Action Schedule

GARYOUNIS UNIVERSITY, LIBYA

ACTION SCHEDULE

Key to Priority: 4 - URGENT

A = Action

3 - High impact, immediate stress to close dates. M = Monitored Urgent attention required 2 - medium impact, if not resolved by due date will put close date under stress 1 - low impact, no immediate need to resolve

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 25.9.10 1.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Completion of Arch. Survey on 30 Sept.10 Architectral Issues submitted on 11.11.2010. M+E still outstanding To confirm which department and rooms are currently fully utilized LAD feedback meeting corpus to set up meeting influence/ co ordination with existing buildings/ services, Corpus will confirm all meetings required as discussed at this meeting for attendance next week Subject to receipt of adequate servey information. Arcadis will review cluster grouping and grid line referencing and set a meeting accordingly Contract confirmation required from Corpus and any actions for clients decisions Contractor feed back who will carry out this design work and when, consider local design teams capability 1. Portuguise contractors and others scope programmes requires / Interfaces 2.1 Sitewide logistic plans required incl.storage, compound offices etc. 2.2 Logistics/University disruption 3. Traffic Management check required against Stage C Report changes Arcadis were issued on 24. Sept. 10 a series of client instructions incl. revised dormitory layouts. LAD to adopt the design for dormitory. The stage C Report will require amending for client instructions as issued. Finalisation of substations required. Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Site survey existing status to be concluded

1.0 Coordination Meeting to share action between ARCADIS and Corpus

2.0 Coordination Meeting to share action between ARCADIS and Corpus 3.0 Coordination Meeting to share action between ARCADIS and Corpus

Understand what space is used and what is not used

25.9.10

1.10.10 M A

open

What space is under used?Which space has over capacity?

25.9.10

1.10.10 A

open

4.0 Coordination Meeting to share action between ARCADIS and Corpus 6.0 Coordination Meeting to share action between ARCADIS and Corpus

Schedule.skedule.programme for future meetings

25.9.10

1.10.10 M A

open

What can be relocated. New versus Renovation and or cluster grouping

25.9.10

1.10.10

open

7.0 Coordination Meeting to share action between ARCADIS and Corpus 8.0 Coordination Meeting to share action between ARCADIS and Corpus

Furniture/Fittings/Equipment provision.

25.9.10

1.10.10 M M A

open

Extent of new build v renovation scope/ blending uniformity approach Which design team is doing what?

25.9.10

1.10.10 M A

open

9.0 Coordination Meeting to share action between ARCADIS and Corpus

Transportation/ logistics.

25.9.10

1.10.10

open

10.0 Coordination Meeting to share action between ARCADIS and Corpus

Design Review proposed drawings for compliance /space layouts. (max teaching space and Dormitory accom/plant space/cluster faculty arrangements and Adjacencies. Landscape/M&E services option. (versus sustainability)

25.9.10 01.10.2010/ new target date 20.11.2010 M M M A

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 1 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 25.9.10 1.10.10 A 25.9.10 1.10.10 A 25.9.10 1.10.10 A 25.9.10 1.10.10 A 25.9.10 1.10.10 A Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis New built / new services Refurbishment / no new services Financial Meeting to be setup - Lump sum figure, agreed with the client day one, has no contingency Financial Meeting to be setup Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Review Internal space storey height planning for internal services Contractor is entitled to lump sum value

11.0 Coordination Meeting to share action between ARCADIS and Corpus 16.0 Coordination Meeting to share action between ARCADIS and Corpus 17.0 Coordination Meeting to share action between ARCADIS and Corpus 18.0 Coordination Meeting to share action between ARCADIS and Corpus 20.0 Coordination Meeting to share action between ARCADIS and Corpus 22.0 Coordination Meeting to share action between ARCADIS and Corpus 25.0 Coordination Meeting to share action between ARCADIS and Corpus 27.0 Coordination Meeting to share action between ARCADIS and Corpus 28.0 Coordination Meeting to share action between ARCADIS and Corpus 31.0 Coordination Meeting to share action between ARCADIS and Corpus 32.0 Coordination Meeting to share action between ARCADIS and Corpus 33.0 Coordination Meeting to share action between ARCADIS and Corpus 33.1 Coordination Meeting to share action between ARCADIS and Corpus 34.0 PM Meeting

open

Design can be flexible but at first we need staged discussions/agreements to off set any cost of changes with contractor. Movement/exchange of cost categories will need to be evaluated.(value engineering) buildability. Monitor abortive changes to programme reasons for delay/also establish extension new or refurbishment. From evaluation we will seek proposal from contractor to agree with client. (approval) Original programme (schedule) split into categories/mobilization/ design/ construction to be issued. Schedule to be developed with Milestones sequence and decant periods. Schedule to show tollgates for payments and reconciliation periods. Risk workshop

