB 1998
STANDARD FORM 1 - LETTER
LETTER OF ACCEPTANCE
Confirmation of Receipt Slip
[TITLE O F [TITLE O F [TITLE O F [TITLE O F [TITLE O F PR PR PR PR PRO JECT O JECT O JECT O JECT O JECT ] ]] ]]
[ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER] [ CO N T RACT /T EN DER N UMBER]
I acknowledge receipt of your letter of acceptance dated ............................... .
Name: .......................................................................... ( name in block capitals)
Signed: ..........................................................................
in the capacity of ................................................ authorised to sign for and on behalf of
.......................................................
Date: ....................................................................... Telephone No.: .........................................
Address: ............................................................................................................................................................
............................................................................................................................................................
............................................................................................................................................................
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
LETTER OF ACCEPTANCE
CRS6/SF1 contd
CRS 6.3.3
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 6.4 DECLINE OF UNSUCCESSFUL TENDERS (This section duplicates
CST 6.4)
It isadvisable to notify the successful tenderer of the intention to
accept their offer before sending decline lettersto unsuccessful
tenderers. Following confirmation from the successful tenderer, decline
lettersshould be sent immediately to all unsuccessful tenderers.
Standard Form CRS6/SF2 isan example decline letter. To an extent the
wording of the letter will be determined by the type of procurement
affected and what issueswere subsumed within the evaluation.
There are two principal reasonsfor responding asfully aspossible:
it givescontractorsconfidence in the process;
it givescontractorsmarket information which helpsto encourage
competitive market performance.
DECLINE OF UNSUCCESSFUL TENDERS
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
CRS 6.4.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
STANDARD FORM 2 - LETTER
Model Letter of Decline
Dear Sirs
[TITLE O F PRO JECT/CO MMISSIO N]
.......................................................................................................................................................... .....................................................
Your tender for the above mentioned project/commission hasbeen evaluated but I must
inform you that you were not successful on thisoccasion. The successful tenderer was
..................................................................................................................................................................................................................
Thiswasthe successful tenderer because
.................................................................................................................................................................................................................
I would like to take thisopportunity to thank you for your considerable effortsin
submitting a tender and for your interest.
Yoursfaithfully
DECLINE OF UNSUCCESSFUL TENDERS
AWARDING CONTRACTS & DECLINING TENDERS
CRS6/SF2
CONTRACTORS
CRS 6.4.2
HOME
GACC
EDITION 2: FEB 1998
EXECUTION OF FORMAL AGREEMENT
CONTRACTORS
AWARDING CONTRACTS & DECLINING TENDERS
CRS 6.5 EXECUTION OF FORMAL AGREEMENT (THIS SECTION
DUPLICATES CST 6.5)
Although the posting of the letter of acceptance should result in the
formation of a legally binding contract, it isessential that for the
avoidance of doubt two setsof contract documentsare properly
executed by both parties.
There ought to be no reason why thiscannot be done at the time of
acceptance, such contract documentsshould be prepared in
anticipation of thisevent. It ishowever essential that the contract
documentsare signed before commencement of any work by the
contractor. The scope for negotiation, if any isstill required, is
significantly reduced after thistime.
CRS 6.5
HOME
GACC
EDITION 2: FEB 1998
REQUESTS FOR DEBRIEFING
CONTRACTORS
DEBRIEFING
CRS 7.0 DEBRIEFING
CRS 7.1 REQUESTS FOR DEBRIEFING (This section duplicates CST 7.1)
Debriefing isthe only way in which unsuccessful tenderersare able to
find out why they were not selected, and therefore to obtain
information about areaswhere they need to improve their future
performance. Thispositive feedback encouragescompetitive
performance and istherefore recognised asbest practice.
CUP Guidance Note No.45 providesuseful guidance on debriefing.
O n receipt of a decline letter either at interview stage or tender stage
a contractor may request more information regarding their
performance, so that they may:
addressparticular problems;
improve competitivenessof future bids.
A letter requesting further information should be answered with a
letter offering the tenderer the opportunity for a formal debriefing
interview.
Where the EC procurement rulesapply then a request for debriefing
must be responded to within 15 daysof receipt of the request.
Dealing with a Telephone Call
A contractor who hasreceived a decline letter islikely to make a
telephone call to the Department.
Thisshould be handled with care. It isrecommended that the following
conventionsbe observed:
do not discussthe performance of other tenderers; bear in mind
that the solutionsand price offered by other contractorsare
confidential;
offer a confirmation of the pointsmade in the decline letter;
confine the information given to mattersthat would be covered in a
debriefing interview;
keep a record of the conversation.
CRS 6.4

