You are on page 1of 15

HYDRAULICS BRANCH OFFICIAL FILE COPY

PAP-447

BUREAU OF RECLAMATION

HYDRAULICS BRANCH

OFFICE FILE COPY


When Borrowed Return Promptly

STv1PEDE DAM OUTLET WORKS AIR SLOT HYDRAULIC MODEL TESTS


BY BRENT

W. MEFFORD

PAP-447

-11 WPRS

61)

INFORMATIONAL ROUTING

I- - - - -- -

JUL2 5 1983

D-1532

I-----

- - - ----- To Regional Director, Saaramento, California Regional Engineer Attention Chief, Division of Research Stampede Dam Outlet I____ ----------

!1om. Subject

L-----------

Works Stilling Basin Air Slot Model Stt1_d.y__.._____

The results of hydraulic model studies conducted on the Stanipede Dam outlet In conjunction with the works ar slot are presented in the enclosed report report,a short video tape covering the main aspects of the model study is being prepared. We feel the video tape will be of value in illustrating the findings of the mdel study. The video tape will be sent separately upon completion

//

GPO 1979 682-262

STAMPEDE DAM OUTLET WORKS AIR SLOT HYDRAULIC MODEL TESTS

INTRODUCTION Stampede Dam is an earth-filled structure located on the Little Truckee River in California. The reservoir is part of the Washoe Project. The Stampede Dam outlet works consists of a 12-ft-diameter concrete-lined tunnel controlled by two 4- by 5-ft tandem gates. The outlet works gates discharge into a type 2 hydraulic jump stilling basin. During an underwater examination on July 29, 1982, cavitation damage was discovered on the outlet works chute floor. To reduce the potential for further cavitation damage during operation, an air slot was designed and installed in the fall of 1982. Operation of the basin in the spring of 1983 indicated the air slot was not performing as expected. The air slot displayed a weak air demand and experienced icing of the air vents during night operation. The left bay air slot failed in March 1983 and the right bay exhibited cavitation damage downstream of the slot. Three areas felt to be involved in the poor performance of the air slot were: (1) misalinement of the air slot during installation, (2) icing of the air intakes during cold weather operation, and (3) the large submergence of the air slot under some operating conditions. A model study of the air slot was requested to determine the ability of the air slot to provide air to the floor of the chute under the operating conditions at Stampede Dam.

THE MODEL An existing 1:8.25 scale model of Mason Dam outlet works and stilling basin was used to conduct the air slot studies for Stampede Dam. Both Mason and Stampede outlet works stilling basins are of a general type 2 hydraulic jump configuration. Although the Mason Dam model did not provide a perfect Froude scale model of Stampede Dam, the major characteristic lengths defining the flow boundaries were close to a 1:12 scale of the Stampede outlet works basin. Geometric differences affecting flow similitude were accounted for by adjusting discharge and gate opening to attain the desired velocity and depth of flow at Sta. 15+85.2, figure 1. Both flow depth and velocity for prototype and model were determined numerically by computing the flow surface from the gate downstream using a finite difference computer model, assuming a gate contraction coefficient of 0.74 and a reservoir elevation of 5945 ft. The Mason Dam model gate size limited the largest Stampede model gate opening to 80 percent.

MODEL STUDIES - PART I Cavitation Potential To determine the cavitation potential of the flow in the original basin, pressures were measured from three piezometers located on 1.71-ft centers at Sta. 15+84.86. The pressures listed in table 1 are an average of the pressures measured by the water manometer across the chute floor. Under normal tailwater conditions, the turbulence within the toe of the hydraulic jump created significant pressure fluctuations. Falvey [1] suggests air slots are generally needed on chutes if the cavitation index is less than 0.20. The cavitation index was defined as P)/Hwhere: = reference pressure of ambient flow vapor pressure of the fluid = free stream stagnation pressure
= =

The values of sigma calculated using average pressure indicate the greatest potential for cavitation exists at between 50 and 60 percent gate openings. To determine the minimum expected cavitation index at each gate opening, floor pressures were calculated for the free jet without the formation of a hydraulic jump. Assuming a free jet as the limiting case, cavitation could be expected to occur due to minor local imperfections in the flow boundary.

