X= 00, 11, 22As built drawings Discipline M or E or I or C (Two Word) System under Discipline (Two Digits)
Year of Document Generation (Two Word) Supplier / Contractor Name (Two Words) Contractors Project Job No. (Three Digits)
M26 SE 12 CO M1 01
Contractor Mecwel Project job number For e.g. Siemens for turbine and Aux 2012 Control oil system Mechanical first doc. Rev no.01
X=0, 1, 2..
Till Approval
X= 00, 11, 22As built drawings Dwg/Doc size-A0 / A1 /A2 /A3 /A4 (Three Digits) Dwg/ Doc No (Three Digits) Tech. Spec. No.=>2 digit No i.e. 0 to99 Vendor Drgs: V (One Word) Discipline M or E or I or C (One Word) VM or VE or VI Supplier / Contractor Name (Two Words) Contractors Project Job No. (Three Digits)
M26 SE V 06 E25 A3 01
Contractor Mecwel Project job number For e.g. Siemens for turbine and Aux Vendor Drawing shall be marked with symbol V For example out of 12 packages we can assign Tech spec no.06 for Cooling water system Electrical document no.25 A3 size paper Rev no.01