You are on page 1of 316

1. Buildings and Meters Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1 Adding an Organization or Building . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2 Adding a Meter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.

3 Setting Up ENERGY STAR for a Building . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4 Modifying Buildings and Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 Modifying Bill Entry Templates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.6 Tracking a Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.7 Calendarization and Normalization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.7.1 Calendarization Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.7.2 Normalization Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.7.3 Resizing the Energy Trend (EUI) Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.8 Cost Avoidance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.8.1 Adding Other Savings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.8.2 Adding Special Adjustments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.8.3 Adjusting Cost Avoidance Meter Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2. Groups and Benchmarking Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1 Adding a Category or Group . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2 Adding a Member to a Group . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3 Managing Categories & Groups . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4 Ranking Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5 Excluding and Re-Including a Group Member . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6 Removing a Group Member . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3. Customers and Chargebacks Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1 Customer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1.1 Adding a Customer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1.2 Modifying a Customer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1.3 Attaching a Customer to a Chargeback Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1.4 Removing a Customer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 Chargeback Accounts & Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2.1 Creating a Chargeback Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2.2 Creating a Chargeback Meter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.3 Chargeback Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.3.1 Setting up a Chargeback Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.3.2 Modifying a Chargeback Distribution Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.3.3 Removing a Chargeback Distribution Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4. Accounts Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.1 Creating a Cost Center . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2 Creating an Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.3 Adding a Meter from an Existing Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.4 Modifying Cost Centers and Accounts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.5 Moving a Cost Center or Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5. Vendors and Rates Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.1 Adding a Vendor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 Adding a Rate Code . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.3 Modifying a Rate Code . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6. Bill Processing Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1 Bill Entry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1.1 Entering a Bill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1.2 Modifying a Utility Bill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1.3 Adding Bill Problem Flags Manually . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2 Bill Import . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.1 Importing Utility Bills from a File . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.2 Rules for Bill Import . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.3 Video Series: Bill Import . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.3.1 Basics of Importing Bills . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.3.2 Preparing Bills for Import . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.3.3 Importing Bills for Accounts with Multiple Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2.3.4 Correcting Bill Import Errors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3 Bill Lists . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.1 Creating a Bill List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.2 Filtering Bill Lists . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.3 Adding/Editing/Removing Filters on a Bill List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.4 Altering/Sorting Columns on a Bill List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.5 Deleting a Bill List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4 5 12 27 32 39 44 48 49 51 52 54 55 58 62 63 64 69 78 81 84 87 89 90 91 95 98 102 103 104 111 126 127 131 133 135 136 138 144 152 159 160 161 163 165 167 168 169 173 177 182 183 190 194 195 196 197 198 200 203 206 208 212 217

6.4 Bill Audits Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.1 Audit Descriptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.2 Creating an Audit Group . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.3 Editing an Audit Group Name/Code/Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.4 Editing Individual Audit Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.5 Running an Audit Group . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4.6 Resolving Bill Problem Flags . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.5 Cost Avoidance Processing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.5.1 Calculating Savings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7. Reports Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.1 Filtering Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.2 Quick Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8. Administration Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.1 Adding a User . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.2 Global Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.3 Adding an Organization Logo . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.4 Normalized Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5 Setup Manager Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1 Setup Manager Import Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.1 Setup Import - Accounts and Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.2 Setup Import - Cost Centers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.3 Setup Import - G/L . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.4 Setup Import - Organizations & Buildings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.5 Setup Import - Rates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.1.6 Setup Import - Vendors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2 Setup Manager Update Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.1 Setup Update - Accounts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.2 Setup Update - Cost Centers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.3 Setup Update - G/L . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.4 Setup Update - Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.5 Setup Update - Organizations & Buildings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.5.2.6 Setup Update - Vendors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.6 Cost Avoidance Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.6.1 Actual Unit Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.6.2 Cost Avoidance Meter Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.6.3 Globally Update Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.7 Template Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.7.1 Adding a Template . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.8 Workflow Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.9 Units of Measure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9. Glossary of Terms & Concepts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.1 Degree Days . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.2 Normalization, M&V, Cost Avoidance and the IPMVP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.3 Setup Manager Importing of Hierarchical Items . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.4 Setup Templates Fundamentals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.5 Statistical Outliers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.6 Use vs. Weather . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

219 220 226 233 235 237 243 246 247 250 251 254 255 256 262 264 266 268 269 271 274 275 276 278 279 280 282 283 284 285 287 288 289 290 292 294 298 299 302 304 306 307 309 310 312 313 314

Buildings and Meters Overview

Overview
The Buildings & Meters Tree View displays an organization's hierarchy consisting of Organizations, Buildings, and Meters. Creating a hierarchy allows energy data to be easily reported on, specifically showing PowerViews and other data that is aggregated at each node level. This kind of organization makes it easy for organizations that have regional divisions, for instance, to quickly see energy use and spend for each region. Individual billing data can always be viewed at the meter level, while aggregated energy usage and cost data can be displayed at each Building or Organization node including the entire organization by using the highest node. Within the Buildings & Meters section there are numerous views of data that all relate to Organizations, Buildings or Meters. The Actual Data tab lists various sub-tabs that display actual bill data into yearly totals, monthly breakdowns, GHG emissions and other trend-type charts. Depending on what kind of node that is selected, some tabs may appear or disappear if it is not relevant to the selected item. A Bills tab, for instance, will only display when a Meter is selected. The Calendarization tab displays similar data to that of the Actual Data views, but adjusted in a way that statistically breaks the data into calendar months based on weather. More information about how Calendarization is done in EnergyCAP can be found on the Calendarization Overview page. The Normalization tab displays similar data to that of the Calendarized Data views, further adjusted to show what energy usage trends would look like if outside weather was not a factor. More information about how Normalization is done in EnergyCAP can be found on the Normalization Overview page.

Rules & Restrictions


The Buildings & Meters view permission is required to access this view To view the Calendarization, Normalization or Savings tab, the Cost Avoidance advanced feature must be included in your EnergyCAP License.

2013 EnergyCAP, Inc.

Adding an Organization or Building


Description
Buildings and Organizations are created as part of an organizational hierarchy. The tree hierarchy includes nodes representing organization subdivisions (departments, agencies, business units, etc.), as well as individual buildings associated with each division.

This topic will...


describe the process for adding organizations to the tree hierarchy. describe the process for adding buildings to the tree hierarchy.

Prerequisites
The ability to add organizations and buildings requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup

Step-by-Step
Adding an Organization 1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Organization menu option.

2013 EnergyCAP, Inc.

3. On the Identity tab, complete all relevant fields and then click Continue. a. Complete the required Name field and press the Tab key b. In the Code field, a code based on the name will be automatically created. This field can be edited if desired. c. Select an Organization Type for the Organization by clicking the Type drop-down list.

2013 EnergyCAP, Inc.

4. Click Finish. The Building/Organization Wizard will close and the new place will be added to the tree hierarchy.

Adding a Building 1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Building menu option.

2013 EnergyCAP, Inc.

3. From the Identity tab, complete all relevant fields and then click Continue. a. Complete the required Name field and press the Tab key. b. In the Code field, a code based on the name will be automatically created. This field can be edited if desired.

2013 EnergyCAP, Inc.

4. Complete desired address information in the fields provided (ZIP/Postal Code is required). Then click Contin ue.

2013 EnergyCAP, Inc.

5. From the Additional Details tab, complete all relevant fields and then click Continue. Radio options are: Select the building Primary Use from the drop-down list OR Add a new Primary Use by clicking the Add button and following the prompts to define the new Primary Use. Complete the Floor Area and Area Unit of Measure fields.

2013 EnergyCAP, Inc.

6. Click Finish. The Building/Organization Wizard will close and the new building will be added to the tree hierarchy.

Rules & Restrictions


Multiple organizational levels can be created by adding organizations under other organizations. Organizations cannot be created below buildings. Buildings can only be created below organizations, not under other buildings.

Additional Information
City and State will automatically be compared to the zip code entered. If the zip code does not match the city and state, an alternate address will be suggested. After the address is save the Organization or Building will automatically be connected to the appropriate weather station based on zip code. The Primary Use is referenced when creating auto-groups in Groups & Benchmarking. The primary use auto-group display data for all buildings of the same primary use.

2013 EnergyCAP, Inc.

Adding a Meter
Description
A meter represents a commodity associated with a utility point of service. All utility bills are associated with a meter, and every meter must be associated with a utility account and a building or organization. This mandatory structure standardizes reporting and viewing of data. Bills must be associated with a meter even when no physical meter exists.

This topic will...


describe the process for adding a meter. NOT describe the process for adding a chargeback meter. Please refer to Creating a Chargeback Meter.

Prerequisites
The ability to add meters is incorporated in the following User Roles: Administration Full Access Bill Entry & Account Setup Obtain a paper copy or facsimile of the utility bill to be modeled. The bill will provide most of the information necessary for setting up the meter.

Step-by-Step
1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Meter menu option.

3.
2013 EnergyCAP, Inc.

3. Review the instructional information provided with the Introduction tab. Then click Continue.

4. On the Cost Center tab, choose the appropriate radio button and then click Continue. Currently Selected Cost Center will be an available option when creating more than one meter. It will display the previously selected cost center so that is can be easily used again. Create a New Cost Center will create a new cost center for the account. Refer to the Creating a Cost Center topic for more explicit cost center creation help. Select a Cost Center will associate the account with an existing cost center. Use the hierarchy to select the desired cost center.

2013 EnergyCAP, Inc.

5. On the Service Address tab, enter Service Address information in the fields provided. Then click Continue.

2013 EnergyCAP, Inc.

6. On the Vendor tab, choose the appropriate radio button: Select the desired vendor using the Vendor drop-down OR Add a new vendor by clicking the Add button. Refer to the Adding a Vendor topic for more explicit vendor help. 7. Click the radio button corresponding to the Vendor Type. Then click Continue.

2013 EnergyCAP, Inc.

8. On the Account Type tab, complete the relevant information and then click Continue. a. Enter the Account Number. b. Click a radio button to indicate how the Account Name will be created. Complete additional fields if displayed.

2013 EnergyCAP, Inc.

9. On the Create Meters tab, select the number of Meters to create using the drop-down list provided and then click Continue.

2013 EnergyCAP, Inc.

10. On the Create/Select tab, choose the appropriate radio button and then click Continue. a. Create a new meter will launch the Meter Wizard and add a new meter to the Building hierarchy. b. Select an existing meter will associate an existing meter with the new account.

2013 EnergyCAP, Inc.

11. On the Place Assignment tab, choose the appropriate radio button and then click Continue. Create a new Building will create a new building for the meter. Refer to the Adding an Organization or Building topic for more explicit building creation help. Select a Place will associate the meter with an existing building. Use the hierarchy to select the desired building.

2013 EnergyCAP, Inc.

12. On the General Info tab, complete the relevant information and then click Continue. a. Based on the commodity selected, the Name and Code are automatically generated. Edit these fields if desired. b. To enter the Address, click the Edit button and add meter address information in the fields provided. Only ZIP/Postal Code is required. Then click OK. c. (optional) Complete the Serial Number information for the meter. Typically, this number is physically stamped on the device by the manufacturer.

2013 EnergyCAP, Inc.

13. On the Additional Meter Info tab, complete the relevant information and then click Continue. a. Select the meter primary use from the Primary Use drop-down OR Add a new primary use by clicking the Add button and following the prompts provided. b. In the G/L Code field, enter an accounting code used to specify how charges are posted to an organizations General Ledger. This code is only necessary if the organization is exporting billing data to an accounting system. c. If desired, complete the optional Bill Entry Note, which will be associated with the meter. Bill Entry Notes are visible during utility bill data entry for the associated account.

2013 EnergyCAP, Inc.

14. On the Rate Code tab, choose the appropriate radio button and then click Continue. The Rate Code button provides a drop-down list to select an existing vendor rate. The Create a new rate for this vendor button provides fields to enter the new Rate Code and enter the associated unit of measure.

2013 EnergyCAP, Inc.

15. If the commodity is Electric, select any demand options on the Demand tab. Then click Continue.

2013 EnergyCAP, Inc.

16. On the Template Selection tab, select the desired bill entry template. Refer to Modifying Bill Entry Templates f or additional template information. Then click Finish to save the meter information and close the Meter Wizard. If multiple meters are being created, the Meter Wizard will cycle through the meter creation process again (see Step 11).

2013 EnergyCAP, Inc.

17. Review all information from the Confirmation tab; then click Finish to close the Account/Meter Wizard. Account setup information will be saved and the Wizard will close.

2013 EnergyCAP, Inc.

Rules & Restrictions


When adding a meter from the Buildings & Meters Tree View, a new account must be created. If it is necessary to associate a new meter with an existing account, launch the meter wizard ( Add Meter button) from the Account Tree View. The Account/Vendor combination must be unique. The same account number can only be used for different accounts when each of the accounts has a different vendor.

2013 EnergyCAP, Inc.

Setting Up ENERGY STAR for a Building


Description
For each ENERGY STAR-enabled building, it is necessary to submit 12 months of utility bills and certain building attributes such as number of occupants and hours of operation in order to receive a rating. The required building attributes vary depending on the building type. To receive a basic "best guess" ENERGY STAR rating, it is only necessary to submit the building type, floor area, and ZIP code. Other building attributes will be assigned standard EPA default values. However, ENERGY STAR participants are encouraged to enter all available building attributes for their buildings in order to get a more accurate ENERGY STAR rating.

This topic will...


describe the process for setting up a building to submit data to the ENERGY STAR Portfolio Manager. provide information on various building use 'spaces' which can be set up under the primary building type.

Prerequisites
The User must have ENERGY STAR access permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Building Administrator

Step-by-Step
1. Select Buildings and Meters from the Main Menu. The Buildings navigation Tree View will be displayed 2. Select the Building that will be submitted to ENERGY STAR. 3. Click the Edit button beneath the Tree View.

2013 EnergyCAP, Inc.

4. On the ENERGY STAR tab: a. Check the Enable automatic ENERGY STAR ratings check box. b. Select the Primary Space Type that represents the largest floor area associated with the building. A corresponding tab will be created under Space Type Properties for the Primary Space. At least one of the space types must have square footage corresponding to more than 50 percent of the total building area or an ENERGY STAR rating will not be returned for the building. c. If there is a dedicated segment of the building representing a different Space Type, select it from the A dditional Space Type drop-down. d. Click to select the additional Space Type, then click the Add This Space button. A tab under the Space Type Properties will be created for the Additional Space Type. Up to eight additional Space Types can be added for a single building.

2013 EnergyCAP, Inc.

5. Enter or update values for all relevant building attributes and effective dates by clicking to select the desired field, and entering the information. Official attribute instructions are available from EPA at: http://www.energystar.gov/ia/busin ess/tools_resources/target_finder/help/Space_Use_Information.htm 6. If there are meters associated with the building that should not be included in ENERGY STAR calculations, click the Include/Exclude tab. 7. On the Include/Exclude tab, uncheck the Include/Exclude checkbox for all meters that are not related to the energy usage of the space(s) managed. See Additional Information, below, for a list of legitimate exclusions.

2013 EnergyCAP, Inc.

8. Click Save. The Building Properties window will close and ENERGY STAR attributes will be updated.

Rules & Restrictions


There are 14 building types eligible for ratings. If the specific building type is not available, select Othe r. Although a building classified as Other will not receive a 1-100 rating, it will still receive valuable energy metrics. The ZIP code and Gross Floor Area fields of the primary type are automatically populated from the General and Floor Area tabs of Building Properties. Either attribute can be modified on the respective tab. 24/7 building access is indicated as 168 hours/week.

Additional Information
When ENERGY STAR setup for a building is complete, EnergyCAP submits the building energy data to the ENERGY STAR Portfolio Manager via the EPA's Automated Benchmarking Service (ABS) as soon as enough billing and setup data is available. Thereafter, building data will be resubmitted when data has changed or new bills have been entered. For EnergyCAP, Inc Hosted clients, the submittals are done automatically. For Self Hosted clients, the submittals must be initiated by the client. An ENERGY STAR rating is calculated against a U.S. Dept. of Energy statistical model known as CBECS. The CBECS model takes certain building characteristics into account when deriving the ENERGY STAR rating. For instance, a General Office Building Type would be assumed to contain both the actual office area AND other areas like lobbies, conference rooms, fitness areas, etc. When a building has 10,000 sq/ft of space, all of these space types would be expected to be part of this number. Likewise, a hospital will always have spaces used for storage, administrative offices, medical offices, restaurant, etc. These are assumed to be present and it is not necessary to define these space types.

2013 EnergyCAP, Inc.

However, suppose that an electric meter also powers the lights in the buildings parking lot. The parking lot is an additional space type not typically associated with that building type. The additional draw on energy resources should be accounted for, in order to obtain the most accurate ENERGY STAR rating. There may be times when it would be advantageous and appropriate to exclude meters from ENERGY STAR submission (see Step 9 in the Step-by-Step, above). Some examples include: A meter that serves exterior signage should be excluded. If a parking lot has a separate meter, exclude the meter and do NOT create a parking sub-space. One of the meters on a building is associated with space assigned to a tenant with a high-energy industrial application.

2013 EnergyCAP, Inc.

Modifying Buildings and Meters


Description
All places and meters have properties that can be modified at any time. Organization properties include name, code and place type. Meter properties include ENERGY STAR properties associated with buildings.

This topic will...


describe the process of modifying existing organization properties. describe the process of modifying existing meter properties.

Prerequisites
The ability to modify organizations, buildings, and meters requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup

Step-by-Step
Modifying Properties of an Organization Node 1. Select Buildings & Meters from the Main Menu. The Buildings & Meters navigation Tree View will be displayed on the left. 2. Select the organization to be modified. 3. Click the Edit button beneath the Tree View.

2013 EnergyCAP, Inc.

4. On the General Tab: Name: Edit the Organization name. Code: Edit the Organization code. Place Type: Select a category from the drop-down list. Or click the Add button to add a new Primary Use.

2013 EnergyCAP, Inc.

5. Click Save. The Organization Properties window will close.

Modifying Properties of a Building Node 1. Select Buildings & Meters from the Main Menu. The Buildings & Meters navigation Tree View will be displayed on the left. 2. Select the building to be modified. 3. Click the Edit button beneath the Tree View.

2013 EnergyCAP, Inc.

4. On the General tab: Name: Edit the Building name. Code: Edit the Building code. Primary Use: Select a category from the drop-down list. Or click the Add button to add a new Primary Use. Address: Click the Edit button to change the existing address.

2013 EnergyCAP, Inc.

5. On the Floor Area tab, either: Add a new floor area and effective date by clicking the Add button above the grid, OR Edit an existing entry for floor area by clicking the Edit icon to the left of the floor area value.

6. For information on the ENERGY STAR and Include/Exclude settings tabs, please refer to Setting Up ENERGY STAR for a Building help topic. 7.
2013 EnergyCAP, Inc.

7. Click Save. Modifying Properties of a Meter Node 1. Select Buildings & Meters from the Main Menu. The Buildings & Meters navigation Tree View will be displayed on the left. 2. Select the Meter to be modified. 3. Click the Edit button beneath the Tree View.

4. On the General tab: Name: Edit the Meter name. Code: Edit the Meter code. Primary Use: Select a category from the drop-down list. Or click the Add button to add a new Primary Use. Address: Click the Edit button to change the existing address. Serial Number: Edit the Meter serial number. Bill Entry Note: Edit the desired information (will be displayed during bill entry for the account/meter). G/L Code: Edit the associated general ledger code information for accounting

2013 EnergyCAP, Inc.

5. Click Save.

Rules & Restrictions


The Code must be unique. It cannot be the same as an existing code. When modifying a Name, the existing associated Code will not be changed to match the new name. It must be manually changed if desired.

2013 EnergyCAP, Inc.

Modifying Bill Entry Templates


Description
Each meter has an associated bill entry template. The goal in template selection is to choose the bill entry template that most closely matches the utility bill while including all desired fields for tracking relevant energy data.

This topic will...


describe the process for adding a Bill Entry Template. provide information on how bill entry templates are named.

Prerequisites
The ability to add a Bill Template requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bldg Administrator

Step-by-Step
Initial Template Selection A bill entry template is always associated with a meter. The original bill entry template for a meter is chosen from the Account/Meter Wizard during meter creation. Refer to the Adding a Meter topic for information on initial template selection. Changing a Bill Entry Template 1. Select Buildings and Meters from the Main Menu. The Buildings and Meters navigation Tree View will be displayed on the left. 2. Select the meter. 3. Select the Meter Properties tab. If necessary, scroll down to view the Templates list. 4. Click the Add Template button.

2013 EnergyCAP, Inc.

5. On the Demand tab (only visible on electric meters), click the check box(es) in the Demand tab that corresponds to the Demand details to be tracked. The click Continue.

2013 EnergyCAP, Inc.

6. On the Template Selection tab: a. Enter or select a Begin Date that the template should become effective. b. Click the radio button corresponding to the desired template selection option. The Standard template is the simplest template option (used for tracking a minimum amount of information). The Advanced template is a more complex bill entry template with options for tracking additional utility bill information. Pick a Template from the Library provides a drop-down list of all available templates for the commodity. Select a template from the drop-down list to display/select the template design.

2013 EnergyCAP, Inc.

7. Click Finish. The template will be effective as of the selected Begin Date.

Rules & Restrictions


To maintain consistency in tracked data, frequent changes to the bill entry template are not recommended. Always select the template which most closely matches the desired bill line items to be tracked.

Additional Information
Occasionally it may become necessary to change the bill entry template for a meter. Reasons for a change might include: The initial template was assigned in error. Data tracking needs of the organization have changed. The vendor has changed. The bill format has changed. Common naming conventions for the default list of available bill entry templates are (sequentially from left to right):

2013 EnergyCAP, Inc.

Vendor Type

FD_ signifies full service vendor or distribution vendor. This template prefix often indicates a more complex and detailed EnergyCAP-defined template, usually including more bill line items than the Standard or Advanced templates. S_ signifies a "supply" vendor. This template prefix indicates that usage for this template is information-only and is not included in any calculations (because the usage should already be tracked by a parallel FD vendor for this meter). Optional prefix for the commoditys abbreviated unit of measure (DKTHM, KWH, etc.) A - Advanced S - Standard N - Not tracking demand Y - Yes tracking demand T1 - NOT a time-of-use rate T2 - Off-Peak and On-Peak rates T3 - Off-Peak, Mid-Peak, and On-Peak rates

Abbreviated template description:

The demand indicator (Y(es) or N(o), electric meters only): Time-of-Use indicator (electric meters only):

Template revision number (1, 2, 3, etc...)

2013 EnergyCAP, Inc.

Tracking a Project
Description
All Energy Projects can be recorded and tracked through the application. Energy project data, including project cost, start and end dates, anticipated savings, rebates, and other information can then be reviewed at any roll-up level of the organization.

This topic will...


describe the process for adding a project. describe the process for editing a project describe the process for deleting a project

Prerequisites
The ability to add projects requires permissions associated with the following User Roles: Administrator Full Access Bill Entry & Account Setup

Step-by-Step
1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will appear on the left. 2. Select the Building for which the project will be added. 3. Click the Building Properties tab. Then click the Projects subtab. 4. Click the Add Project button located directly above the Energy Projects list.

5.
2013 EnergyCAP, Inc.

5. From the Identity tab, input the project parameters and then click Continue. In the Name field, enter the name of the project. In the Short name field, enter an abbreviated name that can be used for project-related charts. In the Project Manager field, enter the name of the individual appointed to manage the project, if applicable.

6. From the Details tab, input the project details and then click Continue. In the Start Date field, click the associated calendar icon to select the appropriate project start date. In the End Date field, click the associated calendar icon to select the appropriate project end date. In the Project Type field, select a type from the drop-down menu OR add a new project type by clicking the Add button to the right of the Project Type drop-down.

