You are on page 1of 18

TIMBER VEHICULAR BRIDGES IN GHANA THE PROGRESS TO DATE

K. A. Solomon-Ayeh Building and Road Research Institute (BRRI) Kumasi, Ghana solomonayeh@yahoo.com

Abstract The infrastructure in Ghana is relatively low because of, among other factors, the lack of crossing structures like bridges. Existing bridges are predominantly of reinforced concrete and as the cost of the imported steel and cement became expensive, research, particularly at the Building and Road Research Institute (BRRI), started on the possibility of using Lesser Used Timber Species (LUS) for vehicular bridges, at least on low-volume feeder roads in Ghana. A prototype 7.6 metre-span, I-sectioned timber girder vehicular bridge was built by the BRRI over the Subin stream at Kaase, in Kumasi, Ghana, in 1991. This bridge is successfully performing its designed functions to date. The structural forms used then and the likely spans achievable, brought to the fore likely problems should spans beyond 8 metres be bridged and, together with the Timber Research and Development Association (TRADA), the possibility of the use of timber truss bridges was looked at. The form of the prototype I-girder bridge, the technical problems inherent in taking this structural form beyond 8 metres and the consequent truss bridge proposed, are presented in this paper. Problems that arose during the design of the truss bridge were those to d with the size f transverse beams, the design of couplers and the need to proof test the integrity f the proposed joints. Design solutions t some of the foregoing problems are given. However, lack of relevant equipment such as loading rams and strain/displacement transducers have meant that the research efforts at validating the design options adopted for the joints have not been possible. Future collaborative research and testing efforts are required if more bridges are to be provided as crossing structures on low-volume roads, if more efficiency in use is to be made of LUS and a likely industry in pre-fabricated timber bridge components engendered in Ghana. Keywords: Bridges, girder, timber, truss, couplers

1.0

INTRODUCTION

In 1991, following research carried out at the Building and Road Research Institute (BRRI) on scaled timber I-girders (Allotey, 1990, 1992), a prototype timber bridge was built over the Subin Stream at Kaase, in Kumasi, Ghana. Considerable problems arose with the construction of the bridge and these problems and their solutions are briefly highlighted.

The bridge is functioning structurally well though some challenges have arisen with regards to the rate of maintenance. However, the main aim of proving that Lesser Used Timber Species (LUS) can be used for bridges has been achieved. Replicating this particular bridge configuration in the design for crossings wider than 8 metres brought to the fore short-comings, mainly to do with the rather deep sizes of I-girders.Timber truss bridges were looked at in a bid to overcome the challenges with I-girder bridges. At the design stages of this alternative bridge type, there are problems to do with the material and size of transoms, couplers at truss node points, lateral bracing methods and the need to proof test the integrity of joints. Where solutions were proposed, these are highlighted in this paper. The successful solution to the identified problems should increase the choice of forms of crossing structures available, make better structural use of LUS, introduce skills in the construction of timber bridges, engender an industry in pre-fabricated timber bridge components and improve commerce by the access provided by better transport infrastructure.

2.0

HIGHLIGHTS OF I-GIRDER BRIDGE

The bridge was designed to AASHTO HS-20-44 and American Interstate Highway loads. It is simply-supported over a span of 7.6m. The superstructure is made up of seven mechanically built I-girders, 1.143m deep. The girders are braced by timber cross-braces. The deck over the girders is made up of transverse 50x150mm timber members laid on edge and toe-nailed to previous members to form a continuous plate. Asphaltic concrete was applied over the deck and this forms the running surface of the bridge. The parapets are also timber. The I-girder is made up of a web of two layers of diagonally crossed planks (25x100mm) with the flanges bolted to the outside of the web members. The webflange system is fastened together by mechanical fasteners made up of screws and bolts (from 20mm and 25mm mild steel reinforcement bars). The deck is fastened to the

girders by toe-nailing and by bolts connected intermittently through 150mm long, 75x75 steel angle plates.

The substructure is made up of 22 end-bearing timber piles which also act as abutment and wing wall braces (columns). The abutments and wing walls are of timber planks and the piles are held together at their tops by timber pile caps. The pile cap provides a seat for the I-girder.

The I-sections were fabricated off site and given a preservative treatment by the use of chromated copper arsenate (CCA) under pressure. Treatment of site cuts and additional treatment of timber in direct contact with the soil was by a mixture (by volume) of 60% creosote and 40% bitumen, heated till almost boiling.

