You are on page 1of 29

Project Management Professional (PMP)

PMP Study Notes & Formula Guide

Knowledge Areas (9)


Project Integration Management Project Scope Management Project Time Management

Project Cost Management

Project Quality Management

Project Human Resource Management Project Procurement Management


2

Project Communications Management

Project Risk Management

Leverage Blueprint - PMP Study Notes & Formula Guide

Processes (5)

Initiation

Planning

Execution

Monitor and Control

Closing

Leverage Blueprint - PMP Study Notes & Formula Guide

Project Management Processes (42)


Develop Project Charter Develop Project Management Plan Direct / Manage Project Execution Monitor / Control Project Work Perform Integrated Change Control Close Project or Phase
Leverage Blueprint - PMP Study Notes & Formula Guide 4

Project Integration Management

Project Management Processes (42)


Project Scope Management
Collect Requirements Define Scope Create WBS Verify Scope Control Scope
5

Leverage Blueprint - PMP Study Notes & Formula Guide

Project Management Processes (42)


Define Activities

Project Time Management

Sequence Activities

Estimate Activity Resources


Estimate Activity Durations Develop Schedule Control Schedule

Leverage Blueprint - PMP Study Notes & Formula Guide

Project Management Processes (42)


Project Cost Management

Estimate Costs Determine Budget Control Costs

Leverage Blueprint - PMP Study Notes & Formula Guide

Project Management Processes (42)


Project Quality Management

Plan Quality Perform Quality Assurance

Perform Quality Control

Leverage Blueprint - PMP Study Notes & Formula Guide

Project Management Processes (42)


Project Human Resource Management
Leverage Blueprint - PMP Study Notes & Formula Guide

Develop Human Resource Plan Acquire Project Team Develop Project Team Manage Project Team
9

Project Management Processes (42)


Project Communications Management
Identify Stakeholders Plan Communications

Distribute Information
Manage Stakeholder Expectations Report Performance

Leverage Blueprint - PMP Study Notes & Formula Guide

10

Project Management Processes (42)


Plan Risk Management

Project Risk Management

Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Monitor and Control Risks

Leverage Blueprint - PMP Study Notes & Formula Guide

11

Project Management Processes (42)


Project Procurement Management
Plan Procurements Conduct Procurements Administer Procurements Close Procurements
12

Leverage Blueprint - PMP Study Notes & Formula Guide

Network Diagram
Activity Duration = EF ES + 1 or Activity Duration = LF LS + 1

Total Float = LS - ES or Total Float = LF EF

Free Float = ES of Following - ES of Present - DUR of Present

EF = ES + duration - 1

ES = EF of predecessor + 1

LF = LS of successor - 1

LS = LF - duration + 1

Leverage Blueprint - PMP Study Notes & Formula Guide

13

Project Selection
PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Formula not required. Select biggest number.

ROI = Formula not required. Select biggest number.

IRR = Formula not required. Select biggest number.

Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment.

BCR = Benefit / Cost

CBR = Cost / Benefit

Opportunity Cost = The value of the project not chosen.

Leverage Blueprint - PMP Study Notes & Formula Guide

14

Earned Value Management


BAC = Budget At Completion EV = Actual % * BAC PV = Planned % * BAC AC = Sum of all incurred costs

CPI = EV / AC
CV = EV - AC SV = EV - PV
< 1 = Over Budget > 1 = Under Budget

SPI = EV / PV
< 1 = Behind Schedule > 1 = Ahead of Schedule

EAC = BAC / CPI

EAC = AC + ETC

EAC = AC + (BAC + EV) / CPI

ETC = EAC - AC

VAC = BAC - EAC

BCWS = PV

BCWP = EV

ACWP = AC

Leverage Blueprint - PMP Study Notes & Formula Guide

15

TIPS: Earned Value Management


Negative is bad Positive is good If Variance: EV - Something

If Index: EV / Something

If Cost related use AC

If Time related use PV

Most formulas start with EV


Leverage Blueprint - PMP Study Notes & Formula Guide 16

PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT = (Pessimistic Optimistic) / 6

