Professional Documents
Culture Documents
2.65
Angle of repose of soil () b Ka = 1-sin()/1+sin() Height of C.F. C/c dist bet. C.F. Over all depth of C.F. Clear cover to Reinforcement Maximum dia of rebar Eff. Depth of C.F. Width of C.F. Width of heel slab Width of Toe slab
Design of Wall
Length of Abutment wall Length of Wing wall Minimum height of wing wall Average height of wing wall Effective thickness of wall Min. horizontal steel required on each face Min. vertical steel required on each face Ht of wall (m) 11 9 7 5 3 Max. load on wall Kn/m2 EP SP 66.00 3.33 54.00 3.33 42.00 3.33 30.00 3.33 18.00 3.33 40 30 3 7 0.28 3.5 2.1 m m m m m cm2/m 2 cm /m Reinforcement required in wall Earth face Away from Earth face Mu/b*d2 Pt Ast Pt Ast 0.70 19.71 2.24 0.57 16.02 0.572 16.02 1.85 0.461 12.91 0.434 12.15 1.46 0.355 9.94 0.316 8.85 1.08 0.265 7.42 0.202 5.66 0.69 0.166 4.65 Nos 4 0.6 3 m Plan of CF
Max. Moment Kn.m EF AEF 140.4 117 116.1 96.75 91.8 76.5 67.5 56.25 43.2 36
Horizontal Reinforcement Provided Ht of wall Horizontal steel provided on Each face (m) 11m to 9m 20 Tor @ 150c/c 9m to 7m 20 Tor @ 150c/c 7m to 5m 16 Tor @ 150c/c 5m to 3m 16 Tor @ 150c/c up to 3m 12 Tor @ 150c/c
Reinforcement quantity in wall Vertical steel provided on Each 12 Tor @ 150c/c 12 Tor @ 150c/c 12 Tor @ 150c/c 12 Tor @ 150c/c 12 Tor @ 150c/c
11m to 7m 7m to 3m 7m to 3m up to 3m up to 3m Vert.R/F Vert.R/F 54 54 54 41 41 2.48 kg/m 2.48 kg/m 1.59 kg/m .89 kg/m .89 kg/m .89 kg/m .89 kg/m 45 m 125 m 45 m 125 m 45 m 12.8 m 7.8 m 6.0 T 16.7 T 3.8 T 4.6 T 1.6 T 6.1 T 11.1 T
534
1601
Abut wall Wing wall Abut wall Wing wall Abut wall Abut wall Wing wall
Pt Ast Provide 25 dia@ on Tension face Provide 25 dia@ on compression face 28 nos. 7 nos. As As
Abut wall Abut wall Abut wall Wing wall Wing wall Wing wall Abut wall Abut wall Wing wall Wing wall
3 3436 mm
9 8 7 10 dia@
2 2094.40 mm
0.35 2.65 Dead load of wall per m Dead load of Base slab Earth fill on base slab Total Dead load acting on base slab Total Stabilizing Moment Net Moment acting at the base slab Area of base slab Section Modulus of base slab Maximum base pressure Minimum base pressure Eccentricity of load Maximum Base pressure 4.25
96.25 79.7 524.7 700.6 634 898.2 4.25 3.01 463 -134 1.28 0.84 554.1
554.1 Kn/m2 216.75 Kn/m2 337.4 Kn/m2 264 Kn.m Mu/b*d2 0.87 Pt 0.215 % Ast-earth Reinforcement required on earth face 14.51 cm2/m Provide 16 Tor @ 125 c/c (16.11 cm2/m) in Toe slab on earth face Minimum Ast required in Toe Slab Pt 0.12 % Ast-away earth steel required on away earth face 4.05 cm2/m 2 Provide 12 Tor @ 150 c/c (7.54 cm /m) in Toe slab on away earth face Maximum Upthrust on Toe slab Maximum downward load on slab Net upthrust on toe slab Maximum moment in Toe slab
% cm2/m Provide 12 Tor @ 150 c/c (7.54 cm2/m) in Heel slab on each face Minimum Ast required in Toe Slab Pt 0.12 % Ast-away earth steel required on away earth face 4.05 cm2/m Provide 12 Tor @ 150 c/c (7.54 cm2/m) as distribution reinforcement Reinforcement quantity in Base slab 1601 nos. 1.58 kg/m 5.6 m 14.0 T Base slab 1334 nos. .89 kg/m 5.6 m 6.6 T Base slab 58 nos. .89 kg/m 213.30 m 11.0 T Base slab 50.2 Total quantity of steel in CF's 32 T Total M30 Grade concrete in Base slab 638 cum Kg/cum Reinforcement required on earth face Description M30 Grade Concrete in Abutment wall & Returnwalls HYSD Reinforcement (Fe-500 ) TMT Bars Unit Cum MT Quantity 1438 129 Rate 6500 50000 Amount 93 65
Lakhs Lakhs
158
Lakhs
3.33
42.00
3.33
48.00
3.33
54.00
3.33
60.00
3.33
66.00
3.33
Due to EP
Due to Surcharge
IS : 456 - 2000
IS : 2911 - Part-I/Sectio
SP-16
= = =
mm mm mm mm
Capacity of Pile
= = = =
Load carrying capacity of piles Kn Size of Column B mm
Kn
mm
Nos
1 5 9 13 17 20 23 26 30
8 8 8 8 8 8 8 8 8
2 2 3 3 3 3 3 3 2
33 36 39 43 47 51 55 59 62 65 68 72 75 78 82 86 90 94 97 100 103 107 111 115 118 121 124 128 131 134
513.99 256.64 225.69 1035.29 1527.92 1241.66 710.05 847.31 657.89 415.80 668.76 921.93 585.03 737.88 1281.42 1040.77 674.83 669.03 576.71 495.02 351.17 655.77 696.64 890.04 887.82 891.55 616.59 340.80 430.60 297.87
0.86 4.77 2.92 10.51 19.42 34.99 7.00 2.83 2.77 2.86 0.98 4.50 1.94 14.70 11.80 25.55 11.45 9.44 7.06 9.44 17.42 4.47 23.87 4.32 1.67 8.52 37.78 0.87 8.56 9.85
