You are on page 1of 20

Completed By Bob Kunz Superintendent Jon Vaslet Position Analyzed Entire Project New Revised

Title Corporate Safety Director

Analysis Date June 2010

Project Yale University School of Management

Date Approved June 2010

Approved By Bob Kunz

Required Personal Protective Equipment: Hard hat, ANSI Z-87 rated safety spectacles (clear lenses are required inside buildings), face shields are required where hazard of flying objects, chemical splashes or radiant energy exists), work boots (hard-toe as needed), long trousers, and shirt with stitched collar and minimum of 4 sleeves. Hand protection is mandatory when there is a recognized hazard see OSHA 1910 Subpart I Appendix B (consult MSDS and equipment / tool operating instructions for recommendations, for example). All workers must wear a Class II ANSI retro-reflective garment. Note: Goggles are required for overhead, demolition, abatement, chemical handling work. Equipment Required to Perform Work: Aerial equipment (i.e. articulating, boom lifts, ladders, supported and suspended scaffold, scissor lifts), cranes, mobile equipment (e.g. excavation, material handling, delivery) portable generators, pumps, pumps, compressors, small hand tools (e.g. drills, saws, grinders, torches, powder actuated tools, putty knives, hammers, and screw drivers), etc. Training Requirements: Dimeo Site Specific Safety Orientation, Supported and Suspended Scaffold (including aerial lift use), OSHA Construction 10-hour for all site workers, powder-actuated tool, and other as determined by job-specific contractor JHA. The contractor shall designate an appropriate number of Competent Persons for the activities to be performed on the captioned project see designation form in Contacts section of Site-Specific Safety & Loss Control Program. Each subcontractor is to provide project-specific JHA (and in some cases, task-specific) five (5) days prior to beginning work. Each subcontractor must designate a safety representative to perform a minimum of one project safety inspection per week see DCC Form No. 5.011A. The subcontractor foreman shall attend the weekly project safety committee meeting. The subcontractor shall provide a weekly safety meeting for their workforce. This project has a NO SMOKING (designated location only) and NO HORSEPLAY policy. Required permits and checklist include, confined space entry, crane and hoist use and lift plan (48 hrs prior to pick), excavation, hot work, lockout-tagout (LOTO), scaffold and steel erection checklist, guardrail or hole opening, roof access and off-shift work..

Activity
Public Safety

Potential Hazards
General public entering the construction area

Procedures
The construction site will be controlled with a fence fitted with scrim. Warning signage will be placed at each gate and at appropriate intervals along the body of the fence. Each gate will be closed or controlled to mitigate the possibility of non-construction personnel from entering the site. See DCC Procedure No. 5.010 Subcontractors must provide a spotter or flagperson to facilitate safe access and egress for delivery trucks and to ensure the safe passage of pedestrians. See DCC Procedure No. 5.010 Subcontractors shall protect the public from their operations occurring on, or adjacent to site. The subcontractors shall consider use of the following means and method: Work zone constructed in accordance with MUTCD Part VI 2003 Edition Safety Nets

Pedestrians struck by construction equipment.

Pedestrians struck by falling object; exposure to optical light or airborne substances; or slip, trip or fall.

Project No. 074-10

Job Hazard Analysis No. 1

Page 1 of 20

Activity

Potential Hazards

Procedures
Welding screens Housekeeping Signalman nd rd 2 or 3 shift work Worksite inspection Dust suppression Tethered tools Tarps Securement of stored materials Covered walkways Etc The subcontractors shall not create an atmosphere or environment that may create a hazard or nuisance to any abutter to the project. See DCC Procedure No. 5.010 An evacuation plan will be established, provided to site-workers during orientation and weekly safety meeting, posted on the site bulletin board, and updated as required. Note: Each subcontractor shall have a sufficient amount of first aid supplies, and spill kits on-site to take a defensive position. DCC provided fire extinguishers are intended for emergency use only not for hot work fire watch. Subcontractors shall provide support without delay or concern for reimbursement the response that is appropriate and necessary to mitigate all imminent danger situations that may arise during the execution of their work. It is understood that maintaining, creating, or allowing access to the entire length of the tunnel shall be given priority over any other operational activity in the event of an imminent danger situation. See DCC Site Specific Safety & Loss Control Program tab no.1 CONTACTS, and no. 2 EVACUATION, and DCC Policy No. 5.508. Dimeo is committed to providing a workplace that has a level of awareness and worker education that is consistent with the DRUG FREE WORKPLACE ACT OF 1988. The use, possession and working under the influence of controlled substances and / or alcohol create unnecessary risk and will not be tolerated. See DCC Procedure no. 5.002, 5.004, 5.005 and 5.007, and Program no. 5.109. Dimeo will not tolerate sexual harassment or discrimination of any kind. Do not stare, whistle or otherwise create an uncomfortable work environment. The posting of materials (snap-on tool calendars or air fresheners depicting a scantly clothed person, for example) can create an uncomfortable work environment. These materials must be promptly removed when discovered. The use of foul language, clothing with

Emergency Response

Fire, explosion, building collapse, spills for example.

