You are on page 1of 26

Example Location : Egypt

Project :

May 30, 2009 Designed by : Zanitty


Date :

Assumed Data Calculated data


No. of Rooms No. of persons per room Building Lowest level (m) Building Highest level (m) Total No. of persons = = = = =

* You are allowed to change * You are NOT ALLOWED to change

328 2 0 20 656

Project Location

: :

Example Egypt

Date Designed by

Assumed Data Calculated data


Table of total fixtures Fixture type : private
FIXTURES / POINT NO. Water closet (flush valve) Water closet (flush tank) Water Bidet Hose for W.C Lavatory (& H.B.) Janitor Sink Service sink Shower Bath tub Kitchen sink Dishwashing machine Laundry Ablution (Public) Urinal (1" flush valve) Urinal (3/4" flush valve) Urinal (flush tank) B3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 B2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 B1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 G.F. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 F.F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

: :

May 30, 2009 Zanitty

* You are allowed to change * You are NOT ALLOWED to change

2nd.F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3rd F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4th F. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

7th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

8th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

9th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

10th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

11th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

12th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

13th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

14th F 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Total fixtures
15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data Calculated data Given Data:


Number of persons Water Supply Demand: Water Consumption(L/person/day) Water demand per day(m3/ day) Main Water Feeder : Flow rate required ; Q(m3/ sec) Under Ground Water Tank : Duration Assumption (day) Storage Fire Fighting Demand (m3) = 2 = 150 = 0.003 = 400 = 263 = 656 Design Basis of Water Supply System

* You are allowed to change * You are NOT ALLOWED to change

Storage water supply Demand (m3) Total Storage Demand (m3)


Tank depth (m) Tank Length (m) Tank Width (m)

= 658 = 808
= 3 = 10 = 27 * Could be changed according to Arch. Requirement * Could be changed according to Arch. Requirement

Actual Area of Tank (m2) Tank depth (m) Tank Length (m) Tank Width (m)
Upper Roof Water Tank : Duration Assumption (day)

= = = =

269 3 10 27

= 0.5

Tank Storage Required (m3)

= 132

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data Calculated data


Q (m3/day) Pump working hours Then = 263 = 12

* You are allowed to change * You are NOT ALLOWED to change

Lifting Pump Calculations Pump Discharge Q (GPM) Pump Head Static Head Hs (m) Losses Pump Head (m) = 22 = 1.93 = 27 = 97

Time Required to Fill Upper Roof Tank T (Hr) Power Pump Efficiency Power (Hp) = 0.8 = 3 = 0.38

Booster Pump Calculations Pump Discharge Q (L/s) Pump Head (m) Power Pump Efficiency Power (Hp) = 0.8 = 4 = 10 = 22

Project Location

: :

Example Egypt

Date : Designed by :

May 30, 2009 Zanitty


* You are allowed to change * You are NOT ALLOWED to change
For DOMESTIC WATER BOOSTER Accumulative Pressure m 10 10.07 10.34 10.37 10.54 10.57 41.93 41.93 Local factors of fittings Total head (DH+GH) / pipe m 10 0.07 0.27 0.03 0.17 0.02 31.4 RE Reynolds number

Assumed Data Calculated data


Head loss calculation using (1) ID Pipe Inner diameter COLBROOK Formula

DN Nominal diameter

Loss m per 100 m

K Pipe roughness

Total local factors

V Mean Velocity

F Liner loss factor

1.0 discharge outlet

1.0 Multimedia filter

0.3 elbow ( 45 leg.)

0.3 elbow ( 90 leg.)

dh(2) Local loss m 7E-04 0

dh(1) Liner loss

no. part of pipe

GH Static head

2.0 check valve

1.0 Foot valve

0.2 gate valve

no. PUMP TO A A TO B B TO C C TO D D TO E E TO F F TO G 300 300 350 250 200 150 63

DN PVC PVC PVC PVC PVC PVC PVC

mm 267 267 302 213 170 136 53.6

m 10 83 879 195 322 47 32

mm 0.01 0.01 0.01 0.01 0.01 0.01 0.01

GPM 40 400 350 100 100 50 50

l/s 2.52 25.2 22.1 6.3 6.3 3.15 3.15

2.0 Strainer

0.5 reducer

0.9 tee

1/1 6.9 0.9 2.9 1.1

m 10 0 0 0 0 0 30

m/s

1/1

1/1 0.0295

m 0 0.07 0.03 0.02 0.05 0.04 3.69

m 0

1 1 8 2 3 2 1 1 1 1 1 1

0.04487 11999.116

0.44873 119991.16 0.01754 0.30701 92840.383 0.01844 0.17714 37694.592 0.02241 0.27691 47129.313 0.02137 0.21621 29447.17 0.02377 1.39602 74826.578 0.01993