EPP 1.14

CRS 7.2

CRS 7.1
HOME
GACC
EDITION 2: FEB 1998
DEBRIEFING INTERVIEWS
CONTRACTORS
DEBRIEFING
CRS 7.2 DEBRIEFING INTERVIEWS (This section duplicates CST 7.2)
If unsuccessful tenderersrequest a debriefing interview, thisshould be
agreed to if possible. Any such interview should be undertaken assoon
after the contract/commission award date aspracticable, generally
between three to six weeks.
Debriefing interviewsfor commissionsare conducted by the
commission manager/project sponsor but debriefing interviewsfor
contractsmay be conducted by the consultant who invited and
subsequently evaluated the tenders.
Valuable time and money isspent in debriefing, but should alwaysbe
considered worthwhile on large contracts/commissionsasthere are
certain long term benefits. These are:
to establish a reputation in the market place asa strictly fair, honest
and ethical client, which will encourage the best firmsto submit
their best offer first time around;
to offer unsuccessful tendererssome return for the time and money
expended in preparing their tenders;
to assist firmsto improve their performance.
Interview Format
The agenda for the interview will be dependent upon the individual
commission/contract but generally the person conducting the interview
should be accompanied by at least one other person and an agenda
agreed between them prior to the meeting. If possible the agenda
should follow the evaluation criteria set out prior to receipt of tenders
and where applicable, listed in the EC/O fficial Journal advertisement.
The meeting should allow sufficient time for the unsuccessful tenderer
to be told the reasonsfor failure in thisinstance and for the firm to ask
any questionsthat they feel are relevant.
The interviewersshould be aware that the reason for the interview is
diplomatically to convey to the tenderer weaknessesand strengths
within cost, schedule, design, delivery, experience etc. It must be made
clear that only the unsuccessful tender will be discussed and not a
comparison with the other tenderersor competitors.
Formal minutesare not distributed following the meeting but it is
recommended that a copy of notestaken at the meeting should be
kept on the commission file for future reference by the Department.
CRS 7.2
HOME
GACC
EDITION 2: FEB 1998
CRS 8.0 NOMINATION OF SUB-CONTRACTORS
CRS 8.1 NOMINATION PROCEDURES
General
Nomination iswidely used in the construction industry for the
appointment on major workscontracts, of specialist contractors, such
aspiling, earthworksand mechanical and electrical services.
Departmentswho wish to secure the work of a particular specialist as
part of the overall workscontract can do so by nominating such a
contractor. It can be used for both the provision of services( sub-
contractors) and for plant and materials. It generally requiresthe
inclusion of specific sums( Prime Cost or Provisional Sums) in contracts
to be expended only on the nomination of a sub-contractor or supplier.
GC/Works/1 ( 1998) makesprovision for nomination at Clause 63 for
example.
The problem with nomination, particularly under JCT contracts, isthat
it createsa transfer of risk back to the Department particularly for
delay on the part of the nominated sub-contractor. Thusdepending on
the choice of contract strategy, experienced Departmentsoperate on
the basisthat wherever possible, worksshould be asfully pre-planned
and designed aspossible. A fully pre-planned and designed project will
obviate the need to:
include Prime Cost ( PC) itemsin respect of work to be executed or
materialssupplied by specialistsor others;
include Provisional Sums( both defined and undefined) for work
which may or may not be required to be carried out by the main
contractor;
enter into direct contractsfor servicesor materialswhich may
interfere with the main contractorscontrol of the contract.
NOMINATION PROCEDURES
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
CRS 8.1.1
HOME
GACC
EDITION 2: FEB 1998
NOMINATION PROCEDURES
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
Nominated Sub-Contractors
If a contractor hasnot got the resourcesto undertake such worksor
serviceswithin itsown organisation, the main contractor should be
permitted, wherever possible, to enter into sub-contracts, subject to
Departmental approval, with firmsof itsown choice. O n the other
hand, should the Department require a sub-contractor to undertake
works, outside the expertise of the main contractor, it isrecommended
that they appoint such a sub-contractor through the nomination
process. Thismeansthat the main contractor takeson the
sub-contractor, making the main contractor fully responsible for its
performance and default.
Key Points
PC sumsare included in a contract to cover the nomination of
specialist contractors.
Ideally, the need for PC and provisional sumsshould be avoided
through the development of full design, although thiswill clearly
depend on other objectivesand the chosen contract strategy.
CRS 8.1.2
HOME
GACC
EDITION 2: FEB 1998
CRS 8.2 PRIME COSTS
General
For specialist work which cannot be described in the specification or
BQ asa priceable item, the estimated value may be included asa PC
sum and the work and/or supply involved isundertaken by a
nominated or named sub-contractor/supplier. The agreed sum for the
contract isthen subject to appropriate adjustment on nomination. The
main contractor isentitled to payment for attendance on the sub-
contract and for itsprofit in accordance with the ratesincluded in the
BQ sor Schedule of Rates.
Inclusion of PC Items in Contract Documentation
PC sumsare not appropriate for non-lump sum contractssince their
purpose isto achieve a fully inclusive fixed price for the Worksat
tender stage by allowing the main contractor to quote a price or
percentage addition for profit and providing attendance. PC sumsare
used in the following documentation:
BiIIs of Quantities - - - - - billed following the last work section in each
measured bill and forming a separate section to each measured bill;
Lunp 5un Contracts Witbout BQs - - - - - detailed asa Summary
of Prime Cost and Provisional Sumswhich can be associated with
the tender form and make clear that the tender figure isintended to
include all prime cost sums( including profit thereon) and provisional
sums.
Removal of PC Sums
Departmentsshould be careful over the decision to include PC sums
since their removal once the contract hasbeen let may cause nugatory
expenditure.
PRIME COSTS
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
L
! !! !!
CRS 8.2
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
ARRANGING NOMINATED SUB-CONTRACT
CRS 8.3 ARRANGING A NOMINATED SUB-CONTRACT
When a PC Sum is Included
In general, specialist work should be invited concurrently with the
tendersfor the main contract, so that nomination of the preferred sub-
contractor may be made assoon asthe main contract islet.
Late nomination isa major contributor to delay and disruption to
project completion and consequent claims, it should therefore be
avoided.
If the specialist work isnot required until later in the contract period it
may be easier for the main contractor to appoint the sub-contractor
provided thisisagreed prior to the formation of the main contract. This
will prevent the main contractor seeking additional costsfor delay and
disruption due to programming difficulties. It may also be prudent to
delay inviting main contract tender until tender nominationsfor
nominated sub-contract are ready. Thisallowsco-ordination between
both and reducesthe risk of delay and disruption which may otherwise
occur.
Invitation of Nominated Sub-Contracts Well in Advance of a
Main Contract
O n occasion nomination and appointment of sub-contractswell in
advance of the invitation of the main contract tendersmay be required.
Thismay be necessary because the design of the main project cannot
be completed until:
a sub-contractor isknown;
because an item like a special boiler will take many monthsto
manufacture;
because the sub-contract includespreliminary work such asdesign
and/or fabrication of materials( e.g., structural steel) .
In exceptional circumstancesit isnecessary to invite tenderswell in
advance of the main contract, where it should be made clear in the
invitation that the work isto be the subject of a sub-contract to a main
contractor not yet appointed.
L
! !! !!
CRS 8.3.1
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
ARRANGING NOMINATED SUB-CONTRACT
The tender documentsin thiscase should state:
the responsibilitiesof the main contractor;
the anticipated form of main contract e.g. GC/Works/1 ( 1998) ;
contract particularssuch ascontract period, start date and level of
liquidated damagesetc.
Main Contractors Responsibilities for Sub-Contractors Design
The Department should ensure that the specification for the main
contract containsan appropriate description of the scope and nature of
the work to which the PC sum relates. Equally the sub-contract
specification should be clear and consistent with the above, in order
that the main contractor will be able to seek redressfrom the
sub-contractor in the event of failure of the sub-contractorsdesign
( not through the Department) .
Specialist Design
Exceptionally, the design element may be such that neither the main
contractor nor the design team leader hasthe expertise to undertake
the specialist design proposals( e.g., novel or innovative proposals) . In
such casesa separate design contract can be arranged directly with the
specialist ( wherever possible in competition) with an understanding
that, subject to a satisfactory lump sum, the successful specialist will be
nominated asa sub-contractor to the main contractor.
Warranties
It isrecommended that where nomination isenvisaged that the main
contractor becomesliable for the design liability of the nominated sub-
contractors. Accordingly, any direct design warrantiessuggested by the
main contractor between the sub-contractor and the Department
would only serve to obscure the main-contractorsdesign liability.
It isto be noted that thisisnot the approach adopted in the JCT forms
of contract, where liability for the design of nominated sub-contract
workswill bypassthe main contractor, unlessalternative arrangements
are made.
L
! !! !!
CRS 8.3.2
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
ARRANGING NOMINATED SUB-CONTRACT
Where the design responsibility of the specialist sub-contractor formsa
major part of the total cost of the project, consideration can be given
to appointing the specialist contractor asthe main contractor.
Key Points
Depending on circumstancesit isrecommended that the
specification and requirementsof any nominated sub-contractors
are developed concurrently with the main contract specification and
drawingssuch that conditionsimposed on nominated sub-
contractorsand the main contractorsare consistent.
Late nomination can cause seriousdelaysto a worksproject.
L
! !! !!
CRS 8.3.3
HOME
GACC
EDITION 2: FEB 1998
CRS 8.4 ESTABLISHING A CONTRACT
General
It isrecommended that where the Department choosesto nominate,
the main contractor should enter into a sub-contract with the
nominated sub-contractor without delay.
Problems with Establishing a Contract
In certain circumstancesthe main contractor and the proposed
nominated sub-contractor may not reach agreement. The most
common causesof failure to agree between main and sub-contractor
are:
disagreement over the programme;
the sub-contractorsreluctance to accept conditionsimposed by the
main contractor;
the main contractorsdoubtsabout the financial stability of the
nominated sub-contractor;
the main contractorsdislike of the nominated firm.
Resolution to Problems
Most problemsmay be resolved by the Department mediating
between both parties. Most conditionsof contract provide that, if the
main contractor hasvalid objectionsregarding a particular nominee
that another firm should be nominated or that the main contractor is
permitted to execute the work or appoint itsown sub-contractor, as
appropriate. The Department may be liable for any increase in price
but thiswill depend on the termsof the main contract.
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
ESTABLISHING A CONTRACT
L
! !! !!
CRS 8.4
HOME
GACC
EDITION 2: FEB 1998
CRS 8.5 LIQUIDATION OF A NOMINATED SUB-CONTRACTOR
O nce the contract ismade between the main and sub-contractor, it
should be clear in the main contract conditionsthat the main
contractor isfully responsible for the work including all design.
Employer/sub-contractor agreementsprovided for under JCT 80 forms
give the employersdirect redressagainst the sub-contractor in certain
circumstances, e.g. design liability. These agreementsare not used in GC
formssince they may affect the contractual relationship between the
main contractor and sub-contractor.
Under the GC forms, the contractor assumesresponsibility for any
nominated sub-contractorsand if the sub-contract isterminated due to
the liquidation or bankruptcy of the sub-contractor then the main
contractor may be required to find other meansof completing the
work. The Department carriesthe risk of any extra cost of securing a
replacement.
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
LIQUIDATION OF A NOMINATED SUB-CONTRACTOR
CRS 8.5
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
NOMINATION OF SUB-CONTRACTORS
SELECTED OR APPROVED SUB-CONTRACTORS
CRS 8.6 SELECTED OR APPROVED SUB-CONTRACTORS
Nomination and Naming
For a sub-contractor to be contractuallynominated itsselection must
be the subject of a PC sum. Sub-contractorswho may be approved by
the architect or engineer, under other provisionsof the contract ( e.g.
listing or naming) are effectively domestic sub-contractors.
It isrecommended that listing isnot used unlessthe specialist firm is
willing to take on the work asa domestic sub-contractor. The reason is
that if difficultiesoccur in establishing the sub-contract many of the
problemsand delaysassociated with formal nomination can arise.
O nce the Department hasaccepted the domestic arrangementsof the
main contract they cannot later choose to nominate formally.
The practice should be to use selected or approved
sub-contractor listscarefully and not to treat them asan easy way of
nominating by the back-door.
CRS 8.6
HOME
GACC
EDITION 2: FEB 1998
CRS 9.0 MANAGEMENT OF CONTRACTS
CRS 9.1 ROLE OF THE PROJECT MANAGER
General
The project manager isusually appointed on major workscontractsto
manage the contract from design and construction through to
completion. The appointment of a project manager should not be an
automatic decision, for instance it isunlikely that a project manager is
required for maintenance works.
The Department will normally appoint a project manager at the
feasibility stagesof a Project. The project managersdutiesinclude acting
on behalf of the Department and advising them on the procurement of
design resources, on estimatesof costsand time, on the meritsof
alternative schemesand on choosing the most appropriate contract
strategy.
Project Manager Appointed for the Duration of the Project
Ascontractsare placed for construction work, it ispreferable to
appoint the person or organisation already appointed for the whole
project to act asthe project manager on a particular contract.
However, it isessential that the project manager for a particular
contract issufficiently close to the work and hasthe time to carry out
hisor her dutieseffectively. O n very large projects, especially where
there are several contractsto be placed, it may be necessary to appoint
a different project manager for each contract or for the project
manager to delegate responsibilitiesfor some of the contracts.
O n certain contractse.g. GC/Works/1 ( 1998) the project manager may
take on the role of the lead consultant.
CONTRACTORS
MANAGEMENT OF CONTRACTS
ROLE OF THE PROJECT MANAGER
PS 3.1