Controlled Substances and Alcohol: -possession -use -under the influence

Creates unnecessary risks of accidents, theft and violence

Harassment

Hostile work environment

Project No. 074-10

Job Hazard Analysis No. 1

Page 2 of 20

Activity

Potential Hazards

Procedures
offensive language, derogatory or slang remarks will not be tolerated. See DCC Procedure no. 5.010 The subcontractor shall designate and identify a competent person for Confined / Enclosed Space activity. All employees assigned to this activity must be properly trained. The subcontractor shall contact local fire department to plan for Confined / Enclosed Space work. It is essential that capabilities of local responders be identified. Air monitoring, mechanical air exchange, personal fall arrest equipment, rescue equipment, protective clothing, ladder and additional personnel may be necessary. Control stored energy, and review MSDS and equipment manuals for warnings concerning use of product(s) and equipment in confined or enclosed space, for example: - Flammable and / or toxic vapors can quickly accumulate and create a flammable or lethal atmosphere in confined or enclosed spaces; - Carbon monoxide generated by a combustion or diesel engine can quickly accumulate and become lethal in a confined or enclosed space. The subcontractor shall ensure that CO emissions from equipment do not exceed the EPA NAAQS standard beyond the limits of the project, nor 35 PPM within the limits of the project. - Subcontractors shall take whatever measures are necessary to ensure that the public and site workers are not exposed to atmospheres containing hazardous vapors. - Material can become bridged in a cement silo and entrap workers entering space, if proper safe guards are not taken, for example. - Equipment can be accidentally started with worker inside, if proper safeguards are not taken. Note: Compressed air shall not be utilized for to mechanically exchange air. Develop task specific JHA and prepare and submit DCC Confined Space Pre-Entry Checklist Form No. 5.103A. See DCC Procedure No. 5.007, Policy No. 5.051 and Program No. 5.103 and 5.107. Subcontractors shall erect and maintain dust barriers prior to start of demolition work. Open building (e.g. exterior doors / windows, walls) when undertaking general demolition, if possible. Consider the use of mechanic ventilation to foster air exchange. The exhaust air shall not create a hazard to site workers or the public. No dry cutting of any CMU, STONE, BRICK,

Confined / Enclosed Space Work (in or around): -manholes -metering / Test pits -HVAC equipment -tunnels -dewatering equipment -etc.

Hazardous atmosphere: -oxygen deficient -flammable -toxic Stored Energy: -electric -mechanical -pressure Engulfment / Entrapment Temperature Extremes Etc.

Hazardous Substances:

Inhalation of airborne dust (respirable and total)

Project No. 074-10

Job Hazard Analysis No. 1

Page 3 of 20

Activity

Potential Hazards

Procedures
and CONCRETE will be allowed. All cuts will be done by using wet saws or equipment fitted with HEPA vacuum attachments. Place mortar mixing operation in, or create an area that will minimize the amount of dry cement that becomes entrained by wind. Use water spray to keep dust under control where mobile equipment is operating. When sanding or grinding (wood, plaster, concrete, etc) engineering controls (HEPA vacuum, for example) are preferred over respirators to protect workers. See DCC Procedures No. 5.006 and 5.010, and Policy No. 5.070 and 5.072. Read all MSDS sheets, and labels, all MSDS must be filed on site with DIMEO. Contact DCC prior to work near air intake ducts. Combustible or toxic vapors can travel beyond the work area via the air handling system. Wear appropriate PPE and label secondary containers. Keep chemicals in secured area. Use Engineering controls where possible. Mobile equipment operating within the tunnel and foundation area must be equipment with Tier 3 engines and emission scrubbers and / or catalytic convertors. The State of Ct anti-idling regulations shall be observed. Use mechanical ventilation to induce air exchange see Confined / Enclosed Work Space above. See DCC Procedure No. 5.006 and 5.010, and Policy No. 5.070 and 5.072. All combustible chemicals (e.g. solvents, strippers) are to be stored in a metal fire rated cabinet outside of the building. All chemical impacted rags or towels must be segregated from ordinary combustible waste and removed from site daily. See DCC Policy No. 5.057. Read all MSDS sheets, and labels, all MSDS must be filed on site with DIMEO. Portland and Masonry cement can cause chemical burns proper PPE shall be worn to mitigate this hazard. Eye wash stations are recommended. Wear appropriate PPE and label secondary containers. Keep chemicals in secured area. Use Engineering controls where possible. Chemicals may not be stored within any building without the prior consent of DCC. Barricade area around application area to prevent access to potential overspray area. See DCC Policy No. 5.070

