Professional Documents
Culture Documents
10/7/2010
Coverage is not limited to equipment built to ASME Codes Covers repairs after equipment has been placed in service. Repairs during construction are covered by the new construction codes.
10/7/2010
10/7/2010
10/7/2010
10/7/2010
Repair Life Many M of f th the repair i techniques t h i included i l d d in i this thi Standard St d d are considered to be permanent, intended to remain in place for the life of the repaired component. Others may only be suitable for short-term service, and should be replaced with a more permanent repair at the appropriate opportunity. The anticipated life of the repair depends on many circumstances, and could include consideration of risk. As such, this Standard does not classify repair methods as permanent or temporary.
10/7/2010
10/7/2010
10/7/2010
Fig. 2 Flush Insert Plate (With or Without Nozzle/Manway) With Its Butt Weld Intersecting Existing Butt Weld in Shells or Heads
NOTES: (1) Existing butt weld in vessel shell or head. head (Fig (Fig. 2 shows butt weld in a cylindrical shell.) (2) Thirty deg minimum angle. (3) Full RT or UT, or MT or PT both sides of existing butt weld, 100 mm (4 in.) min. each side of intersection with insert plate. (4) Insert plate butt weld. Full RT or UT, or MT or PT both sides of weld. (5) For nonpostweld heat-treated carbon and low alloy steel nozzle/manway assemblies, 150 mm (6 in.) minimum between the toe of the
10/7/2010
10
10/7/2010
Mechanical Clamp
(1)
Y = Generally appropriate. S = Although may be acceptable, is not generally used for this condition. R = May be used, but requires special cautions. N = Not generally appropriate.
Note (1): Normally, mechanical clamps are used to contain leaks at packings, and at flange and gasketed joints, or to contain leaks/potential leaks due to
(1)
Y = Generally appropriate. S = Although may be acceptable, is not generally used for this condition. R = May be used, but requires special cautions. N = Not generally appropriate. Note (1) Welded leak repair box applies to leaking flanges, valves, pipe components, welded
11
10/7/2010
The weld overlay repair provides a practical technique for repairing degraded walls of piping components. As shown above, the weld overlay restores the load carrying capability and integrity of the repaired location through the application of external weld material.
12
10/7/2010
Y = Generally appropriate. S = Although may be acceptable, is not generally used for this condition. R = May be used, but requires special cautions. N = Not generally appropriate.
Note (1): Normally, mechanical clamps are used to contain leaks at packings, and at flange and gasketed joints, or to contain leaks/potential leaks due to
13
10/7/2010
14
10/7/2010
15
10/7/2010
Lmax = maximum axial dimension of base metal predicted to degrade below the required thickness over the remaining life of the repair, mm (in.). Amax =maximum area of base metal predicted to degrade below the required thickness over the remaining life of the repair, mm2 (in2). ) Do = pressure component nominal outside diameter, mm (inches).
Do < DN300 DN300 - 600 k1 0.21 0.11 k2 14 mm (0.55 inch) 46.7 mm (1.84inch) k3 581 mm2 (0.9 in2) in2) 516mm2 (0.8
16
10/7/2010
Flaw Excavation
Genera al wall thinning
NA
Flaw excavation
NA
Y = Generally appropriate. S = Although may be acceptable, is not generally used for this condition. R = May be used, but requires special cautions. N = Not generally appropriate. Note (1): Also applies to the repair of hardened surfaces.
Pitting
Y
Gouges
Y
Blisters s
Y
(1)
Other
17
10/7/2010
Flaw Excavation - 2
Material or weld flaws open to the surface are typically removed by a mechanical (abrasive) method.
1. If the remaining wall thickness of the excavation, with allowance for future corrosion, is greater than the minimum required wall thickness required by the construction t ti or post-construction t t ti code d (such ( h as the local thin area rules of API 579) the excavated area may be blended to a 3:1 or smoother profile slope, and left as-is for return to service.
Flaw Excavation - 3
2. .W When e the t e removal e ova o of a flaw aw p produces oduces a remaining e a g wall thickness below the limit permitted by the construction or post-construction code, including allowance for future corrosion, then the cavity shall be repaired by deposition of weld metal or analyzed for fitness-for-service.
When the depth of material excavated necessitates a weld repair, repair the cavity shall be prepared for welding. welding Either during or following defect removal, the excavation shall be shaped to provide adequate access for the welding operation in order to facilitate proper fusion, and avoid slag entrapment, or lack of penetration
18
10/7/2010
Flaw Excavation - 4
Fabrication - The following steps are generally followed to excavate a flaw: 1. Locate and expose the flaw. Characterize the flaw (size, depth, orientation) to the extent possible. If the flaw is a crack, the crack tips may be rounded by drilling to preclude crack from propagating during its excavation. 2. Remove the flaw by grinding, machining, honing or thermal gouging. In selecting and applying a removal process refer to the guidance process, g idance in Sections 2 and 3.. 3 3. Verify defect removal by inspecting the cavity using visual examination (VT), and liquid penetrant testing (PT), or magnetic particle testing (MT) or eddy current testing (ET) as appropriate.
Grinding Repairs
Grinding of cracks, arc burns, gouges and grooves is an acceptable method of permanent repair, repair provided the length and depth of metal loss is in accordance with the formula given below. For arc burns, confirmation of complete removal of altered metallurgical structures by etching the ground area with a 10% solution of ammonium persulfate or a 5% solution of nital is recommended.
19
10/7/2010
Grinding Repairs
Areas to be repaired by grinding shall be thoroughly cleaned before grinding is initiated initiated. Grinding shall be performed to produce a smooth transition between the surface contour of the repaired area and the surrounding pipe surface. External metal loss resulting from grinding to a depth of 40% of the nominal wall thickness of the pipe is permitted, i d provided id d that h the h longitudinal l i di l length l h of f the h ground area does not exceed length L as determined by the following formula: L = 0.441 B1 (Dt)0.5
Grinding Repairs
Where L = maximum allowable longitudinal length of the metal loss area resulting from a grinding repair, inches. D = nominal outside diameter of pipe, inches. T = nominal wall thickness of pipe, inch. B1= a value equal to 4 for maximum depths up to and including 13% of the nominal wall thickness. = a value determined from the following equation for maximum depths greater than 13% of the nominal wall thickness up to and including 40% of the of the nominal wall thickness: B1 ={[(c/t)/ (1.1 c/t) 0.11)] 2 1} 0.5 c = maximum depth of the ground area, inches.
20
10/7/2010
Grinding Repairs
For gouges, grooves and cracks, confirming complete l t removal l of f the th defects d f t by b using i dye d penetrant or magnetic particle inspection and measuring the remaining wall thickness using a mechanical or ultrasonic technique is recommended.
21