(To be read in conjunction with letter dated 17th December 2012 bearing reference AHEL/TRICHY /WO/ Flooring Trichy

y /104)

To,M/s.Apollo Hospitals Enterprises Ltd, Ali Towrs, Greams Road,Chennai 60006. Dear Sir , Sub: Quotation for Marble laying

9/2/2013

With reference to the above subject, please find our lowest Offer. Sl. No DESCRIPTION Qty UNIT BoQ - Nellore Rate Amount

Marble / Granite Slabs Flooring & Dadoing :Laying of Marble / granite slabs of any size & thickness supplied by client 49500 as per approved pattern laid over a base of cement mortor as detailed below. Base Preparation & Base Cement Mortor :Top of the slab which receives the flooring shall be throughly cleaned with air blowers and saturated with water. Cement slurry @ 3.30 Kgs / Sqm shall be sprayed over the water saturated surface. Base cement mortor of ratio 1:5 (One part of grey cement: five parts of river sand) of minimum 20mm thick shall be laid over the cement slurry. Pointing :All the joints shall be pointed with the matching cement based polymer of makes as stated in this order. Rate to Include:Quote rate to include all charges towards receiving, shifting, handling, cutting, leads, lifts, wastages, transportations, laying and polishing of laid marble slabs, all labour charges, tools & tackles, working at any floors, cement, sand, pointing compound, etc., complete.

Sq.ft

120.00

5940000

All works to be executed as per drawings and as instructed by Architect / Engineer In Charge.

Marble Skirting (100mm High) :5000 Laying of granite tiles / slabs supplied by client with base grey cement mortor of 12 -15mm thick 1:5 (One part of grey cement: five parts of river sand) , over a coat of cement slurry laid at 3.30Kgs/sqm, pointing with matching approved grouting compounds, finishing with acid washing, etc., complete. Rate to include preperation of surface including chipping of existing surfaces (brick / rcc) so that the finished skirting surface to be flush with the existing plastered surface, all wastages, lead, lift, loading, unloading, transpotation, wastages, labour charges, comsumables, tools & tackles, working at any floors, etc., complete. All works to be executed as per drawings and as instructed by Architect / Engineer In Charge. Rft 120.00 600000

Page 1 of 3

(To be read in conjunction with letter dated 17th December 2012 bearing reference AHEL/TRICHY /WO/ Flooring Trichy /104)

Sl. No

DESCRIPTION

Qty

UNIT

BoQ - Nellore Rate Amount

Corner Beads :Providing and fixing in position PVC corner beads of approved make and colour matching to the colour of the tiles. Rate to include all wastages, lead, lift, loading, unloading, transpotation, wastages, labour charges, comsumables, tools & tackles, working at any floors, etc., complete. All works to be executed as per drawings and as instructed by Architect / Engineer In Charge. 1250 Rft 50.00 62500

POP Covering:Providing and laying polythene sheets of minimum 400 micron thick over finished floors to protect the floors from damaging, tampering, etc., including lappping of joints. Rate to include providing and laying 1 minimum /2" thick POP layer over and above the polythene sheet and remove the same as and when instructed by Architect / Engineering In Charge. Rate to include all wastages, lead, lift, loading, unloading, transpotation, wastages, labour charges, comsumables, tools & tackles, working at any floors, etc., complete. All works to be executed as instructed by Architect / Engineer In Charge.

Qro

Sq.ft

12.00

*****

Skirting Finishing:Chipping and redoing the plaster for fixing of skirting tiles and above skirting with CM 1:5 with necessary groove. Rate to include preperation of surface including chipping of existing plastering surfaces so that the finished skirting surface to be flush with the existing plastered surface, finishing the excess chipped plaster surface above the skirting with cement mortor 1:5, forming a groove between the skirting and finished plaster surface, etc., complete. Rate to include all wastages, lead, lift, loading, unloading, transpotation, wastages, labour charges, comsumables, tools & tackles, working at any floors, etc., complete. All works to be executed as instructed by Architect / Engineer In Charge.

5000

Rft

15.00

75000

GRAND TOTAL =

Rs.

6,677,500

Make: Cement - As approved Sand - Locally available good quality river sand Pointing Compound - CREA / ROFF / BAL PVC corner beads / trims - Dural Permissible Wastages: Maximum of 10% (Ten Percentage Only) of theoretical consumption of slabs / tiles Penalty for excess consumption : Excess consumed quantity will be recovered at 2 times of market price of tile.

Page 2 of 3

(To be read in conjunction with letter dated 17th December 2012 bearing reference AHEL/TRICHY /WO/ Flooring Trichy /104)

Sl. No

DESCRIPTION

Qty

UNIT

BoQ - Nellore Rate Amount