Sirajganj 150MW Peaking Power Plant

Site Testing for Electrical Equipments 230kV Transmission Line Insulation Test Measurement of Resistance, Impedance and Reactance (R,X and Z) of the transmission line Phasing check High Voltage Withstand Test

230kV Isolators and Earth Switches Operational tests: check contact pressures, contact resistances, simultaneous operation of all phases and the ease of operation Motorised operation tests: local and remote operation, timing tests and motor protection tests Visual / Physical Inspection: interlocks, local and remote indications, manual locking devices and operation of auxiliary contacts Check the opening and closing sequences of earth switches

230kV Circuit Breakers Visual / Physical Inspection: interlocks, local and remote indications and operation of auxiliary contacts Contact Resistance Tests Operational Tests: local and remote trip / close Timing tests Insulation Test High Voltage Withstand Test

Current Transformers Insulation Test Magnetising curve check CT resistance measurement

Ratio Check Polarity Check Burden (VA) rating check

Voltage Transformers Insulation Test Ratio Check Polarity Check / Phasing and Phase Rotation Check Induced Voltage Check

230kV Surge Arrestors Visual / Physical Inspection: mounting of the arrestors, earth connections and electrodes

230kV Busbars and Connections Sags and Tensions Check Clearances Check Conductivity Test

Power Transformers Insulation Resistance Test between Core and Earth Insulation Resistance test between Windings and Earth Voltage Ratio at all tap positions Continuity Test for On Load Tap Changers Vector Group Test Dielectric Strength Measurement, acidity and moisture content test of oil Leak Test Buchholz Stability Test Conservator Shut Off Valve Stability / Operation Test

Zero Sequence Impedance Measurement Winding Power Factor DLA Bushing Power Factor DLA Oil Power Factor (Mai Tank, Conservator & OLTC) DLA Power Factor Measurement Wiring Check Oil Winding Temperature Test Magnetizing Curve for Winding Temperature HV & LV CT Insulation Oil Tests before transformer energizing Complete tests on protection, alarm and indication circuits including nitrogen gas injection of the Buchholz to simulate operation of the alarm and surge elements

Isolated Phase Bus Ducts Resistance Measurement of bus bar trunking Joint Conductivity Measurement Insulation Resistance to Earth Measurement High Voltage Withstand Test Air Pressure Test

6.6kV Switchgears Bus bar Continuity Checks Insulation Resistance Test High Voltage Test Visual Inspection Operation and interlocking test