Professional Documents
Culture Documents
SPRING BOX DESIGN: The appropriate type of intake box suitable for the spring is selected from the Standard Type of Springs, depending upon the actual condition in the field. Spring box should be provided with adequate overflow pipe so as not to damage the spring box in times where the spring discharge increases due to excessive rains or where the aquifer level is fluctuating.
PUMP DESIGN: Pump size should be determined by Well Yield Number of Operating Hours Fill and Draw or Float System Hydraulic Zones Delivery Pressures
If the pump is used directly to supply water to the distribution system, the capacity must be equal to PHD If the water distribution system has a reservoir, the pump capacity must be equal to MDD
Pump Selection:
Centrifugal Pumps , If TDH = < 6 meters Jet Pumps, If TDH = 6 to 20 meters Submersible Pumps, If TDH = > 20 meters TDH is the sum of the depth of pumping water level + maximum reservoir elevation + friction losses
Calculate Pump Capacity: Power (Kw) = 9.8 x (1/eff) x Q x TDH Power (HP) = Kw/0.746 Where: Q = Discharge (cms) TDH = Total Dynamic Head (m) eff = Pump Efficiency Pump Efficiency: Centrifugal Pump: 30 60% Jetmatic Pump: 20 30% Submersible Pump: 50 60%
DESIGN OF RESERVOIR: Reservoirs are employed in the distribution system to meet the peak demand (if water source is available), to equalize pressure and to store water. The elevation of the bottom tank is computed to be at least equal to but preferably higher than the elevation of the farthest and highest tap in the system plus the minimum pressure head plus the total head losses from the point up to source.
PIPELINE DESIGN:
In applying the design minimum requirements for the design of pipeline, the following should be considered: It must be designed to handle the PHD of the service area The minimum Pressure at the remotest end of the system (tap stand or communal faucet) shall not be less than 2.0 meters The pipeline must be designed considering that the Maximum Velocity in the pipe is 3m/s for main pipes and distribution pipes. Ensure that there is no negative hydraulic gradient or negative pressure in the pipelines.
1.852 x D^4.87
Plastic Iron
EXAMPLE 1
Proposed Source 1 Spring, 12 km away Confirmed yield, 20 lps
Barangay B 120 HH
Barangay A 100 HH
reservoir
Barangay D 200 HH
Barangay C 80 HH
Barangay F 400 HH
Barangay E 350 HH
EXAMPLE 1
No ROW problem anticipated All identified water sources have confirmed yields, and of acceptable water quality Water rights can be secured by LGU Water source site are free from environmental and social constraints Proposed Service Area, 5 Barangays (# OF PAX/HH =5.5) A 550 pax 100 HH B 660 120 C 440 80 D 1,100 200 E 1,925 350 F 2,200 400 Proposed Water Sources: 1. Spring 5 kms away sufficient elevation confirmed yield, 20 lps 2. Groundwater Well no. 1 10 lps, 50 m away Well no. 2 8 lps, 250 m
EXAMPLE 1
Population Projections
Barangay Name A B C D E F TOTAL
Population Households Population Households Population Households Population Households
Year 1
Year 5
Year 10
Year 15
Growth Rate: Year 5 = 1.21% Year 10 = 1.35% Year 15 = 0.99% Water Demand: at 110 liters/cap/day add 30% non-revenue water
EXAMPLE 1
demand
First year, immediate and long-terms (design
EXAMPLE 1
Investment Cost Operation and Maintenance Cost Probable water tariff Financial & Economic Indicators Willingness-to-connect and willingness-to-pay
EXAMPLE 1
Other Considerations
Reservoir Requirements
Maybe needed to provide supplemental flow
during peak periods Or simply to balance pressures during peak flows Normally sized at 20% to 30% of the average day demand Should consider fill-and-draw systems or float systems
END OF PRESENTATION