METHOD STATEMENT FOR BLINDING CONCRETE

Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT

METHOD STATEMENT FOR BLINDING CONCRETE


**** (CIVIL)

AMENDMENTS
REV. NO PAGE NUMBER DESCRIPTION OF AMENDMENT APPROVED BY (SIGNATURE) EFFECTIVE DATE

METHOD STATEMENT FOR BLINDING CONCRETE

DESCRIPTION Prepared by Reviewed by Approved by

TITLE ENGR. PRASATH.S

SIGNATURE

DATE

Page 1 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT

CONTENTS

1. ACTIVITY 2. INTRODUCTION 3. TERMINOLOGY 4. SIGNIFICANT HAZARDS IDENTIFIED 5. ROLES & RESPONSIBILITY 6. SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES 7. REQUIREMENTS 7.1 Plans /Records and Job instructions (Documentations) 7.2 Trainings 7.3 PPE (Personal Protective Equipment) 7.4 Equipment and Tools required 8. EMERGENCY PROCEDURES 9. REFERENCES 10. ATTACHMENTS

1). ACTIVITY: BLINDING CONCRETE This activity deals with the blinding concreting (PCC) works upon the compacted soil of the site.
Page 2 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
2). INTRODUCTION After attaining the required compaction of the soil, blinding concrete is the first concreting, that acts as a barrier between the compacted soil and the upcoming building. This also prevents the rising of the water table. 3). TERMINOLOGY O/E: Owner / Engineer PPE: Personal Protective Equipment QC: Quality Control 4). SIGNIFICANT HAZARDS IDENTIFIED Contact of concrete with eyes Collapse of concrete pump Movement of vehicle Sharp pointed edges Electrical shock Slip/trip/fall/hazards

5). ROLES & RESPONSIBILITY Project Manager (Main Contractor) o Site construction and his team will report to project manager. Construction Manager (Main Contractor) o Make arrangement for availability of all relevant documents. o Ensure the availability of necessary documents & resources available with Subcontractor. o Liaison with Owner/Engineer & Subcontractor in-charges for necessary test & inspection. o Tracks the schedule & plan work accordingly. o Liaison with all Electrical/MEP work in-charges for all interfaces works and plans the work accordingly at site.

Engineer (Main Contractor) o Ensures the control at work spots in person.


Page 3 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
o Verifying the percentage compliance as per risk assessment. o Ensures the emergency preparedness of team and taking the part in Subcontractors TBT (Tool Box Talk) o Ensures the work carried out as per latest approved drawings. o Ensure availability of necessary resources and approved documents. o Inspects the incoming materials in line with approved documents. o Ensure the quality of work/material and readiness for inspection. Safety Officer (Main Contractor) o Responsible for ensuring HSE at all stages of work. o Ensures the compliance of all control measures at site as per approved risk assessment plan. o Ensures for all checklist as per HSE plan. Project Manager (Subcontractor) o Ensure that appropriate resources are provided for the safe delivery of the work Site In charge (Subcontractor) o Ensuring the relevant document o Organized the necessary men and material resources for timely completion and quality QA/QC Engineer (Subcontractor) o o o o Ensuring quality of work carried out at site Ensuring for inspection on hold points Maintaining all QC records Coordinating with O/E for inspections

Site Engineer (Subcontractor) o o o o o o o Ensuring the controls at work spot in person Verifying the % compliance as per risk assessment. Ensuring the emergency preparedness. Arranging the required inspections and permit Ensures all scaffolding are erected safely and scaffolding tag system followed Ensures availability of the necessary resources. Ensuring availability of all activity relevant latest approved drawing and documents

Supervisor / Foreman (Subcontractor/Supplier)


Page 4 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
Obtaining the permit (if required -e.g. Steel cutting) Conducting Tool Box Talk (TBT) based on risk assessment Arranging for appropriate tools and necessary skilled work force as required. Ensuring the works are carried out as per approved and latest drawing/documents Ensuring for Housekeeping always at work place. Implementing the control measures as per risk assessment and also as mentioned in the permit. o Close monitoring till completion of work. o Close the work permit after restoration of work spot. o o o o o o Workmen (Subcontractor/Supplier) o o o o o Wearing appropriate PPEs. Understanding and following the instructions given by line staff. Following the scaffolding tag system No horseplay and shortcuts. Informing the supervisor/foreman about any near misses, injuries and unusual

Safety Officer (Subcontractor) o o o o o Ensures all safety measures implemented/followed as per risk assessment and HSE Plan Should inform the site engineer for any deviations from required procedure/standard practice Should conduct a safety briefing in co-ordination with site engineer/supervisor over a specific HSE issue Ensure all First aid cases are entered in first aid register and necessary awareness given to the victim Ensures for inspection of power tools and scaffoldings

Surveyor (Subcontractor) o To check the levels, coordinates and alignments of every work activity at site.

