PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block- D superstructure

08

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE

8F/-

ELECTRICAL INSTALLATION
Note : All materials, equipments, wiring and workmanship shall confirm to local codes of specifications, B.S Standards, latest I.E.E regulations (17th edition) and Ceylon Electricity Board specifications. Contractor shall investigate the site conditions before submitting their quote

Contractor shall obtain sample approvals from all the items used from CEE-SEC Contractor shall propose shop drawings/conduit layouts drawings and obtained approval from CEESEC before commencing installation General Inspection and testing 8F/01 Testing of the complete Electrical Installation and issuing a certificate by a chartered Electrical Engineer, registered with Ceylon Electricity Board. Main Power Supply System cables Note : Rates should include for all necessary cable accessories such as cable ties, Cable Lugs, Glands, identification tags, and accessories All horizontal and vertical Cable trays should be adequately sized to provide 40% spare space.Contractor shall investigate the site conditions and include all the cost involved in point rates given below.

Item

21,000.00

All the Cables quoted below shall be on measure and pay basis. Rates shall include installation of Cable taryas,Cable Ladders, PVC trunking or conduits and accessories where required .

TO COLLECTION
PROJECT NAME

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION

Block- D superstructure

08

QTY.

UNIT

UNIT RATE

8F/02 Supply,Installation & Termination of 4 x 70mm2 XLPE/SWA/PVC/Cu Cable from MSB to Meter Room 01 (For Block C) 8F/03 Supply,Installation & Termination of 4 x 16mm2 PVC/PVC/Cu + 16mm2 PVC/Cu(E) Cable from G.SDB-2 to Lift DB 8F/04 Supply,Installation & Termination of 2 x 6mm2 PVC/PVC/Cu Cable from Meter Room-2 to Each House Distribution Board 8F/05 Supply,Installation & Termination of 6mm2 PVC/Cu Earth Cable from DB to Cu Plate at Electrical Shaft. Distribution Boards. All Distribution Boards shall be flush/Surface mounted type Distribution Boards complete with powder coated 1.5 mm thick sheet steel enclosure with lockable doors.

150

13,125.00

80

3,675.00

3600 1350

m m

1,470.00 265.00

note The panel board should have wire numbering and a laminated circuit diagram pasted on the inside surface of the door. Make of MCCBs and MCBs, etc shall be Merlin Gerin / ABB / Terasaki / Hager or equivalent make approved by the Electrical Engineer. Manufactures soft drawings should be submitted and aproved by chief electrical engineer before fabrication. note COMMON AREA 8F/06 Lift DB 01 No. 4P 63A MCB 01 No. DP 32A MCB 01 No. 4P 63A,100mA RCCB 01 No. DP 40A,30mA RCCB 01 No. SP 20A MCB 02 Nos.SP 10A MCB 01 No. SP 16A MCB Flush mounted Powder Coated Steel Enclosure c/w bus bars and Accessories 1 no 68,250.00

note

note

Lockable

TO COLLECTION
PROJECT NAME BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION

Block- D superstructure

08

QTY.

UNIT

UNIT RATE

HOUSES 8F/07 DB.H 01 No. 32A DP MCB 01 No. DP 40A,30mA RCCB 01 No.SP 16A MCB 09 Nos.SP 20A MCB Flush mounted Powder Coated Steel Enclosure c/w bus bars and Accessories 45 no 26,250.00

Lockable

Wiring for light points, ceiling fans, socket outlets

Rate point wiring shall include for all the conduits, conduit fittings, casings,surface cable trunks, fixing material, switches, wiring and terminations, holders for light fittings and socket outlets for power points. Contractor shall obtain approvals from the Chief Electrical Engineer for above items. Aproved samples should be displayed at the site office. As a standard of quality for switches and socket outlets, the contractor may use 'CLIPSAL/hager /mk or approved equal'. COMMON AREA 8F/08 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU + 1.5mm2 PVC/cu(E) cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 72 HOUSES 8F/09 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 8F/10 Supply and Installation a Bell point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a Bell push as shown in the drawings. 45

note

note

no

2,890.00

360

no

2,890.00

no

3,340.00

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block- D superstructure

08

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE

8F/11 Supply and Installation a 5A single switched socket outlet fixed on wall, from the respective consumer unit using 2x1.5mm2 PVC/PVC/CU + 1.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. 8F/12 Supply and Installation a 15A single switched socket outlet fixed on wall, from the respective consumer unit using 2x2.5mm2 PVC/PVC/CU + 2.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. Light fittings The light fittings supplied and installed under this contract shall be in every respect suitable for the intended purpose. Each fitting shall include bulbs, internal wiring, hanging and fixing material and be complete without any additional item/material being required to make it so.

