You are on page 1of 29

M MTEKP PRO

POW WER TRANSF R FORME ER TES STING

MT TEKPRO Technolo ogies Pvt t. Ltd, Ne ew Delhi -110048 8


Phone:- +91 P 1 11 4617 3333, Fax:-+91 11 41825662 Email:- info@m mtekpro.com, shonal@ @mtekpro.c com, Web:-m mtekpro.co om

m[T Type text]

[Type tex xt]

[Typ pe text]

Power Transformer Testing 2

Testing of Power Transformers


1. Verification of voltage Ratio and vector Group or phase displacement and polarity.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing

1. Turn Ratio Measurement


1.1 Purpose of measurement
The no-load voltage ratio between two windings of a transformer is called turn ratio. The aim of measurement is; confirming the no-load voltage ratio given in the customer order Specifications, determining the conditions of both the windings and the connections and examining the problems (if any). The measurements are made at all tap positions and all phases.

1.2 Turn Ratio Measurement Bridge method


Measurement of turn ratio is based on, applying a phase voltage to one of the windings using a bridge (equipment) and measuring the ratio of the induced voltage at the bridge. The measurements are repeated in all phases and at all tap positions, sequentially. During measurement, only turn ratio between the winding couples which have the same magnetic flux can be measured, which means the turn ratio between the winding couples which have the parallel vectors in the vector diagram can be measured.

Theoretical turn ratio = HV winding voltage / LV winding voltage


The theoretical no-load turn ratio of the transformer is adjusted on the equipment by an adjustable transformer; it is changed until a balance occurs on the % error indicator. The value read on this error indicator shows the deviation of the transformer from real turn ratio as %.

(Measured turn ratio) - (Designed turn ratio) % Deviation = (Designed turn ratio) * 100

The % deviation of the turn ratios should be 0.5 %.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

1.2 Determining the Vector Group

Power Transformer Testing 4

Depending on the type of the transformer, the input and output windings of a multi-phase transformer are connected either as star ( Y ) or delta( D ) or zigzag( Z ). The phase angle between the high voltage and the low voltage windings varies between 0 and 360. Representing as vectors, the HV winding is represented as 12 (0) hour and the other windings of the connection group are represented by other numbers of the clock in reference to the real or virtual point. For example, in Dyn 11 connection group the HV winding is delta and the LV winding is star and there is a phase difference of 330 (11x30) between two windings. While the HV end shows 12 (0), the LV end shows 11 oclock (after 330). Determining the connection group is valid only in three phase transformers. The high voltage winding is shown first (as reference) and the other windings follow it. If the vector directions of the connection are correct, the bridge can be balanced. Also, checking the connection group or polarity is possible by using a voltmeter. Direct current or alternating current can be used for this check. The connections about the alternating current method are detailed in standards. An example of this method is shown on a vector diagram below.

Fig: - Connection group representation and measuring

The order of the measurements: 1) - 3 phase voltage is applied to ABC phases 2) - voltage between phases (e.g. AC) is measured 3) - A short circuit is made between C and n 4) - voltage between B and B is measured 5) - voltage between A and c is measured As seen from the vector diagram, in order to be Dyn 11 group, A.c > AB > B.b correlation has to realized. Taking the other phases as reference for starting, same principles can be used and also for determining the other connection groups, same principles will be helpful.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 5

MTEKPRO Technologies Pvt. Ltd, New Delhi.

1.3 Polarity test 1.3.1 Polarity test using voltmeters Single-phase transformers

Power Transformer Testing 6

For single-phase transformers the polarity can be either additive or subtractive. The low voltage winding is connected in series with the high voltage winding, either in phase or in opposite phase. For additive determination of polarity, if the phase displacement is correct, see figure 1.3.1.

Figure 1.3.1: Connection for additive polarity test And for subtractive determination of polarity, see figure 1.3.2

Figure 1.3.2: Connection for subtractive polarity test. Polyphase Transformers. The vector group must be checked for three-phase transformers. This is done by connecting a terminal from the low voltage side to a terminal on the high voltage side, see figure 1.3.3. When a three-phase supply is connected to the high voltage winding, potential differences appear between the open terminals and are used to determine the vector group.