2013 EnergyCAP, Inc.

7. From the Financials tab, input the financials relating to the project.

2013 EnergyCAP, Inc.

8. Click Finish. The Project Wizard will close, and the project will be added to the Energy Projects table.

Rules & Restrictions


The Project Name must be unique; it cannot be the same as any existing project associated with any building. Projects can only be associated with a building, not any other node. Organizations display the projects for all buildings listed below them. This allows the projects to be reviewed at any roll-up level of the organization.

Additional Information
An icon is added to the Energy Use Intensity(EUI) chart indicating months that completed energy projects. The EUI chart is located on the Normalized tab

2013 EnergyCAP, Inc.

Calendarization and Normalization


Description
Topics in this section provide guidance on Calendarization and Normalization in EnergyCAP. Calendarization more accurately allocates utility bill usage and cost data for reporting purposes by dividing the data into day-size chunks and allocating them to the appropriate calendar month using weather adjustments. Normalization compensates for year-to-year weather variations by imposing the same years weather (in terms of degree days) on each year of usage data. Doing so effectively removes year-to year changes in consumption caused by weather so that a true apples-to-apples comparison can be made when examining the effectiveness of energy saving projects. These features are available to EnergyCAP clients who have purchased the Cost Avoidance or Calendarization/Normalization option.

This topic will...


explain the calendarization and normalization processes in EnergyCAP.

Prerequisites
Purchase of Cost Avoidance module user permissions for access to the Cost Avoidance functions

Step-by-Step
In both the calendarization and normalization processes, a sophisticated and fully automatic process is used to: 1. determine if a meter is statistically weather sensitive due to a valid correlation between usage and degree days. 2. determine if it is weather sensitive in summer, winter, neither or both. 3. create a mathematical model of the meters response to degree days which indicates how sensitive it is (in usage per degree day) and how much non-weather base load it has (in usage per day). 4. determine which process is appropriate for each meter (the mathematical model if weather sensitive, or simple daily proration if not weather sensitive) to create the calendarized and normalized results. The results of calendarization and normalization may be viewed from the Calendarized Data and Normalized Data tabs in the Buildings & Meters chart displays, and in a series of specialized Calendarized or Normalized reports.

Rules & Restrictions


N/A

2013 EnergyCAP, Inc.

Calendarization Overview
Description Calendarization more accurately allocates utility bill usage and cost data for reporting purposes by dividing the data into day-size chunks and allocating them to the appropriate calendar month using weather adjustments. Without daily meter readings the splitting cant be exact, but it is reasonably accurate. Most utility bills have start and end dates that do not correspond to an exact calendar month: Exact calendar month: Start date: 9/1/2011 Start date: 10/1/2011 Typical utility bill: Start date: 9/12/2011 Start date: 10/14/2011 End date: 10/14/2011 End date: 11/13/2011 End Date: 10/1/2011 End Date: 11/1/2011

Why calendarize? Calendarization provides better month-to-month and year-to-year comparisons for reporting purposes by more accurately allocating monthly usage from bi-monthly and quarterly bills, estimated bills, and bills with variable billing periods (28 days one month, 34 days the next). The calendarized data is therefore more representative of actual monthly energy use when used in fiscal reporting, budgeting, auditing, accruals and energy performance evaluation. In EnergyCAP, two methods of calendarization are used. Option 1: Simple average daily use and cost allocation: When a meter is not weather sensitive, the bill is simply prorated into each month based on the number of billing period days. A bill from 9/12 to 10/14 has 32 days (the first day counts, the last day doesnt because the next bill begins on 10/14). There are 19 days in September, so 19/32 of the usage and cost is allocated to September and 13/32 to October. Option 2: Weather (degree day) allocation: When a meter is weather sensitive, the simple method described above is inadequate and provides less reliable results. A much more sophisticated method is used to prorate the weather sensitive portion of the energy bill based on the number of degree days in the appropriate billing period in each month, and to prorate the remaining non-weather sensitive portion based on the number of days. See the Use vs. Weather topic for more details. Annual Totals Note that calendarizing does not appreciably affect annual totals. Since the calendarization process merely moves usage and cost data to the most appropriate calendar month for reporting and analysis purposes, the annual usage and cost totals should be almost identical to the actual data (the data shown on a billing period basis). There may be slight differences due to year-end roll-over, but that is typically less than 1%.

2013 EnergyCAP, Inc.

In EnergyCAP, calendarized data is displayed in two places: calendarized reports and the Calendarized Data tab. The example below demonstrates the value of calendarization: Due to the sequence of raw bills, there are two bills with a Nov 2009 billing period and no bill with a Feb 2010 billing period: Just by looking at the chart, it would easily be possible to conclude that: There was a problem in Nov 2009 that caused high cost and usage There is a missing a bill for Feb 2010. The anomaly merits investigation. However, the calendarized view (more accurately allocated to the calendar months), reveals that nothing was unusual in Nov 2009 or Feb 2010. The calendarized data is easier to understand, reflects the actual usage pattern more accurately, and avoids unnecessary false alarms. Additional Information: The weather regression calculations used by Calendarization and Normalization do not exclude statistical outliers. Calendarization and Normalization data is not intended to be used for IPMVP approved cost avoidance purposes which would need the more precise weather regression result that is produced when outliers are excluded. Only EnergyCAP Enterprise currently provides IPMVP compliant cost avoidance data.

2013 EnergyCAP, Inc.

Normalization Overview

Description Normalization in EnergyCAP helps answer the question: "If the weather was exactly the same year-after-year, how has my energy use changed"? Since weather is often the largest variable affecting energy use, historical comparisons which have been "normalized" for weather can help provide a clearer picture of the effectiveness of energy management actions. How it works Calendarization provides the starting point for normalization, since the calendarization process takes raw billing data and allocates it to the most appropriate reporting calendar day and month. Calendarization also takes into account the weather sensitivity of each meter (see Use vs. Weather topic for more information). Normalization takes calendarization a step further by actually applying month-by-month weather conditions from a user-selected calendar base year to the calendarized monthly usage data of all other years. More specifically, the weather-sensitive usage value from the base year is applied to the mathematical 'model' of weather-sensitivity for each of the comparison years. The recalculated weather-sensitive monthly usage is added to the non-weather-sensitive monthly usage (base load) to produce a monthly data point on a line graph. As an example, if the charted 2011 normalized usage for a building is lower than the normalized 2009 usage, it is certain that the reduction is not due simply to milder weather in 2011 because the consumption data for both years has been weather-adjusted to the comparison weather year. The usage difference could be due to energy management efforts or other factors such as occupancy, production, square footage or equipment changes, or hours of operation. But the weather is no longer a variable. The baseline year for normalization is selected from the Administration menu (Administration > Normalized Settings), and can be changed at any time.

2013 EnergyCAP, Inc.

Resizing the Energy Trend (EUI) Chart


Description One of the more useful chart overviews of Building or Organization's energy usage and trending is the Energy Use Intensity(EUI) chart located on the Normalized Data tab of any building This chart provides a trend analysis for up to a ten-year span with monthly bar graph plots for all energy commodities associated with the selected node, as well as a monthly trend line expressing annualized use per unit area for the selected Place(s). Annualization helps minimize trend effects caused by missing bills. Each trend line data point represents the average of the prior 12 months. For accounts with multiple years of data, it is possible to limit the data shown in the EUI chart to a different range of dates by using the date sliders that appear atop the chart. This topic will... describe the process of resizing the Energy Use Intensity Chart Prerequisites The ability to view and resize the Energy Use Intensity chart requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup Step-by-Step 1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will be displayed on the left. 2. Select the building with the EUI chart to be viewed. 3. Click the Normalized Data tab 4. Click the Energy Trend (EUI) subtab 5. Click and drag the date slider to the desired date range. To move the date range, click between the date sliders and drag to the desired date range.

2013 EnergyCAP, Inc.

Rules & Restrictions Commodity energy use (colored bars) is expressed in global units. The EUI Trend line is not visible until at least 18 months of previous data exist. The slider option is only available if 5+ years of data are available.

2013 EnergyCAP, Inc.

Cost Avoidance

2013 EnergyCAP, Inc.

Adding Other Savings


Description Other savings are one-time or recurring cost reductions that do not fit within the normal cost avoidance calculations for current bills vs. baseline bills. However, they are valid savings attributable to energy management activities. This topic will... describe the process of adding an Other Savings record Prerequisites Must have purchased Cost Avoidance The ability to add other savings requires permissions associated with the following User Roles: Administration Full Access

Step-by-Step 1. Select Buildings and Meters from the Main Menu. The Buildings and Meters navigation Tree View will be displayed on the left. 2. Select the meter. 3. Select the Savings tab. 4. Select the Other Savings subtab. 5. Click the Add Other Savings button.

6. Review the instructional information provided with the Introduction tab. Then click Continue.

2013 EnergyCAP, Inc.

6.

7. On the Category tab, complete all fields and then click Continue. For the savings category: Select the desired category using the Savings Category drop-down OR Ad d a new Category by clicking the Add button. Enter an Other Savings Amount. Enter a Description to better explain the reason for this Other Savings.

2013 EnergyCAP, Inc.

8. On the Frequency tab, select the appropriate radio button and complete the corresponding fields. Then click Continue. One Time will only add the savings to bill for the month specified Continuous will continue each month for the dates specified Recurring will add savings for bill in the annual cycle months specified

9. Click Finish.

2013 EnergyCAP, Inc.

Adding Special Adjustments


Description A special adjustment is needed when there has been a change in energy usage of a building meeting one of the following conditions: It occurred AFTER the baseline year. It is NOT the result of an Energy Manager's actions. It is NOT weather related. This topic will... describe the process of adding a Special Adjustment record Prerequisites Must have purchased Cost Avoidance The ability to add Special Adjustments requires permissions associated with the following User Roles: Administration Full Access

Step-by-Step 1. Select Buildings and Meters from the Main Menu. The Buildings and Meters navigation Tree View will be displayed on the left. 2. Select the meter. 3. Select the Savings tab. 4. Select the Adjustments subtab. 5. Click the Add Special Adjustments button.

2013 EnergyCAP, Inc.

6. Review the instructional information provided with the Introduction tab. Then click Continue.

7. On the Category tab, complete all fields and then click Continue. Select the desired category using the Adjustment Category drop-down.

2013 EnergyCAP, Inc.

7.

Enter a Description to better explain the reason for this Special Adjustment.

8. On the Frequency tab, select the appropriate radio button and complete the corresponding fields. Then click Continue. Continuous will continue each month for the dates specified Recurring will add savings for bill in the annual cycle months specified

2013 EnergyCAP, Inc.

9. On the Method tab, complete all fields. Select an adjustment method to be applied to baseline bills. Enter the adjustment amount.

10. Click Finish.

2013 EnergyCAP, Inc.

Adjusting Cost Avoidance Meter Settings


Description Meter Settings can be adjusted one meter at a time. This topic will... describe the process for updating individual meter settings does NOT describe the process for updating multiple meters' settings at once. Please refer to Globally Update Meters help topic. Prerequisites The ability to adjust cost avoidance meter settings requires permissions associated with the following User Roles: Administration Full Access Step-by-Step 1. Select Buildings and Meters from the Main Menu. The Buildings and Meters navigation Tree View will be displayed on the left. 2. Select the meter. 3. Select the Savings tab. 4. Select the Use vs. Weather subtab. 5. Change all appropriate settings. 6. Click Save & Reprocess.

2013 EnergyCAP, Inc.

Groups and Benchmarking Overview

Overview
The Groups & Benchmarking Tree View is a powerful tool that can easily highlight buildings and meters that have abnormal use, cost or demand. These abnormal buildings and meters often offer the greatest opportunity for cost reduction and energy savings. The Tree View displays categories and groups of buildings and meters to help compare similar data to help identify anomalies. Blue folders signify auto-groups which EnergyCAP maintains for you. Yellow folders show categories and groups that have been created by users. The PowerViews that are displayed for each Building or Meter group show aggregated consumption, cost or demand data from each member of the group. The data can then be ordered in ascending or descending order to find the buildings or meters that could potentially benefit the most from more active energy management. Currently, data is displayed for raw cost and use, unit cost per commodity, and by usage per floor area. The average for all members of the group is always displayed to provide guidance on how much of an outlier a specific member is. Although the most recent twelve months of data is compared by default, a custom date range can be set. Finally, as Group PowerViews are examined, any member that appears to be skewing the comparison can be excluded from groups calculations while still remaining part of the group. This is particularly useful when the Building and Meter Group filters are provided on reports and in other parts of the application, allowing a user-friendly way to get a consistent list of like members. Key terms in Groups and Benchmarking include: A Category is the parent folder containing all the related groups. A User-Created Group is created by an individual EnergyCAP user with the appropriate permissions. A user-created Group is indicated by a yellow folder icon. An AutoGroup is automatically created by EnergyCAP, and is indicated by a blue folder icon. A Group Member is a meter or a building that will be included in the Benchmarking chart data.

2013 EnergyCAP, Inc.

Adding a Category or Group


Description
Categories are a way of organizing multiple benchmarking Groups. Any number of groups can be listed under each Category; each Group will display roll-up data based on the defined collection of Meters or Places in the Group.

This topic will...


describe the process for adding a Category. describe the process for adding a Group.

Prerequisites
The ability to add a category requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup The ability to add a group requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bldg Administrator

Step-by-Step
To Add a Category: 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View will be displayed on the left. There are two default root Categories: Place Groups and Meter Groups. 2. Click to highlight the Place Groups or Meter Groups node, depending on the type of new Category desired. Click the Add button beneath the Tree View.

2013 EnergyCAP, Inc.

3. On the General tab: a. In the Name field, enter the display name for the Category. b. In the Code field, a code based on the name will be automatically created. This field can be changed to any desired value.

2013 EnergyCAP, Inc.

4. Click Finish. The Category Wizard will close and the new Category will be available on the tree. To Add a Group to an Existing Category: 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View will be displayed on the left, divided into Place and Meter Groups. 2. Click to highlight the Place Category or Meter Category tree node under which the Group will reside. 3. Click the Add button beneath the Tree View.

2013 EnergyCAP, Inc.

4. On the General tab: a. In the Name field, enter the display name for the Category. b. In the Code field, a code based on the name will be automatically created. This field can be changed to any desired value. c. For Meter Groups, the Hide Group Members check box determines how to honor an individual's user permissions if others with a different set of permissions will be viewing data for the Group. d. Click a Group View Permission: All Users can view this group allows any user to view this group Restrict access based on Minimum Topmost Permission enables the Topmost place tree. Select the Available Topmost Place desired and move it to the Minimum Topmost Permission by clicking the appropriate arrow button.

2013 EnergyCAP, Inc.

5. Click Finish. The Category Wizard will close and the new Category will be available on the tree.

Rules & Restrictions


Categories cannot be created beneath Groups. Groups must be created under a Category. Groups cannot be added to an Auto-Category, indicated by the blue-colored folder. These are automatically generated by EnergyCAP, and cannot be modified. A user having a Topmost Place permission (established in Users & Permissions) that is EQUAL TO OR HIGHER THAN ANY ONE of the Minimum Topmost Permission selected for the Group may view the Group's Benchmark charts. A user having a Topmost Place permission that is LOWER THAN the Minimum Topmost Permission selected lacks sufficient viewing rights, and will not be able to see the Group from the Tree View.

2013 EnergyCAP, Inc.

Adding a Member to a Group


Description
After a Group has been created, it must be populated with desired group members. A Group Member is a meter or a place that will be included in the Benchmarking chart data.

This topic will...


describe the procedure for adding members to an existing group. list the differences between adding single or multiple group members at one time.

Prerequisites
The ability to add Group members to a Group requires permissions associated with the following User Roles: Administration Full Access Role Bill Entry & Account Setup Role Building Admin Role Create the Group under which to add the Group Members. Refer to Adding a Category or Group help topic for more information.

Step-by-Step
Adding Members to a Place Group 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View will be displayed on the left, divided by place groups and meter groups. 2. Click to expand the Place Category under which the Group resides. 3. Click to highlight the Place Groups tree node where the members will be added. 4. Click the Add button beneath the tree view.

2013 EnergyCAP, Inc.

5. On the Single/Multi tab, click the radio button to add either one or multiple members and then click Continue.

2013 EnergyCAP, Inc.

6. On the Select Members tab, complete all relevant fields and then click Continue. If Single was selected on the previous tab: Select the place/meter on the tree. If Multiple was selected on the previous tab, select the Topmost Place filter and enter any relevant filter information in the fields provided.

2013 EnergyCAP, Inc.

7. On the confirmation tab, review all Group Members listed in the box. Uncheck any unwanted Group Members.

2013 EnergyCAP, Inc.

8. Click Finish. The Group Member Wizard will close and the charts will recalculate based on the new group members added. Adding Members to a Meter Group 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View will be displayed on the left, divided by place groups and meter groups. 2. Click to expand the Category under which the Group resides. 3. Click to highlight the Meter Groups tree node where the members will be added. 4. Click the Add button beneath the tree view.

2013 EnergyCAP, Inc.

5. On the Single/Multi tab, click the radio button to add either one or multiple members and then click Continue.

6.
2013 EnergyCAP, Inc.

6. On the Select Members tab, complete the relevant filters and then click Continue. If Single was selected on the previous tab: Select the place/meter on the tree. If Multiple was selected on the previous tab, select the Topmost Place filter and enter any relevant filter information in the fields provided.

7. On the second Select Members tab, Enter any additional relevant filter information in the fields provided and then click Continue.

2013 EnergyCAP, Inc.

8. On the Confirmation Tab, review all Group Members listed in the box. Uncheck any unwanted Group Members.

2013 EnergyCAP, Inc.

9. Click Finish. The Group Member Wizard will close and the charts will recalculate based on the new group members added.

Rules & Restrictions


Group members cannot be added the Auto-Groups, indicated by the blue color folder. Auto-Groups are automatically generated by the application and cannot be modified. Only Buildings/Meters can be selected on the tree with the Single Building/Meter group member option. In order to select an Organization on the tree, select all the buildings under the Organization using the Multiple Building selection option. Group Members can be added at any time, not just when creating the Group.

Additional Information
To include all buildings/meters on the confirmation tab of the wizard, select Multiple on the first tab and do not enter any information on the Select Members tab.

2013 EnergyCAP, Inc.

Managing Categories & Groups


Description
Categories are a way of organizing multiple Groups. Multiple groups can be organized by category. Each Group displays roll-up data based on the collection of Meters or Places associated with the Group.

This topic will...


describe the process for viewing Groups. list explanations of the tabs and charts. list the Groups auto generated by the application.

Prerequisites
All User Roles EXCEPT Public - Reports Only are permitted to view Categories and Groups.

Step-by-Step
1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View will be displayed on the left, divided into Place and Meter Groups. 2. Click to expand the Place Category under which the Group resides. 3. Click any Place Group or Meter Group tree node. 4. Click any tab to view the corresponding charts. See Additional Information for a list of the tabs and the information displayed on them.

Rules & Restrictions


Any changes to how the charts are displayed can be updated in Ranking Options. Refer to the Ranking Options help topic for more information. Buildings with no data, buildings set to Exclude from Benchmark and buildings exceeding the Row Limit are not shown. Voided bills are excluded from all charts. Accruals, reversals and adjustments are included on all charts. Cost/area, use/area and unit cost data is processed in intermediate 'staging tables' in order to provide instant viewing results. The staging tables are updated automatically each hour. Bills entered, edited or deleted are NOT represented on charts until the staging tables have been updated.

Additional Information
The vertical line shows the average of included members FOR THE ENTIRE GROUP, which may include buildings not shown on this chart. Meter Group tabs are: General Cost Rank General group information Average Cost Per Day vs. Total Cost for Billing Period Range

2013 EnergyCAP, Inc.

Unit Cost Rank

Average unit cost ($ per unit) vs. Total Cost for Billing Period Range Average Use (unit) per Day vs. Total Cost for Billing Period Range Average Unit Cost ($ per unit) vs. Total Cost for Billing Period Range Average Unit Cost ($ per unit) vs. Total use (unit) for Billing Period Range Average Demand (unit) vs Total Cost for Billing Period Range

Use Rank

Unit Cost by Cost Rank

Unit Cost by Use Rank

Demand Rank

Place Group tabs are: General Cost/Area Rank Use/Area Rank Demand/Area Rank Cost Rank Use Rank HDD Sensitivity CDD Sensitivity General group information Annualized Cost per Area Annualized Use (unit) per Area Peak Demand Per Area Average Cost Per Day Average Use (unit) per Day

There are several Auto-Groups that are created by the application: Place Primary Use Auto-Group maintained for each place by primary use (i.e. courthouse, general office, higher education) maintained for each commodity (i.e. electric, natural gas)

Commodity Auto-Group

2013 EnergyCAP, Inc.

Meter Primary Use Auto-Group

maintained for each specified meter primary use (i.e. cooking, heat, office equipment) maintained for each commodity associated with a particular vendor maintained for every vendor and every utility rate associated with that vendor

Vendor-Commodity Auto-Group

Vendor-Rate Auto-Group

2013 EnergyCAP, Inc.

Ranking Options
Description
The charts that are displayed on all tabs of the Group folders in Groups & Benchmarking have default ranking options set by EnergyCAP that determine how the group data is collected and displayed. The default settings can be changed.

This topic will...


describe the process for navigating to ranking Options. explain each configuration listed in ranking Options.

Prerequisites
The ability to change ranking Options requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bldg Administrator

Step-by-Step
1. Select Groups & Benchmarking from the Main Menu. The Groups & Benchmarking Tree View will appear on the left. 2. Click the Settings button beneath the Tree View.

3. Remove, add or change any combination of fields. Refer to the Additional Information section of this topic

2013 EnergyCAP, Inc.

3. for an explanation of each field.

4. Click the Save button. Changes will take effect immediately.

Rules & Restrictions


The Limit Rows setting does not limit the vertical average line OR the average shown in the chart title. The vertical line and title show the average for all included Group members, which may include buildings and meters not shown on the chart display.

Additional Information
Fields listed on Ranking Options: Billing Period There are four options for Billing Period display: Last Twelve Months Last Calendar Year Last Fiscal Year User Defined Range Start Date This field is enabled if the User Defined Range for the Billing Period value is selected (previous option). This can be any date between January 1900 and December 2099.

2013 EnergyCAP, Inc.

End Date

This field is enabled if the User Defined Range for the Billing Period value is selected. This can be any date between January 1900 and December 2099. This date cannot be before the Start Date selected. There are two order options: Highest to Lowest Lowest to Highest

Order By

Commodity Filter

Any commodity can be selected. NOTE: This may remove all members from the chart if the commodity does not exist for the group. There are four options for Limit Rows display: 10 25 50 100

Limit Rows

Show Excluded

This option provides the ability to show or hide the excluded group members on the charts. The Average vertical line and Average amount in the title are only based on the included group members.

Sort DD Sensitivity By Exclude Zero Weather Load Meters

2013 EnergyCAP, Inc.

Excluding and Re-Including a Group Member


Description
It may be desirable to exclude a Group Member(s) from the benchmarking charts. Excluding a Group Member prevents display of the member data in the bar chart, and adjusts the median/average (vertical) line accordingly.

This topic will...


describe the process of excluding a Group Member from benchmarking charts.

Prerequisites
The ability to remove Group Members from a Group requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bldg Administrator

Step-by-Step
To Exclude a Group Member: 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View should appear on the left, divided into Place Groups and Meter Groups. 2. Click to expand the Category under which the Group resides. 3. Select the Place Groups or Meter Groups node from which members will be excluded. 4. Click on any tab other than the General tab. 5. On the tab selected, locate the group member to be excluded and 'mouse over' the member name to the left of the chart. The Exclude icon will appear to the left of the member name. 6. Click the Exclude icon. The member will be removed from the charts.