CST 1.4

CRS 9.1.1
HOME
GACC
EDITION 2: FEB 1998
Project Managers Responsibilities
Clearlythe project manager will have important obligationsunder the
contract entered into between the Department and the contractor.
Where other dutiesare considered to exist they must be stated clearly
and without ambiguity to avoid disputes.
Throughout each of the stagesit should be stated that it isthe project
manager who isresponsible for the overall successof the project
including responsibility for the Departmentsteam and ensuring each
consultant performsin a manner which will bring about the success
required.
Design Co-ordination
The project managersrole includesthe important one of design co-
ordination, and to keep the Department properly and fully informed
throughout each stage.
EmployersAgent
At the construction stage it must be remembered that the project
manager will have obligationsunder the contract asthe Employers
Agent, i.e. issue of certificates, instructionsetc.
Claims and Disputes
With respect to contractual claimsthe project manager must be seen
to be impartial and act independently.
If the Department findsitself locked in a dispute going all the way to a
formal hearing, the project manager islikely to be a key witnessbut he
or she will of course be a witnessasto fact and not opinion, which
would indeed be the role of an independent expert if required.
CONTRACTORS
MANAGEMENT OF CONTRACTS
ROLE OF THE PROJECT MANAGER
L
! !! !!
CRS 9.1.2
HOME
GACC
EDITION 2: FEB 1998
CRS 9.2 ROLE OF THE PROJECT SPONSOR (PS)
Where a major worksproject isbeing procured then it is
recommended that a project sponsor isappointed, and the appropriate
management structure isin place to ensure the sponsor can be an
effective representative of the Department.
The sponsor will commonly have a number of key dutiesincluding:
monitoring the performance of the project manager, and indirectly
that of the design team and contractor;
acting asthe channel for Departmental changesor information flow;
monitoring the budget and obtaining necessary financial
authorisation;
other duties.
Key Points
The project sponsor should be sufficiently empowered to make
quick and effective decisionscovering project execution; however it
should be kept in mind that the project manager isengaged to
manage and advise not to delegate responsibility back to the
Department.
CONTRACTORS
MANAGEMENT OF CONTRACTS
ROLE OF THE PROJECT SPONSOR
PS 1.5

INT 1.7

CRS 9.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 9.3 BILL PAYING
Function of the Quantity Surveyor (QS)
O nly under some of the Government contractsformsisthere a specific
role for a Q S but it will be usual to appoint a Q S where the work
requiresregular measurement and/or valuation. It will ordinarily be the
function of the Q S to prepare interim valuationsin accordance with
the contract and such valuationswill be submitted to the project
manager for approval.
Gross Valuation
O nce the project manager issatisfied asto the valuation of the sums
due he or she should inform the main contractor of the amount to be
certified for payment. The grossvaluation iscalculated asthe sum of
work executed, the value of materialson site, the value of any
variationsand the grossamount of VAT. Where nominated sub-
contractorsare present the grossvaluation shall normally include the
value of work undertaken by the sub-contractor, exclusive of VAT.
Advanced Payment
In certain circumstancesthe Department may consider it appropriate
to pay advanceson account for goodsand materialsto be
incorporated into the works. Thismay be reasonable when the goods
and materialshave been brought on site and are adequately stored and
protected. In exceptional circumstancesadvance payment for materials
held off-site may be appropriate, e.g. where materialscannot be
brought on site asprogrammed possibly due to a failing on the part of
the Department. The purpose of such advance payment isto protect
the Department against claimsfor lossand/or expense due to delay
and disruption The payment for materialsoff-site raisesquestionsof
ownership and may expose the Department to further financial risk.
It istherefore recommended that clear professional advice issought
regarding such action.
Key Point
The Construction Industry Tax Scheme requiresthat any firm must be
in possession of a valid registration card or tax certificate before any
paymentsare made.
CONTRACTORS
MANAGEMENT OF CONTRACTS
BILL PAYING
LE 1.19

LE 1.19

L
! !! !!
CRS 9.3
LE 2.11

HOME
GACC
EDITION 2: FEB 1998
CRS 9.4 CHECKING PROCEDURES
Cost Control
The project manager will usually be responsible for maintaining control
of the costsfor the contract within hisdelegated limits, and should
report regularly to the project sponsor, using a suitable commitment
and forecasting record system.
The system should show a running record of expenditure through
variation orderswhich can be readily checked against the project
managersfinancial delegation. It should also record the letting of
nominated sub-contractsand the expenditure of provisional sums.
These recordsshould be brought together to show, month by month,
fundscommitted and those yet uncommitted. Thiscan be readily
compared with the physical progressof the project.
Limits on the Project Managers Authority
It isrecommended that the project managersauthority to commit
money beyond the contract sum islimited asfollows:
to the limit of contingenciesand daywork provision; and
to a maximum limit on individual variations.
Financial Reporting
The Q S should be required to submit to the project manager a
monthly financial report showing current and future commitment. From
thisinformation the project manager will update and summarise the
financial position.
Each month the project manager should send to the project sponsor a
statement of the financial position of the work.
CONTRACTORS
MANAGEMENT OF CONTRACTS
CHECKING PROCEDURES
CRS 9.4
HOME
GACC
EDITION 2: FEB 1998
CRS 9.5 DETERMINATION PROCEDURES
General
Failure by the contractor to carry out hisor her obligationsunder the
contract, isgroundsunder most contractsfor the Department to
determine the contract. Furthermore some Government formsof
contract often give the Department discretionary powersto determine
the contract at any time by notice to the contractor.
Default Notices
Great care should be taken in producing noticesof default, warning
lettersand noticesof determination to ensure that the Departments
rightsunder the contract are not prejudiced in any way by the termsof
the letter. It isrecommended that the wording of the condition under
which any letter or notice isissued should be reflected exactly in the
letter of notice.
Default Procedure
The following isa recommended procedure for dealing with default,
but any specific requirementsof the contract must be adhered to:
assoon asthe project manager isconvinced that normal day to day
communicationswith the contractor isnot achieving the desired
improvement/remedial action the project manager should issue a
Notice of Default. The notice should specify not only the defective
work, or work which isbeing improperly performed but also any
remedial measuresrequired;
if the project manager considersthe contractor isstill in default
seven daysafter the receipt of the Notice of Default, he or she
should discusswith the Department and, if instructed, initiate action
to determine the contract;
in the event that the contractor hassuspended the works, or, in the
project managersopinion, the contractorsprogressissuch that the
contract will not be completed by the date for completion of the
contract, or the project manager experiencesdifficulty in obtaining
the contractorsfull compliance with the requirementsof the
contract, he or she should report the position to the Department
and recommend the issue of a Formal Final Warning Letter or
Notice of Determination;
CONTRACTORS
MANAGEMENT OF CONTRACTS
DETERMINATION PROCEDURES
LE 1.4

L
! !! !!
CRS 9.5.1
HOME
GACC
EDITION 2: FEB 1998
if a satisfactory response hasnot been received from the contractor
within seven daysof the receipt of the warning, the project manager
should immediately take action to determine the contract;
once the decision istaken to determine the contract the quantity
surveyor should be advised of the effective date of determination in
order that a certificate may be prepared on the statusand valuation
of the workson the day of determination and for instructionsto be
issued to cover the security of the site on and after the day of
determination.
Completion of the Works in Case of Default
The following procedure isrecommended on determination:
upon determination of a contract due to default, arrangements
should be made for the work to be completed by another
contractor, any additional cost being claimed from the original
contractor, or deducted from sumsdue to him;
the project manager should recommend assoon aspossible to the
Department hisor her proposalsfor completing outstanding work
on the contract; whatever the course recommended, it isessential
that excesscostsover the balance of the contract price should be
avoided or, if unavoidable, kept to an absolute minimum consistent
with obtaining a satisfactory completion of the works;
any contract to complete the worksmust be placed without delay
and be based, asfar aspossible, on the same specification and
conditionsasthe original contract;
any additional cost incurred asa result of determination may not be
recoverable from the original contractor if they could reasonably
have been mitigated by prompt or decisive action, on the part of
the department.
Key Points
Seek advice before proceeding.
Where there are contractual provisionswhich entitle the
Department to determine the contract, and there isoccasion to
operate them, the provisionsin question should be followed to the
letter.
CONTRACTORS
MANAGEMENT OF CONTRACTS
DETERMINATION PROCEDURES
L
! !! !!
CRS 9.5.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CONTRACTORS
CLAIMS AND DISPUTES
GENERAL
CRS 10.0 CLAIMS AND DISPUTES
CRS 10.1 GENERAL
Claimsinclude all mattersfrom a routine request for additional time to
complete, to a major allegation of breach of contract. In fact a claim is
simply a demand by one party on the other that a particular
entitlement isdue. Not all claimssignify a dispute. But where a claim is
not met in full and there isdisagreement by one party asto the
entitlement of the other then unlessagreement can be reached
through negotiation, it can be said that a dispute or difference has
arisen between the parties.
The majority of claimsarise from a failure or an alleged failure of one
party to fully comply with the requirementsof the contract or in some
instancesconditionsimplied by the common law. The remedy sought
for an alleged breach isusually damages.
Claimsgenerally fall into the categorieslisted below ( examplesare
given of each) :
Contractual Claims (specific entitlement in accordance with the
terms of the contract):
for delay/additional time for specified reasonssuch as:
- issue of variationsexpanding the scope of the contract,
- late issue of information and/or variations;
for the additional cost of variations;
for disruption or lost productivity due to interference by the
Department;
Common Law Claims (ex-contractual claims):
damagesfor breach of contract;
damagesin tort/delict ( e.g. negligence - breach of a duty of care) ;
damagesfor breach of copyright;
LE 1.7