Figure 1.3.3: Polarity test and connection test on three-phase transformer Using one voltmeter

MTEKPRO Technologies Pvt. Ltd, New Delhi.

1.3.2 Polarity check using DC current.

Power Transformer Testing 7

This method establishes the polarity of single and three-phase transformers by briefly switching on a DC current source at the high voltage winding, see figure 1.3.4. The polarity is shown on a polarized voltmeter connected to the low voltage side.

Figure 1.3.4: Basic analog ratio bridge circuit

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 8

Testing of Power Transformers 2. Winding Resistance Measurement.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

2. Winding Resistance Measurement. 2.1 Purpose of the test


Winding resistance serves a number of important functions like:

Power Transformer Testing 9

Providing a base value to establish load loss. Providing a basis for an indirect method to establish winding temperature and Temperature rise within a winding. Inclusion as part of an in-house quality assurance program, like verifying electric continuity within a winding.

2.2 General.
Winding resistance is always defined as the DC-resistance (active or actual resistance) of a winding in Ohms [].

Temperature dependence
It should be noted that the resistivity of the conductor material in a winding copper or aluminum is strongly dependent on temperature. For temperatures within the normal operating range of a transformer the following relationship between resistance and temperature is sufficiently accurate:

C+2 R 2 = R1 C+1
Where: R1 = resistance at temperature 2 R2 = resistance at temperature 1 = temperature in C C = constant which is a function of material type IEC [1] specifies: C = 235 for copper = 225 for aluminum

Principle and methods for resistance measurement:There are basically two different methods for resistance measurement: namely, the so-called voltmeterammeter method and the bridge method.

Voltmeter-ammeter Method
The measurement is carried out using DC current. Simultaneous readings of current and voltage are taken. The resistance is calculated from the readings in accordance with Ohms Law. This measurement may be performed using conventional analog (rarely used nowadays) or digital meters; however, today digital devices such as Data Acquisition Systems (DAS) with direct resistance display are being used more and more.

Measurement with voltmeter and ammeter


The measuring circuit is shown in figure 2.1. Resistance RX is calculated according to Ohms Law:

RX=U/I
MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing


The advantage of this method is the simplicity of the test-circuit. On the other hand, this method is rather 10 inaccurate and requires simultaneous reading of the two instruments.

Resistance measurement using a Kelvin (Thomson) Bridge


This measurement is based on the comparison of two voltage drops: namely, the voltage drop across the unknown winding resistance RX, compared to a voltage drop across a known resistance RN (standard resistor), figure 2.2. DC-current is made to flow through RX and RN and the corresponding voltage drops are measured and compared. The bridge is balanced by varying the two resistors Rdec and RV, which have relatively high resistance values. A balanced condition is indicated when the galvanometer deflection is zero, at which time the following relationship holds:

Rdec RX = RN Rv
The influence of contact resistances and the connection cable resistances (even of the connection between RX and RN) can be neglected.

Figure 2.1: Voltmeter - ammeter method measuring circuit

Figure 2.2: Kelvin (Thomson) Bridge method

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing Value of the DC-current of measurement


Maximum value: To avoid an inadmissible winding temperature rise during the measurement, the DC-current should be limited to a maximum 10% of the rated current of the corresponding winding. Minimum value: The lower limit of the DC-current is given by the following considerations: The measuring circuit for all resistance measuring methods consists of a DC-source and a transformer winding fixed around an iron core as represented by the following equivalent circuit, Winding inductance is strongly dependent on current and displays the following characteristic for transformers, see figure 3.4. As the measuring circuit time-constant is given by the relation L/R, the current-time characteristic differs quite significantly when switching on the DC-source, depending on the measuring current value (magnetizing current). Therefore, the DC measuring current should be at least 1.2 times higher than the crest value of the magnetizing current to be sure to saturate the iron core

11

Figure 3.3: Equivalent circuit of a Winding

Figure 3.4: Inductance of transformer winding as a function of the current.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 12

Testing of Power Transformers 3. Magnetic Balance and Magnetising Current Measurement.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 13 Magnetic Balance Test on 3-phase Transformers


This test is conducted only in three-phase transformers to check the imbalance in the magnetic circuit. In this test, no winding terminal should be grounded; otherwise results would be erratic and confusing. The test shall be performed before winding resistance measurement. The test voltage shall be limited to maximum power supply voltage available at site.

