RATE ANALYSIS

Note: Labour Constants have been taken from IS: 7272 (Part I)
1 Excavation and Earth Works a) Excavation over areas (Hard/dense soil ), depth up to I.5 m and removal ( up to one metre from edge ) Quantity Considered Sr. No 1 a) b) Labour/Material/Others Labour Mate Mazdoor Sum 2 Water @ Sum 3 Contractor's Profit @ Total For 10m3 3 Therefore, Per m 10 m3 Day 1 1 earthwork 3 Quatity/10m Rate Per 0.6 6.2 1.50% 10% 162 day 166 day Amount in Rs. 97.38 1030.13 1127.51 16.91 1144.42 114.44 1258.86

126.00

2 Plain Cement Concrete Unreinforced concrete 1 : 4 : 8 in foundations including mixing, pouring, consolidating and curing: 1) Hand mixed cement concrete Quantity Considered Sr. No Labour/Material/Others a) b) c) 2 a) b) c) 1 Labour Mason Mazdoor Bhistie Materials Cement bags Sand Coarse Aggregates Sum 3 Water @ 4 Tools and Machinery Sum
3 10 m

concrete Quatity/10m3 Rate Per 1 21.3 7 34.34 4.77 182 day 166 day 162 day 329 bag 3 437 m
3

Day 1 1 1

Amount in Rs. 181.80 3539.00 1136.10 11290.99 2083.54 10217.34 28448.77 426.73 500.00 29375.50 Page 1 of 6

Calculation of Materials For 10 m dry concrete = 15.5 m3 wet concrete Therefore, cement required = 15.5 / (1 + 4+
3

8)

Therefore, cement required = Density of Cement = Cement Required = Therefore, Cement Required = 1 bag of cement = No. of Cement bags reqd. = No. of Cement bags reqd. = Sand Required = Coarse Aggregates Reqd. =

1.19 1440 1.19 1717

m kg/m3 x 1440 kg

50 kg 1717 / 50 34.34 bags 3 4.77 m 3 9.54 m

9.54 1071 m 1.50% Lump sum

5 Contractor's Profit @ Total For 10m3 Therefore, Per m3

10%

2937.55 32313.05

3232.00

3 Concrete Reinf. cement concrete 1 : 1.5 : 3 insitu in foundations, concrete footings bases tor columns, etc excluding form work and reinforcement Quantity Considered Sr. No Labour/Material/Others 1 Labour a) b) c) d) e) f) 2 a) b) c) Mason Mazdoor Bhistie Mixer Operator Mixer Vibrator Materials Cement bags Sand 81.16 4.23 329 bag 437 m
3 3

10 m3 Day 1 1 1 1 1 1

concrete Quatity/10m3 Rate Per 1.7 20 9 0.7 0.7 0.7 182 166 162 182 182 182 day day day day day day

Amount in Rs. 309.06 3323.00 1460.70 127.26 127.26 127.26 26685.41 1847.66 9049.95 43057.56 645.86 500.00 44203.42 4420.34 48623.76

Calculation of Materials 3 For 10 m dry concrete = 15.5 m wet concrete Therefore, Cement required = 15.5 / (1+ 1.5 +
3

3)

Cement = Density of Cement = Cement Required = Therefore, Cement Required = 1 bag of cement = No. of Cement bags reqd. = No. of Cement bags reqd. = Sand Required = Coarse Aggregates Reqd. =

2.82 1440 2.82 4058 50 4058 81.16

m kg/m3 x 1440 kg kg / 50 bags

4.23 m3 8.45 m3

Coarse Aggregates Sum 3 Water @ 4 Tools and Machinery Sum 5 Contractor's Profit @ Total For 10m3 3 Therefore, Per m

8.45 1071 m 1.50% Lump Sum 10%

4863.00

4 Brick work ( Straight Walls) a) Brick work in walls exceeding one brick thick, in cement mortar 1: 4 Quantity Considered Sr. No Labour/Material/Others 10 m3 Day brickwork Quatity/10m3 Rate Per Amount in Rs. Page 2 of 6

Calculation of Materials Size of Modular brick is 20 x 10 X In 1 m3, no of bricks = 1 / 0.2 / In In 1 m3, no of bricks = 500 5000 nos nos 10 m3, no of bricks =

10 cms 0.1 / 0.1

1 a) b) c) 2 a) b) c)

Labour Mason Mazdoor Bhistie Materials Bricks Cement bags Sand Sum Sum

1 1 1

9.4 18 2 5000 20.08 2.79 1.50% 10%

182 day 166 day 162 day 5.8 nos 329 bag 3 437 m

1708.92 2990.70 324.60 29000.00 6602.30 1218.67 41845.20 627.68 42472.88 4247.29 46720.17

Size of Actual Brick is For 1 m3, Actual volume of by bricks= Actual volume of by bricks= Volume of cement mortar = Volume of cement mortar = Add 10% for undulations = Add 10% for frogs, wastage = For 10 m3 of brickwork = For 10 m3 of brickwork = 3 For 10 m dry mortar = For 10 m3 of c.m, Cement = For 2.79 m3 of c.m. = For 2.79 m3 of c.m. = Density of Cement = Cement Required = 1 bag of cement = No. of Cement bags reqd. = Sand Required =

