Professional Documents
Culture Documents
Scrapper Area( Receiver Area) Well Fluid Manifold(Oil Manifold) Gas Lift Manifold PRE HEATER Bath Heater Platforms On module Inter Connecting Piping Bath Heater Shed LP.Separator On module Inter Connecting Piping Test Separator On module Inter Connecting Piping Heater Treater Platforms On module Inter Connecting Piping Transformers, Bushes Heater Treater Shed 400M3 Crude oil Tanks 92M3 Test Fluid Tanks 1000M3 Crude Oil tank 2000M3 Effluent Water tanks Pump House Oil Recirculation Pumps Crude Oil Dispatch Pumps Crude Oil Start up Pumps Effluent Dispatch Pumps Pump House Shed Tank manifold Scraper Crude oil Launcher Area. Box Flare Water Seal Drum Platforms & ladders Insulation KOD & Pumps at Flare KOD KOD platform Pumps Flare ignition Panel & burners
Hydrotesting
4No.s Alignment completed Equipment insulation balance 4No.s Alignment & Inspection completed
under progres GI sheet order placed Expected 95% completed from 1st week of May Separators erected & aligned
GI sheet order placed Expected from 1st week of May hydro test expected by 10th april hydro test expected by 10th april hydro test completed hydro test expected by 10th april
for 4 tanks Nozzle fit up completed.2tanks 1 no. 20inch Roof nozzles to be replaced. Tanks painting to be start for 1 tank water fill up completed ---
(6 No. Pumps are erected on the foundation and aligned.) Start up pump received site
fabrication and Erection of supports under progress piping started Errection works started up to 10meters completed available at site Site manufacture Module Type Insulation despatched to site. Board to be installed available at site sand blasting painting completed
Theft problem
Process Utilities
(FGC Package)Presuure Reduction System Closed Blow Down (CBD)System Closed Blowdown Vessel Pumps DMF Dosing System Tanks Demulsfier Dosing Pumps
Fabrication under progress Valve pit Balance --Fab. Work u/p Dispatch to site by 05.04.2013 PDS preparation under progress at Mott --drawings by SGK PS in Rev.C submitted Comments received
Description
Demulsfier Unloading Pump PPD Unit PPD Dosing Tank PPD Dosing Pumps PPD Unloading Pump CI Unit CI Dosing Tank CI Dosing Pumps CI- Un loading Pumps Chemical Storage shed
Hydrotesting
drawings by SGK
PS in Rev.C submitted Comments received PS in Rev.C submitted Comments received afc awaited erection under progress
Common Utilities
Bore well Room Pumps Raw Water Storage Tank Pumps Potable Water System Potable Water Tank Pumps Soft Water Tanks with Pumps Soft Water Tank PUMPS Piping connection Water Softner Package POL Diesel Tank & Pumps Diesel Storage Tank Diesel Unloading/Transfer Pumps Storage Shed Loading/Un loading area platform Instrument Air Package & Plant Air Compressors AAir Dryer Receivers-Plant Air Receivers-Inst. Air shed SWD System Pumps OWS system Filter Pumps
One No.Installed. Room under construction PS to be submit RCC Sump Tank. available at site --NA available at site
RCC Sump available at site Site manufacture mfg under progress expected in 2nd week of April
fabrication work started theft problem GI sheet order placed Expected from 1st week of May Supply:- M/S Tushaco Pumps availble at site. Tag No.301-Perection completed Erected --erection completed erection completed erection completed erection completed GI sheet order placed Expected from 1st week of May Erction of purlins to be done Foundations are not started. theft problem ready to dispatch dispatched to site PS(ONGC)
Description
Pipe Rack Structure
Hydrotesting
F/W Tanks Fire water Pump House Fire Water Net work High Mast Light (Relocated) High Mast Light(New) Electrical Sub Station Temporary Pig Receiver Area D.G. Room Electrical Switch Yard Diesel Day Tank Wireless Telephone Tower Incinerator Package Hazardous Waste Pit Main Gate(electrically Operated Security Barrier) Control Room Transformer(Main) Transformer(Lighting) DCS/ESD Lighting Poles Instrumentation supports Fabrication CC TV Cameras CC TV Cameras Structure
cabling to be done
D.G.Set of capacity 600 KVA installed. Small pedastals with chain link fencing & gate is to be installed. Drg details are not available. Errection to be done
cabling to be done
Panels erected oreder placed Site fabrication Despatched to site Pole/Structure mounted.Drawing to be