2013 EnergyCAP, Inc.

To Re-Include an Excluded Group Member: 1. Select Groups & Benchmarking from the Main Menu. The Groups Tree View should appear on the left, divided into Place Groups and Meter Groups. 2. Click to expand the Category under which the Group resides. 3. Select the Place Groups or Meter Groups node from which members will be re-included. 4. Click the General tab of selected Group. 5. Click the Checkbox to the left of the Group Member on the Group Members Excluded from Benchmarking chart table. 6. Click the Reinclude Member in Benchmarking Charts button. The Group Member will be added back onto the benchmarking charts, and the median/average vertical line will be adjusted accordingly.

2013 EnergyCAP, Inc.

Rules & Restrictions


A Group Member can be excluded from any Group (user-created AND auto-groups). An excluded member is not removed from a Group. Its data is simply not displayed or used in the calculations for the associated benchmarking charts.

Additional Information
Excluding a Group Member may be desirable when its values are insignificant for benchmarking purposes for reasons such as: The Group Member has very little cost associated with it. It is not worth the energy manager's time or effort. The Group Member has unique characteristics that exclude it from consideration for benchmarking. The Group Member has valid issues but these are already being addressed. A report including the member in the group display would reduce the value of the report. If there are more Group Members than the chart is configured to display, a specific Member may not appear on the chart. Up to 100 Group Members can be displayed at a time by changing the Limit Rows field under R anking Options. Refer to the Ranking Options help topic for more information.

2013 EnergyCAP, Inc.

Removing a Group Member


Description
Group members can be removed from user-created Groups at any time. A Group Member is a meter or a place that will be included in the Benchmarking chart data.

This topic will...


describe the process of removing a Group Member from a Group.

Prerequisites
The ability to remove Group Members from a Group requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bldg Administrator

Step-by-Step
1. Select Buildings & Meters from the Main Menu. The Buildings navigation Tree View will be displayed on the left. 2. Select the Meter or Building node to be removed from a group. 3. Select the Building Properties or Meter Properties Tab. If necessary, scroll down to view the Groups list. 4. Click the Remove icon to the left of the desired Group.

5. Click Yes in response to the confirmation message to remove the Group member.

2013 EnergyCAP, Inc.

Rules & Restrictions


Group members cannot be removed from auto-groups, indicated by the blue color folder. These are auto-generated by EnergyCAP, and cannot be modified. For auto-generated Group members, the Remove icon will not be available from list of Group members (Properties tab).

Additional Information
There is a distinct difference between Removing and Excluding Group Members from a Group. To Exclude a Group Member is to maintain the member's association with the Group but exclude the Place or Meter data from the benchmarking chart calculations. For more information, see Excluding and Re-Including a Group Member. To Remove a Group Member is to remove the member from the Group entirely.

2013 EnergyCAP, Inc.

Customers and Chargebacks Overview


Overview
The Customers & Chargebacks Tree View contains three separate organizational hierarchies consisting of: Customers and Chargeback Accounts Buildings and Chargeback Meters Chargeback Distributions

Rules & Restrictions


No drag and drop capabilities exist on this tree If a user is given access to the module, they are given access to all three sections of the Tree View.

2013 EnergyCAP, Inc.

Customer

2013 EnergyCAP, Inc.

Adding a Customer
This topic will... describe the process for adding a Customer from the Customers & Chargebacks tree describe the process for adding a Customer through Account Properties NOT describe how to attach Accounts to Customers. Please refer to Attaching a Customer to a Chargeback Account. Step-by-Step Adding a Customer from the Customers & Chargebacks tree 1. Select Customer & Chargebacks from the Main Menu. The Customers navigation Tree View will be displayed on the left. 2. Click the Add button below the tree view. Select Add Customer from the menu.

3. On the General tab, enter the Name and Code and then click Continue.

2013 EnergyCAP, Inc.

4. On the Contact Information tab, enter Customer Address information in the fields provided.

2013 EnergyCAP, Inc.

5. Click Finish. The Create Customer wizard will close. Adding a Customer from Account Properties 1. 2. 3. 4. Select Accounts from the Main Menu. The Accounts navigation Tree View will be displayed on the left. Select the chargeback account that the customer is to be added to. Click the Edit button below the tree view On the Customers tab, a. Click the Add button to the right of the of the customer dropdown. b. Add all relevant Customer information

2013 EnergyCAP, Inc.

5. Click Save. The window will close and the account properties will be updated.

2013 EnergyCAP, Inc.

Modifying a Customer
This topic will... describe the process for modifying Customer information. Step-by-Step 1. Select Customer & Chargebacks from the Main Menu. 2. Select the customer node that is to be modified. 3. Click the Edit button below the tree view.

4. On the General tab, the name and code can be modified.

2013 EnergyCAP, Inc.

5. On the Contact Information tab, the Customer Address information can be modified.

2013 EnergyCAP, Inc.

6. Click Save. The Customer Properties window will close.

2013 EnergyCAP, Inc.

Attaching a Customer to a Chargeback Account


Description It is recommended that all chargeback accounts have a customer attached to them. When creating a new Chargeback Account, a customer is required. If a Chargeback Account has been added in the past without a customer, the account is displayed under a node of the Customer tree labeled 'Accts w/o Customers'. This topic will... describe the process of attaching a customer from the Customers & Chargebacks tree describe the process of attaching a customer from the Accounts tree Step-by-Step Attaching a Customer from the Customers & Chargebacks tree 1. Select Customers & Chargebacks from the Main Menu. The Customers navigation Tree View will be displayed on the left. 2. Expand the Customer node, then expand the Accts w/o Customers node. 3. Highlight the Account the Customer will be attached to. 4. Click the Edit button beneath the Tree View.

5. Select the Customer tab of the Account Properties window. 6. On the Customer Tab, select the appropriate Customer from the dropdown. If the Customer does not exist, select the Add button to the right of the Customer dropdown. For more information, please refer to the Addin g a Customer help topic.

2013 EnergyCAP, Inc.

6.

7. Click Save. The window will close and the account should be displayed under the newly selected customer node in the tree. Attaching a Customer from the Acccount Tree 1. Select Accounts from the Main Menu. The Accounts navigation Tree View will be displayed on the left. 2. Highlight the Account the Customer will be attached to. 3. Click the Edit button beneath the Tree View.

2013 EnergyCAP, Inc.

4. Select the Customer tab of the Account Properties window. 5. Select the appropriate Customer from the dropdown. If the Customer does not exist, select the Add button to the right of the Customer dropdown. For more information, please refer to the Adding a Customer help topic.

2013 EnergyCAP, Inc.

6. Click Save. The window will close and the account should be displayed under the newly selected customer node in the tree. Rules & Restrictions Customers can ONLY be attached to Chargeback Accounts The Accts w/o Customers tree node is always present on the Customer tree, regardless of whether Additional Information It is recommended that accounts NOT be transferred from one customer to another. Instead, create a new account and attach the existing meter to it.

2013 EnergyCAP, Inc.

Removing a Customer
Description Any customer can be removed from the tree. This topic will... describe the process for deleting a Customer. Step-by-Step 1. Select Customer & Chargebacks from the Main Menu. 2. Select the customer node to be deleted. 3. Click the Delete button below the tree view.

4. On the confirmation window, click Yes. The confirmation window will close and the customer will be removed from the tree. Rules & Restrictions You must delete all accounts assigned to this customer before the customer can be deleted.

2013 EnergyCAP, Inc.

Chargeback Accounts & Meters

2013 EnergyCAP, Inc.

Creating a Chargeback Account


Description Before creating any Chargeback Setup, it is necessary to create the account/meter/vendor associations related to the utility billing data. This topic will... describe the process for creating a new chargeback account from the Customers & Chargebacks Tree View. NOT describe the process for creating a traditional utility bill account. Please refer to Creating an Account. Prerequisites The ability to add a chargeback account requires permissions associated with the following User Roles: Step-by-Step 1. Select Customers & Chargebacks from the Main Menu. The Chargeback Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Chargeback Account/Meter menu option.

3. Review the instructional information provided with the Introduction tab. Then click Continue.

2013 EnergyCAP, Inc.

3.

4. On the Cost Center tab, choose the appropriate radio button and then click Continue. Create a New Cost Center will create a new cost center for the account. Refer to the Creating a Cost Center Center topic for more explicit cost center creation help. Select a Cost Center will associate the account with an existing cost center. Use the hierarchy to select the desired cost center.

2013 EnergyCAP, Inc.

5. On the Service Address tab, enter Service Address information in the fields provided and then click Continue .

2013 EnergyCAP, Inc.

6. On the Vendor tab, either: Select the desired vendor using the Vendor drop-down OR Add a new vendor by clicking the Add button. Refer to the Adding a Vendor topic for more explicit vendor help. 7. Select the radio button corresponding to the Vendor Type. Then click Continue.

2013 EnergyCAP, Inc.

8. On the Customer Tab, complete the field and then click Continue. Select the desired customer using the Customer drop-down OR Add a new customer by clicking the Add button. Refer to the Adding a Customer topic for more explicit customer help.

2013 EnergyCAP, Inc.

9. On the Account Type tab, complete all fields and then click Continue. a. Enter the account Account Number. b. Click a radio button to indicate how the Account Name will be created. Complete additional fields if displayed. c. Click a radio button to select the appropriate Account Type.

2013 EnergyCAP, Inc.

To continue through the meter section of the wizard, refer to the Creating a Chargeback MeterAdding a Meter topic for more explicit meter help.

Rules & Restrictions An Account can only be placed under a cost center. This includes the topmost cost center listed on the tree. Chargeback Accounts can only be attached to one meter. Additional Information The Chargeback Account/Meter wizard can also be launched from the Chargeback Distribution Setup.

2013 EnergyCAP, Inc.

Creating a Chargeback Meter


Description In EnergyCAP, a meter represents a commodity associated with a utility point of service. All utility bills are associated with a meter, and every meter must be associated with a utility account and a building. This mandatory structure standardizes reporting and viewing of data. Bills must be associated with a meter even when no physical meter exists (EXAMPLE: trash, sewer). This topic will... describe the process for adding a chargeback meter. NOT describe the process for adding a traditional meter. Please refer to Creating a Meter. Prerequisites The ability to add chargeback meters requires permissions associated with the following User Roles: Before a meter can be created, the building under which the meter will reside in the organizational hierarchy must already exist. Obtain a paper copy or facsimile of the utility bill to be modeled. The bill will provide most of the information necessary for setting up the meter. Step-by-Step 1. Select Customers & Chargebacks from the Main Menu. The Chargeback navigation Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Chargeback Account/Meter menu option.

3. Review the instructional information provided with the Introduction tab. Then click Continue.

2013 EnergyCAP, Inc.

3.

4. On the Cost Center tab, choose the appropriate radio button and then click Continue. Create a New Cost Center will create a new cost center for the account. Refer to the Creating a Cost Center Center topic for more explicit cost center creation help. Select a Cost Center will associate the account with an existing cost center. Use the hierarchy to select the desired cost center.

2013 EnergyCAP, Inc.

5. On the Service Address tab, enter Service Address information in the fields provided and then click Continue .

2013 EnergyCAP, Inc.

6. On the Vendor tab, either: Select the desired vendor using the Vendor drop-down OR Add a new vendor by clicking the Add button. Refer to the Adding a Vendor topic for more explicit vendor help. 7. Select the radio button corresponding to the Vendor Type. Then click Continue.

2013 EnergyCAP, Inc.

8. On the Customer Tab, complete the field and then click Continue. Select the desired customer using the Customer drop-down OR Add a new customer by clicking the Add button. Refer to the Adding a Customer topic for more explicit customer help.

2013 EnergyCAP, Inc.

9. On the Account Type tab, complete all fields and then click Continue. a. Enter the account Account Number. b. Click a radio button to indicate how the Account Name will be created. Complete additional fields if displayed. c. Click a radio button to select the appropriate Account Type.

2013 EnergyCAP, Inc.

10. On the Create/Select tab, choose the appropriate radio button and the click Continue. a. Create a new meter will launch the Meter Wizard and add a new meter to the Building hierarchy. b. Select an existing meter will associate an existing chargeback meter with the new account.

2013 EnergyCAP, Inc.

11. On the Place Assignment tab, choose the appropriate radio button and then click Continue. Create a new Building will create a new building for the meter. Refer to the Adding an Organization or Building topic for more explicit building creation help. Select a Place will associate the meter with an existing building. Use the hierarchy to select the desired building.

2013 EnergyCAP, Inc.

12. On the General Info tab, complete all appropriate fields and then click Continue. a. Based on the commodity selected, the Name and Code are automatically generated. Edit these fields if desired. b. To enter the Address, click the Edit button and add meter address information in the fields provided. Only ZIP/Postal Code is required. Then click OK. c. (optional) Complete the Serial Number information for the meter. Typically, this number is physically stamped on the device by the manufacturer.

2013 EnergyCAP, Inc.

13. On the Additional Meter Info tab, complete all appropriate fields and then click Continue. a. Select the meter primary use from the Primary Use drop-down OR Add a new primary use by clicking the Add button and following the prompts provided. b. In the G/L Code field, enter an accounting code used to specify how charges are posted to an organizations General Ledger. This code is only necessary if the organization is exporting billing data to an accounting system. c. If desired, complete the optional Bill Entry Note, which will be associated with the meter. Bill Entry Notes are visible during utility bill data entry for the associated account.

2013 EnergyCAP, Inc.

14. On the Rate Code tab, choose the appropriate radio button and then click Continue. The Rate Code provides a list to select an existing vendor rate. The Create a new rate for this vendor provides fields to enter the new Rate Code and enter the associated unit of measure.

2013 EnergyCAP, Inc.

15. If the commodity is Electric, select any demand options on the Demand tab and then click Continue.

2013 EnergyCAP, Inc.

16. On the Template Selection tab, select the desired bill entry template. Refer to Modifying Bill Entry Templates f or additional template information. 17. Then click Finish to save the meter information and close the Meter Wizard.

2013 EnergyCAP, Inc.

18. Review all information from the Confirmation tab; then click Finish to close the Account/Meter Wizard.

2013 EnergyCAP, Inc.

Rules & Restrictions The Account/Vendor combination must be unique. The same account number can only be used for different accounts when each of the accounts has a different vendor. Chargeback accounts can only have one active meter attached to them. When the wizard is launched from a Chargeback Distribution setup, the Commodity field on the General Info tab will be read only. It is automatically set to the same commodity as the Master Meter of the current distribution.

2013 EnergyCAP, Inc.

Chargeback Distribution

2013 EnergyCAP, Inc.

Setting up a Chargeback Distribution


Description The bill split specifications must be defined before running the Chargeback Processor. These specifications are established by creating a Chargeback Distribution. This topic will... describe the process for creating a new Chargeback Distribution from the Customers & Chargebacks Tree View. Step-by-Step 1. Select Customers & Chargebacks from the Main Menu. The Chargeback Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Create Chargeback Distribution menu option.

3. On the general tab, complete all the fields and then click save. a. Search for the account that the Distributions Master Meter is attached to. b. Select the master meter from the dropdown c. Change the Effective Date if it is a date other than 01/01/2004

2013 EnergyCAP, Inc.

c.

4. From the Chargeback Setup tab, manipulate the setup tree until it depicts the correct Chargeback Distribution. Refer to the Additional Information section below for an explanation of control functions.

2013 EnergyCAP, Inc.

5. When complete, click Save. The new distribution will be displayed on the tree to the left. Rules & Restrictions A meter can only be added as a destination meter once per distribution A destination meter must be of the same commodity as the master meter. A master meter of one distribution can also be a destination meter of another distribution A meter may show up in the create bill widget search multiple times if the meter is attached to more than one account. Additional Information Object Functionality Current add options are Add an Account Charge and Add a Bill Split. Selecting either menu option add a widget to the Chargeback Setup directly under the add button

2013 EnergyCAP, Inc.

Account charges will be added to the bills created for the destination meters. The position of the Account Charge widget in the setup hierarchy determines which meters the account charge will be applied to.

The meter and customer selected will be the recipient of the bill split. If the meter cannot be found using the search, a new meter can be added by selecting the Add button to the right of the field. Selecting this will launch the account/meter wizard. No setup information will be lost by selecting this button.

The exact amount of the master bill that will be allocated to the destination meter is determined by the split percentage field. Use the Add Split button to incorporate more destination meters.

2013 EnergyCAP, Inc.

Modifying a Chargeback Distribution Version


Description It is possible to modify any part of an existing chargeback setup. This includes the effective dates, meters attached, and charges. This topic will... describe the process for modifying a chargeback setup Prerequisites an existing chargeback setup must be accessible on the chargeback tree Step-by-Step 1. Select Customers & Chargebacks from the Main Menu. The Customer's navigation Tree View will be displayed on the left. 2. Highlight the Chargeback Distribution master meter node to be modified. 3. Select the Chargeback Setup tab 4. Click the Edit button.

5. From the Chargeback Setup tab, manipulate the setup tree until it depicts the correct Chargeback Distribution. Refer to the Setting up a Chargeback Distribution help page for the explanation of control functions. 6. When complete, click Save. The new distribution setup will be displayed on the tree to the left.

2013 EnergyCAP, Inc.

Rules & Restrictions The version edit pencil becomes visible once the chargeback setup edit button has been selected. Any portion of the setup can be modified except the master meter. When a meter is removed from the setup, it will also be removed from the tree hierarchy

2013 EnergyCAP, Inc.

Removing a Chargeback Distribution Version


Description It is possible to delete a version of chargeback setup. This topic will... describe the process for removing a chargeback setup Prerequisites an existing chargeback setup must be accessible on the chargeback tree Step-by-Step 1. Select Customers & Chargebacks from the Main Menu. The Customer's navigation Tree View will be displayed on the left. 2. Highlight the Chargeback Distribution master meter node to be modified. 3. Select the Chargeback Setup tab 4. Click the Delete button.

5. If the only version, click Yes on delete confirmation. Chargeback setup will be removed from the tree. 6. If one of multiple versions a Setup Chargeback window will appear. On the gap options tab, select the appropriate radio button and then click Save.

2013 EnergyCAP, Inc.

6.

Rules & Restrictions Removing a chargeback setup does not remove the bills already split to the destination meters.

2013 EnergyCAP, Inc.

Accounts Overview
Overview
The Accounts Tree View displays an organization's hierarchy of the accounting side of utility bill management, shown as Cost Centers and their related Accounts. The structure of the Accounts Tree View is user configurable to help provide the most valuable analytics and display of utility bill data as typically needed by accounting departments. Similar to other Tree Views in EnergyCAP, all bill data represented by an account is rolled up to each higher level of Cost Center that the account falls within providing aggregated PowerViews. For any Account or Cost Center that is selected, PoweViews are displayed with data relevant to that node within the tree. The Accounts tree is often organized in one of three ways: by departments, vendors, or to mimic the Buildings & Meters tree organization. All nodes of the tree can be moved by dragging and dropping to provide flexibility throughout the setup process. As with other key organizational nodes in other Tree Views, Cost Centers provide the added value of being a filter on many reports and throughout the application as an additional method to quickly find a group of accounts. The Actual Data tab lists various sub-tabs that display actual bill data into yearly totals, monthly breakdowns, GHG emissions and other trend-type charts. Depending on what kind of node that is selected, some tabs may appear or disappear if it is not relevant to the selected item. A Bills tab, for instance, will only display when an Account is selected.

Rules & Restrictions


The Accounts view permission is required to access this view Multiple organizational levels can be created by adding Cost Centers under other Cost Centers.

2013 EnergyCAP, Inc.

Creating a Cost Center


Description
A Cost Center is a group or collection of related accounts. Cost Centers are used to organize vendor accounts in a hierarchy representing your organization's financial structure. Cost Centers also provide a way of reporting and viewing energy use and cost data related to groups of accounts. Cost Centers can contain other Cost Centers, as well as individual accounts.

This section will...


describe the process for adding a cost center.

Prerequisites
The ability to add cost centers requires permission associated with the following User Roles: Administration Full Access Bill Entry & Account Setup

Step-by-Step
1. Select Accounts from the Main Menu. The Accounts Tree View will be displayed on the left. 2. Click the Add button below the Tree View. Click the Add Cost Center menu option.

3. On the General tab, input the general information:

2013 EnergyCAP, Inc.

3. In the Name field, enter the display name for the Cost Center. In the Code field, a code based on the name will be automatically created. This field can be changed to any desired value. Spaces and special characters cannot be included in the Code.

4. Click Finish. The Cost Center/Account Wizard will close and the new Cost Center will be added to the tree hierarchy.

Rules & Restrictions


A Cost Center can only be placed under another Cost Center. This includes the topmost Cost Center listed on the tree.

2013 EnergyCAP, Inc.

Creating an Account
Description
Before entering utility bill data, it is necessary to create the account/meter/vendor associations related to the utility billing data, and to choose a utility bill template for entering desired billing information.

This section will...


describe the process for creating a new utility bill account from the Accounts Tree View. describe the process for creating a new utility bill account from the Buildings and Meters Tree View. NOT describe the process for creating a new chargeback account. Please refer to Creating a Chargeback Account.

Prerequisites
The ability to Create an Account is incorporated in the following User Roles: Administration Full Access Bill Entry & Account Setup Obtain a paper copy or facsimile of the utility bill to be modeled. The bill will provide information necessary for setting up the account. Every account must be set up with at least one meter. Be prepared to continue to Add a Meter topic for the help with the Meter portion of the Wizard.

Step-by-Step
1. The Account/Meter Wizard can accessed via Accounts or Buildings & Meters. a. To add from Accounts: i. Select Accounts from the Main Menu. The Accounts navigation Tree View will be displayed on the left. ii. Click the Add button below the Tree View. Click the Add Account menu option.

2013 EnergyCAP, Inc.

b. To add from Buildings & Meters: i. Select Buildings and Meters from the Main Menu. The Buildings and Meters navigation Tree View will be displayed on the left. ii. Click the Add button below the Tree View. Click the Add Meter menu option.

2013 EnergyCAP, Inc.

2. Review the instructional information provided with the Introduction tab. Then click Continue.

3. On the Cost Center tab, choose the appropriate radio button: Currently Selected Cost Center will display the cost center highlighted on the tree when launching the wizard, if any. Create a New Cost Center will create a new cost center for the account. Refer to the Creating a Cost Center Center topic for more explicit cost center creation help. Select a Cost Center will associate the account with an existing cost center. Use the hierarchy to select the desired cost center. 4. On the Service Address tab, enter Service Address information in the fields provided and then click Continue .

2013 EnergyCAP, Inc.

5. On the Vendor tab, either: Select the desired vendor using the Vendor drop-down OR Add a new vendor by clicking the Add button. Refer to the Adding a Vendor topic for more explicit vendor help. 6. Select the radio button corresponding to the Vendor Type. Then click Continue.

2013 EnergyCAP, Inc.

7. On the Account Type tab, complete all fields and then click Continue. a. Enter the account Account Number. b. Click a radio button to indicate how the Account Name will be created. Complete additional fields if displayed. c. Click a radio button to select the appropriate Account Type.

2013 EnergyCAP, Inc.

To continue through the meter section of the wizard, refer to the Adding a Meter to pic for more explicit meter help.

Rules & Restrictions


An Account can only be placed under a cost center. This includes the topmost cost center listed on the tree. Every account must be set up with at least one meter.

