owner architect
adjustment to service agreement

September 12, 2012 Client: Project: DSA Application: DSA File: Client Number: dsk Number: Regards: For: Attention: Emery Unified School District (EUSD) Emery Center of Community Life (ECCL) To be determined To be determined 09-001 09003.01 Adjustment to: Architectural Services Agreement Approved 120416 Feasibility Study and related services Roy Miller, District Architect

The following service tasks are considered to be an Additional Service under the terms of our Owner-Architect Agreement approved by the EUSD board on March 16, 2012. dsk aka Nexus Partners was directed to stop work on June 6, 2012. On July 30, 2012, we were subsequently directed to proceed with a Feasibility Study to be completed by approximately September 7, 2012. The Study is to address a EUSD program within a construction cost budget of approximately thirty two million dollars ($32,000,000) and a City of Emeryville program within a construction cost budget of approximately sixteen million dollars ($16,000,000). The Study is to also include a schedule that identifies occupancy of the site in the summer of 2012. The study shall also include a recommendation and potential identifiable risks. The Feasibility Study includes the following tasks as additional services: 1) Attend weekly Working Group meetings. 2) Prepare a site study in sketch-up to indicate the exhibit C 120323 Program List of Spaces on the existing Emery Secondary School Site with a maximum utilization of the existing approximately 76,000 square foot main building. The plan shall represent the project proceeding both with and without the Phase Two City program. 3) Prepare a cost model in excel working in conjunction with Turner Construction. 4) Provide a recommendation. In addition to the efforts of dsk, the following consultants from the Basic Service Contract may be included in this agreement: MKThink Concordia LLC Saylor associates Architects Architects Cost Estimating

As such, we will require additional compensation in accordance with the Owner-Architect Agreement, and will submit invoices for payment for this Additional Service. This Additional Service will be performed on a: Lump sum fee basis including reimbursable expenses.

dsk architects design studio of seiberlich and kakavand 926 natoma street suite 200 san francisco ca 94103 page 1 of 2 phone: 415-839-6418 fax: 415-839-7584 design@dskarch.com www.dskarch.com

dsk
architects

owner architect
adjustment to service agreement

The terms and conditions of the Owner-Architect Agreement apply to this Additional Service Agreement. FEE OF THE ADDITIONAL SERVICE:

TOTAL LUMP SUM FEE

$137,495

Please sign and return one original of this Agreement as your acceptance of the Additional Services and your approval of the cost. Receipt of this signed original shall be confirmation of our authorization to proceed/continue with the service. _______________________________ Mark Seiberlich, dsk architects Partner Enc; C;

Roy Miller District Architect

P:\ECCL\09003\A.0-admin\A.03-clientagree\2-addservices\as01\as01 eccl 120828.doc