Practice questions API-570 course

Api-578 recommended practice Open Book

Q1)

API 578 provides guidelines for a quality assurance system to verify: a all metals. b. all alloy materials. c. non-ferrous materials. d. For Carbon steels

Q2)

An inspection lot includes: a. all materials from same supplier. b. all materials from same manufacturer. c. all materials of the same material type but different heat numbers d. all materials of the same material type and from the same heat numbers

Q3) Who has the responsibility to verify that the material verification program is properly implemented? a. Authorized inspector b. Owner/User c. Repair organization d. Engineering organization Q4) The material verification program specified by API 578 covers: a. only new pressure-containing components b. only old pipe, and fittings. c. only old and new pipe, fittings, and welds. d. .none of these During alloy welding: a. one electrode from each box should be sampled. b. two electrodes from each box should be sampled. c. one electrode from each lot should be sampled. d. two electrodes from each lot should be sampled. Q6) Who has the responsibility to determine the extent of PMI testing required on existing piping systems? a. Authorized inspector b. Owner/User c. Repair organization d. Engineering organization Q7) PMI tools that use X-Ray fluorescence can not detect: a. carbon content.

Q5)

b. chrome content. c. iron content. d. molybdenum content. Q8) All personnel performing PMI tests should be: a. qualified by ASNT exam. b. qualified by the owner/user. c. knowledgeable about the operation of the PMI test equipment. d. knowledgeable about the operation of the plant where the PMI is conducted.

Practice questions API-570 course


Api-578 recommended practice Open Book- answer key 1 2 3 4 5 6 7 8 b d b c a b a c