Safety Information 1. Information About the Installation 2. Installing the BBU in the APM30 3. Installing the BBU in the APM30H 4. Installing the BBU in the APM30 (+24 V) 5. Installing the BBU in the 19-Inch Cabinet 6. Installing the BBU on the Wall 7. Installing the BBU in the PS4890 Cabinet 8. Installing the BBU in the OMB Cabinet 9. Installing the BBU in the TMC 10. Installing the BBU in the TMC11H 11. Checking the Power-On Status of the BBU 12. Reference

2 3 8 15 17 19 23 28 33 39 41 42 43

Safety Information
Following All Safety Precautions
Before any operation, read the instructions and precautions in this document carefully to minimize the possibility of accidents. The Danger, Caution, and Note items in the documents do not cover all the safety precautions that must be followed. They only provide the generic safety precautions for operations. When operating Huawei products and equipment, you must comply with safety precautions and special safety instructions related to corresponding equipment provided by Huawei. The safety precautions in the document are related to only Huawei products. Huawei is not liable for any consequence that results from the violation of universal regulations for safety operations and safety codes on design, production, and equipment use.

Complying with the Local Safety Regulations


When operating the device, comply with the local safety regulations. The safety precautions provided in the documents are supplementary. You must comply with the local safety regulations.

Qualified Personnel Only


The personnel in charge of installation and maintenance must be trained and master the correct operating methods and safety precautions before beginning work.

Symbols
This symbol indicates that casualty or serious accident may occur if you ignore the safety instruction. This symbol indicates that serious or major injury may occur if you ignore the safety instruction. This symbol indicates that the operation may be easier if you pay attention to the safety instruction.

Safety of Personnel
The high voltage power supply provides power for running the system. Direct contact with the high voltage power supply or contact through damp objects may result in fatal danger. Non-standard and improper high voltage operations may result in fire and electric shock. In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel tower and mast. Ground the device before powering on the device. Otherwise, the personnel and device are in danger. Power off the device before performing operations on the power supply equipment. High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down. When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes. Protect yourself when drilling holes. Flying dust may hurt your eyes or you may inhale the dust. Power off the batteries before connecting the cables to the batteries. Otherwise, casualties may occur. When working at a height, be cautious about falling objects.

Device Safety
Check the electrical connection of the device before operation and ensure that the device is reliably grounded. The static electricity generated by the human body may damage the electrostatic sensitive components on the circuit board, such as the large-scale integrated circuit (LIC). Wear an ESD wrist strap or ESD gloves when performing the operation. When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards. The NodeB must be powered on within one week after installation.

1 Information About the Installation a


Installation Tools

Insulated screwdriver

Cross screwdriver

Straight screwdriver

Adjustable wrench

Socket wrench

Torque wrench

Power cable crimping pliers

RJ-45 crimping pliers

Wire cutter

Rubber hammer

Claw hammer

Cable peeler

Percussion drill

Heat gun

Level bar

Multimeter

Long measuring tape

Vacuum cleaner

1 Information About the Installation b


Installation Scenarios
2.APM30H

1.APM30

BBU

BBU

3.TMC

4.TMC11H

BBU

BBU

1 Information About the Installation b


Installation Scenarios
6.PS4890

5.APM30 (+24V

BBU BBU

7. In OMB cabinet

8. In other 19-inch cabinet

9. On the Wall

BBU BBU BBU

1 Information About the Installation c


BBU Hardware and Cables

1. Appearance of the BBU (Unit: mm)

2. Configuration Principles of the BBU Boards

Board

Mandatory/Op tional Mandatory Mandatory

Full Configuration 2 4

Installation Slot

Remarks

WMPT WBBP

S6 and S7 S0 to S3

Preferentially configured in Slot 7. Preferentially configured in Slot 3, then Slot 2, at last Slot 0,1. Preferentially configured in PWR2. Only in the FAN slot. Preferentially configured in Slot 4, 5. Preferentially configured in Slot 4. Preferentially configured in Slot 4. Preferentially configured in PWR1.

UPEU UBFA UTRP

Mandatory Mandatory Optional

2 1 5

PWR1 and WR2 FAN S0 to S5

UELP UFLP UEIU

Optional Optional Optional

2 2 1

S0 and S4 S0 and S4 PWR1

1 Information About the Installation d


Cable connections of the BBU
Alarm Equipment Monitoring Equipment

Power System BBU Power Cable E1 surge protection transfer cable E1 Cable Monitoring Cable Alarm Cable CPRI Optical FE cable FE surge protection transfer cable

Procedure

2 Installing the BBU in the APM30 a


Cable connections

NO.