270

no

3,150.00

45

no

4,725.00

note

note All control gear of light fittings such as choke, starters, PF Correction Capacitors shall be of European make note The contractor shall obtain consultants and clients approval for the fittings before fixing the fittings in the site COMMON AREA 8F/13 Bulk Head Lamp- Type A HOUSES 8F/14 Bracket Lamp c/w 70W CFL 8F/15 Pendent Lamp c/w 70W CFL 8F/16 600mm ,18W Single fluorescent fitting with Linear Diffuser 8F/17 Electrical Bell With Bell Push 8F/18 Provisional Sum for Lightning Protection System 8F/19 Provisional Sum for Telephone and TV Wiring System Item TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

note

72

no

3,675.00

45 270

no no

3,675.00 2,625.00

45 45

no no Item

2,940.00 3,675.00

Block- D superstructure

08

ELECTRICAL INSTALLATION
COLLECTION Page No. 8/27 Page No. 8/28 Page No. 8/29 Page No. 8/30

CARRIED TO BILL NO. 8 SUMMARY

PAGE NO.

8/27

TOTAL PRICE RUPEES

21,000.00

21,000.00
PAGE NO.

8/28
TOTAL PRICE RUPEES

1,968,750.00

294,000.00

5,292,000.00 357,750.00

68,250.00

7,980,750.00
PAGE NO.

8/29
TOTAL PRICE RUPEES

1,181,250.00

208,080.00

1,040,400.00

150,300.00

2,580,030.00
PAGE NO.

8/30

TOTAL PRICE RUPEES

850,500.00

212,625.00

264,600.00

165,375.00 708,750.00

132,300.00 165,375.00

2,499,525.00
PAGE NO.

8/31
TOTAL PRICE RUPEES

21,000.00 7,980,750.00 2,580,030.00 2,499,525.00

13,081,305.00

PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block- E superstructure

08

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE

8F/-

ELECTRICAL INSTALLATION
Note : All materials, equipments, wiring and workmanship shall confirm to local codes of specifications, B.S Standards, latest I.E.E regulations (17th edition) and Ceylon Electricity Board specifications. Contractor shall investigate the site conditions before submitting their quote

Contractor shall obtain sample approvals from all the items used from CEE-SEC Contractor shall propose shop drawings/conduit layouts drawings and obtained approval from CEESEC before commencing installation General Inspection and testing 8F/01 Testing of the complete Electrical Installation and issuing a certificate by a chartered Electrical Engineer, registered with Ceylon Electricity Board. Main Power Supply System cables Note : Rates should include for all necessary cable accessories such as cable ties, Cable Lugs, Glands, identification tags, and accessories All horizontal and vertical Cable trays should be adequately sized to provide 40% spare space.Contractor shall investigate the site conditions and include all the cost involved in point rates given below.

Item

21,000.00

All the Cables quoted below shall be on measure and pay basis. Rates shall include installation of Cable taryas,Cable Ladders, PVC trunking or conduits and accessories where required .

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block- E superstructure

08

QTY.

UNIT

UNIT RATE

8F/02 Supply,Installation & Termination of 4 x 70mm2 XLPE/SWA/PVC/Cu Cable from MSB to Meter Room 01 (For Block C) 8F/03 Supply,Installation & Termination of 4 x 16mm2 PVC/PVC/Cu + 16mm2 PVC/Cu(E) Cable from G.SDB-2 to Lift DB 8F/04 Supply,Installation & Termination of 2 x 6mm2 PVC/PVC/Cu Cable from Meter Room-2 to Each House Distribution Board 8F/05 Supply,Installation & Termination of 6mm2 PVC/Cu Earth Cable from DB to Cu Plate at Electrical Shaft. Distribution Boards. All Distribution Boards shall be flush/Surface mounted type Distribution Boards complete with powder coated 1.5 mm thick sheet steel enclosure with lockable doors.