Inhalation of toxic vapors

Fire hazards

Contact with chemical

Project No. 074-10

Job Hazard Analysis No. 1

Page 4 of 20

Activity
Housekeeping

Potential Hazards

Procedures
All abated material is to be disposed of properly later than the end of each shift. See DCC Procedure No. 5.006 and Policy No. 5.059 and 5.062. Equipment with obstructed view to rear must be equipped with an automatic reverse activated alarm audible above the surrounding noise level. Bi-directional equipment must have audible alarm. The OEM equipment provided on each piece of equipment must be operational (e.g. lights, horn, windshield wipers, safety devices). A rear view mirror and side view mirrors shall be provided. Swing radius barricades shall be established with three decals affixed to each end and center of the counterweight. Each spotter or flagperson must wear an ANSI Class II [class III for night operations] retroreflective garment. The use of hand signals alone is not permitted. Ground personnel shall maintain eye contact with equipment operators and a respectful distance from equipment while working and walking near mobile equipment. Work zones shall be established to create a separation between active and inactive work areas See DCC Policy No. 5.052 and 5.068. Seatbelts must be provided and worn on each piece of mobile equipment that is equipped with seatbelts and / or a roll-over protective structure (ROPS). No ROPS shall be removed from a machine without a plan designed by a professional engineer. The plan must be reviewed by DCC. A physical berm(s) must be constructed along elevated ramps or roadways. Each dump site must be provided with a stop log, bumper block or curb to prevent over travel. This safety device shall be at least axle height. The dumpsite must be periodically inspected by a competent person to ensure that it has not been undermined or soil too soft. Dump trucks shall not dump side by side, unless separated by at least the length of the truck. Equipment may only be operated by a properly qualified (and licensed if required by jurisdiction) worker. Equipment (combustion engine) shall not be allowed to idle for longer than 5 minutes. The contractor shall monitor equipment emissions utilizing appropriate data logging capable instruments. The instrument(s) shall be utilized by a qualified person who has been trained to utilize such instrument(s) and react in

Mobile Equipment Operation / R&M: -delivery trucks -material handling -excavation

Struck by equipment

Upset equipment

Unqualified operator

Hazardous atmosphere

Project No. 074-10

Job Hazard Analysis No. 1

Page 5 of 20

Activity

Potential Hazards

Procedures
an appropriate manner to abate potential hazards. A monitoring report shall be prepared and provided to DCC on a daily basis. Mobile equipment operating within the tunnel and foundation area must be equipment with Tier 3 engines and emission scrubbers and / or catalytic convertors. The State of Ct anti-idling regulations shall be observed. See DCC Procedure No. 5.006. Equipment (e.g. buckets, forks) must not be used to convey personnel unless designed to do so. Workers (truck drivers and placement personnel) shall not climb up or on delivery chutes. Personnel may not stand on or in dump bodies while being loaded. Personnel may not ride in truck beds or on saddle tanks, or exterior ladders.

Fall from equipment

Electrocution / Explosion Unstable ground

See Electrical section. Equipment ground pressure rating must be compared with ground (paved and unpaved) / floor (slab on grade and elevated) load ratings, prior to mobilization of equipment. The use of mud mats and outrigger cribbing will decrease ground pressure imposed by equipment. The existence of subterrarean features shall be identified to determine ground stability. A competent person must inspect excavations, embankments, and stockpiled material to ensure that stability of equipment operating near or on those areas is not adversely impacted. The operator must maintain an adequate supply of spill response materials including, pads, booms and drums to ensure that a defensive position is immediately taken. The impacted area must be cleaned by the operator and an incident closure report provided to DCC. The subcontractor shall retrofit equipment with biodegradable hydraulic oil while perform any site enabling work (i.e. in and around the tunnel) The operator (responsible party) must contact the local jurisdiction regarding the incident. See DCC Procedure No. 5.006 and Policy No. 5.060 and 5.062. The mobile equipment shall be fitted with exhaust muffler. Equipment may not be started prior to 7:00 AM. Equipment may not be staged outside the project prior to 7:00 AM without the prior consent of DCC.

Spills (fuel, lubricating fluids, hydraulic fluids, anti-freeze, etc)

Noise

Project No. 074-10

Job Hazard Analysis No. 1

Page 6 of 20

Activity
Excavation / Backfill: -utility -underpining -structural concrete / masonry -pile driving -mechanical excavation or demolition -etc. Soil collapse

Potential Hazards
Underground utility damage

Procedures
The subcontractor shall identify the name of the competent person that has been designated to conduct the excavation related (excavation / backfill / utility / formwork) activity. Provide DCC with CBYD call ticket ID number and start time. DCC requires 30 day re-mark requests. The subcontractor shall provide DCC with the engineering data that has been prepared for all earth retention and / or support systems that will be utilized on the project. The data must be prepared by a PE. See DCC Policy No. 5.054 and Form 5.054A, and a job specific JHA. The subcontractor shall monitor vibration created by vibratory compaction, sheet or pile driving, blasting, and/or mechanical demolition; rock excavation shall be monitored with a seismograph. Additional measures may be required depending upon the site specifications. Levels shall be maintained within the limits established by contract or the USBM Report No. RI 8507, or project specifications, whichever is more conservative. Use the MUTCD Part VI 2003 Edition to establish traffic, pedestrian, bicyclist control plan. Use of road plate must be done in accordance with a plan prepared by a qualified person. The excavation shall be protected to prevent pedestrians, workers and equipment from entering the open hole. (Note: Obtain local municipal excavation permit, if required) A qualified person must assess the structural integrity of structures that area adjacent to, or above an excavation prior to the start of work. Structure(s) must be properly supported during the backfill process. It may be necessary to backfill in lifts and to compact the lifts prior to the continuation of backfill operation. Consequently, the engineer of record or owner of the facility must be contacted prior to backfilling so that the proper procedure can be identified. 100% fall protection is required when workers are exposed to a fall of 6or greater, irrespective of their trade or activity. For example: Persons loading and unloading materials / supplies / demolition debris from a scaffold platform must be tied off while the platform gate is open. A suitable guardrail system, personal fall arrest system (5000 lb anchor point per person, anchor attachment, lifeline, and full-body harness), and secured adequately constructed covers are considered acceptable means of protecting elevated workers (Note: PFAS are