Table 1. - Cavitation index

R (ft) R (ft) % gate (submerged) (free jet) P

(ft of H20) H

(ft of H20)

(submerged) (free jet)

20 30 40 50 60 70 80

36.7 34.4 34.6 33.9 32.5 32.5 34.5

27.9 28.1 28.3 28.6 28.8 29.0 29.3

0.28 0.28 0.38 0.28 0.28 0.28 0.28

182.8 189.2 187.2 187.2 180.1 168.6 144.6

0.193 0.180 0.189 0.179 0.179 0.191 0.238

0.150 0.148 0.151 0.153 0.160 0.172 0.202

MODEL STUDY - PART II Air Slot Tests Four air slots were milled from brass plate and tested in the model. The air slots tested are given in table 2.

Table 2. - Air slots tested

Air slot

Ramp slope (degrees)

RL Ramp length (ft)

RH Ramp height (ft vertical)

Sn Slot depth (ft vertical)

1 2 3A 38

2 4 4 4

17' 34' 34' 34'

1.58 1.58 2.69 2.69

0.063 0.126 0.215 0.215

0.50 0.53 0.53 0.10

Air slots 1, 2, and 3A were tested with air grooves downstream of the ramp as shown on figure 2a. Air was vented to the slots through the triangular section formed by the air slot and old floor line. Air slot 3B was tested using a ported air vent below the ramp, figure 2b. Air was vented to the ports through the circular tube upstream of the air slot. All air slots were tested using a single-ended air vent - per bay - passing through the outside walls of the Each air slot was placed in the model with the upstream end stilling basin. of the ramp adjacent to the stainless clad steel liner, Sta. 15+84.12. In addition to visual observations, three piezometers were placed on equal centers across the air groove of each slot. Average pressures were measured on each tap to determine the air distribution across the slot. The air vent intake for each slot was connected to a vane anemometer. The anemometer was used to measure total air volume over a 10- to 15-minute test period. The air volume was converted to an average air discharge passing through the model vent. Prototype air vent head losses were not modeled. Each air slot was tested in the model using outlet gate openings from 20 to 80 percent in 10 percent increments. Tailwater elevations used were based on prototype measurements conducted during the January 1983 field tests, figure 3.

AIR SLOT TEST RESULTS Air slot 1, table 2, was initially placed in the model for testing. The air slot partially flooded with water at 20 and 30 percent gate openings. From 40 to 60 percent gate, a pulsating flow of air into and out of the slot occurred. Gate openings above 60 percent again showed significant flooding of the air The pressure at tap 3 was lower than tap 1 during all tests. groove, figure 4. The air volume being drawn in by the air slot was too small to be measured by the vane anemometer. The slot appeared highly sensitive to taiiwater conditions. The tailwater was lowered and the slot performance was again observed. The slot exhibited only minor intermittent flooding and blowback as long as the toe of the hydraulic jump was downstream of the air groove.

The ramp angle and offset height were doubled on the second air slot. Gate openings of 20 to 40 percent resulted in a strong pulsating airflow in the air vent. The air cavity downstream of the air slot appeared very unstable. At gate openings of 40 to 60 percent, the air vent pulled air with occasional blowback from the slot. At larger gate openings, the air in the vent returned to a weak pulsating flow condition. Pressures measured at tap 3 were lower than at tap 1 for gate openings of 20 to 70 percent. The average ratio of air to water downstream of the slot is shown on figure 5. The air volume induced by the slot was too small to be measured by the anemometer at 20 percent gate. The ramp length and offset height were extended on the third air slot tested. The longer ramp placed the air groove 1.1 ft downstream from the prior location creating approximately 0.5 ft higher tailwater submergence. Steady pulsating airflow was again observed at 20 to 30 percent gate openings. Some intermittent blowback associated with partial air cavity collapse was observed at all gate openings above 30 percent. The average percent of air being pulled into the chute was about 40 percent higher than occurred using the second air slot. The third air slot design was modified to eliminate choking of the entire air slot by the random feedback of small jets of water into the slot area. A ported air vent was installed to replace the open triangular air slot, figure 2b. The ported vent design was implemented to provide better air access to the total width of the chute. Air slot 3B provided a nearly uniform pressure distribution across the width of the slot during each test. At low discharges the amount of air introduced to the flow by the air slot showed a significant increase over the open slot designs tested, figure 5. The model gates were shut and reopened to determine if the ported vent would clear itself of water during initial outlet works operation. As the outlet gates were opened, the air vent quickly drained itself entirely of water through the ports.

