Professional Documents
Culture Documents
Contents
1. Overview of JCM project 2. Reference scenario setting 3. Monitoring methods 4. Quantification of GHG emissions and MRV methods 5. Scale of investment 6. Progress and project implementation time frame 7. Others
Forest preservation
Alternative land
Soil improvement
Farmland
Forest logging
GHG emission
Project emissions
Forest conservation
Year
3. Monitoring methods
Monitoring Items
1. GHG emission by project
Item Electricity to produce products Fuel to transport products Fuel for soil improvement Emission by improved soil Method Wattmeter Receipt Receipt Actual measurement by chamber Frequency Continuous 1 / year 1 / year More than 10 days / year
4. Quantification of GHG emissions and MRV methods Eligibility criteria The project should avoid existing practice plan. The land for improvement should not be peat land. Land targeted for improvement should not be used for other purposes. Fossil fuel and electricity for project should be quantitative.
5. Scale of investment
Initial and operating cost (under consideration)
Category Initial Item Construct facility for coal ash products Purchase equipment for soil improvement Operation for 1year Soil improvement Produce coal ash products Transport coal ash products Monitoring Cost (million yen) 195 18 11 13 6 Under consideration Note 33t / d Ex tractor 2 units / 250 ha/y 250 ha 10,000 t 160,000 km
7. Others
To widely diffuse the project
Exchange of land should be approved between forest owner and strong acid soil land-owner
Practice plan
Exchange
7. Others
Collaboration with our great partner FORDA