open

Financial Meeting to be setup

open

A 25.9.10 1.10.10 A 25.9.10 1.10.10 M 25.9.10 1.10.10 M 25.9.10 1.10.10 M 25.9.10 1.10.10 A A A A A A A A A A A

Corpus to produce a recovery programme to ensure the contractual end date is archieved. Collaborative tool to be put in place as soon as possible Copy to be issued recommencing 27. Sept. Corpus to issue the schedules for Arcadis review, recommencing the 27. Sept. Corpus agreed to issue when finalised. Date required from Corpus. Templates to be issued

open

open

open

open

open

open

Collaborative hub agreement

25.9.10

1.10.10 A A A A A A A

Evaluation setup

open

Design codes reassessment

25.9.10

1.10.10 A

Architectual Code (IBC)

25.9.10

1.10.10 A

Change Management workshop

27.9.10 TBD M M M A

35.0 PM Meeting

38.0 PM Meeting 39.0 PM Meeting 42.0 PM Meeting

3 3 3

Team to Debate Omissions discussed from our scope.(conference centre blending/ set standard). Short term look ahead schedules(3 weeks weekly update) 3 month look ahead Project Management Plan Contractor

27.9.10

4.10.10 M M M M M A A A A

27.9.10 27.9.10 27.9.10

4.10.10 4.10.10 4.10.10

M M M

Contractor Design Team to propose New/renovation division of codes to be utilised Corpus to discuss with LAD a full metric dimensioned set of drawings Based on design master plan prior to University Finalisation meetings for approval Contractors action to ensure conceptual design is aligned DELAYED DELAYED Meeting to be arranged documents to be issued for construction Meeting to be arranged documents to be issued for construction. Method statement review

open

open

open

open

open open open

44.0 PM Meeting

Health and Safety Plan / Report

27.9.10

4.10.10 M A

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 2 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 27.9.10 4.10.10 M 27.9.10 4.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Awaiting Corpus to provide the Project Management Plan to reach an agreement. A meeting is to be arranged to fully scope and understand what Corpus are proposing to ensure that the design is fully coordinated. Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Definition of lab. Test Standards, the list of required equipments,tests apparatus etc. For HVAC systems, i) quantity of centers, , reports and calculations (LAD), ii)definition and endorsement of design concept on infrustructure works such as gallery,pipe bridges and underground iii) Identification of design concept of heating systems such as Boiling water,hot water etc. and determination of chiller equipments type and concept. Identification and agreement of Fire protection systems to be used,determination of the facilities under the scope of Utility Center area (in whole campus)and preparation of the report(LAD-ARCADIS) Taking into consideration of using solar energy heaters for provision of hot water in terms of Sustainabilty where requires and found in the scope of work . Advises of ARCADIS. The information and report about building automotion systems,what should be the scope?

46.0 Case List from Corpus

47.0 Case List from Corpus

open

49.0 Case List from Corpus

27.9.10

4.10.10 M A

Designmeeting in respect to this subject is to be set by Corpus. German DIN codes has been agreed.

open

51.0 Case List from Corpus

27.9.10

4.10.10 M M M A

Corpus to set up a Sustainability Meeting to address all possible oportunities. Corpus to set up a Building Automotion Systems Meeting to address all possible oportunities. Corpus to discuss this statement further.

open

52.0 Case List from Corpus

27.9.10

4.10.10 M M M A

open

53.0 Case List from Corpus

GN-The resolution of the status of GN Engineering company, the opportunity to find another company instead of them and having a contract. (Kayaalp) It is required to abstract of Heating and Cooling loads,the volume of fire water and service water to be used input-data for central campus . The protocol needs to be signed accordingly. Following the actual conditions review,there are some uncertainity came up(about the replacing,renewing or new installation which is not existing). The scope need to be agreed and clarified by ARCADIS. Need to prepared a Protocol and signed by all parties. Determination and selection of the brands,types of materials to be used for renovation.