2013 EnergyCAP, Inc.

Adding a Meter from an Existing Account


Description
A meter represents a commodity associated with a utility point of service. All utility bills are associated with a meter, and every meter must be associated with a utility account and a building. This mandatory structure standardizes reporting and viewing of data. Bills must be associated with a meter even when no physical meter exists (EXAMPLE: trash, sewer).

This topic will...


describe the process for adding a meter from an existing account.

Prerequisites
The ability to add meters requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup Obtain a paper copy or facsimile of the utility bill to be modeled. The bill will provide most of the information necessary for setting up the meter.

Step-by-Step
1. Select Accounts from the Main Menu. The Account Tree View will be displayed on the left. 2. Select the Account that the new Meter is going to be attached to. 3. Select the General sub tab. 4. Click the Add Meter button.

5.
2013 EnergyCAP, Inc.

5. On the Create/Select Meter tab, choose the appropriate radio button and then click Continue. Create a new meter will add a new meter to the Building hierarchy. This is the process outlined below. Select an existing meter will associate an existing meter with the new account. Selecting this option will skip ahead to the Rate Code tab.

6. On the Place Assignment tab, choose the appropriate radio button and then click Continue. Currently Selected Building will associate the meter with the building you previously selected in the Tree View. Create a new Building will create a new building for the meter. Refer to the Adding an Organization or Building topic for more explicit building creation help. Select a Place will associate the meter with an existing building. Use the hierarchy to select the desired building.

2013 EnergyCAP, Inc.

7. On the General Info tab, select the commodity and then click Continue. a. Based on the commodity selected, the Name and Code are automatically generated. Edit these fields if desired. b. The address defaults to the address of the building with which the meter is associated. To change the Address, click the Edit button and add meter address information in the fields provided. Only ZIP/Postal Code is required. Then click OK. c. (optional) Complete the Serial Number information for the meter. Typically, this number is physically stamped on the device by the manufacturer.

2013 EnergyCAP, Inc.

8. On the Additional Meter Info tab, complete the relevant fields and then click Continue. a. Select the meter primary use from the Primary Use drop-down OR add a new primary use by clicking the Add button and following the prompts provided. b. In the G/L Code field, enter an accounting code used to specify how charges are posted to an organizations General Ledger. This code is only necessary if the organization is exporting billing data to an accounting system. c. If desired, complete the optional Bill Entry Note, which will be associated with the meter. Bill Entry Notes are visible during utility bill data entry for the associated account.

2013 EnergyCAP, Inc.

9. On the Rate Code tab, choose the appropriate radio button and then click Continue. The Rate Code button provides a drop-down list to select an existing vendor rate. The Create a new rate for this vendor button provides fields to enter the new Rate Code and select the associated unit of measure.

2013 EnergyCAP, Inc.

10. If the commodity is Electric, select any demand options on the Demand tab and then click Continue.

2013 EnergyCAP, Inc.

11. On the Template Selection tab, Select the desired bill entry template. Refer to Modifying Bill Entry Templates for additional template information.

2013 EnergyCAP, Inc.

12. Click Finish to save the meter information and close the Meter Wizard.

2013 EnergyCAP, Inc.

Modifying Cost Centers and Accounts


Description
All Cost Centers and Accounts have specific properties that can be modified at any time. These properties include: name and code identifiers, address properties, etc.

This topic will...


describe the process of modifying existing Cost Center properties. describe the process of modifying existing Account Properties.

Prerequisites
The ability to modify Cost Centers and Accounts requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup

Step-by-Step
Modifying a Cost Center

1. Select Accounts from the Main Menu. The Accounts Tree View will be displayed on the left. 2. Select the cost center node to be modified. If necessary, click to expand the Cost Center hierarchy to display hidden nodes. 3. Click the Edit button below the Tree View.

2013 EnergyCAP, Inc.

4. On the General tab; Name: Edit the Cost Center name. Code: Edit the Cost Center code.

2013 EnergyCAP, Inc.

5. Click Save. The Cost Center Properties window will close.

Modifying an Account

1. Select Accounts from the Main Menu. The Accounts Tree View will be displayed on the left. 2. Select the Account to be modified. If necessary, click to expand the Cost Center hierarchy to display hidden nodes. 3. Click the Edit button below the Tree View.

2013 EnergyCAP, Inc.

4. On the General tab: Name: Edit the Building name. Code: Click the Edit button to change the existing code. Address: Click the Edit button to change the existing address

2013 EnergyCAP, Inc.

5. On the memo tab, a. To edit the Memo, click the Edit Memo button. b. When done, click the Save Memo button.

2013 EnergyCAP, Inc.

6. On the Deposit Info tab, modify any of the available fields.

2013 EnergyCAP, Inc.

7. Click Save. The Account Properties window will close.

Rules & Restrictions


The Account Code must be unique for the account/vendor combination. It cannot be the same as an existing code for the same vendor. When modifying a Name, the existing associated Code will not be changed to match the new name. It must be manually changed if desired.

2013 EnergyCAP, Inc.

Moving a Cost Center or Account


Description
As the organization structure changes, it is sometimes necessary to reorganize Cost Centers and/or move accounts from one Cost Center to another.

This section will...


describe the process for moving a Cost Center. describe the process for moving an Account. describe what types of moves are accepted.

Prerequisites
The ability to move Cost Centers and Accounts requires permissions associates with the following User Roles: Administration Full Access Bill Entry & Account Setup

Step-by-Step
1. 2. 3. 4. Select Accounts from the Main Menu. The Accounts Tree View will be displayed on the left. Locate the Account/Cost Center to be moved. Click and hold to select it; then drag the selected item to the desired destination. Release the left mouse button when the correct destination has been highlighted. The selected item(s) will be relocated under the new node of the tree, and a confirmation message will be displayed. 5. Click Yes to confirm the move.

Rules & Restrictions


An Account can only be (re)located under a Cost Center. A Cost Center can only be (re)located under another Cost Center (not an Account). When a Cost Center is moved, all Cost Centers and Accounts under that node of the tree will be moved with it. An Account or Cost Center will ONLY be relocated to the selected node of the tree if the node is an acceptable location for the object being moved. When the Cost Center or Account is dragged to an unacceptable location (such as under an Account, or outside the Tree View), a red caution icon will be displayed.

2013 EnergyCAP, Inc.

Vendors and Rates Overview


Overview
The Vendors and Rates Tree View provides a heirarchical view of the Vendors and their associated Rates that are create during EnergyCAP setup. Each node of the Vendor and Rates tree provides PowerView rollup charts and account list that show utility cost and consumption for each Vendor. Similar PowerView rollup charts are also displayed for each commodity and rate under a Vendor. Vendors and their associated Rates can be created from this Tree View. Typically, however, they are most often created when setting up new Accounts and Meters as part of the wizard or Setup Import process.

Rules & Restrictions


The Contacts view permission is required to access this view

2013 EnergyCAP, Inc.

Adding a Vendor
Description
Vendor information must be established before inputting utility bill data associated with that Vendor.

This topic will...


describe the process for adding a Vendor.

Prerequisites
The ability to add accounts requires permissions associated with one of the following User Roles: Administrator - Full Access Bill Entry & Account Setup

Step-by-Step
1. Select Vendors & Rates from the Main Menu. The Vendors & Rates navigation tree view will appear on the left. 2. Click the Add button beneath the tree view. Click the Add Vendor menu option.

3. Input all General Information: a. In the Name field, enter the display name for the Vendor. b. In the Code field, a Vendor Code based on the name will be automatically created. This field can be changed to any desired value. c. If known, enter the full vendor website URL in the Website field. To check the accuracy of the website URL entered, select View Site. The website associated with the URL will open in a new window.

2013 EnergyCAP, Inc.

3.

c.

4. Click Save. The Add New Vendor window will close and the Vendor will be displayed in the tree.

Rules & Restrictions


A Vendor can only be created if the Vendors & Rates root node is selected. If an existing vendor node is highlighted when the Add button is selected, the Rate Wizard window for the selected vendor will appear. The Vendor Code for each vendor MUST be uniqueit cannot be the same as any other existing Vendor in the database. The Vendor Code is up to 16 characters long, and is automatically created based on the Vendor Name. The code field does not allow special characters, only numbers and letters. If special characters are entered in the Code field, they will be removed when the Vendor Code is created. If the Name is not unique, the code will be created with a unique numeric extension (e.g. name-01). This may result in the entered code being truncated.

2013 EnergyCAP, Inc.

Adding a Rate Code


Description
A Vendor provides a Rate Code(s) for each commodity for which services are offered.

This topic will...


describe the process for adding a Rate Code associated with a vendor.

Prerequisites
The ability to add a Rate Code requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup

Step-by-Step
1. Select Vendors & Rates from the Main Menu. The Vendors & Rates navigation tree view will be displayed on the left. 2. Click the Add button below the tree. Click the Add Vendor menu option.

3. On the General tab: Enter a unique Rate Code. Select a commodity by clicking the Commodity drop-down list.

2013 EnergyCAP, Inc.

3.

4. Click Save. The Rate Wizard window will close and the rate code is added.

Rules & Restrictions


The Rate Code must be unique for the rate and commodity combination selected. The same Rate Code can exist for another Vendor OR another commodity for the same Vendor.

Additional Information
Rate Code is used to create the various groups under Vendor-Rate Auto-Group, located in Groups & Benchmarking

2013 EnergyCAP, Inc.

Modifying a Rate Code


Description
A Vendor provides a Rate Code(s) for each commodity for which services are offered.

This topic will...


describe the process for modifying a Rate Code associated with a vendor.

Prerequisites
The ability to modify a Rate Code requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup

Step-by-Step
1. Select Vendors & Rates from the Main Menu. The Vendors & Rates navigation tree view will be displayed on the left. 2. Click to expand the Vendor under which the rate exists. 3. Click to expand the commodity for the rate to be modified. 4. Click to highlight the rate to be modified. 5. Click the Editbutton below the tree view.

6. On the general tab, edit the new Rate Code.

2013 EnergyCAP, Inc.

6.

7. Click Save.The Rate Properties window will close and the Rate Code will be updated.

Rules & Restrictions


The Rate Code must be unique for the rate and commodity combination selected. The same Rate Code can exist for another Vendor OR another commodity for the same Vendor.

Additional Information
Rate Code is used to create the various groups under Vendor-Rate Auto-Group, located in Groups & Benchmarking

2013 EnergyCAP, Inc.

Bill Processing Overview


Overview
Bill Processing is the heart of utility bill management within EnergyCAP. It is the main view for creating bills and batches, auditing existing bills, processing Cost Avoidance data, and creating Chargeback bills for Customers. Utility Bills can be created manually or through a flexible bill import wizard using an Excel file template. EnergyCAP also allows users to create customized bill lists to help find and organize specific workflow processes. Each list can be filtered, sorted and organized to display just the bills necessary. As with other bill lists in EnergyCAP, the results can then be exported to Excel for further processing and sharing.

Rules & Restrictions


The Workflow permission is required to view this Bill Processing Audit - Execute permission is required to run and modify audit groups Cost Avoidance Processor - Execute permission is required to process Cost Avoidance data

2013 EnergyCAP, Inc.

Bill Entry
Topics in this section provide guidance on Bill Entry in EnergyCAP.

2013 EnergyCAP, Inc.

Entering a Bill
Description Utility bill data represents the core of EnergyCAP. Bills can be entered manually one-by-one in a user session, or they can be imported. This topic will... describe the process for manually entering utility bills into EnergyCAP. Prerequisites The ability to manually enter utility bill data requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup Bill Entry Obtain a paper copy or facsimile of the utility bill to be entered.

Step-by-Step 1. Navigate to the bill entry window in one of the following ways: From the Bill Processing menu: 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will appear. 2. Select Enter Bills from the Tree View. 3. Click the Enter Bills button.

4.
2013 EnergyCAP, Inc.

4. Enter the Account number in the field provided. Or, if the account number is unknown, begin typing the Name, Street, City, Vendor or any meter information. As values are entered, a list of matching accounts will be displayed. 5. Click to select the desired account from the list. From a Meter: 1. Select Buildings & Meters from the Main Menu. The Buildings Tree View will appear. 2. Click to expand the building node under which the Meter resides. 3. Click to highlight the meter where the bill is attached. 4. Select the Bills tab. 5. Click the Add Bill button. If there are multiple accounts attached to the meter, select the account from the add bill button drop down.

From an Account: 1. Select Accounts from the Main Menu. 2. Click to expand the Cost Center node(s) under which the account resides. 3. Click to highlight the account where the bill is attached. 4. Select the Bills tab. 5. Click the Add Bill button.

2013 EnergyCAP, Inc.

2. Enter all relevant bill information.

3. Click Save Bill. The Bill Entry window will close and the bill will be added to the bill list.

2013 EnergyCAP, Inc.

Rules & Restrictions Number formatting: EnergyCAP automatically formats numbers. No commas are needed in the numeric fields. Account Level Charges: Account level charge assignment is prompted after Save Bill is selected if the total cost and pay amount do not match. Bill Entry Field Defaults: The bill entry window automatically defaults to certain dates: Start Date End Date Due Date Statement Date The end date of the previously-entered bill 30 days from the start date 30 days from the end date 3 days after the end date

Additional Information Date entry shorthand: It is not necessary to enter the complete date. If using the keypad, separate days, months, and years with slashes (/), periods (.), or hyphens (-). If the bill is for the current year, leave it off and EnergyCAP will auto-complete the current year. See the examples below: 4.12 = 04/12/xxxx where xxxx represents the current year. 4-12-09 = 04/12/2009 0412 = 04/12/2010

2013 EnergyCAP, Inc.

Modifying a Utility Bill


Description It is often necessary to edit existing utility bill data. This topic will... describe the process for editing existing utility bills. Prerequisites The ability to modify an existing utility bill requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup Bill Entry When possible, obtain a paper copy or facsimile of the utility bill to be edited. Step-by-Step 1. Navigate to the bill entry window in one of the following ways: From the Bill Processing menu: 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will appear. 2. Click to select the desired Bill List from the Tree View. 3. Click on the bill record row in the grid. The row will expand. 4. Click the Editbutton for the desired bill record.

2013 EnergyCAP, Inc.

From a Meter: 1. Select Buildings & Meters from the Main Menu. The Buildings Tree View will appear. 2. Click to expand the building node under which the Meter resides. 3. Click to highlight the meter where the bill is attached. 4. Click to select the Bills tab. 5. Click on the bill record row in the grid. The row will expand. 6. Click the Edit button for the desired bill record.

From an Account: 1. Select Accounts from the Main Menu. 2. Click to expand the Cost Center node(s) under which the account resides. 3. Click to highlight the account where the bill is attached. 4. Select the Bills tab. 5. Click on the bill record row in the grid. The row will expand. 6. Click the Edit button for the desired bill record.

2013 EnergyCAP, Inc.

2. Enter all relevant bill information.

3.
2013 EnergyCAP, Inc.

3. Click Save Bill. The Bill Entry window will close and the updated bill will be saved to the bill list. Rules & Restrictions Number formatting: The application automatically formats numbers. No commas are needed in the numeric fields. Account Level Charges: Account level charge assignment is prompted after Save Bill is selected if the total cost and pay amount do not match. Bill Entry Field Defaults: The bill entry window automatically defaults to certain dates: Start Date End Date Due Date Statement Date The end date of the previously-entered bill 30 days from the start date 30 days from the end date 3 days after the end date

Additional Information Date shorthand: It is not necessary to enter the complete date. If using the keypad, separate days, months, and years with slashes (/), periods (.), or hyphens (-). If the bill is for the current year, leave it off and EnergyCAP will auto-complete the current year. See the examples below: 4.12 = 04/12/xxxx where xxxx represents the current year. 4-12-09 = 04/12/2009 0412 = 04/12/2010

2013 EnergyCAP, Inc.

Adding Bill Problem Flags Manually


Description Bill Problem Flags are created automatically during the audit process. It is also possible to add one or more Problem Flags to a bill manually, in order to document abnormal circumstances and to serve as a reminder for future action. This topic will... describe the process of adding a Problem Flag manually. provide a list of available problem flag messages. Prerequisites The ability to manually add a Bill Problem flag requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup Step-by-Step 1. Navigate to the bill requiring the problem flag in one of the following three ways: From any Bill Processing List: 1. Select Bill Processing from the Main Menu. The Bills Processing tree view will be displayed. 2. Select any available Bill List from the tree. This includes Enter Bills, Bills with Problem Flags, or any node listed under Bill Lists. 3. Use the filters to narrow down the list until the bill can be located. See Filtering Bill Lists f or more information. 4. Click on the bill record row in the grid. The row will expand. 5. Click the Edit button for the desired bill record.

2013 EnergyCAP, Inc.

From Buildings & Meters: 1. 2. 3. 4. 5. Select Buildings & Meters from the Main Menu. Click to expand the Organization node(s) under which the meters building resides. Click to expand the building node under which the Meter resides. Click to highlight the meter associated with the bill. Select the Actual Data tab and the Bills subtab; then scroll the bill list until the bill can be located. See Filtering Bill Lists for more information. 6. Click on the bill record row in the grid. The row will expand. 7. Click the Edit button for the desired bill record.

2013 EnergyCAP, Inc.

From Accounts: 1. 2. 3. 4. 5. 6. Select Accounts from the Main Menu. Click to expand the Cost Center node(s) under which the account resides. Click to highlight the account associated with the bill. Select the Bills tab. Click on the bill record row in the grid. The row will expand. Click the Edit button for the desired bill record.

2013 EnergyCAP, Inc.

2. Select the Notes/Alerts tab. and expand the Problem Flags section of the tab, if necessary. 3. Select a relevant Problem Flag message from the drop-down list. 4. Click Add. The new Problem Flag will be displayed in the list.

5.
2013 EnergyCAP, Inc.

5. Click Save Bill. Rules & Restrictions Comments can be added to bills after they have been added to the grid. Once a Bill Problem flag is saved, it becomes a permanent part of the bill record/audit history. Additional Information A predefined list of associated Problem Flag messages is provided. This list includes: account number has changed add fees together add Meter bill is incomplete cost is questionable edited Value illegible bill meter has been removed meter has changed overlapping dates routine supervisor attention urgent supervisor attention use is questionable

A full list of bills that have active problem flags can be viewed by: BL27 report Bills with Problem flags bill list

2013 EnergyCAP, Inc.

Bill Import
Topics in this section provide guidance on Importing Bills into EnergyCAP.

2013 EnergyCAP, Inc.

Importing Utility Bills from a File


Description The Bill Import Wizard can be used to import data from up to 10,000 utility bills for multiple accounts and meters from a single spreadsheet file. Imported bills are always added to a batch, a mechanism used to group bills that have something in common, such as creation date, bill date range, or import origin file. During the import process, bills can be either be appended to an existing batch or placed in a new batch. This topic will... describe the process for importing multiple utility bills. provide a written supplement to the Video Series: Bill Import. Prerequisites 1. The ability to add organizations and buildings requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup 2. Read the Rules for Bill Import topic to get an overview of the various import options and rules. Much of this information is also included with the sample bill import file (see below). 3. Download the Sample Bill Import File (see steps 1-2, below) for examples of common bill import data formats. 4. Prepare the import file and save it in an accessible location. Assistance is Available: Setting up bill import the first time can be complex and tricky due to multiple file formats and data elements. EnergyCAP, Inc. offers optional Implementation Services in blocks of five hours. A few hours of assistance and training from a Project Manager may save many hours of trial and error in the future. Step-by-Step 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will appear. 2. Select Enter Bills from the Tree View. 3. Click the Import Bills button.

2013 EnergyCAP, Inc.

4. On the General tab, read the import overview information. If desired, click the Download Sample Import File button to download a sample import file for study. When done, click Continue.

5. On the Batch Selection tab, select which batch should include the imported bills and the click Continue.

2013 EnergyCAP, Inc.

5.

6. On the File Selection tab, complete the fields and then click Continue. Select the file type (Excel or CSV) Click the Browse button to locate and select the import file previously prepared.

7. On the Profile tab, select the appropriate radio button and then click Continue.

2013 EnergyCAP, Inc.

7. Select a profile from the dropdown of previously created profiles. Create a new profile and add the name in the field provided.

8. On the Column Mapping tab, map import data to the Bill Template Label by clicking the drop-down arrow and select the value that best matches the import data header. For more information on column mapping, see Additional Information, below. Then click Continue.

2013 EnergyCAP, Inc.

9. On the Sample Data tab, view the first three lines of the import file mapped to the column selected on the previous tab. Verify that the bill data is mapped as expected and then click Import.

10. On the Import Progress tab, monitor the progress of the import. For large files, a progress indicator and estimated time remaining will be displayed.

2013 EnergyCAP, Inc.

11. On the Results tab, view the results from the import will be displayed after the bill import is finished.

Rules & Restrictions All dates in the import file must use the same date format. Under normal circumstances 10,000 bills should take between 8-10 minutes to import. Additional Information Bill import profiles are used to quickly import files that have the same format as a previously-imported file. Once columns of the import file have been matched with the bill template fields, the same mapping will be applied each time the profile is used. If using an existing profile, click to select its name from drop-down list of available profiles. If creating a new profile, input the new profile name in the field provided. When mapping import file data: Be sure to select the date format that matches the dates in your file. Data items normally found on the top portion of a utility bill (Account Code, bill dates etc.) are listed first in the drop-down list, followed by an alphabetical list of unique bill line items choices. The Advanc ed option provides an interface for adding new items to the list of Data Label choices. Select Do Not Import for any columns that should be ignored by the importer. Required fields for mapping to the database (Account Code, Start Date, End Date) are indicated in bold type with an asterisk. When a usage value is mapped, a supplemental Units of Measure column will appear; make certain that the correct usage unit is selected. Some drop-down list choices are Orange. This means that this Data Label is an "informational" field that is not rolled up on reports and charts. The most common informational fields are electric and natural gas "supply usage" -- the consumption reported on a deregulated supplier bill. Typically, both the local utility company distributor (the LDC - Local Distribution Company) and the supplier of choice

2013 EnergyCAP, Inc.

display the SAME usage on their bills. It's common to track the usage on both bills, but you don't want to count it twice on roll-up reports and charts. So use an orange informational data label for the supplier (the electric generator or the gas wellhead) to enable both bill-level tracking and accurate roll-ups.