Vibration

Open hole

Structure collapse / failure

Elevated Work: -all trades

Fall from structure

Project No. 074-10

Job Hazard Analysis No. 1

Page 7 of 20

Activity

Potential Hazards

Procedures
typically rated for 310 lbs inclusive of tools and equipment). Do not terminate a lifeline with a knot. A termination plate or thimble eye and snaphook shall be utilized. Use a double lanyard to maintain 100% contact with an anchor point. Do not tie a lanyard back onto itself unless it has been designed for that purpose, for example Miller BackBiter. Evaluate the total fall distance that a worker is exposed see guide below:

Each subcontractor exposed to falls must prepare a job-specific JHA that describes the fall protection system that will be utilized. The subcontractor shall obtain a Guardrail and Floor / Roof Opening Permit prior to removing guardrails or covers, and prior to creating holes. Subcontractors shall prepare a rescue plan. See DCC Policy No. 5.056 for guidance. Subcontractors shall provide any control necessary to ensure that falling objects do not represent a hazard to workers or the public. The following control may be utilized: Covered walkways to and from the building egress points Nets Mesh set along perimeter and interior guardrails Toeboards Material stored +6 from floor edge, or +15 from roof edge Tethered tools Etc Subcontractors shall provide all equipment and fire watches and take all precautions necessary to eliminate the possibility of a fire / explosion. Obtain hot work permit from local jurisdiction, owner, and DCC prior to beginning work. The hot work permit must be updated as may be necessary. Ensure that equipment (gauges, hoses, fire extinguishers, tanks in secured and upright position) is duty ready condition. Inventory the area for combustibles (e.g. liquid, lint, dust, oil, or pipes / containers / duct work that may have previously contained combustible material).

Falling objects

Fire Prevention / Protection: -demolition -make safe work -excavation

Arc welding, uncontrolled sparks, open flame, heat transference. Note: Fire / Explosions can occur during welding, cutting (oxy/acetylene or abrasive blade), grinding operations, or in the presence of an open flame

Project No. 074-10

Job Hazard Analysis No. 1

Page 8 of 20

Activity

Potential Hazards

Procedures
Do not bring compressed gas bottles / tanks into a confined or enclosed space. Remember to turn the bottles off, remove the hoses from confined or enclosed space, and to purge the fuel from hoses when finished at break, at lunch time and at the end of the shift. Fuel bottles (empty or full) may not be inside of the building or job boxes, at anytime, except for those in use. The stored bottles must have caps in place. Combustibles like architectural form liners, blankets, and wood forms will ignite when exposed to hot work (arc welding, uncontrolled sparks, open flame, heat transference, for example). Only fire retardant tarps shall be utilized. The tarp shall have fire retardant stamped on the material so that it easily identifiable. Note: Temporary heating devices shall not be utilized until DCC has reviewed the application and coordinated same with project specifications. See DCC HOT WORK PERMIT and Policy No. 5.057 and 5.077. Maintain and review Material Safety Data Sheets (MSDS). Provide a copy of MSDS listing and MSDS to DCC. Wear appropriate PPE and label secondary containers. Keep chemicals in secured area. Chemicals may not be stored within any building without the prior consent of DCC. Use of these materials around building air intake units must be coordinated with DCC, prior to the start of work. KEEP FIRE HYDRANTS (10 on either side) and EXTINGUISHERS clear of stored / staged material. Compressed gas cylinders must be stored outside of the building envelope in an upright and secured position with valve stem protecting caps in place. The fuel gases must be separated from oxygen by a distance of 20 or by a 5 tall 1 hr rated fire wall. The cylinders shall be protected from accidental contact by mobile equipment. See DCC Policy No. 5.050, 5.507, 5.061, 5.063, and 5.077. Work impeding tunnel access will require deliberate planning with abutters and the City of New Haven Fire Department. Subcontractors shall cooperate fully with the fire prevention / protection plan that is developed for this work activity Equipment operators must be properly qualified and license (if required by jurisdiction). If outriggers are utilized, employ them per the OEM operators guide. Typically, the outriggers

Poor housekeeping

Collateral structures

Crane and Material Hoisting: -crane -telescopic handler -etc.