Evaluation Criteria
The voltage induced in the center phase is generally 50% to 90% of the applied voltage on the outer phases. However, when the center phase is excited then the voltage induced in the outer phases is generally 30 to 70% of the applied voltage. Zero voltage or very negligible voltage with higher excitation current induced in the other two windings should be investigated. The voltage induced in different phases of transformer in respect to neutral terminals given in the table below.

Left side phase AN Voltage applied at left side phase Voltage applied at central phase Voltage applied at right side phase 230 V 115 V 50 V

Central phase BN 180 V 230 V 180 V

Right side phase CN 50 V 115 V 230 V

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 14 EXCITING/ MAGNETISING CURRENT MEASUREMENT


This test should be done before DC measurements of winding resistance to reduce the effect of residual magnetism. Magnetising current readings may be effected by residual magnetism in the core. Therefore, transformer under test may be demagnetised before commencement of magnetizing current test. Three-phase transformers are tested by applying Single-phase 10 kV voltage to one phase (HV terminals) and keeping other winding open circuited and measuring the current at normal, minimum and max. tap positions. Keep the tap position in normal position and keep HV and LV terminals open. Apply 1phase 10kV supply on IV terminals. Measure phase to phase voltage between the IV terminals and current on each of the IV terminals. The set of reading for current measurement in each of the tap position should be equal. Unequal currents shall indicate possible short circuits in winding. Results between similar single-phase units should not vary more than 10 % .The test values on the outside legs should be within 15 % of each other, and values for the centre leg should not be more than either outside for a three-phase transformers. Results compared to previous tests made under the same conditions should not vary more than 25%. If the measured exciting current value is 50 times higher than the value measured during precommissioning checks, then there is likelihood of a fault in the winding which needs further analysis. The identical results confirm no damage due to transportation. The availability of test data of normal condition and faulty condition results help us to analyze the problem in future.

Measurement of Magnetization Current at Low Voltage


For 3-phase transformers, the test shall be conducted either with 415 V, 3-phase (neutral grounded) or 230 V, 1 phase (preferred). For single phase transformers, the test shall be conducted with 230 V. This test is performed to locate defect in magnetic core structure, shifting of windings, failures in turn insulation or problem in tap changers. The acceptance criteria for the results of exciting current measurement should be based on the comparison with the previous site test results or factory test results. The general pattern is two similar high readings on the outer phases and one lower reading on the center phase, in case of three phase transformers. An agreement to within 25% of the measured exciting current with the previous test is usually considered satisfactory. If the measured exciting current value is 50% higher than the value measured during precommissioning checks, then the winding needs further analysis.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 15

Testing of Power Transformers 4. MEASUREMENT OF SHORT CIRCUIT IMPEDANCE

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing MEASUREMENT OF SHORT CIRCUIT IMPEDANCE


This test is used to detect winding movement that usually occurs due to heavy fault current or mechanical damage during transportation or installation since dispatch fro the factory. Ensure the isolation of Transformer from High Voltage & Low voltage side with physical inspection of open condition of the concerned isolators/disconnectors. In case tertiary is also connected, ensure the isolation of the same prior to commencement of testing The measurement is performed in single phase mode. This test is performed for the combination of two winding. The one of the winding is short circuited and voltage is applied to other winding. The voltage and current reading are noted. The test shall be conducted with variac of 0-280 V, 10 A, precision RMS voltmeter and ammeter. The conductors used for short-circuiting one of the transformer windings should have low impedance (less than 1m-ohm) and short length. The contacts should be clean and tight. The acceptable criteria should be the measured impedance voltage having agreement to within 3 percent of impedance specified in rating and diagram nameplate of the transformer. Variation in impedance voltage of more than 3% should be considered significant and further investigated. The formula for calculating the percentage impedance with current and frequency correction is:

16

Where: Vtest = Test voltage Vrated =Rated voltage Itest = Test current Irated = Rated current ft = Test frequency fr = Rated frequency

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 17

Testing of Power Transformers 5. Measurement of dissipation factor (tan) of the insulation system capacitances.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing

Measurement of dissipation factor (tan) of the insulation system capacitances


The purpose of the measurement
The insulation power-factor test, similar to the insulation resistance test, allows certain conclusions to be drawn concerning the condition of the transformer insulation. The significance of the power factor figure is still a matter of opinion. Experience has shown, however, that the power-factor is helpful in assessing the probable condition of the insulation when good judgment is used [51].

18

General
IEC defines the power factor as the ratio between the absorbed active power to the absolute value of the reactive power. This corresponds to tan. IEEE [51], on the other hand defines the insulation power-factor as the ratio of the power dissipated in the insulation in watts, to the product of the effective voltage and current in volt-amperes (corresponding to the apparent power) when tested using a sinusoidal voltage. Insulation power-factor is usually expressed in percent [51]. Measurement of power-factor values in the factory is useful for comparison with field power-factor measurements and assessing the probable condition of the insulation. It has not been feasible to establish standard power-factor values for the following reasons: There is little or no relationship between power-factor and the ability of the Transformer to withstand the prescribed dielectric tests. The variation of power-factor with temperature is substantial and erratic. The various liquids and insulation materials used in transformers result in Large variations in insulation power factors [51].

The measuring circuit / the measuring procedure [51] Measurement using a bridge
The method is based on comparing the capacitance CX (transformer under test) with a well-known capacitance CN (standard capacitor).

Conventional Schering-Bridge
Figure shows the measuring circuit for the insulation power-factor measurement of a two-winding transformer using a conventional Schering-bridge.

Instrumentation
The Schering-Bridge test circuit consists of three main parts: The unknown capacitance CX, which represents the transformer under test whose power-factor (or tan) and capacitance are to be measured. The standard capacitor CN, which must be a HV capacitor with very low dielectric losses. Normally its capacitance is between 100 pF and 10 nF. The Schering-Bridge casing contains resistors R3, R4 and r, adjustable capacitor C4 and galvanometer G. In order to reduce the influence of external disturbances, coaxial cables must be used for the connection between CX (the transformer under test) to the bridge and also between standard capacitance CN and the bridge.
MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 19

Figure: Measuring circuit for the measurement of power factor and winding Capacitances. When the bridge is balanced, the unknown capacitance CX and tan can be calculated using the following equations:

In most bridges the following resistance values are used for R4, to simplify the calculation: 100/, 1000/ or 10000/ etc. in ohms. For a 50 Hz measurement, with R4 = 1000/ and C4 in nF, the insulation power factor tan will be:

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing

A modern tan bridge with current comparator and microprocessor


This bridge uses basically the same measuring principle as described above. Figure 18.1 b shows the measuring circuit for dissipation factor and capacitance measurement with a modern tan _ measuring bridge with incorporated microprocessor. The currents are balanced in a comparator (more-winding differential transformer) and quadrature current is injected to balance the losses. For the unknown capacitance Cx, the standard capacitor CN and the connections between transformer and bridge are the same as mentioned above for the conventional Schering Bridge.