2013 EnergyCAP, Inc.

Rules for Bill Import


Description To ensure a successful import of utility bill data, the import process must be followed carefully. The Bill Import Wizard provides an interactive tool to guide the process. Additionally, data in the import file itself must conform to certain specifications. Each bill record must include certain types of data. This topic will... provide rules and specifications for a successful import of utility bill data. Required Fields Each bill record corresponds to a row of data in the spreadsheet file. Each bill record must include data for three required fields: Account Code, Start Date and End Date. A/C/E Rules The A/C/E flag is set for a bill using a column that contains an A, C or E for each bill record. "A" is the standard code and indicates an actual, routine bill. "E" indicates an Estimated bill (the usage or meter reading has been estimated) and results in the bill's estimated flag being set to true. "C" indicates a corrected bill. Blank value will be imported as "A". The A and C codes are of particular importance when there is already an existing bill in the database for the same account, same vendor, same start and end dates (see next section). A/C/E Rules for a Bill Import Record that Matches an Existing Bill in the Database What happens when a bill is imported that is already in the database? In other words, the account, start date and end date all match an existing bill. The existing bill could have been keyed or imported previously, or even imported moments ago as an earlier record in the same import file. Estimated: If "E," any existing bills on the same account with the same dates will be deleted and the new bill will be entered with the estimated flag set to "True." Actual: If "A," any existing bills on the same account with the same dates will be deleted and the new bill entered. (In essence, the prior bill is overwirtten.) Corrected: If "C," the bill is treated as a correction (a "true-up" transaction); existing bills on the same account with the same dates are NOT deleted, and the new bill is entered. Any other A/C/E column value, or no value, is interpreted as if it were an "A." Meter and Commodity Rules In EnergyCAP, a bill is associated with an account and a meter. While Account Code is required, EnergyCAP can attempt to find the correct meter if the Meter Code is not specifically provided. To find the meter for this bill, EnergyCAP uses the following logic to locate a meter connected to the specified Account Code: If METER CODE is supplied, it is used as provided. If the provided Meter Code could not be found, an Import

2013 EnergyCAP, Inc.

Error message will be generated. If METER CODE and COMMODITY are provided they must match. If the Commodity provided does not match the Meter Code commodity, an Import Error message will be generated. If METER CODE is not provided, the importer will look for a COMMODITY column associated with the bill record. If no meters are found OR more than one meter is found for that account and commodity, the importer will not be able to import that bill. An Import Error message will be logged providing details. If no COMMODITY or METER CODE is specified in column mapping, the Import Wizard will ask if all bills are for the same commodity and will prompt to select a commodity from the list provided. If YES, the commodity code will be applied to all bills in the import file. Otherwise, the importer will attempt to locate the meter based on the account code with the assumption that there will be only one meter. If there is more than one meter on the account, the bill will be processed as an import error, since EnergyCAP will not be able to determine the meter to which usage should be applied

Example 1: Both Account and Meter Code are provided. Assuming they match an account/meter in the database, this bill will be imported correctly.
AccountCode 123456-1 STARTDATE 20071201 ENDDATE 20071231 MeterCode 12345-ELEC

Example 2: Account Code and Commodity Code are provided . The importer will look for the Electric meter on this account. If only ONE is found, the bill will import correctly. If more than one electric meter is found, the bill will fail to import because the importer cannot correctly determine which electric meter the bill is associated with.
AccountCode 123456-1 STARTDATE 20071201 ENDDATE 20071231 COMMODITY ELECTRIC

Example 3: Only Account Code is provided. The Import Wizard will ask if all lines in the file are for the same commodity (eg. all electric bills). If they are, select the
2013 EnergyCAP, Inc.

commodity; then each bill will be treated like Example 2 above. If they are not all for the same commodity, the importer will attempt to locate the meter based on the Account Code. If more than one meter exists for this account, the import will fail because the importer cannot correctly determine which meter the bill is associated with.
AccountCode 123456-1 STARTDATE 20071201 ENDDATE 20071231

Account-level Bill Charges If a bill contains a charge that should be associated with the account only (a late fee for instance), this can be specified during the mapping processes. To accomplish this, add two additional columns to the import file; one for the charge (late fee) and one to signal that this line of the bill should be charged to the account, not a meter on the account. In the "account charge" column, place an "X" on any line that should be an account charge. This will cause the importer to ignore any Meter Code or Commodity provided. Account Charge Example: This bill consists of two import lines, which the importer identifies because the lines are consecutive and have the same Account Code, Start Date and End Date. The first line is for an electric meter, the second for an account-level charge. Even though the Meter Code is given on the second line, it will be ignored because the Account Charge column has an "X" in it. Account Code 123456-1 123456-1 Start Date 20071201 20071201 End Date 20071231 20071231 Meter Code 12345-ELE C 12345-ELE C Use (kWh) 2534 Cost 254.24 50 X Late Fee Account Charge

Suggestion: When using a new profile, test a sample of the import file format with a small number of bill records. Optional Fields This is a list of optional fields which can be used in the bill import process. These fields can provide additional information for a bill that may be useful or necessary information for specific data needs. Billing Period: (format MM:YYYY): Providing this information forces a bill to be assigned to a particular calendar month billing period; otherwise, the billing period is determined by the month in which the mid-point of the bill falls. Example: 10:2012 = October 2012 Due Date (same format as start and end date fields)

2013 EnergyCAP, Inc.

Statement Date (same format as start and end date fields) Accounting Period (format MM:YYYY): The calendar month Accounting Period associated with the bill. Example: 10:2012 = October 2012. If October is month #1 of fiscal year 2013, use 10:2012 for Accounting Period of Oct 12. Vendor Code (format alphanumeric) The Vendor Code associated with the bill. Invoice Number (format alphanumeric)

2013 EnergyCAP, Inc.

Video Series: Bill Import


This video series provides information on the bill import process in EnergyCAP.

2013 EnergyCAP, Inc.

Basics of Importing Bills

Description

It's easy to import bills from an Excel format or comma-separated value (CSV) format file. Watch this video, and others in the series, to gain an understanding of the bill import process in EnergyCAP.

2013 EnergyCAP, Inc.

Preparing Bills for Import


Description

It's easy to import bills from an Excel format or comma-separated value (CSV) format file. Watch this video, and others in the series, to gain an understanding of the bill import process in EnergyCAP. This topic will discuss batch import options, explain import file data matching, and demonstrate the bill import procedure.

2013 EnergyCAP, Inc.

Importing Bills for Accounts with Multiple Meters


Description

It's easy to import bills from an Excel format or comma-separated value (CSV) format file. Watch this video, and others in the series, to gain an understanding of the bill import process in EnergyCAP. This topic will explain how the importer processes an import file for accounts with multiple meters, and how to prepare an import file for accounts with multiple meters.

2013 EnergyCAP, Inc.

Correcting Bill Import Errors

Description

It's easy to import bills from an Excel format or comma-separated value (CSV) format file. Watch this video, and others in the series, to gain an understanding of the bill import process. This video provides information on correcting bill import errors. Additional information is provided below.
Addressing Import Errors

To display the Bill Import Errors list, click Bill processing > Bill Import Errors.

The Bill Import Errors list includes any bill records which were not successfully imported. The list will display the Account Code (if it was provided in import file), the error message associated with the record, the created date, and the User ID associated with the import. The most common import error is Account Code Not Found, which means that the Account Code in the import file did not match an Account Code in the database. To correct the bill error, click the Edit icon for the bill record to open the Bill Import Error window for that bill. Then edit the billing information provided. When done, click Save to save the corrected bill to the Import Errors folder. Or click Reimport to import the bill again. If successful, the bill will be removed from the Import Errors folder. Repeat the process for any remaining bills in the errors folder. Instead of editing bills individually, it may be more time-effective to edit the import file and re-import the entire file. To delete a bill (or multiple bills) from the Bill Import Errors bill list: 1. Click the checkbox option next to each bill to be deleted. 2. Select the Delete Selected Bill(s) option from the drop-down action menu. 3. Click the Apply button.

2013 EnergyCAP, Inc.

2013 EnergyCAP, Inc.

Bill Lists
Bill lists exist in the following locations: Buildings & Meter > Any Meter > Bills Accounts > Any Account > Bills Bill Processing > Enter Bills Bill Processing > Import Errors Bill Processing > Any List under My Bill Lists Bill Processing > Bill Audits > Bills with Problem Flags Bill Processing > Batches Each bill lists contains a large number of icons used to perform various tasks Each icon has a tool tip available that can be viewed by hovering over the button. These icons can be divided into two groups: Multiple Bill icons and Single Bill icons Multiple Bill Buttons After navigating to any bill list, there are several buttons present above the grid. These buttons can be used in conjunction with the check boxes to apply changes to several bills at the same time. Button Explanation Delete selected bill(s); Clicking this button prompts a delete confirmation with bill count. If yes is clicked on the confirmation, all checked bills are deleted and the grid will refresh Audit selected bill(s); Clicking this button will prompt the Run Selected Audit Group wizard. The selected groups with run over all checked bills. Set problem(s) to Fixed; Clicking this button will set all the checked bills to the Fixed status. Set problem(s) to Ignored; Clicking this button will set all the checked bills to the Ignored status. Approve selected bill(s); Clicking this button sets the status of all checked to Approved. This button is only available if the approval setting is turned via the Enterprise version of the application. Hold selected bill(s) for A/P export; Clicking this button sets the status of the bill to 'Hold for Export' and makes the bill visible in the 'Hold for Export' folder in the Enterprise version of the application. Release selected bill(s) for A/P export; Clicking this button removes the 'Hold for Export' status from the bill and it is no longer visible in the 'Hold for Export' folder in the Enterprise version of the application.

2013 EnergyCAP, Inc.

Reset bill list to Defaults; Clicking this button prompts a restore confirmation. If yes is clicked on the confirmation, the bill lists resets to the default columns, filters, and column sorting. Filter Bill List(s); Clicking this button displays the bill list filter window above the bill list. Add/Remove Columns; Clicking this button display the select columns window above the bill list. Export Bill List to Excel; Clicking this button prompts an export confirmation with bill count. If yes is selected, an excel version of the bill list will be downloaded.

Single Bill Buttons

After navigating to any bill list, click on a grid row to expand it. On the expanded view of any grid row, there are several buttons present. These buttons can be used to change attributes of the selected bill. Button Explanation Edit Bill; Clicking this button opens the Bill Entry screen for the bill. Delete Bill; Clicking this button prompts a delete confirmation. If yes is clicked on the confirmation, the bill is deleted and the grid will refresh removing this bill. View PDF; Clicking this button opens a new browser tab with a pdf version of the bill View Scanned Image; Clicking this button opens a new browser tab with an image based on the bill image settings Audit Bill; Clicking this button will prompt the Run Selected Audit Group wizard Fix All Problems; Clicking this button will set all the audit problems for the bill to the Fixed status Ignore All Problems; Clicking this button will set all the audit problems for the bill to the Ignore status Approve Bill; Clicking this button sets the status of the bill to Approved. This button is only available if the approval setting is turned via the Enterprise version of the application.

2013 EnergyCAP, Inc.

Hold Bill for A/P Export; Clicking this button sets the status of the bill to 'Hold for Export' and makes the bill visible in the 'Hold for Export' folder in the Enterprise version of the application. Release Bill for A/P Export; Clicking this button removes the 'Hold for Export' status from the bill and it is no longer visible in the 'Hold for Export' folder in the Enterprise version of the application.

2013 EnergyCAP, Inc.

Creating a Bill List


Description Each user has the ability to create custom bill lists that will provide a quick and convenient way to view and access a small subset of the total bills available. This topic will... explain how to create a bill list from scratch explain how to duplicate an existing bill list Prerequisites The ability to create custom bill lists requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bill Entry Only Step-by-Step 1. Select Bill Processing from the Main Menu. The Bill Processing navigation Tree View will be displayed on the left. 2. Select the My Bill Lists node 3. Click the Add Bill List button located above the grid

4. On the Bill List Properties screen, enter all relevant information: a. Enter the new bill list's Name. b.
2013 EnergyCAP, Inc.

4.

b. (optional) Enter a Description for the bill list. c. Choose the appropriate radio button: The Create a new bill list button creates a bill list with the default columns and filters. The Copy and modify an existing bill list button provides a field to select an existing bill list. The new list duplicate the selected bill list exactly.

5. Click the Save button. The new bill list has now been created and available on the tree. Refer to Adding/Edi ting/Removing Filters on a Bill List and Altering/Sorting Columns on a Bill List to apply additional settings to the newly created list. Rules & Restrictions When creating new bill lists, each list Name must be unique. Additional Information Q: What are the default columns and filters? A: The default columns (left to right) are Account Code, Billing Period, Begin Date, End Date, Total Cost, and Created Date. The default filter is to show only the 'previous two months billing periods'. Q: Where did the Default bill list go? A: Once the default bill list is deleted, it will never be recreated automatically. A new bill list named 'Default Bill List' may be created to replace it. Q: Can other users see the Bill Lists I have created? A: The bill lists created under 'My Bill Lists' are unique to a user. Every user in the database will have their own set of bill lists. Q: Can I see and duplicate other user's bill lists

2013 EnergyCAP, Inc.

A: There is currently no way for a user to share their bill list with another user. Similarly, when duplicating a bill list, there is no way to select another user's bill list to duplicate.

2013 EnergyCAP, Inc.

Filtering Bill Lists


Description Bill Lists provide a quick and convenient way to view and access a small subset of the total number of bills in the EnergyCAP database. This topic will... explain filter options in EnergyCAP bill lists explain how to filter the bill list to view only the desired bills. Prerequisites Bills must be entered in the EnergyCAP database. Step-by-Step 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will be displayed on the left. 2. Select the node under My Bill Lists that the filters will be applied to. 3. Click the Filters button.

4. In the filters window, add and remove filters as needed. To add filters, select any of the filters listed in the Additional Filters grid, update the settings and select Save. To remove filters, select the filter from the Current filters grid, and select Clear.

2013 EnergyCAP, Inc.

4.

5. Click the Filters button again to close the filters window and view the bills matching the new filter settings. Additional Information Once a specific bill has been located, it is possible to Edit it by clicking the Edit icon for the bill. Refer to Addi ng/Editing/Removing Filters on a Bill List Click on a column heading to sort the list by that heading. The list will display up to 1,000 items;the values indicate how many are being displayed and how many pass the filter condition(s). The total cost is for all bills, not just the first 1,000 displayed in the list. Click Export Data from the Details & Actions tab to export the data in a spreadsheet format.

2013 EnergyCAP, Inc.

Adding/Editing/Removing Filters on a Bill List


Description Filters can be applied to any bill lists to make them more useful. This topic will... describe how to add, edit, or remove filters on any bill list. Prerequisites The ability to filter bill lists requires permissions associated with the following User Roles: Administrator Full Access Bill Entry & Account Setup Bill Entry Only Become familiar with the various bill list locations. Refer to the Bill Lists help topic for more information. Step-by-Step Adding Filters on a Bill List Navigate to the desired Bill List. 1. 2. 3. 4. Click the Filter Bill List button. Select a filter from the Additional Filters list. Select the Operator. Select OR enter a filter Value.

2013 EnergyCAP, Inc.

5. Click Save. 6. Verify the the filter was saved by reviewing the Current Filters list.

Editing Filters on a Bill List Navigate to the desired Bill List. 1. 2. 3. 4. Click the Filter Bill List button. Select a filter from the Current Filters list. Select the Operator. Select OR Enter a filter Value.

5. Click Save. 6. Verify the the filter was edited by reviewing the Current Filters list.

Removing Filters on a Bill List Navigate to the desired Bill List. Filters can be removed from a bill list two different ways: 1. Click the X button preceding the filter in the Filter Settings list.

2013 EnergyCAP, Inc.

1.

OR 1. Click the Filter Bill List button. 2. Select a filter from the Current Filters list. 3. Click Clear. The filter will be removed from the Current Filters list, and will reappear on the Additional Filters list.

2013 EnergyCAP, Inc.

4. Verify the filter was removed by reviewing the Current Filters list.
Rules & Restrictions

Filter values are only available if sort data is being tracked in other parts of the application. e.g. Pay Status v alues will not be available unless Pay Status is a data field for saved bills in the system. Additional Filters lists are different for each bill list. e.g. Meter bill list has fewer filter options since this list is already filtered to a specific meter. Additional Information Q: How do I change the way filter values are displayed? A: There are three ways to display filter values: Dropdown list, search, or search if Dropdown count exceeds a specific number. Refer to Global Settings for a more detailed explanation. Q: Will the filter settings be saved for the next login? A: Yes, a user's settings are permanently saved. Q: Why aren't any bills showing up on the list? A: EnergyCAP does not prevent a user from filtering all bills. If MeterA is attached to AccountA but the filters are set for MeterA and AccountB, no bill will be present on the list. Q: Why can't I remove the filters on the bill list? A: Some of the bill lists have filters that cannot be removed. These filters appear above the list in the filter settings section and are color-coded (gray).

2013 EnergyCAP, Inc.

Altering/Sorting Columns on a Bill List


Description Columns can be altered and column sorting can be applied to any bill lists to make them more useful. This topic will... describe how to add and remove columns. describe how to change column sorting. describe how to rearrange columns. describe how to adjust column width. Prerequisites The ability to change columns and sort bill lists requires permissions associated with the following User Roles: Administrator Full Access Bill Entry & Account Setup Bill Entry Only Familiarity with the various bill list locations. Refer to the Bill Lists help page for more information. Step-by-Step Adding Columns to a Bill List Navigate to the desired Bill List. 1. Click the Add/Remove Columns button.

2013 EnergyCAP, Inc.

2. Click the check box next to all the column names to be added to the list 3. Click the Apply Changes button. 4. To close the Select Columns window, click the Add/Remove Columns button.

Removing Columns on a Bill List Navigate to the desired Bill List. 1. Click the Add/Remove Columns button.

2013 EnergyCAP, Inc.

2. Click the check box next to all the column names to be removed from the list. 3. Click the Apply Changes button 4. To close the Select Columns window, click the Add/Remove Columns button.

Rearranging Columns on a Bill List Navigate to the desired Bill List. 1. Click and hold down the mouse key on the column header. 2. Slide the mouse left or right to drag the column header to a new location, which will be defined by a blue column divider. 3. When the blue divider is in the desired position, release the mouse. The selected column will be relocated to the new position.

Sorting Columns on a Bill List Navigate to the desired Bill List. To start a new sort based on a different column, click the header of the column to be used as the new sort criterion. Click the column header again to reverse the sort. EXAMPLE: The Bill List is currently sorted by Account Code. Click the Billing Period column to replace the current sort by a new sort by Billing Period.

Sorting Columns on a Bill List Using Multiple Sort Criteria

2013 EnergyCAP, Inc.

Navigate to the desired Bill List. To expand the current sort to include another column as a subordinate sort criterion, hold the Ctrl key while clicking the header of the column to be sorted. A number will appear to the right of the header name, indicating the column sort priority/order. EXAMPLE: The Bill List is currently sorted by Begin Date. Ctrl-clicking the Account Code column header will preserve the Begin Date sort, but if multiple bills have the same Begin Date, those bills will be sorted by Account Code.

Resizing Column Width on a Bill List 1. Navigate to the Bill List where column widths are to be adjusted. 2. Move the cursor to the header row for the Bill List and position it over the column dividing line. The cursor will change its shape:

3. Click and drag the column divider until the column is the desired width. 4. Release the mouse button. Rules & Restrictions A maximum of three column sorts can be applied to any bill list. Available Column names are different for each bill list based on what is appropriate for the list location. Additional Information Q: Why can't I remove the column? A: EnergyCAP logic prevents removal of certain columns from certain Bill Lists. Columns which cannot be removed are indicated by a grayed-out column name in the Add/Remove Columns window. Q: Can the list be restored to the original sort? A: Restore the list to the default sort order by clicking the Reset Bill List to Default button. NOTE: Restoring the original sort will also restore the default filter and column settings for the Bill List. Q: Will current column settings be saved for the next login or list view? A: Yes.

2013 EnergyCAP, Inc.

Q: Why isn't the list applying the sort when the header is clicked using Ctrl? A: The bill list lists only honor a sort of three columns at a time. If three column sorts have been applied, no further sorts are allowed. If desired, reset the sort by clicking a column header without using Ctrl. Q: Why does the list keep going back to the first page? A: The list must refresh in order to display the new sort order. On refresh, the list is returned to the first page defined by the sort. Q: What happens if a column in the sort is removed from the Bill List? A: The bill list refreshes every time the column Apply Changes button is selected. If a column of the sort is removed, the sort will adjust to accommodate the change. e.g. If columnA, columnB, and columnC have been sorted as 1,2,3 and columnB is removed, columnA and columnC become a sort of 1,2.

2013 EnergyCAP, Inc.

Deleting a Bill List


Description User-created Bill Lists can be removed from the Bill Processing tree at any time. This topic will... describe the process to remove a Bill List. Prerequisites The ability to delete user-created Bill Lists requires permissions associated with the following User Roles: Administrator Full Access Bill Entry & Account Setup Bill Entry Only The presence of existing Bill Lists created by the User. Users can only view their own bill lists (My Bill Lists) and can only delete their own Bill Lists. Step-by-Step 1. Select Bill Processing from the Main Menu. The Bill Processing navigation Tree View will be displayed on the left. 2. Select the My Bill Lists node. 3. Click the check box to the left of the bill list to be removed. 4. Click the Delete button.

5. From the confirmation window, click the Yes button.

2013 EnergyCAP, Inc.

Rules & Restrictions The Default bill list can be deleted but once deleted, it cannot be restored. It must be recreated manually by the user.

2013 EnergyCAP, Inc.

Bill Audits Overview

2013 EnergyCAP, Inc.

Audit Descriptions
Description Audits provide a way of examining utility bill data to ensure accurate data entry, identify missing data, and highlight unusual patterns of use or cost that may present savings opportunities. Each EnergyCAP audit looks at utility billing data in a different way. Used together, audits are powerful tools for data validation and energy management. This topic will... discuss the four categories of audits provide a description for each audit available. Description Audits in EnergyCAP Online/Express are grouped into four categories that suggest their function and application. Bill Audits examine primary elements of the bill itself, including statement dates, billed amount, control codes, observation types, etc. For organizations with in-house coding expertise, the BILL11 Audit even provides a method for executing a stored procedure against a selected group of bills. Usage Audits examine use values on the bill for accuracy/reasonableness, based on comparisons with previous billing data. Cost Audits examine cost values on the bill for accuracy/reasonableness, based on comparisons with previous billing data. Demand Audits examine demand values on the bill for accuracy/reasonableness, based on comparisons with previous billing data. Below is a tabular list of Audits in EnergyCAP. Information items included are: CODE: The code ID for the audit DESCRIPTION: The Audit description/purpose. LABEL: Name of measured parameter category (if applicable) DEFAULT: The default value for the audit (if applicable). AUDIT LIST CODE BILL AUDITS BILL1 Possible duplicate bill indicated by Pay Amount and start or end or due or statement date is equal to an existing bill. Invoice number is equal to an existing bill. Pay amount does not equal sum of cost line items. N/A None DESCRIPTION LABEL DEFAULT

BILL2 BILL3

N/A N/A

None None

2013 EnergyCAP, Inc.

BILL4 BILL5

Control code is equal to an existing bill. Select up to 5 line items by observation type code. Select observation type code with a greater than or equal to value. Select observation type code with a less than or equal to value. Select up to 5 line items by caption. Select line items by caption with a greater than or equal to value. Select line items by caption with a less than or equal to value. Execute a custom stored procedure.

N/A Observation Type

None Selected Observation Type Code(s) joined by "OR" logic. Selected Observation Type Code. Selected Observation Type Code. Selected Caption(s) -"Like", not "Equals"joined by "OR" logic. None

BILL6

Observation Type

BILL7

Observation Type

BILL8

Caption

BILL9

Caption

BILL10

Caption

None

BILL11

N/A

None [stored procedure name]

USAGE AUDITS USE1 Use per Day is greater than the average of the prior 2 calendar months. Use per Day is less than the average of the prior 2 calendar months. Use per Day is greater than the same month last year. Use per Day is less than the same month last year. Use per Day is the same as the prior two months. Possible estimated bill, but estimated flag not checked. [this audit only applies when use/day >0]. Percent above Average Use Per Day. Percent below Average Use Per Day. Percent above last year's Use Per Day. Percent below last year's Use Per Day. Percent difference to allow for rounding. 20%

USE2

50%

USE3

20%

USE4 USE5

50% 0.10%

2013 EnergyCAP, Inc.

USE6

Use per Day is greater than the highest use/day of any bill for this meter in the last 12 months. Use per Day is less than the lowest use/day of any bill for this meter in the last 12 months. Cost but no usage for 2 months in a row. Is this meter now inactive?

Percent above highest Use Per Day.

20%

USE7

Percent below highest Use Per Day.

50%

USE8

N/A

None (NOTE: Does not flag meters that have NEVER had any usage, i.e. cost-only accounts. Only meters for which there is usage at some point in history.) 100,000

USE9

Use exceeds high limit in common rollup units of measure. Use below low limit in common rollup units of measure.