Cable

Installation Position From... To ... PWR on BBU INSIDE on UELP Transmission equipment MON1on BBU CPRI on RRU

1 2 3 4 5

BBU power cable E1 transfer cable E1cable Monitoring cable CPRI

LOAD3 on PDU E1/T1 on WMPT OUTSIDE on UELP TX/RX on APMI CPRI on BBU

2 Installing the BBU in the APM30 b


Installing BBU
1 Install the mounting ears at both sides of the BBU reversely.

PDU

BBU M6 bolt

2 Slide the BBU case into the cabinet. 3 Check the DIP switches (see appendix).

Installing cables
1. Install power cable.
Connect the OT terminal of the power cable to the LOAD3 terminal of the PDU, and then fix the 3V3 connector of the power cable to the PWR port on the BBU.

LOAD3 NEG(-) RNT(+)

PWR
The power cable is to be made depending on field requirements.

2 Installing the BBU in the APM30 b


Installing the BBU cables

2. Install optical cables. Connect one end of the optical cable to CPRI0, CPRI1, or CPRI2 on the WBBP. Then, connect the other end to the RRU. Insert the optical module into CPRI0, CPRI1, or CPRI2. Turn outwards the puller on the optical module.

Optical module Puller

Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. lead the CPRI optical cable out of the cabinet along the left side of the cabinet.

Wrap the fiber tail with the winding pipe till the first cable tie.

Connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU. Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI5 ports on the WMPT.

Optical cable connector

Winding pipe

10

2 Installing the BBU in the APM30 b


Installing the BBU cables
Fix the DB25 connector of the E1 transfer cable to the INSIDE port on the UELP and the DB26 connector to the E1/T1 port on the WMPT.

3. Install the E1 transfer cable.

4. Install the E1 cable.


Cabling the E1 cable. Fix the DB26 connector of the E1 cable to the OUTSIDE port on the UELP. Strip the jacket off the E1 cable near the grounding point at the lower right corner of the cabinet to expose the shielding layer
25mm

E1 cable

E1 transfer cable

Thread the E1 cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the E1 cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the grounding bolt of the APM30.
Shielding layer of the E1 cable

INSIDE

OUTSIDE

E1/T1

11

2 Installing the BBU in the APM30 b


Installing the BBU Cables
5. Install the FE transfer cable (FE transmission mode). Connect one end of the FE transfer cable to the FE0 port near the INSIDE label on the UFLP and the other end to the FE0 port on the WMPT. 6. Install the FE cable (FE transmission). Connect one end of the FE cable to the FE0 port near the OUTSIDE label on the UFLP. Then, lead the other end out of the cabinet along the right side of the cabinet. Strip the jacket off the FE cable near the grounding point at the lower right corner of the cabinet to expose the shielding layer 25mm
INSIDE FE0

FE transfer cable FE cable

OUTSIDE FE0

FE0

Thread the FE cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the FE cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the grounding bolt of the APM30.
Shielding layer of the FE cable

12

2 Installing the BBU in the APM30 b


Installing the BBU Cables
7. Install the monitoring signal cable between the APMI and the BBU.
Fix the RJ45 connector at one end of the cable to the MON1 port on the UPEU.

Monitoring signal cable between the APMI and the BBU

MON1

EXT-ALM1 External alarm cable

8. Install the external alarm cable.


Connect one end of the alarm cable to the EXT-ALM port on the UPEU, and the other end to the associated alarm device. The port on the external alarm device is added depending on field requirements.

9. Install the EMUA monitoring signal cable.


When the MON0 port on the BBU is available, fix the RJ45 connector of the EMUA monitoring signal cable to the MON0 port on the UPEU, and the DB9 connector to the corresponding port on the EMUA.

MON0

RS485

13

2 Installing the BBU in the APM30 b


Installing the BBU Cables
b. When the MON0 port on the BBU is unavailable, cut off the RJ45 connector of the EMUA monitoring signal cable, and then connect the four exposed bare wires to the RX+, RX-, TX+, and TX- ports on the APMI. For the relationship between the ports and wires. Fix the DB9 connector to the corresponding port on the EMUA.

