You are on page 1of 2

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SAUDI ARAMCO TYPICAL INSPECTION PLAN


Irrigation Piping
PROJECT TITLE:

SATIP No.

APPROVED DATE

DISCIPLINE:

SATIP-S-070-02
WBS/BI/JO/NO.

18-May-05
CONTRACTOR/SUBCONTRACTOR

PLUMBING

ITEM NO.

PROJECT PHASE & ACTIVITY CODE

TASK / ACTIVITY

QUALITY PROCEDURE

QUALITY RECORD

INSPECTION RESPONSIBILITY ASSIGNMENTS


CNTRCTR SAUDI ARAMCO

REMARKS

1.0 1.1 2.0 2.1 3.0 3.1

DOCUMENT REVIEW Hydrostatic Package MATERIAL RECEIVING Thermoplastic and RTR piping INSTALLATION Trench Inspection Motor Operated Valves, Control Valves and Valves Piping lay-out Inspection Irrigation Piping Accessories Inspection RTR & Thermoplastic Piping Hydrostatic Testing Control Wiring (Same Trench) Inspection Backfill placement and compaction See Remarks See Remarks SAIC S-4052 SAIC S-4053 See Remarks See Remarks SAIC S-4032 See Remarks See Remarks See Remarks SAIC S-4052 SAIC S-4053 See Remarks See Remarks SAIC S-4032 See Remarks See SATIP-S-070-01 Excavation and Backfilling for Underground Utilities See SATIP-P-J-700-01 Motor Operated Valves and Control Valves and SATIP-L-108-01 Valves as applicable See Remarks See Remarks See SATIP-S-070-03 Thermoplastic and RTR piping See Remarks See Remarks See SATIP-A-004-02 Pressure Testing

3.2

3.3

W1 W1

W2 S

Saudi Aramco to be notified on start of this activity for each location

3.4

3.5 3.6

See SATIP-S-070-03 Thermoplastic and RTR Piping See SATIP-A-004-02 Pressure Testing Saudi Aramco to be notified on start of this activity for each location / area See SATIP-S-070-01 Excavation and Backfilling for Underground Utilities

3.7

W1

W2

3.8

Page 1 of 2

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SAUDI ARAMCO TYPICAL INSPECTION PLAN


Irrigation Piping
PROJECT TITLE:

SATIP No.

APPROVED DATE

DISCIPLINE:

SATIP-S-070-02
WBS/BI/JO/NO.

18-May-05
CONTRACTOR/SUBCONTRACTOR

PLUMBING

ITEM NO.

PROJECT PHASE & ACTIVITY CODE

TASK / ACTIVITY

QUALITY PROCEDURE

QUALITY RECORD

INSPECTION RESPONSIBILITY ASSIGNMENTS


CNTRCTR SAUDI ARAMCO

REMARKS

4.0 4.1

PRE-COMMISSIONING Not applicable

GENERAL NOTES 1 2 3 4 5
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saudi Aramco participation based upon the Contractors performance. Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present. Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance. If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1 W2 H1 100% Witness Inspection/Test Sample Witness Inspection/Test 100% Hold Point for QC Inspection or Test H2 R1 R2 Sample Hold Point for QC Inspection or Test 100% Review of Documents sample Review of Documents RH1 100% Review and Approval of Documents RH2 Sample Review and Approval of Documents S Surveillance

Page 2 of 2