Use above Common Rollup value. Use below Common Rollup value.

USE10

COST AUDITS COST1 Cost per Day is greater than the same month last year. Cost per Day is less than the same month last year. Unit Cost is greater than the same month last year. Unit Cost is less than the same month last year. Cost per Day is greater than the highest cost/day of any bill for this meter in the last 12 months. Cost per day is less than the lowest cost/day of any bill for this meter in the last 12 months. Percent above last year's Cost Per Day. Percent below last year's Cost Per Day. Percent above last year's Unit Cost. Percent below last year's Unit Cost. Percent above highest Cost Per Day. 20%

COST2 COST3 COST4 COST5

50% 10% 50% 20%

COST6

Percent below highest Cost Per Day.

50%

2013 EnergyCAP, Inc.

COST7

Cost Per Unit is greater than the highest cost/unit of any bill for this meter in the last 12 months. Cost Per Unit is less than the lowest cost/unit of any bill for this meter in the last 12 months. Meter Cost exceeds high limit. Meter Cost below low limit. Unit Cost exceeds high limit. Unit Cost below low limit. Cost per Day is greater than the average of the prior two calendar months. Cost per Day is less than the average of the prior two calendar months. Cost per Unit is greater than the average of the prior two calendar months Cost per Unit is less than the average of the prior two calendar months.

Percent above highest Cost Per Unit.

10%

COST8

Percent below lowest Cost Per Unit.

50%

COST9 COST10 COST11 COST12 COST15

Cost above: Cost below: Cost above: Cost below: Percent above Average Cost Per Day

50,000 5 0.25 0.04 20%

COST16

Percent below Average Cost Per Day Percent above Average Unit Cost Percent below Average Unit Cost.

50%

COST17

20%

COST18

50%

DATE AUDITS DAY1 DAY2 Abnormally short billing period. Abnormally long billing period. Assigned Billing Period month falls outside of start/end dates. Days Less Than Average Billing Period Length. Days Longer Than Average Billing Period Length. N/A >5 days below average of prior 12 months >10 days above average of prior 12 months. None

DAY3

2013 EnergyCAP, Inc.

DAY4

Start/end dates overlap with another bill for this account and vendor. Deregulated accounts will have overlapping on a meter basis, but not on an account/vendor basis. Gap between this bills start date and prior bills end date indicates possible missing bills or incorrect dates. Due date is too long after bill End Date. Statement Date is too long after bill End Date.. Bill end date is later than today. Multiple bills for this account in one billing period [account and vendor]. Due date or Statement Date is before End Date [only applies when non-null].

N/A

None

DAY5

Number of Days Between Bills to Indicate gap.

>1 day in gap

DAY6 DAY7 DAY8 DAY9

Number of Days After End Date. Number of Days After End Date N/A N/A

30 days 10 days None >1 bill [looks at accountID]

DAY10

N/A

None

DEMAND AUDITS DEM1 Abnormal load factor (over 100%). Use too high, demand too low, or days too low. Abnormal load factor (.1% to 15%). Use too low, demand too high, or days too high. Billed demand greater than the same month last year. Skip test if either month = null or zero. Maximum Realistic Load Factor Percentage >100%

DEM2

Minimum Realistic Load Factor Percentage

<15% AND >0%

DEM3

Percent above previous year.

20%

2013 EnergyCAP, Inc.

DEM4

Billed demand less than the same month last year. Skip test if either month = null or zero. Billed demand greater than the highest billed demand of any bill for this meter in the last 12 months. Billed demand lower than the lowest billed demand of any bill for this meter in the last 12 months. Months with BD=0 or null are skipped. Billed demand exceeds high limit. Billed demand lower than low limit. Include bills with BD=0 ONLY WHEN at least 1 other bill for the same account/meter has BD>0, i.e. doesn't show every electric meter if they never have demand.

Percent below previous year.

50%

DEM5

Percent above highest billed demand.

20%

DEM6

Percent below lowest billed demand.

50%

DEM7 DEM8

Billed demand above: Billed demand below:

5000 5

2013 EnergyCAP, Inc.

Creating an Audit Group


Description Audit Groups are used to apply multiple audits to a utility bill or a number of utility bills. After the Audit Group has been created, one or more audits can be placed in the group. Specific audit settings and specific filter settings unique to that Audit Group can be assigned to each audit. These settings determine the rigor of the audit, and the range of bills to which the audit will be applied. This section will... provide step-by-step instructions on how to Create an Audit Group. explain the intention of the Recommended Audit Group. provide notes on Audit Group Rules and Restrictions. offer suggestions on how to structure Audit Groups. Prerequisites The ability to create an Audit Group requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bill Entry Only Building Administrator

Step-by-Step 1. Click Bill Processing from the Main Menu. Audit options will be displayed on the left. 2. Click to highlight the Audit Groups node. 3. Click the Add a Group button located above the list of Audit Groups.

2013 EnergyCAP, Inc.

4. On the General tab, complete all fields and then click Continue. a. Enter the Name and Code for the new Audit Group b. Select the appropriate radio button: Create a New Audit Group: Select this option to create a new Audit Group 'from scratch.' Copy and Modify an Existing Group: if this radio button is selected, a drop-down list is enabled which will display all existing Audit Groups for the current user. When an existing Audit Group is selected from the list, all audits from the selected Audit Group will be added to the newly-created Audit Group, although individual audit settings will revert to their default values in the new Audit Group.

2013 EnergyCAP, Inc.

5. On the Bill Audits tab, click the check box to the left of each audit to add it to the Audit Group. Note that if creating a new Audit Group, the audits that EnergyCAP recommends are automatically selected. These are not required and can be unchecked at any time. Then click Continue.

6. On the Usage Audits tab, click the check box to the left of each desired audit to add it to the Audit Group. Then click Continue.

2013 EnergyCAP, Inc.

6.

7. On the Cost Audits tab, click the check box to the left of each desired audit to add it to the Audit Group. Then click Continue.

8. On the Date Audits tab, click the check box to the left of each desired audit to add it to the Audit Group. Then click Continue.

2013 EnergyCAP, Inc.

8.

9. On the Demand Audits tab, click the check box to the left of each desired audit to add it to the Audit Group. Then click Continue.

10. On the Add Filters tab, add and remove filters. To add a filter to the Current Filters list, click the filter name. Filter settings will be displayed. Adjust

2013 EnergyCAP, Inc.

10.

settings as necessary using the controls provided. When done, click Save. Repeat the process until all desired filters have been added. If it is necessary to remove a filter, click the filter name from the Current Filters list. Filter settings will be displayed. Click the Clear button to remove the filter from the Current Filters list.

11. When done, click Finish to save the new Audit Group. Rules & Restrictions The Audit Group Code MUST be unique. At least one audit must be selected in order to save the Audit Group. Additional Information Q: Why are some of the audits automatically selected? A: The audits that are automatically selected are simply audits that EnergyCAP has recommended. They can be removed from the Audit Group if desired. Q: What is the benefit of copying an existing Audit Group? A: If an Audit Group has already been created that is similar to the new Audit Group, it may be easier to pre-load the existing set of audits as a template. Note that if an existing Audit Group is copied, all audit settings are restored to the default settings. Saved custom settings for individual audits from the copied group are NOT transferred to the new group. Q: Can the same audit be added to an Audit Group more than once so that different audit settings can be applied?

2013 EnergyCAP, Inc.

A: No, each group can only have one of each audit attached. If the same audit needs to be run with two or more different settings on the same set of bills, it will be necessary to create an additional Audit Group. Each Audit Group can contain the same audit, but audits can be customized with different settings. Both groups can then be run on the same set of bills by running them together. For more information see: Running an Audit Group Q: Why cant the default audit setting be altered during Audit Group creation? A: This is a limitation of the Add an Audit Group Wizard. However, default settings for individual audits can be altered after the group has been created. For more information see: Editing Individual Audit Settings

2013 EnergyCAP, Inc.

Editing an Audit Group Name/Code/Description


Description Use Audit Group names to describe the nature and purpose of the group. This topic will... explain how to edit/update the Name, Code or Description of an audit. Prerequisites The ability to edit audit group information requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bill Entry Only Building Administrator Step-by-Step 1. Click Bill Processing from the Main Menu. The Bill Processing navigation Tree View will be displayed on the left. 2. Click Audit Groups from the tree view. 3. Click the Edit icon for the desired Audit Group.

4. From the General tab, revise the editable fields as desired.

2013 EnergyCAP, Inc.

4.

5. Click Save.

2013 EnergyCAP, Inc.

Editing Individual Audit Settings


Description Audit tolerances can be set individually for each audit in each Audit Group. The same audit may be run in different Audit Groups with different audit settings in each. In this way, a series of increasingly tighter tolerances can be defined for any auditable characteristic of a bill. This topic will... explain how to edit Audit Settings. Prerequisites The ability to edit individual audit settings requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bill Entry Only Bldg Administrator

Step-by-Step 1. Select Bill Processing from the Man Menu. The Bill Processing navigation Tree View will be displayed on the left. 2. Select the desired node under Audit Groups. 3. Click the Edit icon for the desired Audit listed in the Audits in This Group grid. See Additional Information for an explanation of the grid columns.

2013 EnergyCAP, Inc.

4. On the General tab, make all necessary changes to the available fields. Settings options will vary depending on the nature of the audit.

5. Click Save to save the new Audit Settings. Additional Information Below are the grid columns and descriptions of their values. Column Name Descriptions Severity Settings Skip Zero Comparison Description Name of Audit Identifies the audit characteristics of the bill User-determined severity level for a failed audit User-determined tolerance for the audit Flag indicating whether or not comparisons will be run if the bill being compared has a value of '0'.

2013 EnergyCAP, Inc.

Running an Audit Group


Description There are two ways to run audit groups: from the Audit Groups root folder or from the user's specific Audit Group. This topic will... describe how to run multiple Audit Groups. describe how to run one specific Audit Group. explain the advantages/limitations of each process. Prerequisites The ability to run audits requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup Bill Entry Only Bldg Administrator Step-by-Step Running Multiple Audit Groups 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will be displayed on the left. 2. Select the Audit Groups node of the tree 3. Click the checkbox to the left of any audit group being added to processing. 4. After the groups have been selected, click the Run Selected Audit Group(s) button.

2013 EnergyCAP, Inc.

5. On the Add Filters tab, add all desired filters to be applied to all audit groups for this instance. When done, click Continue.

6. On the Audit Progress tab, monitor the processing of bills fitting the filter parameters selected.

2013 EnergyCAP, Inc.

6.

7. On the Confirmation tab, view the bills with failed audits will be posted to the Bills With Problem Flags fold er.

8. Click Finish to close the wizard.

2013 EnergyCAP, Inc.

Running One Specific Audit Group 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will be displayed on the left. 2. Select the node under Audit Groups tat corresponds to the specific audit group to be processed. 3. Click the Audits tab to view the audits included in the group. 4. Review the audits to be run and make any necessary changes. Add or remove desired audits by selecting them and clicking the appropriate button (Remove Selected Audit(s) or Add Selected Audit(s)) 5. Click the Filters tab to review the filter settings and make any necessary changes. Filters are added and removed in the same manner as when the Audit Group is created. 6. When done, click the Audits tab and then click the Run This Audit Group button.

7. On the Add Filters tab, add all desired filters to be applied to all audit groups for this instance. When done, click Continue.

2013 EnergyCAP, Inc.

8. On the Audit Progress tab, monitor the processing of bills fitting the filter parameters selected.

9. On the Confirmation tab, view the bills with failed audits will be posted to the Bills With Problem Flags fold er.

2013 EnergyCAP, Inc.

9.

10. Click Finish to close the wizard. Rules & Restrictions Running multiple audits does not affect saved filter settings for individual audit groups. Additional Information Advantages to running multiple audit groups Multiple audit groups can be run simultaneously The chosen filter settings will preempt any previously-saved filter settings for the individual audit groups selected, making it convenient to apply a single set of filter variables quickly for a number of audits/audit groups. Advantages to running one specific audit group Only the selected audit group can be run. Filter settings changes will be saved for all future iterations of the audit in this audit group.

2013 EnergyCAP, Inc.

Resolving Bill Problem Flags


Description In EnergyCAP, bills with potential errors or issues are flagged in the database whenever an audit is run. These bills are listed in the Bills with Problem Flags folder (Bill Processing > Bill Audits). Supervisory review of bills with problem flags should be part of the bill processing workflow for any organization. This topic will... explain how to view bills with problem flags in EnergyCAP. suggest a review process for handling bills with problem flags. Prerequisites Enter bills and run audits. Failed audits will generate problem flags. Bills with problem flags will be added to the Bills with Problem Flags folder. Step-by-Step Go to Bill Processing and click Bill Audits > Bills with Problem Flags. Two tables will be displayed: Bills with Problem Flags and Problem Flags for Selected Bill. Note that table data that may be hidden can be viewed by using the scroll bars to the bottom and right of each table. Click to highlight a bill from the top table to display the bill's associated problem flags in the bottom table. The top table, Bills with Problem Flags, lists bills with problems, and provides basic billing information and a link to the associated account. Information included in the BIlls With Problem Flags table includes (by column): Account: Account associated with the bill. Click the hyperlink to switch to an account view of the billing data. Vendor: Vendor associated with the bill. Period: Billing Period Month associated with the bill. Year: Year associated with the bill. Start Date: Start date of the billing period. End Date: End date of the billing period. Cost: Cost associated with the bill (includes all line item costs on the bill). Cost/Day: Cost per day associated with the bill. Determined by dividing total cost by number of days in the billing period. Severity: Level of severity associated with audit failure (user-configured). Variance: Variance from the expected audit value, expressed as a percentage. Days: Number of days in the billing period. V-E-A: Bill types (Void/Estimated/Actual) . Created Date: Date the bill was created. Created By: EnergyCAP User who created the bills. The bottom table, Problem Flags for Selected Bill, displays a list of specific audit messages associated with the currently-selected problem bill in the top table, and may be used as a permanent audit record. There is a line in the table for each failed audit.

2013 EnergyCAP, Inc.

The Problem Flags for Selected Bill table includes (by column): Severity: Severity of the Audit failure (user-determined Audit setting). Status: Status of the Audit (see below for an explanation of Status messages and logic). Message: Audit message/explanation. Variance: Variance from the expected audit value, expressed as a percentage. Comment: Editable "Notes" field for auditor/supervisor review comments. Audit: Name of the problem Audit. Audit Group: Name of the problem Audit Group that was run when the problem flag was created. Created Date: Date of the Audit. Created By: User logged in to run the Audit. Modified Date: The date of the last change to the Audit record (Status change, edited comment, etc.) Modified By: User who last modified the Audit. A status is assigned to each bill based upon the audit results: Problem: Bill has failed the audit. Fixed: User has reviewed the information and updated Status to Fixed. Ignored: User has reviewed the failed audit and updated Status to Ignored. Bills with audits which are flagged as Ignored will not be audited with that specific audit in that specific Audit Group in the future. However, if the same audit is run via a different Audit Group, the audit will be run for that bill. Re-Audit Failed: Indicates that the audit was run again and a problem remains. Re-Audit Passed: Indicates that the audit was run again and passed. Below is a table explaining the Status record logic: If Current Bill Message Log Status is: Problem, Re-Audit Failed Then: Re-Audit Bill Upon Re-Audit if the bill: Passes Then Bill Message Log Entry will state: Update status of all message logs for this Auditor/group to have 'Re-Audit Passed' status Update status of current message log for this Auditor/group to have 'Re-Audit Failed' status Update status of all message logs for this Auditor/group to have 'Re-Audit Passed' status Create a new Message Log with a status of 'Re-Audit Failed'. The status of the previous messages for this auditor/group are not altered

Fails

Re-Audit Passed, Fixed

Re-Audit Bill

Passes

Fails

2013 EnergyCAP, Inc.

Ignored

Skip Re-Audit

Below is a suggested audit review process:Sample Audit Review Process 1. Click the problem bill in the Bills with Problem Flags bill list (top table). 2. Review each problem associated with the bill (bottom table). Correct the bill record if necessary by clicking the Edit icon for the desired bill record. The Bill Entry window will be displayed, and the bill can be edited as desired. When done, click the Save Bill button to save bill edits. 3. When the bill issue has been resolved, change the status per your established review procedures; use the Co mment field to document the issue resolution. 4. From the Problem Flags table, use the Status drop-down to update the status of the problem for the selected bill. 5. Change status Problem to Ignore if it is desirable to ignore the bill data in all future audits for that Audit Group. When the problem flag is set to Ignore, the Problem Flags message for that bill will be removed from the table unless the Show All ... checkbox is selected. 6. Following review of the problems associated with each bill, re-audit the bills using the same filter set to verify that all audit issues have been resolved. Other Bills with Problem Flags functionality The Bills With Problem Flags display includes a running total of problem bills (total cost and number of bills in the folder). This information is displayed in the header above the top table. These control totals can be useful during the review process. The Show Accruals & Voids checkbox above the top table is a toggle. If the box is checked, accruals and void bills will be displayed. If the box is unchecked, these lines will be hidden and will not be displayed or counted in totals. The Export Data button will export an Excel-format file to the location you specify. The Show All ... checkbox option for the Problem Flags for Selected Bills table will, when checked, enable display of the complete audit history, including those audits with status of Fixed, Ignored, and Re-Audit Passed. Rules & Restrictions

2013 EnergyCAP, Inc.

Cost Avoidance Processing

2013 EnergyCAP, Inc.

Calculating Savings
Description The Cost Avoidance processor can be applied to select bills in order to calculate Cost Avoidance. This topic will... describe how to run the Cost Avoidance processor.

Prerequisites Must have purchased Cost Avoidance The ability to run the Cost Avoidance Processor requires permissions associated with the following User Roles: Administration Full Access Step-by-Step 1. Select Bill Processing from the Main Menu. The Bill Processing Tree View will be displayed on the left. 2. Select the Run Processor node of the tree 3. Click the Calculate Savings button.

4. On the Calculation Options tab, check all desired options to be applied. Refer to the Additional Information section of this page for an explanation of each checkbox option. When done, click Continue.

2013 EnergyCAP, Inc.

4.

5. On the Add Filters tab, add all desired filters to be applied. When done, click Continue.

6. On the Confirmation tab, review the information.

2013 EnergyCAP, Inc.

6.

7. Click Finish. The processing status can be viewed in the Status column of the grid.

2013 EnergyCAP, Inc.

Reports Overview
Overview
EnergyCAP includes more than 250 reports to help visualize and analyze data from utility bills, setup information, interval and weather data, and even advanced tools like Cost Avoidance. Most reports can be filtered by 30 or more application values to easily narrow down the scope of information to only what is important to a users' specific need. Every user can filter their own version of any report without affecting other users. Every report can be printed, exported to a PDF file and in cases of tabular data, exported to Excel for easy sharing and further analysis. Every report that is installed provides a sample image of what the report will look like as well as a brief description. This allows users to quickly scan many reports to find the best fit for their need. As reports are run, they are automatically added to the convenient My Recent Reports list so that the reports used most often are easy to find.

Additional Information
Online Sample Reports Viewer A more detailed overview of every EnergyCAP report, including descriptions, available filters, and images, is available on the online Sample Report Viewer. Use this helpful online tool to search the EnergyCAP report database with report-related keywords, view sample reports, read report descriptions, review report filter options, and even download a PDF image of the sample.

2013 EnergyCAP, Inc.

Filtering Reports
Description
Filters are a powerful tool for creating numerous variations of any available report. If filters are not properly set for a report, the report will return unnecessary or unhelpful data. For this reason, it is important to use report filter options for most EnergyCAP reports.

This topic will...


describe the process for filtering reports. explain the purpose of the green filters. explain all operators.

Prerequisites
ALL roles have the ability to create, modify and delete report filters.

Step-by-Step
1. Select Reports from the Main Menu. A list of all reports divided into folders by category will appear on the left. 2. Select the folder for the desired report category. All available reports for the selected category will appear on the right. 3. Select/highlight the desired report from the list. A report sample image will appear on the right, along with a report description. 4. After reviewing the report image/description, click Continue. A list of Current Filters and Additional Filters will appear. Current Filters are filters that are currently set to be applied for this report. Additional Filters are other available filters that can be added to this report. 5. Make all necessary filter changes. To remove a Current Filter from the report, click to highlight the filter name from the Current Filters li st and then click Clear. The filter will be removed. To add an Additional Filter to the report, click to highlight the filter name from the Additional Filters li st. Filter settings for that filter will be displayed. Enter/update all filter information and Save. The filter will be added to the Current Filters list. 6. Repeat Step 5, adding and removing filters as necessary, until the filter configuration is satisfactory. 7. Click Run Report. The report will be created using the newly-saved filter settings.

Rules & Restrictions


Your EnergyCAP administrator has the ability to restrict user access to all data, or just a subset of data based on a Topmost node in the Buildings & Meters and/or Account hierarchies. Topmost means that the user has access to items directly under that node in the hierarchy, but cannot access anything else. This topmost permission also applies to the users reports, regardless of the filters selected. Report filters are saved for the specific user only. They will not be applied to reports created by other users. When adding filters, the filter settings value field can either be selected from a dropdown list of acceptable values OR entered as text to return all possible matches. This is determined by the Administrator under Glob al Settings. Shared Reports and Email reports have a different set of rules for saving filters. Refer to the help topic pages in these areas for more information.

2013 EnergyCAP, Inc.

Additional Information
Q: What are the filters highlighted by the green font color? A: The green font is user to distinctly mark the filters that are recommended for that report by EnergyCAP. These filters are recommended for two reasons: Either it was determined that the report will provide more meaningful data if the recommended filters are used OR two filters are mutually exclusive and one is suggested. i.e. Topmost Place Name vs. Topmost Place Code.

Q: What is an Operator? A: An Operator is a parameter that helps define a filter. The following operators are used: Equals Only data matching the input filter Value will be included in the report. Only data not matching the input filter Value will be included in the report. Only data with a value less than the input filter Value will be included in the report. Only data between the input filter Values will be included in the report. Only data matching the selected input filter Value(s) will be included in the report. Click to select from available values. Shift-Click to select a range. Only data greater than the input filter Value will be included in the report. Only data less than or equal to the input filter Value will be included in the report. Only data greater than or equal to the input filter Value will be included in the report. Only data including the the input filter Value will be included in the report. Only data not including the input filter Value will be included in the report. Only data not matching the selected input filter Value(s) will be included in the report. Click to select from available values. Shift-Click to select a range.

Not Equals

Less than

Between

One of

Greater than

Less than equal

Greater than equal

Like

Not like

Not one of

2013 EnergyCAP, Inc.

Not Between

Only data not between the input filter Values will be included in the report.

2013 EnergyCAP, Inc.

Quick Reports
Description
Quick Reports are pre-filtered reports that provide context-sensitive information depending on the portion of the web application that is being displayed. Running Quick Reports is a good way to become familiar with available reports that have proved to be the most helpful. Report filter settings can be customized to obtain more relevant data.

2013 EnergyCAP, Inc.

Administration Overview

Overview The Administration menu in EnergyCAP is used to create users, modify global settings and import setup information into the system. All users with the Administrator permission can perform these functions. Additionally, any advanced modules that are purchased as part of a license, like Cost Avoidance for instance, will often display settings categories here. Users of EnergyCAP Express, payment and account information is also available here. Rules and Restrictions The Administrator permission is required Some features require advanced license options

2013 EnergyCAP, Inc.

Adding a User
Description
All individuals wishing to use the application must have a user name and password. Each user is assigned a role based on the permissions necessary to complete the tasks assigned to them.

