You are on page 1of 2

mine of the month – Glensanda

The granite from the elevated quarry reaches the


stockpile via a 300 m shaft and 1.8 km conveyor

King of quarries
Little known to most in the UK, Scotland’s Glensanda quarry
is one of the largest and most productive in the world

L
ocated in a remote and inaccessible area Other crushed rock is distributed by Aggregate glensanda summary
of western Scotland lies Glensanda quarry, Industries from sites in Ireland and Scandinavia. Production
producing 7 Mt/y of granite, making it not Glensanda aggregate is used mainly for rail ballast Circa 7 Mt/y granite for rail ballast, concrete,
only Europe’s biggest single quarry, but and concreting aggregate (80%) due to its high roadstone markets, mainly in Europe
one of the largest in the world. Situated on hardness, with the remaining 20% largely for road
a 2,430 hectare site on the banks of Loch Linnhe, construction and maintenance. History
near Oban, Glensanda now has reserves in excess of Opened 1986 by Foster Yeoman Ltd
800 Mt of granite and ships material to meet the Production Planning permission granted 2002 until 2043
demands of not only the UK market, but also Europe Granite is mined on the plateau of Meall Mhuic Artair Expansion granted 2006
and further afield as far as the Americas. with conventional large-scale methods, including Foster bought by Aggregate Industries 2006
The quarry is a major employer in the region drilling and blasting, loading and haulage, and
with a workforce of up to 200. At the heart of the primary crushing operations, all performed above Equipment summary
operation are an innovative quarrying method and the 520 m level. The mining fleet mainly consists of Drilling: two DM45 Drillmaster (Atlas Copco)
dedicated ship logistics, which combine to minimise Caterpillar 777D haul trucks, loaded using Caterpillar rotary rigs; four ECM 350 (Atlas Copco)
environmental impact and provide a sustainable 992G wheel loaders. Drilling and blasting is development rigs
alternative to road supplies.
Surface mining
Glensanda is the only coastal superquarry in the
UK, with Lafarge’s Harris project finally consigned to At the heart of the Six Caterpillar 777D trucks, one Caterpillar D400
the history books when the company withdrew its
application in 2004. The quarry, formerly owned by
operation are an fuel bowser and one Caterpillar 14G grader;
loading with one Liebherr 984C excavator and
Foster Yeoman Ltd, is now part of Aggregate innovative quarrying two Caterpillar 992G wheel loaders
Industries Limited, a member of the Holcim Group,
following Foster’s acquisition in September 2006.
method and dedicated Crushing
Glensanda is connected to the sea by a 200 m- ship logistics Primary HD 54-80 Nordberg (Metso) gyratory
deep channel and provides a 24-hour sheltered crusher; secondary Metso Minerals HP800 cone
berth for vessels with a draught of up to -12.3 m CD. crusher; tertiary Svedala (Sandvik) H4000, H6000
The granite is exported using bulk vessels called conducted via two Atlas Copco DM45 Drillmaster and H8000 cone crushers
Yeoman Brook, Yeoman Bank, Yeoman Bridge and large, rotary-drilling rigs for the main bench work.
Yeoman Bontrop. At the time of its completion in A fleet of four Atlas Copco ECM 350 rigs is used for Screening
2000, the Yeoman Bridge was the world’s largest development work, such as constructing access Siebtechnik – two double-deck scalping screens;
self-discharging aggregate carrier, with a capacity ramps and opening up new levels. One of the DM45s one double-deck final screen; one single-deck
of 97,000 t. was acquired in 2005 while the other has worked final screen; one single-deck selector screen;
As well as serving the company’s own quarry in continuously in the quarry for the past 15 years. one double-deck washing and final screen;
Scotland, the vessels regularly ship gypsum rock The local Atlas Copco drilling distributor, H&F one single-deck dewatering screen. Two Don
from the south of Spain to the UK, allowing the Drilling Supplies, delivers all the necessary drill Valley triple-deck final screens
development of a back-haul trade in aggregate. Continued on page 19

April 2007 Mining Magazine 17

17,19MM0704.indd 17 26/3/07 13:03:26


mine of the month – Glensanda

The Yeoman Bridge bulk carrier

Continued from page 17


consumables. In the past, both 5 in (127 mm) and 6 in
(152 mm) Secoroc DTH hammers, with 5.5 in and
6.5 in ballistic button bits, were used.
The size of the blasts can vary from about 20,000 t
for a smaller development blast to 250,000 t for a
main bench-production single blast. Usually, there
are two to three blasts per week. The drill pattern
using DM45s is 4.75 by 6.0 m (burden and spacing), Two Caterpillar 992G wheel loaders
while the corresponding figure for the ECM rigs form the main loading fleet
is 3.5 by 5 m.
Granite is loaded into a large, primary crusher
that feeds a 300 m-deep, 4 m-diameter, vertical extracted. The tunnel is a permanent installation for the 520 m level, but some of the workings are now
shaft, known as the ‘Glory Hole’. This enables the the life of the project. at 440 m, meaning all production has to be hauled
transportation of crushed rock from the plateau at The stone is taken through secondary and tertiary uphill. Some workings are higher, with a major
over 500 m high down to sea level. crushing, as well as screening into sizes demanded face-development advance planned for the 520 m
The glory hole is met by a 1.8 km horizontal, by the market. Reclaim, blending and shiploading and 540 m levels.
tunnel conveyor that carries the crushed rock to a facilities are rated at 6,000 t/h throughout, which The extension expands the permitted mining area
500,000 t stockpile. The material is then transferred to means a typical 75,000 t cargo can be loaded at the by 81 hectares to a total of 206 hectares in an easterly
the secondary and tertiary crushing and screening harbour in under 24 hours. and then south-westerly direction of development.
operations, and from there to massive storage bins This has increased reserves figure from 400 Mt to
where the current foreshore storage facility has Expansion more than 800 Mt.
another 430,000 t. In 2002, the quarry was granted planning approval The company points to the future projected
The glory hole provides long-term solutions to until January 2043 for the current working site. The production decline of the major hard-rock quarries
the economic and environmental extraction of this output is currently around 7 Mt/y, with consent to in England over the long term, such as Cliffe Hill
deposit. The quarry represents a crater, with only produce up to 15 Mt/y. Planning permission was (Tarmac and Midland Quarry Products) and
the uppermost benches visible from a distance. granted in 2006 for the extension of the extraction Mountsorrel (Lafarge Aggregates) in Leicestershire.
The primary crushing station levels and glory hole area itself at Glensanda, mainly to address the At present extraction rates, reserves at Glensanda
collar are progressively lowered as the deposit is current working situation. The primary crusher is at will last 50 years, but at the expanded production
rates expected to be required to meet future
demand, this would have declined if the additional
Two Atlas Copco DM45 Drillmasters are reserves had not been added.
used for the main bench production
Reclamation and restoration
Given the location of the quarry, environmental
aspects, such as the visibility of the pit, as well
as dust, noise and vibration, and the effect on
protected wildlife are all closely monitored. The
quarry management is currently working towards
producing a biodiversity plan for the long-term
future of the area.
The visual impact of the primary crusher building,
glory hole cover and interconnecting conveyor has
been mitigated by the placement alongside of a
bund with an irregular top edge. The exposed rock
side is expected to be seeded on the western side.
With the expansion plans, a number of viewpoints
have been assessed for visual impact, with terrain
modelling used to address the extent of faces –
restored or unrestored – that will be visible. All
visible faces will be restored by covering with peat
and seeding.

April 2007 Mining Magazine 19

17,19MM0704.indd 19 26/3/07 13:03:33

You might also like