The mechanical properties of the timber used in various sections of the bridge are given in Table 1.0. A sketch of the arrangement of the girder at the abutment is shown in Fig. 1.0 and pictures of the existing bridge are shown in Figs. 2 to 7. Table 1.0:
Section

Mechanical Properties of Timber Species for I-girder Bridge


Timber Species Afina (Strombosia glaucescens) Kusia (nauclea diderrichii) Dahoma (Piptadenistrum Africanum) Kusia Dahoma Dahoma Density Kg/m 3 Mechanical Properties (Nmm2) Compressive Bending Modulus of Strength (Parallel) Stregnth Elasticity 24.5 17.0 12.5 17.0 12.5 12.5 25.0 17.6 12.5 17.6 12.5 12.5 18,500 14,500 10,600 14,500 10,600 10,600

Pile Wing/Retaining Wall Pile Cap Girders Floor Deck Parapet

900 760 720 76.0 720 720

At the time of construction, the cost of the timber bridge, at $72,000 compared favourably with an assumed equivalent reinforced concrete crossing (4.0 x 4.0m, box culvert, 11.50m long) which was $92,000 (Allotey, 1992).

FIG 2 FIG 3

FIG 5 FIG 4

FIG 6

FIG 7

3.0

PROBLEMS WITH I-GIRDER

Problems of the prototype I-girder were those to do with construction and the structural configuration as regards its use with spans longer than 7.6m (Allotey, 1992).

3.1 (i)

Construction Problems Slanted Piles The piling machine used was defective and had no feature for

maintaining the poles in line and in a plumb position. Some piles became slanted and though the slants were not excessive they were likely to: introduce considerable moments at the base of the piles by the applied vertical load at the pile head and the eccentricity of the slant; result in the pile cap not sitting centrally on the piles; make the backs of the piles to receive the retains/abutment out of line.

The foregoing problems were solved by a combination of use of braces, (using same material as the pile) in-between piles to form a truss-like support, finding the line of best fit between the two end piles of an abutment and arranging the centre of the width of the pile cap to lie on this line and fastening timber packing in the gaps at the backs of piles till a plane back is achieved to receive the abutment planks.

(ii)

Size of I-girders Because of the design loads used, AASHTO H20-44, the I-

girders were rather deep (1.143m) for the span considered (7.6m). Such deep girders required the use of heavy hoisting equipment (cranes) and resulted in major (and costly) earthworks for the approach roads to align with the bridge deck. Also, an increase in span beyond 8m will call for even deeper I-girders or the use of midspan piers; a situation which will be expensive on account of the construction of piers, the prolonged use of heavy lifting equipment and the inconvenience of working with large-sized sections (DFID, 1999, Solomon-Ayeh et al., 2002).

If timber bridges are to be used as crossings for spans larger than the foregoing then the identified shortcomings of large girder depth, weight and size, number of superstructure timber members and the very many fasteners must be overcome. The choice of a structural configuration different from the I-girder should be looked at and truss bridges and stress laminated decks come readily to mind. Stress-laminated decks offer considerable equipment and technical difficulties if opted for in the Ghanaian setting since its a novel technology and the funds outlay in the acquisition of the relevant equipment can only be justified if more of such decks are envisaged.Timber truss bridges were looked at in collaboration with TRADA Technology, U.K., because they have potential advantages such as: fewer superstructure materials; flexibility in spans and permissible loads by the use of modular construction using pre-fabricated components; use of fewer fasteners; use of a variety of medium-sized hoisting equipment; fabrication technology and equipment needs within Ghana.

4.0

TIMBER TRUSS BRIDGE

4.1

Highlights

The initial truss bridge proposed was a Warren through truss of 6m triangular modules, fastened at their nodes by steel couplers. Timber (Afina) round poles, of 300mm were

proposed for the members of the truss. The transverse transoms were to be either steel 533x210x92 universal beams (UB) or 1500x250 (300kg/m) mechlam assembly. Stringers were to be 254x146x46 UB or 525x250 (105kg/m) mechlam. The running deck was to be of 50x100 dahoma (D50) toe-nailed lumber and 50x250 dahoma running decks (DFID, 2001).

The design depended on U-frame action for bracing and the same 300mm

Afina poles

were utilized as members of a horizontal truss bracing at the top of the through bridge.

The configuration was arrived at from designs to nominally span 20 metres and to full HA loading and 20 HB (abnormal) loading.