150

13,125.00

80

3,675.00

3200 900

m m

1,470.00 265.00

note The panel board should have wire numbering and a laminated circuit diagram pasted on the inside surface of the door. Make of MCCBs and MCBs, etc shall be Merlin Gerin / ABB / Terasaki / Hager or equivalent make approved by the Electrical Engineer. Manufactures soft drawings should be submitted and aproved by chief electrical engineer before fabrication. note COMMON AREA 8F/06 Lift DB 01 No. 4P 63A MCB 01 No. DP 32A MCB 1 no 68,250.00

note

note

01 No. 4P 63A,100mA RCCB 01 No. DP 40A,30mA RCCB 01 No. SP 20A MCB 02 Nos.SP 10A MCB 01 No. SP 16A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block- E superstructure

08

HOUSES 8F/07 DB.H 01 No. 32A DP MCB 01 No. DP 40A,30mA RCCB 01 No.SP 16A MCB 09 Nos.SP 20A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories Wiring for light points, ceiling fans, socket outlets 45 no 26,250.00

Rate point wiring shall include for all the conduits, conduit fittings, casings,surface cable trunks, fixing material, switches, wiring and terminations, holders for light fittings and socket outlets for power points. Contractor shall obtain approvals from the Chief Electrical Engineer for above items. Aproved samples should be displayed at the site office. As a standard of quality for switches and socket outlets, the contractor may use 'CLIPSAL/hager /mk or approved equal'. COMMON AREA

note

note

8F/08 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU + 1.5mm2 PVC/cu(E) cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 45 HOUSES 8F/09 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 360 8F/10 Supply and Installation a Bell point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a Bell push as shown in the drawings. 45 no 3,340.00 no 2,890.00 no 2,890.00

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block- E superstructure

08

8F/11 Supply and Installation a 5A single switched socket outlet fixed on wall, from the respective consumer unit using 2x1.5mm2 PVC/PVC/CU + 1.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. 8F/12 Supply and Installation a 15A single switched socket outlet fixed on wall, from the respective consumer unit using 2x2.5mm2 PVC/PVC/CU + 2.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. Light fittings The light fittings supplied and installed under this contract shall be in every respect suitable for the intended purpose. Each fitting shall include bulbs, internal wiring, hanging and fixing material and be complete without any additional item/material being required to make it so.

270

no

3,150.00

45

no

4,725.00

note

note

All control gear of light fittings such as choke, starters, PF Correction Capacitors shall be of European make note The contractor shall obtain consultants and clients approval for the fittings before fixing the fittings in the site note COMMON AREA 8F/13 Bulk Head Lamp- Type A HOUSES 8F/14 Bracket Lamp c/w 70W CFL 8F/15 Pendent Lamp c/w 70W CFL 8F/16 600mm ,18W Single fluorescent fitting with Linear Diffuser 8F/17 Electrical Bell With Bell Push 8F/18 Provisional Sum for Lightning Protection System 8F/19 Provisional Sum for Telephone and TV Wiring System Item TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

45

no

3,675.00

45 270

no no

3,675.00 2,625.00

45 45

no no Item

2,940.00 3,675.00

Block- E superstructure

08

ELECTRICAL INSTALLATION
COLLECTION Page No. 8/27 Page No. 8/28 Page No. 8/29 Page No. 8/30

CARRIED TO BILL NO. 8 SUMMARY

PAGE NO.

8/27

TOTAL PRICE RUPEES

21,000.00

21,000.00
PAGE NO.

8/28
TOTAL PRICE RUPEES

1,968,750.00

294,000.00

4,704,000.00 238,500.00

68,250.00

7,273,500.00
PAGE NO.

8/29
TOTAL PRICE RUPEES

1,181,250.00

130,050.00

1,040,400.00

150,300.00

2,502,000.00
PAGE NO.

8/30
TOTAL PRICE RUPEES

850,500.00

212,625.00

165,375.00

165,375.00 708,750.00

132,300.00 165,375.00

2,400,300.00
PAGE NO.