27.9.10

4.10.10 A

open

54.0 Case List from Corpus

27.9.10

4.10.10

55.0 Case List from Corpus

27.9.10

4.10.10

56.0 Case List from Corpus

27.9.10

4.10.10 M M A

Corpus has an overall scope to provide all infrastructure to the complete site. A meeting is to be arranged to discuss this specific issue. A protocol is to be set up following a complete submission of full signed survey on refurbishment and infrastructure. Dates to be reconfirmed to allow the team to set up a meeting accordingly. Arcadis will provide a tick list against a schedule of materials that should be issued from Corpus for our consideration.

open

open

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 3 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 27.9.10 4.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis All subject to receipt of site conditional suvey of conditions. Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Clarification and giving a decision for preservation of existing facilities/systems or if it needs to replace , it is required to decide with a protocol for which system is going to be considered at ; 1)The pipe bridges at Faculty of Science, 2)Pipes in the gallery,supports and fittings 3)Old boilers at exisiting heating center and treatment&nitrogen systems 4)Chiller in the exixsting cooling centers Consolidation of the required capacity of old ,new and future planned Buildings in terms of heating,cooling,service water and fire water systems to find out ant to plan the whole campus requirement. Definition of the status of buildings out of our scope such as "Library" , and the service loads of them and decision need to make for the requirements of these buildings and to be signed of a protocol. Determination of alignments ,location of facilities/plants and their quantitites. Review of LAD transmittals such as: Gate Border Wall 21.09 Design Narrative 22.09 Campus Plan Update 22.09 Energy systems &Mep Report 22.09 Dormitories 24.09

57.0 Case List from Corpus

58.0 Case List from Corpus

27.9.10

4.10.10

All subject to receipt of site conditional suvey of conditions.

open

59.0 Case List from Corpus

27.9.10

4.10.10 M M M A

Proposal to be prepared by Corpus Official transmition required. If there are any cost adjustments these are to be provided. When in receipt of this Arcadis will review as a status as to wheither it is foe either information or our action. Should it be for our action we will seek a clients approval accordingly. Cost Management Meeting to be arranged by Corpus at the earliest.

open

61.0 Case List from Corpus

27.9.10

4.10.10

open

62.0 Case List from Corpus

64.0 Case List from Corpus

65.0 66.0 67.0 68.0 69.0

Case List from Corpus Case List from Corpus Case List from Corpus Case List from Corpus Case List from Corpus

3 3 3 3 3 3

The BoQs need to be distrubuted in percentage subjected to main BoQsgiven in the contract and shall be expected to get the approval from ARCADIS. Project Coordination Procedures such as below: 1) Planning and Scheduling Procedure 2) Project Communication Procedure 3)HSE Management Plan 4) Project Quality Plan 4.a) Quality Control Procedures 4.b) ITPs 4.c)Other Executive Control Plans and Procedures (Such as Orientation and Training Procedure, corporate procedures) 5)Project Control Plans 6)Risk Management Plan

27.9.10

4.10.10 M A

open

27.9.10

4.10.10 A

27.9.10 27.9.10 27.9.10 27.9.10 27.9.10 27.9.10

4.10.10 4.10.10 4.10.10 4.10.10 4.10.10 4.10.10 M M

A A A A A

70.0 Case List from Corpus

A A A

71.0 Case List from Corpus 72.0 Case List from Corpus

3 3

27.9.10 27.9.10

4.10.10 4.10.10

Individual meetings are to be arranged by Corpus to capture all these items referred to. see above item 64 see above item 64 see above item 64 see above item 64 Not sure what ITP means. Will form part of Corpus Project Management Plan procedures document. as above item 70 as above item 70

open

open open open open open open

open open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 4 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 27.9.10 4.10.10 M M Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis as above item 70 A Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Change order / variation order process control. How it would be managed? It should have been bothside aggreed in case of any change and variation requirement raised in the project. LANDSCAPE CONCEPT DESING IS SUPERSEDED AND THE FEATURES AND REQUIREMENTS IN STAGE C HAS TO BE APPLIED. NAMAR EDUCATIONAL CONSULTANT'S REPORT AND PRESENTATION(WILL BE HELD ON 24.09.2010,THURSDAY , 15:00 )

73.0 Case List from Corpus

75.0 Case List from Corpus

27.9.10

4.10.10 M M A

Please clarify if there are any extended actions with this comment. From this Namar Report Corpus are to extend this current information to establish from each faculty which departments ,number of rooms to each department and number of students to each room to ensure the design develops accordingly. Please can we receive from Corpus their Design Management process details. When we are in receipt of relevant information we will respond accordingly.

open

77.0 Case List from Corpus

27.9.10

4.10.10

open

78.0 Case List from Corpus

PROCEDURE FOR DESIGN PROCESS MANAGEMENT HAS TO BE DRAFTLY COMPLETED. GETTING THE APPROVAL FROM OWNER AND ARCADIS TO START CONSTRUCTION OF FOUNDATIONS IN TERMS OF GETTING 50% DD DONE. 329,400 m2 check design