0.06 0.009 0.07 0.26 0.014 0.27 0.03 0.002 0.03 0.16 0.013 0.17 0.02 0.003 0.02 1.18 0.179 1.36

1 1

3.4 1.1 1.8

TOTAL

1,568

1 16 1

18.1

40

2.86688 413928.31 0.15297

3.9

Static head Outlet pressure 35 PSI total friction loss total dynamic head Add 10 % safety

= = = = 0.00 =

40.00 m 5.00 m 1.93 m 46.93 m 51.62 m

DH Total loss m 0 2

L Pipe length

Q Flow rate

Head Loss Calculations:


The total friction loss Hs Consist of: Hs Where: = Hs1 + Hs2 Hs1 Hs2 . (1) : Friction loss Inside pipes : Friction loss inside fittings

Linear friction loss equation: Hs = J . L ... .... (2)

J = l . V / ( 2 g D ) .... (3) Where: J L l V g D : linear loss factor : length Of the pipe (m.) : friction loss factor (COLBROOK-WHITE formula) : velocity of water (m/s) : gravity acceleration (9.81 m/s) : pipe inside diameter (m.)

COLBROOK WHITE formula:.. ( 4 )

1 sqr(l)

= - 2 x log [

k 3.7 x D

2.51 Re x sqr( l )

Where:

K D RE

: pipe inside Surface roughness (m.) : pipe inside diameter (m.) : REYNOLDS no. is given as follows: (1/1)

RE = V x D / n . ( 5 ) Where: n V D : water viscosity= ( n = : velocity of water (m/s) : pipe inside diameter (m.) 1E-06 m2/s)

V = Q/A Where:

.... ( 6 ) Q A : flow rate (m/s) : cross section are of the pipe (m)

Data for the First pipe :

300 PVC 315 mm 23.8 mm D = K = 0.2674 m 0.00001 m

Pipe type & size 300 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.)

Flow :

Q = 400.0 GPM = 25.2 l/s = 0.0252 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

m/sec

3.14 x 0.267 / 4 = 0.05616 m

0.449 m/s 0.449 x 0.2674 / 0.000001 = 119991.16 0.00001 3.7 x 0.267 2.51 119991.2 x sqr( l )

1 sqr(l)

= - 2 log [

By solving above equation : l= 0.01754 0.01754 x 0.4487 x 0.449 2 x 9.81 x 0.2674 0.00067 x 100 m = 0.067

J = l . V / ( 2 g D ) =

= 0.00067 m/m

Loss m per 100 m = J x 100 = Pipe length L = 10.0 m

m / 100m

dh(1) Liner loss = J x L = 0.00067 x 10.0 = 0.007 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) .... (7) G V SUM ZE : Gravity acceleration (9.81 m/s) : Velocity of water (m/s) : Sum of local loss factors 3 1 1 1 1 0 0 0 1 x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 = = = = = = = = = 0.6 1 1 2 0.3 0 0 0 2

Where:

SUM ZE =

gate valve Multimedia filter Foot valve check valve elbow ( 45 leg.) elbow ( 90 leg.) tee reducer Strainer

discharge outlet Total local factors HS2 = SUM ZE . V / ( 2 . g )

1 = =

0 6.90

HS(2) = SUM ZE.x V / ( 2 g ) =

6.9 x

0.4487 X 0.4487 2 x 9.81

= 0.0708 m

DH Total loss = HS1 + HS2 = 0.007 + 0.071 = 0.078 m Total head (DH+GH) / pipe = Static head + Friction losses . ( 8 ) = 10.0 + 0.078 = 10.078 m

Data for the Second pipe :

300

PVC 315 mm 23.8 mm

Pipe type & size =f_loss!B11 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.) m/sec

D = K = Flow :

0.2674 m 0.00001 m

Q = 400.0 GPM = 25.2 l/s = 0.0252 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

3.14 x 0.267 / 4 = 0.05616 m

0.177 m/s .177 x 0.2674 / 0.000001 = 37694.59 0.00001 3.7 x 0.267 l= 2.51 37694.6 x sqr( l )

1 sqr(l)