This section will...


describe the process for adding a new user. list and define User Roles.

Prerequisites
The ability to create Users requires permissions associated with the following User Roles: Administrator - Full Access The ability to view Users and Role Assignments requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup

Step-by-Step
1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Users & Permissions tree node. 3. Click the User button. EnergyCAP Online: the button is labeled Add User. EnergyCAP Express/Pro: the button is labeled Invite User.

2013 EnergyCAP, Inc.

4. On the general tab, input the new user's email address and select the appropriate User Role. View User Role descriptions below. Then click Continue.

2013 EnergyCAP, Inc.

5. On the Limit Building View tab, select the appropriate radio button and then click Continue. all Buildings and Meters OR all Buildings or Meters under a specific node of the Buildings tree view.

2013 EnergyCAP, Inc.

6. On the Limit Account View tab, select the appropriate radio button and then click Continue. all accounts OR all accounts under a specific Cost Center node of the Accounts tree view.

2013 EnergyCAP, Inc.

7. Click Finish to complete the user creation. EnergyCAP Online: The User Wizard will close. The user has now been created. EnergyCAP Express: The User Wizard window will close and EnergyCAP will send an email inviting the new user to create a login. When the invitation is accepted, the new user can create a username and password.

Rules & Restrictions


A users topmost Buildings & Meters and Account permissions apply to all areas of the application, including reports. Depending on system settings, a user may not be able to change his/her password more than once a day. Depending on system settings, a user may not be able to change his/her password to a previously-used password.

Additional Information
A User Role is comprised of a group of permissions. Each permission defines what type of access (view/create/modify/delete) is given to each feature. Each user must be assigned one of the following User Roles*. They are listed below in order from the greatest access to the least access:

2013 EnergyCAP, Inc.

Administrator - Full Access

Full view and write access to all menus, features, and functions. The Administrator User Role is the only one that can create new users or change a User Role assignment. Ideal for a Data Entry Specialist who is responsible for day to day bill processing and associated setup tasks. This User Role has the same permissions as an Administrator, except it cannot create or modify users or access the Account Information window. View access to all menus, features, and functions. Write access is limited to building and meter setup data such as name, address, floor area, and ENERGY STAR attributes. This role is ideal for distance users who receive bills and need to enter them into the system. They cannot create or modify other data in the system but have full viewing access to all parts of the application. Intended for a department/building manager or a consultant, this User Role has View access only, and is limited to six menus: Home, Buildings & Meters, Groups & Benchmarking, Accounts, Vendors & Rates, and Reports. The Public Access User Role grants view only access to four menus: Home, Buildings & Meters, Groups & Benchmarking, and Shared Reports. It is similar to Building Manager View Only, but does not allow view of Vendors & Rates and Accounts. A Reports Only user can only view Shared Reports in the application. This is ideal for users that need to actually run reports on a periodic basis but would otherwise find the other data viewing options overwhelming and not useful.

Bill Entry & Account Setup

Bldg Administrator

Bill Entry Only

Bldg Manager - View Only

Public - View Only

Public - Report Only

* In EnergyCAP Online, it is possible that there may be other User Roles besides those listed above. The 'extra' User Roles are custom User Roles created by an Administrator through the Installed Version of EnergyCAP. If using EnergyCAP Express, no additional user roles can be provided.

2013 EnergyCAP, Inc.

Global Settings
Description
Changes to the application that are NOT User-based are considered Global changes. Global changes can be made from the Global Settings window.

This topic will...


describe the process for navigating to the Global Settings section. explain each configuration listed in Global Settings.

Prerequisites
The ability to view or change Global Settings requires permissions associated with the following User Roles: Administrator - Full Access Bill Entry & Account Setup

Step-by-Step
1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Global Settings tree node. 3. Update Global Settings as necessary. Refer to the Additional Information section of this page for an explanation of each field. 4. Click Save. Changes will take effect on the next login.

Rules & Restrictions


All changes made will be applied on the next login.

Additional Information
Below is a list of configuration fields provided in Global Settings, along with a description of each: Set Automatic logout to Select any number of minutes between 10 and 480 before the system automatically logs a user out for inactivity. On automatic logout, the last window an action was performed on will remain visible. However, a logout warning and forced logout will occur the next time an action is attempted.

2013 EnergyCAP, Inc.

Display report filter values as

Dropdown list: Displays all values in a dropdown. Search: Displays a blank text box. As text is entered, all values that match are displayed in a dropdown for selection. Search if dropdown count exceeds: The search option will only be available if the number of dropdown values is greater than the number listed. The logo can be a maximum of 600x60 pixels. That logo image must be made available on a dedicated web page. The webpage URL should be listed in this field. The name entered will be displayed on all report headers. This is the first month of the organization's fiscal year. This will be the basis for all fiscal year calculations, including reports and charts. If no, the home option will not be accessible at all. The Home menu option will be removed from the Main Menu and the Home icon will be removed from the available header options. Any country field in the application will default to the value selected. i.e. address. Even though the country name is inserted by default, it can be changed for any particular field at any time. This determines the unit in which all weather will be displayed.

Customize with your logo. Enter URL

Organization Name

Fiscal Year Start Month

Show Home in Main Menu

Default Country

Weather Degree Unit

2013 EnergyCAP, Inc.

Adding an Organization Logo


Description
Branding the EnergyCAP online interface involves replacing the EnergyCAP name and logo with your organizational brand logo.

This section will...


describe the process for adding a custom logo to the application. describe the process for adding the organization name to the header of all reports.

Prerequisites
The ability to add/modify company information requires permissions associated with the following User Roles: Administration Full Access Bill Entry & Account Setup A logo that is a maximum of 600 pixels in width x 60 pixels in height. Make the logo accessible from a dedicated web page.

Step-by-Step
1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Global Settings tree node. 3. In the Customize with your logo field, enter the complete URL for the dedicated web page containing the logo image file. 4. In the Organization Name field, enter the name as it should appear on all report headers.

2013 EnergyCAP, Inc.

5. Click Save. Changes will take effect on next login.

Rules & Restrictions


The basic branding option does not remove every mention of EnergyCAP. EnergyCAP branding will remain on the page title and URL, in online Help, on the weather data website, and on the login screen.

Additional Information
The linked image will replace the EnergyCAP logo. To revert back to the EnergyCAP logo, remove the URL and leave the field blank. If self-hosted, the login screen logo can also be changed in a configuration file. If this is desired, please contact your EnergyCAP Project Manager.

2013 EnergyCAP, Inc.

Normalized Settings
Description
The Normalization Settings are used to modify how weather data is used during the Calendarization and Normalization process.

This topic will...


Demonstrate how to modify the weather settings that effect Calendarization and Normalization.

Prerequisites
The ability to edit normalized settings requires permissions associated with the following User Roles: Administration Full Access

Step-by-Step
1. Navigate to the Administration section in on of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Normalized Settings tree node. 3. Update the Normalized Settings as necessary. Refer to the Additional Information section of this page for an explanation of each field.

4. Click Save. Changes to these settings may take 24 hours to be applied to the data.

Rules & Restrictions

2013 EnergyCAP, Inc.

These settings only pertain to the Calendarization and Normalization sections of Buildings and Meters. They are NOT used to set any parameters for the Cost Avoidance section. The weather degree unit can be changed in Global Settings. Refer to Global Settings help topic for more information. Changes to these settings can take up to 24 hours to be applied to the data.

Additional Information
Below is a list of fields provided in Normalized Settings, along with a description of each: Normalization Comparison Year This is the year that is used as the weather standard. Every other year of data is compared to this year of weather. Cooling calculations to be applied when the temperature is above the degree specified Heating calculations to be applied when the temperature is below the degree specified

Meter Settings: Cooling Needed Meter Settings: Heating Needed

2013 EnergyCAP, Inc.

Setup Manager Overview


Description
The Setup Manager provides an easy way to import multiple Vendors, Rates, Places, Organizations, Accounts/Meters and Cost Centers into EnergyCAP. All imports are accomplished using Excel spreadsheet templates provided by EnergyCAP. The process is simple. 1. First, download (export) the appropriate template. This template will be customized using existing organization data. 2. Then add the organization setup data to the spreadsheet using the columns provided. 3. When done, save the spreadsheet and then upload (import) the data to the EnergyCAP database using the Import Wizard. This method greatly speeds and simplifies the initial organization setup process. NOTE: The EnergyCAP-generated setup spreadsheet templates may contain data from the current database. Always download a new template each time the Setup Manager is used, so that the most current information is used to generate the import template.

2013 EnergyCAP, Inc.

Setup Manager Import Process


This topic will... describe the general process for using the Setup Manager. Prerequisites The ability to perform import processes requires permissions associated with the following User Roles: Administrator - Full Access

To avoid problems associated with missing data, EnergyCAP recommends that setup information be imported in the following order: 1. 2. 3. 4. 5. Vendors Rates Organizations & Buildings Cost Centers Accounts & Meters

Step-by-Step 1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select Import from the first dropdown menu presented. 3. Select the type of item (Vendors, Cost Centers, etc.) to be imported. 4. Generate and export the template by clicking the Generate Template button. 5. Add the required/desired data to the template. 6. When done, save the file and return to the Setup Manager screen. 7. Click the Launch Import Wizard button. 8. Click the Browse button. 9. Locate the prepared template file and click to select it. Then click Open. 10. Click Continue from the Setup Sheet Importer. EnergyCAP will attempt to import the spreadsheet data and will display the import results. 11. To accept the import results, click Finish. To cancel this import attempt (including all items that were successfully created), click Cancel. All items that were created will be deleted. Rules & Restrictions If a row of data representing an item has errors, that item will be added to a new Excel file containing all errors, and the problem cells will be highlighted; cell notations will be provided specifying the errors. Once the import process has been completed, the application will display how many items were successfully created and how many items failed to be created. These failed items will be saved to a new Import Error

2013 EnergyCAP, Inc.

spreadsheet template. Additional Information It is strongly suggested that users always download a new import template each time the Setup Manager is used; this will ensure that spreadsheet import columns will have the most current pre-populated data available for selection when preparing the spreadsheet, and that the most current version of the import spreadsheet will be used.

2013 EnergyCAP, Inc.

Setup Import - Accounts and Meters


Description

The Setup Manager offers a specific template for importing Account and Meter information.
This topic will...

provide all the rules and restrictions included in the Setup Import Account template.
Prerequisites

All the vendors, rates, cost centers, and buildings to be referenced in the template must be imported before creating the Setup Import Account Template. Understand how to set up hierarchical templates. Please refer to Setup Manager Importing of Hierarchical Items for more specific details. Setup Import Account Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Column Account Code

Rules Required for Accounts; Account Code does not have to be unique. However, the combination of the Account Code and the Vendor Code must be unique. Required for Accounts; Does not have to be unique. Can consist of letters, numbers, and special characters. Not Required for Accounts; The address entered will be imported as the billing address for the account. Not Required for Accounts; The address street2 can be added without filling in address street1 Postal Code is required if the Service Country is United States or Canada; Code format should be xxxxx-xxxx (xxxxx is accepted) for United States OR xxx xxx for Canada; Can consist of numbers and dashes

Account Name

Service Address Street1

Service Address Street2

Service Postal Code

2013 EnergyCAP, Inc.

Service Country

Not Required for Accounts; Only Canada and United States are specifically identified. Anything else can be classified as 'Other' If blank, country will default to United States Required for Accounts; This is the Cost Center that the account is directly listed under. Required for Account If blank, chargeback account type will default to No Required for Account if Chargeback Account value is Yes No value allowed if Chargeback Account value is No Select a Customer from the available customers in the dropdown list. Required for Account AND for Meter; Required for Meter; Not Required for Meter; Required for Meter; Meter Code MUST be unique in order to create a new meter. The meter code can exist in the sheet multiple times when creating a new meter/account combination. Required for Meter; Does not have to be unique. Can consist of letters, numbers, and special characters. Required for Meter; This is the Building the meter is directly listed under; Select a Building from the available buildings in the dropdown list. Required for Meter; Required for Meter; Rates available in the drop down are populated based on the Vendor and Commodity selected.

Cost Center Code

Chargeback Account

Customer

Vendor Type Commodity Meter Serial # Meter Code

Meter Name

Parent Building Code

Parent Account Code Rate Schedule Code

2013 EnergyCAP, Inc.

Bill Entry Template

Required for Meter; Templates available in the drop down are populated based on the commodity selected

Additional Information

Q: Can Accounts and Meters be added in the same spreadsheet row? A: No, accounts and meters need to be put on separate rows of the spreadsheet. Parent items must preceed child items. Please refer to Setup Manager Importing of Hierarchical Items for more specific details. Q: How do I create Chargeback Meters? A: If the meter being created is attached to a Chargeback Account, the meter type is automatically set to Chargeback.

2013 EnergyCAP, Inc.

Setup Import - Cost Centers


Description

The Setup Manager offers a specific template for importing Cost Center information.
This topic will...

provide all the rules and restrictions included in the Setup Import Cost Center template.
Prerequisites

Setup Import Cost Center Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Column Cost Center Code

Rules Required for Cost Center; Code must be unique Required for Cost Center; Does not have to be unique Not Required for Cost Center; This is the Cost Center that the newly created Cost Center will be listed under. If blank, the User's Top Most Place will be selected as the parent Cost Center.

Cost Center Name

parent Cost Center Code

Additional Information

Q: Can the parent Cost Center be a newly-created Cost Center? A: Yes, the parent Cost Center can be a Cost Center that is being created in the same import template. Cost Centers are created in the order they are listed on the sheet. To list a Cost Center as a parent, define it in a preceding row of the spreadsheet.

2013 EnergyCAP, Inc.

Setup Import - G/L


Description

The Setup Manager offers a specific template for importing General Ledger Code information.
This topic will...

provide all the rules and restrictions included in the Setup Import G/L Template.
Prerequisites

All the accounts, vendors, and meters to be referenced in the template must be imported before creating the Setup Import G/L Template. Setup Import G/L Template must be generated using the instructions provided by the Setup Manager. Use the filters to narrow the number of records being created
Rules & Restrictions

Template Columns Account Code

Rules Required for G/L Setup; Value should not be altered or removed Required for G/L Setup; Value should not be altered or removed Not Required for G/L Setup; If value is removed, the G/L code will be attached to the account/vendor Required for G/L Setup; Code must be unique Not Required for G/L Setup

Vendor Code

Meter Code

GL Code

Subcodes 1-20

Additional Information

Q: Why are my columns not named 'Subcode 1', 'Subcode 2', etc? A: Subcode names are set up by your company EnergyCAP administrator. The default names are Subcode 1 through Subcode 20. Q: Why are some of the subcode columns text fields and others drop down fields? A: Subcode field setup is determined by your company EnergyCAP administrator. The options are a text field or a dropdown. Q: How are Account G/L codes created? A: The meter column of the template is optional to accommodate the creation of Account G/L Codes. Remove the meter code value and the G/L code will be attached to the account/vendor combination specified.

2013 EnergyCAP, Inc.

Setup Import - Organizations & Buildings


Description

The Setup Manager offers a specific template for importing Organization and Building information.
This topic will...

provide all the rules and restrictions included in the Setup Import Organizations & Buildings template.
Prerequisites

All the vendors, rates, and cost centers to be referenced in the template must be imported before creating the Setup Import Organization and Buildings Template. Understand how to set up hierarchical templates. Please refer to Setup Manager Importing of Hierarchical Items for more specific details. Setup Import Organization and Buildings Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Columns Organization Code

Rules Required for Organization; Code must be unique Required for Organization; Does not have to be unique Not Required for Organization Not Require for Organization; This is the Organization that the newly create Organization will be listed under; If blank , the User's Tope MOst organization will be selected as the Parent Organization Required for Building; Code must be unique Required for Building; Does not have to be unique Not Required for Building; The address entered will be imports as the billing address for the building

Organization Name

Organization Type Code Parent Organization Code

Building Code

Building Name

Street1

2013 EnergyCAP, Inc.

Street2

Not Required for Building; The address street2 can be added without filling in an address street1 Required if the Service Country is United States or Canada; Code format should be xxxxx-xxxx (xxxxx is accepted) for United States OR xxx xxx for Canada; Can consist of numbers and dashes Not Required for Building; Only Canada and United States are specifically identified. Anything else can be classified as 'Other' If blank, country will default to United States Not Required for Building; Positive Numeric Values only; Decimals are rounded to the closest whole number; Negative values are not imported and cause a kickout error Not Required for Building; If a value exists in the floor area column, unit defaults to Square Feet if left blank Not Required for Building; If a value exists in the floor area column, date defaults to 1/1/2000 if left blank Required for Building; If blank, Primary Use will default to 'Other'

Postal Code

Country

Floor Area

Floor Area Unit

Floor Area Effective Date

Primary Use Code

Additional Information

Q: After I import a building, is EnergySTAR enabled for the building? A: EnergyStar will be enabled if a floor area and postal code for the building are included in the setup template. However, if the building Primary Use is not defined, the Primary Use field for the new building will default to Other. If a building with a Primary Use type of Other is submitted to ENERGY STAR, a building rating will not be returned.

2013 EnergyCAP, Inc.

Setup Import - Rates


Description

The Setup Manager offers a specific template for importing Rate information.
This topic will...

provide all the rules and restrictions included in the Setup Import Rate template.
Prerequisites

All the vendors to be referenced in the template must be imported before creating the Setup Import Rate Template. Setup Import Rate Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Column Vendor Commodity Rate Code

Rules Required for Rate; Required for Rate; Require for Rate; Does not have to be unique. However, the combination of the vendor and commodity and rate code must be unique.

Additional Information

N/A

2013 EnergyCAP, Inc.

Setup Import - Vendors


Description

The Setup Manager offers a specific template for importing Vendor information.
This topic will...

provide all the rules and restrictions included in the Setup Import Vendor template.
Prerequisites

Setup Import Vendor Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Column Vendor Code

Rules Required for Vendor; Must be unique Required for Vendor Not Required for Vendor

Vendor Name Website

Additional Information

N/A

2013 EnergyCAP, Inc.

Setup Manager Update Process


This topic will... describe the general process for using the Setup Manager to update items in EnergyCAP. Prerequisites The ability to perform update processes requires permissions associated with the following User Roles: Administrator - Full Access There are three main differences that should be understood before embarking on updates through the Setup Manager: 1. Most update spreadsheets can be generated on a filtered subset of your data. The provided filters are limited and specific to the items being updated. 2. There is no specific order required for items to be updated, 3. Update spreadsheets are provided with the existing data pre-populated. This makes it easy to locate and update any items.

Step-by-Step 1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select Update from the first dropdown menu presented. 3. Select the type of item (Vendors, Cost Centers, etc.) to be imported, using the drop-down list provided. 4. Generate and export the template by clicking the Generate Template button. 5. Add the required/desired data to the template. 6. When done, save the file and return to the Setup Manager screen. 7. Click the Launch Import Wizard button. 8. Click the Browse button. 9. Locate the prepared template file and click to select it. Then click Open. 10. Click Continue from the Setup Sheet Importer. EnergyCAP will attempt to import the spreadsheet data and will display the import results. 11. Click Accept to finish. In order to change the currently updated information, make the changes on the import file and reimported.
Rules & Restrictions

If a row of data representing an item has errors, that item will be added to a new Excel file containing all errors, and the problem cells will be highlighted; cell notations will be provided specifying the errors. Once the import process has been completed, the application will display how many items were successfully created and how many items failed to be created. These failed items will be saved to a new Import Error spreadsheet template.

2013 EnergyCAP, Inc.

Updates cannot be canceled or rolled back in the current release. In order to change the currently updated information, changes need to be made on the original file and reimported.
Additional Notes

It is strongly suggest that users always download a new update template each time the Setup Manager is used; this will ensure that spreadsheet update columns will have the most current pre-populated data available for selection when preparing the spreadsheet and that the most current version of the update spreadsheet is used.

2013 EnergyCAP, Inc.

Setup Update - Accounts


Description

The Setup Manager offers a specific template for updating Account information.
This topic will...

provide all the rules and restrictions included in the Setup Update Account template.
Prerequisites

Setup Update Account Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Column Account Code Update Effective Date Update

Rules New Code must be unique If an account code update value is entered, use this field to list the date the account code changed. If an account code is added and effective date is not entered, the old account code will be replaced New account name does not have to be unique Date overwrites the existing service begin date Date overwrites the existing service end date Select to make the account active or inactive New value overwrites the existing service address New value overwrites the existing service address Postal Code must match the selected Country OR a new country must be selected If a Country is selected, the existing postal code must match OR a new postal code must be selected This is the Cost Center that the account is directly listed under. New values overwrites the existing vendor role

Account Name Update Service Begin Date Update Service End Date Update Active Update Service Address Street1 Update Service Address Street2 Update Service Postal Code Update

Service Country Update

Cost Center Code Update

Vendor Role Update

2013 EnergyCAP, Inc.

Setup Update - Cost Centers


Description

The Setup Manager offers a specific template for updating Cost Center information.
This topic will...

provide all the rules and restrictions included in the Setup Update Cost Center template.
Prerequisites

Setup Update Cost Center Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Columns Cost Center Code Update Cost Center Name Update Parent Cost Center Code Update

Rules Code must be unique Name does not have to be unique Cost center code must already have been created

2013 EnergyCAP, Inc.

Setup Update - G/L


Description

The Setup Manager offers a specific template for updating General Ledger Code information.
This topic will...

provide all the rules and restrictions included in the Setup Update G/L Template.
Prerequisites

Setup Update G/L Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Columns Subcodes 1-20

Rules Not Required for G/L Setup

Additional Information

Q: What if the subcode needs to be removed? A: Put the value "NULL" in the field

2013 EnergyCAP, Inc.

Setup Update - Meters


Description

The Setup Manager offers a specific template for updating Meter information.
This topic will...

provide all the rules and restrictions included in the Setup Update Meter template.
Prerequisites

Setup Update Meter Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Meter Code Update

Meter Code does not have to be unique. However, the combination of the Meter Code and the Vendor Code must be unique. Does not have to be unique. Can consist of letters, numbers, and special characters.