AIR SLOT SUBMERGENCE During spillway operation the outlet works tailwater elevation at Stampede may exceed the levels given on figure 3. Model tests were conducted using air slot 3B to determine te effect of 1.0 and 2.0 ft additional submergence on air demand, figure 6. For a reference, the air demand of a free jet passing over the slot is also shown. Increasing the slot submergence produces a sharp decrease in the air demand at gate openings less than 40 percent. At gate openings of 40 to 60 percent the air slot pulled a strong steady stream of air under the additional submergence. Above 60 percent gate opening, the air slot exhibited a steady but reduced inflow. The air cavity was suppressed to a length of about 2.0 ft at 80 percent gate under 2 ft of additional tailwater. The air demand is largely dependent on tailwater at small gate openings where a thin jet exists. Depending on submergence, the air demand may increase or decrease over that of a free jet. For a thick jet, gate openings above 70 percent, the air demand consistently drops with increasing tailwater. A series of air

demand readings were taken at 20 percent gate opening to define the full effect of tailwater from sweepout to high iailwater levels, figure 7. The air demand was found to decrease as the toe of the hydraulic jump submerged the lower half of the air cavity. As the jump submerged the air slot and ramp, the air demand increased sharply rising above the free jet level. Continued submergence of the air slot then produced a steady decrease in air demand to levels well below the free jet.

CONCLUSIONS The turbulent intensity of the stilling basin, depth of air slot submergence, and air vent icing at Stampede Dam require special design considerations. The model study test results indicate at normal tailwater a niinimum offset height of 0.2 ft is needed to develop stability in the air cavity downstream of the air slot. Open air slot designs have the potential for air cavity collapse and intermittent flooding of the air slot. Flooding of the triangular air slot near the single air vent opening can block air access and produce flooding of the entire slot width. The ported air slot was effective in reducing air cavity collapse and flooding of the model air slot. The single air access vent can be used to supply air evenly across the width of the chute for the ported-type air slot. Peterka [2] suggests - from laboratory tests on concrete samples - a minimum of 2.0 to 7.0 percent air concentration by volume is needed to significantly reduce the cavitation damage potential. Although the air concentrations given on figures 5, 6, and 7 cannot be directly scaled to prototype due to geometric model differences and scale effects, prototype air contents are expected to be greater than those measured in the model. Prototype air velocity measurements should be made to define the air demand over the operating range. Tailwater has a major effect on the air slot's air to the flow. The outlet works should be o demand of at least 7 percent when operating at 70 percent. At gate openings above 70 percent falls below 7 percent, the outlet works should levels at or below those shown on figure 3. ability to induce sufficient erated to maintain an air gate openings lower than where the model air demand be operated only at tailwater

REFERENCES

1.

Falvey, Henry T., Aeration Groove Design for Cavitation Protection, Unpublished USBR Research Paper Peterka, Alvin J., The Effect of Entrained Air on Cavitation Pitting, IAHR Hydraulics Conference, September 4, 1953 Pan, Shui-bo, Shao Ying-ying, Shi Qu-sui, Dong Xing-lin, Self Aeration Capacity of a Water Jet over an Aeration Ramp, Translation from Chinese Journal of Hydraulic Enginering, Beijing, No. 5, 1980

2.

3.

4. Siegenthuler, A., and L. Eccher, Spillway Aeration of the San Rogue Project, Water Power and Dam Construction, September 1982 5. Colgate, D. M., Hydraulic Model Studies of Aeration Devices for Yellowtail Dam Spillway Tunnel, Pick-Sloan Missouri Basin Program, Montana, USBR publication REC-ERC-71-47

2-4'-Oi 5!_OOutlet

75KW Unit healer MOunt bottom of heater , (40 i8-0 Metal door 8-0'- above floor'-..
\

E ,Sta 15+87.54

unit tbr ventilatici,


--

--------

ii Steel ladder. Top section Pilo. i. N-7. bottom section iva See Owq.