27.9.10

4.10.10 M A

open

79.0 Case List from Corpus

27.9.10

4.10.10 M A

open

80.0 Review Corpus/LAD contract signed on 02.09.10 81.0 Review Corpus/LAD contract signed on 02.09.10 82.0 Review Corpus/LAD contract signed on 02.09.10

26.9.10

3.10.10 M A

Check design/schedules

open

Exhibit A B CD E F require copies

26.9.10

3.10.10 M A

Not attached copies required please We need to understand the term kick off meeting they probably mean different things to different people. Concerns that there is not any visitation to oversee the detailed design stages in their agreement.Who is ultimatley responsible for this very important coordinanation/with in the Corpus design team Constructability monitoring of the design and construction activities as they both develop.Corpus to present information in a timely manner for our review and monitoring.

open

Verification of m2 @client kick off meeting

26.9.10

3.10.10 M M A

open

83.0 Review Corpus/LAD contract signed on 02.09.10

Working drawings by others (what about overseeing)

26.9.10

3.10.10

open

84.0 Review Corpus/LAD contract signed on 02.09.10

Client advise support on constructability to meeting clients programme and budgets.

26.9.10

3.10.10

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 5 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 26.9.10 3.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis What local practices will be considered?Lets discuss this with Corpus/We need to identify as early as possible a schedule of materials that are importat to control for quality Infrastructure /master plan and high voltage we understand is the responsibility of Corpus. The scope requirements to be issued from other separate contractors to be collected by Corpus /Corpus to share how this will be done and what are the risks associated with not receiving this information in a timely manner. LAD to submit current and up-to-date organisational chart Corpus or the client to issue all contract agreement information we require clean copy of original. as above Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Step by step support for constructability materials an local practices

85.0 Review Corpus/LAD contract signed on 02.09.10

86.0 Review Corpus/LAD contract signed on 02.09.10

Services include Arch /Structural/M.E.P/ communications(IT) low voltage, Fire protect/eng, interior/arch design

26.9.10

3.10.10

open

87.0 Review Corpus/LAD contract signed on 02.09.10 88.0 Review Corpus/LAD contract signed on 02.09.10

Review names in contract against those on project? 45 names in 3 disciplines, phases, sqm, etc. Compensation clauses have been removed?

26.9.10

3.10.10 M A

open

26.9.10

3.10.10 M A

open

89.0 Review Corpus/LAD contract signed on 02.09.10 90.0 Review Corpus/LAD contract signed on 02.09.10 91.0 Review Corpus/LAD contract signed on 02.09.10 93.0 Review Corpus/LAD contract signed on 02.09.10

Phase1 payment prel. schematic 20% of....?.... Phase2 payments schematic 30% of.....? Phase3 50% design 50% of .....?

26.9.10

3.10.10 M A

open

26.9.10

3.10.10 M A

as above

open

26.9.10

3.10.10 M A

as above

open

Client agreed to 30% +/- m2 fee to be adjusted accordingly

26.9.10

3.10.10 M A

94.0 Review Corpus/LAD contract signed on 02.09.10 95.0 Review Corpus/LAD contract signed on 02.09.10 96.0 Review Corpus/LAD contract signed on 02.09.10

Fee rate removed??????

26.9.10

3.10.10 M A

Current status to be establish now that we have client confirmation of changes to stage c scope. as above

open

open

Final m2 to be approved as final. When? Max adjustment to o/a increases in m2 is 15% e/o will be negotiated.

26.9.10

3.10.10 M A

as above

open

26.9.10

3.10.10

Contract relates to the contingency.Corpus to reavaluate if any changes have been agreed which would need acceptance or adjustment in their next payment request for evaluationSee addendum that has not been signed off where are we going?

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 6 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 26.9.10 3.10.10 M Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis We require electronic tranfer system and controls to assist where there is a limitation of visitations of the LAD design team. Check see addendum some added some removed?Corpus to confirm how this contraint can provide certainty in the design programme. Is this necessary if we set up a an electronic system of documentation controls.Note this is an additional cost if more the (3) attend. see above Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description One person full time in Libya 9wks only+(3) visits (4persons) for 7 day durations.(includes travelling time)Travel costs and living accomodation excluded. Agreed to provide 12 assigned buildings/groups and programme statement at kick off meeting??

97.0 Review Corpus/LAD contract signed on 02.09.10

98.0 Review Corpus/LAD contract signed on 02.09.10

26.9.10

3.10.10 M A

open

99.0 Review Corpus/LAD contract signed on 02.09.10

Confict (7) persons required at each visit?