Mainly due to objection to a through truss bridge and the insistence of higher design loads by Ghana Highway authorities (Section 4.2), the configuration of a through truss was changed to a modified Warren half-through truss of 3.0m triangular modules to span distances ranging from 12m to 25.5 metres (in 3-metre modules) (Solomon-Ayeh, 2002, 2004). Other features of the modified bridge were: transverse bracing using 300mm Afina poles diagonally placed between the top

chord of the truss and the horizontal extensions from the transverse transoms; flitch beam (steel/timber) transverse transoms; 150x150mm stringers.

Round timber (Afina) poles were preferred for the truss members (of both truss designs) because these poles: are available in the required lengths; are inherently stronger than processed timber; have a relatively low taper; come in manageable girths (approx. 300mm).

Some design and potential fabrication problems were identified and these are presented.

4.2

Design Challenges and Their Solution

4.2.1

Design loads

The bridges were meant for low-volume roads. Such bridges were predominantly in rural areas which happen to be the source of cash and food crops (cocoa, maize, roots and tubers) and timber logs. These items are heavy. Bridges built on any road should be such as to carry such heavy loads and all others. Also, enforcement of loading regulations on roads in Ghana is not regular and virtually non-existent on rural roads. Thus, the advice of the bridge authorities was for a full HA loading (normal) and a 45 units HB abnormal loading (by British Standards). Such design loads will produce very deep and heavy timber members, and deep trusses of multiple chord members. For the transverse transoms, the depth of the timber members can only be minimized by the use of steel universal beams (UB). Thus the simplicity, use of LUS, economic cost, compatibility and aesthetic appeal inherent in the use of timber would have been lost.

Where design loads for bridges are concerned, the magnitude of the values depend not only on the envisaged weight of material to be carried, but more importantly, on the frequency of their passage on the crossing structures. A heavy load which is infrequently passed on a bridge will produce little distress to the bridge. Also, a single-lane bridge (typical for low-volume roads) puts less load on bridges. TRADA/BRRI took this view and hence designed the original bridge to 20 units HB loading, and to be of single-lane to reduce member sizes. Even with this, steel UBs were specified for the transverse transoms.

The modified truss bridges, were in some instances, to be sited in more populated areas and thus the abnormal load (HB load) was put at 30 units, though the single-lane

10

carriageway was maintained. Also, the transoms were spaced at 1.5m centres to reduce their sizes (though their numbers were increased). 4.2.2 Dimensions of Chord Members and Transoms

For design to spans of between 20 and 27 metres and for 30 units of HB loading, the required capacity of the top and bottom chords suggested 4No. 300mm (Solomon-Ayeh, 2002, 2004). Afina poles each

The transoms will require a capacity to satisfy both I (moment of inertia) of 275.1x10 6mm4 and Z (modulus of elasticity of 34.6x10 6mm3. If round Afina poles are to be used, four (4) poles will be required. The use of mechlam timber (300x75mm basic unit) will require a beam of 300x750mm size. Both solutions will result in unwieldy members, will be heavy and in the former case, be particularly difficult to couple into the truss structure. A composite (fliched) beam was resorted to for the transom, made up of two confining 12mm thick x 225mm wide steel plates and 4No., 225x75mm timber (D50) pieces. The overall dimensions of the flitched beam was 225x375mm (Table 2.0).

4.2.3

Connection at Nodes

Connection at the nodes of the truss in the original TRADA design were of three types, depending on the method of load transfer (DFID, 2001). (i) Transfer of tension forces from pole to nodes

High tensile forces (40 tonnes) are transferred between the timber member through steel couplers. A single plate, set in a kerf cut along the centerline of the pole, is secured with one row of steel dowels (bolts) of 38 to 50mm (ii) Transfer of tension forces to nodes (from pole)

Poles will terminate in axial steel connecting plates and the node will comprise of steel-tosteel connection and bolts will be used. This configuration is simple and minimizes or avoids the tendency of the movement in the truss due to loose joints.

11

12

13

FIG 10

14

Transfer of compression forces from pole to nodes The end-bearing capacity of the timber pole (proved the use of Afina as piles) is exploited by designing a single plate which will bear on the end of the pole and is welded to a second plate set in a kerf cut along the centerline of the pole and is secured by bolting.

The modified truss bridge design (Solomon-Ayeh, 2002, 2004) uses the attachment to the pole through a kerf cut set in the centerline of the pole, as above, in case of spans of below 12 metres. For spans above this, and particularly for more than 24m, where four (4) poles are to be used in both chords, a torso-shaped coupler will be used where two poles will be attached to each arm of the torso ; one on each side of the arm. Two bolts (32 to 50mm size) will secure the poles through the steel arm. The base of the coupler will be attached (by bolting) to the confining bracket of the flitched beam transom. The arrangements are shown in Figs. and 9.

