All the Productivity Rates are for working 8 hours/day Description Earth Works Excavation work in soft soil

Excavation Work in Hard Soil In layer of 150 mm thickness with 95% MDD value

Qty 120 50

Rate m3/day m3/day

Resource Excavator (bucket type) Rock breaker 1 Skilled, 4 Unskilled, 1 shovel,1 Roller compactor

Back Filling + Compaction

150

m2/day

Concrete Protection Works Bitumen Priming Works Bitustic works Protection works (torch applied) Concrete Blinding Works Screed Works

Including surface preparation Horizontal/Vertical surface Horizontal/Vertical Surface 75/100 mm thick Blinding works 40/50 mm thick C/S Screed 75/100 mm thick screed with welded steel fabric

200 150 80 120 200 120

m2/day m2/day m2/day m2/day m2/day m2/day

1 skilled + 1 unskilled 1 skilled + 1 unskilled 1 skilled + 1 unskilled 1 Mason + 2 Helper 1 Mason + 2 Helper 1 Mason + 2 Helper

Reinforcement Works Isolated/ Strap Footing Column/Corewall/Staircase Slab with beam/Raft

Up to 16 mm dia bars Above 16 mm dia bars Up to 12 mm 16 mm and Above

200 300 200 300 400

kg kg kg kg kg

1 SF + 1 SF + 1 SF + 1 SF + 1 SF +

1 Helper 1 Helper 1 Helper 1 Helper 1 Helper

Shuttering Footing Column/Core Wall/Staircase Slab Concrete Pumping Works Placing with concrete Pump Boom Placer Concrete Works Footings Staircase Slab Placing Precast/Hollow Core Slab

With Ordinary(Ply wood) shutter " "

8 6 12

m2/day m2/day m2/day

1 Carpenter + 1 Helper 1 Carpenter + 1 Helper 1 Carpenter + 1 Helper

60 40

m3/hr m3/hr

Concrete Placing and Trowel Finishing " " Placing in line and level

160 60 150 400

m3/day m3/day m3/day m2/day

1 Mason + 3 helper 1 Mason + 2 helper 2 Mason + 3 Helper 2 Rigger + 1 Mason + 2 Helper

Block works Plaster Works

10/15/20 cm thick Block works 15 mm thick Plaster Works with Acc. 20 mm thick Plaster Works with Acc.

10 12 10

m2/day m2/day m2/day

1 mason + 1 Helper 1 Plaster Mason + 1 Helper 1 Plaster Mason + 1 Helper

Ordinary Painting Priming Works Putty Works Painting Works

Including Surface preparation works First Coat Second Coat Surface Prep + Priming Painting Frame + Gypsum Partition Installation Frame + False Ceiling Fixing On Floor On Walls on Floor

150 75 250 350 50 100 120 30 15 12 20

m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day

1 Painter + 1 Helper 1 Painter + 1 Helper 1 painter 1 Painter 1 Painter + 1 Helper 1 Painter + 1 Helper 1 Mason + 1 Helper 1 Mason + 1 Helper 1 Mason + 1 Helper 1 Mason + 1 Helper 2 Mason + 1 Helper

Epoxy Paint

Gypsum Partition Works False Ceiling Tile Works

Marble/Granite Works