Professional Documents
Culture Documents
AESO Reference: {Insert Project Number} {Insert TFO} Reference: {Insert TFO Project Number} Version 1
{Project Name}
Scope Overview {Insert a brief summary of the project scope, for example 2 to 5 sentences} Schedule & Status
Activity Milestone Schedule (Base) Plan Forecast Actual Schedule Status (% Complete) Planned Actual Planned Next Period Explanation (Status) <Comments only required if Behind Schedule should include explanation of why and planned action to recover>
File Need Application Need Approval Issue Functional Specification Submit PPS to AESO AESO Direction to TFO Facilities Application EUB Facilities Approval (P&L) EUB Connection Order Submit Facility Information to AESO Transmission Lines Engineering - Start - Complete Procurement (Materials) - Start - Complete Construction - Start - Complete Commissioning - Start - Complete Substations Engineering Procurement (Materials) - Start - Complete - Start - Complete
Page 1 of 6
Version 1
Activity
Explanation (Status) <Comments only required if Behind Schedule should include explanation of why and planned action to recover>
Construction Commissioning
Telecommunications Engineering
- Start - Complete Procurement (Materials) - Start - Complete Construction - Start - Complete Commissioning - Start - Complete Energization Checklist In-Service-Date Project Close Out
Unplanned/Emerging Issues 1. {Provide comments of unforeseen events that will or have impacted the project, which are of relevance between TFO and AESO} 2. 3. 4. 5. 6. ..
Page 2 of 6
Version 1
Pending Changes
Committed To Date
Labour1 Materials1 Sub-Total Owners Costs1 Distributed Costs1 Salvage1 AFUDC2 E&S3 TOTALS
1 2
These are defined in the notes page of the Service Proposal Estimate and the Proposal to Provide Services document posted on the AESO web site Allowance for Funds Used During Construction 3 As defined in each TFOs General Rate Application. Monthly Project Progress Report Page 3 of 6 Version 1
Project Trends and Changes Description of Trends and Changes 1. 2. 3. 4. 5. 6. 7. Reason or Need Estimated Effects SCH $$
Page 4 of 6
Version 1