St 15+oo--'---2'JnsulOliG,. I

NO. 40-0-6022. Modify mounting to suit.\

o-4 -------- ----t-----l--'-4'-6f-'-V. ______________________________ ,6 Dia. pipe with flange cover for future fan I
Lodder - platform ---Control house-..,,_. Handling hook- ----: ' -. I -_______________

Thermos

10

-_--__i Re2-.u1r level gie pip.'r

it

---k

'
-

:---', .------

14'- Ventilation pipe---. / -Coqhator. mount $2'-'


--

:i
all mounting
for hand roil

64Ji
'p -' ' 1'

Std. pipe handrail and ."-ofz 2'-Cf Opening rome guard chain see Dwg. for fan unl# 40-0-60 ff'4 KW Unit heater suspended from ceiling. MOunt bottom of heater
F.1

Iccess lKiuse------. L -----

ig By-pass

!41

-- 3-Os

7-QMetol dour-

--

SPa. l5^58--11-7'- Risers and '0 treads ) eq spe.-F and cover; J0w 949-D-* Handrail not shown-. ________ -

El.572a08 ,.-- -3'-Oroins fL5728O5 2'-lnsulotion

3Grovelcr cni

rock surfoc,nn

_I

-' 0

/JJ'

-4i --El 573800 2-Cl 5735100


:'--

uIiI. "
e

?
______

.-Controct,on joint $0 BYPOSS


-

:;: . '0 Bypass p:o,


-

jipit"

H. tunnel

Ouflet

Outlet works

Control cobinet-_

ti_4
-

.Qutiet works and


,-----

'\

\ .,,,
-,

e-o obovejloor------

/ / /, ,.

-5-2'

-Sf0. 15+83 -__. ,..Thrrnostat, mount . 4-6 above floor


T-_

pSel pipe
'-. -. .

, .-

.-

-4-i
.

-:-; --;--

60,a. drain

,
7

ventilation louver- ----- -

(91KT- -it 2'-Of'Opening for /


C

-.-

2-6-' . ' 10-5 ------'

'..

ntoc4or. mount -6 above floor,


7ll'-----"-'

'-6 Flanged connection. see dwg. 949-0-19

4'- -- Contoctor -10 KWUnit heater - -6 010. pipe with flange cover for future fan -

SECTION C-C

SECTION 0-0

"-2'-0f'x2.0f M(9)
SECTION

5-l50Slip-.m flange ----- -

Opening for ventilation louver J(91 Detail U(9L....__,, ..-. / - ------- -. .

Hoist anchor ,landlinq see Oeoil V(g)


ofx 2-t.,f Opening or fan unit,C El.5 7, 4..
Ar

hooks,

A-A see

,..Arch,tectural concrete soffits-.

15746.50
____

______

I
_____

-'-4..=,

,.EI..7..6.50
--El.

578.25

5Std pipe cut flush with concrete fxe on downstream end-

-.

SECTION P-P

Sta.

15+00-.

"----2-0fz 2'-Oj' Opening for ventilation louver '2 Insulation 75737.75' 15^1750

-2-04'-x 2'-Of Opening for ventilation louvers ,-5'-Std. pipe for gate control Sf0. 15+58 ______ of first e wall ,.Sfo. l538 Control cabinet-.. Top of 4---El.5735.50 bockfill ----Sets of 40'-z5!0 outlet gates Chain link fence--_

I -- of Metal - ,,

--EI.5 746. 08
-- -,' ----Seven equal arct.itectural concrete panels on
_,

upstream face of house,

I //t-- -J - c,7JPo,l
"-_ '

/J'Ladder-"7

[Ji

El.

E15?3216

C.

-Sto. 15^83 ,.-Sto. 15^87.54 El. 5 730oO---"., 6 Blind flange -El.5728.0. ,3brin. -El.5 72 7.77 6 Slip-on flange weld fdia nut to bottom of , - each bolt hole . -EI,57205O
I

.-f - ------"i'07

Grovel or crushed rock surfecing NOTES For general notes and reference drawings see 0wg 949-0-I. REFERENCE DRAWINGS RESERVOIR LEVEL GAGE PIPING ------------------------- .949-0-Il STEEL OUTLET PIPE. ------------------------------- .949-t-I7 LATERAL"WYE TRANSITIONS-BENDS ------------------ ..949-C'-I9 nv-PASS PIPIN0-DRAIRS--------- _. ------------------ .949-0-Z CT PASS,AJR AND DRAIN PIPiNG ----------------- - ----- .949-0-21 VENTILATION 5YSTEM --------------------------------- 949'OI36
a - 'S - o AS 0i144.T DY 535, tnt. s-a-va.