Upset hoisting device Falling material Struck by

Project No. 074-10

Job Hazard Analysis No. 1

Page 9 of 20

Activity

Potential Hazards

Procedures
must be fully extended with the rubber off the ground. The outrigger pads must be independently cribbed. The amount of cribbing is determined by this rule-of-thumb: cranes capacity / 5 = # of sq ft required under each outrigger pad. Therefore, a 35T hydraulic crane would require 7 sq ft of adequately sized cribbing under each outrigger pad. Each outrigger shall be cribbed so that it can take the entire weight of the crane. Make certain that supporting surfaces (i.e. bridges, concrete slabs, etc) can withstand the maximum intended load (weight of machine plus load) Check for subterranean defects (vaults, drainage pipes, etc) and stability of adjacent earth retention and / or support systems (slope, shoring, sheet, etc.). Coordination and scheduling is important, due to potential need to relocate personnel within an occupied structure, block or restrict building egress points, and develop and implement a control traffic plan, for example. Barricade areas surrounding these areas to prevent pedestrians and workers from being struck by falling material. Fuel must be emptied (diesel, gasoline) or removed (compressed gas cylinder) from mobile equipment prior to hoisting over a building. Daily inspections shall be completed and documented. Each defect affecting the safe operation of the equipment must be corrected prior to the equipment being placed back into service. The equipment must be tagged out-ofservice until it has been properly repaired. Cranes must be inspected annually by a qualified third party. The annual inspection certification shall be on the crane. (Note: Hoists cant be modified without the written consent of the equipment manufacturer.) Calculated the weight of the load, including rigging running rope and blocks. Do not exceed capacity of hoist and / or rigging. Use tag lines to control load. Consider the use of a double choke hitch to maintain 360 degrees of friction on loads such as a bundle of scaffold cross bracing, for example. Winches shall not be utilized to hoist materials. Base mounted drum hoists shall be utilized in accordance with ANSI standards. Cranes operating above 200 shall obtain authority from the FAA, and or any local jurisdiction that has authority over such equipment. The crane shall be equipped with FAA standard red light(s) and flag. Subcontractors shall provide all necessary FAA

Project No. 074-10

Job Hazard Analysis No. 1

Page 10 of 20

Activity

Potential Hazards

Procedures
permits and markings at no cost. Do not attach rigging to forks. See DCC Policy No. 5.068, 5.069, 5.073 and CRANE USE PERMIT (Must be received 48 hours, or 2 business days prior to tentative lift date). See Electrical section. PPE and original equipment manufacturer (OEM) guards shall be utilized and in place guards shall not be cheated. Barricade work area. Knowledge of material handled and capabilities of equipment. Any person handling a small tool shall be trained how to use the equipment prior to use. Powder actuated tool operators shall be trained by a qualified person. The certificate of training shall be on their person. The tool user shall also be familiar with how to safe guard the tool if it malfunctions. This may include clearing or repairing the tool, as well. Follow OEM instructions for cleaning / clearing pressurized paint spray equipment. Follow OEM instructions for cleaning / clearing mortar mixer and silo screw conveyors, for example Remember to lockout and tagout equipment prior to repair and maintenance. Make certain that RPM ratings of drill bits, saw blades, cutting and grinding wheels are compatible with tool. Specify tool adjustments. See DCC Policy No. 5.066 and 5.071. Wear gloves appropriate for the activity. Persons are to wear gloves when cutting metal lath/ stud materials Wear the appropriate gloves [cut / puncture resistant / anti-vibration] and long sleeve shirts for protection when utilizing tools and handling rough, sharp, or puncturing materials. The trade contractors JHA must address hand protection. See DCC Policy No. 5.070. Physical overhead protection must be installed where the conveyor crosses over an active doorway or walkway. Skirts should be utilized to minimize spillage. All moving rollers (return and idler), pulleys (tail, gravity and head), exposed belt and drive gears, chains and belts shall be guarded. Stop cords shall not be used exclusively. Lockout / Tagout (LOTO) procedures shall be established and utilized during maintenance and repair of

Electrocution / Explosion Small Tools and Equipment: -nail guns -powder actuated tools -saws -drills -chipping Guns -pneumatic tools -painting -pressure / steam cleaning equipment -waterproofing -etc. Personnel injury: -unqualified operator -adjacent worker(s) -pedestrian

Material Handling: -sprinkler -electrical -HVAC -ceiling -excavation

Cut hands and fingers

Materials falling from conveyer Caught in unguarded rollers, chains, and gears

Project No. 074-10

Job Hazard Analysis No. 1

Page 11 of 20

Activity

Potential Hazards

Procedures
equipment. The conveyor belt shall not be ridden or walk upon by any person. RI requires a licensed operator. See DCC Policy no. 5.066 and 5.071. Barricade area surrounding work when hoisting equipment over head. Maintain good housekeeping to prevent material from falling from elevated surface or uneven ground condition. Torch cutting can cause oxidized metal and concrete to splatter and spall. Wear appropriate PPE (listed above), including without limitation, welding gloves and goggles (and face shield when welding). This requirement extends to helpers. Must wear a full face shield in addition to safety the requisite safety glasses when chipping or saw cutting. < 20 material drop barricade with red danger tape to prevent pedestrians / workers form being struck by debris. Due not compromise an active doorway / walkway w/o prior coordination with DCC. 20 material drop use a debris chute into a dumpster. The dumpster needs to be maintained to ensure that door is closed and the material not overfilling. See DCC Policy 5.062. Ensure truck is on firm level ground. Chock the wheels. Stand to side of chain binders, or nylon web ratchet binders, and inspect the load for shifting or (and remove) loose objects prior to releasing. Do not stand between loaded trailer and material handling equipment. Use a ladder to climb onto the trailer. Access the loaded unsecured cargo from behind, this will minimize any possibility that a worker will become entrapped. Ensure that the cargo is secured to the truck or mobile equipment that may be positioning it within the project limits. A Competent Person must conduct daily inspections and ensure that employees adhere to good housekeeping practices, for example: Keep oil pans in place when cutting machines are in use. This will protect existing flooring from oils, and mitigate the likelihood of worker exposure injury. Maintain all conduits, pipes on racks, to minimize the hazard of tripping, keep all pipes against walls out of walking areas. Maintain control of concrete slurry generated during wet saw cutting. The slurry may create a slippery underfoot condition due to suspended fines and / or icing conditions. Mix plaster in a designated areas, to minimize water spillage through out job clean this area