LE 1.8

CRS 10.1.1
HOME
GACC
EDITION 2 REV 2: JAN 2000
CONTRACTORS
CLAIMS AND DISPUTES
GENERAL
Third Party Claims:
personal injury claims;
employee claims;
land compensation claims;
Quantum Meruit Claims:
Ex Gratia Claims (out of kindness).
From the Departmentsviewpoint claimsshould be avoided if only
because financial control becomesextremely difficult, especially for
claimsproduced long after the event.
In practice it isdifficult to avoid claims, but it ispossible to deal with
them intelligently and expeditiously so asto avoid disputes.
Key Points
A claim ismore often than not an expression of the additional
entitlement of a party specifically provided for under the termsof
the contract for specified matters.
The better the Departmentsrecords, the better itsability to make
and defend claimsand to negotiate them.
The legal principlesinvolved in making or defending claimscan be
complex and the preparation of a good claim document isan art.
If in any doubt seek professional advice.
LE 1.8

CRS 10.8

CRS 10.3

L
! !! !!
CRS 10.1.2
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
CLAIMS AND DISPUTES
CONTRACT CLAIMS AGAINST THE DEPARTMENT
CRS 10.2 CONTRACT CLAIMS AGAINST THE DEPARTMENT
Claimsoften involve dealing with partiesperceptions, which although
often held very strongly are not alwayssupportable. The manner and
the speed in which claimsare dealt with can, and in most casesdo,
have a major bearing on the eventual outcome of the claim.
Damages
The remedy for a breach of contract which hasnot been excused is
damages. Damagesare awarded to put the innocent party, asnearly as
possible, into the position that party would have been in had the
contract been performed. There are well established criteria for the
determination of the amount of damagesat common law, but these
must be considered in light of what the expresstermsof the contract
have to say about recovery.
Problems with Quantification and Evaluation of Claims
The difficulty with many claimsarising out of construction contractsare
that they are often very difficult to evaluate, and are seldom clear cut.
These difficultiesare asfollows:
construction projectsare frequently very complex involving the
interaction of many tradesthereby often making it very difficult to
determine the connection between an alleged breach of contract
( cause) and the losssuffered by the injured party asa result ( effect) ;
claimsin construction projectsoften arise out of claimsfor
extensionsof time; without the use of up to date computerised
planning/network packages, the determination of the Critical Path
through a particular project, itself a dynamic entity, can be near
impossible;
the area of construction law isextremely specialised; further, statute
and case law isconstantly being updated and the boundaries
redefined; it isrecommended professional advice issought when
considering how the termsof the contract should be interpreted in
the event of a dispute, and in considering the Departmentsliability;
LE 1.8

CRS 10.2.1
HOME
GACC
EDITION 2: FEB 1998
even with professional advice there can and often are grey or
indefinable areaswithin a particular claim, but clearly it isin the
Departmentsintereststo narrow down the issuesand determine
the validity or otherwise of a particular claim asquickly aspossible
so that it can properly consider/advise on:
- -- -- budgets: their accuracy/likely overspend,
- -- -- estimated time of completion of the project,
- -- -- legal action it needsto take or prepare for,
- -- -- negotiation of claimsleading to settlement; it isthe party who is
armed asfully aspossible with the factswho islikely to bring
about or induce a negotiated settlement.
Key Points
Construction workscontract claimstend to be complex and may
include headsof claim which are difficult to prove or evaluate.
Seek professional advice.
CONTRACTORS
CLAIMS AND DISPUTES
CONTRACT CLAIMS AGAINST THE DEPARTMENT
L
! !! !!
CRS 10.2.2
HOME
GACC
EDITION 2: FEB 1998
CRS 10.3 AVOIDANCE OF CLAIMS
The main source of claimsunder the contract are:
discrepanciesbetween drawings, schedulesand billsof quantities;
late submission of information;
variationsand their valuation;
poor communication or attitude on the part of membersof the
construction team;
the contractor discovering, towardsthe end of the job, that it has
lost money through mis-management or otherwise.
Throughout the duration of the project it isconstantly necessary to
hold meetings, monitor progressand budgetsetc. so that assoon asa
problem or potential problem arisesit can be dealt with in the most
expedient manner. O f course it dependson the nature and size of the
project being worked upon, but in the vast majority of casesthe same
holdstrue for dealing with contractual claims. Resourcesexpended up
front in ensuring the brief isproperly delivered, contractual rolesand
obligationsclearly set out, the contractual arrangementsentered into
properly reflect the agreement required, including the contract strategy
adopted, etc., can only help to ensure that the risk of contractual claims
isreduced and/or minimised.
Key Points
In practice it isdifficult to avoid claimsbut the early identification
and prompt resolution of problemsthrough good management will
do much to prevent or control the risk of claims.
CONTRACTORS
CLAIMS AND DISPUTES
AVOIDANCE OF CLAIMS
CRS 10.3
HOME
GACC
EDITION 2: FEB 1998
CRS 10.4 MANAGING CLAIMS
The main stepsto be followed in order to manage claimsare:
ensure that the brief iswell defined and contractual requirements
are consistent;
ensure that the contractor hasthe information required, preferably
before it isrequired;
avoid variations;
where variationsare required, agree time and cost increasesprior
to instruction or assoon aspossible thereafter;
keep good recordsof all eventswhich may lead to a claim;
insist on compliance with the contract where contractual claimsare
being made and evaluate them asquickly aspossible;
negotiate with the contractor.
O nce a claim hasbeen received a report ( with privilege status) should
be drafted to include the following:
detailsof the claim and why there isa dispute;
an assessment of the extent of liability;
include negotiating proposals;
give an assessment of the likely outcome in financial terms.
CONTRACTORS
CLAIMS AND DISPUTES
MANAGING CLAIMS
CRS 10.4
HOME
GACC
EDITION 2: FEB 1998
CRS 10.5 PRESENTATION OF CLAIMS
The degree and type of evidence required to establish monetary claims
arising under a building contract will generally be a matter safely left in
the handsof the professional advisersacting for a Department. But
some important general principalsare asfollows:
there must be a basisfor the claim in law, either under the contract
or otherwise;
there must be some losswhich arisesby reason of the legal right to
claim;
the connection between the legal right and the damagessought
must asfar aspossible be proven by the party claiming the damages;
the mattersin dispute should be set down on paper assoon as
possible and communicated in a cogent and persuasive manner;
if in receipt of a claim, evaluate it, determine the value of any
counter-claim the Department may wish to make and make a
realistic offer assoon aspossible.
Key Points
Claimsonce established by the contractor should be promptly
settled or at least paid to the extent of the Departmentsliability
that can be evaluated.
O fficerswill not normally have any authority to deal with ex-
contractual claims, and should consult their Departmental
handbooksin thisrespect.
CONTRACTORS
CLAIMS AND DISPUTES
PRESENTATION OF CLAIMS
L
! !! !!
CRS 10.5
HOME
GACC
EDITION 2: FEB 1998
CRS 10.6 CLAIMS AGAINST CONTRACTORS
General
The principal claim which a Department islikely to make isone for the
costsof delay by the contractor. Where liquidated damagesprovisions
exist in the contract, then the recovery of such costsiscovered by the
deduction of LADs. Where there are no LAD provisionsand the
contractor isin breach of contract, for example because of delay or
defective workmanship, then the Department may wish to make a
claim provided it can show that it hassuffered lossasa result of the
breach or breaches. Claimsare best dealt with by the architect,
superintending officer or project manager on behalf of the Department
since they should be familiar with the background to the claims. If the
claim isa complex one then it may pay dividendsto seek legal advice
to prepared a high quality claim at the outset.
Loss and Damages
O nce the alleged breach hasbeen confirmed by the Department it is
prudent to issue a notice of default to the contractor explaining that a
claim isbeing considered. It isrecommended that assoon asa breach
of contract hasbeen confirmed, the Department should calculate the
additional cost and losssuffered asa result of the contractorsbreach.
Potential lossesor damagesmay occur at a later date in which case
these losseswould be considered speculative since the contractor may
be able to limit itsliability by mitigating the extent of any future loss. It
isrecommended that any such future lossisperiodically notified to the
contractor asit occurs.
Insurance
If the breach alleged isthe kind of liability which should be covered by
the contractorsstandard policy of insurance, then the insurer may
become involved.
CONTRACTORS
CLAIMS AND DISPUTES
CLAIMS AGAINST CONTRACTORS
CRS 11.1

