Mechanical System / Activity HVAC services CHW flushing CHW pumps CHW balancing Fan Coil Units ( BOH ) Fan Coil Units ( FOH )
Complete T&C
Midmac Remarks
Tanween Comments
AEB Comments
Accepted; this to be done for the entire system ( FOH & BOH) Accepted Accepted; this to be done for the entire system ( FOH & BOH) Accepted Noted; The Run test Shall include the verification of actual Air volume flow rate using Balometer instrument; and the Unit ESP. Run test to prove satisfactory of control system including thermostats. Unit performance Test shall be included to verify the cooling.
Accepted Run test shall include: Proving of air flow at simulated design conditions. I.e. at created design ESP and current drawn to prove air volume flow rate delivered by the equipment. Proving unit cooling capacities, i.e. by measuring inlet and outlet enthalpies. Proving of satisfactory operation of control systems including operation of thermostats and cooling control valves. Run test shall include, Proving of air flow at simulated design conditions i.e. at created design ESP and current drawn to prove air volume flow rate delivered by the equipment. Proving unit cooling capacities, i.e. by measuring inlet and outlet enthalpies.
Noted; The Run test Shall include the verification of actual Air volume flow rate using pitot tube instrument and ESP of the Unit. Run test to prove satisfactory of control system including thermostats
Proving of VFD drive effectiveness when VAVs are tuned down. Proving of satisfactory operation of control systems including operation of cooling control valves, damper actuators, VFDs air heaters where applicable and Energy Recovery Units (ERUs). Run tests shall include, Proving of maximum and minimum air flow. Proving of satisfactory operation of control systems.
VFD drive effectiveness cannot be verified on VAVs when tuned down, as the VAV are bypass type. Noted; The Run test of the Unit can be checked and verify the functionality, including control. The unit desired airflow will be adjusted during air testing and balancing works. (TAB). ( when grilles and diffuser are installed by ID fit-out contractor ) Noted; Unit can be checked and verify the functionality, including control. Shall include the verification and proving the actual duct Air volume flow rate using Pitot tube instrument and ESP of the Unit. Proving of satisfactory operation of control systems
Ecology Units
Run tests shall include, Proving of air flow at simulated design conditions, i.e. at created design ESP and current drawn to prove air volume flow rate delivered by the equipment. Proving of satisfactory operation of control systems.
Accepted
Noted; For Kitchen Exhaust Fans Run test: Shall include the verification and proving the actual duct Air volume flow rate using Pitot tube
instrument and ESP of the Unit. Proving of satisfactory operation of control systems
Accepted
Noted; For Laundry Exhaust Fans Run test: Shall include the verification and proving the actual duct Air volume flow rate using pitot tube instrument and ESP of the Unit Proving of satisfactory operation of control systems
Accepted Accepted Run tests shall include, Proving of air flow at simulated design conditions, i.e. at created design ESP and current drawn to prove air volume flow rate delivered by the equipment. Proving of satisfactory operation of control systems.
Accepted Accepted; This is also applicable for other in-line type exhaust fans. Noted ; For Staircase pressurization system shall be a complete T & C. - Noted ; For Lift Lobby and Lift shaft pressurization system- Proving of satisfactory operation of control systems i.e. ( motorized damper and motorized window operation during fire mode ) - Verification of actual Air volume flow rate using pitot tube instrument and ESP of the Unit. Proving of satisfactory
Can be done only for the systems under Midmac scope of works Water mixers and taps not in Midmac scope of works
Accepted Accepted
Accepted
Plumbing Services Booster Sets Run tests shall include, Demonstration of all operational functions of the equipment. Proving equipments capability to perform at design capacity. Accepted Water mixers and taps not in Midmac scope of works Water mixers and taps not in Midmac scope of works Run test shall include, Demonstration of all operational functions of the equipment. Proving equipments capability to perform at design capacity. Run tests shall include, Demonstration of all operational functions of the equipment. Proving equipments capability to perform at design capacity. Accepted Water mixers and taps not in Midmac Run tests shall include, Demonstration of all operational functions of the equipment. Noted
Noted
Accepted
Noted
Accepted - this shall include complete T & C of the domestic water chiller. Noted
scope of works Swimming Pool Flushing for the pipe works Will be done from the water outlets in the FOH Will be done while flushing the domestic water lines
Proving equipments capability to perform at design capacity. Accepted Accepted Accepted this shall include the domestic water pipe works chlorination. Accepted
Fire Fighting Services Accepted this shall include the Fire hose cabinets, Landing valves, alarm check valves, zone control valves and gongs.
Accepted
Specialties Boiler System X X Laundry equipment not in Midmac scope of works Accepted Noted; The Boiler system to be verified as complete system/installation, controls, fuel system including hydrostatic testing of steam piping networks. And since the Boiler system is correlated to LPG system and K & L equipment; It is therefore recommended that the final T & C of the Boiler system will be done after the ID/K & L works is completed. Noted; The LPG system to be verified as a complete
LPG System
Accepted
system/installation , controls, gas detection system including leak testing of gas piping networks using nitrogen gas. And the installation of the system was approved and certified by Woqood for operations. Functionality test for LPG gas detection sensor using gas in canister. Functionality test for LPG main control panel / main solenoid control valves during fire alarm mode.
Similarly the LPG system is correlated to Boiler system and K & L equipment; It is therefore recommended that the final T & C of the LPG system will be done after the ID/K & L works is completed. Kindly note that the client is required to apply for LPG supply contract to Woqood for requirement of T & C and Hotel operations.
Other System: 1.Linen Chute 2. FM 200 3.Motorized Complete T & C for this system. ( item 1,2 & 3)