26.9.10

3.10.10 M A

open

100.0 Review Corpus/LAD contract signed on 02.09.10 101.0 Review Corpus/LAD contract signed on 02.09.10

PM/DM/Planner/Sen Arch,civil,mech.elec. Meetings agreed are for Programme verification/prel schematics

26.9.10

3.10.10 M A

open

26.9.10

3.10.10 M A

102.0 Review Corpus/LAD contract signed on 02.09.10 103.0 Review Corpus/LAD contract signed on 02.09.10 104.0 Review Corpus/LAD contract signed on 02.09.10 105.0 Review Corpus/LAD contract signed on 02.09.10

Phase 2 Schematic (2) trips start and end for (4) people for 7days incl travelling time. Phase3 50% design development 50% ofdesign start/end of 50% of Dd of effort. Included overall are 24 overall renderings for external /internal =3d imagery. 10 sets of all deliverables

26.9.10

3.10.10 M A

Where are we what has happened to date how many meeting has LAD attended?Programme require to understand the next move. as above

open

open

26.9.10

3.10.10 M A

as above

open

26.9.10

3.10.10

M
26.9.10 3.10.10

106.0 Review Corpus/LAD contract signed on 02.09.10 107.0 Review Corpus/LAD contract signed on 02.09.10 108.0 Review Corpus/LAD contract signed on 02.09.10

Establish if there are any sub/contract agreements in place

26.9.10

3.10.10 M

Phase approval before next by client

26.9.10

3.10.10 M A

International Building code2006Edition(IBCstandards)adopt ed

26.9.10

3.10.10

109.0 Review Corpus/LAD contract signed on 02.09.10

Approvals (2) days ideally if exceeds 14days additional time will be added to programme

26.9.10

3.10.10 M

What has been produced to date ,we need to establish from client what is going to be required. Computer aided red line opportunities will need to be implemented. Print copy numbers requirements for Arcadis.Check Corpus ability to service printing needs also??????? Corpus to advise which sub contracrt agreement are in place for both precontruction ac Has any approved been achieved to date, programme milestones to be shown on programme German dims are to beused to set the standard and avoid any confusion All drawings are to be produced as full metric and not in imperial and converted Milestones on programme required

open

open

open

open

open

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 7 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 26.9.10 3.10.10 M Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Check programme Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Phased durations (1)100,000m2 prlims= 2-3 wks/(2)2-3wks/(3) 89wks=max 14 weeks subject only to decision delays or and flight booking delays. Text does not align with table below

110.0 Review Corpus/LAD contract signed on 02.09.10

111.0 Review Corpus/LAD contract signed on 02.09.10 112.0 Review Corpus/LAD contract signed on 02.09.10 113.0 Review Corpus/LAD contract signed on 02.09.10

26.9.10

3.10.10 M

Check programme

open

M M

A Check programme open

114.0 Review Corpus/LAD contract signed on 02.09.10 115.0 Review Corpus/LAD contract signed on 02.09.10 116.0 Review Corpus/LAD contract signed on 02.09.10

Text on table should represent the overal programme.Either way all phases to run in paralell. Outline of summary listing quantities and qualities of outline spaces of each building draft/questionaire to be provided for stage 1.this to be provided prior to kick off meeting,for review Ref agreed at staged kickoff meetings

26.9.10

3.10.10 M A

26.9.10

3.10.10 M A

copy is required

open

26.9.10

3.10.10 M

Check programme

open

M M

A All names and contact details required 45 people Copy required open

Name of regional director ofeastern Europe required Adendum to Contract with Corpus check who has seen this is this been approved?Main points: 326,895.00m2 Lecture hall added plus see programme dates. Addition entrance gates/walls No fee adjustsments made for lee m2 + gates/walls adj Which action is required from Arcadis for the documents listed in Transmittal Forms TR-GN-000006 and TR-GN000007 (For Information, For Review and Comment or For Approval)? Approval of "Engineering Narratives_22_09_10 (LAD)"

26.9.10

3.10.10 M A

26.9.10

3.10.10

open

117.0 Document Control

28.9.10

5.10.10

As discussed between Leslie and Alp on 28. Sept.

open

123.0 Document Control

29.9.10

13.10.10

125.0 Document Control

Approval of "Master_Plan-24.09.2010HEAT"

29.9.10

13.10.10

Document has been submitted within the Transmittal Form TR-DE000012 on 27.09.2010. It is saved on our Hard Disk Drive. Document has been submitted within the Transmittal Form TR-DE000012 on 27.09.2010. It is saved on our Hard Disk Drive.