EMUA monitoring signal cable


Pin on the RJ45 Connector X1.1 X1.2 X1.4 X1.5 Pin on the DB9 Male Connector X2.3 X2.7 X2.2 X2.6 Color Type Port on the APMI

White Orange Blue White

Twisted pair

TX+ TX-

Twisted pair

RX+ RX-

14

3 Installing the BBU in the APM30H a


BBU Cable Connections
The procedure for installing the BBU case in the APM30H is the same as that in the APM30. For details, see pages 914. The following figure shows the cable connections of the BBU. Page 15 shows how to install the monitoring signal cable between the HEUA and the BBU in the APM30H.

No.

Cable

Installation Position One end is connected to... The other end is connected to... PWR port on the BBU INSIDE port on the UELP External transmission device MON1 port on the BBU

1 2 3 4

BBU power cable E1 transfer cable E1 cable Monitoring signal cable CPRI optical cable

LOAD3 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP COM IN port on the HEUA

CPRI port on the BBU

CPRI port on the RRU

15

3 Installing the BBU in the APM30H b


Installing the Monitoring Signal Cable between the HEUA and the BBU

HEUA COM IN MON1

UPEU on the BBU

16

4 Installing the BBU in the APM30 (+24 V) a


BBU Cable Connections
The procedure for installing the BBU in the APM30 (+24 V) is the same as that in the APM30. For details, see pages 914. The following figure shows the cable connections of the BBU. Page 17 shows how to install the monitoring signal cable of the cabinet.

No.

Cable

Installation Position One end is connected to... The other end is connected to... PWR port on the BBU INSIDE port on the UELP External transmission device MON1 port on the BBU

1 2 3 4

BBU power cable E1 surge protection transfer cable E1 cable Monitoring signal cable CPRI optical cable

LOAD3 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP COM IN port on the HEUA

CPRI port on the BBU

CPRI port on the RRU

17

4 Installing the BBU in the APM30 (+24 V) b


Installing the Monitoring Signal Cable of the Cabinet

Pin assignment of the monitoring signal cable of the cabinet Pin on the RJ45 Connector
X1.1 X1.2 X1.3 X1.6 X1.5 X1.4 X1.7 X1.8

Pin on the RJ45 Connector


X2.1 X2.2 X2.3 X2.6 X2.5 X2.4 X2.7 X2.8

Wire Color

Wire Type

White/orange Orange White/green Green White/blue Blue White/brown Brown

Twisted pair

Twisted pair

Twisted pair

Twisted pair

18

5 Installing the BBU in the 19-Inch Cabinet a


BBU Cable Connections

No.

Cable From...

Installation Position To... PWR port on the BBU

BBU power cable E1 cable FE cable (optional) Monitoring signal cable CPRI optical cable

External power supply

2 3

External transmission device External transmission device

E1/T1 port on the WMPT FE0 port on the WMPT

External monitoring device

MON/ALM on the BBU

CPRI port on the RUU

CPRI port on the BBU

19

5 Installing the BBU in the 19-Inch Cabinet b


Space Requirements

1. 25 mm on the left of the BBU for ventilation 2. 25 mm on the right of the BBU for ventilation 3. 70 mm in front of the BBU for cabling

Installing the BBU Case

Slide the BBU case into the cabinet. Then, tighten the four M6 screws.

20

5 Installing the BBU in the 19-Inch Cabinet d


Installing BBU Cables

1 Install the PGND cable.

Grounding bolt on the right side of the BBU

PGND cable

2 Install the power cable.

PWR

3 Install the signal cable.

EXT-ALM0

MON1

21

5 Installing the BBU in the 19-Inch Cabinet d


Installing the BBU Cables
4 Install the CPRI optical cable and the E1 cable.

E1/T1 E1/T1

Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. Turn outwards the puller on the optical module.

Optical module Puller

Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. Lead the CPRI optical cable out of the cabinet along the left side of the cabinet.

CPRI optical cable

Winding pipe

22

6 Installing the BBU on the Wall a


BBU Cable Connections

External grounding bar External power equipment

External External transmission equipment grounding bar

External monitoring equipment

SN

Cable

Installation Position One End Connected to... The Other End Connected to...
Power supply socket on the RRU CPRI port on the RRU External transmission equipment External monitoring equipment

RRU power cable

LOAD0 to LOAD5 on the DCDU-03

2 3

CPRI optical cable E1 cable

CPRI port on the BBU E1/T1 port on the WMPT

Monitoring signal cable BBU power cable DCDU power cable PGND cable

MON/ALM port on the BBU

5 6 7

PWR port on the BBU DC input port on the DCDU-03 Grounding bolt on the equipment

LOAD6 on the DCDU-03 External power equipment External grounding bar

23

6 Installing the BBU on the Wall b


Space Requirements
BBUDCDU-03C
DCDU-03C BBU

A single BBU

The DCDU is installed near the BBU.