8/31
TOTAL PRICE RUPEES

21,000.00 7,273,500.00 2,502,000.00 2,400,300.00

12,196,800.00

PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block-F superstructure

08

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE

8F/-

ELECTRICAL INSTALLATION
Note : All materials, equipments, wiring and workmanship shall confirm to local codes of specifications, B.S Standards, latest I.E.E regulations (17th edition) and Ceylon Electricity Board specifications. Contractor shall investigate the site conditions before submitting their quote

Contractor shall obtain sample approvals from all the items used from CEE-SEC Contractor shall propose shop drawings/conduit layouts drawings and obtained approval from CEESEC before commencing installation General Inspection and testing 8F/01 Testing of the complete Electrical Installation and issuing a certificate by a chartered Electrical Engineer, registered with Ceylon Electricity Board. Main Power Supply System cables Note : Rates should include for all necessary cable accessories such as cable ties, Cable Lugs, Glands, identification tags, and accessories All horizontal and vertical Cable trays should be adequately sized to provide 40% spare space.Contractor shall investigate the site conditions and include all the cost involved in point rates given below.

Item

21,000.00

All the Cables quoted below shall be on measure and pay basis. Rates shall include installation of Cable taryas,Cable Ladders, PVC trunking or conduits and accessories where required .

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block-F superstructure

08

QTY.

UNIT

UNIT RATE

8F/02 Supply,Installation & Termination of 4 x 70mm2 XLPE/SWA/PVC/Cu Cable from MSB to Meter Room 01 (For Block C) 8F/03 Supply,Installation & Termination of 4 x 16mm2 PVC/PVC/Cu + 16mm2 PVC/Cu(E) Cable from G.SDB-2 to Lift DB 8F/04 Supply,Installation & Termination of 2 x 6mm2 PVC/PVC/Cu Cable from Meter Room-2 to Each House Distribution Board 8F/05 Supply,Installation & Termination of 6mm2 PVC/Cu Earth Cable from DB to Cu Plate at Electrical Shaft. Distribution Boards. All Distribution Boards shall be flush/Surface mounted type Distribution Boards complete with powder coated 1.5 mm thick sheet steel enclosure with lockable doors.

150

13,125.00

80

3,675.00

2200 900

m m

1,470.00 265.00

note The panel board should have wire numbering and a laminated circuit diagram pasted on the inside surface of the door. Make of MCCBs and MCBs, etc shall be Merlin Gerin / ABB / Terasaki / Hager or equivalent make approved by the Electrical Engineer. Manufactures soft drawings should be submitted and aproved by chief electrical engineer before fabrication. note COMMON AREA 8F/06 Lift DB 01 No. 4P 63A MCB 01 No. DP 32A MCB 1 no 68,250.00

note

note

01 No. 4P 63A,100mA RCCB 01 No. DP 40A,30mA RCCB 01 No. SP 20A MCB 02 Nos.SP 10A MCB 01 No. SP 16A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block-F superstructure

08

HOUSES 8F/07 DB.H 01 No. 32A DP MCB 01 No. DP 40A,30mA RCCB 01 No.SP 16A MCB 09 Nos.SP 20A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories Wiring for light points, ceiling fans, socket outlets 36 no 26,250.00

Rate point wiring shall include for all the conduits, conduit fittings, casings,surface cable trunks, fixing material, switches, wiring and terminations, holders for light fittings and socket outlets for power points. Contractor shall obtain approvals from the Chief Electrical Engineer for above items. Aproved samples should be displayed at the site office. As a standard of quality for switches and socket outlets, the contractor may use 'CLIPSAL/hager /mk or approved equal'. COMMON AREA

note

note

8F/08 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU + 1.5mm2 PVC/cu(E) cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 72 HOUSES 8F/09 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 288 8F/10 Supply and Installation a Bell point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a Bell push as shown in the drawings. 36 no 3,340.00 no 2,890.00 no 2,890.00

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block-F superstructure

08

8F/11 Supply and Installation a 5A single switched socket outlet fixed on wall, from the respective consumer unit using 2x1.5mm2 PVC/PVC/CU + 1.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. 8F/12 Supply and Installation a 15A single switched socket outlet fixed on wall, from the respective consumer unit using 2x2.5mm2 PVC/PVC/CU + 2.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. Light fittings The light fittings supplied and installed under this contract shall be in every respect suitable for the intended purpose. Each fitting shall include bulbs, internal wiring, hanging and fixing material and be complete without any additional item/material being required to make it so.