L
! !! !!
CRS 10.6.1
HOME
GACC
EDITION 2: FEB 1998
Procedure
Assoon asit becomesreasonably apparent that a claim against the
contractor islikely, the Department should put in place adequate
proceduresto compile evidence which can be used to support the
claim. The following are recommended proceduresfor dealing with
damaged or defective work:
inspect the damage, take any necessary photographsand record the
detailsin the site diary;
arrange a meeting on the site with the contractor to establish what
isagreed or disagreed asto fact and pressfor a written acceptance
of liability to either indemnify, reinstate, make good or compensate
with regard to the damage;
if the contractor assertsthat the damage wasnot due to itsneglect
or default then request itscase in writing;
in the event that the contractor admitsliability the PM or
superintending officer must ensure that the remedial worksare put
in hand; any resultant delay in the programme may give rise to the
Departmentsright to deduct liquidated damages( where
appropriate) ;
if a contractor hasacknowledged liability or where there isa strong
case against them ( but they deny liability) , should they delay in
carrying out remedial work, the department should consider having
the work undertaken by an alternative contractor at the original
contractorscost.
Dispute Resolution
Where the contractor formally disputesitsresponsibility to make good
or compensate damage the aim must be to resolve the argument by
negotiation, rather than resorting to arbitration or litigation. But a legal
opinion isgenerally necessary at an early stage, and protracted
negotiation should be avoided.
In the event that the contractor iscausing problemson a contract, a
full report should be sent to NQ S so that other possible usersof the
contractor are alerted.
CONTRACTORS
CLAIMS AND DISPUTES
CLAIMS AGAINST CONTRACTORS
CRS 12.2

CRS 10.6.2
HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 10.7 ARBITRATION
For arbitration to be an option there must be a written agreement in
the contract to arbitrate ( an arbitration clause) ; or there may be
subsequent written agreement to arbitrate.
The Government workscontractsgenerally include contractual
provisionsfor resolution of disputesby arbitration after completion,
abandonment of the works, or determination ( for example see
Condition 60 of GC/Works/1 ( 1998) ) . Thisamountsto a written
agreement to arbitrate. Where there issuch an agreement, arbitration
isa pre-condition to litigation.
The advantagesof arbitration are asfollows:
the partiesmay choose the arbitrator ( tribunal) ;
confidentiality - arbitration isprivate;
should be faster;
flexibility - partiesmay agree to relax procedural rulesor rulesof
evidence;
the partiesdo not have to be represented by counsel;
limited appeals;
no reliance on Rulesof Court.
The conditionsof contract usually set out the procedure to be adopted
for the arbitration however, the partiesare free to agree on their own
procedures.
O nce an arbitration notice hasbeen issued by either party, failure to
respond may be a breach of contract.
Asan alternative to arbitration, it may be possible to agree with the
contractor to attempt a method of alternative dispute resolution. If
successful thiscan be a cheaper and quicker method of resolution.
All the GC/Works/1 contractsinclude an adjudication clause which
providesfor an independent adjudicator to find on disputeswhich
occur during the progressof the works. The adjudicatorsdecision is
binding until the completion, abandonment of the worksor
determination.
CONTRACTORS
CLAIMS AND DISPUTES
ARBITRATION
CST 9.3

CRS 10.7.1
LE 2.9

HOME
GACC
EDITION 2 REV 2: JAN 2000
CONTRACTORS
CLAIMS AND DISPUTES
ARBITRATION
Key Points
Part II of the Housing Grants, Construction and Regeneration Act
1996 requiresthat a party to any construction contract hasa right
to refer any dispute for impartial adjudication. Any such adjudication
must be effected within a certain timescale.
Arbitration isa meansof dispute resolution by the decision of a
third party.
The service of a notice of arbitration may be a very effective means
of encouraging settlement, however, it isnot a step that should be
taken lightly. There must be a case to argue, and there must be a
reasonable prospect of success.
Seek professional advice before issuing a notice of arbitration or
upon receipt of one.
It should be cheaper and lesstime consuming to attempt to settle
the dispute either through settlement negotiationsor ADR.
L
! !! !!
CRS 10.7.2
LE 2.9

HOME
GACC
EDITION 2 REV 2: JAN 2000
CRS 10.8 EX GRATIA CLAIMS (THIS SECTION DUPLICATES CST 9.6)
These claimsusually arise where the claimant hasno grounds( other
than possibly moral grounds) for additional costs.
Ex-gratia paymentsare generally made in exceptional circumstances
and with the agreement of the finance section of the department.
CONTRACTORS
CLAIMS AND DISPUTES
EX GRATIA CLAIMS
CRS 10.8
HOME
GACC
EDITION 2: FEB 1998
CONTRACTORS
MATTERS ARISING ON COMPLETION
LIQUIDATED AND ASCERTAINED DAMAGES
CRS 11 MATTERS ARISING ON COMPLETION
CRS 11.1 LIQUIDATED AND ASCERTAINED DAMAGES
General
Liquidated and Ascertained Damages( LADs) are contractual damages
which do not have to be proved and they are independent of the
actual losssuffered by the Department due to the contractorsfailure
to complete the worksby the contract completion date.
Quantum of Damages
Damagesare levied at the rate set out in the contract by the period of
the delay ( i.e. the period between certified completion and the
extended date for completion) . The damagesmay be deducted from
any amountsdue to the contractor, or the sum may be claimed from
him asa debt.
Calculation of the amount due asLADsisstraightforward, requiring
merely that the rate per day or week be multiplied by the number of
daysor weeksthe work overran. Under some formsof contract e.g.,
GC/Works/1 ( 1998) , thiscalculation will be essentially a confirming one
if the employer haselected to deduct damagesfrom interim payments
after expiry of the contract period but before certifying completion.
Extensions of Time
For the Department to be entitled to deduct LADs, the superintending
officer or project manager must have properly applied the extension of
time provisions. For thisreason, the deduction of LADsoften givesrise
to disputesover extensionsof time to the contract period. Some
claimsmay be rejected in whole or in part by the superintending officer
or project manager, asnot falling within the conditionsof contract.
Some formsof contract e.g., JCT 80, GC/Works/1 ( 1998) , provide for
the review by the architect or project manager of extension of time
decisionsalready made. Review isnot about whether the Department
should waive LADs, but whether the groundsfor extra time have been
properly and reasonably evaluated.
LE 2.8

