ULT CORPORATION PTE LTD

7E PIONEER SECTOR 1 SINGAPORE 628446 TEL: 64153078 FAX: 68631928

ER420-NEW ROAD LINK BETWEEN UPPER CHANGI ROAD AND UPPER CHANGI ROAD EAST

METHOD STATEMENT

Bakau piling for 1500 RCU Drain along MC02

PREPARED BY APPROVED BY SAFETY OFFICER DATE OF SUBMISSION REVISION

: HARIRAM MANOHARAN : GOO KIANG TIONG, JIMMY : LEE SHANG KENG : :0

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

TABLE OF CONTENTS: 1. Objective 2. Project Overview 3. Resources: Plant and Manpower 3.1. Hierarchy Chart for this Operation 3.2 Relevant certificates for manpower and Equipment 4. Method Statement 4.1. Service/ Utilities in the Vicinity of work 4.1.1. List of services 4.1.2. Protective Measures 4.2 Schedule of Works 5. Emergency Plan 5.1 Evacuation Plan 5.2 Damage to services 5.3 Lists of essential Personnel 6. Safety and Environmental 6.1 Lists of personal protective equipment (PPE) 6.2 Permit to Work System 6.3 Risks Assessment and hazard Analysis Appendix 1- Location Plan of Proposed Bakau piling works Appendix 2- Relevant Certificates for Manpower & Equipment Appendix 3-Services/Utilities in the Vicinity of Work Appendix 4- Permit to Work Forms Appendix 5- Risk Assessment and Hazard Analysis

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

1) OBJECTIVE:The purpose of this document is to describe the methodology for the Installation of Bakau piles for 1500 RCU drain works along Upper Changi road MC02. 2) PROJECT OVERVIEW:The works under contract ER420: New road link between Upper Changi Road and Upper Changi Road East mainly comprises of the following: Construction of new road between Upper Changi Road and Upper Changi Road East Construction of New junctions in the Upper Changi Road and Upper Changi Road East Construction of Rigid Pavements at the junctions Widening a Part of Upper Changi Road Milling and Patching works in Upper Changi Road and Upper Changi Road East Construction of Drains, Box culverts and sumps Construction of Two Bus Bays and Bus Shelter Slabs Installation of railings

3) RESOURCES:PLANT & MANPOWER:Sl.No Machinery: 1 Excavator fitted with 3 meter long steel dolly( Excavator with valid LM certificate) Manpower: Site Engineer Surveyor Site Supervisor Safety Supervisor Banksman General Worker 1 Item Qty

3 4 5 6 7 7

1 1 1 1 1 7

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

3.1)

HIERARCHY CHART FOR THE OPERATION:-

Project Manager

Site Engineer

Safety Supervisor

Site Supervisor

Surveyor

Excavator operator

Foreman

Banksman

General Worker

3.2)

RELEVANT CERTIFICATES FOR MANPOWER AND EQUIPMENT:-

The relevant certificates for Manpower and Equipment are attached in Appendix 2. Updated relevant certificates will be submitted before the commencement of work.

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

4) METHOD STATEMENT:4.1) SERVICES/UTILITIES IN THE VICINITY OF WORK:-

4.1.1) List of services: There are no services running along the work area. The sheet piling works have been completed already. Trial trenches were done before the sheet piling works to ensure the absence of any services within the work area. 4.1.2) Protective measures: Even though there are no services running exactly below the piling area, there is a 500mm AC Main at a distance of 7.5 meter from the bakau piling area. Care is to be taken that no unsafe acts are carried out near the AC main. Regular checks are to be carried out to look for any possible leakage in the 500 AC Main. 4.2.2) SEQUENCE OF BAKAU PILING WORKS: 1) Set out the proposed 1500RCU drain alignment as per setting-out plan. 2) Excavate the trenches to the required depth for the laying of precast RC U-drain. 3) When the excavation reaches the required depth, Start the installation of Bakau piles. 4) Bakau piles are installed with the help of the Steel Dolly attached to the teeth of the excavator bucket. 5) The length of the metal dolly is 3m. The depth of excavation is 2.5m which means that the entire excavator bucket will be above the strut area when the bakau piles are completely installed. 6) The work sequence is; The bakau pile is placed in the required location and is pressed into the soil by the workers up to possible depth. The workers are then to move away from the pile. The dolly attached to the excavator bucket is then lowered and the bakau pile is inserted into the hollow part of the metal dolly. If necessary, worker will assist

in inserting the pile in to the dolly. ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