Falling / flying objects

Struck by cargo from trailer

Physical Hazards: -all trades

Slip / fall on same elevation

Project No. 074-10

Job Hazard Analysis No. 1

Page 12 of 20

Activity

Potential Hazards

Procedures
a minimum of once per shift. Protruding rebar needs to be protected to mitigate impalement or laceration hazard. Locate extension cords, fuel gas, air lines, and welding leads so that they dont become a tripping hazard. Extreme care must be taken by workers entering and moving about the construction site following a deep frost, ice or snow storm to avoid slipping and falling. Workers should prepare the affected work area with friction or ice melt material prior to beginning work. Do not take long strides walk with toes pointed outward. See DCC Procedure No. 5.004, 5.005 and Policy No. 5.062. Hearing protection may be required to reduce worker exposure to the OSHA PEL see chart below:

Excessive noise exposure (continuous and impact)

Noise can also be controlled (not eliminated) with: quieter, modified (with consent of OEM), and well maintained equipment, barriers / baffles, and work activity schedules (when possible). The subcontractor shall perform their work so that it is not in conflict with any local jurisdictional ordinances, rules, regulations, policies. See DCC Policy No. 5.061 Potential sources of stored energy must be identified and isolated before performing any demolition. Disconnect power cords prior to repair electric tools or equipment. Pull the spark wire prior to repairing combustion equipment. Turn air lines off, run the air out of tools or equipment, then disconnect the air line from source prior to repair air tools or equipment. Review manufacturers instruction prior to repairing or maintaining tools and equipment. Electrical contractors must follow NFPA 70E guidelines. Obtain necessary authorization from owner and DCC prior to starting work. See DCC Policy No. 5.066. Subcontractors shall protect workers and the public from optical energy. Do not look directly into or at laser equipment.

Stored energy Note: Serious Injury can occur when cutting steam lines, electrical conduit, and water lines (potable, fire protection, waste) without first de-energizing the system.

Optical radiation

Project No. 074-10

Job Hazard Analysis No. 1

Page 13 of 20

Activity

Potential Hazards

Procedures
Turn laser equipment off when not in use. Wear eye protection if required. Do not work with, or look at welding or cutting activity without proper eye and face protection, for example: cutting goggles (and opaque face shield when welding). This requirement extends to helpers. See DCC Policy No. 5.070 and 5.077. Subcontractors shall provide their own task lighting. Install adequate temporary lighting as required. Ensure that the lighting is maintained in safe operational condition. The lighting must be on a separate circuit. The bulbs must be shielded to prevent accidental contact by debris and small hand tools, for example. Ensure that small tools are in proper working order. The use of vibration isolation gloves will greatly reduce the physiological affects of this equipment. See DCC Policy No. 5.070. Drink water regularly (every hour), avoid hot food and drink, and drinks containing caffeine. Avoid wearing tight fitting or colored clothing. Provide hot weather (exhaustion, cramps, stress) awareness training to all workers exposed to hot environments. Layer clothing and cover exposed skin. Wear insulated clothing and footwear. Provide cold weather (frostbit and hypothermia awareness training to all workers exposed to cold environments. Ensure that mobile equipment, hoisting operations, ladders, scaffold (including enclosures), and aerial lifts are designed to operate in the anticipated conditions. Halt any operation that may be adversely impacted. Secure tarps, materials (decking, plywood, Styrofoam), and form panel, for example to prevent overturning, flying or upset. Erection of trusses and other structures should be planned in conjunction with the extended local weather forecast to ensure that an adequate weather window exists. A severe weather plan shall be provided, which addresses conditions requiring the work cessation. The plan shall address as a minimum: lightning, wind, snow, fog.

Inadequate lighting

Vibration The operation of vibration generating tools (chipping guns and hammer drills, for example) can create operator fatigue.

Extreme environment: -heat stress

Extreme environment: -cold stress

Extreme environment: -wind See the Force of Wind for Severe Velocities below:

Crushed hands / feet

Keep hands and feet from underneath elevated material - use blocking / cribbing and jack stands to support material, and tag lines / push sticks to control elevated material.