CRS 11.1.1
HOME
GACC
EDITION 2: FEB 1998
It issolely a matter for the Department ( i.e. Authority) whether LADs
will be deducted or waived, not that of the superintending officer or
project manager.
Key Points
In the event that a contractor isin culpable delay, then under many
formsof contract the Department hasa contractual right to deduct
LADs.
Contractorsare likely to respond either by claiming that an
extension of time isdue or that mattersfor which extensionswere
previously requested have not been fairly or properly considered.
Contractorsmay offer to trade off a lossand expense claim against
an LAD deduction. It isrecommended that professional advice is
sought if faced with thistype of situation.
CONTRACTORS
MATTERS ARISING ON COMPLETION
LIQUIDATED AND ASCERTAINED DAMAGES
L
! !! !!
CRS 11.1.2
HOME
GACC
EDITION 2: FEB 1998
CRS 11.2 MAINTENANCE PERIODS
General
Certain contractsprovide for a maintenance period, where the
contractor isrequired to rectify any defectsin work resulting from
improper workmanship and materialswhich may arise during the
maintenance period. The period usually commencesfrom the day after
the certified date for completion. When the contract envisages
sectional completion each maintenance period iscalculated from the
day after the certified completion date of the relevant section of the
works. The length of the period variesaccording to the work. Typical
periodsare:
building and civil engineering work - 6 months;
mechanical and electrical work - 12 months( to allow for operation
in one complete cycle of seasons) .
Main Contractors Responsibility for Specialist Sub-Contractors
Where a specialist sub-contract isinvolved in a main building contract
and it carriesa maintenance period that extendsbeyond that of the
main building contract, the main contractorsresponsibility for
maintenance of the specialist workscontinuesuntil the end of the
appropriate period stated in the Abstract of Particularsfor the specialist
works.
Payment
If on expiry of the maintenance period of the main building contract
the Architect/SO etc., issatisfied about the state of the works, he or
she certifiesthis. Each section will have itscertificate issued at the
expiry of the appropriate maintenance period. These certificatesallow
the final paymentsunder the contract to include any retention made
subject to any outstanding claims.
CONTRACTORS
MATTERS ARISING ON COMPLETION
MAINTENANCE PERIODS
CRS 11.2
HOME
GACC
EDITION 2: FEB 1998
CRS 11.3 PAYMENTS
General
It isrecommended that paymentsare made promptly at all stagesin
accordance with the termsof that contract. The timely payment of
sumswhich become due on contractscan be significant in reducing the
cost to companiesthrough financing their operations. When disputes
arise over single itemsof payment, the undisputed itemsshould be paid
immediately, leaving the disputed itemsfor later settlement.
Late Payment and Interest
Where payment isdue in respect of work it isnot reasonable to
withhold paymentsdue to a contractor on the groundsthat internal
procedure hasnot been complied with or completed. Provided that the
arrangementsmade with the contractor for valuation of the
unauthorised work are satisfactory the contractor may receive the
money due to him. Internal proceduresshould be such asto ensure
that the Departmentsobligationsunder the contract are complied
with.
Where a Department hasfailed to make payment due to the
contractor by the agreed date, or hasotherwise unreasonably withheld
a sum due to a contractor, certain Government formsprovide for the
payment of contractual interest to the contractor.
Key Points
It isGovernment policy to make prompt payment in respect of
bona fide liabilitiesespecially to small companies.
Late payment may result in the need to increase the overall budget
because of the contractorsentitlement to interest.
Departmentsshould ensure that they comply with the principlesof
prompt payment ascontained in Government Accounting and the
variousCharter initiatives.
CONTRACTORS
MATTERS ARISING ON COMPLETION
PAYMENTS
CRS 11.3
HOME
GACC
EDITION 2: FEB 1998
CRS 11.4 OVERPAYMENTS
Potential debtscan arise under the contract for overpaymentsto
contractorsby reason of excessadvances.
Overpayments - Recovery by Way of Set-off
Certain Government formsof contract provide for the recovery of
sumsdue under the contract by reason of overpayment asa set-off,
see GC/Works/1 ( 1998) , Condition 51. Condition 51 also providesfor
the recovery of sumsdue under one contract from paymentsdue to
the contractor under any other contract with any other Department.
The Department should be certain of itsright to deduct such monies
before it proceedswith such a course of action. If in doubt seek
professional advice.
Interest on Overpayments
Where overpaymentshave been made to contractorsand the debts
arising are to be discharged within a short period, interest may be
charged only where provision for the charging of interest isexpressly
included in the termsof the contract. Since there isno provision in the
GC and C seriesof contractsto claim interest for overpaymentsit
would be improper to seek to deduct such monies, under these forms.
CONTRACTORS
MATTERS ARISING ON COMPLETION
OVERPAYMENTS
L
! !! !!
CRS 11.4
HOME
GACC
EDITION 2: FEB 1998
CRS 11.5 HANDOVER
O nce the works( or any section) have been satisfactorily completed,
the project manager or supervising officer will issue a certificate after
the maintenance period to that effect.
It isrecommended that copiesof the certificate are distributed by the
project manager to the:
contractor;
quantity surveyor;
project sponsor or workscontract manager.
Effect of Certificate of Completion
Asa result of case law in 1994, the final certificate issued by the
architect under JCT80, which wasissued on the basisthat the works
were complete to the satisfaction of the architect, wasfound to have
the effect of relieving the contractor of liability for any defectsin the
work thereafter.
It wasnot the intention of the draftersof the JCT formsthat a final
certificate should have thiseffect, and asa result amendment 15 was
issued in July 1995 which redrafted Clause 30.9.1.1 to limit the effects
of the final certificate. It isnow only conclusive evidence of the fact that
only mattersexpressed in the contract documentsor instructions, as
being for the approval of the architect, were to the reasonable
satisfaction of the architect. The contractor retainsliability for all other
matters.
CONTRACTORS
MATTERS ARISING ON COMPLETION
HANDOVER
CRS 11.5.1
HOME
GACC
EDITION 2: FEB 1998
The 1998 editionsof the GC/Workscontractshave overcome this
problem asillustrated by clause 39 ( Certifying Works) which states:
The PM shall certify the date when the Works,or any Section, or any
completed part within the meaning of Condition 37 (Early Possession) are
completed in accordance with the contract. Such completion shall include
sufficient compliance by the contractor with Condition 11(7) (Statutory
Notices and CDM Regulations).After the end of the last Maintenance
Period to expire, he shall issue a certificate when the contractor has
complied with Condition 21 (Defects in Maintenance Periods).
Key Points
Care should be taken over the issue of a final certificate or
certificate of completion.
Seek legal advice where in doubt about the effect of such
certificates.
CONTRACTORS
MATTERS ARISING ON COMPLETION
HANDOVER
CRS 11.5.2
HOME
GACC
EDITION 2: FEB 1998
CRS 12.0 PERFORMANCE REPORTING
CRS 12.1 GENERAL
Performance reporting isthe last stage in the procurement processand
closesthe procurement cycle by providing feedback into the long listing
processfor future work.
O n completion of the workscontract the project manager or
supervising officer should prepare a report for the Department on the
performance of the contractor, at least one year from completion of
the construction period. In respect of a major workscontract, the
appraisal may include the following:
whether the premisesmeet the original brief satisfactorily;
whether the premisesare operationally satisfactory or need
modification, either because of unforeseen problemsor changesin
departmental requirements;
whether the engineering servicesare operating satisfactorily or
require any alteration;
whether there are any signsof premature wear or failure in the
building fabric or engineering services;
whether there are any featuresof the design or brief that should
not be repeated in a future similar project;
the cost of operation and maintenance of the premisesin
comparison with anticipated running costs;
any recommended economiesin running costs;
any recommended alterationsto the premisesor installationsto
provide a better service to the department.
Key Points
Performance reporting providesinvaluable intelligence for the
Department and assistswith future procurement decisions.
Performance reporting providesfeedback to NQ S.
Performance reporting providesthe Department with an
opportunity to learn.
CONTRACTORS
PERFORMANCE REPORTING
GENERAL
CRS 12.2