= - 2 log [

By solving above equation : J = l . V / ( 2 g D ) =

0.02241

0.02241 x 0.1771 x 0.177 2 x 9.81 x 0.2674 0.00017 x 100 m = 0.017

= 0.00017 m/m

Loss m per 100 m = J x 100 = Pipe length L = 83.0 m

m / 100m

dh(1) Liner loss = J x L = 0.00067 x 83.0 = 0.056 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) gate valve Multimedia filter Foot valve check valve elbow ( 45 leg.) elbow ( 90 leg.) tee reducer Strainer discharge outlet Total local factors SUM ZE . V / ( 2 . g ) 0.1771 X 0.1771 2 x 9.81 0 0 0 0 0 0 1 0 0 0 x x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 1 = = = = = = = = = = = 0 0 0 0 0 0 0.9 0 0 0 0.90

SUM ZE =

HS2

HS(2) = SUM ZE.x V / ( 2 g ) =

0.9 x

= 0.0018 m

DH Total loss = HS1 + HS2 = 0.056 + 0.009 = 0.065 m Total head (DH+GH) / pipe = Static head + Friction losses = 0.0 + 0.035 = 0.035 m

Data for the Third pipe :

350

PVC 355 mm 26.3 mm

Pipe type & size Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.) m/sec

D = K = Flow :

0.3024 m 0.00001 m

Q = 350.0 GPM = 22.05 l/s = 0.02205 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

3.14 x 0.302 / 4 = 0.07182 m

0.307 m/s .307 x 0.3024 / 0.3 = 92840.38 0.00001 3.7 x 0.302 l= + 0.01844 = 0.0 m/m m / 100m 2.51 47129.3 x sqr( l ) ]

1 sqr(l)

= - 2 log [

By solving above equation : J = l . V / ( 2 g D ) = Loss m per 100 m = J x 100 = Pipe length L = 879.0 m

0.01844 x 0.307 x 0.307 2 x 9.81 x 0.3024 0.00029 x 100 m = 0.029

dh(1) Liner loss = J x L = 0.00029 x 879.0 = 0.257 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) gate valve Multimedia filter Foot valve check valve elbow ( 45 leg.) elbow ( 90 leg.) tee reducer Strainer discharge outlet 0 SUM ZE . V / ( 2 . g ) 2.9 x 0.307 X 0.307 2 x 9.81 = 0.0 m 0 0 0 0 0 8 0 1 0 0 x x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 1 = = = = = = = = = = = 0 0 0 0 0 2.4 0 0.5 0 0 2.90

SUM ZE =

HS2

HS(2) = SUM ZE.x V / ( 2 g ) =

= HS1 + HS2 = 0.257 + 0.014 = 0.271 m = Static head + Friction losses = 0.0 + 0.271 = 0.271 m

Data for the Fourth pipe :

250

PVC 250 mm 18.6 mm

Pipe type & size 250 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.)

D = K =

0.2128 m 0.00001 m

Flow :

Q = 100.0 GPM = 06.3 l/s = 0.0063 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

m/sec

3.14 x 0.213 / 4 = 0.03556 m

0.177 m/s .177 x 0.2128 / 0.00001 3.7 x 0.213 = 92840.38 2.51 0.0 x sqr( l )

1 sqr(l)

= - 2 log [

By solving above equation : l= 0.02241 0.02241 x 0.1771 x 0.177 2 x 9.81 x 0.2128 0.00017 x 100 m = 0.017

J = l . V / ( 2 g D ) =

= 0.0 m/m

Loss m per 100 m = J x 100 = Pipe length L = 195.0 m

m / 100m

dh(1) Liner loss = J x L = 0.00017 x 195.0 = 0.033 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) .... (7) G V SUM ZE : Gravity acceleration (9.81 m/s) : Velocity of water (m/s) : Sum of local loss factors 0 0 0 0 0 2 0 1 0 x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 = = = = = = = = = 0 0 0 0 0 0.6 0 0.5 0

Where:

SUM ZE =

gate valve Multimedia filter Foot valve check valve elbow ( 45 leg.) elbow ( 90 leg.) tee reducer Strainer

discharge outlet Total local factors HS2 = SUM ZE . V / ( 2 . g )

1 = =

0 1.10

HS(2) = SUM ZE.x V / ( 2 g ) =

1.1 x

0.1771 X 0.1771 2 x 9.81

= 0.0018 m

= HS1 + HS2 = 0.033 + 0.002 = 0.035 m = Static head + Friction losses . ( 8 ) = 0.0 + 0.035 = 0.035 m

Data for the Fifth pipe :

200

PVC 200 mm 14.9 mm

Pipe type & size 200 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.)