Installing the BBU Case

1. Install the mounting ears for wall installation.


Mounting ear on the BBU case

Mounting ear for wall installation

24

6 Installing the BBU on the Wall c


Installing the BBU Case

2. Place the BBU against the wall, and then use the marking pen to mark the holes of the mounting ears for wall installation.

wall

BBU

3. Install the expansion bolts.

Bolt M1080 Nut Spring washer 10 Flat washer 10 Expansion tube

55mm60mm

20mm

25

6 Installing the BBU on the Wall c


Installing the BBU Case

4. Mount the BBU on the wall.

Flat washer

Spring washer

Installing the DCDU-03C Case


2. Place the DCDU-03C against the wall, and then use the marking pen to mark the anchor points of the mounting ears for wall installation. wall

1. Turn the mounting ears on the DCDU-03C by 90 degrees.

26

6 Installing the BBU on the Wall d


Installing the DCDU-03C Case
3. Install the expansion bolts.

Bolt M1080 Nut Spring washer 10 Flat washer 10 Expansion tube

55mm60mm

20mm

4. Mount the DCDU-03C on the wall.

27

7 Installing the BBU in the PS4890 Cabinet a


BBU Cable Connections

No.

Cable From...

Installation Position To...


PWR port on the BBU

BBU power cable

LOAD6 terminal on the DCDU External transmission device External transmission device RS232/RS422 port on the PMU

E1 cable

E1/T1 port on the WMPT

BBU alarm cable (optional)

ALM port on the UPEU

Monitoring signal cable between the PMU and the BBU CPRI optical cable

MON0 port on the BBU

CPRI port on the RRU

CPRI port on the BBU

28

7 Installing the BBU in the PS4890 Cabinet b


Installing the BBU

Slide the BBU case into the PS4890 cabinet. Then, tighten the four M6 screws.

29

7 Installing the BBU in the PS4890 Cabinet c


Installing the BBU Cables
1 Install the power cable.

LOAD 6

PWR

30

7 Installing the BBU in the PS4890 Cabinet c


Installing the BBU Cables

2 Install the signal cable.

Install the BBU alarm cable (optional). Install the monitoring signal cable between the PMU and the BBU.

RS232/RS422

MON0

EXT ALM1

31

7 Installing the BBU in the PS4890 Cabinet c


Installing the BBU Cables
Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. Turn outwards the puller on the optical module.

3 Installing the CPRI optical cable and the E1 cable.

Optical module

Puller

Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. lead the CPRI optical cable out of the cabinet along the left side of the cabinet.

E1/T1

CPRI optical cable

Winding pipe

32

8 Installing the BBU in the OMB Cabinet a


BBU Cable Connections

No.

Cable

Installation Position From... To...


Grounding bar of the OMB cabinet DC input terminal of the DCDU

PGND cable

External grounding bar

Input power cable of the OMB

External DC power supply

BBU power cable

LOAD6 output terminal on the DCDU E1/T1 port on the WMPT OUTSIDE port on the UELP CPRI port on the BBU

PWR port on the BBU

4 5 6

E1 transfer cable E1 cable CPRI optical cable

INSIDE port on the UELP External transmission device CPRI port on the RRU

33

8 Installing the BBU in the OMB Cabinet b


Installing the brackets on the metal pole and mounting plate

a.1 Install the brackets on the metal pole.


Use a level bar to adjust the levelness of the brackets to ensure that the front and back brackets are on the same plane.

Flat washer Spring washer Bolt M10110

Inner hexagon spanner 255~306kgfcm

a.2 Install the mounting plate.

Inner hexagon spanner 255~306kgfcm

Flat Spring washer washer

Bolt M10110

appearance of the mounting plate

34

8 Installing the BBU in the OMB Cabinet c


Installing the OMB Cabinet
Slide the BBU case into the OMB cabinet gently. Then, tighten the four M6 screws.