/,,_

---

El. 5724.19--.

-El 572419-'/ Curved linertainles; Sto.!5-v53'. / EL 5724. SEC TI C N B - B Sf015 #5450",.."

. -'

-- El57l8.44

E1.57l844-T --F1.5716.51 ----57/4


--Stainless steel. liner -

/5*6714 /
.

______

-1> --

(' 3
-.

I'
7.-...

P1. 7Jtjz06j

-.11
,fl.5733.9l , '

,._lf Std. pipe handrail, see Dwq 40-0 -6022. Modify mounting as shown. / / 12.l6 'Anchor bolts not Shown

-. --

'P

E1.5734.50--.

-.

I
Do'swistream liner ,' (Stainless clad steelY

-,
-o

y-_E1.57a8.24../
-

RUURYS
1' .............

SAfETY

'
;to. 15

ee Detail Z-

UJIrEO STATES DEPARTMENT OF TNt DUR(AU OF RECLAMATION

IThJ
1'-i kPIoin dowels

*ASMOE PROJECT STAMPEDE DIViSION-NEVADA cAL.IPORNIA

Molded connection-Type H rubber waters tap -"


SECTION E-E

STAMPEDE DAM - OUTLET WORKS CONTROL STRUCTURE


SECOND STAGE teat to _tLt.,.....,

S'

I 91

Dio. holes for and provide J expansion onchors.

SECTION F - F

cn.cnco..C.SS

----- ..*-RflovSO ------.&,iiIT-,AA.Lt-.----- --

OOOAO*^I.,,..a

J
-

949

F' if [1 IRF 11.

t.Lt.VAIIU1'J VL.W

FIGURE 2A-OPEN AiR SLOT

Old floor line

OC) DQDC O
SEGTON A-A

FIGURE 2s-PORTED AIR SLOT

STAMPEDE OUTLET-WORKS TAILWATER ELEVATION


5725. 0 5724. 0

5723. 0
5722.0 5721.0

0 5719.0 5718.0 5717.0 5716.0 5715.0

5720 0

714.0 5713.0

5712. 0
5711.0 C) C rn 5710.0
_______

C')

I!)

PERCENT GATE OPENING

STAMPEDE AIR SLOT MODEL TESTS


100
flT

itr

.r-r-u

A1

80

70
0 LL

60

Ramp
50

Air Vent P3 P2 P Air Slot Pressure taps

40

-o 30 er wall 20J 10

1 C) C

rn

(0

PERCENT GATE OPENING

001

I-,

C' N
I

f-a
(J)t f-FWi
Wa

U)

08

oft
I-

z z
09
0 Ui

F-

F 0 F-

z
Ui Ui
U

Ov W u_I

<a
(I iJ

a
ft

if
'I

Flr,

it

Ill

(\J

_4

-l

.-l

.-4

ci- C (2.LVM) 0/ (dIV) 03

FIGURE 5

001
w

ci:: W F (n<

XI-

._.4z
III

.i

08

(nJ
1J
WI 00 01-I

Trrr

0 z
I-I

z W a0 W F0 Iz W C-) W a-

Fl OF Ji-I

F WO 0-i ci<0 F (flU)


F

(I)
W F

0?

r -, cJ

I,I,r,r-rr ,
.-4 ,
,-4 '-

,,Tyrz (PT! 1J I I I Irr-r1r-T--r


_-4

_-,

1-4

I-* C (eLVM) D/ (JIY) OJ

FIGURE 6

F 0 6ILS 8ILG
-

LIL 91LS

(no wz

(13W x

<0

SILG
ILS
Ui
-

I-'
$

t1
x
U) >Ui

4)
'-I
.

-iw
o oc
F

biD

CILS

z
F<

0
IlLS

-j
5-.

0z

Jo
(I)

>

ILS
5-. -

a:w UI-I Lil< I FO CD F


Ci

J UI F -I
F

60L5 80L5

/ I I
Ui

LLS 90L5 SLS 1LS ELS ?2L5

UI
U. [I.

UI UI
I

WI
Es.

F
1 4
I

I LS
i.-.

c\I

.-.l

,-l

-4

,-l

-5

D
,-4 -4 _S ,-4

I I 1 4 I I I I N Ij)

I I CT)

I I I 1

ZLS

IV) j

FIGURE 7

You might also like