Meter Name Update

Meter Serial # Update Meter Serial # Effective Date Parent Building Code Update Date the meter serial This is the Building the meter is directly listed under; Select a Building from the available buildings in the drop down list. Rates available in the drop down are populated based on the Vendor and Commodity selected. Date the new rate will be effective. Templates available in the drop down are populated based on the commodity selected

Rate Schedule Code Update

Rate Effective Date Bill Entry Template Update

Additional Information

The Rate Schedule Code and Bill Entry Template can be updated numerous ways using the following rules: Current Value blank Original Date blank New Value blank New Date not blank Result Invalid, kicked out

2013 EnergyCAP, Inc.

blank

blank

not blank

blank

New record is created. The effective date is set to the first day of the prior month New record is created. The effective date is set to the date specified. Current value remains the same. New effective date replaces current effective date. Current value is updated with new value. Effective date remains the same. New record is created. Current record is end dated on and new effective date is set to the date specified.

blank

blank

not blank

not blank

not blank

not blank

blank

not blank

not blank

not blank

not blank

blank

not blank

not blank

not blank

not blank

2013 EnergyCAP, Inc.

Setup Update - Organizations & Buildings


Description

The Setup Manager offers a specific template for updating Organization & Building information.
This topic will...

provide all the rules and restrictions included in the Setup Update Organizations & Buildings template.
Prerequisites

Setup Update Organization and Buildings Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Columns Organization Code Update Organization Name Update Organization Type Code Update Parent Organization Code Update Building Code Update Building Name Update Address Street1 Update Address Street2 Update Postal Code Update

Rules Code must be unique Name does not have to be unique

Code must be unique Name does not have to be unique New value overwrites the existing service address New value overwrites the existing service address Postal Code must match the selected Country OR a new country must be selected If a Country is selected, the existing postal code must match OR a new postal code must be selected Positive Numeric Values only; Decimals are rounded to the closest whole number; Negative values are not imported and cause a kickout error

Country Update

Floor Area Update

Floor Area Unit Update Floor Area Effective Date Update Primary Use Code Update

2013 EnergyCAP, Inc.

Setup Update - Vendors


Description

The Setup Manager offers a specific template for updating Vendor information.
This topic will...

provide all the rules and restrictions included in the Setup Update Vendor template.
Prerequisites

Setup Update Vendor Template must be generated using the instructions provided by the Setup Manager.
Rules & Restrictions

Template Columns Vendor Code Update Vendor Name Update Website Update

Rules Code must be unique Name does not have to be unique

2013 EnergyCAP, Inc.

Cost Avoidance Settings

Overview
The Cost Avoidance settings section contains the following: Baseline dates and Length Balance point temperatures Minimum Degree Days Cost Avoidance Reasonableness AUC Ranges

Rules and Restrictions


Must have purchased the Cost Avoidance module Must have Admin view permission to access these pages

2013 EnergyCAP, Inc.

Actual Unit Cost


Description The Actual Unit Cost for each bill is used to calculate cost avoidance. To ensure accuracy before processing, the Actual Unit Cost is checked to make sure it is a reasonable value. By setting the Upper and Lower Limit multipliers per commodity, the Cost Avoidance processor is able to flag outliers. This topic will... describe the process for setting the limits for used commodities describe the process for setting the limits for unused commodities Prerequisites The ability to change Actual Unit Costs requires permissions associated with the following User Roles: Administrator - Full Access Step-by-Step 1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Cost Avoidance Settings tree node. 3. Click the AUC Range tab. 4. To show all commodities, click the Include Unused Commodities checkbox. 5. Enter all the values to be changed.

6.
2013 EnergyCAP, Inc.

6. Click Save. Settings were saved popup will appear. Rules & Restrictions Limits can be a maximum of 2 decimal places The Range can be no lower than .1 and no higher than 20 The grid shows only commodities used on bills by default. In order to see all commodities, check the Include Unused Commodities checkbox. If values will not be saved if navigating away from the screen without selecting the Save button. No warning will be displayed.

2013 EnergyCAP, Inc.

Cost Avoidance Meter Settings


Description Cost Avoidance meter settings determine the default values applied to meters on creation of the meter. This topic will... describe the process of changing meter settings Prerequisites The ability to change meter settings requires permissions associated with the following User Roles: Administrator - Full Access Step-by-Step 1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Cost Avoidance Settings tree node. 3. Click the Meter Settings tab. 4. Change all appropriate information.

5. Click Save. The settings were saved popup will appear.

2013 EnergyCAP, Inc.

2013 EnergyCAP, Inc.

Globally Update Meters


Description The Globally Update Meters wizard provides the ability to update the Cost Avoidance settings for multiple meters at one time. This topic will... describe the process for updating multiple cost avoidance meter settings at once Prerequisites The ability to globally update meters requires permissions associated with the following User Roles: Administration Full Access Step-by-Step 1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Cost Avoidance Settings tree node. 3. Click the Globally Update Meters button located above the Meter Settings.

4. On the Update Fields tab, add all fields to be updated and then click Continue. To add a field to the Fields to be Updated list, click a value from the Available fields list. Field settings will be displayed to the right. Adjust settings as necessary using the controls provided. When done, click Save. Repeat the process until all desired fields have been added.

2013 EnergyCAP, Inc.

4.

If it is necessary to remove a field, click the field name from the Fields to be updated list. Field settings will be displayed. Click the Clear button to remove the field from the list.

5. On the Add Filters tab, add and remove filters and then click Continue. To add a filter to the Current Filters list, click the filter name. Filter settings will be displayed. Adjust settings as necessary using the controls provided. When done, click Save. Repeat the process until all desired filters have been added. If it is necessary to remove a filter, click the filter name from the Current Filters list. Filter settings will be displayed. Click the Clear button to remove the filter from the Current Filters list.

2013 EnergyCAP, Inc.

6. On the Progress tab, monitor the progress of the update. For changes on a large number of meters, a progress indicator and estimated time remaining will be displayed. 7. On the Confirmation tab, the results will be displayed after the update is finished.

8. Click Finish.

2013 EnergyCAP, Inc.

8.

Rules & Restrictions Global changes can only be made to meters a user has permission to view. At least one field must be added to the Update list in order to complete the wizard. The baseline length value is in months, not years. Summer adjustment and Winter adjustment will not be attempted on meters that have a baseline greater than 12 months. At least one filter must be applied in order to complete the wizard. Additional Information If the 'Include Meter in Cost Avoidance' filter must be selected for meters to be shown on reports and considered in calculations. The purpose of this option is to allow meters to be exclude from the calculations if the meter is considered irrelevant to energy management activities.

2013 EnergyCAP, Inc.

Template Management

2013 EnergyCAP, Inc.

Adding a Template
Description Bill Templates are commodity-specific forms that define a layout and sequence for entering utility bill information. Once they are created, templates can be assigned to accounts/meters, allowing associated billing and/or consumption information to be entered. Bill Templates allow customization to the appearance of the bill entry interface to closely match the billing information provided by the vendor for each account/meter. Templates ensure that bill entry personnel are capturing all desired billing data including use and cost. This topic will... describe the process for adding a template. Prerequisites The ability to add template requires permissions associated with the following User Roles: Administration Full Access Import a bill in the exact layout needed for the template Step-by-Step 1. Select Administration from the main menu. The Admin tree view will be displayed on the left. 2. Select the Templates node from the tree. 3. Click the Add Template button.

4. On the Introduction tab, read the template overview information. When done, click Continue.

2013 EnergyCAP, Inc.

4.

5. On the Acct/Meter Selection tab, locate the meter bill to be copied and then click Continue. a. The Search for an Account field, locates the account the bill to be copied is attached to. b. The Select a Meter field will displayed all the meters attached to the account selected. c. Once the meter has been selected, the last 24 bills will be listed in the Select a Billing Period field. d. The exact layout to be saved will be displayed in the Sample box below the fields.

6.
2013 EnergyCAP, Inc.

6. On the Template Name tab, input and edit the data as needed and then click Finish.

7. Once the template is saved, it must be assigned to a meter before it will be used during manual bill entry of a bill. Assigning a template can be done in one of two ways. Individually through the Meter Properties page Through a mass update, using the Setup Manager, Meter Update spreadsheet. Rules & Restrictions The start date for the template is 1/1/1980. Only one version of a template can be created at this time. A template can not be edited or deleted. Only active accounts show up in the account search. Only active meters that have a rate and template attached will show up in the meter field. Additional Information The name and code default to the following format if there are enough characters: UNIT_VENDORCODE_RA TECODE_SEQNUM but can be changed. This is the first phase of template management. It is the intention to expand this functionality to include editing and deleting of templates during a future release.

2013 EnergyCAP, Inc.

Workflow Settings
Description
Workflow Settings determine the behavior of the Batches, Bill Approvals, Bill Headers, and Bill Exports.

This topic will...


describe how to change workflow settings

Prerequisites
The ability to view or change Workflow Settings requires permissions associated with the following User Roles: Administrator - Full Access

Step-by-Step
1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Workflow Settings tree node. 3. Update Workflow Settings as necessary. Refer to the Additional Information section of this page for an explanation of each field.

4. Click Save.

2013 EnergyCAP, Inc.

Rules & Restrictions


When the Enter Bills in Batches is not selected, EnergyCAP automatically opens a new batch at the beginning of each day. When the Bill Approval System is not selected, EnergyCAP automatically approves all bill as they are entered. The Bill Export Process does not apply to Express users. If selected, export hold buttons will appear on the bill list and be clickable but will hold no value to Express users. Due Date and Next Reading Bill headers cannot have a default setting

Additional Information
Enter Bills in Batches Confirm edit/delete of bills in closed batches Manually manage when a batch is created and when it is closed If a bill is in a batch that has been closed and a user attempts to edit or delete the bill, a warning message will be presented before allowing the change. When manually entering bills, the quick check audit will be applied. The quick check audit will not be applied to the bill unless the total pay amount of the bill is greater than the value specified. Manually approve bills If a bill has been approved and a user attempts to edit or delete the bill, a warning message will be presented before allowing the change. Enable the management of additional bill headers Select the bill headers to be used, which are required, and what the default will be. Enables the ability to put a bill on Hold for Export Bills can be exported: Never, After Entry, After Batch, After Approval, After Batch Approval If a bill has been exported and a user attempts to edit or delete the bill, a warning message will be presented before allowing the change.

Enable quick check audits Run quick check audit only if the total cost is greater than Use bill approval system Confirm edit/delete of approved bills

Enable bill headers Bill header grid Enable bill export process Export bills Confirm edit/delete of exported bill

2013 EnergyCAP, Inc.

Units of Measure
Description
The Units of Measure can be modified to display the Reporting rollup units and Global reporting units differently on summary report and charts.

This topic will...


Describe the process for changing global reporting units Describe the process for changing reporting rollup units NOT describe the process for changing bill or template units of measure

Prerequisites
The ability to modify Units of Measure requires permissions associated with the following User Roles: Administration Full Access

Step-by-Step
1. Navigate to the Administration section in one of two ways: Select Administration from the Main Menu, OR Click Admin under the More page header options. 2. Select the Units of Measure tree node. 3. To show all commodities, click the Include Unused Commodities checkbox. 4. Change all appropriate values.

5. Click Save. The Settings were Saved popup will appear.

2013 EnergyCAP, Inc.

2013 EnergyCAP, Inc.

Glossary of Terms & Concepts


Description
The following glossary pages contain more specific details of terms and concepts used throughout EnergyCAP and this documentation.

2013 EnergyCAP, Inc.

Degree Days
Description
Degree Days are an important concept in measuring weather severity. EnergyCAP uses the mean daily temperature readings in determining degree days.

This topic will...


explain the degree day concept and how it is used in EnergyCAP. define the balance point temperature concept and its importance in calculating cooling degree days and heating degree days. discuss the advantages of using degree day weather information rather than average daily temperatures in evaluating weather severity and its effect on energy use.

Information
A degree day is calculated as the difference between the average daily temperature (the 'middle value' between the daily high and the daily low) and the building balance point temperature or BPT (default BPT is 60 degrees F, 16 degrees C). It can effectively be used an indicator of weather as it affects the cooling and heating energy required to maintain a comfortable building temperature. The balance point temperature is the temperature at which normal building use would require no energy for heating or cooling. At this outside temperature, the indoor heat gains (due to people, lighting, equipment, etc) "balance" with heat loss through windows, walls, roof and ventilation. A standard of 65F (18C) was established in the 1930s when the concept was first introduced. But because todays modern buildings balance at a lower outdoor temperature due to improved insulation and windows and much more internal heat gains, EnergyCAP calculations use 60F (16C) as the default balance point temperature. When the average daily temperature is above the BPT, the difference is expressed as cooling degree days because energy is needed to cool the building. When the average daily temperature is below the BPT, the difference is expressed as heating degree days because energy is needed to heat the building. The greater the disparity between the BPT and the mean daily temperature, the more energy must be consumed to maintain the building at a desirable temperature. Example 1: Average daily temperature = 80. BPT = 60. Cooling degree days = 20 CDD. (80-60=20) Example 2: Average daily temperature = 60. BPT = 60. No degree days. Example 3: Average daily temperature = 30. BPT = 60. Heating degree days = 30 HDD (60-30=30) In the above examples, Example #2 would require the least energy consumption, and example #3 would require the most. Example #1 would require cooling to maintain the building at a comfortable temperature, while example #3 would require heating. Someone might ask, "To keep it simple, why not use daily average temperature as an indication of weather severity instead of degree days?" The problem with this approach is that highs and lows will cancel each other out over time, falsely indicating lower heating and cooling needs than actually experienced by the building's mechanical systems. The annual average temperature for Chicago is 49 degrees. Does that mean a building in Chicago needs no cooling system? A warm day (80F average temp) combined with a cold day (40F average temp) average 60F. So do two mild days of 61F and 59F. But in the first case there are 20 CDD and 20 HDD while in the second there are 1 CDD

2013 EnergyCAP, Inc.

and 1 HDD. Using degree days, it is clear that the relative amount of energy required to maintain a comfortable building temperature during the first set of days is much greater than for the second set of days. But using average temperature, data, both sets of days would appear to be about the same. For a complete degree day report and charts, navigate to Building Properties for any building in the Buildings & Meters tree, and then click the weather button. Or visit http://www.WeatherDataDepot.com.

2013 EnergyCAP, Inc.

Normalization, M&V, Cost Avoidance and the IPMVP


Description
Cost Avoidance and normalization are related concepts but there are important differences.

This topic will...


explain the related concepts of normalization and Cost Avoidance. discuss measurement and verification of energy savings, and the importance of the International Performance Measurement and Verification Protocol. clarify important differences between Cost Avoidance and normalization in EnergyCAP.

Information
M&V is the industry standard term for the Measurement and Verification of energy savings due to energy management projects. In EnergyCAP, M&V is referred to as Cost Avoidance because the underlying purpose of M&V is to calculate the avoided cost attributable to energy management initiatives. IPMVP, the International Performance Measurement and Verification Protocol, is a document published and maintained by an international non-profit organization (www.EVO-World.org), a recognized authoritative guidance on M&V calculations. EnergyCAP uses the whole building protocol model from the IPMVP for Cost Avoidance calculations. Although EnergyCAPs normalized charts and reports enable comparisons of meter and building usage on more of an apples-to-apples basis due to calendarization and weather adjustments, normalization falls far short of IPMVP-compliant M&V. Here are some important M&V features that are available only in EnergyCAPs Cost Avoidance module: Special adjustments to baseline -- independent variables other than degree days requiring adjustment to todays conditions (floor area, new equipment, occupancy, etc). No loss/no gain treatment of missing bills, new accounts, inactive accounts. Fuel switch and dual fuel scenarios. Calculation of Cost Avoidance -- valuation of avoided usage using todays pricing. Tuning of weather regression results (selection of the best balance point temperature for each meter, removal of statistical outlier months). Manual calculation of savings when needed due to unique circumstances. Meter-by-meter configuration of baseline period and savings start date.

2013 EnergyCAP, Inc.

Setup Manager Importing of Hierarchical Items


Description
The Setup Manager provides a quick and easy way to import organizational setup information. A series of downloadable Excel-format spreadsheets provide a customized template for data entry. The spreadsheets also make it easy to organize and import hierarchical setup data.

This topic will...


provide information about importing hierarchical information into EnergyCAP using the Setup Manager. illustrate the process for creating an organization hierarchy with an example.

Prerequisites
The ability to perform import processes is incorporated in the Administrator - Full Access User Role. See the Setup Templates Fundamentals topic for basic information on the setup process.

Rules & Restrictions


The spreadsheets are structured in a way that allows the hierarchical relationships between items to be defined. Some columns are only used when a row represents a "Parent" item (like an Organization or Account); other columns are only used when the row represents a "Child" item (like a Building or a Meter). In hierarchical templates the Parent item must have been created before it is referenced as a Parent. Parent and Child items can be defined in a single import file as long as the Parent item is defined in a previous row of the import file, or if the Parent already exists in the EnergyCAP database. But if a Child (e.g. Building or Meter) references a Parent item that does not exist, the Child item will not be created. Instead, it will be added to the error file created at the end of the import. Currently there are two templates that require the hierarchical structure to be honored: Organizations & Buildings Accounts & Meters

Additional Information
Q: Why were the templates structured this way? What is the benefit? A: This provides two benefits when viewing the spreadsheet data: It is easy to differentiate different types of objects. In a file that contains both Organization nodes and Building nodes, for example, a user can quickly see which rows represent each item type. Using separate column and row combinations for hierarchy levels provides a visual representation of the Parent-Child relationship even before the data is imported into EnergyCAP. Q: What does this structure look like? Please provide an example. A: An Organization & Building template could look like this:

2013 EnergyCAP, Inc.

Organization Code AGSCI

Organization Name Agriculture Sciences

Organization Type Code Department

Parent Organization Code

Building Code

BuildingName

AGSCI ATHLETIC Athletic Department Department ATHLETIC ATHLETIC

CLASS1

Classroom Building

ICERINK RECHALL

Ice Rink Recreation Hall

Note that two Parent organizations would be created/updated, along with Child buildings for each.

2013 EnergyCAP, Inc.

Setup Templates Fundamentals


Description
This page details principles that are common to all import and update templates. Understanding the Rules & Restri ctions is important for using the templates successfully.

This topic will...


present common rules and restrictions that must be understood and observed to successfully and correctly import or update organization data into EnergyCAP using the Excel spreadsheet templates provided.

Prerequisites
The Administrator - Full Access User Role is required to use the Setup Manager.

Rules & Restrictions


All EnergyCAP-generated Setup templates have these elements in common: Row 1: Contains the EnergyCAP description for the data to be imported. Row 2: Indicates if the data is required for that column, as well as any default values that will be populated during the import if no value is provided. Row 3: Indicates the format and limits for the data that is expected. If the data does not match what is indicated, that item will not be created and an error file with details will be generated following the import. Some template columns contain pre-populated dropdown lists based on data from the existing database. This helps ensure that the correct data is imported. A value can either be selected from the dropdown or typed directly into the cell. However, if the entered value is not contained in the provided drop-down list, an error will result. In cases where there is a relationship between multiple columns (e.g. Vendors and Rates), the drop-down selection options will change based on available data. Imports that provide hierarchical structure (e.g. Buildings and Organizations) have several data specifications that need to be understood before completing in the import spreadsheet. These details are discussed in the Setup Manager Importing of Hierarchical Items topic. Most items in EnergyCAP are identified by a Name and a Code. A Name is usually the friendly text that is the 'common name' of the item (e.g. Recreation Building). The Code is typically an abbreviated form that is a unique identifier for that item. Every Code in EnergyCAP must be unique. Whenever a Name is required in the setup template, the Code is required as well, and vice versa.

Additional Information
Import errors and the resulting returned Template Any items that could not be created because of errors in the spreadsheet data are saved to a new file following the import process. This new file contains ONLY spreadsheet rows that did not import correctly. Any cell that had problems is highlighted in red; text notes are provided in the first column of the spreadsheet and as cell notes for each problem cell. After the errors have been corrected, the new file can be saved and imported using the Setup Manager. If there are any remaining errors, a new file will be provided, and the process can be repeated.

2013 EnergyCAP, Inc.

Statistical Outliers
Description
Handling statistical outliers in use vs. weather calculations is important in performing accurate energy-related adjustments to usage data.

This topic will...


define what a statistical outlier is in EnergyCAP weather analyses. explain how statistical outliers are identified and handled for the related processes of Cost Avoidance and calendarization/normalization.

Information
Defining Statistical Outliers Statistical outliers are handled differently in the EnergyCAP Express Calendarization/Normalization process than they are in the EnergyCAP Enterprise Cost Avoidance module. In the Cost Avoidance module (currently available only in EnergyCAP Enterprise), statistical outliers (those periodic usage data points which fall more than two standard deviations away from the regression line defining a use/weather correlation for a meter) are handled as exceptions and are excluded from the weather adjustment process. In other words, if June is a strange month (for whatever reason), its data is excluded from the regression calculation. This allows a better usage vs. weather correlation using the remaining (non-excluded) bills. In EnergyCAP Online/Express, the Calendarization and Normalization processes handle outliers differently. These processes are less sophisticated and less calculation-intensive than Cost Avoidance. Outliers are not excluded or handled differently than other bills. If an outlier causes the regression to fail, it invalidates weather adjustments for that meter, that season, that year. If an outlier exists and the regression remains valid, the weather factors are applied to outlier bills just as they are applied to non-outlier bills. Identifying Statistical Outliers How does EnergyCAP identify outliers? An outlier is a bill point that falls far from where it might be expected to fall, based upon the trend established by other bills. Benefits of Statistical Outliers Outliers provide potentially valuable information because they help identify an abnormal bill that has usage far different than we might expect. Questions that outliers prompt might include: Is the recorded usage accurate? Was the usage entered correctly? Were we billed correctly? Did something unusual occur in the building during the month that caused higher than expected usage? Are there problems with HVAC or lighting controls?

2013 EnergyCAP, Inc.

Use vs. Weather


Description
In Cost Avoidance and normalization calculations, EnergyCAP performs a straight line regression analysis, plotting use vs. weather to determine the impact of weather on energy use. Below are several use/weather graph examples that help explain the theory behind the determination of weather sensitivity for a meter.

This topic will...


explain the use vs. weather regression calculations that enable EnergyCAP to determine weather sensitivity of a meter. explore different use/weather scenarios and how they affect weather sensitivity calculations.

Information
The Use vs. Weather charts in EnergyCAP indicate if, and how much, weather sensitivity exists for each meter, each year, and each summer/winter season. EnergyCAP calculates weather sensitivity by comparing building energy use with known weather data for the time period represented by the utility bills associated with that building. IMPORTANT NOTE: During organization setup, each building should be assigned a correct postal code ( Buildings & Meters > Building Properties) because EnergyCAP uses the building location to identify the nearest weather station in order to retrieve the degree day weather data for meters assigned to the building. The EnergyCAP single linear regression approach to calculating weather sensitivity can be visualized as a plot of the utility bills for each calendar year, month-by-month, on a grid with consumption on the vertical axis and weather (as expressed using the degree days concept) on the horizontal axis. EnergyCAP does this internally via statistical analysis, but it is possible to obtain the same results by plotting the monthly consumption data in a spreadsheet. The degree days are totaled for each day in each bills billing period. Example 1 - Not Weather Sensitive Consider this raw plotted data from an electric meter in the winter.

2013 EnergyCAP, Inc.

Each point represents an electric bill received in a winter month. The "best fit" line is found by statistical single linear regression analysis, and is called the "regression line." For the charted data above, it is easy to see that the regression line would be horizontal. The meter uses about the same amount of electricity every month. This suggests that the meter is not weather-sensitive in winter, because the cold weather apparently has no effect on usage. A line slope of zero means that the weather factor (amount of weather-related usage, expressed as kWh per degree day) would also be zero. Example 2 Highly Weather Sensitive

Consider this data from a gas meter in winter. This graph is very different. As the regression line makes clear, the usage increases as the weather gets colder, and decreases as the weather gets milder. Clearly, this meter is weather sensitive. At the point of zero heating degrees (mild weather), the usage is zero. This means that the meter has no base load. There is no non-weather sensitive usage. All of the energy used is related to the weather. Example 3 Partially Weather Sensitive

2013 EnergyCAP, Inc.

This winter utility data from an electric meter shows a consistent slope which rises to the right, so the meter is weather sensitive. In the cold months such as December, January, and February, the weather load is greater, while in the mild months the weather load is smaller. Note, however, that unlike the previous example, the Y-intercept (the point at which the regression line meets the vertical axis) has a value greater than zero in this case, about 5,000 kWh. The Y intercept reveals the base loadthe non-weather-related portion of the total usage. This meter uses 5,000 kWh even if there is mild weather (zero heating need degrees) plus some additional kWh depending on the weather. The slope of the line is the weather factor in usage per degree day. The calendarization and normalization processors multiply the weather factor times the total degree days to determine how much weather sensitive energy to allocate to each month. The weather sensitive usage is then subtracted from the total usage. The remainder is the non-weather sensitive usage. This data is then day-prorated to each month of the billing period. NOTE: The weather model used for each calendar year is derived from utility bill data for the previous year. If previous year data is incomplete, no weather adjustments are calculated.

2013 EnergyCAP, Inc.

You might also like