216

no

3,150.00

36

no

4,725.00

note

note

All control gear of light fittings such as choke, starters, PF Correction Capacitors shall be of European make note The contractor shall obtain consultants and clients approval for the fittings before fixing the fittings in the site note COMMON AREA 8F/13 Bulk Head Lamp- Type A HOUSES 8F/14 Bracket Lamp c/w 70W CFL 8F/15 Pendent Lamp c/w 70W CFL 8F/16 600mm ,18W Single fluorescent fitting with Linear Diffuser 8F/17 Electrical Bell With Bell Push 8F/18 Provisional Sum for Lightning Protection System 8F/19 Provisional Sum for Telephone and TV Wiring System Item TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

72

no

3,675.00

36 216

no no

3,675.00 2,625.00

36 36

no no Item

2,940.00 3,675.00

Block-F superstructure

08

ELECTRICAL INSTALLATION
COLLECTION Page No. 8/27 Page No. 8/28 Page No. 8/29 Page No. 8/30

CARRIED TO BILL NO. 8 SUMMARY

PAGE NO.

8/27

TOTAL PRICE RUPEES

21,000.00

21,000.00
PAGE NO.

8/28
TOTAL PRICE RUPEES

1,968,750.00

294,000.00

3,234,000.00 238,500.00

68,250.00

5,803,500.00
PAGE NO.

8/29
TOTAL PRICE RUPEES

945,000.00

208,080.00

832,320.00

120,240.00

2,105,640.00
PAGE NO.

8/30
TOTAL PRICE RUPEES

680,400.00

170,100.00

264,600.00

132,300.00 567,000.00

105,840.00 132,300.00

2,052,540.00
PAGE NO.

8/31
TOTAL PRICE RUPEES

21,000.00 5,803,500.00 2,105,640.00 2,052,540.00

9,982,680.00

PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block-G superstructure

08

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE

8F/-

ELECTRICAL INSTALLATION
Note : All materials, equipments, wiring and workmanship shall confirm to local codes of specifications, B.S Standards, latest I.E.E regulations (17th edition) and Ceylon Electricity Board specifications. Contractor shall investigate the site conditions before submitting their quote

Contractor shall obtain sample approvals from all the items used from CEE-SEC Contractor shall propose shop drawings/conduit layouts drawings and obtained approval from CEESEC before commencing installation General Inspection and testing 8F/01 Testing of the complete Electrical Installation and issuing a certificate by a chartered Electrical Engineer, registered with Ceylon Electricity Board. Main Power Supply System cables Note : Rates should include for all necessary cable accessories such as cable ties, Cable Lugs, Glands, identification tags, and accessories All horizontal and vertical Cable trays should be adequately sized to provide 40% spare space.Contractor shall investigate the site conditions and include all the cost involved in point rates given below.

Item

21,000.00

All the Cables quoted below shall be on measure and pay basis. Rates shall include installation of Cable taryas,Cable Ladders, PVC trunking or conduits and accessories where required .

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION

BILL OF QUANTITIES

BILL NO.

SPEC. DIV. NO.

Block-G superstructure

08

QTY.

UNIT

UNIT RATE

8F/02 Supply,Installation & Termination of 4 x 70mm2 XLPE/SWA/PVC/Cu Cable from MSB to Meter Room 01 (For Block C) 8F/03 Supply,Installation & Termination of 4 x 16mm2 PVC/PVC/Cu + 16mm2 PVC/Cu(E) Cable from G.SDB-2 to Lift DB 8F/04 Supply,Installation & Termination of 2 x 6mm2 PVC/PVC/Cu Cable from Meter Room-2 to Each House Distribution Board 8F/05 Supply,Installation & Termination of 6mm2 PVC/Cu Earth Cable from DB to Cu Plate at Electrical Shaft. Distribution Boards. All Distribution Boards shall be flush/Surface mounted type Distribution Boards complete with powder coated 1.5 mm thick sheet steel enclosure with lockable doors.