The metal dolly is the pressed down gradually until the whole length of the bakau pile is inserted into the ground. The dolly is then lifted up with much care to prevent it from hitting the workers near the work area. The next bakau pile is placed 300mm from the previous pile and the same process is continued.

Excavator Bucket

3m

Metal Dolly

300mm Bakau Pile

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

Struts

2.5m

1900mm

1500mm RCU Drain

50mm Thick lean concrete

3.5m x 75mm Bakau pile

Sheet Pile

300mm 300mm

300mm

300mm

300mm

300mm

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

SAFETY PRECAUTION 1) Work site shall be cordon off from public access. 2) Proper barricade and signage shall be provided to warn the workers to divert away from deep excavation 3) Work area must be cleaned and stagnant water cleared daily. 4) All workers shall wear Personal Protective Equipment e.g. reflective safety vest, safety helmet within the site. 5) Site supervisor shall supervise throughout the entire piling works; he is wholly in-charge of safety, supervision and traffic control in work areas. 6) Where excavators are used, care shall be taken to ensure that no materials are stacked within the swinging area of the excavator.

5) EMERGENCY PLAN:5.1) EVACUATION PLAN:Upon the occurrence of work site accident, the emergency evacuation plan is as follows: Site work in the vicinity will be stopped The reporting of the occurrence of accident will go up the company hierarchy i.e. workers inform supervisors/engineers, who will inform the project manager, and then the RTO and LTA will be informed Site and safety supervisors will be taking charge of securing the area Any hurt personnel will be carefully shifted to a secure location for first aid and subsequent evacuation to nearby hospital Unhurt work personnel will be gathered at a safe with headcount accounted for. They will receive further instructions Accident area to be investigated and subsequently cleared.

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

5.2)

DAMAGE TO SERVICES:-

In spite of all the precautionary measures taken, if there is any damage to the existing service, the follow up action is as follows: Site work in the vicinity will be stopped The reporting of the occurrence of accident will go up the hierarchy Site and safety supervisors will be taking charge of securing the area A report for services damage are be made immediately to the following hotline number; PUB-1800-284 6600 SPPG-1800-778 8888 SINGTEL-1800-288 4099 5.3) LIST OF ESSENTIAL PERSONNEL:Name Jimmy Goo Hariram Lee Shang Keng Soh Eng Soon Fong Heng Wong Solaiappan Subramanian Velayutham Muniyandi Designation Project Manager Site Engineer Safety Officer Site Supervisor Site Supervisor Site Supervisor Safety supervisor Contact number 9695 7413 9447 7749 9666 0582 9068 4578 8402 5141 8433 2276 8259 0048

6) SAFETY AND ENVIRONMENTAL:6.1) List of Personal Protective Equipment (PPE):S/No 1 2 3 4 5 6 Safety Helmet Safety boots Reflective vest Hand Gloves Full Body Harness( If applicable) Face Mask and Safety Goggles PPE

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

6.2)

Permit to Work System:All relevant Permit to Work forms would be submitted before the operation. Refer to Appendix 6 for the relevant forms.

6.3)

Risk Assessment and Hazard Analysis:-

Refer to Appendix 7 for the Risk assessment and Hazard analysis for the work.

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

APPENDIX 1 LOCATION PLAN FOR BAKAU PILING WORKS

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

APPENDIX 2 Relevant Certificates for Manpower and Equipment

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

APPENDIX 3 Services/Utilities in the Vicinity of Work

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

APPENDIX 4 Permit to Work- Forms

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc

APPENDIX 5 Risk Assessment and Hazard Analysis

ER420_MS of Bakau Piling works for 1500 RCU_r0.doc