20

MEASURING METHODS: CAPACITANCE AND TAN MEASUREMENT OF BUSHINGS


C & Tan measurement of bushings shall be done at 10kV with fully automatic test kit so as to have reliable test result. For 3-Ph auto-transformer, short together all 400kV, 220kV and Neutral (isolated from earth) Bushings. Also short all 33kV Bushings and earth the same. Measurement of C1 Capacitance and Tan: Connect the crocodile clip of the HV cable to the top terminal of the shorted HV/IV bushings. Unscrew the test tap cover, Insert a pin in the hole of the central test tap stud by pressing the surrounding contact plug in case of 245 kV OIP Bushing and remove the earthing strip from the flange by unscrewing the screw (holding earth strip to the flange body) in case of 420 kV OIP Bushing. Connect the LV cable to the test tap (strip/central stud) of the bushing under test to the C & TAN KIT through a screened cable and earth the flange body. Repeat the test for all Bushings by changing only LV lead connection of the kit to test tap of the Bushing which is to be tested. Measurement of C2 Capacitance and Tan : HV lead to be connected to the test tap of the bushing under test (if required additional crocodile type clip may be used) and LV of the kit to be connected to the ground. HV of the bushing is to be connected to the Guard terminal of the test kit. Test to be carried out in GSTg mode at 1.0kV. For measurement of 33kV Bushing Tan Delta, earth HV/IV Bushings (already shorted). Apply HV lead of the Test kit to shorted 33kV Bushings and connect LV lead of the test kit to Test tap of the Bushing under test. Measurements shall be made at similar conditions as that of a previous measurement. The oil-paper insulation combination of bushings exhibit fairly constant tan delta over a wide range of operating temperature. Hence, effort is to be made for testing at temperature near to previous test and Correction factor need not be applied. Do not test a bushing (new or spare) while it is in its wood shipping crate, or while it is lying on wood. Wood is not as good an insulator as porcelain and will cause the readings to be inaccurate. Keep the test results as a baseline record to compare with future tests.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing


It is to be ensured that C& Tan measurement of bushings and testing of turrets carried out before 21 installation. This will prevent installation of bushings having C& Tan values beyond permissible limits.

It is to be ensured that Test Tap points are earthed immediately after carrying out the measurements for that particular Bushing and earthing of test tap to be ensured by carrying out continuity test.

CAPACITANCE AND TAN MEASUREMENT OF WINDINGS


The combination for C & tan measurement of winding is same as that of measurement of IR value. The summery of probable combination is given below:

Auto-Transformer (Two Test Mode winding) HV + IV to LV HV + IV to E LV to E UST V GSTg GSTg

Shunt Reactor HV to E

Test

Mode GST

3 winding Test Transformer HV to LV1 HV to LV2 LV1 to LV2 UST UST UST

Mode

HV to Ground GSTg LV1 to Ground GSTg LV2 to Ground GSTg Table: Combination for C & tan measurement of winding for various Transformers/ Shunt Reactor.

Ensure that test specimen is isolated from other equipments. Removal of Jumpers from Bushings is PreRequisite for C & Tan Measurement of Windings.

For ICTs (Auto-Transformers): Shorting of all three phase Bushings (400kV&220kV) and neutral to be done. In case of single phase, 400kV, 220kV and neutral Bushings to be shorted Capacitance and Tan measurement of windings should be done in following combinations:

Test Test Winding Combination No. mode

Cap Symbol

Test lead Connection

Remarks

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing


1. HV-IV/LV UST CHL HV lead of test kit to HV/IV bushings of transformer LV lead of test kit to LV bushing of transformer

22

2. 3.

HV-IV/ LV+G HV-IV / LV with Guard

GST GSTg

CHL +CHG C HG

-do- doLV to be Guarded

HV-IV/LV

UST

CHL

LV lead of test kit to HV/IV bushings of transformer HV lead of test kit to LV bushing of transformer

LV/

HV-IV +G

GST

CHL +CLG LG

-doHV to be Guarded

6.

LV/ HV-IV with Guard

GSTg

C LG

-do-

Table :.Winding combination for C & tan measurement for auto transformer. Measurement inter-check can be done by calculating C1= C2-C3 & C4= C5- C6 & DF1=C2DF2-C3DF3 / C2-C3= C4DF4-C5DF5 / C4-C5 Where C stands for capacitance and DF for dissipation factor or tan and attached suffix (16) denotes the sr. no. of test in above table. For Reactors: All 400kV and neutral Bushings to be shorted. HV of the test kit to be connected to shorted Bushings and LV of the test kit to be connected to Earth connection. Measure the Capacitance and tan Delta in GST mode. Neutral connection with earth/ NGR to be isolated before the test.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 23

