You are on page 1of 2

INSPECTION AND TESTING PLAN (ITP)

Doc. No.: QF-QC-17 Issue Date: 18/01/10 Rev: 1 Page: 1 of 2

Job # / Project name: _____________________________ Job Site Location: _______________________________ Customer: ______________________________________ Reference specifications: MBMA ------------Metal Building Manufacturers Association IBC ---------------- International Building Code AWS D 1.1 ------- American Welding Society SSPC -------------- Steel Structures Painting Council ASTM--------------American Society for Testing and Materials AISC----------------American Institute of Steel Construction

Sr #

Stage of Production Material Selection and Verification: Plates, Sheets, hot and cold rolled shapes, tubular, fasteners, etc. Welding: WPS /PQR, WPQR

Applicable Specification / Procedures 1. ASTM standards or equiv. 2. AISC Codes & Standards 3. AWS D1.1 (2006) AWS D1.1 (2006) 1. Shop Drawings 2. MBMA 3. Standard Fab. tolerances 1.Shop Drawings 2.AWS D1.1 (2006) 3.MBMA 4.Standard Fab Tolerances. Web Flange fillet weld shall be single side welding (unless noted otherwise)

Activity Extent of Inspection Record / Forms # PEB 1. Dimensional 5% 2. Review of MTRs -100% 3. Visual 30% Review & Verification 100% 1. Visual 25% 2. Dimensional 25% CUST.

1.

1. PO 2. QF QC 01 & 02

I/R/H

DR

2.

3.

Preparation Stage

Approved WPS/PQR, WPQR 1. Shop Drawings 2. QF QC 08

DR

W/I

DR

4.

Fabrication: Built up, Cold Formed & Roll Formed.

1. Visual 25% 2. Dimensional 25%

1. Shop Drawings 2. QF QC 07, 08 & 09

W/I

DR

INSPECTION AND TESTING PLAN (ITP)

Doc. No.: QF-QC-17 Issue Date: 18/01/10 Rev: 1 Page: 2 of 2

Sr #

Stage of Production

Applicable Specification / Procedures 1. AWS D1.1 (2006) 2. Standard Weld Map (Unless Note Otherwise) 1. AWS D1.1 (2006)

Activity Extent of Inspection Record / Forms # PEB CUST.

5.

In Process Welding

1. Visual 100% 2. Dimensional 25%

1. QF QC-14

W/I/H

RI

6.

NDT other than visual: UT for

1. UT 10%

10mm butt joint


7. Surface Preparation & Painting 1. PIF 2. SSPC 1. Visual 100% 2. DFT Gauging 10%

1. QF-QC-05 & 18 2. NDT report 1. QF-QC-06 2. QF-QC-12

W/H/R

DR

W/I

DR

8.

Final Inspection 1. Preparation for Shipment 2. Documentation

1. Shop Drawing

1. Visual 30% 1. Visual 20% 2. Review of documents 20%

1. QF-QC-13

W/I/H

RI

9.

Procedure QPRCSD-03

1. Shipping List

W/RI/SD

DR

Legend: R = Review W = Witness H = Hold Point I = Inspection MTR = Manufacturers Test Report P.O = Purchase Order DR = Document Review RI = Random Inspection S = Submit Document

You might also like