1.0 Purpose:
2.0 Scope:
This procedure is applicable to all incoming, in-process and final items/ products.
4.0 Procedure:
4.10.1 Inspection and testing shall be carried out for all processes carried out , process
parameters and product characteristics in the
Company. The inspection can be divided into three broad categories:
- Incoming Inspection
- In-process Inspection
- Final Inspection
a) On receipt of material it is logged into the Stores Receipt Voucher STR FO2.
c) The conforming material shall be entered in the stock register and kept in the
stores under appropriate conditions.
d) Reports of NC materials shall be raised, and sent to the CMD for further action
wherever required. All NC material shall be segregated and visually identified by
Red Tags.
e) A sampling plan is used for all incoming inspection .In case of any NC of raw
Material/Products supplied by the vendor, 100% inspection shall be carried out for
that item or as advised by the CMD.
f) In case, the incoming material is released for urgent production purposes prior to
verification, it shall be done with prior approval of the CMD. Record for the same
shall be maintained in Positive Recall Register INSP RO1 in order to permit
Quality System Manual
immediate recall and replacement in the event of any non conformity to specified
requirements.
a) Final inspection and testing shall be carried out for all manufactured products .
d) All accepted material shall be suitably identified by green tag/ QC TESTED sticker as
per procedure for inspection and test status.
e) All inspection and tests shall be carried out as per sampling plan. In case of any
deviation, 100% inspection shall be carried out for that characteristic or as advised by the
CMD, as per details given under procedure of NC Products.
f) All inspected material shall be positively identified for its inspection status by the
inspection authority on the Final Inspection Reports INSP FO3A, INSP FO3B.
5.0 Reference:
6.0 Records:
Quality System Manual