Testing of Power Transformers 6. Measurement Insulation Resistance.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing

Measurement of insulation resistance


Insulation resistance tests - Megger tests - are performed to determine the insulation resistance from individual windings to earth or between individual windings. Knowledge of the insulation resistance is of value when evaluating the condition of the transformer insulation. Insulation resistance is commonly measured in megohms, (M). It should be stated, that variations in insulation resistance can be caused by numerous factors including: design, temperature, dryness, and cleanliness of parts, especially of bushings. When insulation resistance falls below specified value, it can often be brought back to the required value by cleaning and drying. Insulation resistance varies with the applied voltage. Any measurement comparisons should always be carried out at the same voltage.

24

Figure: Principal measuring circuit for the insulation resistance measurement IEEE Std. C57.12.00 [50] also specifies the insulation resistance measurement between core and earth. It shall be measured after complete assembly of the transformer at a level of at least 0.5 Kv DC for a duration of 1 minute. The test is conducted with the help of mega-ohmmeter. IR is proportional to the leakage current through/over the insulation after capacitive charging and absorption currents become negligible on application of DC voltage. Insulation resistance shall be measured after the intervals of 15 sec, 60 sec and 600 sec. The polarization index (PI) is defined as the ratio of IR values measured at the intervals of 600 and 60 seconds respectively. Whereas, the dielectric absorption is the ratio of IR values measured after 60 sec and 15 sec. IR is normally measured at 5 kV DC or lower test voltage, but the test voltage should not exceed half the rated power-frequency test voltage of transformer windings. Polarization index (PI) is useful parameters for logistic interpretation of IR test results. This ratio is independent of temperature and gives more reliable data for large power transformers. A PI of more than 1.3 and dielectric absorption factor of more than 1.25 are considered satisfactory for a transformer when the results of other low voltage tests are found in order. PI of less than 1 calls for immediate corrective action. For bushings, an IR value of above 10000 M-ohms is considered satisfactory. The IR value of transformer is dependent on various factors such as configuration of winding insulation structures, transformer oil, atmosphere condition etc. therefore, present trend is to monitor oil characteristics
MTEKPRO Technologies Pvt. Ltd, New Delhi.

for judging the condition of dryness of the transformer and not to rely solely on absolute values of IR. It may be note that no national/international standards specify minimum insulation resistance values of 25 transformers. The value of IR may be very low under heavy fog or humid conditions. During IR measurement, we must ensure following conditions: Transformer is disconnected from other associated equipment Bushings are cleaned and free of moisture Transformer tank and core are properly grounded Both ends of winding under test are short-circuited.

Power Transformer Testing

Measuring Methods:IR measurements shall be taken between the windings collectively (i.e. with all the Windings being connected together) and the earthed tank (earth) and between each winding and the tank, the rest of the windings being earthed. Before taking measurements the neutral should be disconnected from earth. Following table gives combinations of IR measurements for auto-transformer, three -winding transformer & Shunt Reactor. For Auto-transformer For 3 winding transformer HV + IV to LV HV + LV to IV HV + IV +LV to E For Shunt Reactor HV to E

HV + IV to LV HV + IV to E LV to E

Where HV-High voltage, IV-Intermediate voltage, LV-Low voltage/Tertiary voltage windings, E- Earth Unless otherwise recommended by the manufacturer the following IR values as a thumb rule may be considered as the minimum satisfactory values at 30C (one minute measurements) at the time of commissioning.

Insulation resistance varies inversely with temperature and is generally corrected to a standard temperature (usually 20 C) using table (Source: BHEL instruction Manual) as given below.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 26

PI= R10 / R1 (dimensionless),


Where PI is Polarisation Index and R is resistance The following are guidelines for evaluating transformer insulation using polarization index values:

A PI of more than 1.25 and DAI of more than 1.3 are generally considered satisfactory for a transformer when the results of other low voltage tests are found in order. PI less than 1 calls for immediate corrective action. For bushings, an IR value of above 10,000 M is considered satisfactory.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing 27

Testing of Power Transformers 7. CHECK LIST FOR ENERGISATION OF TRANSFORMER.

