DATE Friday, November 15, 2013

Saturday, November 16, 2013

Monday, November 18, 2013

Tuesday, November 19, 2013

Wednesday, November 20, 2013

ACTIVITY Excavation of eroded portions Delivery of Deformed Steel Bars on Site Transport of delivered steel bars from drop off area to fabrication area Transport of delivered steel bars from drop off area to fabrication area Excavation of eroded portions Facbrication of steel bars Installation of horizontal reinforcements (4-layers) on all concrete walls Transport of delivered steel bars from drop off area to fabrication area Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Facbrication of steel bars Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1 Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Facbrication of steel bars Layout of grid positions on foundation excavation site Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1 Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Facbrication of steel bars Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1

Wednesday, November 20, 2013 Engr. Virgilio B. Pineda VP for Project Management Subject: Construction Work Accomplishment Report Since the recommencement of the civil construction works last November 15, 2013 for the foundation to grade slab civil works, all works were done on full course mode as tabulated below.

DATE Friday, November 15, 2013

Saturday, November 16, 2013

Monday, November 18, 2013

Tuesday, November 19, 2013

Wednesday, November 20, 2013

ACTIVITY Excavation of eroded portions Delivery of Deformed Steel Bars on Site Transport of delivered steel bars from drop off area to fabrication area Transport of delivered steel bars from drop off area to fabrication area Excavation of eroded portions Facbrication of steel bars Installation of horizontal reinforcements (4-layers) on all concrete walls Transport of delivered steel bars from drop off area to fabrication area Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Fabrication of steel bars Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Pile Cap bottom steel reinforcements Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1 Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Fabrication of steel bars Layout of grid positions on foundation excavation site Pile Hacking Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Pile Cap bottom steel reinforcements Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1 Excavation of eroded portions Backfilling of excavations around concreted tie beams and pile caps Facbrication of steel bars Pile Hacking Installation of Main Reinforcements (32mm) for FB-2 & FCB-1 Installation of Pile Cap top and bottom steel reinforcements Installation of Stirrup Reinforcements (16mm) for FB-2 & FCB-1

The Steel Reinforcements along the perimeter tie beams (FB-1) and elevator shaft footing beams (FB-3 and FB-2) will be installed once the excavation and clearing operations on the eroded areas are fully accomplished.
Prepared by:

Engr. Mark Gregory Rimando Larossa Project Structural Engineer

Engr. Alvin Sarmiento Larossa Project Quantity Surveyor