Professional Documents
Culture Documents
Background
1.1 Project description:
Pumped storage hydroelectricity is a type of power generation used by some other power plants for load balancing. It is only method of large scale electrical energy storage in widespread use today. The basic concept is simple. Energy is stored as hydraulic potential energy by pumping water from a low-level into a high-level reservoir. When recovery of energy is required, the water is returned to the lower reservoir through turbines which drive electrical generators. It helps on load balancing only. No extra energy is added, it only stores electrical energy and provides it according to need. However we dont have any extra or off-peak energy in our system during dry period but during wet period we would have enough amount of energy to pump water. So seasonal Pumped storage hydropower can be integrated in our system to cover the peak demand. The energy used in pumping a volume V of water of density and through a height h with a pumping efficiency p E1= (gh/3600* p) MWH... (1) The energy recoverable with a regeneration efficiency g
E2= (gh * g /3600) MWH. (2) Where g is the acceleration due to gravity Typically, the overall efficiency (E2/E1) = g * p; which is in the range 70-80 %
Hence, this scheme will help in peaking capacity and also load balancing. Pumped storage hydropower is environmental friendly as it is pollution free and is renewable source of electricity.
Page | 2
2. Description of proposal
2.1 Objective of the project
The objectives of the project are as follows: To To To To To To To To To To To calculate the inundation area in Rupa lake predict necessary methods for slope stabilization of Rupa lake shore determine the capacity of pumped storage hydropower in Rupa and Begnas lake design intake, dam and powerhouse for pumped storage hydropower perform the structural analysis of purposed dam find the transmission distance from powerhouse to nearest grid estimate the cost of different components of hydropower study the geology of site using geotechnical investigations design the cross-section of the tunnel conduct socio-economic survey at site predict environmental impact due to project implementation
Page | 3
2.5 Review of the available expertise within the institution and host organisation
S.N.
1. 2. 3. 4.
Name Prof. Dr. Ramesh Kumar Maskey Dr. Chandra Prakash Poudel Er. Khimananda Kandel Er. Kalidas Neupane
Organisation Kathmandu University Kathmandu University EPSOM Engineering Consultancy Pioneer Engineering Consultancy
Page | 4
Page | 5
4. Methodology
4.1 Desk study
Planning is the initial stage of any development work. And to plan our project perfectly we are studying the works in the field of development of Pumped storage hydropower. We are collecting data required for our work. For our project work we are studying the annual reports that have been published by NEA; to establish the relation between present demand and supply, future demand and supply and other sources of energy available in grid except hydropower. We are studying the topography & geological maps of the area. We discussed about the need and feasibility of the project with our supervisors. We will also study the works done by other organization or institution in this field.
4.4 Calculation
The calculation works that would be done in our projects are presented under following subheadings:
Page | 6
4.4.1 Calculation of Inundation area The inundation area will be calculated from the contour map. We will calculate the inundation area for maximum and minimum discharge from Begnas to Rupa Lake. The inundation area will be different for different option of power generation. 4.4.2 Calculation of Power The power of Pumped storage hydropower will be calculated at different discharge available. While deciding the plant capacity, the surplus energy available from the system to pump the water will be considered.
4.5 Design
The design work of following components will be done. Intake Dam Powerhouse Cross-section of tunnel
4.6 Drawing
Detailed drawing of each component will be done in AutoCAD.
Page | 7
WORK PLANNNED
DESK STUDY AND LITERATURE REVIEW PREPARATION FOR FIELD WORK SURVEY WORK DATA HANDLING AND ANALYSIS CALCULATION DESIGN COST ESTIMATE FEASIBILITY AND POTENTIALITY CHECK FINAL REPORT PREPARATION AND SUBMISSION
WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK 1 2 3 4 5 6 7 8 9 10
Page | 8
6. Budget
The estimated budget of the project is shown below. Table No.2: Estimated Budget for pumped storage project
S.N. Description 1 Survey Instrument a Total Station b Tape c GPS d Manpower 2 3 4 a b c d Bus fare Lodging Fooding breakfast lunch breakfast dinner
Unit Rs./day
total Rs. 60,000.00 Rs. Rs. Rs. 9,000.00 Rs. 69,000.00 Rs. 6,000.00 Rs. 22,500.00
remarks for 15 days from CEPTE from CEPTE Hire two way for 15 days
2 5 5
5 5 5 5
Rs. 3,750.00 Rs. 11,250.00 Rs. 6,000.00 Rs. 12,750.00 Rs. 33,750.00 Rs. 10,000.00 Rs. 1,41,250.00
Page | 9
Page | 10
8. Likely impact
It will not be false to say that each project has some impact on nature or on mankind. While some projects have undesirable impacts more than the favourable one; Pumped storage hydropower seems to have less adverse effects on living and non-living environment. Few of the likely impacts have been listed below: Inundation of the Rupa lake Slope failure due to inundation of the shoreline of Rupa Lake Slight increase of temperature of both lakes due to constant cycling of lake water. Aquatic life will be affected severely during operation Tourism will be affected slightly
Page | 11
9. Reference
Nepal Journals Online, Hydro Nepal: Journal of water, Energy and Environment, volume 5 (2009), Nepal Electricity Authority(NEA), http://www.nea.org.np/ NEA Annual Report 2009 ,
NEA
Annual
Report
2010
NEA
Annual
Report
2011
NEA
Annual
Report
2012
Electricity Crisis (Load Shedding) in Nepal, Its Manifestations and Ramifications, Ratna Sansar Shrestha .
Electrical Energy Storage - Large Scale (August 2009) Amit Kumar Lohiya, MIT, Manipal. Water Power Development (Volume 2 High head power plants), Emil Mosony.
Wikipedia, http://en.wikipedia.org/wiki/ Pumped Hydroelectricity ROAM report on Pumped Storage modeling for AEMO 100%, Renewables project, 24 September 2012.
Page | 12