D = K =

0.1702 m 0.00001 m

Flow :

Q = 100.0 GPM = 06.3 l/s = 0.0063 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

m/sec

3.14 x 0.17 / 4 = 0.02275 m

0.277 m/s 0.277 x 0.1702 / 0.00001 3.7 x 0.17 = 47129.31 2.51 47129.3 x sqr( l )

1 sqr(l)

= - 2 log [

By solving above equation : l= 0.02137 0.02137 x 0.2769 x 0.277 2 x 9.81 x 0.1702 0.00049 x 100 m = 0.049

J = l . V / ( 2 g D ) =

= 0.00049 m/m

Loss m per 100 m = J x 100 = Pipe length L = 322.0 m

m / 100m

dh(1) Liner loss = J x L = 0.00049 x 322.0 = 0.158 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) .... (7) G V SUM ZE : Gravity acceleration (9.81 m/s) : Velocity of water (m/s) : Sum of local loss factors 0 0 0 0 0 3 0 1 1 x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 = = = = = = = = = 0 0 0 0 0 0.9 0 0.5 2

Where:

SUM ZE =

gate valve Multimedia filter Foot valve check valve elbow ( 45 leg.) elbow ( 90 leg.) tee reducer Strainer

discharge outlet Total local factors HS2 = SUM ZE . V / ( 2 . g )

1 = =

0 3.40

HS(2) = SUM ZE.x V / ( 2 g ) =

3.4 x

0.2769 X 0.2769 2 x 9.81

= 0.0133 m

= HS1 + HS2 = 0.158 + 0.013 = 0.171 m = Static head + Friction losses . ( 8 ) = 0.0 + 0.171 = 0.171 m

Data for the Sexth pipe :

150

PVC 160 mm 11.9 mm

Pipe type & size 150 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.) m/sec

D = K =

0.1362 m 0.00001 m

Flow :

Q = 50.0 GPM = 03.15 l/s = 0.00315 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

3.14 x 0.136 / 4 = 0.01457 m

0.216 m/s 0.216 x 0.1362 / 0.00001 3.7 x 0.136 = 29447.17 + 2.51 0.0 x sqr( l ) ]

1 sqr(l)

= - 2 log [

By solving above equation : l= 0.02377 0.02377 x 0.2162 x 0.216 2 x 9.81 x 0.1362 0.00042 x 100 m = 0.042 = 0.0 m/m m / 100m

J = l . V / ( 2 g D ) = Loss m per 100 m = J x 100 = Pipe length L = 47.0 m

dh(1) Liner loss = J x L = 0.00042 x 47.0 = 0.02 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) .... (7) G V SUM ZE 0 0 0 0 0 0 0 0 0 0 0 SUM ZE . V / ( 2 . g ) 1.1 x 0.2162 X 0.2162 2 x 9.81 = 0.0026 m : Gravity acceleration (9.81 m/s) : Velocity of water (m/s) : Sum of local loss factors 0 0 0 0 0 2 0 1 0 0 x x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 1 = = = = = = = = = = = 0 0 0 0 0 0.6 0 0.5 0 0 1.10

Where:

SUM ZE =

HS2

HS(2) = SUM ZE.x V / ( 2 g ) =

= HS1 + HS2 = 0.02 + 0.003 = 0.022 m = Static head + Friction losses . ( 8 ) = 0.0 + 0.022 = 0.022 m

Data for the Seventh pipe :

63

PVC 63 mm 4.7 mm

Pipe type & size 63 Out side diameter (mm) Wall thickness (mm) : pipe inside diameter (m.) : pipe inside Surface roughness (m.) m/sec

D = K =

0.0536 m 0.00001 m

Flow :

Q = 50.0 GPM = 03.15 l/s = 0.00315 A = p x D2 / 4 = V = Q/A = Re = V x D / n =

3.14 x 0.054 / 4 = 0.00226 m

1.396 m/s 1.396 x 0.0536 / 0.00001 3.7 x 0.054 = 74826.58 + 2.51 0.0 x sqr( l ) ]

1 sqr(l)

= - 2 log [

By solving above equation : l= 0.01993 0.01993 x 1.396 x 1.396 2 x 9.81 x 0.0536 0.03694 x 100 m = 3.694 = 0.0 m/m m / 100m