open

open

128.0 Clarify specs of exterior wall / fence

129.0 Collecting Approvals 132.0 Design Review

3 3

133.0 134.0 135.0 136.0

Design Review Design Review Design Review Design Review

3 3 3 3

There is a lack of information regarding Campus Security Concept. Proposed design suggestions should reffer to Security issues Corpus to submit all approvals given by the client until now Corpus to provide updated sqm schedule for each building measured externally Copy of testing regime Ceiling specifications Roof test regime Roof replacement status by others

29.9.10 13.10.2010 20.11.2010

open

M M M M M M M M M

A A
25% circulation space open open

29.9.10

1.10.10

28.9.10 05.10.2010 20.11.2010 28.9.10 28.9.10 28.9.10 28.9.10 5.10.10 5.10.10 5.10.10 5.10.10

A A A A A
open open open open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 8 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 28.9.10 5.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Relocation design map showing that there are no holes in the delivery of the design, organisation with communication links also. Programme required Method statement for cleaning regime required within refurbishment scope Spread sheet identifying what is the current status of the inclusion of stage C report.We also require from Corpus any desciptions that are not provided in the stage C report. We would ask that from the Excel spread sheet it is marked up in Red and green for the above status controls Recent Option/ cost evaluation for agreed standard/design for dormortory designs presented Copy of specification/Criteria set for all scope/ specification for refurbishment Accreditation report to be expanded to provide from a review of the current Faculties to ensure that in order to provide this accred, we have the correct number of departments and rooms provided to achieve this.We also request confirmation that Dept/ Room services provisions are adequate for the accreditation Scope required for barrier free design that is to be included for both new, refurbishment and infrastucture. Corpus to provide a Survey on the condition of the existing border walls. Based on these surveys a flexible design option will be develloped by LAD. Corpus mentioned that there are a few verbal agreements between Corpus and ODAC. It is neccessary to clear this Clarify 50 % developped design in the contract between CORPUS and LAD FS for new buildings FS for old buildings FS for rescue and fire-work -beside structural and M+E -Acoustic -Geologist -Building physist -Sprinkler expert For a fast approval process it is neccessary to reconsider the forbiddance of direct contact.

137.0 Design Review

M
28.9.10 28.9.10 28.9.10 5.10.10 5.10.10 5.10.10

A A A
open open open

138.0 Design Review 139.0 Design Review 140.0 Design Review

3 3 3

M M

141.0 Design Review

28.9.10

5.10.10

open

M
28.9.10 5.10.10

A
open

142.0 Design Review

M
28.9.10 5.10.10

A
open

143.0 Design Review

145.0 Design Review

28.9.10

5.10.10

open

M
29.10.10 21.10.10

A
open

159.0 Gate and Border Wall

M
29.9.10 29.10.10

A
open

160.0 RFI CORPUS Unwritten agrreements with client

M
29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.9.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10 29.10.10

A M M M M M M M M A A A A
open open open open open

161.0 RFI CORPUS What means 50 % DD 162.0 RFI and Meeting FireSafety 163.0 RFI and Meeting FireSafety 164.0 RFI and Meeting FireSafety 165.0 RFI and meeting expert engineer 166.0 RFI and meeting expert engineer 167.0 RFI and meeting expert engineer 168.0 RFI and meeting expert engineer 169.0 RFI and meeting expert engineer 170.0 Discussion: forbiddance of direct contact between Designer Arcadis

3 3 3 3 3 3 3 3 3 3

M M M M M

M M M M M

A A A A A

open open open open open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 9 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 29.9.10 29.10.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description -to involve the structural and M+E engineers asap. -to clear the interfaces between LAD and local architects. -to agree concerning file system, layer system and if possible about CAD system Preparation of presentation concept for: renovation, new building design and site plan concept including landscape CORPUS and LAD work internal on basis of IBC 2006 regardless of we decided to use DIN standard. Discussion about most used DIN codes and less used ones, concerning Benghazi project

171.0 Design meeting between CORPUS LAD and local architects 172.0 Design meeting between CORPUS LAD and local architects 173.0 Design meeting between CORPUS LAD and local architects 174.0 Preparation for design meeting with ODAC

M
29.9.10 29.10.10

M M M M M M

A
open

M
29.9.10 29.10.10

A
open

M
29.9.10 29.10.10

A
open

M
30.9.10 15.10.10

A
We have to emphase very clear that this is a running breach of agreement. -we can't judge about importance, the entire DIN collection is agreed and valid, but it is possible to say how often a special DIN Code relevant topic will arise open

175.0 DIN versus IBC

M
30.9.10 15.10.10

176.0 Review DIN Codes

open

177.0 Collecting approvals 178.0 Clarification on Building Codes in respect to materials 179.0 Responsibilities facade renovation

2 3

180.0 Surface mounted installation i.eElectrical fittings 181.0 Change of use in renovation areas 182.0 Dimension of doors etc.

