Example The table below shows a pavement condition survey for sample unit 07, section JPB-KM2 of Jalan

Parit Botak. Determine the Pavement Condition Index for this sample unit.
JALAN PARIT BOTAK (ASPHALT SURFACED ROAD) CONDITION SURVEY DATA SHEET
BRANCH: TRAFFIC LABORATORY UTHM DATE: 25 AUGUST 2007 SURVEYED BY: BDD SAMPLE UNIT: 07 SECTION: JPB-KM2 SAMPLE AREA: 6 m x 100 m 01. Alligator Cracking (m2) 06. Depression (m2) 11. Patching & Utility 02. Bleeding (m2) 07. Edge Cracking (m) Cut Patching ((m2) 03. Block Cracking (m2) 08. Joint Reflection 12. Polished 04. Bumps and Sags (m) Cracking (m) Aggregate (m2) 05. Corrugation (m2) 09. Lane/Shoulder Drop 13. Potholes (no.) Off (m) 14. Railroad Crossing 10. Longitudinal & (m2) Transverse Cracking 15. Rutting (m2) (m) DISTRESS QUANTITY TOTAL SURVEY

16. Shoving (m2) 17. Slippage Cracking (m2) 18. Swell (m2) 19. Weathering/ Ravelling (m2)

DENSITY %

DEDUCT VALUE

03 M 01 L 01 H 11 M 13 M 10 L 10 M

7.8 2.5 6.3 3.1 0.5 0.8 0.7

4.1 4.2 1.8

0.4 0.8 1.2 1.1 0.3 0.4 0.5

Solution: (1) Determine the Distress Density and Deduct Value


QUANTITY TOTAL DENSITY % DEDUCT VALUE

DISTRESS SURVEY

03 M 01 L 01 H 11 M 13 M 10 L 10 M

7.8 2.5 6.3 3.1 0.5 0.8 0.7

4.1 4.2 1.8

11.9 8.5 6.3

0.4 0.8 1.2 1.1 0.3 0.4 0.5

3.5 1.3 2.8 2.2

100*(11.9/600 ) = 1.98 100*(8.5/600) = 1.42 100*(6.3/600) = 1.05 100*(3.5/600) = 0.58 100*(1.3/600) = 0.22 100*(2.8/100) = 2.80 100*(2.2/100) = 2.20

6 13 32 7 50 2 6

(2)

Maximum allowable number of deducts, m

Highest deduct value, HDV = 50 m = 1 + (9/98)(100 HDV) = 1 + (9/98)(100 50) = 5.6 Deduct values in descending order: 50, 32, 13, 7, 6, 6, 2 Number of deduct values = 7 Since the maximum allowable number of deducts is 5.6, therefore only the first 5 and 0.6 of the 6th deduct value are selected, i.e. 50, 32, 13, 7, 6, and 0.6*6 = 3.6. (3) Maximum corrected deduct value, CDV

Number of deduct values greater than 2, q = 6 Total deduct value = 50 + 32 + 13 + 7 + 6 + 3.6 = 111.6 From Figure B-45, CDV = 58 Reduce the smallest individual deduct value to 2 (q is now 5) and determine the CDV. Repeat until q reaches 1.
No. 1 2 3 4 5 6 7 8 9 10 50 50 50 50 50 50 32 32 32 32 32 2 Deduct Values 13 13 13 13 2 2 7 7 7 2 2 2 6 6 2 2 2 2 3.6 2 2 2 2 2 Total 111.6 11 106 101 90 60 q 6 5 4 3 2 1 CDV 58 58 61 65 63 60

Maximum CDV = 65

(4)

Determine the Pavement Condition Index

PCI = 100 CDVmax = 100 65 = 35 Based on the rating for PCI value of 35, this section of pavement is in very poor condition.