J = l . V / ( 2 g D ) = Loss m per 100 m = J x 100 = Pipe length L = 32.0 m

dh(1) Liner loss = J x L = 0.03694 x 32.0 = 1.182 m Local losses equation is given as follows: HS2 = SUM ZE . V / ( 2 . G ) .... (7) G V SUM ZE 0 0 0 0 0 0 0 0 0 0 0 SUM ZE . V / ( 2 . g ) 1.8 x 1.396 X 1.396 2 x 9.81 = 0.1788 m : Gravity acceleration (9.81 m/s) : Velocity of water (m/s) : Sum of local loss factors 0 0 0 0 0 1 0 1 0 1 x x x x x x x x x x 0.2 1 1 2 0.3 0.3 0.9 0.5 2 1 = = = = = = = = = = = 0 0 0 0 0 0.3 0 0.5 0 1 1.80

Where:

SUM ZE =

HS2

HS(2) = SUM ZE.x V / ( 2 g ) =

= HS1 + HS2 = 1.182 + 0.179 = 1.361 m = Static head + Friction losses . ( 8 ) = 30.0 + 1.361 = 31.361 m

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated *data Given Data:
Number of persons Boiler Design Water Consumption(L/person/day) Hot Water Consumption (L) Hot Water demand per day(m3/ day) Average Demand per Hour (m3/h) Peak Duration (h) Volume of Heated Water (m3) Cold Water Tank Volume % Tank Volume (m3) = = = = = = = = 400 120 79 4 3 12 25% 15 = 656

Tank Diameter (m) Tank Length (m)

= 2 = 5

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated*data
Design of Circulating Pump Q (m3/h) Q (l/s) Head (m) Pump Efficiency Power (Hp) = = = = = 4 2 22

0.8
1

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated *data
Drain Sump Sewer Drainage No. of Drainage Fixtures Fixtures Flow Rate (L / min) Parking Area Drainage Car Demand (L / car / day) No. of cars Parking Drainage (L / min) Laundry Drainage Laundry Demand (L / bed / day) No. of beds Laundry Drainage (L / min) Kitchen Drainage Kitchen Demand (L / person / day) No. of persons Kitchen Drainage (L / min) Total Drainage Flow (L / min) Duration Time of Empting Sump (min) Sump Capacity (m3) = 160 = 656 = 73 = 419 = 10 = 4 = 130 = 656 = 60 = 30 = 20 = 1

= 48 = 285

Sump Depth (m) Water Surface Area (m2)


Pump occupancy of Sump Area Water occupancy of Sump Area

= 1.5 = 3
= 40% = 60%

Sump Surface Area (m2)


Sump Dimension

= 5

Sump depth (m) Sump Length (m) Sump Width (m)

= 2 = 3 = 3

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated*data
Design of submersible Pump Sump Capacity (m3) = 18 Sump Empting Time (min) = 10 Q (L/S) Q (m3/s) Main Pipe Velocity (m/s) Main Pipe Diameter (mm) Pump Head Static Head Hs (m) Assume Losses (m) Losses Pump Head (m) Power Pump Efficiency Power (Hp) = 0.8 = 4 = 6 = 0.1 = 0.6 = 8 *From Sump Bottom Level to Septic Tank of static Head

= = = =

30 0.03

1 200

* Take the larger Standard Size

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated * data
Design of Reaction Tank Q (m3/day) Q Sewer (m3/day) Sewerage Flow to Be Treated (m3/day) Assume Reaction Tank Dimension Length (m) Width (m) Depth (m) Water Dimensions Length (m) Width (m) Depth (m) Reaction Tank Capacity (m3) Times to Fill Tank (time/day) Filter Design Filtration Rate (m3/m2/h) Qpump (m3/h) Filter Area (m2) = 22.5 = 22 = 1.02 = 3 = 3 = 3 = 3 = 3 = 2.5 = 22.5 = 10 = 263 = 237 = 214

Filter Diameter

(m)

= 1.15

Project : Example Location : Egypt

Date : May 30, 2009 Designed by : Zanitty

Assumed Data * You are allowed to change You are NOT ALLOWED to change Calculated*data
Filtration Pump Capacity (m3) Pump working hours Working time (h) Qpump (L/S) Pump Head (m) Pump Efficiency Power (Hp) = 23 = 12 = 1.2 = 6 = 22 = 0.8 = 3

You might also like