17.26 15.16 12.23 5.64 28.90 24.60 0.46 4.50 16.69 7.08 0.23 0.00 1.10 11.72 32.39 46.56 3.55 5.11 4.16 1.25 6.16 0.90 14.85 114.20 121.66 113.57 15.42 2.54 6.15 5.69
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400
2 2 2 3 5 4 2 3 2 2 2 3 2 3 4 3 2 2 2 2 2 2 2 3 3 3 2 2 2 2
725.718 725.718 725.718 1088.577 1814.295 1451.436 725.718 1088.577 725.718 725.718 725.718 1088.577 725.718 1088.577 1451.436 1088.577 725.718 725.718 725.718 725.718 725.718 725.718 725.718 1088.577 1088.577 1088.577 725.718 725.718 725.718 725.718
230 230 230 230 230 450 450 230 230 230 450 230 230 230 230 450 450 230 230 230 230 230 450 450 450 450 450 230 230 230
Design of Pilecap Two-Pile Pile cap Diameter of pile provided Number of Piles Provided = =
B D 550
= = = = = = = =
Maximum Load on column Load on each pile Size of Pile cap 350 1200 350
PU RU L B D
Diameter of main rebar Effective depth of Pile cap Maximum moment in pilecap Reinforcement required Minimum Reinforcement required Hence Provide Provide Provide 12 6 6 Tor bars @ 16 12 200 dia bars dia bars at bottom at top pt = deff Mu Ast-req Ast-min Ast-prov Ast-prov Ast-prov
= = = = = = =
Check for Shear Critical section for shear shall be at a distance of deff from face of support Distance of critical section from face of support Distance Pile outer face from face of column Since the critical section falls outside pile section, there will be no shear in pilecap Hence no shear reinforcement is required Three-Pile Pile cap Diameter of pile provided Number of Piles Provided 1039 B2 700 B1 = = = =
12 00
1039
00 12
1039
12 00
1200
700
1900 L B D = = = = = = = = deff Mu Ast-req Ast-min 20 12 125 dia bars dia bars at bottom at top pt = Ast-prov Ast-prov Ast-prov = = = = = = =
1039
00 12
B D
Maximum Load on column Load on each pile Diameter of main rebar Effective depth of Pile cap Maximum moment in pilecap Reinforcement required Minimum Reinforcement required Hence Provide Provide Provide 12 5 5 Tor bars @
PU RU
Check for Shear Maximum shear force in Beam Shear stress in beam B1 Maximum permissible shear stress for concrete Shear strength of concrete Shear to be resisted by stirrups for Pt = 0.78 Vu tv tc-max tc Vus Vus/deff Hence provide 12 Tor 4-legged stirrups @ 150c/c Design of Beam Marked B2 Size of beam Proposed Vus/deff L B D = = = = = = = = = =
Maximum Load on Beam B2 Maximum moment in pilecap Reinforcement required Minimum Reinforcement required Hence Provide Provide Check for Shear Maximum shear force in Beam Shear stress in beam B1 Maximum permissible shear stress for concrete Shear strength of concrete Shear to be resisted by stirrups for Pt = 0.50 Vu tv tc-max tc Vus Vus/deff Hence provide 10 Tor 4-legged stirrups @ 150c/c Four-Pile Pile cap & Five Pile Pile cap Three-Pile Pile cap Diameter of pile provided Number of Piles Provided 1900 1200 Vus/deff 5 5 16 12 dia bars dia bars at bottom at top Mu Ast-req Ast-min Ast-prov Ast-prov
= = = = = =
= = = = = = =
= =
1200 1900 Size of column Provided B Maximum Load on column Load on each pile Size of Pile cap 2397 D PU = = = = = =
12 00
RU 1697 L B
12 00
Diameter of main rebar Effective depth of Pile cap Maximum moment in pilecap Reinforcement required Minimum Reinforcement required Provide Provide 12 10 Tor bars @ Tor bars @ 125 125 c/c at bottom in both directions c/c at top in both directions 1697 2397
1697
= =
= = = = = =
Check for Shear Critical section for shear shall be at a distance of deff from face of support Distance of critical section from face of support Distance Pile outer face from face of column Since the critical section falls outside pile section, there will be no shear in pilecap Hence no shear reinforcement is required = =
ilding
IS : 456 - 2000
IS : 2911 - Part-I/Section-2
25 500 75
N/mm2 N/mm2 mm
17.5
Kn
375 375 375 375 375 600 600 375 375 375 600 375 375 375 375 600 600 375 375 375 375 375 600 600 600 600 600 375 375 375
400 2
mm Nos
mm mm Kn
692.5 612.5
mm mm
400 3
mm Nos
mm mm mm mm mm
1040.77 Kn 346.9233 Kn 20 505 270.4 13.7 4.04 15.71 5.65 9.05 mm mm Kn-m cm2 cm2 cm
2
cm2 cm2/m
780.5775 mm
520.39
Kn
156.1155 Kn-m 7.9 4.04 10.05 5.65 cm2 cm2 cm2 cm2
Kn N/mm2 N/mm
2
400 4
mm Nos
230 375
mm mm
600 20 505
mm mm mm
315.1335 Kn-m 8.4 6.06 9.05 6.28 cm2/m cm2 cm2/m cm2/m
692.5 612.5
mm mm