Professional Documents
Culture Documents
Supported by: Ministry of Environment of Japan, FY2010-FY2012 GEC: Global Environment Center Foundation
Berbak delta
Berbak river
Batang hari
10km
After (=Project)
Water table and rice production increase
Water gate
Peat in Groundwater
ash
Pipe installation
PlotA
BHA1-1
AP-2
AP-5
AP-12
AR-1
AR-6
Precipitation
0 20 40 60 80 100
Precipitation (mm/10min)
2011/10/31
2011/12/30
2012/2/28
2012/4/28
2012/6/27
2012/8/26
2012/10/25
4.5
4.0
SK-6 Road
Flap Gate
PlotA
Tertiary Channel Tertiary Channel
PC-2
B
: Tertiary Channel
Road SK-5
Tertiary canals and water gate plan (12ha rice field in Plot A)
A. B. Water Retention
Secondary channel Land Land
Water channel
Tertiary channel
High tide/Flooding
Low tide/Rainfall
B. A.
III. HYDROLOGY MODEL Calculate Ground Water Level with Lumped Model or 3D Model.
No
Reference
(Reference Water Level)
RWL
Project
Water gate
PWL
2 3
4 5 6
Reference Scenario
BaU: Rewetting of developed peatlands will not become obligatory in the Republic of Indonesia.
Reference scenario
Aerobic peat CO2 decomposition N2O Anaerobic peat CH4 decomposition Aerobic peat CO2 decomposition
Main source to be addressed in reference scenario. Conservatively not accounted. Conservatively not accounted. Main source and gas to be addressed by the project activities. When rice production exceeds national policy target, N2O and CH4 emissions shall be evaluated (3 ton/ha in 2004-2014, 4 ton/ha in 2015-2019, 5-6 ton/ha after 2020).
Project scenario
Rice production
N2O
Yes
Calculated using a hydraulic model using satellite climate data (precipitation, air-temperature) and confirmed with groundwater levels (RMSE<10cm) measured at specified points. Mean annual peat Peat depth of each plot shall be measured before project depth implementation. During project activity, peat depth shall be measured before each Verification. Annual change of DP can be assumed to be constant.
Precipitation (mm/d)
150
GWL (GL-m)
Pilot Project
-1.0 -0.8 -0.6 -0.4 Rainfall(mm/d) Box Model Obs. (Average) 0 50 100
RMSE=10cm
RMSE=8cm
450 500
Precipitation (mm/d)
150
GWL (GL-m)
C + 2H2 CH 4 + 75(KJ/mol) C + O2 CO 2 + 406(KJ/mol) H 2 + 1/2O 2 H 2O + 242(KJ/mol) CO2 + C 2CO - 173(KJ/mol) C + H2 O CO + H2 - 131(KJ/mol) CO2 + H 2 CO + H 2O + 41(KJ/mol)
Briquette maker
Gasification furnace
Project Cost
Project cost: Estimation of the project cost for 10,000ha
Initial Cost Cost
million USD
1 2 3 4 5 6
Water gate restoration Leakage & bypass stop Ccanal maintenance Monitoring equipment Gas furnace & generator Project preparation & Validation Total
10 location x 20,000USD, 120 locations x 5,000USD 120 locations x 10,000USD Prim: 50km x 20,000USD/km Second: 200km x 3,000USD/km Tertiary: 500km x 1,000USD/km + 1,000
Annual Operation Cost 1 2 3 4 5 6 7 Water gate maintenance Canal maintenance Gate operation Monitoring equipment Hydrology model calculations Gas furnace & Generator maintenance Monitoring Report & Verification Total
Cost 1,000USD
Project Scheme
Project Scheme
Japanese Government
Support
Next Steps 1. Continued capacity building 2. PPP Scheme Development under JCM