Organization chat ( See for Attachment )

6). SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES Surface preparation Site survey shall be conducted and axis points shall be established. Surveying & setting out shall be done based on the reference points & coordinates as shown in the approved drawings. The existing ground level shall be verified. The existing surface should be compacted.
Page 5 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
Compaction Test, Plate load test to be carried out before proceeding with any activity on compacted surface and compaction test results to be submitted.

Concreting Concrete shall be carried out as per the approved materials and mix design based on the MAS-0023 (RE Status). Dwg.No RE 5300 V 7261 Rev-A Sheet 1/3 to 3/3 (132/22 kV Basement General Arrangement & sections - AEN) shall be followed for the concreting. The top of the blinding concrete level shall be followed strictly to the approved drawings. 1000 gauge polythene sheet shall be provided above the well compacted soil. Once the polythene sheet has been spreaded over the same surface, level pegs shall be made so as to maintaining the top level of the concrete and shall firmly hold the polythene sheet also. Shuttering to be fixed in the marked area. Cclearances for PCC from MML Electrical Engineer shall be obtained in prior to the concreting. 75 mm thick blinding concrete shall be poured as per the requirement of specification / approved drawings with the help of pump. Maximum Ambient temperature < 400C. Power float machine shall be provided (if needed) to smooth the surface of P.C.C. Required curing period of 7 days for the concrete shall be properly done.

Inspection and Testing Curing Curing of concrete will begin immediately after finishing of the concrete surface and in line with the requirements of the concrete curing and protection of the contract Specification. Immediately after the finishing, horizontal surface will bee covered with polythene sheeting with edges lapped or tied down to exclude air circulation. After concrete has stiffened, sheeting will be removed and replaced with approved type Hessian soaked with water covered with polythene to prevent evaporation.
Page 6 of 8

Surface preparation shall be completely done and notified to the O/E through inspection request Slump test shall be carried out at the check point and slump shall be maintained as per the specifications or as per the O/E requirements. Temperature of concrete shall not exceed +30C at pouring point. Testing cubes for 7 days and 28 days shall be prepared as per the Contract specifications clause 2.8.1 .e of S-TR-CIVIL-CONCRETE (Rev.0-2010) and send for the tests.

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
The blinding concrete shall be kept moist for a minimum of 7 days as per contract specifications.

7). REQUIREMENTS 7.1 Plans /Records and Job instructions (Documentations) Before starting the work the following things should be available: Field density (FDT) and plate bearing test reports shall be submitted in prior to the commencement of the works. Blinding concrete inspection request Approved drawings / Material approval for the work Method statement for the work Key site plan for that work area Trial mix test results shall be submitted for O/Es review.

7.2 Trainings Trained/Experienced persons shall be used for the work All operator / laborer are safety trained and toolbox talk to be conducted.

7.3 PPE (Personal Protective Equipment) Protective clothing Protective footwear (gum boots) Protective gloves Safety helmet Safety goggles Hi-visibility jacket Ear plug (if needed)

7.4 Work force / Equipment and Tools required Manpower requirement 1. General Supervisor/Foreman - 01 no 2. Charge hand - 02 nos 3. Mason - 10 nos 4. Helpers - 06 nos Concrete pump
Page 7 of 8

METHOD STATEMENT FOR BLINDING CONCRETE


Effective Date : Document No : MS-01-BLC Revision No :A Approved By :

PROJECT
Power trowel (if needed) Hand trowel (big/small) Aluminium straight edge Hand float Hand shovel Fork shovel

8). EMERGENCY PROCEDURES In case of any emergency situation, the workmen shall follow the emergency response procedure and shall gather in the assembly point. The emergency response procedure should have been conveyed to the work men through the toolbox talk in prior to the carrying out of the activity. 9). REFERENCES TRANSCO STANDARD: 141110474.DOC TRANSCO STANDARD: 141110474.DOC DRWG. NO. N7204.1E-R-E-5370-S-7261 REV. B SHEET 1~3 REF : PROJECT QUALITY PLAN REF : PROJECT HSE PLAN Ref. No: N7204.1E/MASS/0021 - POLYTHENE SHEET Ref. No: N7204.1E/MASS/0123 - CONCRETE MIX DESIGN Ref. No: N7204.1E/MASS/0037 - CONCRETE REPAIR MORTAR

10). ATTACHMENTS EXTRACT COPY OF TRANSCO STANDARD: 141110474.DOC RISK ASSESSMENT SHEETS OF USE OF CONCRETE PUMP RISK ASSESSMENT SHEETS OF CONCRETING RISK ASSESSMENT SHEETS OF VEHICLES MOVING RISK ASSESSMENT SHEETS OF TRANSPORTING OF MATERIALS RISK ASSESSMENT SHEETS OF USE OF POWER FLOAT MACHINE ORGANIZATION CHART.

Page 8 of 8