Installing the BBU Cables

1. Install the PGND cable of OMB Cabinet.

35

8 Installing the BBU in the OMB Cabinet d


Installing the BBU Cables

2 Install the input power cable.

NEG(-) RNT(+)

3. Install the BBU power cable.

LOAD6

36

8 Installing the BBU in the OMB Cabinet d


Installing the BBU Cables

4 Install the E1 cable (E1 transmission).

OUTSIDE E1/T1 INSIDE

Shielding layer

37

8 Installing the BBU in the OMB Cabinet


d
Installing the BBU Cables
5. Install the FE cable (FE transmission).

6. Install the CPRI optical cable.


1. Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. 2. Turn outwards the puller on the optical module.

Optical module

Puller

3. Remove the dustproof caps from the optical connectors. 4. Insert the optical connector at one end of the CPRI optical cable into the optical module. lead the CPRI optical cable out of the cabinet along the left side of the cabinet.

38

9 Installing the BBU in the TMC a


BBU Cable Connections
The procedure for installing the BBU in the TMC is the same as that in the APM30. For details, see pages 914. Page 39 shows how to install the TMC alarm cable in the TMC.

No.

Cable From...

Installation Position To...


PWR port on the BBU INSIDE port on the UELP External transmission device ALM1 port on the BBU

1 2 3 4

BBU power cable E1 transfer cable E1 cable Monitoring signal cable

LOAD6 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP Wiring terminal of cabinet monitoring CPRI port on the BBU

CPRI optical cable

CPRI port on the RRU

39

9 Installing the BBU in the TMC b


Installing the BBU

Slide the BBU case into the TMC cabinet. Then, tighten the four M6 screws.

Installing the BBU Cables


APMI
Door status sensor

Installing the TMC alarm cable

a. Fix the RJ45 connector at one end of the alarm cable to the EXT_ALM1 port on the BBU. b. Connect the two bare terminals X1.4 (blue) and X1.5 (white) to the alarm wiring terminals on the door status sensor. c. Connect the two bare terminals X1.1 (white) and X1.2 (orange) to the OUT+ and OUT- alarm wiring terminals on the APMI. d. Connect the two bare terminals X1.3 (white) and X1.6 (green) to the alarm wiring terminals on the DCDU.

Wiring terminal of DCDU surge protection

40

10 Installing the BBU in the TMC11H a


BBU Cable Connections
The procedure for installing the BBU in the TMC11H is the same as that in the APM30. For details, see pages 914.

No.

Cable From...

Installation Position To...


CPRI port on the RRU INSIDE port on the UELP External transmission device PWR port on the BBU MON1 port on the BBU

1 2 3 4 5

CPRI optical cable E1 transfer cable E1 cable BBU power cable Monitoring signal cable

CPRI port on the BBU E1/T1 port on the WMPT OUTSIDE port on the UELP LOAD6 terminal on the PDU Wiring terminal of cabinet monitoring

41

11 Checking the Power-On Status of the BBU


Procedure for checking the power-on status of the BBU:
Start

Powering on the BBU3900

Clearing the fault Powering off the BBU3900

a No

Checking whether all LEDs on the BBU are normal? Yes

End

a The normal status of LED on the WMPT is as follows: RUN LED: 1s ON, 1s OFF (blinking at 0.5 Hz) ALM LED: OFF ACT LED: ON The normal status of LED on the UBFA is as follows: STATE LED: Green 1s ON, 1s OFF (blinking at 0.5 Hz) The normal status of LED on the UPEU is as follows: RUN LED: ON The normal status of LED on the WBBP is as follows: RUN LED: 1s ON, 1s OFF (blinking at 0.5 Hz) ALM LED: OFF

42

12 Reference c a
Cable List
Cable PGND cable Connector OT terminal OT terminal Connects to Grounding bolt of the BBU3900 Protection grounding bar

BBU power cable

3V3 connector Bare wire. The connector needs to be made on site according to the field requirements. (The following figure shows the BBU power cable by taking OT terminals as an example.)

PWR port on the UPEU External power supply

CPRI optical cable

DLC connector

Connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI3 ports on the WBBP

DLC connector

E1 cable

DB26 male connector

E1/T1 port on the WMPT, or OUTSIDE port on the UELP Peer device

The connector needs to be made on site according to the field requirements.