19 x 500 0.77 1 0.23 0.25 x 0.19 m3 - 0.77 m3 m3

9x x

9 cms 0.09 x 0.09

3 Water @ 4 Contractor's Profit @ Total For 10m Therefore, Per m3


3

0.28 m3 10 x 0.28 m3 of cement mortar 2.79 m3 of cement mortar 3 12.5 m wet mortar
3 2.5 m

4673.00

2.79 0.7 1440 1004 50 20.08

x 2.5 / 10 m3 of cement kg/m3 kg kg bags 3 2.79 m

5 External Plastering: Cement plaster mixing of mortar Assume: Bottom Layer in cement mortar the top Layer being in cement mortar Quantity Considered Sr. No 1 a) b) c) 2 a) Labour/Material/Others Labour Mason Mazdoor Bhistie Materials Cement bags

15 mm thick over brick walls ( exterior ) including 10 mm thick 1 : 5 and 5 mm thick 1: 3 10 m2 Day 1 1 1 surface area, over which plaster is applied. Quatity/10m3 Rate Per Amount in Rs. 0.6 1 1 1.23 182 day 166 day 162 day 329 bag 181.80 166.15 162.30 404.42 Page 3 of 6

On c.m. c.m. Add Add

Calculation of Materials 10 m2, the quantity of cement mortar in bottom layer, in bottom Layer= 10 x 0.01 in bottom Layer= 0.1 m3 10% for undulations = 0.11 m3 10% for wastage, etc. = 0.12 m3
3

For 10 m dry mortar = For 10 m3 of c.m, Cement = For 0.12 m3 of c.m. = For 0.12 m3 of c.m. = Density of Cement = Cement Required = 1 bag of cement = No. of Cement bags reqd. = Sand Required =

12.5 m wet mortar 3 2.08 m 0.12 0.03 1440 36.3 50 0.73 x 2.083 / 10 m3 of cement kg/m3 kg kg bags

3 0.13 m

b) 3 Water @

Sand Sum Sum

0.18 1.50% 10%

3 437 m

4 Contractor's Profit @ Total For 10m Therefore, Per m2


2

78.62 993.29 14.90 1008.19 100.82 1109.01

On c.m. c.m. Add Add

10 m2, the quantity of cement mortar in top layer, in top Layer= 10 x 0.005 in top Layer= 0.050 m3 1% for undulations = 0.051 m3 10% for wastage, etc. = 0.056 m3 12.5 3.13 0.056 0.017 1440 25 50 0.5 m3 wet mortar m3 x 3.125 / 10 m3 of cement kg/m3 kg kg bags
3

111.00

3 For 10 m dry mortar = For 10 m3 of c.m, Cement = For 0.06 m3 of c.m. = For 0.06 m3 of c.m. = Density of Cement = Cement Required = 1 bag of cement = No. of Cement bags reqd. =

Sand Required =

0.05 m

6 Flooring: Precast terrazo tile flooring 20 mm thick laid over thick cement mortar: 1: 4 including Laying, cutting, grinding and polishing Quantity Considered Sr. No 1 a) b) c) d) e) 2 a) b) c) 3 Water @ Sum 4 Contractor's Profit @ Total For 10m2 10% Labour/Material/Others Labour Mason Mazdoor Bhistie Mazdoor Machine Materials Tiles Cement bags Sand Sum 10 m Day 1 1 1 1 1
2

10 mm Size of a Terrazo tile is In 1


3

Calculation of Materials 250 x 250 1 / 16 160 1 0.010 0.011 0.012 10 0.12 0.25 / 0.25 nos nos x 0.01 m3 m3 m3 x 0.012 m3 of cement mortar m3 of cement mortar 3 12.5 m wet mortar 3 2.5 m 0.12 0.03 1440 43.6 50 0.87 x 2.5 / 10 m3 of cement kg/m3 kg kg bags

surface area, over which flooring is laid. Quatity/10m Rate Per 182 166 162 166 182 day day day day day Amount in Rs. 218.16 332.30 162.30 830.75 727.20 12000.00 286.06 52.42 14609.18 219.14 14828.32 1482.83 16311.15 Page 4 of 6

m2, no of tiles =

1.2 2 1 5 4 160 0.87 0.12 1.50%

75 nos 329 bag 3 437 m

In 1 m2, no of tiles = In 10 m2, no of tiles = Volume of c. m. over 1 m2 = Volume of cement mortar = Add 10% for undulations = Add 10% for wastage = For 10 m2 of terrazo tiling = For 10 m2 of terrazo tiling = 3 For 10 m dry mortar = For 10 m3 of c.m, Cement = For 0.12 m3 of c.m. = For 0.12 m3 of c.m. = Density of Cement = Cement Required = 1 bag of cement = No. of Cement bags reqd. =

Therefore, Per m2 Following has been assumed: Labour Mate Mason Mazdoor Bhistie Mixer Operator Mixer Vibrator Machine Operator Rate/day 162.3 181.8 166.15 162.3 181.8 181.8 181.8 181.8

1632.00

Sand Required = Material Rate Per Unit Cement Sand Coarse Aggregates Bricks Terrazo Tiles

3 0.12 m

Rate 329 bag 437 m3 1071 m3 5.8 no 75 no