150

13,125.00

80

3,675.00

2000 900

m m

1,470.00 265.00

note The panel board should have wire numbering and a laminated circuit diagram pasted on the inside surface of the door. Make of MCCBs and MCBs, etc shall be Merlin Gerin / ABB / Terasaki / Hager or equivalent make approved by the Electrical Engineer. Manufactures soft drawings should be submitted and aproved by chief electrical engineer before fabrication. note COMMON AREA 8F/06 Lift DB 01 No. 4P 63A MCB 01 No. DP 32A MCB 1 no 68,250.00

note

note

01 No. 4P 63A,100mA RCCB 01 No. DP 40A,30mA RCCB 01 No. SP 20A MCB 02 Nos.SP 10A MCB 01 No. SP 16A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block-G superstructure

08

HOUSES 8F/07 DB.H 01 No. 32A DP MCB 01 No. DP 40A,30mA RCCB 01 No.SP 16A MCB 09 Nos.SP 20A MCB Flush mounted Powder Coated Steel Lockable Enclosure c/w bus bars and Accessories Wiring for light points, ceiling fans, socket outlets 27 no 26,250.00

Rate point wiring shall include for all the conduits, conduit fittings, casings,surface cable trunks, fixing material, switches, wiring and terminations, holders for light fittings and socket outlets for power points. Contractor shall obtain approvals from the Chief Electrical Engineer for above items. Aproved samples should be displayed at the site office. As a standard of quality for switches and socket outlets, the contractor may use 'CLIPSAL/hager /mk or approved equal'. COMMON AREA

note

note

8F/08 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU + 1.5mm2 PVC/cu(E) cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 19 HOUSES 8F/09 Supply and Installation a light point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a 5A flush switch as shown in the drawings. 216 8F/10 Supply and Installation a Bell point, from the respective consumer unit using 2x1mm2 PVC/PVC/CU cable drawn through securely fixed concealed PVC conduit controlled by a Bell push as shown in the drawings. 27 no 3,340.00 no 2,890.00 no 2,890.00

TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

Block-G superstructure

08

8F/11 Supply and Installation a 5A single switched socket outlet fixed on wall, from the respective consumer unit using 2x1.5mm2 PVC/PVC/CU + 1.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. 8F/12 Supply and Installation a 15A single switched socket outlet fixed on wall, from the respective consumer unit using 2x2.5mm2 PVC/PVC/CU + 2.5mm2PVC/cu(E) cable drawn through securely fixed concealed PVC conduit shown in the drawings. Light fittings The light fittings supplied and installed under this contract shall be in every respect suitable for the intended purpose. Each fitting shall include bulbs, internal wiring, hanging and fixing material and be complete without any additional item/material being required to make it so.

162

no

3,150.00

27

no

4,725.00

note

note

All control gear of light fittings such as choke, starters, PF Correction Capacitors shall be of European make note The contractor shall obtain consultants and clients approval for the fittings before fixing the fittings in the site note COMMON AREA 8F/13 Bulk Head Lamp- Type A HOUSES 8F/14 Bracket Lamp c/w 70W CFL 8F/15 Pendent Lamp c/w 70W CFL 8F/16 600mm ,18W Single fluorescent fitting with Linear Diffuser 8F/17 Electrical Bell With Bell Push 8F/18 Provisional Sum for Lightning Protection System 8F/19 Provisional Sum for Telephone and TV Wiring System Item TO COLLECTION
PROJECT NAME Proposed Housing Project for relocation of Under Served Settlements, Angulana ITEM REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE BILL OF QUANTITIES BILL NO. SPEC. DIV. NO.

19

no

3,675.00

27 . 162

no no

3,675.00 2,625.00

27 27

no no Item

2,940.00 3,675.00

Block-G superstructure

08

ELECTRICAL INSTALLATION
COLLECTION Page No. 8/27 Page No. 8/28 Page No. 8/29 Page No. 8/30

CARRIED TO BILL NO. 8 SUMMARY

PAGE NO.

8/27

TOTAL PRICE RUPEES

21,000.00

21,000.00
PAGE NO.

8/28
TOTAL PRICE RUPEES

1,968,750.00

294,000.00

2,940,000.00 238,500.00

68,250.00

5,509,500.00
PAGE NO.

8/29
TOTAL PRICE RUPEES

708,750.00

54,910.00

624,240.00

90,180.00

1,478,080.00
PAGE NO.

8/30
TOTAL PRICE RUPEES

510,300.00

127,575.00

69,825.00

99,225.00 425,250.00

79,380.00 99,225.00

1,410,780.00
PAGE NO.

8/31
TOTAL PRICE RUPEES

21,000.00 5,509,500.00 1,478,080.00 1,410,780.00

8,419,360.00