43

12 Reference c a
Cable List
Connector DB26 male connector DB25 male connector Connects to PWR port on the UPEU E1/T1 port on the WMPT

Cable E1 transfer cable

FE cable

RJ45 connector RJ45 connector

FE0 port on the WMPT Routing equipment

FE transfer cable

RJ45 connector RJ45 connector

FE0 port on the WMPT FE0 port near the INSIDE label on the UFLP

Monitoring signal cable between the PMU and the BBU

RJ45 connector RJ45 connector

RS232/RS422 port on the PMU MON port on the BBU

44

12 Reference a
Cable List
Connector Be connected RJ45 connector Connects to APMI MON1 port on the UPEU

Cable
APMI-BBU Monitoring signal cable

EMUA Monitoring signal cable

RJ45 connector

MON0 or MON1 port on the UPEU


RS485 port on the EMUA

DB9 male connector

Alarm cable

RJ45 connector

EXT-ALM0 or EXT-ALM1 port on the MON0 or MON1 port on the UPEU

RJ45 connector

External alarm device

45

12 Reference b
Item Dimensions Weight Input voltage

Engineering Specifications of the BBU


Specification 86 mm (height) x 442 mm (width) x 310 mm (length) Typical configuration: 7 kg; full configuration: 11 kg 48 V DC or +24 V DC

Checking the DIP Switches of the BBU

Wear an ESD wrist strap or a pair of ESD gloves when performing operations related to the boards, as shown in the figure below.

ESD strap

ESD gloves

1. Remove the BBU boards.

46

12 Reference c
Checking the DIP Switches of the BBU
2. Set the DIP switches of the BBU. Settings of the DIP switches on the UELP

75-ohm E1 Mode

Other Modes

Settings of the DIP switches on the WMPT


T1 Mode

75-ohm E1 Mode

120-ohm E1 Mode

3. Reinstall the boards.

47

12 Reference ed
Pin Assignment of the BBU Signal Cables
75-ohm E1 cable Pin on the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring 8 6 4 2 7 5 3 1 RX1+ RX1RX2+ RX2RX3+ RX3RX4+ RX4TX1+ TX1TX2+ TX2TX3+ TX3TX4+ TX4Wire Type Coaxial SN. Label

48

12 Reference d
Pin Assignment of the BBU Signal Cables

120-ohm E1 cable Pin on the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Blue Twisted pair White Orange White Green Twisted pair White Brown Twisted pair White Grey Twisted pair White Blue Twisted pair Red Orange Twisted pair Red Green Twisted pair Red TX4TX3TX4+ TX2TX3+ TX1TX2+ RX4TX1+ RX3RX4+ Twisted pair RX1RX2+ RX2RX3+ RX1+ Wire Color Wire Type Label

49

12 Reference d
Pin Assignment of the BBU Signal Cables

FE cable Pin on the RJ45 Connector X1.2 X1.1 X1.6 X1.3 X1.4 X1.5 X1.8 X1.7 Wire Color Wire Type Pin on the RJ45 Connector X2.2 X2.1 Twisted pair X2.6 X2.3 Twisted pair X2.4 X2.5 Twisted pair X2.8 X2.7

Orange White/orange Green White/green Blue White/blue Brown White/brown

Twisted pair

Monitoring signal cable between the APMI and the BBU Pin on the RJ45 Connector Wire Color Pins on the X2, X3, X4, and X5 X1.1 White X2 Twisted pair X1.2 Orange X3 Twisted pair Twisted pair X1.5 White X5 Twisted pair 50 RXTXTX+ Wire Type Port on the APMI

X1.4

Blue

X4

RX+

12 Reference d
Pin Assignment of the BBU Signal Cables

EMUA monitoring signal cable Pin on the RJ45 Connector Pin on the DB9 Male Connector X2.3 Wire Color Wire Type Port on the APMI

X1.1

White

Twisted pair

TX+

X1.2

X2.7

Orange

Twisted pair

TX-

X1.4

X2.2

Blue

Twisted pair

RX+

X1.5

X2.6

White

Twisted pair

RX-

Alarm cable Pin on the RJ45 Connector X1.1 X1.2 X1.3 X1.6 X1.5 X1.4 X1.7 X1.8 Pin on the RJ45 Connector X2.1 X2.2 X2.3 X2.6 X2.5 X2.4 X2.7 X2.8 White/orange Orange White/green Green White/blue Blue White/brown Brown Twisted pair Twisted pair Twisted pair Twisted pair Wire Color Wire Type