Project No. 074-10

Job Hazard Analysis No. 1

Page 14 of 20

Activity

Potential Hazards

Procedures
PPE like hard toe work boots can also mitigate a foot crushing injury, for example. Utilize adequately sized dunnage under equipment, materials and supplies to mitigate possible crushing injuries. Cut material into sizes that is manageable for available manpower and material handling equipment to safely handle. (Note: Use stretching and proper lifting techniques.) Use hoisting equipment when that is possible. If that is not possible, break down that load into its smallest components to limit the amount of weight that is physically handled, or ask for assistance form a co-worker. Use the proper lifting techniques: Test load: Is it frozen to ground? Is it to heavy for one person? Plan the move walk the path first Keep the load close to your body Keep your back straight Turn feet outward and push buttocks out Bend knees Keep your chin up, and Breathe out as you lift

Ergonomics

Structural Steel Work: -new

Struck by falling object Structure collapse Slip / trip and fall

Pre-activity meeting must be held with DCC obtain certification (anchor bolts / 75% concrete curing) and site layout. The skybridge will be erected off-site and installation performed in conjunction with authority provided by the City of New Haven and DCC. The subcontractor shall provide DCC with a written Site-Specific Steel Erection Plan, which includes: -site layout (crane and material placement) -crane permit -hoisting and rigging -structural steel assembly -column anchorage -beams and columns -open web steel joists -systems engineered metal buildings -falling object protection -fall protection, and -training. JHA required for each task. Rigging must not be utilized as part of a PFAS. See DCC Policy No 5.076 and Crane Permit. The subcontractor shall ensure that all personnel working (erecting, dismantling, using, maintaining, repairing) on scaffold are properly trained. Ensure that all scaffolding equipment has been inspected and that it meets or exceeds OSHA standard. At least one competent person shall be

Scaffolds -baker -supported -suspended -etc

Competent person -erection -use -dismantling

Project No. 074-10

Job Hazard Analysis No. 1

Page 15 of 20

Activity

Potential Hazards

Procedures
designated by each subcontractor erecting, dismantling or using scaffold system. A competent person shall be assigned to work with each scaffold operation. At least one competent person shall inspect the scaffold prior to use each shift. The inspection shall be recorded on a scaffold inspection tag located at each access point. See DCC Scaffold Checklist and Policy no. 5.075. Subcontractors shall attend whatever coordination and training sessions that may be required as a result of multi-trade scaffold utilization. Subcontractors shall accept full responsibility as users when on scaffold. This responsibility includes all provisions that OSHA has established for scaffold use and inspection. And shall provide whatever PPE and fall protection equipment may be required while utilizing the equipment. Subcontractors shall ground mast climbing scaffold when winds exceed 29 mph and at the end of the shift on Friday. 3.5 toe-boards shall be installed and maintained on each scaffold platform. Mesh is required between the handrail and toeboards to further minimize the possibility of falling objects. Materials and supplies shall not be allowed to accumulate on the platform higher than the toeboard. When bumping planks up or down, for example the trade contractor must make sure that all safety precautions are taken. Subcontractors must close off ends of staging with proper guard rails, and toe boards when planks are removed. Scaffolds shall be designed by a professional engineer and shall be constructed and loaded in accordance with that design. A scaffold plan must be prepared by a qualified person and submitted to DCC prior to erection. The scaffold system must be erected and dismantled in accordance with the plans and / or instructions prepared by the qualified person. Scaffold must be properly inspected by each trade contractor utilizing the system. The following inspection tags shall be utilized: GREEN Safe YELLOW Conditional Use RED Unsafe Do Not Use Supported scaffold The supporting surface must be capable of supporting the dead load and 4 times the intended load applied or transmitted to it (live load). A qualified person shall determine that the supporting surface is adequate, for example: a distribution plate may need to be

Multi-trade

Falling objects -scaffold components -materials -supplies -debris

Scaffolding failure

Project No. 074-10

Job Hazard Analysis No. 1

Page 16 of 20

Activity

Potential Hazards

Procedures
installed on an elevated concrete floor in order to distribute the dead and live loads of the erected scaffold system. Suspended scaffold Direct connections to roofs and floors, and counterweights used to balance adjustable suspension scaffolds, shall be capable of resisting at least 4 times the tipping moment imposed by the scaffold operating at the rated load of the hoist, or 1.5 (minimum) times the tipping moment imposed by the scaffold operating at the stall load of the hoist, whichever is greater. Each suspension rope, including connecting hardware, used on adjustable suspension scaffolds shall be capable of supporting, without failure, at least 6 times the maximum intended load applied or transmitted to that rope with the scaffold operating at either the rated load of the hoist, or 2 (minimum) times the stall load of the hoist, whichever is greater. The stall load of any scaffold hoist shall not exceed 3 times its rated load. Suspended scaffold platforms shall be grounded or secured when not in use, especially in extreme weather conditions. Wire rope clips and thimbles may be utilized to form eyes to terminate tiebacks, but only if they are appropriately sized, installed, and inspected (visually and physically torqued). Note: Suspended scaffold systems must have inspection tags at anchor points and platform. The contractor must prepare and submit a fall protection plan to DCC. The activity is controlled by a 6 fall protection rule. Disconnect all equipment, and use job specific lockout / tagout (LOTO) procedures. Use of all proper PPE (NFPA 70E protocol is encouraged), in conjunction with nonconductive barriers, equipment, and tools. Each contractor performing work (tie-in, cut-out, or troubleshooting) on energized (irrespective of voltage) systems should submit their project specific (LOTO) procedure to DCC, so that DCC can coordinate work with owners, if required. Only qualified workers may perform this work. Live conductors shall be properly covered duct tape and cardboard may not be utilized to cover junction boxes or openings in breaker cabinet, for example. See DCC Policy no. 5.053 and 5.066. Underground utility locations must be marked prior to the start of work. Each underground utility must first be located by non-mechanical means when the proposed excavation is located within safety envelope of the utility. No equipment shall operated closer than 10 to