The size and types of fastening envisaged in both truss types call for proof testing of the nodal joints to validate the design options chosen. The tests are to be carried out at the BRRI when the necessary equipment becomes available. It is hoped that at the end of this activity, vital skills in proof testing of joints in timber and other materials will have been established at the BRRI as part of any collaborative effort.

4.2.4

Vehicle Containment and Through Truss Bridges

The initial TRADA design (DFID, 2001) was for a through truss bridge. For such a bridge, the vertical and diagonal members are vulnerable to vehicle impact and given the generally undisciplined nature of driving and lax enforcement procedures in Ghana, this option was found unacceptable by the bridge authorities. A half-through truss was therefore proposed (Section 4.2.3). Whist this option is possible, there is a concern for the torsional rigidity of this truss and the large number of connections required. The former concern is partly negated by the proposed use of diagonal pole braces at alternate transom positions (i.e. at 3.0m centres).

15

The risk of vehicle impact on truss members is to be minimized by ensuring adequate vehicle containment. The containment must safely direct or re-direct if necessary, the path of the vehicle travelling across the bridge. Timber handrail (with diagonal bracing) will be used for vehicle containment (Fig. 10).

5.0

ERECTION AND TENTATIVE COSTS

The proposed half-through bridge, being modular and with individual components of manageable sizes and weight can be assembled quite easily on site on trestles or erected on prepared ground behind one abutment. Launching can be by crane or tractors commonly used to haul timber logs in the bush. For launching, the deck, which accounts for about a third of the total self-weight of the bridge can be temporarily omitted. The estimated cost of a typical25.5m bridge in 2004, was $57,000, made up of: $30,000 6,000 5,000 7,000 9,000 $57,000 Cost of materials, off and on-site assembly Excavation, materials and construction of abutment. Launching of bridge. Transportation, tools and equipment Supervision (off and on-site)

The estimated cost of the proposed through truss bridge was $46,000 in 2001.

6.0

CONCLUSION

Structural designs using realistic design loads have shown that it is possible to use Afina round poles as main members of truss bridges in Ghana, to span crossings above 8 metres. The designed spans are recommended to be to a maximum of 24 metres. Distances above 24m will need to be spanned by the introduction of piers in the crossings and the provision of simply-support truss bridges in modulus of 12m, 18m, 21m, 24m, etc.

16

Configuration of nodal couplers have been given to support the large loads and the many members typical of half-through trusses and the high abnormal (HB) loading used. The integrity of these couplers have to be validated by proof test loads, preferably at the BRRI, if the requisite equipment is made available. The proof test loads will equip local personnel with the valuable knowledge in proof testing of joints of timber and other materials

Overall, the success to be achieved when these bridges are constructed will include the engendering of an industry and market in the fabrication of modular bridge components and making of the transportation of people, goods and services safer and less expensive.

6.0

REFERENCES

ALLOTEY, I.A. (1990). Laboratory tests on mechanically built-up timber girder for bridge construction. Materials and Structures, Vol.23, No. 137; pp. 372-380. ALLOTEY, I.A. (1992). Design and construction of a new timber Bridge in Ghana: Problems and Solutions. ASAE Technical Paper No. 924558. International Winter Meeting of the American Society of Agricultural Engineers, Nashville. DFID PROJECT CNTR 986147 (1999). Timber bridges a review. TRADA Technology, High Wycombe, 40pp. DFID PROJECT CNTR 986147 (2001). Bridge specification and design options. TRADA Technology, High Wycombe, 12pp. SOLOMON-AYEH, K.A., ALLOTEY, I.A., FOLLETT, P., JAYANETTI, L. (2002). Advances made in transportation structures by the design and construction of timber vehicular bridges in Ghana. Proceedings of IABSE Symposium, Melbourne, pp. 442. SOLOMON-AYEH, K.A. (2002). Proposed design of timber bridges on feeder roads in 5 regions for the Department of Feeder Roads. Unpublished design report for the Department of Feeder Roads, Ghana.

17

SOLOMON-AYEH, K.A. (2004). Final (Draft) bridge design and specifications for the design of three timber vehicular bridges at the Mole National Park. Ministry of Lands and Forestry (Game and Wildlife Division) (Unpublished).

18

You might also like