Professional Documents
Culture Documents
Underbalanced and Managed Pressure Drilling: Technologies for Improving Drilling Performance, Enhancing Production, and Reducing Project Risk
12-15 O October 2008 Ho Chi Minh City, Vietnam C C
Concept
Binary Geothermal Power Plant Heat Exchanger
4 4.5km
+ +
+ + +
270 C
0
+ +
Granite
Reserves Equivalent
Thermal equivalent of 50 Bbbls of oil 12 x greater than NW shelf gas reserves in W.A.
Habanero 3 Jolokia 1
Manifold rated to 10,000 psi Experimental control system High pressure flow meter Rig pump #2 for backpressure HP & LP PRVs
Manifold rated to 5,000 psi State of the art automation LP flow meter Dedicated pump
Connection Plot
Habanero 1
Drilled conventionally with 5kpsi BOP stack. Started with 11.8 ppg 11 8 Weighted up to 15.8 ppg
Over pressured, required 10kpsi BOP pressured Added to energy potential
Recurring kicks, H2O, CO2 , Methane Gas. g , , Mud degraded by influxes. Lost circulation / kicks Drilling NPT = 60 days
Better method of controlling pressure required
Habanero 2
Drilled w/ MW below pore pressure (UBD).
Maintained BHP at 15.3 ppg with between 75 and 300 psi backpressure. Encountered first fracture and stopped influx by increasing backpressure. Mud M d system not tolerant to f l formation water. i Drilled ahead maintaining constant bhp at top fracture. ROP 6 -12 ft/hr. Approx 1.5 days to round trip. Using heavy mud. Total losses into lower fracture. Unable to establish circulation with LCM and still drill ahead Could not reduce BHP and prevent influx from top fracture. p p Drilled mud cap at reduced pump rate with no apparent plugging. BHA failure, fish left in hole.
ST- 1
MPD to maintain BHP at +/- 14 9 15 3 ppg 14.9 15.3 ppg. Did not intersect fractures. Suspected plugging due to mud cap but directional problems?
Source: Presentation by Phil Frink Blade Energy Partners. Managed Pressure Drilling Geothermal applications SPE ATW, Phuket Thailand, June 11-14, 2006
ROP 5 20 ft / hr M 10 h Max hours d illi t drilling to reduce risk of bit failure. 3 days to round trip. Borehole stability? Hole cleaning problems. Drill string stuck / failures failures.
Source: Presentation by Phil Frink, Blade Energy Partners. Managed Pressure Drilling Geothermal applications SPE ATW, Phuket Thailand, June 11-14, 2006
Habanero 3
Drilled 300 feet UBD for kick detection.
Minor kicks. Adjusted backpressure to stop influxes. Flow out increased > 500 gpm. 1.2 ft bit drop. Increased backpressure to control influx. 16.1 ppg equivalent. 1200 psi maximum surface pressure. New bit design ROP 10 12 ft / hr.
14.8 ppg
In ncreased pump Q p
15.3 ppg
Ga at surface as
15.0 ppg
16. ppg .1
15. ppg .2
Jolokia - 1
Drilled 3770 ft UBD and MPD 150 psi minimum / 1000 p maximum backpressure. p psi p Initial fracture identification via kick then MPD. Further identification assumed on drilling breaks and gas. Average ROP of 5 8 ft/hr Well circulated to heavy mud for trips. Backpressure t reduce swab effects while t i i out. B k to d b ff t hil tripping t Approximately 1.5 days to round trip. No mud losses losses. Objectives met without incident.
Geodynamics Summary
Identified fractures using UBD. Initially stopped influxes with backpressure. Automated chokes with manual bhp setpoint. Minimized increase in mud weight. Eliminated NPT due to kicks / losses losses. HP UBD trips 2x as long as MPD. HP UBD / borehole stability / hole cleaning p y g problems. MPD borehole stability maintained. Short bit life due to granite and temperatures. Higher Hi h pressure RCD may b h l f l be helpful.
Reduce mud weight / solids. Reduce mud contamination problems.
Thank You
Special thanks to Geodynamics and Paul Fredericks, At Balance Americas for developing this presentation.