CRS 12.1
HOME
GACC
EDITION 2: FEB 1998
CRS 12.2 PERFORMANCE REPORTING TO NQS
Performance Report
Assoon asthe contract iscomplete it isrecommended that the project
manager preparesa performance report on behalf of or together with
the Department and forwardsit to the designated NQ S section for the
benefit of future users.
It isrecommended that the Department usesitsdiscretion and
judgement in making itsassessment. The box for Contract Period
should state the time allowed under the contract including extensions
of time awarded. Thiscan then be compared with the entry for Time
Taken and the actual duration of construction work. The assessment
for Speed should be consistent with the other information.
Markings
Where classificationsof performance indicate problems, NQ S requires
that supporting correspondence and other information should be
attached to the report indicating that problemshave been brought to
the contractorsattention together with any repliesreceived.
CONTRACTORS
PERFORMANCE REPORTING
PERFORMANCE REPORTING TO NQS
CRS 12.2
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 1
INDEX
AbbreviationsUsed in thisDocument .................................................................................................................................................................. INT 1.7
Acceptance of a Tender ............................................................................................................................................................................ CST 6.2, CRS 6.2
Adjudication.............................................................................................................................................................................................................................. LE 2.9
Alternative Dispute Resolution Procedures................................................................................................................................................. CST 9.3.1
Alternative O ffers............................................................................................................................................................................................................. CRS 5.4
Amended Tender Documents................................................................................................................................................................................... CST 5.8
Amended Tenders........................................................................................................................................................................................ CST 5.7, CRS 5.5
Appointment Through Competition.......................................................................................................................................................................... PS 3.3
Arbitration ................................................................................................................................................................................. LE 2.9, CST 9.4, CRS 10.7.1
Assignment ............................................................................................................................................................................................................................. LE 1.11
Avoidance of Claims.................................................................................................................................................................................................... CRS 10.3
Award Criteria .................................................................................................................................................................................................................. EPP 1.13
Background............................................................................................................................................................................................................................ INT 1.1
Best Practice Client, Principlesof ............................................................................................................................................................................... PS 1.3
Bill Paying............................................................................................................................................................................................................................... CRS 9.3
Bill Paying and Checking Procedures.................................................................................................................................................................... CST 8.4
Breach of Contract ............................................................................................................................................................................................................... LE 1.7
C1303 - Window Cleaning and C1304 - Chimney Sweeping..................................................................................................... CRS 1.15.13
C1306 - Maintenance of Gardens, Grounds, Etc. and
C1312 - Supplyand Application of Herbicides, Etc. ........................................................................................................................... CRS 1.15.14
C1804 - Repair of Plant ....................................................................................................................................................................................... CRS 1.15.15
Checking Procedures..................................................................................................................................................................................................... CRS 9.4
Choice of Contract, Introduction to the........................................................................................................................................................ CRS 1.3.1
ClaimsAgainst Contractors.................................................................................................................................................................................. CRS 10.6.1
Claimsand Disputes, General ............................................................................................................................................................................. CRS 10.1.1
ClaimsArising from Default or Negligence bya Department Consultant or Contractor................................................... CST 9.2
Claimsbyand Against the Department, Handling of .............................................................................................................................. CST 9.1.1
Claims, Presentation of ............................................................................................................................................................................................... CRS 10.5
Commission Manager/the Project Sponsor, Rolesand Responsibilitiesof the ........................................................................ CST 8.1.1
Conduct of Staff, The........................................................................................................................................................................................................... PS 1.4
Construction IndustryTax Scheme.......................................................................................................................................................................... LE 2.11
Construction Management Contracts........................................................................................................................................................... CRS 1.11.1
Consult Noticeswith NQ S..................................................................................................................................................................................... CST 10.3
Consultants Section, General ............................................................................................................................................................................... CST 4.1.1
Consultant and Sub-Consultants......................................................................................................................................................................... CST 8.2.1
Contract ClaimsAgainst the Department ................................................................................................................................................... CRS 10.2.1
Contract Notice, Decline and Debriefing......................................................................................................................................................... EPP 1.14
Contract Strategy.......................................................................................................................................................................................................... PS 2.4.1.1
General .............................................................................................................................................................................................................. PS 2.4.1.1
Property Management Functions....................................................................................................................................................... PS 2.4.2.1
FacilitiesManagement Strategies......................................................................................................................................................... PS 2.4.3.1
WorksContract Strategies.................................................................................................................................................................... PS 2.4.4.1
HOME
Page 2
GACC
EDITION 2 REV 2: JAN 2000
Contractors Section, General............................................................................................................................................................................... CRS 5.1.1
ContractsbyDeed............................................................................................................................................................................................................... LE 1.3
ContractsFile, Retention Periods....................................................................................................................................................... CST 2.3, CRS 2.3
Contractsusing Billsof Q uantities...................................................................................................................................................................... CRS 1.4.1
Contractsusing Schedulesof Rates....................................................................................................................................................................... CRS 1.5
Criteria for Evaluation................................................................................................................................................................................................ CRS 5.2.1
Damagesfor Breach of Contract................................................................................................................................................................................. LE 1.8
Debriefing Interviews................................................................................................................................................................................................. CST 7.2.1
Decline O f Unsuccessful Tenderers........................................................................................................................................... CRS 6.4.1, CST 6.4.1
Departmental Management Roles.......................................................................................................................................................................... PS 1.5.1
Design and Build Contracts.................................................................................................................................................................................... CRS 1.8.1
Design and Manage Contracts.............................................................................................................................................................................. CRS 1.12
Determination Due to Default ................................................................................................................................................................................ CST 8.6
Determination Procedures............................................................................................................................................................. CST 8.5.1, CRS 9.5.1
Discharge of a Contract .................................................................................................................................................................................................... LE 1.5
Dispatch of Tenders......................................................................................................................................................................................................... CST 4.8
Documentation.............................................................................................................................................................................................................. CRS 4.1.1
Documentation Standards.......................................................................................................................................................................................... CST 4.7
EC Procurement Procedures, Accelerated Timescales................................................................................................................................. EPP 1.9
EC Procurement Procedures, Directives, The................................................................................................................................................ EPP 1.2.1
EC Procurement Procedures, General .............................................................................................................................................................. EPP 1.1.1
EC Procurement Procedures, Proceduresand Timescalesfor
Advertising and Awarding Contracts................................................................................................................................................. Annex EPP 1.3.1
EC Procurement Procedures, Application of ............................................................................................................................... CST 1.2, CRS 1.2
EC Procurement Procedures, Categoriesof Services............................................................................................................. Annex EPP 1.1.1
EC Procurement Procedures, Deciding which Directive Applies...................................................................................................... EPP 1.3.1
EC Procurement Procedures, Estimating the Value of Commissionsand Aggregation......................................................... EPP 1.6.1
EC Procurement Procedures, NoticesRequired under ......................................................................................................... Annex EPP 1.2.1
EC Procurement Procedures, Number of Tenderers................................................................................................................................ EPP 1.11
EC Procurement Procedures, Procedure for Advertising and Awarding Contracts.............................................................. EPP 1.8.1
EC Procurement Procedures, ServicesContract - Model Notices................................................................................. Annex EPP 1.5.1
EC Procurement Procedures, WorksContracts- Model Contract Notices............................................................. Annex EPP 1.4.1
EC/GATT Reporting Requirements................................................................................................................................................................. EPP 1.15.1
Effective Decision-Making................................................................................................................................................................................................. PS 1.6
Errorsin Priced Bills........................................................................................................................................................................................................ CRS 5.6
Establishing A Contract ................................................................................................................................................................................................. CRS 8.4
Evaluating Performance...................................................................................................................................................................................................... PS 4.1
Evaluation Criteria........................................................................................................................................................................................................ CST 5.1.1
Evaluation Procedure ..................................................................................................................................................................................................... CST 5.4
Evidence of Contract ....................................................................................................................................................................................................... LE 1.10
Ex Gratia Claims......................................................................................................................................................................................... CST 9.6, CRS 10.8
Exclusions............................................................................................................................................................................................................................ EPP 1.4.1
Execution of Formal Agreement ......................................................................................................................................................... CST 6.5, CRS 6.5
Extension Contractsand Variations................................................................................................................................................................. CRS 1.13.1
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 3
FacilitiesManagement Strategies........................................................................................................................................................................... PS 2.4.3.1
Fair Employment ( Northern Ireland) Acts......................................................................................................................................................... LE 2.4.1
Fee Schedules..................................................................................................................................................................................................................... CST 5.2
Firm Price and Variation of Price.............................................................................................................................................................................. LE 2.7.1
Focuson O utput Value.................................................................................................................................................................................................. PS 1.7.1
Formsof Tendering.......................................................................................................................................................................................................... CST 4.2
Fostering Teamwork ............................................................................................................................................................................................................. PS 3.4
GC/Works/1 ( 1998) - Lump Sum with Q uantities............................................................................................................................ CRS 1.15.1.1
GC/Works/1 ( 1998) - Lump Sum without Q uantities.................................................................................................................... CRS 1.15.2.1
GC/Works/1 ( 1998) - Single Stage Design and Build Version..................................................................................................... CRS 1.15.3.1
GC/Works/1 ( 1999) - Two Stage Design and Build Version ........................................................................................................ CRS 1.15.4.1
GC/Works/1 ( 1999) - With Q uantitiesConstruction Management Trade Contract
- Without Q uantitiesConstruction Management Trade Contract ............................................ CRS 1.15.5.1
GC/Works/2 ( 1998) - Building and Civil Engineering Minor Works....................................................................................... CRS 1.15.4.1
GC/Works/3 ( 1998) - Mechanical and Electrical Engineering Works.................................................................................... CRS 1.15.5.1
GC/Works/4 ( 1998) - Building, Civil Engineering, Mechanical and Electrical Works..................................................... CRS 1.15.6.1
GC/Works/5 ( 1998) - WorksCommission Consultant Documentation....................................................................................... CST 1.5
GC/Works/5 ( 1999) - WorksCommission Consultant Document ( Framework/Term) ..................................................... CST 1.6
GC/Works/6 ( 1999) - Daywork Term Contract ................................................................................................................................. CRS 1.15.9.1
GC/Works/7 ( 1999) - Measured Term Contract ............................................................................................................................ CRS 1.15.10.1
GC/Works/8 ( 1999) - Specialist Term Contract for Maintenance of Equipment......................................................... CRS 1.15.11.1
GC/Works/9 ( 1999) - O peration, Repairsand Maintenance of Equipment for Mechanical and
Electrical Plant, Equipment and Installationsetc................................................................................................................................ CRS 1.15.12.1
Guide to the Appointment of Consultantsand Contractors- Edition 2........................................................................................ INT 1.2
Handover......................................................................................................................................................................................................................... CRS 11.5.1
Health & Safety( CDM) ................................................................................................................................................................................................. LE 2.1.1
Identification............................................................................................................................................................................................. CST 2.1.1, CRS 2.1.1
Incentive Fees...................................................................................................................................................................................................................... CST 5.3
Individual Discipline Commissions.......................................................................................................................................................................... CST 1.5
Individual Project Management Type Commission........................................................................................................................................ CST 1.4
Insolvency and Bankruptcy........................................................................................................................................................................................ LE 1.18.1
Instructions/NoticesTo Tenderers/Tender Periods................................................................................................................................... CRS 4.2.1
Intellectual Property, Copyright, and RoyaltiesEtc. ....................................................................................................................................... LE 2.5.1
Intelligent Customer and the Role of C AU/PACE, The ........................................................................................................................ PS 1.2.1.1
Intelligent Customer Role....................................................................................................................................................................... PS 1.2.1.1
The Role of CAU/PACE.......................................................................................................................................................................... PS 1.2.2.1
