ADMINISTRATION

BUILDING:
In Progress

EDITION NO. 7, October 20, 2008

1
Progress in Construction
of the Administration Building

In early October, the concrete for the 1st lift of basement floor was placed.
The works like rebar and form installation for the 2nd lift of basement and 1st
floor and water curing of the placed concrete were the major activities
during the middle of October.

Simultaneously, construction works for the Boiler, Turbine and Control


Buildings are on-going. Preparations for the chimney stack area have also
been done while the design calculations have been prepared by the
contractor.

Next month’s major activity will be the rebar, form and staging works for the
1st floor of the superstructure of the Administration Building.

On-going works for Administration Building


(October 14, 2008)

2
Boiler and Turbine Bldg Foundation Progress
In the month of September 2008, the bored piling works for Boiler No. 1 has
been finished. Excavation works around the bored pile have proceeded
during October. After the piles have been exposed, cutting or removing the
concrete material of that exposed portion will be done. Soil backfilling
compaction is done to make the excavated ground uniform.

The installation of re-bars for the foundation will be proceeded. Concrete


pouring will be done after all necessary installations are placed for the
foundation. A curing period for the concrete foundation will be observed
before structural works could be proceeded.

For Boiler Unit No. 2, bored piling works are still on-going and is projected
to be finished by the end of October 2008.

For the Turbine Building, pile works for building foundation are still on
going. PC piles are used to bear the load of the turbine building. For the
turbine generator, pedestal bored piles are used and the works has been
started in October, 2008.

On-going excavation & pile cutting works for Boiler # 1


foundation (October 10, 2008)

3
Signing of MOA for MMT, EMF and EGF

On September 22, 2008, a Memorandum of Agreement (MOA) was mutually


signed by KEPCO SPC Power Corporation (KSPC) and the Department of
Environment and Natural Resources – Environmental Management
Bureau (DENR-EMB) at the City Hall of Naga, Cebu, creating the KSPC
Multi-Partite Monitoring Team (MMT) and establishing the
Environmental Monitoring Fund (EMF) and Environmental Guarantee
Fund (EGF) in coordination with the City of Naga-LGU and SPC Power Corp.

The KSPC-MMT, being a multi-sectoral committee, is represented by DENR-


EMB, City of Naga LGU, Barangay LGUs, Public Organizations, SPC Power
Corp. and KSPC with the primary task of monitoring on the environmental
compliance of the project during construction stage and all throughout the
operation stage as well as the implementation of various Social Development
Plan/Corporate Social Responsibilities Program of KSPC.

One of the contents of the MOA is the Environmental Guarantee Fund


(EGF) which shall be earmarked for the immediate rehabilitation and
compensation of affected communities in cases of any damages or accidents.

Signing of MOA for the creation of MMT, EMF and EGF at the
City Hall of Naga, Cebu (September 22, 2008)

4
Project Progress

Close-up of Excavation and pile cutting for Boiler Building #1


(October 2, 2008)

Concrete Pouring of Administration Building basement wall


(October 3, 2008)

5
Project Progress

Administration Bldg. basement wall after concrete pouring


(October 3, 2008)

Wall Chipping of Administration Building basement


(October 7, 2008)

6
Project Progress

Perimeter Fence of construction site


(October 7, 2008)

Main Gate of construction site


(October 14, 2008)

7
Project Progress

On-going construction works


(October 14, 2008)

Automatic Truck and Heavy Equipment washing facility


(October 14, 2008)

8
Project Information

 PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC)

 CAPACITY : 100 MW x 2 Units

 PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed


Combustion)

 LOCATION : Colon, City of Naga (20 Km from Cebu City)

 TARGET COMPLETION : Unit #1: February 2011; Unit #2: May 2011
DATE

Contact us

Mr. Bag Woon Choi


Mr. Beach Padogdog
KEPCO SPC Power Corporation
Colon, City of Naga, Cebu
Tel. No. (032) – 272 6290~91, 93
Fax No. (032) – 489 7010