Fall protection

Electrical

Electrical contact

Electrocution / explosion

Project No. 074-10

Job Hazard Analysis No. 1

Page 17 of 20

Activity

Potential Hazards

Procedures
overhead power lines <50kv, an additional 4 must be added to clearance distance for each 10kv 50 kv. Mobile equipment may safely pass under (transit only) overhead electric lines with a minimum clearance distance of 4 (lines <50kv) and 10 (lines 50kv to 345 kv). Commonwealth of MA requires dump trucks to have a visible and audible alarm within the cab to warn drivers when body is elevated. This BMP should be adopted on jobsites were overhead line exposure is present. Flags installed by utility company and ground positioned signs indicating the presence of overhead utilities is also considered proactive. Workers must be trained to handle emergency situations. Verify that switch gear panels are not back feeding other buildings or panels. See DCC Policy no. 5.066. Double cleated ladders provide egress for 25 or more workers from an elevated work area, and allow workers to travel in two (2) directions. Construction considerations Seasoned lumber with moisture content of no more than 19%. Lumber to have a minimum fiber stress of 1200 psi. Cleats (rungs) are to be 2 by 4 nominal stress grade dimension lumber and relatively clear of knots (tight with side face of <3/4 in diameter, no more than 2 in a cleat that are more than 6 apart, nor located closer than 1 from the cleat edge).

Shut downs

Ladders / Stairways

Job built ladders inadequate construction

The slope of the grain of the cleat to a line parallel to the sides of the cleat should not be greater than 1 in 12.

Ensure that cleats are continuous and extend full width of double cleated ladders. The 16 to 20 wide (measured inside the side rails) cleats shall be secured with 12D common nails, 3 to each rail. Use 2 by 4 filler blocks to fill the approximate 81/2 gap between cleats Spliced rails shall not be utilized.

Project No. 074-10

Job Hazard Analysis No. 1

Page 18 of 20

Activity

Potential Hazards

Procedures
Side load capacity of the rails is a function of working length and pitch, as follows: 2 x 4 if working length is 12 and pitch. 2 x 6 if working length is >12 and pitch. Note: A job built wooden ladder shall not exceed 24 feet in length. Portable ladders shall be rated type 1A or greater. Ensure that each manufactured portable ladder has all required decals. Refer to DCC Policy No. 5.065. Temporary stairs must be installed at 30 to 50 degrees from the horizontal. Stairway landings must be 22 wide and 30 deep at every 12 or less of vertical rise. Stairway parts must be free of dangerous projections, such as protruding nails and screws. Stairways with more than 3 treads or 30 in height must have hand rails. The open side(s) of stairways must be equipped with a handrail / midrail, while stairways with walls on both sides shall be equipped with only a handrail. The handrail surfaced to prevent injury and clothing from snagging. The handrail have 3 of clear space from the wall or other objects and shall be capable of withstanding 200 lbs of force when applied within 2 of the top edge in any downward or outward direction, at any point along the top of the handrail. Midrails when used shall be located midway between the top of the handrail and the tread. Screen material and intermediate vertical members can be used in lieu of midrails when installed in accordance with OSHA regulations. The height of handrail must be between 36 and 37 above the height of the stairway tread. The treads shall be secured and extend the full width of the stairway. The tread depth and riser height of temporary stairs shall not deviate by more than in any system. Landings must extend and additional 20 beyond the swing of any door or gate. The full width and depth of metal pan landings and tread shall be temporarily filled with wood or other solid material. Correct slippery conditions immediately. Stairways shall be kept free of debris and other obstructions. The competent person (operator) must conduct a pre-shift inspection of the lifts tires, fluid levels, outriggers (if provided), guardrails, gates, operators manual, and to be certain that the key is in ground controls, for example.

Manufactured ladders: -portable -fixed

Stairway -improper maintenance -improper temporary construction

Aerial / Scissor Lifts

Defective equipment

Project No. 074-10

Job Hazard Analysis No. 1

Page 19 of 20

Activity

Potential Hazards

Procedures
Contractors shall be certain the lifts have had all periodic inspections recommended by the manufacturer. The equipment should be delivered to site ready for use with a documented inspection by the rental house. Contractors shall provide DCC with evidence of competency for each aerial lift operator. Set traffic control in accordance with the MUTCD Part VI, if required. Inspect the site for hazards, such as, holes, drop-offs, bumps, debris, overhead power lines and other obstructions. The manufacturer may require that outriggers be fully deployed. Be certain that there is adequate space and bearing for all of the pads to be fully deployed and supported. Barricade the work area underneath the aerial lift, if required. Look for overhead power lines see Electrical section. Always close lift platform chains or gate. Keep both feet on floor of platform. Do not lean over guardrail. Transfers by personnel from an aerial / scissor lift to an elevated structure may only be undertaken with the written approval and conditions set forth by the equipment manufacturer. Do not modify equipment without the written consent of the manufacturer. Extreme weather, such as, wind can drastically effect the safe operation of aerial lift equipment check the manufacturers manual for limitations of use.

Unsafe worksites

Improper use

Project No. 074-10

Job Hazard Analysis No. 1

Page 20 of 20

You might also like