MTEKPRO Technologies Pvt. Ltd, New Delhi.

Power Transformer Testing CHECK LIST FOR ENERGISATION OF TRANSFORMER/ REACTOR PRELIMINARY CHECKS
1. Release air at the high points, like oil communicating bushings, buchholz petcock, tank cover and the cooling devices including headers, radiators, pumps, expansion joints etc. of the transformer. Air release should be resorted from low points to high points. 2. Check the whole assembly for tightness and rectify where necessary. 3. Check the general appearance and retouch the paint work if need be. 4. Check that the valves are in the correct position: Tank: valves closed and blanked Cooling circuit: valves open Conservator connection: valves open By-pass: valves open or closed as the case may be. On-load tap changer: valves open 5. Check that the silica gel in the breather is blue and that there is oil in the breather cup (oil seal) 6. Check that CC-CL-G are shorted 7. Check the oil level in the main conservator and the conservator of on-load tap changer, bushing caps, flanges, turrets, expansion bellows as per manufacturers recommendation. Level should correspond to 35 C mark on oil level gauges for BHEL transformers 8. Check the bushings: Oil level (bushings fitted with sight-glasses) Adjustment of spark-gaps /arcing horn gaps, if provided Conformity of connection to the lines (no tensile stress on the terminal heads) Bushing CT secondary terminals must be shorted and earthed, if not in use. Neutral bushing effectively earthed 9. Check the on-load tap changer: Conformity of the positions between the tap changer control cubicle and the tap Changer head Adjustment of the tap-changer control cubicle coupling Electric and mechanical limit switches and protective relays Step by step operation- local and remote electrical operation as well as manual Operation and parallel operation, if any Signaling of positions 10. Check the quality of the oil: Draw off a sample from the bottom of the tank Carry out DGA and oil parameters test (i.e. BDV, Moisture content, resistivity & tan at 90C and IFT )
MTEKPRO Technologies Pvt. Ltd, New Delhi.

28

before energisation.

Power Transformer Testing 29

11. Check the oil of OLTC chamber, if not good, drain and fill with filtered oil upto desired level. 12 Check that equalising link between OLTC tank and Main tank is removed 13 Extraneous materials like tools, earthing rods, pieces of clothes, waste etc. should be removed before energisation.

CHECKING OF AUXILIARY AND PROTECTIVE CIRCUITS


1. Check temperature indicator readings and their calibrations 2. Check the setting and working of the mercury switches of winding and oil temperature indicators and presence of oil in the thermometer pockets Follow the same procedure for the thermal replicas 3. Check the direction of installation of buchholtz relay. 4. Check the operation of the buchholz relay and the surge protective relay of the tap-changer : Alarm and tripping Protections and signals interlocked with these relays 5. Check the insulation of the auxiliary circuits in relation to the ground by 2 kV megger for 1 min. 6. Check the earthing of the tank and auxiliaries like cooler banks at two places. 7. Measure the supply voltages of the auxiliary circuits 8. Check the cooling system : Check the direction of installation of oil pumps Check the direction of rotation of the pumps and fans Check the working of the oil flow indicators Check the setting of the thermal overload relays Go through the starting up sequences, control and adjust, if necessary, the relay time delays 9. Check that there is efficient protection on the electric circuit supplying the accessories and tightness of all electrical connections 10. Check the heating and lighting in the cubicles 11. Check the differential protection, over-current protection, restricted earth fault protection, over-fluxing protection etc. are in service and settings are as per CC/Engg recommendations. After the inspection / tests are completed, the transformer may be energised from the incoming side on NO LOAD. The initial magnetising current at the time of switching will be very high, depending upon the particular moment in the cycle. The transformer should always be soaked for few hours under constant care i.e. keep it energised for twelve hours. Excessive vibrations of radiator parts etc. should be located and corrected. The transformer hum should be observed for any abnormality. After that it may be checked for gas collection. Should the gas prove to be inflammable, try to detect the cause which may probably be an internal fault? If the breaker trips on
MTEKPRO Technologies Pvt. Ltd, New Delhi.

You might also like