PERT Activity Variance = ((Pessimistic Optimistic) / 6)^2


Leverage Blueprint - PMP Study Notes & Formula Guide

PERT Variance all activities = sum((Pessimistic Optimistic) / 6)^2


17

Values
1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73%

6 sigma = 99.99%

Control Limits = 3 sigma from mean

Control Specifications = Defined by customer; looser than the control limits

Order of Magnitude estimate = -25% to +75%

Preliminary estimate = -15% to + 50%

Leverage Blueprint - PMP Study Notes & Formula Guide

18

Values
Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0%

Float on the critical path = 0 days

Pareto Diagram = 80/20

Time a PM spends communicating = 90%

Crashing a project = Crash least expensive tasks on critical path.

JIT inventory = 0% (or very close to 0%.)

Minus 100 = (100) or -100

Leverage Blueprint - PMP Study Notes & Formula Guide

19

Procurement

PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + TargetCost


Leverage Blueprint - PMP Study Notes & Formula Guide 20

Depreciation
Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life)
Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense

Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.

Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)

Leverage Blueprint - PMP Study Notes & Formula Guide

21

Human Resource Management


Organizational Structures:
Functional, Matrix (weak, balanced, strong) , Projectized, Composite

Maslows Hierarchy of Needs:


Physiological, Safety, Social, Selfesteem, Self-actualization.

McGregor:
Theory X, Theory Y.

Ouchi:
Theory Z. Motivated by commitment, opportunity advancement.

Herzbergs Theory of Motivation:


Hygiene factors, Motivating Agents.

Leadership Styles:
Directing, Facilitating, Coaching, Supporting, Autocratic, Consultative, Consensus.

Project Manager Powers:


Formal (legitimate,) Reward, Penalty (coercive), Expert, Referent.

Conflict Management:
Withdraw (avoid), Smooth (accommodate), Compromise, Force, Collaborate, Confront (problem solving.)

Leverage Blueprint - PMP Study Notes & Formula Guide

22

Quality Management
Ishikawa = Fishbone Diagram: cause and effect. Pareto Diagram: Identify problems and frequency. 80/20 Rule.

Flow Charts; Control Charts.

Just in Time: Reduces inventory; requires additional quality control.

Quality Theories: Kaizen (continuous improvement,) Six Sigma, TQM (total quality management.)

Kaizen: Small improvements to reduce costs and improve consistency.

Deming Cycle: Plan, Do Check, Act

Leverage Blueprint - PMP Study Notes & Formula Guide

23

Risk Management
Risk Strategies (threats):
Avoid Transfer Mitigate Accept

Risk Strategies (opportunities):


Exploit Share Enhance Accept

Qualitative Risk Analysis: Chance and impact of risk occurrence Results in prioritized list of risks; risk ranking. Tools:

Quantitative Risk Analysis: Numerical analysis of probability and impact.

Interviews Sensitivity Analysis Decision Tree Analysis Simulation Monte Carlo Analysis

Leverage Blueprint - PMP Study Notes & Formula Guide

24

Communications

Communication Channels = n * (n-1) / 2


Leverage Blueprint - PMP Study Notes & Formula Guide 25

Probability

EMV = Probability * Impact in currency


Leverage Blueprint - PMP Study Notes & Formula Guide 26

Rules Based on Numbers


80 Hour Rule = Max size of work packages
80/20 Rule = Paretos Law
20% of causes responsible for 80% of problems

0/50/100 = Work package completion


No credit until 50% complete No additional credit until 100% complete

Leverage Blueprint - PMP Study Notes & Formula Guide

27

Contact Details

Leverage Blueprint - PMP Study Notes & Formula Guide

28

Contact Detail
Postal
P.O. Box CT 6440, Cantonments Accra, Ghana

Telephone
233 (0) 200 116 119

Email
blueprint@leverage-blueprint.com

Website
www.leverage-blueprint.com

Skype
leverage.blueprint

Facebook
www.facebook.com/leverage.blueprint.com

Twitter
www.twitter.com/levBlueprint
Leverage Blueprint - PMP Study Notes & Formula Guide 29

You might also like