Professional Documents
Culture Documents
Tire-to-Fuel Plant
Water with the Wet Cake 0.08 kg/s (a) Overall Water Balance Before Mass Integration
Tire-to-Fuel Plant
No Fresh Water
Seal Pot Feed Water 0.15 kg/s Water-Jet Makeup 0.20 kg/s Water Generation 0.08 kg/s
Next, we represent the problem from a species viewpoint as shown in Fig. 5.2.
Flare Gas
Air Carbon
Resin
Decanter Wastewater
Seal Pot
Fresh Water
To Flare
0.25 0.20
0.18
Decanter Wastewater
0.15
Seal Pot Wastewater
Seal Pot
0.10
0.05 0.00
50
400
500
600
R1
600 y, ppmw
0
150
135
100
200
300
400
500
Pinch Point
R1
100 200 200 300 400 500
550
x1out = 600
900
0.25 0.20
0.18
0.15
50
400
500
600
C =
r j
r C2 =
Cj x x
t j s j
Therefore,
Similarly, and
Let us also examine the thermodynamic feasibility of the three external MSAs
R1
300 400 500 S2 S3 10 S4 20 600 200 300 600 y, ppmw x1, ppmw 1,000 x2, ppmw x3, ppmw x4, ppmw
Fig. 3.3. Examining Thermodynamic Feasibility of the External MSAs (not to scale) From Fig. 3.3 it can be seen that S2 is not thermodynamically feasible to remove the remaining load. Therefore, S4 is the optimum external MSA with an annual operating cost of 30x10-6 x68.97x3600x8760 = $65,246/yr. Fixed cost of stripper = 270,000 (0.2)0.65 = $94,850
Condenser
Gaseous Fuel
To Atmosphere
Flare
Wastewater Decanter Reactor Off-Gases Tires Shredded Tires Pyrolysis Reactor Light Oil 0.20 kg/s 500 ppm
Wastewater
L iquid F uels
Separation
Finishing
Compression
Payback period = 94,850/(110,000 - 65,246) = 2.1 yrs < 3 yrs (acceptable) p.s. For biotreatment, payback period = 240,000/ (110,000 - 60,000) = 4.8 yrs > 3 yrs (unacceptable)
0.079 kg solvent/s
Solvent Decomposition 0.011 kg/s Exhaust Gas leaving Drying 0.022kg/s
(b) Overall Solvent Balance After Mass Integration Including Recycling the Recovered Solvent
Maximum recovery of solvent entails reducing outlet composition of R1 and R2 to 2x10 -4 (corresponding to lowest inlet supply of S3).
0.077 kg solvent/s
R1
0.039 kg/s
0.038 0.021
2x10-4
0.004 0.001
R2
0.006 0.012 0.016 0.019 0.032 S1 0.014 0.040
y x1
S3 0.001 0.010
C1r= 0.002/(0.040 - 0.014) = $0.077 kg C3r= 0.002/(0.010 - 0.001) = $0.220 kg Therefore, we use S1 to remove 0.039 kg/s then follow up with S3 to remove 0.038 kg/s. Total solvent recovered = 0.039 + 0.038 = 0.077 kg/s Value of recovered solvent = $0.80/kg*0.077kg/s*3600*8760 = $1.943 MM/yr Annual operating cost 0.220x0.038)x3600x8760 = (0.077x0.039 +
10
= $358,000/yr (compare to value of recovered solvent being $1.943 million/yr.) Annual savings = 1,943,000 - 358,000 = $1,585,000/yr
11
Network Configuration
0.077 kg solvent/s Schematic (not to scale)
R1
0.039 kg/s
0.038 0.021
2x10-4
0.004 0.001
R2
0.006 0.012 0.016 0.019 0.032 S1 0.014 0.040
y x1
S3 0.001 0.010
R1 G1 = 3.0 kg/s y1s = 0.019 Ex1 S1 R1 G1 = 3.0 kg/s ypinch = 0.006 G = 8.5 kg/s Ex2 S3 R2 G2 = 5.5 kg/s y2s = 0.004
12
To convert from annualized fixed cost to fixed cost, need to assume useful life period (e.g., 5 years) Fixed cost = 5*18,000 (Gas flowrate)0.65 Fixed cost of exchanger 1 = 90,000 (3.0) 0.65 = $184,000 and Fixed cost of exchanger 2 = 90,000 (8.5)0.65 = $362,000 Fixed cost = 184,000 + 362,000 = $546,000 Payback period = 546,000/1,585,000 = 0.34 year (` 4 months)
13