Corpus to submit all approvals related to renovation works to Arcadis How to deal with building codes in existing buildings. Probably they refer to American standards Acc. to Corpus facades not within their scope. Who's dealing with that in managing, co-ordination, and financial issues? How to proceed with surface mounted installation in renovation areas? Define procedure if usage of rooms/floors/departments will be changed - standards, M&E issues. In order to define the building codes in existing builtings dimensions of assembly parts to be checked Clarify whether colour concept according to Stage C Report to be used in renovation areas Deadlines for clearing of construction/renovation areas prior to start of works to be defined and monitored "General Plan View" (Schedule) to be updated and more detailed Review and Comment "010 - Student Guest Houses - Women Engineering Narrative 01 - 1010"

29.9.10

04.10.2010 20.11.2010 20.11.10

M M

M M

M M

A A
Clear interfaces to be definded; M&E issues as for ex. cooling units on facades, etc. A general agreement has to be implemented Time and effort probably will exceed "renovation level"

open open

29.9.10

open

M
29.9.10

open

M
30.9.10

M M

M M M

M M M

A A A

open

M
30.9.10

open

M
30.9.10

M M

183.0 Colour concept

open

A
open

184.0 Clearing construction areas

30.9.10

M
1.10.10 13.10.10

A
divided in design and construction; key dates for each building Document has been submitted within the Transmittal Form TR-DE000015 on 04.10.2010. It is saved on our Hard Disk Drive. Document has been submitted within the Transmittal Form TR-DE000015 on 04.10.2010. It is saved on our Hard Disk Drive. open

185.0 Overall Schedule GUP

M
4.10.10 18.10.10

186.0 Document Control

open

191.0 Document Control

Review and Comment "Garyounis_Fire Protection_101001"

4.10.10

18.10.10

open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 10 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 2.11.10 15.11.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description LAD to update the Campus Plan dated 29.10.10 based on the presentation dated 02.10.10 and discussed comments In the masterplan for future development, LAD shall define the footprint of the Library Expansion. ARC requests area schedules, efficiency ratios, and relevant cross sections to be prepared and developed by LAD prior to and during schematic design. The format is to be agreed between LAD/ARC. ARC requests a study of traffic volume and flow, also incorporating number of parking spaces, and location from LAD. A road classification, reflecting types, i.e. pedestrian etc., is requested by ODAC. The width of lanes, pedestrian walkways,bicycle lanes, lighting and landscape is to be defined within the types. In view of the construction schedule and an early start of construction, stress is to be placed on the building footprint incl. all implication like e.g. distance to roads. LAD is to review and update the elevations, LAD is to provide sections, detail wall sections ARC to check design overall, i.e. dimensions, grids, acoustics etc. to achieve ODAC sign off of the building footprint. Generally, the programme and reqments for the SCC are to be reviewed between ODAC/ARC, and feedback will be given to LAD. Library area reqments are to be confirmed between ODAC/ARC. ARC recommends due diligence of existing facilities. LAD is to review and update the the pre schematic design plan according to the comments. ODAC/ARC will develop and advise on popular sports. The necessity for an Olympic standard pool is discussed andwill be assessed by ODAC LAD is to review and update the the pre schematic design documents according to the comments. ARC states the upper limit of allocated area is 103.000 sqm, Corridor widths are to be optimized by LAD,

193.0 Design Presentation 02.11.10 / LAD (issued 29.10.10) Campus Master Plan 194.0 Design Presentation 03.11.10 / LAD (issued 29.10.10) Campus Master Plan 195.0 Design Presentation 02.11.10 / LAD / General

M
3.11.10 20.11.10

A
open

M
2.11.10 15.11.10

A
open

196.0 Design Presentation 02.11.10 / LAD / General

2.11.10

15.11.10

open

M
2.11.10 15.11.10

A
open

197.0 Design Presentation 02.11.10 / LAD / Masterplan

198.0 Design Presentation 02.11.10 / LAD / Lecture Hall

2.11.10

15.11.10

LAD / Corpus to provide an updated plan

open

M
2.11.10 15.11.10

A
LAD / Corpus to provide an updated plan open

199.0 Design Presentation 02.11.10 / LAD / Lecture Hall 200.0 Design Presentation 02.11.10 / LAD / Lecture Hall 201.0 Design Presentation 02.11.10 / LAD / Lecture Hall 202.0 Design Presentation 02.11.10 / LAD / Students Culure Center 203.0 Design Presentation 02.11.10 / LAD / Students Culure Center 204.0 Design Presentation 02.11.10 / LAD / Sports Center 205.0 Design Presentation 02.11.10 / LAD / Sports Center 206.0 Design Presentation 02.11.10 / LAD / Sports Center