Late Tenders.......................................................................................................................................................................................... CST 4.14.1, CRS 4.7.1
Law of Contract in England & Wales, PrinciplesCovering the............................................................................................................... LE 1.1.1
Legal Advice........................................................................................................................................................................................................................... LE 1.21
Legal Contract Formation....................................................................................................................................................................... CST 6.1, CRS 6.1
Letter of Acceptance.......................................................................................................................................................................... CST 6.3.1, CRS 6.3.1
Limitation.................................................................................................................................................................................................................................... LE 1.9
Liquidated and Ascertained Damages....................................................................................................................................... LE 2.8.1, CRS 11.1.1
Liquidation of a Nominated Sub-Contractor .................................................................................................................................................. CRS 8.5
HOME
Page 4
GACC
EDITION 2 REV 2: JAN 2000
List of Related Reference Documents.................................................................................................................................................................. INT 1.6
Long Listing Process, The.................................................................................................................................................................. CST 3.3.1, CRS 3.3.1
Maintenance Periods.................................................................................................................................................................................................... CRS 11.2
Management Contracts.......................................................................................................................................................................................... CRS 1.10.1
Managing Claims............................................................................................................................................................................................................. CRS 10.4
Mid-Tender Interviews................................................................................................................................................................................................... CRS 4.3
Mistake and Misrepresentation.................................................................................................................................................................................. LE 1.6.1
Model Noticesand Their Content .................................................................................................................................................................... EPP 1.10.1
Monitoring Performance................................................................................................................................................................................................... PS 3.6
Nominated Sub-Contract, Arranging a............................................................................................................................................................ CRS 8.3.1
Nomination Procedures........................................................................................................................................................................................... CRS 8.1.1
N ovation.............................................................................................................................................................................................................................. LE 1.12.1
NQ S, New Q ualification System......................................................................................................................................................................... CST 3.2.1
Number of Tenderers, The...................................................................................................................................................................... CST 3.7, CRS 3.6
O pening of Tenders.......................................................................................................................................................................... CST 4.12.1, CRS 4.5.1
O pening the Tender box ........................................................................................................................................................................................... CST 4.11
O verpayments................................................................................................................................................................................................................. CRS 11.4
Parent Company Guarantees.................................................................................................................................................................................. LE 1.14.1
Partnering............................................................................................................................................................................................................................... PS 5.1.1
Payments............................................................................................................................................................................................................................. CRS 11.3
Performance and Determination ............................................................................................................................................................................. LE 1.4.1
Performance Bonds....................................................................................................................................................................................................... LE 1.15.1
Performance Incentives.................................................................................................................................................................................................. PS 3.5.1
Performance Reporting Generally....................................................................................................................................................................... CST 10.1
Performance Reporting to CMIS......................................................................................................................................................................... CRS 12.2
Performance reporting to the Register of Consultants( CO NREG) ............................................................................................. CST 10.2
Performance Reporting, General ......................................................................................................................................................................... CRS 12.1
Personal Injury Claims................................................................................................................................................................................................... CST 9.7
Post Tender Negotiation............................................................................................................................................................................................... CRS 5.7
Pre-selection Criteria, Identify................................................................................................................................................................................... CST 3.4
Pre-Selection Information........................................................................................................................................................................................ CST 3.5.1
Pre-Selection Procedures........................................................................................................................................................................................ CRS 3.4.1
Pre-tender Interview Stage..................................................................................................................................................................................... CST 3.9.1
Prime Cost Contracts................................................................................................................................................................................................ CRS 1.9.1
Prime Costs.......................................................................................................................................................................................................................... CRS 8.2
Principal Termsand Conceptsin the Construction Industry.................................................................................................................. INT 1.8
Private Finance Initiative................................................................................................................................................................................................. PS 5.2.1
ProceedingsInstituted Against Departments..................................................................................................................................................... LE 1.17
Procurement Processand Programme ................................................................................................................................... CST 1.1.1, CRS 1.1.1
Procurement Strategies, General ......................................................................................................................................................................... PS 2.4.1.1
Professional Indemnity Insurance............................................................................................................................................................................ CST 8.3
Project Brief, Defining the............................................................................................................................................................................................. PS 2.5.1
Project Critiques................................................................................................................................................................................................................ PS 4.2.1
Project Identification........................................................................................................................................................................................................ PS 2.1.1
HOME
GACC
EDITION 2 REV 2: JAN 2000 Page 5
Project Manager, Role of the ................................................................................................................................................................................. CRS 9.1.1
Project Manager, The Need for a................................................................................................................................................................................. PS 3.1
Project O bjectives, Defining............................................................................................................................................................................................. PS 2.2
Project Sponsor, Role of the...................................................................................................................................................................................... CRS 9.2
Project Team, Defining the............................................................................................................................................................................................ PS 3.2.1
Property management Functions......................................................................................................................................................................... PS 2.4.2.1
Property Management Type Commissions........................................................................................................................................................ CST 1.3
Proprietary Components/Articles............................................................................................................................................................................... LE 2.6
Publicityand the Typesof Notice Required.................................................................................................................................................... EPP 1.7.1
Purpose of the Guide ..................................................................................................................................................................................................... INT 1.3
Q ualified Tenders.......................................................................................................................................................................................... CST 5.6, CRS 5.3
Q uality Price Mechanism......................................................................................................................................................................................... CST 3.8.1
Q ueriesbyTenderers................................................................................................................................................................................................. CST 4.9.1
Racial Discrimination ........................................................................................................................................................................................................... LE 2.3
Re-invitation of Tenders........................................................................................................................................................................ CST 5.9, CRS 5.8.1
Recommendation for Acceptance....................................................................................................................................................................... CST 5.10
Record Keeping...................................................................................................................................................................................................................... PS 3.7
Requestsfor Debriefing............................................................................................................................................................................ CST 7.1, CRS 7.1
RequestsFor Further Information Debriefing Interviews........................................................................................................................ CRS 7.2
Reservation of Title........................................................................................................................................................................................................ LE 1.19.1
Risk Management ............................................................................................................................................................................................................... PS 2.3.1
Role of CAU/PACE...................................................................................................................................................................................................... PS 1.2.2.1
Secure Information.......................................................................................................................................................................................................... CST 4.6
Selected or Approved Sub-Contractors............................................................................................................................................................. CRS 8.6
Selection of Firms................................................................................................................................................................................. CST 3.1.1, CRS 3.1.1
Short Lists, Compilation of ............................................................................................................................................................. CST 3.6.1, CRS 3.5.1
Simple Contracts............................................................................................................................................................................................................... LE 1.2.1
Simple Lump Sum Contracts..................................................................................................................................................................................... CRS 1.6
Single Tender..................................................................................................................................................................................................................... CST 3.10
Stamp Duty............................................................................................................................................................................................................................ LE 1.16
Standard Government Contracts..................................................................................................................................................................... CRS 1.15.1
GC/Works/1 ( 1998) - Lump Sum with Q uantities.......................................................................................................... CRS 1.15.1.1
GC/Works/1 ( 1998) - Lump Sum without Q uantities.................................................................................................. CRS 1.15.2.1
GC/Works/1 ( 1998) - Single Stage Design and Build Version................................................................................... CRS 1.15.3.1
GC/Works/1 ( 1999) - Two Stage Design and Build Version....................................................................................... CRS 1.15.4.1
GC/Works/1 ( 1999) - With Q uantitiesConstruction Management Trade Contract
- Without Q uantitiesConstruction Management Trade Contract ........................... CRS 1.15.5.1
GC/Works/2 ( 1998) - Building and Civil Engineering Minor Works..................................................................... CRS 1.15.6.1
GC/Works/3 ( 1998) - Mechanical and Electrical Engineering Works................................................................... CRS 1.15.7.1
GC/Works/4 ( 1998) - Building, Civil Engineering, Mechanical and Electrical Works................................... CRS 1.15.8.1
GC/Works/5 ( 1998) - WorksCommission Consultant Documentation..................................................................... CST 1.5
GC/Works/5 ( 1999) - WorksCommission Consultant Document ( Framework/Term) .................................... CST 1.6
GC/Works/6 ( 1999) - Daywork Term Contract ............................................................................................................... CRS 1.15.9.1
GC/Works/7 ( 1999) - Measured Term Contract ........................................................................................................... CRS 1.15.10.1
HOME
Page 6
GACC
EDITION 2 REV 2: JAN 2000
GC/Works/8 ( 1999) - Specialist Term Contract for Maintenance of Equipment ....................................... CRS 1.15.11.1
GC/Works/9 ( 1999) - O peration, Repairsand Maintenance of Equipment for Mechanical and
Electrical Plant, Equipment and Installationsetc............................................................................................................... CRS 1.15.12.1
C1303 - Window Cleaning and C1304 - Chimney Sweeping................................................................................... CRS 1.15.13
C1306 - Maintenance of Gardens, Grounds, Etc. and
C1312 - Supplyand Application of Herbicides, Etc. ......................................................................................................... CRS 1.15.14
C1804 - Repair of Plant ..................................................................................................................................................................... CRS 1.15.15
Structure of the Guide................................................................................................................................................................................................... INT 1.4
Sub Files.............................................................................................................................................................................................................. CST 2.2, CRS 2.2
Tender Anomalies............................................................................................................................................................................................................. CST 5.5
Tender Boards............................................................................................................................................................................................. CST 4.10, CRS 4.4
Tender Boxes...................................................................................................................................................................................................................... CST 4.5
Tender Documents...................................................................................................................................................................................................... CST 4.3.1
Tender Periods................................................................................................................................................................................................................... CST 4.4
Tender Reporting............................................................................................................................................................................................................. CRS 5.9
Tenderer Selection...................................................................................................................................................................................................... EPP 1.12.1
Term Commissions.......................................................................................................................................................................................................... CST 1.6
Term Contracts........................................................................................................................................................................................................... CRS 1.14.1
The Procurement Process........................................................................................................................................................................................... PS 1.1.1
The Tender Record Book ............................................................................................................................................................. CST 4.13.1, CRS 4.6.1
Thresholds.......................................................................................................................................................................................................................... EPP 1.5.1
Traditional Lump Sum Contracts........................................................................................................................................................................ CRS 1.7.1
Transactionswith O utside Businesses................................................................................................................................................................ LE 1.13.1
Transfer of Undertakings( TUPE) ............................................................................................................................................................................ LE 2.2.1
Use of the Guide............................................................................................................................................................................................................... INT 1.5
Unfair Contract TermsAct 1977............................................................................................................................................................................... LE 1.20
WorksContract Strategies...................................................................................................................................................................................... PS 2.4.4.1
Writsand Summonses.................................................................................................................................................................................................. CST 9.5
HOME

You might also like