DAILY REPORT

DATE: TIME: 10/12/2011 (Wednesday) 8:30am -5:30 pm

Technician/s

Designation

Area
Common

Activities/Complaints
Conducted roving, testing and inspection to all electrical equipments. Conducted double roving, testing and inspection to all electrical equipments. Every hour monitoring of mother meter

Status/Remarks
All electrical equipments are in good and normal condition. All electrical equipments are in good and normal condition. Turn over to the next shift Done. Turn over to next shift

Common B1/TA & B1/TB Alfred Taladtad/Rolly Magistrado Duty Shift Electrician (Unit and Common)

Every after three (3) hours monitoring of B2 Lawton LV Switchgear KiloWatt Hour Meter at Emergency panel for B2 Lawton LED only B2 Cameron LV Switchgear B3 Electrical Room Lawton Every after three (3) hours monitoring of KiloWatt Hour Meter at Emergency supply fo B1 to B3 LED Every after three (3) hours monitoring of KiloWatt Hour Meter at Emergency supply fo B3 Conducted roving, testing and inspection to all plumbing equipments.

Done. Turn over to next shift

Done. Turn over to next shift

Done. Turn over to next shift All plumbing equipments are in good and normal operation. All water tank are in normal level. Except Indoor pool water heater. DONE

Rogelio Legaspi

Duty Shift Plumber (Common )

Common

Attended unit calls

Rogelio Legaspi

Duty Shift Plumber (Common )

Common All plumbing equipments are in good and normal operation. All water tank are in normal level. Except Indoor pool water heater.Turn over to the next shift All A/C equipments are in good and normal condition.

Conducted double roving, testing and inspection to all plumbing equipments.

Conducted roving, testing and inspection to all AC equipments. Alejo Libre/Crislie Anecito Duty Shift AC Technician (Common) Common Conducted double roving, testing and inspection to all AC equipments. Romy Cabanizas Allan Book Crislie Anecito Cipriano Malakas Alex Maningas Crisaldo Luna Roberto Carcajante Gilbert Hidlao Rolando Andico Jr. Plumber (Unit ) Electician (Unit) AC Technician (Unit) Carpenter (Unit) Painter (Unit) Utility/Carpenter (Common) Carpenter (Common) Mason/Utility (Common) ATTENDED UNIT CALLS ATTENDED UNIT CALLS ATTENDED UNIT CALLS ATTENDED UNIT CALLS ATTENDED UNIT CALLS Fabricated console for BMS Fabricated console for BMS ATTENDED UNIT CALLS ATTENDED UNIT CALLS

All A/C equipments are in good and normal condition.

Painter (Common)

Cesar Molbog

Painter (Common)

ABSENT All elevators are operational.

GM room

Conduct brief orientation together with facility manager about the operation of the building

Done

Solar heating panel

Conduct inspection on the ongoing repair of the unit

On-Going

Michael Advincula

Shift Engineer

Engineering office

Locating fire protection certificates and documents

On-Going

PE 1 & PE 2

Conduct preventive maintenance, all elevators are operational

Done

GM Room

Conduct short meeting together with GM,OM,FM and shift engr about the installation of lights

Done