M
2.11.10 15.11.10

A A

open

M
2.11.10 22.11.10

M
2.11.10 22.11.10

Final Location and dimensions of the Lot to be clarified by Corpus meeting with Mr.Amer to be set up

open

open

A
2.11.10 22.11.10

A
2.11.10 22.11.10

meeting with Mr.Amer to be set up

open

M
2.11.10 20.11.10

A A

meeting with Mr.Amer to be set up

open

open

M
2.11.10 20.11.10

A
3.11.10 20.11.10

feedback will be given through ARC to LAD. / meeting with Mr.Amer to be set up

open

207.0 Design Presentation 03.11.10 / LAD / Science Buildings 208.0 Design Presentation 02.11.10 / LAD / Students Guest Houses

open

M
2.11.10 20.11.10

A
open

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 11 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 2.11.10 20.11.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description The elevation of the dormitories perceived as too repetitive by ODAC, LAD to develop a more varying treatment. The female quarters need to be revised and carefully considered

209.0 Design Presentation 02.11.10 / LAD / Students Guest Houses / Male 210.0 Design Presentation 02.11.10 / LAD / Students Guest Houses / Female

M
2.11.10 20.11.10

A
LAD is to provide sketch options. ARC will review, coordinate with ODAC and communicate back to LAD. open

211.0 Design Presentation 02.11.10 / LAD / Entrance and Enclosures

212.0 Design Presentation 02.11.10 / LAD / North Campus

In the design of Entrances and Enclosures LAD is to take into account findings of the traffic analysis. ARC to communicate with ODAC and fed back to LAD LAD is to review and update the the pre schematic design plan according to the comments.

3.11.10

20.11.10

open

M
3.11.10 20.11.10

A
LAD is to present sketch options, which show variety and explore the potential of three vs. two storey buildings. open

M
3.11.10 20.11.10

213.0 Design Presentation 02.11.10 / LAD / North Campus

214.0 Design Presentation 02.11.10 / LAD / North Campus 215.0 Design Presentation 02.11.10 / LAD / North Campus 216.0 Transmittal TR-EN000001 Principles of technical specifications for road construction 217.0 Transmittal TR-GN000018 / Lecture Hall Fence 218.0 Renovation Works / current status of the survey 219.0 Renovation Works

The buildings are serviced via the covered walkway, LAD to investigate if the new buildings can be serviced via the same route. A termination of the Academic Boulevard is needed, and LAD shall present suggestions. A termination of the Academic Boulevard is needed, and LAD shall present suggestions. Review and comment by ARC

open

M
3.11.10 20.11.10

A
open

M
3.11.10 20.11.10

A
open

M
6.11.10 17.11.10

A
open

A
3 Approval by ARC 6.11.10 20.11.10

A
Final Location and dimensions of the Lot to be clarified by Corpus open

A
3 Sembol to provide all as built drawings, building survey, quantity survey and calculations Sembol to provide a schedule for renovation works (including 6 weeks preview) by 09.11.10. Sembol t submit the requested document e.g. (with Concrete plant) Method Statements of activities to be submitted by GC Weekly Reports to be submitted Corpus to provide a proramme for Desgan meetings (including 6 weeks preview) GC to complete the Appartment No1 GC to complete the Appartment No2 6.11.10 20.11.10

open

M
6.11.10 15.11.10

A
open

M
9.11.10 15.11.10

A
open

220.0 Site Logistic Plan:

M
9.11.10 15.11.10

A
open

221.0 Renovation Works

M
9.11.10 8.11.10 11.11.10 20.11.10

A A M A A A
open open open open

222.0 Renovation Works 223.0 Design Programme

3 3

224.0 Staff accomodation / Villa 225.0 Staff accomodation / Villa

3 3

8.11.10 8.11.10

15.11.10 1.12.10

M M

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 12 of 13

Action Schedule

Last updated: 14.11.2010 Author: ARCADIS

Document No: GARUN-63-GN-GN-GN-MM-0001-00 Target Date Point Completion Logged Date 14.11.10 20.11.10 Project Director

ARCADIS
Commercial Constructio Architecture Mechanical Manager n Electrical Legal

CORPUS
Corpus Comments Arcadis Comments Corpus Current Status open Date Closed

Ref #

Activity

Priority 3

Description Clustering suggestion by ARC

226.0 Coordination Meeting to share action (clustering) between ARCADIS and Corpus

ARCADIS Deutschland GmbH

Print Date 15.11.10

Page 13 of 13